Understanding EIAUnderstanding EIA
requirementsrequirements
Aaron BowdenAaron Bowden
Transport for NSWTransport for NSW
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
2
Presentation overviewPresentation overview
๏ฌ Transport for NSW
๏ฌ Planning approvals pathways
๏ฌ Navigating the process:
๏‚ก Guidance
๏‚ก Define the activity
๏‚ก Permissibility
๏‚ก Significance
๏‚ก Legal precedents
๏‚ก Ancillary development
๏‚ก Subdivision
๏‚ก Critical infrastructure
๏‚ก Staging
๏ฌ Post-approval considerations โ€“ consistency assessment and modifications
๏ฌ Opportunities for system improvement
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
3
Personal backgroundPersonal background
๏ฌ Bachelor of Town
Planning, UNSW
๏ฌ Department of Planning
๏ฌ Leichhardt Council
๏ฌ Randwick Council
๏ฌ Parsons Brinckerhoff
๏ฌ JBA Planning
๏ฌ Transport for NSW
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
4
PreamblePreamble
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
5
Transport for NSWTransport for NSW
๏ฌ Announced by the
Minister for Transport
on 15 July 2011
๏ฌ Opportunity for the
integration of
planning, design,
delivery, operation
and maintenance of
transport systems in
NSW
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
6
Transport for NSWTransport for NSW
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
7
Transport for NSWTransport for NSW
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
8
Transport ProjectsTransport Projects
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
9
Transport ProjectsTransport Projects
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
10
Transport ProjectsTransport Projects
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
11
Environmental servicesEnvironmental services
๏ฌ Planning and
Assessments
๏ฌ Environmental
Management
๏ฌ Sustainability
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
12
Planning approvals pathwaysPlanning approvals pathways
๏ฌ Environmental Planning
& Assessment Act 1979
(NSW)
๏ฌ Protection of the
Environment Operations
Act 1997 (NSW)
๏ฌ Environment Protection
& Biodiversity
Conservation Act 1999
(Comm.)
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
13
Planning approvals pathwaysPlanning approvals pathways
1. Exempt development
2. Complying development
3. Development with consent
4. State significant development
5. Development without consent
6. State significant infrastructure
7. Commonwealth controlled actions
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
14
Exempt developmentExempt development
๏ฌ Introduced in 1997 as
part of NSW
Government reforms to
streamline planning
approvals
๏ฌ Minor works with
minimal environmental
impact
๏ฌ No need for
development consent or
building certification
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
15
Exempt developmentExempt development
๏ฌ State Environmental Planning
Policy (Infrastructure) 2007
๏ฌ Clause 20 โ€“ General
development
๏ฌ Clause 82 โ€“ Rail facilities
๏ฌ Clause 97 โ€“ Road facilities
๏ฌ Enduring duty to consider
environmental impact under
section 111 of the
EP&A Act
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
16
Complying developmentComplying development
๏ฌ Commenced in 1997
๏ฌ Principal certifying
authority
๏ฌ Not utilised by
TfNSW
๏ฌ Under Division 3,
Part 4 CDCs do not
apply to Crown
development
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
17
Development with consentDevelopment with consent
๏ฌ Local government
authority is the consent
authority
๏ฌ Part 4 of the EP&A Act
๏ฌ Permissibility usually
determined by local
environmental plans
(LEP)
๏ฌ Can be problematic for
integrated delivery of
transport projects
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
18
State significant developmentState significant development
๏ฌ SSD is determined in
accordance with Division 4.1,
Part 4 of the EP&A Act
๏ฌ Introduced in June 2011
๏ฌ Minister for Planning the
consent authority
๏ฌ Consent role delegated to
Planning Assessment
Commission
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
19
State significant developmentState significant development
Fox Studios,
Moore Park
Westfield,
Eastgardens
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
20
State significant developmentState significant development
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
21
State significant developmentState significant development
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
22
State significant developmentState significant development
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
23
State significant developmentState significant development
๏ฌ Asset Divestment
Program for residual
construction land
๏ฌ North Ryde Precinct key
TfNSW opportunity for
transit oriented
development
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
24
Development without consentDevelopment without consent
๏ฌ Part 5 of the EP&A
Act
๏ฌ TfNSW the
determining authority
๏ฌ Most flexible and
efficient means of
assessment for
Transport Projects
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
25
State significant infrastructureState significant infrastructure
๏ฌ Required for activities
triggering the need for an
EIS and other activities
identified under the SRD
SEPP
๏ฌ Assessed under
Part 5.1 of the
EP&A Act
๏ฌ Minister for Planning is
the determining authority
๏ฌ Mandatory consultation
and exhibition
requirements
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
26
Navigating the processNavigating the process
๏ฌ Transport Projects
Quality Management
System (QMS) /
Environmental
Management System
(EMS)
๏ฌ Planning and
Environment Handbook
๏ฌ Project Management
Methodology Framework
(PMMF)
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
27
Navigating the processNavigating the process
๏ฌ Step 1: What is the
activity?
๏‚ก Nature
๏‚ก Scale
๏‚ก Extent
๏‚ก Location
๏‚ก Cost
๏‚ก Duration
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
28
Navigating the processNavigating the process
๏ฌ Step 2: What is the
permissibility of the
activity on my site?
๏ฌ Check the applicable
EPIs โ€“ particularly
the Infrastructure
SEPP, SRD SEPP
and the relevant LEP
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
29
Navigating the processNavigating the process
๏ฌ Step 3:
Significance of
impact
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
30
Navigating the processNavigating the process
๏ฌ โ€˜Fullest extent possibleโ€™,
as โ€˜reasonable and
practicableโ€™
๏ฌ Duty to consider
environment ongoing
๏ฌ The nature and extent of
the activity sets the
scope of the
environment
๏ฌ Significance of impact is
relative
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
31
Ancillary developmentAncillary development
๏ฌ โ€˜ancillary and
independentโ€™ versus
โ€˜ancillary and subsumedโ€™
๏ฌ Ancillary and subsumed
no longer a valid
argument
๏ฌ Assessment level of the
dominant use does not
stop ancillary elements
from triggering higher
level of assessment or
additional approvals
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
32
SubdivisionSubdivision
๏ฌ Subdivision is included in
the definitions of both
โ€˜developmentโ€™ and
โ€˜activityโ€™ for the purposes
of the EP&A Act
๏ฌ Infrastructure SEPP
makes some allowance
for subdivision as
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
33
Critical infrastructureCritical infrastructure
๏ฌ Ministerial declaration
๏ฌ Essential for economic,
environmental or social
reasons
๏ฌ Streamlined assessment
process
๏ฌ Restrictions on the availability
of merit appeals
๏ฌ Applies to SSI only
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
34
StagingStaging
๏ฌ SSI projects can be
staged
๏ฌ Staging provisions allow
for an initial concept plan
to be approved with
subsequent more
detailed project
approvals
๏ฌ South West Rail Link is
an example of a
successfully staged
approval process
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
35
Post-approval considerationsPost-approval considerations
๏ฌ Design development
is evolutionary
๏ฌ EIA is done early in
design
๏ฌ Scope change is
inevitable, post-
approval
๏ฌ Need to compare the
impacts of the
approved project with
the new scope
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
36
Post-approval considerationsPost-approval considerations
๏ฌ Consistency assessment
checklists:
๏‚ก Compares the likely
impacts of scope
changes with those of
the approved activity
๏‚ก Allows the Director
Planning and
Assessments to
determine when a
formal modification to
approval is required
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
37
Post-approval considerationsPost-approval considerations
๏ฌ Modifications to
approval:
๏‚ก Part 4: section 96
๏‚ก SSD: section 96
๏‚ก Part 5: section 111
๏‚ก Part 5.1: section
115ZI
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
38
Opportunities for improvementOpportunities for improvement
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
39
Opportunities for improvementOpportunities for improvement
๏ฌ Allowances for minor
retail development
permissible without
consent when ancillary
to transport works
๏ฌ Allowances for
advertising to be
permissible without
consent when ancillary
to transport works
๏ฌ Clarification of when an
EIS is required
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
40
Opportunities for improvementOpportunities for improvement
๏ฌ Guidance for when
modifications to SSI
approvals are required
๏ฌ Clarification of trumping
provisions for combined
SSI/SSD projects
๏ฌ Clarification/renewal of
bilateral agreement for
SSI projects with EPBC
Act referrals
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
41
QuestionsQuestions
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
42
ReferencesReferences
References:
TCA Annual Report 2011
TfNSW Website http://www.transport.nsw.gov.au
TfNSW Quality Management System (2012)
Figures:
All figures are copyright of TfNSW, except the following:
๏ฌ Slides 13,16: NSW Parliamentary Counsels Office: http://www.legislation.nsw.gov.au
๏ฌ Slide 17: NSW Government Licensing Service:
http://www.licence.nsw.gov.au/new/categories/home-owner-building-renovation
๏ฌ Slide 20: Wikipedia: http://www.wikipedia.org
๏ฌ Slide X: Macarthur Chronicle:
๏ฌ Slide X: Rygate Surveyors, Subdivision design: http://www.rygate.com.au/subdesign.html
๏ฌ Slide X: NSW Department of Planning: http://www.planning.nsw.gov.au
๏ฌ Slide X: Tarte, Justin, Top 10 Questions to Ask Yourself:
http://justintarte.blogspot.com.au/2011/12/top-10-questions-to-ask-yourself-in.html
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
43
ReferencesReferences
Legislation/Regulation:
๏ฌ Environmental Planning and Assessment Act 1979
๏ฌ Environmental Planning and Assessment Regulation 2000
๏ฌ Environment Protection and Biodiversity Conservation Act 1999 (Comm.)
๏ฌ Protection of the Environment Operations Act 1997
๏ฌ State Environmental Planning Policy (Infrastructure) 2007
๏ฌ State Environmental Planning Policy (State and Regional Development) 2011
๏ฌ Transport Administration Act 1988
Monday, 28 May
2012
Aaron Bowden
A/Senior Manager
44
ReferencesReferences
Cases:
๏ฌ Guthega Development Pty Limited v. Minister Administering the National Parks and
Wildlife Act (NSW) 1974 (1986) 7 NSWLR 353 at 366
๏ฌ Transport Action Group Against Motorways Inc. v. RTA (1999) 104 LGERA 133 at 145 per
Mason P.
๏ฌ Drummoyne Council v Maritime Services Board (1991) 72 LGRA 186
๏ฌ Residents of Blacktown and Seven Hills Against Further Traffic Inc v RTA [1996] NSWLEC
170 - Pearlman CJ (21 June 1996)
๏ฌ Bailey v. Forestry Commission of New South Wales (1989) 67 LGRA 200 at 211-212
๏ฌ Residents Against Improper Development Inc & Anor vs Chase Property Investment Pty
Ltd (2006) NSWCA 323
Further queries:
Aaron Bowden, A/Senior Manager, Planning
E: aaron.bowden@projects.transport.nsw.gov.au
P: 9200 0200

More Related Content

Similar to Understanding EIA Requirements, Environmental Assessments and Approvals Summit 2012 (10)

Construction of Data Centre (Hemel Hempstead).pptx
Construction of Data Centre (Hemel Hempstead).pptxConstruction of Data Centre (Hemel Hempstead).pptx
Construction of Data Centre (Hemel Hempstead).pptx
ย 
environmental impact assessment
environmental impact assessment environmental impact assessment
environmental impact assessment
ย 
West east gas pipeline project ok
West east gas pipeline project okWest east gas pipeline project ok
West east gas pipeline project ok
ย 
Basic concept of environment safeguard
Basic concept of environment safeguardBasic concept of environment safeguard
Basic concept of environment safeguard
ย 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessment
ย 
CV project operation events 2016
CV project operation events 2016CV project operation events 2016
CV project operation events 2016
ย 
Environmental Categorization[1]
Environmental Categorization[1]Environmental Categorization[1]
Environmental Categorization[1]
ย 
Tables Presentation Refinery Overhauling
Tables Presentation Refinery OverhaulingTables Presentation Refinery Overhauling
Tables Presentation Refinery Overhauling
ย 
Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012
ย 
Appendix b stakeholder engagement and consultation final_dec2010
Appendix b stakeholder engagement and consultation final_dec2010Appendix b stakeholder engagement and consultation final_dec2010
Appendix b stakeholder engagement and consultation final_dec2010
ย 

Recently uploaded

Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...
MOHANI PANDEY
ย 
RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995
garthraymundo123
ย 
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
ย 
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
SUHANI PANDEY
ย 
Call Girls Service Pune โ‚น7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...
Call Girls Service Pune โ‚น7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...Call Girls Service Pune โ‚น7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...
Call Girls Service Pune โ‚น7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...
SUHANI PANDEY
ย 

Recently uploaded (20)

Hertwich_EnvironmentalImpacts_BuildingsGRO.pptx
Hertwich_EnvironmentalImpacts_BuildingsGRO.pptxHertwich_EnvironmentalImpacts_BuildingsGRO.pptx
Hertwich_EnvironmentalImpacts_BuildingsGRO.pptx
ย 
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
ย 
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING  SYSTEMS- IGBC, GRIHA, LEED--.pptxRATING  SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptx
ย 
Sector 18, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 18, Noida Call girls :8448380779 Model Escorts | 100% verifiedSector 18, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 18, Noida Call girls :8448380779 Model Escorts | 100% verified
ย 
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...
ย 
Climate Change
Climate ChangeClimate Change
Climate Change
ย 
RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995
ย 
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
ย 
Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...
ย 
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
ย 
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
ย 
Cyclone Case Study Odisha 1999 Super Cyclone in India.
Cyclone Case Study Odisha 1999 Super Cyclone in India.Cyclone Case Study Odisha 1999 Super Cyclone in India.
Cyclone Case Study Odisha 1999 Super Cyclone in India.
ย 
Book Sex Workers Available Pune Call Girls Kondhwa 6297143586 Call Hot India...
Book Sex Workers Available Pune Call Girls Kondhwa  6297143586 Call Hot India...Book Sex Workers Available Pune Call Girls Kondhwa  6297143586 Call Hot India...
Book Sex Workers Available Pune Call Girls Kondhwa 6297143586 Call Hot India...
ย 
Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...
Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...
Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...
ย 
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
ย 
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
ย 
DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024
ย 
Call Girls Moshi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Moshi Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Moshi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Moshi Call Me 7737669865 Budget Friendly No Advance Booking
ย 
Call Girls Service Pune โ‚น7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...
Call Girls Service Pune โ‚น7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...Call Girls Service Pune โ‚น7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...
Call Girls Service Pune โ‚น7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...
ย 
Kondhwa ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Kondhwa ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Kondhwa ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Kondhwa ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
ย 

Understanding EIA Requirements, Environmental Assessments and Approvals Summit 2012

  • 1. Understanding EIAUnderstanding EIA requirementsrequirements Aaron BowdenAaron Bowden Transport for NSWTransport for NSW
  • 2. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 2 Presentation overviewPresentation overview ๏ฌ Transport for NSW ๏ฌ Planning approvals pathways ๏ฌ Navigating the process: ๏‚ก Guidance ๏‚ก Define the activity ๏‚ก Permissibility ๏‚ก Significance ๏‚ก Legal precedents ๏‚ก Ancillary development ๏‚ก Subdivision ๏‚ก Critical infrastructure ๏‚ก Staging ๏ฌ Post-approval considerations โ€“ consistency assessment and modifications ๏ฌ Opportunities for system improvement
  • 3. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 3 Personal backgroundPersonal background ๏ฌ Bachelor of Town Planning, UNSW ๏ฌ Department of Planning ๏ฌ Leichhardt Council ๏ฌ Randwick Council ๏ฌ Parsons Brinckerhoff ๏ฌ JBA Planning ๏ฌ Transport for NSW
  • 4. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 4 PreamblePreamble
  • 5. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 5 Transport for NSWTransport for NSW ๏ฌ Announced by the Minister for Transport on 15 July 2011 ๏ฌ Opportunity for the integration of planning, design, delivery, operation and maintenance of transport systems in NSW
  • 6. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 6 Transport for NSWTransport for NSW
  • 7. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 7 Transport for NSWTransport for NSW
  • 8. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 8 Transport ProjectsTransport Projects
  • 9. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 9 Transport ProjectsTransport Projects
  • 10. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 10 Transport ProjectsTransport Projects
  • 11. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 11 Environmental servicesEnvironmental services ๏ฌ Planning and Assessments ๏ฌ Environmental Management ๏ฌ Sustainability
  • 12. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 12 Planning approvals pathwaysPlanning approvals pathways ๏ฌ Environmental Planning & Assessment Act 1979 (NSW) ๏ฌ Protection of the Environment Operations Act 1997 (NSW) ๏ฌ Environment Protection & Biodiversity Conservation Act 1999 (Comm.)
  • 13. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 13 Planning approvals pathwaysPlanning approvals pathways 1. Exempt development 2. Complying development 3. Development with consent 4. State significant development 5. Development without consent 6. State significant infrastructure 7. Commonwealth controlled actions
  • 14. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 14 Exempt developmentExempt development ๏ฌ Introduced in 1997 as part of NSW Government reforms to streamline planning approvals ๏ฌ Minor works with minimal environmental impact ๏ฌ No need for development consent or building certification
  • 15. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 15 Exempt developmentExempt development ๏ฌ State Environmental Planning Policy (Infrastructure) 2007 ๏ฌ Clause 20 โ€“ General development ๏ฌ Clause 82 โ€“ Rail facilities ๏ฌ Clause 97 โ€“ Road facilities ๏ฌ Enduring duty to consider environmental impact under section 111 of the EP&A Act
  • 16. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 16 Complying developmentComplying development ๏ฌ Commenced in 1997 ๏ฌ Principal certifying authority ๏ฌ Not utilised by TfNSW ๏ฌ Under Division 3, Part 4 CDCs do not apply to Crown development
  • 17. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 17 Development with consentDevelopment with consent ๏ฌ Local government authority is the consent authority ๏ฌ Part 4 of the EP&A Act ๏ฌ Permissibility usually determined by local environmental plans (LEP) ๏ฌ Can be problematic for integrated delivery of transport projects
  • 18. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 18 State significant developmentState significant development ๏ฌ SSD is determined in accordance with Division 4.1, Part 4 of the EP&A Act ๏ฌ Introduced in June 2011 ๏ฌ Minister for Planning the consent authority ๏ฌ Consent role delegated to Planning Assessment Commission
  • 19. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 19 State significant developmentState significant development Fox Studios, Moore Park Westfield, Eastgardens
  • 20. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 20 State significant developmentState significant development
  • 21. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 21 State significant developmentState significant development
  • 22. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 22 State significant developmentState significant development
  • 23. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 23 State significant developmentState significant development ๏ฌ Asset Divestment Program for residual construction land ๏ฌ North Ryde Precinct key TfNSW opportunity for transit oriented development
  • 24. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 24 Development without consentDevelopment without consent ๏ฌ Part 5 of the EP&A Act ๏ฌ TfNSW the determining authority ๏ฌ Most flexible and efficient means of assessment for Transport Projects
  • 25. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 25 State significant infrastructureState significant infrastructure ๏ฌ Required for activities triggering the need for an EIS and other activities identified under the SRD SEPP ๏ฌ Assessed under Part 5.1 of the EP&A Act ๏ฌ Minister for Planning is the determining authority ๏ฌ Mandatory consultation and exhibition requirements
  • 26. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 26 Navigating the processNavigating the process ๏ฌ Transport Projects Quality Management System (QMS) / Environmental Management System (EMS) ๏ฌ Planning and Environment Handbook ๏ฌ Project Management Methodology Framework (PMMF)
  • 27. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 27 Navigating the processNavigating the process ๏ฌ Step 1: What is the activity? ๏‚ก Nature ๏‚ก Scale ๏‚ก Extent ๏‚ก Location ๏‚ก Cost ๏‚ก Duration
  • 28. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 28 Navigating the processNavigating the process ๏ฌ Step 2: What is the permissibility of the activity on my site? ๏ฌ Check the applicable EPIs โ€“ particularly the Infrastructure SEPP, SRD SEPP and the relevant LEP
  • 29. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 29 Navigating the processNavigating the process ๏ฌ Step 3: Significance of impact
  • 30. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 30 Navigating the processNavigating the process ๏ฌ โ€˜Fullest extent possibleโ€™, as โ€˜reasonable and practicableโ€™ ๏ฌ Duty to consider environment ongoing ๏ฌ The nature and extent of the activity sets the scope of the environment ๏ฌ Significance of impact is relative
  • 31. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 31 Ancillary developmentAncillary development ๏ฌ โ€˜ancillary and independentโ€™ versus โ€˜ancillary and subsumedโ€™ ๏ฌ Ancillary and subsumed no longer a valid argument ๏ฌ Assessment level of the dominant use does not stop ancillary elements from triggering higher level of assessment or additional approvals
  • 32. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 32 SubdivisionSubdivision ๏ฌ Subdivision is included in the definitions of both โ€˜developmentโ€™ and โ€˜activityโ€™ for the purposes of the EP&A Act ๏ฌ Infrastructure SEPP makes some allowance for subdivision as
  • 33. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 33 Critical infrastructureCritical infrastructure ๏ฌ Ministerial declaration ๏ฌ Essential for economic, environmental or social reasons ๏ฌ Streamlined assessment process ๏ฌ Restrictions on the availability of merit appeals ๏ฌ Applies to SSI only
  • 34. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 34 StagingStaging ๏ฌ SSI projects can be staged ๏ฌ Staging provisions allow for an initial concept plan to be approved with subsequent more detailed project approvals ๏ฌ South West Rail Link is an example of a successfully staged approval process
  • 35. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 35 Post-approval considerationsPost-approval considerations ๏ฌ Design development is evolutionary ๏ฌ EIA is done early in design ๏ฌ Scope change is inevitable, post- approval ๏ฌ Need to compare the impacts of the approved project with the new scope
  • 36. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 36 Post-approval considerationsPost-approval considerations ๏ฌ Consistency assessment checklists: ๏‚ก Compares the likely impacts of scope changes with those of the approved activity ๏‚ก Allows the Director Planning and Assessments to determine when a formal modification to approval is required
  • 37. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 37 Post-approval considerationsPost-approval considerations ๏ฌ Modifications to approval: ๏‚ก Part 4: section 96 ๏‚ก SSD: section 96 ๏‚ก Part 5: section 111 ๏‚ก Part 5.1: section 115ZI
  • 38. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 38 Opportunities for improvementOpportunities for improvement
  • 39. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 39 Opportunities for improvementOpportunities for improvement ๏ฌ Allowances for minor retail development permissible without consent when ancillary to transport works ๏ฌ Allowances for advertising to be permissible without consent when ancillary to transport works ๏ฌ Clarification of when an EIS is required
  • 40. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 40 Opportunities for improvementOpportunities for improvement ๏ฌ Guidance for when modifications to SSI approvals are required ๏ฌ Clarification of trumping provisions for combined SSI/SSD projects ๏ฌ Clarification/renewal of bilateral agreement for SSI projects with EPBC Act referrals
  • 41. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 41 QuestionsQuestions
  • 42. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 42 ReferencesReferences References: TCA Annual Report 2011 TfNSW Website http://www.transport.nsw.gov.au TfNSW Quality Management System (2012) Figures: All figures are copyright of TfNSW, except the following: ๏ฌ Slides 13,16: NSW Parliamentary Counsels Office: http://www.legislation.nsw.gov.au ๏ฌ Slide 17: NSW Government Licensing Service: http://www.licence.nsw.gov.au/new/categories/home-owner-building-renovation ๏ฌ Slide 20: Wikipedia: http://www.wikipedia.org ๏ฌ Slide X: Macarthur Chronicle: ๏ฌ Slide X: Rygate Surveyors, Subdivision design: http://www.rygate.com.au/subdesign.html ๏ฌ Slide X: NSW Department of Planning: http://www.planning.nsw.gov.au ๏ฌ Slide X: Tarte, Justin, Top 10 Questions to Ask Yourself: http://justintarte.blogspot.com.au/2011/12/top-10-questions-to-ask-yourself-in.html
  • 43. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 43 ReferencesReferences Legislation/Regulation: ๏ฌ Environmental Planning and Assessment Act 1979 ๏ฌ Environmental Planning and Assessment Regulation 2000 ๏ฌ Environment Protection and Biodiversity Conservation Act 1999 (Comm.) ๏ฌ Protection of the Environment Operations Act 1997 ๏ฌ State Environmental Planning Policy (Infrastructure) 2007 ๏ฌ State Environmental Planning Policy (State and Regional Development) 2011 ๏ฌ Transport Administration Act 1988
  • 44. Monday, 28 May 2012 Aaron Bowden A/Senior Manager 44 ReferencesReferences Cases: ๏ฌ Guthega Development Pty Limited v. Minister Administering the National Parks and Wildlife Act (NSW) 1974 (1986) 7 NSWLR 353 at 366 ๏ฌ Transport Action Group Against Motorways Inc. v. RTA (1999) 104 LGERA 133 at 145 per Mason P. ๏ฌ Drummoyne Council v Maritime Services Board (1991) 72 LGRA 186 ๏ฌ Residents of Blacktown and Seven Hills Against Further Traffic Inc v RTA [1996] NSWLEC 170 - Pearlman CJ (21 June 1996) ๏ฌ Bailey v. Forestry Commission of New South Wales (1989) 67 LGRA 200 at 211-212 ๏ฌ Residents Against Improper Development Inc & Anor vs Chase Property Investment Pty Ltd (2006) NSWCA 323 Further queries: Aaron Bowden, A/Senior Manager, Planning E: aaron.bowden@projects.transport.nsw.gov.au P: 9200 0200

Editor's Notes

  1. Explain the process of nominated determining authority and the duty to consider the environment of third party public authorities
  2. Is an EIS required? Best practice guidelines for Part 5 of the Environmental Planning and Assessment Act 1979, Department of Planning, NSW