SlideShare une entreprise Scribd logo
1  sur  20
NESTLE NIGERIA PLC
QUARTER 1
EIA-IMPACT MITIGATION MONITORING (IMM)
OF
NESTLE WATERS GREENFIELD FACTORY
PROJECT, ABAJI, FCT ABUJA
21ST
MAY, 2015
QUARTER 1 IMM
TABLE OF CONTENTS
CHAPTER 1 INTRODUCTION
CHAPTER 2 METHODOLOGY FOR MONITORING
CHAPTER 3 MATERIALS AND METHODS OF ANALYSIS
CHAPTER 4 RESULT OF MONITORING
CHAPTER 5 CONCLUSIONS
BIBLIOGRAPHY / APPENDIX
IMM PREPARERS
• Alh SOLABI, Gbolahan Adisa FIPAN ,FNIFST, JP Executive Director /CEO
• Mr. OKUMODI Adewunmi Olufemi, (M.Sc) MNIFST, Snr. Scientific Officer
• Mr. BAMTEFA Joseph A. MNIFST Technical Coordinator
• Mr. IKUGBYIGBE Oluwatoyin (M.Sc) Environmental Officer
• Dr. OJOSIPE, Sola FIPAN Associate (BATO LAB)
• NESTLE NIGERIA Plc
Engr. KOBOU Sylvain E2E Project Manager
• Engr. ALUKO Ezekiel Project Engineering Manager (Ind. Services)
• Engr. CHARBON Luc Project Engineering Manager (Process)
• Mr. FAMBEGBE Ayodele SHE Officer
EXECUTIVE SUMMARY
• Impact Mitigation Monitoring (IMM) Background
• Project Background
• IMM Objective
• The EIA mitigation monitoring exercise is aimed at ensuring compliance with regulatory
requirements and standards as well as implementation of prescribed mitigation measures already
outlined in the EIA - EMP
• Methodology
• Sampling and analysis to generate verifiable empirical data by accredited FMEnv Laboratory
• Inspection and surveillance / Audit of project site
• Environmental data collection on and socio- economic and health condition measurements (i.e
payment of compensation, employment of local people, report of any health challenges, consultations)
• Discussion, finding and Results of Monitoring
• Conclusions
CHAPTER ONE
INTRODUCTION
• Impacts Mitigation Monitoring Plan ( IMMP) is an
important tool that can be used to measure and
check, in a continous mode the efficacy of the
proposed mitigation measures recommended by an
Environmental Assessment.
• The Mitigation measures incorporated into the
project implementation process, which is aimed at
eliminating, minimizing negative impacts and
enhancing the positive impacts are hereby
evaluated whether they are adequate or not.
INTRODUCTION
• Impacts Mitigation Monitoring (IMM) is
necessary to ensure that corrective actions
are taken where proposed mitigation
measures are found to be inadequate.
• Impact mitigation for this stage of the
project covers both the site preparation
and the construction phases.
PROJECT BACKGROUND
• Nestle proposed to build a New Water
factory at Abaji in 2013
• Project was approved for EIA studies in
July 2013
• EIA was completed and reviewed in May
2014
• Approval was given for Construction to
begin and IMM to be conducted.
CHAPTER TWO
METHODOLOGY OF MONITORING
• Awareness and Training
• Safety Health and Environment Induction
• Sampling and Analysis
• Inspection and Surveillance / Audit
• Socio-economic and Health evaluation
• Consultations
• Parameters Monitoring
IMM SAMPLING STATIONS
• A TOTAL OF NINE SAMPLING STATIONS WERE CHOSEN
• SAMPLING STATIONS WERE CHOSEN TO COVER AREA
THAT HAVE BEEN IMPACTED
• AIR QUALITY - 6 SAMPLING STATIONS
• WATER - 3 SAMPLING
STATIONS
• SOIL - 3 SAMPLING
STATIONS
• VEGETATION - TAKEN WITHIN AND
AROUND PROJECT SITE
CHAPTER FOUR
RESULTS OF AIR QUALITY MONITORING
Parameters SAMPLING POINTS
A B C D E F FMENV
LIMITSControl
Mandereji
Near Borehole
No.2
Waste
Segregation
Area
Uphill near fence
Mandereji
Community
Within the
Factory building
Near
Gate House
BL MN BL MN BL MN BL MN BL MN BL MN
NO, (ppm) ND ND ND ND ND 0.2 ND ND ND ND ND ND 0.05
CO, (ppm) 4.6 3.2 2.9 3.1 3.1 7.6 3.5 3.9 4.5 5.9 4.2 4.7 20
SO2 (ppm) 0.15 ND ND ND ND 0.2 <0.1 0.1 0.15 <0.1 0.1 ND 0.1
CH4 (ppm) ND ND ND ND ND 1.4 ND ND ND ND ND ND NS
O2 (%) 21.5 20.8 21.4 20.6 21.5 20.5 21.5 20.520.5 21.5 20.5 21.6 20.4 NS
TSP (ug/m3
) 150 ND 210 ND 210 ND 200 ND 190 ND 160 ND 250
Summary of Air Quality Monitoring : Quarter 1, 2015
 • 4.2.1 Nitrogen Oxide
• Nitrogen  Oxide   was  not  detected  in  any  other  area  of  the  project  site  except  for  the  Waste  segregation 
area  (0.2ppm) which  is  close  to the  point  of  source  of   project  generator  area.  The  impact  is  short  term  as  
the  diesel  powered  generator  will  only  be  used  for  the  construction  phase  only.  Appropriate  mitigation  
measures  are  however  in  place.
•  
• 4.2.2 Carbon Monoxide
• Carbon  monoxide  range  of  (3.2 – 7.6)ppm  were  all  within  the  FMEnv  limit  of  20.0ppm. Baseline  maximum  
of  4.9ppm  was  however  exceeded  at  three  locations  which  were  close  to  the  generator  area  and  also  the  
direction  of  wind  in  the  project  area. The  deviation  may  not  be  unconnected  with  the  power  generating  
set  in  use  for  the  construction  phase  of  the  project.
•  
• 4.2.3 Sulphur Dioxide
• The  maximum  concentration  of  Sulphur  dioxide  (0.2ppm)  was  recorded  in  only  one  location,  near  the  
waste  segregation  area close  to  the  power  generating  set. The  values  is  slightly  above  the  FMEnv  limit  of  
0.1ppm.  Baseline  condition  also  showed  a  maximum  of  0.15  hence  the  marginal  increase  may  be  
connected  to  the  site  power  source. The  impact  will  be  temporal  and  not  of  significant  effect  if  all  the  
recommended  mitigation  measures  are  strictly  adhered  to.
•  
• 4.2.4 Combustible Gas as Methane (CH4)   
• The  value of  combustible methane  were  not  detected  during  the  baseline  studies.  A  concentration  of  
1.4ppm  was  detected  in  one  location  during  the  IMM,  although  there  is  no  FMEnv  standard, the  level  is  
not  of  any  negative  significance  environmentally.
•  
•  
• 4.2.5 Percentage Atmospheric Oxygen
• The  percentage  atmospheric  oxygen  ranged  between 20.4 – 20.8.  Highest  baseline  data ranged  between  21.4 
 and  21.6.  Both  values  are  normal  and  satisfactory.
•  
• 4.2.6 The  values  of  TSP  for  baseline  conditions were  all  within  the  FMEnv  standards.  IMM  measurements 
 were  not  determined  due  to  calibration  exercise  being  conducted  on  the  meter  outside  the  country.
NOISE LEVEL
S/N AVERAGE NOISE LEVEL dB(A)
LOCATION BL MN FMENV
WET DRY AVR. (WET&DRY) QUARTER 1
A ControlMandereji 69 76 72.3 77 90
B Near BoreholeNo.2 56.5 60.0 58.3 61 90
C WasteSegregation
Area
54.6 62.5 58.6 75 90
D Uphill near fence
ManderejiCommunity
60.0 58.5 59.3 65 90
E Withinthe
Factorybuilding
61.0 63.5 62.5 57 90
F Near
GateHouse
59.0 63.0 61.0 67 90
RESULT OF GROUND AND SURFACE WATER
MONITORING
• Summary of Results
• Ground water analysis for Quarter 1
• The  quality  of  the  raw  borehole  water  samples  analyzed  were  both  
satisfactory pH  ranged  between  7.0  and  7.3 for  drinking  water  standards  
except  for the  high  Iron  level  of  1.4 mg/kg  present  in  the  Nestle Borehole  
water  sample. The  same  high  trend  was  recorded  as  baseline.  Iron  removal  
has  been  incorporated  in  the  water  treatment  system.
•  
• Surface Water analysis for Quarter 1
• The   parameters  analyzed  for  in  the  Mandereji  Stream  Water  sample  showed 
 satisfactory  physico-chemical  properties  except  for  the  high  Iron  level as  
well.  The  microbiological  parameters  investigated   showed  the  presence of  
coliforms (17cfu/ml)  and  bacteria  count  too numerous  to count.
• All  the  parameters  measured  for  both  surface  and  ground  water  were  in   
the  same  trend  as  those  of  the  EIA  baseline.  There  is  no  indication  of  
pollution from  the  on-going  project  activities.
•  
SOIL  EVALUATION
• Soil Analysis
• The  Soil  Samples  are  neutral  with  pH  
values ranging  from  6.96 - 7.12.  Also, this  
samples  are  considered  rich  in minerals.  No 
 negative  impact  on  the  soil  as  a  result  of  
on-going  construction  work.
VEGETATION AND WILD LIFE
• Vegetation
• Impact mitigation was conducted for the project construction phase that is in progress. The
identified impacts on vegetation, proposed mitigation measures and comments on the
impact mitigation monitoring are presented in Table 4.8
• Apart from basic farming activities that have been stopped in the project area, The natural
vegetation have been eliminated in the area where construction activities are on-going.
• The natural habitat of most of the plant species have been altered with some permanently
concreted for factory use.
• The trees within the project site have been cut and are being used as firewood for the
temporary canteen and also given free to the local community.
• Some economic trees were still in place as construction activities were yet to get to their
location.
• Table 4.3 is a list of economic trees still existing in the project area.
• Wildlife
• The construction of perimeter fence to secure the project site from unnecessary intrusion
has led to the displacement of wildlife identified during the baseline studies. Apart from
some of the area where the bush have been left for future development, wildlife
population have been negatively impacted., Mammals and birds have virtually migrated from
the project site. A biodiversity monitoring plan has been prepared for monitoring of the
ecology of the project area. Table 4.4.
Table 4.8: Summary of Identified Impacts and Proposed Mitigation
Measures and the compliance status for NNAGFWF Project
Mitigation Monitoring – COMPLIANCETable 4.8: Summary of Identified Impacts and Proposed Mitigation Measures and the compliance status for NNAGFWF
Project
Mitigation Measure Mitigation Monitoring
• Compensate communities for land take and farmlands.
• Recruitment and training of locals for project’s jobs (security,
unskilled labour)
• Engagement of Local as interpreters and mediators in
compensation processes.
o Evidence of compensation with detailed of the beneficiaries available (Appendix
1)
o Engagement of local labour through construction firm effected. List of names
and post of local engaged provided in Appendix 2
o Appropriate channel of dissemination of job availability and recruitment was
followed by presenting the vacancies to the community head and assuring that
qualified locals will be engaged. List of names of local employees and their
residence. Appendix 2
• use existing access routes / ways and ensure minimum clearing
during site survey.
• Re – grassing / Flowering of Project surrounding.
• Removal of excess excavated soil for re – use (in other project –
road repairs / remediation of erosion areas etc)
• Cement concrete / paving of un – grassed area.
• Use equipment with low levels of noise and emissions that are
within the acceptable national standards and specifications
• Ensure that water be sprinkled on open surface during excavation
to reduce amount of soil particulates
• Use Power sourced from the National grid where available to
minimize burning of fossil fuel.
• Ensure movement of trucks and heavy duty vehicles are properly
timed to ensure minimal interference with local transportation as
well as that of the major highway.
• construction of screens on storm water pathway to reduce surface
water contamination
o Only the areas to be use for construction has been excavated. Thereby still
leaving some areas of natural vegetation for existing wildlife to inhabit. (See
Plates 1 &2)
o The topograghy of the land were taken advantaged of. The upland has been
slightly leveled removing majorly the topsoil and to some extent some laterites
to fill up undulating areas. (see plate 3)
o Topsoils have been piled at specific location for re-use during landscaping for
flowering and regressing purposes. Plate 4
o The structure of the land (profile) has not been significantly affected see
Table 4.7
o The generator on site were carefully chosen and strategically located. One
sound proof generator is used at the borehole site due to the proximity to the
office there. The noise level measured confirms the observation. Table 4.2
o While the construction phase is one, the storm water course is being
determined. Thus natural flow of storm water is to be followed for the
discharge into the bigger body of water. Plate 5
o The fencing has thus put into consideration the storm eater pathway and outlet
for the storm water has been incorporated into the project design. (see plate 5)
Table 4.8: Summary of Identified Impacts and Proposed Mitigation
Measures and the compliance status for NNAGFWF Project
Mitigation Monitoring – COMPLIANCE
Table 4.8: Summary of Identified Impacts and Proposed Mitigation Measures and the compliance status for NNAGFWF
Project
• Use of appropriate PPE.
• Use of relevant safety instruction and illustrations
• Site Safety Health Management Procedures
• Limit Access to project Site.
• Clearing and Excavations to be done in Dry Season
• Good housekeeping practices and proper handling of oil.
• Solid wastes to be disposed off by licensed/ accredited waste
contractors.
• Storage of construction materials at designated area within the site
and enforcement of good site management and engineering
practices.
• Reduction at source, sorting and separation of materials for re-use
and sale to third party users.
• Proper insulation of pipes to prevent leakage and damage.
o Compliance with the use of PPE on site is over 95% . Plate 9 & 10. See
Appendix 3 – She requirement for Contractors.
o Relevant safety instructions are displayed at strategic places around the project
site. (Plates 6)
o Daily safety briefing are held every morning before work commences. Plates 7-
10
o Good house keeping practices is evidence at the site. Construction area are
marked, walk ways are designated with reflective tapes, (plates 11-14)
o Handling of oil waste from operation in the site is well documented. Waste
oil are received into empty kegs and properly labeled for recycle via selling to
third party vendors.
o Source reduction of waste is practiced and segregation ensured. Iron, wood,
and domestic wastes are separated. Plate 14
o Waste bags of cement is segregated and packaged for sale. Plate 13
o Pipes are well buried at about 1m below foundation and the foundation casted
to prevent damage which may result to leakages.
o Solid waste contractor for landfill waste has been appointed. The construction
firm handling the project also has in-house waste handling team. Appendix 4
o The site offices located away from the construction area.
o Social waste are presently received into concrete septic tank which are being
evacuated by the LG Council contractors. Appendix 5, 6 & 7
Table 4.8: Summary of Identified Impacts and Proposed Mitigation
Measures and the compliance status for NNAGFWF Project
Mitigation Monitoring – COMPLIANCE
Table 4.8: Summary of Identified Impacts and Proposed Mitigation Measures and the compliance status for NNAGFWF
Project
• Adequate compensation shall be paid to affected farmers for
their farms, crops and economic trees.
• Awareness campaign by means of consultative and stakeholders
forum shall be held at various stages of the project.
o Adequate compensation paid with evidence.
o Consultation is continuous with the Local Authority and communities.
Visit to The Community/ Local Council heads is in progress.
• Proponent shall as part of agreed Memorandum of
Understanding undertake, identified community development
project(s) for the host community.
• Proponent shall support existing social infrastructure to reduce
pressure on the limited ones as a result of influx of people
into the area.
o As part of the Community relation, water is being provided to
irrigate the farms nearby and for the cattle’s rearing around the
project environment. Plate 17
o Woods cut from the project site are given free to the community for
their domestic use. Plates 15 & 16
CHAPTER FIVE
CONCLUSION
• IMM CONCLUSION
• The IMM report has captured the identified and potential impacts of the
project construction stage. The report took into cognizance all the proposed
mitigation measures and proposed plan of measuring compliance in the EIA
for the factory.
• The exercise is a sum total of various activities and programmes carried out
since the project activities began late 2014 to date.
• The evaluation of magnitude and significance of the projects impacts showed
that the environmental components impacted upon are human, heath,
physical surrounding and socio – economics.
• With the exception of vegetation upon which impacts are negative and
permanent for the built up area, air quality is temporal and reversible once
the construction phase is over. The other impacts have been found to be
positive in nature and beneficial both on the short and long term basis.
• A major area of compliance is the preparation of a project phase EMP
document which is being strictly followed and will be reviewed when
necessary.
• In conclusion, the mandatory IMM Exercise for the EIA of the proposed
Nestle Waters Abaji Green Field Factory is compiled and presented with all
the mitigation measures for consideration and approval.

Contenu connexe

Tendances

Consolidation
ConsolidationConsolidation
ConsolidationAmr Assr
 
Methods of in site Permeability Test
Methods of in site Permeability TestMethods of in site Permeability Test
Methods of in site Permeability TestGaurang Kakadiya
 
Historical Development of Fiction
Historical Development of FictionHistorical Development of Fiction
Historical Development of FictionBruce Clary
 
Presentation on Full Depth Rehabilitation
Presentation on Full Depth RehabilitationPresentation on Full Depth Rehabilitation
Presentation on Full Depth Rehabilitationhsiengineering
 
Geotechnical engineering 1
Geotechnical engineering   1Geotechnical engineering   1
Geotechnical engineering 1R VIJAYAKUMAR
 
Presentation on Ah, you are digging my grave? By Thomas Hardy
Presentation on Ah, you are digging my grave? By Thomas HardyPresentation on Ah, you are digging my grave? By Thomas Hardy
Presentation on Ah, you are digging my grave? By Thomas HardyMuhammed Arif
 
Various Tests in Highway Engineering
Various Tests in Highway Engineering Various Tests in Highway Engineering
Various Tests in Highway Engineering SK Iftekhar Islam
 
Importance of highway maintenance
Importance of highway maintenanceImportance of highway maintenance
Importance of highway maintenanceDharmesh Vadher
 
Geogrid-As a soil reinforcement
Geogrid-As a soil reinforcementGeogrid-As a soil reinforcement
Geogrid-As a soil reinforcementssp1505
 
Important Transport Highway related agencies in India
Important Transport Highway related agencies in India Important Transport Highway related agencies in India
Important Transport Highway related agencies in India RAMPRASAD KUMAWAT
 
9.INTRODUCTION TO CONSTRUCTION MANAGEMENT (ACE) GTU
9.INTRODUCTION TO CONSTRUCTION MANAGEMENT (ACE) GTU9.INTRODUCTION TO CONSTRUCTION MANAGEMENT (ACE) GTU
9.INTRODUCTION TO CONSTRUCTION MANAGEMENT (ACE) GTUVATSAL PATEL
 
Report on airport engineering
Report on airport engineeringReport on airport engineering
Report on airport engineeringAbhishekChavan63
 
Basicsofsoilmechanics
Basicsofsoilmechanics Basicsofsoilmechanics
Basicsofsoilmechanics Dr. N. Nalanth
 
Soil stabilisation (1)
Soil stabilisation (1)Soil stabilisation (1)
Soil stabilisation (1)Safiullah Khan
 

Tendances (20)

Consolidation
ConsolidationConsolidation
Consolidation
 
Geo environmental engineering assignment
Geo environmental engineering assignmentGeo environmental engineering assignment
Geo environmental engineering assignment
 
Methods of in site Permeability Test
Methods of in site Permeability TestMethods of in site Permeability Test
Methods of in site Permeability Test
 
Historical Development of Fiction
Historical Development of FictionHistorical Development of Fiction
Historical Development of Fiction
 
Lateral Earth pressure
Lateral Earth pressureLateral Earth pressure
Lateral Earth pressure
 
Presentation on Full Depth Rehabilitation
Presentation on Full Depth RehabilitationPresentation on Full Depth Rehabilitation
Presentation on Full Depth Rehabilitation
 
Geotechnical engineering 1
Geotechnical engineering   1Geotechnical engineering   1
Geotechnical engineering 1
 
Presentation on Ah, you are digging my grave? By Thomas Hardy
Presentation on Ah, you are digging my grave? By Thomas HardyPresentation on Ah, you are digging my grave? By Thomas Hardy
Presentation on Ah, you are digging my grave? By Thomas Hardy
 
Various Tests in Highway Engineering
Various Tests in Highway Engineering Various Tests in Highway Engineering
Various Tests in Highway Engineering
 
Importance of highway maintenance
Importance of highway maintenanceImportance of highway maintenance
Importance of highway maintenance
 
Geogrid-As a soil reinforcement
Geogrid-As a soil reinforcementGeogrid-As a soil reinforcement
Geogrid-As a soil reinforcement
 
Compaction
CompactionCompaction
Compaction
 
Canadian pdf
Canadian pdfCanadian pdf
Canadian pdf
 
Important Transport Highway related agencies in India
Important Transport Highway related agencies in India Important Transport Highway related agencies in India
Important Transport Highway related agencies in India
 
9.INTRODUCTION TO CONSTRUCTION MANAGEMENT (ACE) GTU
9.INTRODUCTION TO CONSTRUCTION MANAGEMENT (ACE) GTU9.INTRODUCTION TO CONSTRUCTION MANAGEMENT (ACE) GTU
9.INTRODUCTION TO CONSTRUCTION MANAGEMENT (ACE) GTU
 
READY MIX CONCRETE
READY MIX CONCRETEREADY MIX CONCRETE
READY MIX CONCRETE
 
Report on airport engineering
Report on airport engineeringReport on airport engineering
Report on airport engineering
 
Basicsofsoilmechanics
Basicsofsoilmechanics Basicsofsoilmechanics
Basicsofsoilmechanics
 
July 30-130-Ken Kagy1
July 30-130-Ken Kagy1July 30-130-Ken Kagy1
July 30-130-Ken Kagy1
 
Soil stabilisation (1)
Soil stabilisation (1)Soil stabilisation (1)
Soil stabilisation (1)
 

Similaire à IMM PRESENTATION

Environmental Risk Assessment - BOSH
Environmental Risk Assessment - BOSH Environmental Risk Assessment - BOSH
Environmental Risk Assessment - BOSH Abirami V Veeramani
 
Emergency Management Plan
Emergency Management PlanEmergency Management Plan
Emergency Management PlanAbdullah Madir
 
Procedure for EIA.pptx
Procedure for EIA.pptxProcedure for EIA.pptx
Procedure for EIA.pptxthanga2
 
Procedure for EIA.pptx
Procedure for EIA.pptxProcedure for EIA.pptx
Procedure for EIA.pptxthanga2
 
manunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdfmanunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdfChandanLawrence
 
environmental impact assessment
environmental impact assessment environmental impact assessment
environmental impact assessment Pramoda Raj
 
Regulatory Approach in Soil Erosion and Sedimentation Control for EIA Project
Regulatory Approach in Soil Erosion and Sedimentation Control for EIA ProjectRegulatory Approach in Soil Erosion and Sedimentation Control for EIA Project
Regulatory Approach in Soil Erosion and Sedimentation Control for EIA ProjectDrAbdulRahmanMahmud
 
Assessment and operational control of on site environmental impacts- moemen a...
Assessment and operational control of on site environmental impacts- moemen a...Assessment and operational control of on site environmental impacts- moemen a...
Assessment and operational control of on site environmental impacts- moemen a...Moemen Ahmed
 
CET 415 Module IV.pptx
CET 415 Module IV.pptxCET 415 Module IV.pptx
CET 415 Module IV.pptxFARSANA26
 
ENVIRONMENTAL IMPACT ASSESSMENT (EIA) .
ENVIRONMENTAL IMPACT ASSESSMENT (EIA) .ENVIRONMENTAL IMPACT ASSESSMENT (EIA) .
ENVIRONMENTAL IMPACT ASSESSMENT (EIA) .onkar solshe
 
Environmental Auditing in a Austainable Setting in Malaysia by Mr Subramaniam...
Environmental Auditing in a Austainable Setting in Malaysia by Mr Subramaniam...Environmental Auditing in a Austainable Setting in Malaysia by Mr Subramaniam...
Environmental Auditing in a Austainable Setting in Malaysia by Mr Subramaniam...Moon Girl
 
Environmental Impact Assignment
Environmental Impact Assignment Environmental Impact Assignment
Environmental Impact Assignment Hemant Thakur
 
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )sandeepprasad87
 
REVIEW ON ENVIRONMENTAL IMPACT ASSESSMENT FOR CHENNAI METRO RAIL PHASE 2
REVIEW ON ENVIRONMENTAL IMPACT ASSESSMENT FOR CHENNAI METRO RAIL PHASE 2REVIEW ON ENVIRONMENTAL IMPACT ASSESSMENT FOR CHENNAI METRO RAIL PHASE 2
REVIEW ON ENVIRONMENTAL IMPACT ASSESSMENT FOR CHENNAI METRO RAIL PHASE 2Sadique Khan
 
HOW PROJECT IMPACT ASSESSMENT OF THE ENVIRONMENT OF AN ORGANIZATION AND STAK...
 HOW PROJECT IMPACT ASSESSMENT OF THE ENVIRONMENT OF AN ORGANIZATION AND STAK... HOW PROJECT IMPACT ASSESSMENT OF THE ENVIRONMENT OF AN ORGANIZATION AND STAK...
HOW PROJECT IMPACT ASSESSMENT OF THE ENVIRONMENT OF AN ORGANIZATION AND STAK...Abraham Ncunge
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact AssessmentSonikaPawar
 
Environmental Literacy Assignment 2 Video 4 ,6 and 7 (1).pptx
Environmental Literacy Assignment 2 Video 4 ,6 and 7 (1).pptxEnvironmental Literacy Assignment 2 Video 4 ,6 and 7 (1).pptx
Environmental Literacy Assignment 2 Video 4 ,6 and 7 (1).pptxSharonmusekese
 

Similaire à IMM PRESENTATION (20)

Environmental Risk Assessment - BOSH
Environmental Risk Assessment - BOSH Environmental Risk Assessment - BOSH
Environmental Risk Assessment - BOSH
 
Emergency Management Plan
Emergency Management PlanEmergency Management Plan
Emergency Management Plan
 
Procedure for EIA.pptx
Procedure for EIA.pptxProcedure for EIA.pptx
Procedure for EIA.pptx
 
Procedure for EIA.pptx
Procedure for EIA.pptxProcedure for EIA.pptx
Procedure for EIA.pptx
 
Iee
IeeIee
Iee
 
manunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdfmanunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdf
 
environmental impact assessment
environmental impact assessment environmental impact assessment
environmental impact assessment
 
Regulatory Approach in Soil Erosion and Sedimentation Control for EIA Project
Regulatory Approach in Soil Erosion and Sedimentation Control for EIA ProjectRegulatory Approach in Soil Erosion and Sedimentation Control for EIA Project
Regulatory Approach in Soil Erosion and Sedimentation Control for EIA Project
 
Environmental impact assessment (EIA)
Environmental impact assessment (EIA)Environmental impact assessment (EIA)
Environmental impact assessment (EIA)
 
Assessment and operational control of on site environmental impacts- moemen a...
Assessment and operational control of on site environmental impacts- moemen a...Assessment and operational control of on site environmental impacts- moemen a...
Assessment and operational control of on site environmental impacts- moemen a...
 
CET 415 Module IV.pptx
CET 415 Module IV.pptxCET 415 Module IV.pptx
CET 415 Module IV.pptx
 
ENVIRONMENTAL IMPACT ASSESSMENT (EIA) .
ENVIRONMENTAL IMPACT ASSESSMENT (EIA) .ENVIRONMENTAL IMPACT ASSESSMENT (EIA) .
ENVIRONMENTAL IMPACT ASSESSMENT (EIA) .
 
Environmental Auditing in a Austainable Setting in Malaysia by Mr Subramaniam...
Environmental Auditing in a Austainable Setting in Malaysia by Mr Subramaniam...Environmental Auditing in a Austainable Setting in Malaysia by Mr Subramaniam...
Environmental Auditing in a Austainable Setting in Malaysia by Mr Subramaniam...
 
Environmental Impact Assignment
Environmental Impact Assignment Environmental Impact Assignment
Environmental Impact Assignment
 
Ecw 579 week 13
Ecw 579 week 13Ecw 579 week 13
Ecw 579 week 13
 
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )
 
REVIEW ON ENVIRONMENTAL IMPACT ASSESSMENT FOR CHENNAI METRO RAIL PHASE 2
REVIEW ON ENVIRONMENTAL IMPACT ASSESSMENT FOR CHENNAI METRO RAIL PHASE 2REVIEW ON ENVIRONMENTAL IMPACT ASSESSMENT FOR CHENNAI METRO RAIL PHASE 2
REVIEW ON ENVIRONMENTAL IMPACT ASSESSMENT FOR CHENNAI METRO RAIL PHASE 2
 
HOW PROJECT IMPACT ASSESSMENT OF THE ENVIRONMENT OF AN ORGANIZATION AND STAK...
 HOW PROJECT IMPACT ASSESSMENT OF THE ENVIRONMENT OF AN ORGANIZATION AND STAK... HOW PROJECT IMPACT ASSESSMENT OF THE ENVIRONMENT OF AN ORGANIZATION AND STAK...
HOW PROJECT IMPACT ASSESSMENT OF THE ENVIRONMENT OF AN ORGANIZATION AND STAK...
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
Environmental Literacy Assignment 2 Video 4 ,6 and 7 (1).pptx
Environmental Literacy Assignment 2 Video 4 ,6 and 7 (1).pptxEnvironmental Literacy Assignment 2 Video 4 ,6 and 7 (1).pptx
Environmental Literacy Assignment 2 Video 4 ,6 and 7 (1).pptx
 

IMM PRESENTATION

  • 1. NESTLE NIGERIA PLC QUARTER 1 EIA-IMPACT MITIGATION MONITORING (IMM) OF NESTLE WATERS GREENFIELD FACTORY PROJECT, ABAJI, FCT ABUJA 21ST MAY, 2015
  • 2. QUARTER 1 IMM TABLE OF CONTENTS CHAPTER 1 INTRODUCTION CHAPTER 2 METHODOLOGY FOR MONITORING CHAPTER 3 MATERIALS AND METHODS OF ANALYSIS CHAPTER 4 RESULT OF MONITORING CHAPTER 5 CONCLUSIONS BIBLIOGRAPHY / APPENDIX
  • 3. IMM PREPARERS • Alh SOLABI, Gbolahan Adisa FIPAN ,FNIFST, JP Executive Director /CEO • Mr. OKUMODI Adewunmi Olufemi, (M.Sc) MNIFST, Snr. Scientific Officer • Mr. BAMTEFA Joseph A. MNIFST Technical Coordinator • Mr. IKUGBYIGBE Oluwatoyin (M.Sc) Environmental Officer • Dr. OJOSIPE, Sola FIPAN Associate (BATO LAB) • NESTLE NIGERIA Plc Engr. KOBOU Sylvain E2E Project Manager • Engr. ALUKO Ezekiel Project Engineering Manager (Ind. Services) • Engr. CHARBON Luc Project Engineering Manager (Process) • Mr. FAMBEGBE Ayodele SHE Officer
  • 4. EXECUTIVE SUMMARY • Impact Mitigation Monitoring (IMM) Background • Project Background • IMM Objective • The EIA mitigation monitoring exercise is aimed at ensuring compliance with regulatory requirements and standards as well as implementation of prescribed mitigation measures already outlined in the EIA - EMP • Methodology • Sampling and analysis to generate verifiable empirical data by accredited FMEnv Laboratory • Inspection and surveillance / Audit of project site • Environmental data collection on and socio- economic and health condition measurements (i.e payment of compensation, employment of local people, report of any health challenges, consultations) • Discussion, finding and Results of Monitoring • Conclusions
  • 5. CHAPTER ONE INTRODUCTION • Impacts Mitigation Monitoring Plan ( IMMP) is an important tool that can be used to measure and check, in a continous mode the efficacy of the proposed mitigation measures recommended by an Environmental Assessment. • The Mitigation measures incorporated into the project implementation process, which is aimed at eliminating, minimizing negative impacts and enhancing the positive impacts are hereby evaluated whether they are adequate or not.
  • 6. INTRODUCTION • Impacts Mitigation Monitoring (IMM) is necessary to ensure that corrective actions are taken where proposed mitigation measures are found to be inadequate. • Impact mitigation for this stage of the project covers both the site preparation and the construction phases.
  • 7. PROJECT BACKGROUND • Nestle proposed to build a New Water factory at Abaji in 2013 • Project was approved for EIA studies in July 2013 • EIA was completed and reviewed in May 2014 • Approval was given for Construction to begin and IMM to be conducted.
  • 8. CHAPTER TWO METHODOLOGY OF MONITORING • Awareness and Training • Safety Health and Environment Induction • Sampling and Analysis • Inspection and Surveillance / Audit • Socio-economic and Health evaluation • Consultations • Parameters Monitoring
  • 9. IMM SAMPLING STATIONS • A TOTAL OF NINE SAMPLING STATIONS WERE CHOSEN • SAMPLING STATIONS WERE CHOSEN TO COVER AREA THAT HAVE BEEN IMPACTED • AIR QUALITY - 6 SAMPLING STATIONS • WATER - 3 SAMPLING STATIONS • SOIL - 3 SAMPLING STATIONS • VEGETATION - TAKEN WITHIN AND AROUND PROJECT SITE
  • 10.
  • 11. CHAPTER FOUR RESULTS OF AIR QUALITY MONITORING Parameters SAMPLING POINTS A B C D E F FMENV LIMITSControl Mandereji Near Borehole No.2 Waste Segregation Area Uphill near fence Mandereji Community Within the Factory building Near Gate House BL MN BL MN BL MN BL MN BL MN BL MN NO, (ppm) ND ND ND ND ND 0.2 ND ND ND ND ND ND 0.05 CO, (ppm) 4.6 3.2 2.9 3.1 3.1 7.6 3.5 3.9 4.5 5.9 4.2 4.7 20 SO2 (ppm) 0.15 ND ND ND ND 0.2 <0.1 0.1 0.15 <0.1 0.1 ND 0.1 CH4 (ppm) ND ND ND ND ND 1.4 ND ND ND ND ND ND NS O2 (%) 21.5 20.8 21.4 20.6 21.5 20.5 21.5 20.520.5 21.5 20.5 21.6 20.4 NS TSP (ug/m3 ) 150 ND 210 ND 210 ND 200 ND 190 ND 160 ND 250
  • 12. Summary of Air Quality Monitoring : Quarter 1, 2015  • 4.2.1 Nitrogen Oxide • Nitrogen  Oxide   was  not  detected  in  any  other  area  of  the  project  site  except  for  the  Waste  segregation  area  (0.2ppm) which  is  close  to the  point  of  source  of   project  generator  area.  The  impact  is  short  term  as   the  diesel  powered  generator  will  only  be  used  for  the  construction  phase  only.  Appropriate  mitigation   measures  are  however  in  place. •   • 4.2.2 Carbon Monoxide • Carbon  monoxide  range  of  (3.2 – 7.6)ppm  were  all  within  the  FMEnv  limit  of  20.0ppm. Baseline  maximum   of  4.9ppm  was  however  exceeded  at  three  locations  which  were  close  to  the  generator  area  and  also  the   direction  of  wind  in  the  project  area. The  deviation  may  not  be  unconnected  with  the  power  generating   set  in  use  for  the  construction  phase  of  the  project. •   • 4.2.3 Sulphur Dioxide • The  maximum  concentration  of  Sulphur  dioxide  (0.2ppm)  was  recorded  in  only  one  location,  near  the   waste  segregation  area close  to  the  power  generating  set. The  values  is  slightly  above  the  FMEnv  limit  of   0.1ppm.  Baseline  condition  also  showed  a  maximum  of  0.15  hence  the  marginal  increase  may  be   connected  to  the  site  power  source. The  impact  will  be  temporal  and  not  of  significant  effect  if  all  the   recommended  mitigation  measures  are  strictly  adhered  to. •   • 4.2.4 Combustible Gas as Methane (CH4)    • The  value of  combustible methane  were  not  detected  during  the  baseline  studies.  A  concentration  of   1.4ppm  was  detected  in  one  location  during  the  IMM,  although  there  is  no  FMEnv  standard, the  level  is   not  of  any  negative  significance  environmentally. •   •   • 4.2.5 Percentage Atmospheric Oxygen • The  percentage  atmospheric  oxygen  ranged  between 20.4 – 20.8.  Highest  baseline  data ranged  between  21.4   and  21.6.  Both  values  are  normal  and  satisfactory. •   • 4.2.6 The  values  of  TSP  for  baseline  conditions were  all  within  the  FMEnv  standards.  IMM  measurements   were  not  determined  due  to  calibration  exercise  being  conducted  on  the  meter  outside  the  country.
  • 13. NOISE LEVEL S/N AVERAGE NOISE LEVEL dB(A) LOCATION BL MN FMENV WET DRY AVR. (WET&DRY) QUARTER 1 A ControlMandereji 69 76 72.3 77 90 B Near BoreholeNo.2 56.5 60.0 58.3 61 90 C WasteSegregation Area 54.6 62.5 58.6 75 90 D Uphill near fence ManderejiCommunity 60.0 58.5 59.3 65 90 E Withinthe Factorybuilding 61.0 63.5 62.5 57 90 F Near GateHouse 59.0 63.0 61.0 67 90
  • 14. RESULT OF GROUND AND SURFACE WATER MONITORING • Summary of Results • Ground water analysis for Quarter 1 • The  quality  of  the  raw  borehole  water  samples  analyzed  were  both   satisfactory pH  ranged  between  7.0  and  7.3 for  drinking  water  standards   except  for the  high  Iron  level  of  1.4 mg/kg  present  in  the  Nestle Borehole   water  sample. The  same  high  trend  was  recorded  as  baseline.  Iron  removal   has  been  incorporated  in  the  water  treatment  system. •   • Surface Water analysis for Quarter 1 • The   parameters  analyzed  for  in  the  Mandereji  Stream  Water  sample  showed   satisfactory  physico-chemical  properties  except  for  the  high  Iron  level as   well.  The  microbiological  parameters  investigated   showed  the  presence of   coliforms (17cfu/ml)  and  bacteria  count  too numerous  to count. • All  the  parameters  measured  for  both  surface  and  ground  water  were  in    the  same  trend  as  those  of  the  EIA  baseline.  There  is  no  indication  of   pollution from  the  on-going  project  activities. •  
  • 15. SOIL  EVALUATION • Soil Analysis • The  Soil  Samples  are  neutral  with  pH   values ranging  from  6.96 - 7.12.  Also, this   samples  are  considered  rich  in minerals.  No   negative  impact  on  the  soil  as  a  result  of   on-going  construction  work.
  • 16. VEGETATION AND WILD LIFE • Vegetation • Impact mitigation was conducted for the project construction phase that is in progress. The identified impacts on vegetation, proposed mitigation measures and comments on the impact mitigation monitoring are presented in Table 4.8 • Apart from basic farming activities that have been stopped in the project area, The natural vegetation have been eliminated in the area where construction activities are on-going. • The natural habitat of most of the plant species have been altered with some permanently concreted for factory use. • The trees within the project site have been cut and are being used as firewood for the temporary canteen and also given free to the local community. • Some economic trees were still in place as construction activities were yet to get to their location. • Table 4.3 is a list of economic trees still existing in the project area. • Wildlife • The construction of perimeter fence to secure the project site from unnecessary intrusion has led to the displacement of wildlife identified during the baseline studies. Apart from some of the area where the bush have been left for future development, wildlife population have been negatively impacted., Mammals and birds have virtually migrated from the project site. A biodiversity monitoring plan has been prepared for monitoring of the ecology of the project area. Table 4.4.
  • 17. Table 4.8: Summary of Identified Impacts and Proposed Mitigation Measures and the compliance status for NNAGFWF Project Mitigation Monitoring – COMPLIANCETable 4.8: Summary of Identified Impacts and Proposed Mitigation Measures and the compliance status for NNAGFWF Project Mitigation Measure Mitigation Monitoring • Compensate communities for land take and farmlands. • Recruitment and training of locals for project’s jobs (security, unskilled labour) • Engagement of Local as interpreters and mediators in compensation processes. o Evidence of compensation with detailed of the beneficiaries available (Appendix 1) o Engagement of local labour through construction firm effected. List of names and post of local engaged provided in Appendix 2 o Appropriate channel of dissemination of job availability and recruitment was followed by presenting the vacancies to the community head and assuring that qualified locals will be engaged. List of names of local employees and their residence. Appendix 2 • use existing access routes / ways and ensure minimum clearing during site survey. • Re – grassing / Flowering of Project surrounding. • Removal of excess excavated soil for re – use (in other project – road repairs / remediation of erosion areas etc) • Cement concrete / paving of un – grassed area. • Use equipment with low levels of noise and emissions that are within the acceptable national standards and specifications • Ensure that water be sprinkled on open surface during excavation to reduce amount of soil particulates • Use Power sourced from the National grid where available to minimize burning of fossil fuel. • Ensure movement of trucks and heavy duty vehicles are properly timed to ensure minimal interference with local transportation as well as that of the major highway. • construction of screens on storm water pathway to reduce surface water contamination o Only the areas to be use for construction has been excavated. Thereby still leaving some areas of natural vegetation for existing wildlife to inhabit. (See Plates 1 &2) o The topograghy of the land were taken advantaged of. The upland has been slightly leveled removing majorly the topsoil and to some extent some laterites to fill up undulating areas. (see plate 3) o Topsoils have been piled at specific location for re-use during landscaping for flowering and regressing purposes. Plate 4 o The structure of the land (profile) has not been significantly affected see Table 4.7 o The generator on site were carefully chosen and strategically located. One sound proof generator is used at the borehole site due to the proximity to the office there. The noise level measured confirms the observation. Table 4.2 o While the construction phase is one, the storm water course is being determined. Thus natural flow of storm water is to be followed for the discharge into the bigger body of water. Plate 5 o The fencing has thus put into consideration the storm eater pathway and outlet for the storm water has been incorporated into the project design. (see plate 5)
  • 18. Table 4.8: Summary of Identified Impacts and Proposed Mitigation Measures and the compliance status for NNAGFWF Project Mitigation Monitoring – COMPLIANCE Table 4.8: Summary of Identified Impacts and Proposed Mitigation Measures and the compliance status for NNAGFWF Project • Use of appropriate PPE. • Use of relevant safety instruction and illustrations • Site Safety Health Management Procedures • Limit Access to project Site. • Clearing and Excavations to be done in Dry Season • Good housekeeping practices and proper handling of oil. • Solid wastes to be disposed off by licensed/ accredited waste contractors. • Storage of construction materials at designated area within the site and enforcement of good site management and engineering practices. • Reduction at source, sorting and separation of materials for re-use and sale to third party users. • Proper insulation of pipes to prevent leakage and damage. o Compliance with the use of PPE on site is over 95% . Plate 9 & 10. See Appendix 3 – She requirement for Contractors. o Relevant safety instructions are displayed at strategic places around the project site. (Plates 6) o Daily safety briefing are held every morning before work commences. Plates 7- 10 o Good house keeping practices is evidence at the site. Construction area are marked, walk ways are designated with reflective tapes, (plates 11-14) o Handling of oil waste from operation in the site is well documented. Waste oil are received into empty kegs and properly labeled for recycle via selling to third party vendors. o Source reduction of waste is practiced and segregation ensured. Iron, wood, and domestic wastes are separated. Plate 14 o Waste bags of cement is segregated and packaged for sale. Plate 13 o Pipes are well buried at about 1m below foundation and the foundation casted to prevent damage which may result to leakages. o Solid waste contractor for landfill waste has been appointed. The construction firm handling the project also has in-house waste handling team. Appendix 4 o The site offices located away from the construction area. o Social waste are presently received into concrete septic tank which are being evacuated by the LG Council contractors. Appendix 5, 6 & 7
  • 19. Table 4.8: Summary of Identified Impacts and Proposed Mitigation Measures and the compliance status for NNAGFWF Project Mitigation Monitoring – COMPLIANCE Table 4.8: Summary of Identified Impacts and Proposed Mitigation Measures and the compliance status for NNAGFWF Project • Adequate compensation shall be paid to affected farmers for their farms, crops and economic trees. • Awareness campaign by means of consultative and stakeholders forum shall be held at various stages of the project. o Adequate compensation paid with evidence. o Consultation is continuous with the Local Authority and communities. Visit to The Community/ Local Council heads is in progress. • Proponent shall as part of agreed Memorandum of Understanding undertake, identified community development project(s) for the host community. • Proponent shall support existing social infrastructure to reduce pressure on the limited ones as a result of influx of people into the area. o As part of the Community relation, water is being provided to irrigate the farms nearby and for the cattle’s rearing around the project environment. Plate 17 o Woods cut from the project site are given free to the community for their domestic use. Plates 15 & 16
  • 20. CHAPTER FIVE CONCLUSION • IMM CONCLUSION • The IMM report has captured the identified and potential impacts of the project construction stage. The report took into cognizance all the proposed mitigation measures and proposed plan of measuring compliance in the EIA for the factory. • The exercise is a sum total of various activities and programmes carried out since the project activities began late 2014 to date. • The evaluation of magnitude and significance of the projects impacts showed that the environmental components impacted upon are human, heath, physical surrounding and socio – economics. • With the exception of vegetation upon which impacts are negative and permanent for the built up area, air quality is temporal and reversible once the construction phase is over. The other impacts have been found to be positive in nature and beneficial both on the short and long term basis. • A major area of compliance is the preparation of a project phase EMP document which is being strictly followed and will be reviewed when necessary. • In conclusion, the mandatory IMM Exercise for the EIA of the proposed Nestle Waters Abaji Green Field Factory is compiled and presented with all the mitigation measures for consideration and approval.