European Journal of Business and Management                                                     www.iiste.org
ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online)
Vol 4, No.1, 2012

         The Adequacy of Contractual Provisions in Managing

                          Construction Failure in Malaysia

           Mohamad Ibrahim Mohamad1 Mohammad Ali Nekooie1* Naadira Binti Che Kamaruddin1
    1.   Department of Structures and Material, Faculty of Civil Engineering (FKA), Universiti Teknologi
         Malaysia (UTM), Skudai, Johor, 81310, Malaysia.
    * E-mail of the corresponding author: anmohammad2@live.utm.my


Abstract
Arising of any failure in construction is a vital issue. It could be a source of dispute among different parties
involved in construction. Therefore, the contract is the main reference to overcome issues regarding to
failure claims. When construction failure occurred after the contractual period, the contract provisions are
not applicable. Moreover, the contractual relationships couldn’t be referred anymore. Thus, all parties seek
to the justice to define their role and duty on failure loss and remedial cost based on the contract. The level
of inadequacy of failure management consideration in the current contract documents was measured.
Moreover, the limitations in current contractual provisions were evaluated to suggest the new scope for
contractual provisions in managing construction failure. The evaluations were performed by interview with
a panel of experts in the construction industry and legal sector. Furthermore, all current contracts provisions
were investigated. Therefore, any related issues to the failure events were illustrated precisely. Then, the
questionnaire survey identified the limitations and indicated opportunities to extend the scope of current
provisions. Related Index was used to rank the factors and issues based on their importance. Refusing to
cooperate during the failure event from default parties is the main limitation. Moreover, low quality of
completed projects; bringing a bad image to client, and disputes between the involved parties are the main
causes due to limitations based on engineers’ and the legal sector’s ideas. The new scope of contractual
provisions was approved by more than %70 of the respondents.
Keywords: Building failure; Contract conditions; Contract documentation; Contract law.


1. Introduction
The incidents of structural failures have generated a lot of tension to the public recently. Despite some of
the cases have been publicity reported by the mass media, but most of the cases are not reported at all and
only known to the stakeholders of the effected structures (Allen, 2010). Structural failure can be
contributed by many factors. It can be due to poor design, poor detailing, poor quality control and
construction error or due to inferior material quality used in construction or even manmade mistakes
because of poor health and long working time of the labours. Some of these issues cause fatigue and stress,
and an accident is one possible outcome (Carper, 1986, Bracken and Roda, 2007, Sang et al., 2007,
Frühwald and Thelandersson, 2008, Chan, 2011). Arising of any failure in construction is a vital issue.
Since, construction firms have not put sufficient emphasis on strategic planning; it could be a source of
dispute among different parties involved in construction (Soetanto and Dainty, 2009). Therefore, the
contract is the main reference to overcome any issues regarding to failure claims (Janney, 1986). However,
any uncertainty and equivocalness of clients should be managed to prevent any further disputes (Levander
et al., 2011). Janney (1986) defines the construction failure as a failure that occurs during the construction
project and after the project completed. They are considered to be either collapse, or distress of a structural
system to such a degree that it cannot safely serve its intended purpose. Hence, these study focusing on the
failure after the construction period; most of the failures in a construction project mainly in building
construction generate controversy, long and expensive argument (Jacob Feld, 1997). This will follow by a



                                                      22
European Journal of Business and Management                                                       www.iiste.org
ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online)
Vol 4, No.1, 2012

litigation process to resolve those issues. Therefore, failure in a construction project has close relations to
the ability of building structure to receive such massive loads and also depends on the quality of the
material applied.
Structural failure affects both the appearance and structural stability of the building. Most of the building
consists of combination of three basic elements such as walls, roofs and floors. These elements are
arranged to create both space division and unobstructed space (Ambrose, 1993) according to building’s
functions. Commonly, the causes of structural collapse include poor workmanship, lack of supervision just
to name a few, which lead to serviceability problems such as distress, excessive deformation, leaking roofs
and facades, and also inadequate interior environmental control system (Kaminetzky, 1976, Yates and
Lockley, 2002, Messervey, 2007, Jacob Feld, 1997, Carper, 1986). On the other hand, former studies try to
estimate exact probabilities of occurrence of fault events (Pan, 2006). However, more precise
categorization for classifying the structural failure could be defined as element errors, errors in site
selection and development, planning and scheduling deficiencies, errors in design, errors during
construction, deficiencies of material and errors in service operation.
From previous research, there were surveys, which indicated several numbers of methods that appropriate
to minimize construction failure (Yates and Lockley, 2002, Hall and Tomkins, 2001). It is commonly
known that construction failure cannot be eliminated as it only can be reduced or minimized by improving
the current construction environment. The lists of methods in reducing the failure in construction gained
from that survey which received most responds from their respondents as stated below:
1. Design and detailing of critical connections by the engineer of record.
2. Design and supervision of construction of temporary structures by a professional engineer.
3. Clear definition of responsibility among the engineer, contractor and employer or client.
4. Constructability reviews during design stage.
5. Full time inspection of construction by structural engineers.
6. Peer review of the structural design and details by an independent professional.
In order to overcome the failure event, several contract documents are established by the statutory body and
professional societies. There are a number of provisions that govern the quality of construction works, and
some of the research shows the need of prequalification to ensure the quality of contactors’ work (Hatush
and Skitmore, 1997, Russell et al., 1992). They also specify the role and responsibilities of parties in the
contracts in respect of defects. Moreover, the party’s rights and obligations to a contract are governed by
the contract itself. Previous study also stated that most construction contracts specify certain extraordinary
powers to a particular person. This person’s decisions are final and binding upon both parties (Iyer and
Satyanarayana, 2002). However, the effects of provisions are only limited during the contractual period.
Although there are governing laws to manage construction failure, the process is lengthy and costly.
The investigation of documents only focused on the available form of contract that is commonly used in
Malaysia. These forms of contracts are:
 PWD Form 203/203A (Rev.2007);
 PAM Contract 2006 (With Quantities);
 I.E.M Conditions of Contract for Works Mainly of Civil Engineering Construction;
 CIDB Standard Form of Contract for Building Works 2000 Edition and
 Occasional reference shall be made to the FIDIC Form as a matter of interest. FIDIC contract which is
better described by its title ‘Conditions of Contract (International) for Works of Civil Engineering
Constructions’.
The contract documents are necessary as aid tools in a construction process (Laryea, 2011). Thus in the
occurrence of construction failure it helps to each party know their rights and obligations during
construction activities. The significant reasons are the client, and the professional advisors will know
exactly what they want the respected party that doing the construction to perform well in terms of design,



                                                       23
European Journal of Business and Management                                                     www.iiste.org
ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online)
Vol 4, No.1, 2012

quantity, quality and specification. Since legal knowledge is important in dealing with contract terms,
construction practitioners must have at least basic knowledge to ensure the effectiveness of particular
provisions. Therefore, rights and obligations of the parties to a contract are governed by the contract itself
(Neo, 2005, Kremers et al., 2010). These rights and obligations will be expressly informed in the contract
and are known as the express terms of the contract. In addition, there are instances where the terms of
contract may be implied to relate the failure in construction with the provision in contract documents.
Better understanding and clear interpretation are needed to avoid any disputes regarding to contract terms
(Ashworth, 2001).
The adequacy of contractual provisions in managing construction failure is aimed to be evaluated.
Moreover, the new scope of contractual provision for managing structural failure should be provided. Thus,
the objectives consist of identifying the state of art of the existing provisions in managing construction
failure and identifying the limitation of the current provisions in managing construction failure. It tries to
suggest new scopes of provision that should be included in contract document in Malaysia.


2. Method of study
In the first step, it is focusing only on provisions in contract document such as PWD 203/203A, IEM1989,
CIDB 2000, PAM2006 and FIDIC conditions (red book) which related to construction failure. The
comparative table has been extracted and developed based on the clauses in aforementioned contract
documents. The comparative table projects the factors which are covered in the scope of different
provisions in Malaysian and international contract documents.
In general, there are a lot of case laws in construction industries consist of various cases mainly caused by
disputes and breach of contracts due to the failure event. Ten case studies from Malaysian construction
industry extracted from official document of Malaysian central curt. All the case studies have been
investigated, and several limitations due to insurance provision and others are identified and categorized
precisely.
The structured interview has been carried out. This interview consists of ten questions in parallel to the
study objectives, which focuses on the contract limitations and new scope of contract provisions. The aim
of this interview is to identify the relevant clauses and limitations of contract provisions. The interview
session for this study was conducted with ten professionals who are tolerantly dedicated in their respective
field. They have wide knowledge and experience in managing construction failure of more than three years.
Their profession backgrounds consist of Civil Engineers, Lawyers and Quantity Surveyors. Out of ten
interviewees, five of them are Civil Engineers from local authority and consultant firms. Three
interviewees represent Quantity Surveyors from the developers, and other two are the law practitioners.
The study is continued by the questionnaire survey developed based on the information gathered in
previous interview session. The design of the questionnaire is purposely to achieve the second and third
objectives, which are oriented to identify any limitations and the potential of new scope to be considered in
the contract provisions. Respondents were required to rate the information provided in terms of several
choices. The questionnaire was established in three steps. In the first step, respondents presented their
personal information including the field of their profession. In the next step, the respondents identify any
constraints in the contract document based on the information collected in literature search and interview.
Respondents are required to respond on all information by stating their level of agreement based on five
ordinal measures known as Likert Scale from one (1) to five (5) according to specified level. The last
section in this questionnaire requires respondents to state their level of agreement on which the new scope
is suitable to be considered in current contract documents. There were eight potential new scopes identified
from the literature search and interview.
According to the scale, questionnaire rating is following the five-point scale described previously and
converted into relative important indices for each factor. These indices are adopting the Relative Index (RI)
ranking technique based on equation 1 (Kometa et al., 1994).




                                                      24
European Journal of Business and Management                                                       www.iiste.org
ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online)
Vol 4, No.1, 2012


                        n(1) ×1 + n(2) × 2 + n(3) × 3 + n(4) × 4 + n(5) × 5
                 RI =                                                                                           (1)
                                             Ntotal × 5
Where n(i) is the number of responses with scale, i (i=1,..., 5) and N is the total number of responses to
each question. The maximum value for RI is 1, and the minimum is 0.2 accordingly. Moreover, Mann-
Whitney U Test as a non parametric analysis has been employed to illustrate any significant differences
between two independent samples regarding to different professions as engineers and non-engineers.
Totally, 30 questionnaires have been collected from respondents. The frequency distribution is 66.7 percent
for engineers versus 33.3 percent for non-engineers.


3. Result and discussions
3.1 Literatures and Interview
According to the comparative research on different contract document, the provisions could be categorized
in two categories. First are the related provisions, which are mentioned about managing structural failure
straight forward. These provisions are defined in table 1 among all 5 aforementioned contractual
documents.
                                                 ‘Table 1 here’
The second category is regarding to the provisions, which are related to managing structural failures by
their effects. These provisions try to contribute solutions regarding to minor effect of structural failures.
Table 2 defines these provisions in different contractual documents.
                                                 ‘Table 2 here’
Based on the results of the interview, 90% of the respondents had been engaged with structural failure
previously and among all the respondent 70% of them agree with the lack of the adequacy of provisions in
managing structural failure. All the experts appointed clause 44 as the most affected provision in the event
of construction failure. Since the 70% of experts have faced with problems in the current guideline in
managing structural failure, the need of improvement of the guideline is perceived. However, 60% of
interviewees agree with this issue. Furthermore, most of the experts agree for adding the new scope
regarding to managing construction failure. The reasons for adding the new scope consist of protecting the
client’s right, improving quality, to suit current construction scenario and minimizing construction dispute
with scope, which is easy to understand based on experts’ idea. Table 3 tries to identify and summarise the
panel of experts’ idea on each of the questions.
                                                 ‘Table 3 here’
3.2 The Limitations of Current Provisions in Managing Construction Failure
Based on the questionnaire survey nine factors are introduced that lead to limitation in the contract
provisions. Four factors record the highest RI among the others. The first rank is the default parties refused
to cooperate in managing construction failure after the contractual period is over. Although the RI value
(0.81) for first rank is similar with second rank, the frequency on agreed and strongly agreed in the first
factor is higher. Second rank is the need of third party to continue the work if failure happened. Followed
by the 3rd rank (RI=79) which is the lack of knowledge from parties involved about relevant applicable
laws and provisions. Factor with rank 4 also shares a similar RI value (0.79) with 3rd factor, which is the
inconsistency with other standards. The reason is current governing laws, and contract provisions to use
redundant legal expressions. Table 4 summarizes the results of the questionnaire for limitations of current
provisions.
                                                 ‘Table 4 here’
Since the respondents are categorized in two groups, which are engineers and non-engineers such as lawyer
and Quantity Surveyors (QS), table five shows, there is not any significant difference between the ideas on
probable causes that lead to limitation in contract documents of these two groups based on Mann-Whitney



                                                       25
European Journal of Business and Management                                                     www.iiste.org
ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online)
Vol 4, No.1, 2012

test. The results show, there is not any significant different between different groups’ ideas as P values >
0.05 for all factors. Both groups seem to share a similar idea upon these causes.
                                                ‘Table 5 here’
3.3 Effects due to the Limitation of Contractual Provisions
The effects during the construction and after the handovers of the project are being considered to evaluate
the impact of limitations in contractual provisions. Table 6 shows seven effects of limitations stated in
questionnaire and 20 respondents of the engineer group are responding thoroughly. Decreased in project
quality is being identified as the most preferable cause due to the limitations of contractual provisions. It
records the highest RI value (0.84) compare to other causes. Followed by increased in project costs
(RI=0.79). “Disputes between parties involved” and “delay in completion schedule” (RI=0.78) also mostly
preferable by the engineers.
                                                ‘Table 6 here’
Table 7 shows the responses from non engineering group. They give aggressive responds towards the
limitation effects during construction. Their Relative Index value is the highest (RI=0.86) for “increasing in
project cost”, “decreased in project quality” and also “disrespectful aroused from parties involve”. This can
be assumed that non engineer emphasis more on the effects of contractual provisions itself compared to
engineer group.
                                                ‘Table 7 here’
After indicating the limitations, the effects during construction also are identified to show the impact from
the limitation of contractual provisions. Table 8 shows that these two groups have similar ideas on “the
delay in payment and decreased of project quality”. However, they don’t share the similar idea for
“disrespectful from parties involved” as a limitation since the P value is 0.042 < 0.05.
                                                ‘Table 8 here’
Table 9 shows the causes due to the contractual limitations after the project handovers. According to
highest RI value (0.81), “low quality of completed project” is the most important factor in engineers’ side
of view. This also would “bring bad images to the client or employer who owns that project” which get the
3rd rank (RI=0.77) between respondents’ answer.
                                                ‘Table 9 here’
Table 10 shows that majority of non engineer group agreed that contract limitations cause “low quality of a
completed project” (RI=0.92). Then, “disputes would be occurred between parties involved” get second
rank with RI=0.86. Finally, the 3rd rank achieved by “bring bad images to clients as their credibility”.
                                               ‘Table 10 here’
It is also an emphasis on the issues taking place after the handover of construction projects to the client, for
instance “the certified completed building”. There are significant differences between the ideas of an
engineer and non engineer group. This can be seen in table 11, where the P value is 0.015 on “clients do not
have rights to request any action from the contractor after the project handover” and 0.004 on “the client
cannot claim as the contract period is already expired”. Hence, this responds is being assumed with a higher
impression from the engineer group as they practice the construction activities compared to non engineer
who mostly relied on the theory and assumptions from previous cases.
                                               ‘Table 11 here’
3.4 Suggestion of New Scope of Provisions to be Included in Contract Documents
This suggestion is combining all these two groups’ ideas. They state their level of agreement due to the
suggestion provided in the questionnaires.
The result shows 53.33% of the total respondents agree on the suggestion of new scopes. Other 30% are
strongly agreed due this suggestion. Only 16.67% of the total respondents are neither disagree nor agree
with the suggestions. Hence, table 12 below shows the frequency of each suggestion. First rank indicates
that most respondents agreed to this factor “there should be detail and proper procedures of claim issuance


                                                      26
European Journal of Business and Management                                                   www.iiste.org
ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online)
Vol 4, No.1, 2012

to resolve matters arising” (RI=0.85). It is followed by the suggestion on separated clause of construction
failure due to its scope of an event (RI=0.84). Same RI value recorded on specific clauses related to
managing the failure events.
                                              ‘Table 12 here’
4. Conclusions
Majority of the respondents shared similar ideas about the lack of adequacy for contractual provisions.
Either engineers or non engineers are giving strong agreement based on the results except for certain
factors. Decreasing the project quality and increasing the project cost are two main effects due to
limitations in the contractual provisions during the construction period. From the survey, certain questions
are agreed mostly by non engineer group based on their professional point of view; in contrast to the
practitioners in construction industry who are directly involved in managing construction failure. Thus, the
survey also shows that most of the respondents agree, there are limitations when using the contract
documents. Both engineer and non engineer group giving a positive responds to the suggestion of
modifying the new scope in contractual provisions. This scope should follow certain principals as:
- Clear procedure;
- Simplicity;
- Clear classification;
- Ensure effectiveness;
- Extending duration of applicability;
- Developing the guideline.


There is a gap between theory from non engineering group and practice from the engineering group.
However, neither of them sufficiently explains underlying reasons to this gap. Further research is
recommended due to these issues as might help in finding that reasons.

Acknowledgements
References
ALLEN, D. E. 2010. Structural failures due to human error : what research to do? Risk,
Structural Engineering and Human Error : Proceedings of the 2nd University
Symposium on Structural Technology and Risk. Waterloo, Ont. Canada.
AMBROSE, J. 1993. Building Structures, Canada, John Wiley & Sons.
ASHWORTH, A. 2001. Contractual Procedures in the Construction Industry, England,
Pearson Education Limited.
BRACKEN, W. C. & RODA, T. A. 2007. Establishing Protocols for Catastrophe
Damage Assessments of Multiple Buildings, ASCE.
CARPER, K. L. 1986. Forensic Engineering: Learning from Failures, New York, NY,
ASCE.
CHAN, M. 2011. Fatigue: the most critical accident risk in oil and gas construction.
Construction Management and Economics, 29, 341-353.
FRÜHWALD, E. & THELANDERSSON, S. 2008. Design of safe timber structures -
How can we learn from structural failures in concrete, steel and timber? 10th World
Conference on Timber Engineering. Miyazaki, Japan.
HALL, M. & TOMKINS, C. 2001. A cost of quality analysis of a building project:
towards a complete methodology for design and build. Construction Management and
Economics, 19, 727-740.


                                                     27
European Journal of Business and Management                               www.iiste.org
ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online)
Vol 4, No.1, 2012

HATUSH, Z. & SKITMORE, M. 1997. Assessment and evaluation of contractor data
against client goals using PERT approach. Construction Management and Economics,
15, 327-340.
IYER, K. C. & SATYANARAYANA, K. N. 2002. Final and Binding Power Clauses in
Indian Construction Contract. International Journal of Project Management, 20, 13-22.
JACOB FELD, K. L. C. 1997. Construction failure, Canada, John Wiley and Sons.
JANNEY, J. R. 1986. Guide to investigation of structural failures, with editorial
revisions incorporated, Unite State, ASCE Publications.
KAMINETZKY, D. 1976. Structural Failures and How to Prevent Them. Civil
Engineering—ASCE, 46, 60-63.
KOMETA, S. T., OLOMOLAIYE, P. O. & HARRIS, F. C. 1994. Attributes of UK
construction clients influencing project consultants' performance. Construction
Management and Economics [CONSTR. MANAGE. ECON.], 12, 433-443.
KREMERS, J., RIETJENS, B., VOORDIJK, H. & DE BOER, S. J. 2010. Construction
contracting and civil–military interaction. Construction Management and Economics, 28,
871-883.
LARYEA, S. 2011. Quality of tender documents: case studies from the UK. Construction
Management and Economics, 29, 275-286.
LEVANDER, E., ENGSTRÖM, S., SARDÉN, Y. & STEHN, L. 2011. Construction
clients’ ability to manage uncertainty and equivocality. Construction Management and
Economics, 29, 753-764.
MESSERVEY, T. B. 2007. Integration of Structural Health Monitoring into the Design,
Assessment, and Management of Civil Infrastructure. Ph.D, University of Pavia.
NEO, M. 2005. Construction Defects: Your Rights and Remedies, Singapore, Sweet &
Maxwell Asia.
PAN, N. F. 2006. Evaluation of building performance using fuzzy FTA. Construction
Management and Economics, 24, 1241-1252.
RUSSELL, J. S., HANCHER, D. E. & SKIBNIEWSKI, M. J. 1992. Contractor
prequalification data for construction owners. Construction Management and Economics,
10, 117-135.
Soetanto, R., & Dainty, A. R. J. 2009. Integrating uncertainty management in strategic
planning practice. In (pp. 309-319). Seattle, WA.
Sang, K. J. C., Dainty, A. R. J., & Ison, S. G. 2007. Gender: A risk factor for
occupational stress in the architectural profession? Construction Management and
Economics, 25, 1305-1317.
YATES, J. K. & LOCKLEY, E. E. 2002. Documenting and Analyzing Construction
Failures, ASCE.




                                            28
European Journal of Business and Management                                                                                    www.iiste.org
   ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online)
   Vol 4, No.1, 2012


                     Table 1. Related Provisions to failure management in different contact documents
           PWD 203/203A                                                      PAM Contract                     IEM                      FIDIC
                                                  CIDB 2000
            (Rev.2007)                                                          2006                          1989                 (International)
1) Clause 13                                1) Clause 3.5 Urgent        1) Clause 15.0 Practical     1) Clause 3 Scope of       1) Clause 20.1
Performance Bond(PB)/Performance            Repairs                     Completion and defects       the Contract               Contractor
Guarantee Sum(PGS): Clause 13.1(a),         2) Clause 7 General         Liability: Clause 15.1,      2) Clause 32               responsibility until
Clause 13.3, Clause 13.5                    Obligations of The          Clause 15.3, Clause 15.4,    Indemnities to             Taking Over
2) Clause 14.0                              Contractor: Clause 7.1:     Clause 15.5, Clause 15.6     Employer in Respect of     Certificate
Indemnity in Respect of Personal Injuries   Contractor’s General        2) Clause 18.0 Injury to     Personal Injuries and      2) Clause 20.2
and Damage to Property: Clause 14.1         Responsibilities.           Person or Loss and/or        Damage to Property         Contractor
3) Clause 18.0                              3) Clause 12 Setting Out:   Damage of Property and       3) Clause 33 Insurance     responsibility for loss
Insurance of Works: Clause 18.1: Taking     Clause 12.2: Errors in      Indemnity to Employer:       Against Personal           and damage to the
of Insurance, Clause 18.3: Payment of       Setting out                 Clause 18.2                  Injuries and Damage to     satisfaction of the
Insurance in the Event of any               4) Clause 15.7 Defects      3) Clause 19.0 Insurance     Property                   Engineer with his own
Loss/damage                                 during Progress of the      Against Injury to Person     4) Clause 34 Insurance     cost
4) Clause 40.0                              Works                       and Loss and/or Damage       of Works                   3) Clause 40(1)
Damages for Non-Completion: Clause          5) Clause 20.3 Access for   to Property: Clause 19.1     5) Clause 37               Suspension of Work:
40.1, Clause 40.2                           Remedial work               4) Clause 20.A Insurance     Performance Bond: (a)      (b) & (d)
5) Clause 43.0                                                          of New Buildings/ Works      & (d)                      4) Clause 21.1
Delay and Extension of Time: Clause         6,7) Clause 24(1),          – By the Contractor:         6) Clause 40 Damages       Contractor
43.1                                        24(3)(b) Extension of       Clause 20.A.1                for Non-Completion         responsibilities for
6) Clause 45.0                              Time                        5) Clause 20.B Insurance                                insurance
Investigation by the Government and                                     of New Buildings/Works       7) Clause 43               5) Clause 44.1 EOT
Other Persons in Case of Accident,          8) Clause 26 Non-           – By the Employer:           Delay and Extension of     6) Clause 49(1)
Failure or Other Event.                     Completion and Damages      Clause 20.B.1                Time (EOT): (d)            Defects Liability
7) Clause 48.0                              For Delay in Completion:    6) Clause 22.0 Damages       8) Clause 45 Defects       Period: (a) & (b)
Defects After Completion: Clause 48.1:      Clause 26.2:Damages for     for Non-Completion:          After Completion: (a)
Completion of outstanding Work and          non Completion, Clause      Clause 22.1, Clause 22.2     & (e)
Remedying Defects. Clause 48.2: Default     26.3:Employer’s rights      7) Clause 23.0 Extension
in Remedying Defects.Clause 48.3:           for Damages at Law          of Time (EOT): Clause
Diminution of Works. Clause 48.4:           9) Clause 27 Defects        23.1
Certificate of Completion of Making         Liability After
Good Defects                                Completion
8) Clause 50.0                              10) Clause 27.5
Suspension of Works: Clause 50.1:           Contractor To Search
Suspension and Resumption of Works.
Clause 50.2: Extension of Time (EOT)




                                   Table 2. Semi-related provisions in different contract documents
         PWD 203/203A                                                   PAM Contract                      IEM                        FIDIC
                                            CIDB 2000
          (Rev.2007)                                                       2006                           1989                   (International)
   1) Clause 3.1 Duties of S.O       1) Clause 1 Definitions and    1) Clause 1.0 Contractor’s   1) Clause 4 Work to be to    1) Clause 22.1
   and S.O’s Representative          Interpretation: Clause 1.1:    Obligations: Clause 1.2:     Satisfaction of Engineer     Damage to Persons and
   2) Clause 4.0 S.O’s Rights to     Definitions                    Temporary Work and           2) Clause 5 Engineer’s       Property
   Take Action                       The All Risk Insurance         Construction Method          Instruction (EI)             2) Clause 22.3
   3) Clause 5.0 S.O’s               2) Clause 3 Superintending     2) Clause 5.0 Levels and     3) Clause 13 Setting Out     Employer indemnify the
   Instructions: Clause 5.1(g)       Officer’s Instructions:        Setting Out of The           4) Clause 51                 Contractor
   4) Clause 6.0 Scope of            Clause 3.1: Compliance with    Works: Clause 5.1            Termination of               3) Clause 40.1
   Contract: Clause 6.3              the S.O’s Instruction (SOI)    3) Clause 7.0 Royalties      Contractor’s Employment      Contractor can recover
   5) Clause 7.0 Contract Sum        3) Clause 4.8 Consequences     and Intellectual Property                                 extra cost due to suspend
   6) Clause 10.1 Obligations of     of Delay in Supplying          Rights: Clause 7.1                                        the work progress
   the Contractor: (f), (j)          Further Drawings               4) Clause 25.0                                            4) Clause 50.1
   7) Clause 15.0 Insurance          4) Clause 7.3 Contractor’s     Determination of                                          Engineer may instruct the
   Against Personal Injuries and     Responsibility for Sub-        Contractor’s Employment                                   Contractor with copy to
   Damage to Property: Clause        Contractors                    by Employer: Clause 25.1                                  the Employer to search if
   15.1: Taking Insurance (b),       5) Clause 18.0 Other           (a), (b) & (f)                                            any defects, shrinkage or
   Clause 15.5: Loss or Damage       Contractors: Clause 18.2       5) Clause 37.0                                            other fault in the works
   Occasioned by Insured Risk                                       Performance Bond (PB):                                    appears prior to the end
   (c)                                                              Clause 37.3                                               of DLP.
   8) Clause 19.0 Setting Out :
   Clause 19.3
   9) Clause 22.0 Design: Clause
   22.2: Design Guarantee Bond
   (b)
   10) Clause 31. Final Account
   and Payment Certificate
   Clause 31.3
   11) Clause 32.0 Effect of




                                                                           29
European Journal of Business and Management                                                                                     www.iiste.org
ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online)
Vol 4, No.1, 2012

S.O’s Certificates
12) Clause 38.0 Possession of
Site: Clause 38.4
13) Clause 39.0 Completion of
Works: Clause 39.3 (b)
14) Clause 57.0 Effect of
Force Majeure: Clause 57.1




                                      Table 3. Results of interview with professionals
 No.                                  Interview Questions                                                        Responses
 Q1        Do you have any experiences in handling matters like           90% answered ‘yes’
           construction failure before?                                   10% answered ‘no’
  Q2       Can you please explain about your role in managing the         40% answered ‘supervise construction work’
           construction failure?                                          30% answered ‘checking, inspecting and evaluating the material and
                                                                          method used in project’
                                                                          20% answered ‘managing claim’
                                                                          10% answered ‘in charge in remedial work’
  Q3       From your knowledge, which provisions in contract              100% answered ‘Clause 44’
           document is the most affected in the event of                  40% answered ‘Clause48’
           construction failure?                                          30% answered ’Clause 45’
                                                                          30% answered ‘Clause 50’
                                                                          20% answered ‘Clause 10’
  Q4       Do you think that current provisions in standard form          70% answered ‘no’
           are adequate in managing construction failure?                 30% answered ‘yes’
  Q5       If the relevant provisions are limited, are there any          70% answered ’yes-available laws and contract acts’
           related laws that can be referred to?                          10% answered ‘yes-Engineer code of ethics’
                                                                          20% answered ‘not sure’
  Q6       In your opinion, are there any problems with current           70% answered ‘yes’ and 30% answered ‘no’
           guideline in managing construction failure?
  Q7       Do you think there necessary to improve the current            60% answered ‘yes’, 30% answered ‘no’, and 20% answered ‘not sure’
           provision?
  Q8       As a professional directly / indirectly involved in the        50% answered ‘review by expertise often’ and 30% answered ‘not
           construction, would you like to propose the new scope          necessary’
           of the provisions of the contract, in order to make it         10% answered ‘add provisions of claim
                                                                          procedure’ and 10% answered ‘provision of third party’
           more sufficient?
  Q9       Why did you think this new scope is necessary in               - To protect client’s rights        - Emphasis on quality control of
           managing that event?                                           - To suit with current              project
                                                                          construction                        - To gain respect from party
                                                                          scenario                            involve
                                                                          -- Easy to understand               - To minimize construction
                                                                                                              disputes
 Q10       Lastly, what you can conclude on the overall                   - still lacking in direct           - do not have right provision for
           performance of current contract documents?                     information                         managing failure after contract
                                                                          - provision for re-construct of     period
                                                                          existing                            - still need to be improved
                                                                          building still not available        - provisions should be revised by
                                                                                                              right expertise




                                                                     30
European Journal of Business and Management                                                                          www.iiste.org
ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online)
Vol 4, No.1, 2012

                                Table 4. The frequency of responses in the limitations
                       Limitations                                         Likert Scale                    Total   Relative    Rank
                                                                                                                    Index
                                                                           Frequency                                 (RI)
                                                              1        2        3         4          5

Default parties refused to cooperate during failure event.                 3      22                 5      30       0.81       1
The need of third party to continue the works if failure            1      4      17                 8      30       0.81       2
occurred.
Lack of knowledge about relevant applicable laws and          1     1      3      19                 6      30       0.79       3
provisions.
There is an inconsistency with other standards.                            9      14                 7      30       0.79       4
Unable to use the contract provisions as they lack of               2      8      11                 9      30       0.78       5
guidance and experiences.
Misinterpret the true intent of contract provisions.                3      7      14                 6      30       0.75       6
Discrepancies in contract document (between drawing and             3      9      14                 4      30       0.73       7
specifications in particular) which may lead to the failure.
Default parties make unreasonable claim’s amount as           1     4     10      15                        30       0.66       8
there is no details procedures in issuing a claim.
Although current provisions have been superseded, they              4     17      9                         30       0.63       9
prefer to use old form.
Notes:
1. Scale used: 1=Strongly disagree, 2=Disagree, 3=Neither Disagree nor Agree, 4= Agree,
               5=Strongly Agree




                                  Table5. Mann Whitney U Test for the limitations
                                      Lack of                 Misinterpret the                Unable to use the      Default parties
                                      knowledge about         true intent of                  contract               refused to
                                      relevant                contract                        provisions as they     cooperate
                                      applicable laws         provisions.                     lack of guidance       during failure
                                      and provisions.                                         and experiences.       event.


       Mann-Whitney U                 79.000                  81.500                          64.500                 92.000
       Wilcoxon W                     289.000                 291.500                         274.500                147.000
       Asymp. Sig. (2-tailed)         .282                    .385                            .101                   .650


      Table 6. Frequency of responses from engineer group regarding to the effects during construction
          Cause due limitations                   Likert Scale                      Total Relative                  Rank
           during construction                    Frequency                                Index
                                                1 2 3 4        5                            (RI)

       Decreased in project                          1            13        6        20                  0.84           1
       quality
       Increased in project cost                          5       11        4        20                  0.79           2
       Dispute between parties                            3       16        1        20                  0.78           3
       involved
       Delay in completion                                6       10        4        20                  0.78           4
       schedule
       Decreased in productivity                          5       13        2        20                  0.77           5

       Disrespectful from                                 7       11        2        20                  0.75           6



                                                              31
European Journal of Business and Management                            www.iiste.org
ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online)
Vol 4, No.1, 2012

     parties involve regarding
     to the contractual
     provisions effectiveness.
     Delay in payment              2      8        7   3   20   0.69     7
     Notes:
     1. Scale used: 1=Strongly disagree, 2=Disagree, 3=Neither Disagree nor
     Agree,
      4= Agree, 5=Strongly Agree




                                              32
European Journal of Business and Management                                www.iiste.org
ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online)
Vol 4, No.1, 2012


Table 7. Responses from non engineer group regarding to the effects during construction
      Cause due Limitations        Likert Scale     Total Relative Rank
      during construction           Frequency                  Index
                                  1 2 3 4 5                     (RI)


       Increased in project cost         1     4 5     10       0.86        1
       Decreased in project                  1 5 4     10       0.86        2
       quality
       Disrespectful from                    1 5 4     10       0.86        3
       parties involve regarding
       to the contractual
       provisions effectiveness.
       Delay in completion               1 1 3 5       10       0.84        4
       schedule
       Dispute between parties               1 7 2     10       0.82        5
       involved
       Delay in payment                    2 5 3       10       0.82        6
       Decreased in productivity         2 1 4 3       10       0.76        7

      Table 8. Mann Whitney U Test for both groups regarding to the effects during
                                    construction
                                Delay in      Decreased in Disrespectful
                                payment          project       from parties
                                                 quality          involve
                                                               regarding to
                                                                     the
                                                                contractual
                                                                 provisions
                                                               effectiveness.
         Mann-Whitney U             65.000           93.500             58.000
         Wilcoxon W               275.000           303.500           268.000
         Asymp. Sig. (2-
                                       .103             .741             0.042
         tailed)




                                             33
European Journal of Business and Management                                  www.iiste.org
ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online)
Vol 4, No.1, 2012

Table 9. Responses from engineer group for causes due to the contractual limitations after
                                the project handovers
       Cause due Limitations       Likert Scale      Total Relative Rank
       after project handover       Frequency                   Index
                                 1 2 3 4 5                       (RI)
      Low quality of                 1 3 10 6          20        0.81         1
      completed projects
      Bring bad images to               7 5 8          20        0.81         2
      Client
      Disputes between the              6 11 3         20        0.77         3
      parties involved.
      Client cannot claim the        3 9 5 3           20        0.68         4
      contractor as the
      contract period is
      already expired.
      Client does not have       2 2 6 7 3             20        0.67         5
      rights to request from
      the contractor to make
      good of defects.
      Client has to suffer the   2 2 6 7 3             20        0.67         6
      loss caused by the
      failure alone.



    Table 10. Responses from non engineer group for contract limitations cause after
                                     handovers
       Cause due Limitations      Likert Scale     Total Relative Rank
       after project handover      Frequency                   Index
                                 1 2 3 4 5                      (RI)


       Low quality of                            4 6    10       0.92        1
       completed projects
       Disputes between the                1 5 4        10       0.86        2
       parties involved.
       Bring bad images to                 2 5 3        10       0.82        3
       Client
       Client has to suffer the         4 2 4           10       0.60        4
       loss caused by the
       failure alone.
       Client does not have         1 6 2 1             10       0.46        5
       rights to request from
       the contractor to make
       good of defects.



                                            34
European Journal of Business and Management                  www.iiste.org
ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online)
Vol 4, No.1, 2012

       Client cannot claim the      1 5 4        10   0.46   6
       contractor as the
       contract period is
       already expired.




                                            35
European Journal of Business and Management                                 www.iiste.org
ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online)
Vol 4, No.1, 2012

   Table 11. Mann Whitney U Test for both groups for contract limitations cause after
                                     handovers
                              Client does not Bring bad Client cannot
                               have rights to     images to         claim the
                                request from        Client       contractor as
                               the contractor                     the contract
                                to make good                        period is
                                  of defects.                        already
                                                                     expired.
      Mann-Whitney U                     46.500        97.500             37.500
      Wilcoxon W                        101.500       307.500             92.500
      Asymp. Sig. (2-tailed)               .015          .907               .004




                                            36
European Journal of Business and Management                                    www.iiste.org
 ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online)
 Vol 4, No.1, 2012

                      Table 12. List of suggestions for the new scope
  Suggestion of the new scopes in          Likert Scale        Total    Relative      Rank
       contract provisions                 Frequency                     Index
                                         1 2 3 4 5                        (RI)


The detail and proper procedures of               3   16 11     30       0.85           1
claim issuance to resolve matters
arising.
The relevant provisions of                        4   16 10     30       0.84           2
construction failure should be stated
in separate clause due to its scope of
event.
There should be a specific clauses in             4   16 10     30       0.84           3
the contract related to managing
construction failure.
Each matter in provisions should be               7   15   8    30       0.81           4
reviewed by related expertise to
enhance its effectiveness.
The needs for client and parties to               7   15   8    30       0.81           5
understand the contractual
provisions thoroughly.
The clause related to managing                    7   15   8    30       0.81           6
failure in contract document must
be made to enforce reasonable
period of DLP.
The default party should be liable if       1     5   18   6    30       0.79           7
the failure happened due to its work.
It should completely being charged.
A specific agencies or bodies must          1 10 15        4    30       0.75            8
be existed for the party involved to
set guideline in resolving that
matters.




                                             37
International Journals Call for Paper
The IISTE, a U.S. publisher, is currently hosting the academic journals listed below. The peer review process of the following journals
usually takes LESS THAN 14 business days and IISTE usually publishes a qualified article within 30 days. Authors should
send their full paper to the following email address. More information can be found in the IISTE website : www.iiste.org

Business, Economics, Finance and Management               PAPER SUBMISSION EMAIL
European Journal of Business and Management               EJBM@iiste.org
Research Journal of Finance and Accounting                RJFA@iiste.org
Journal of Economics and Sustainable Development          JESD@iiste.org
Information and Knowledge Management                      IKM@iiste.org
Developing Country Studies                                DCS@iiste.org
Industrial Engineering Letters                            IEL@iiste.org


Physical Sciences, Mathematics and Chemistry              PAPER SUBMISSION EMAIL
Journal of Natural Sciences Research                      JNSR@iiste.org
Chemistry and Materials Research                          CMR@iiste.org
Mathematical Theory and Modeling                          MTM@iiste.org
Advances in Physics Theories and Applications             APTA@iiste.org
Chemical and Process Engineering Research                 CPER@iiste.org


Engineering, Technology and Systems                       PAPER SUBMISSION EMAIL
Computer Engineering and Intelligent Systems              CEIS@iiste.org
Innovative Systems Design and Engineering                 ISDE@iiste.org
Journal of Energy Technologies and Policy                 JETP@iiste.org
Information and Knowledge Management                      IKM@iiste.org
Control Theory and Informatics                            CTI@iiste.org
Journal of Information Engineering and Applications       JIEA@iiste.org
Industrial Engineering Letters                            IEL@iiste.org
Network and Complex Systems                               NCS@iiste.org


Environment, Civil, Materials Sciences                    PAPER SUBMISSION EMAIL
Journal of Environment and Earth Science                  JEES@iiste.org
Civil and Environmental Research                          CER@iiste.org
Journal of Natural Sciences Research                      JNSR@iiste.org
Civil and Environmental Research                          CER@iiste.org


Life Science, Food and Medical Sciences                   PAPER SUBMISSION EMAIL
Journal of Natural Sciences Research                      JNSR@iiste.org
Journal of Biology, Agriculture and Healthcare            JBAH@iiste.org
Food Science and Quality Management                       FSQM@iiste.org
Chemistry and Materials Research                          CMR@iiste.org


Education, and other Social Sciences                      PAPER SUBMISSION EMAIL
Journal of Education and Practice                         JEP@iiste.org
Journal of Law, Policy and Globalization                  JLPG@iiste.org                       Global knowledge sharing:
New Media and Mass Communication                          NMMC@iiste.org                       EBSCO, Index Copernicus, Ulrich's
Journal of Energy Technologies and Policy                 JETP@iiste.org                       Periodicals Directory, JournalTOCS, PKP
Historical Research Letter                                HRL@iiste.org                        Open Archives Harvester, Bielefeld
                                                                                               Academic Search Engine, Elektronische
Public Policy and Administration Research                 PPAR@iiste.org                       Zeitschriftenbibliothek EZB, Open J-Gate,
International Affairs and Global Strategy                 IAGS@iiste.org                       OCLC WorldCat, Universe Digtial Library ,
Research on Humanities and Social Sciences                RHSS@iiste.org                       NewJour, Google Scholar.

Developing Country Studies                                DCS@iiste.org                        IISTE is member of CrossRef. All journals
Arts and Design Studies                                   ADS@iiste.org                        have high IC Impact Factor Values (ICV).

Contenu connexe

Tendances

Ditching Defect Drama: Keeping Construction Claims Objective
Ditching Defect Drama: Keeping Construction Claims ObjectiveDitching Defect Drama: Keeping Construction Claims Objective
Ditching Defect Drama: Keeping Construction Claims ObjectiveKipcon Inc.
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overruneSAT Publishing House
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"Abhishek Shah
 
Causes and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitCauses and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitIJERA Editor
 
IRJET- Dispute Resolution Mechanism in Construction Project
IRJET-  	  Dispute Resolution Mechanism in Construction ProjectIRJET-  	  Dispute Resolution Mechanism in Construction Project
IRJET- Dispute Resolution Mechanism in Construction ProjectIRJET Journal
 
Causes of Variation Orders 1268
Causes of Variation Orders 1268Causes of Variation Orders 1268
Causes of Variation Orders 1268HASHIM HANIF
 
Management of government funded construction projects in ghana
Management of government funded construction projects in ghanaManagement of government funded construction projects in ghana
Management of government funded construction projects in ghanaAlexander Decker
 
IRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET Journal
 
Risk Mitigation In Construction Contracts
Risk Mitigation In Construction ContractsRisk Mitigation In Construction Contracts
Risk Mitigation In Construction ContractsIRJET Journal
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSIAEME Publication
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Managementijsrd.com
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsTwana Ahmad
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentationelliotfus
 

Tendances (20)

Ditching Defect Drama: Keeping Construction Claims Objective
Ditching Defect Drama: Keeping Construction Claims ObjectiveDitching Defect Drama: Keeping Construction Claims Objective
Ditching Defect Drama: Keeping Construction Claims Objective
 
Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
Causes and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitCauses and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in Kuwait
 
IRJET- Dispute Resolution Mechanism in Construction Project
IRJET-  	  Dispute Resolution Mechanism in Construction ProjectIRJET-  	  Dispute Resolution Mechanism in Construction Project
IRJET- Dispute Resolution Mechanism in Construction Project
 
Causes of Variation Orders 1268
Causes of Variation Orders 1268Causes of Variation Orders 1268
Causes of Variation Orders 1268
 
Risk management
Risk managementRisk management
Risk management
 
Chapter 1- Procurement management
Chapter 1- Procurement managementChapter 1- Procurement management
Chapter 1- Procurement management
 
Management of government funded construction projects in ghana
Management of government funded construction projects in ghanaManagement of government funded construction projects in ghana
Management of government funded construction projects in ghana
 
IRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction Projects
 
Risk Mitigation In Construction Contracts
Risk Mitigation In Construction ContractsRisk Mitigation In Construction Contracts
Risk Mitigation In Construction Contracts
 
Dispute_paper[1]
Dispute_paper[1]Dispute_paper[1]
Dispute_paper[1]
 
Lawyer-Monthly_Metehan-Sonbahar
Lawyer-Monthly_Metehan-SonbaharLawyer-Monthly_Metehan-Sonbahar
Lawyer-Monthly_Metehan-Sonbahar
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
33 article text-127-1-10-20181005
33 article text-127-1-10-2018100533 article text-127-1-10-20181005
33 article text-127-1-10-20181005
 
Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 

Similaire à Evaluating Contractual Provisions for Construction Failure Management

Implementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projectsImplementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projectsIAEME Publication
 
An Empirical Investigation into the Origins and Causes of Variation Orders in...
An Empirical Investigation into the Origins and Causes of Variation Orders in...An Empirical Investigation into the Origins and Causes of Variation Orders in...
An Empirical Investigation into the Origins and Causes of Variation Orders in...IRJET Journal
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...IRJET Journal
 
Evaluating the success factors of partnering in the building construction ind...
Evaluating the success factors of partnering in the building construction ind...Evaluating the success factors of partnering in the building construction ind...
Evaluating the success factors of partnering in the building construction ind...Alexander Decker
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delayEst
 
PAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxPAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxsaeedahmed433704
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of timeJoseph Sangpang
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...IRJET Journal
 
Claims Management And Assessment Through Documentation
Claims Management And Assessment Through DocumentationClaims Management And Assessment Through Documentation
Claims Management And Assessment Through Documentationvivatechijri
 
To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...Harish Rajmane
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...IJMREMJournal
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...IJMREMJournal
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...World-Academic Journal
 
design bid build or Traditional contract shortcomings and alternative method,...
design bid build or Traditional contract shortcomings and alternative method,...design bid build or Traditional contract shortcomings and alternative method,...
design bid build or Traditional contract shortcomings and alternative method,...Tehmas Saeed
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractTom Joseph Mukasa
 
IRJET- Interface Management and its Effect on Project Complexity in Constr...
IRJET- 	  Interface Management and its Effect on Project Complexity in Constr...IRJET- 	  Interface Management and its Effect on Project Complexity in Constr...
IRJET- Interface Management and its Effect on Project Complexity in Constr...IRJET Journal
 
BIM based organizational learning
BIM based organizational learningBIM based organizational learning
BIM based organizational learningIJRES Journal
 

Similaire à Evaluating Contractual Provisions for Construction Failure Management (20)

Implementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projectsImplementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projects
 
Y4408131137
Y4408131137Y4408131137
Y4408131137
 
L012238891
L012238891L012238891
L012238891
 
An Empirical Investigation into the Origins and Causes of Variation Orders in...
An Empirical Investigation into the Origins and Causes of Variation Orders in...An Empirical Investigation into the Origins and Causes of Variation Orders in...
An Empirical Investigation into the Origins and Causes of Variation Orders in...
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
 
Evaluating the success factors of partnering in the building construction ind...
Evaluating the success factors of partnering in the building construction ind...Evaluating the success factors of partnering in the building construction ind...
Evaluating the success factors of partnering in the building construction ind...
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delay
 
PAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxPAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptx
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
 
Claims Management And Assessment Through Documentation
Claims Management And Assessment Through DocumentationClaims Management And Assessment Through Documentation
Claims Management And Assessment Through Documentation
 
To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
 
E253446
E253446E253446
E253446
 
design bid build or Traditional contract shortcomings and alternative method,...
design bid build or Traditional contract shortcomings and alternative method,...design bid build or Traditional contract shortcomings and alternative method,...
design bid build or Traditional contract shortcomings and alternative method,...
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction Contract
 
IRJET- Interface Management and its Effect on Project Complexity in Constr...
IRJET- 	  Interface Management and its Effect on Project Complexity in Constr...IRJET- 	  Interface Management and its Effect on Project Complexity in Constr...
IRJET- Interface Management and its Effect on Project Complexity in Constr...
 
BIM based organizational learning
BIM based organizational learningBIM based organizational learning
BIM based organizational learning
 

Plus de Alexander Decker

Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Alexander Decker
 
A validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale inA validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale inAlexander Decker
 
A usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesA usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesAlexander Decker
 
A universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksA universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksAlexander Decker
 
A unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dA unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dAlexander Decker
 
A trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceA trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceAlexander Decker
 
A transformational generative approach towards understanding al-istifham
A transformational  generative approach towards understanding al-istifhamA transformational  generative approach towards understanding al-istifham
A transformational generative approach towards understanding al-istifhamAlexander Decker
 
A time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaA time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaAlexander Decker
 
A therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenA therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenAlexander Decker
 
A theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksA theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksAlexander Decker
 
A systematic evaluation of link budget for
A systematic evaluation of link budget forA systematic evaluation of link budget for
A systematic evaluation of link budget forAlexander Decker
 
A synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabA synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabAlexander Decker
 
A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...Alexander Decker
 
A survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalA survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalAlexander Decker
 
A survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesA survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesAlexander Decker
 
A survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbA survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbAlexander Decker
 
A survey on challenges to the media cloud
A survey on challenges to the media cloudA survey on challenges to the media cloud
A survey on challenges to the media cloudAlexander Decker
 
A survey of provenance leveraged
A survey of provenance leveragedA survey of provenance leveraged
A survey of provenance leveragedAlexander Decker
 
A survey of private equity investments in kenya
A survey of private equity investments in kenyaA survey of private equity investments in kenya
A survey of private equity investments in kenyaAlexander Decker
 
A study to measures the financial health of
A study to measures the financial health ofA study to measures the financial health of
A study to measures the financial health ofAlexander Decker
 

Plus de Alexander Decker (20)

Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...
 
A validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale inA validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale in
 
A usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesA usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websites
 
A universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksA universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banks
 
A unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dA unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized d
 
A trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceA trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistance
 
A transformational generative approach towards understanding al-istifham
A transformational  generative approach towards understanding al-istifhamA transformational  generative approach towards understanding al-istifham
A transformational generative approach towards understanding al-istifham
 
A time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaA time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibia
 
A therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenA therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school children
 
A theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksA theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banks
 
A systematic evaluation of link budget for
A systematic evaluation of link budget forA systematic evaluation of link budget for
A systematic evaluation of link budget for
 
A synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabA synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjab
 
A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...
 
A survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalA survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incremental
 
A survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesA survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniques
 
A survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbA survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo db
 
A survey on challenges to the media cloud
A survey on challenges to the media cloudA survey on challenges to the media cloud
A survey on challenges to the media cloud
 
A survey of provenance leveraged
A survey of provenance leveragedA survey of provenance leveraged
A survey of provenance leveraged
 
A survey of private equity investments in kenya
A survey of private equity investments in kenyaA survey of private equity investments in kenya
A survey of private equity investments in kenya
 
A study to measures the financial health of
A study to measures the financial health ofA study to measures the financial health of
A study to measures the financial health of
 

Dernier

Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditNhtLNguyn9
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 

Dernier (20)

Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal audit
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 

Evaluating Contractual Provisions for Construction Failure Management

  • 1. European Journal of Business and Management www.iiste.org ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online) Vol 4, No.1, 2012 The Adequacy of Contractual Provisions in Managing Construction Failure in Malaysia Mohamad Ibrahim Mohamad1 Mohammad Ali Nekooie1* Naadira Binti Che Kamaruddin1 1. Department of Structures and Material, Faculty of Civil Engineering (FKA), Universiti Teknologi Malaysia (UTM), Skudai, Johor, 81310, Malaysia. * E-mail of the corresponding author: anmohammad2@live.utm.my Abstract Arising of any failure in construction is a vital issue. It could be a source of dispute among different parties involved in construction. Therefore, the contract is the main reference to overcome issues regarding to failure claims. When construction failure occurred after the contractual period, the contract provisions are not applicable. Moreover, the contractual relationships couldn’t be referred anymore. Thus, all parties seek to the justice to define their role and duty on failure loss and remedial cost based on the contract. The level of inadequacy of failure management consideration in the current contract documents was measured. Moreover, the limitations in current contractual provisions were evaluated to suggest the new scope for contractual provisions in managing construction failure. The evaluations were performed by interview with a panel of experts in the construction industry and legal sector. Furthermore, all current contracts provisions were investigated. Therefore, any related issues to the failure events were illustrated precisely. Then, the questionnaire survey identified the limitations and indicated opportunities to extend the scope of current provisions. Related Index was used to rank the factors and issues based on their importance. Refusing to cooperate during the failure event from default parties is the main limitation. Moreover, low quality of completed projects; bringing a bad image to client, and disputes between the involved parties are the main causes due to limitations based on engineers’ and the legal sector’s ideas. The new scope of contractual provisions was approved by more than %70 of the respondents. Keywords: Building failure; Contract conditions; Contract documentation; Contract law. 1. Introduction The incidents of structural failures have generated a lot of tension to the public recently. Despite some of the cases have been publicity reported by the mass media, but most of the cases are not reported at all and only known to the stakeholders of the effected structures (Allen, 2010). Structural failure can be contributed by many factors. It can be due to poor design, poor detailing, poor quality control and construction error or due to inferior material quality used in construction or even manmade mistakes because of poor health and long working time of the labours. Some of these issues cause fatigue and stress, and an accident is one possible outcome (Carper, 1986, Bracken and Roda, 2007, Sang et al., 2007, Frühwald and Thelandersson, 2008, Chan, 2011). Arising of any failure in construction is a vital issue. Since, construction firms have not put sufficient emphasis on strategic planning; it could be a source of dispute among different parties involved in construction (Soetanto and Dainty, 2009). Therefore, the contract is the main reference to overcome any issues regarding to failure claims (Janney, 1986). However, any uncertainty and equivocalness of clients should be managed to prevent any further disputes (Levander et al., 2011). Janney (1986) defines the construction failure as a failure that occurs during the construction project and after the project completed. They are considered to be either collapse, or distress of a structural system to such a degree that it cannot safely serve its intended purpose. Hence, these study focusing on the failure after the construction period; most of the failures in a construction project mainly in building construction generate controversy, long and expensive argument (Jacob Feld, 1997). This will follow by a 22
  • 2. European Journal of Business and Management www.iiste.org ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online) Vol 4, No.1, 2012 litigation process to resolve those issues. Therefore, failure in a construction project has close relations to the ability of building structure to receive such massive loads and also depends on the quality of the material applied. Structural failure affects both the appearance and structural stability of the building. Most of the building consists of combination of three basic elements such as walls, roofs and floors. These elements are arranged to create both space division and unobstructed space (Ambrose, 1993) according to building’s functions. Commonly, the causes of structural collapse include poor workmanship, lack of supervision just to name a few, which lead to serviceability problems such as distress, excessive deformation, leaking roofs and facades, and also inadequate interior environmental control system (Kaminetzky, 1976, Yates and Lockley, 2002, Messervey, 2007, Jacob Feld, 1997, Carper, 1986). On the other hand, former studies try to estimate exact probabilities of occurrence of fault events (Pan, 2006). However, more precise categorization for classifying the structural failure could be defined as element errors, errors in site selection and development, planning and scheduling deficiencies, errors in design, errors during construction, deficiencies of material and errors in service operation. From previous research, there were surveys, which indicated several numbers of methods that appropriate to minimize construction failure (Yates and Lockley, 2002, Hall and Tomkins, 2001). It is commonly known that construction failure cannot be eliminated as it only can be reduced or minimized by improving the current construction environment. The lists of methods in reducing the failure in construction gained from that survey which received most responds from their respondents as stated below: 1. Design and detailing of critical connections by the engineer of record. 2. Design and supervision of construction of temporary structures by a professional engineer. 3. Clear definition of responsibility among the engineer, contractor and employer or client. 4. Constructability reviews during design stage. 5. Full time inspection of construction by structural engineers. 6. Peer review of the structural design and details by an independent professional. In order to overcome the failure event, several contract documents are established by the statutory body and professional societies. There are a number of provisions that govern the quality of construction works, and some of the research shows the need of prequalification to ensure the quality of contactors’ work (Hatush and Skitmore, 1997, Russell et al., 1992). They also specify the role and responsibilities of parties in the contracts in respect of defects. Moreover, the party’s rights and obligations to a contract are governed by the contract itself. Previous study also stated that most construction contracts specify certain extraordinary powers to a particular person. This person’s decisions are final and binding upon both parties (Iyer and Satyanarayana, 2002). However, the effects of provisions are only limited during the contractual period. Although there are governing laws to manage construction failure, the process is lengthy and costly. The investigation of documents only focused on the available form of contract that is commonly used in Malaysia. These forms of contracts are:  PWD Form 203/203A (Rev.2007);  PAM Contract 2006 (With Quantities);  I.E.M Conditions of Contract for Works Mainly of Civil Engineering Construction;  CIDB Standard Form of Contract for Building Works 2000 Edition and  Occasional reference shall be made to the FIDIC Form as a matter of interest. FIDIC contract which is better described by its title ‘Conditions of Contract (International) for Works of Civil Engineering Constructions’. The contract documents are necessary as aid tools in a construction process (Laryea, 2011). Thus in the occurrence of construction failure it helps to each party know their rights and obligations during construction activities. The significant reasons are the client, and the professional advisors will know exactly what they want the respected party that doing the construction to perform well in terms of design, 23
  • 3. European Journal of Business and Management www.iiste.org ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online) Vol 4, No.1, 2012 quantity, quality and specification. Since legal knowledge is important in dealing with contract terms, construction practitioners must have at least basic knowledge to ensure the effectiveness of particular provisions. Therefore, rights and obligations of the parties to a contract are governed by the contract itself (Neo, 2005, Kremers et al., 2010). These rights and obligations will be expressly informed in the contract and are known as the express terms of the contract. In addition, there are instances where the terms of contract may be implied to relate the failure in construction with the provision in contract documents. Better understanding and clear interpretation are needed to avoid any disputes regarding to contract terms (Ashworth, 2001). The adequacy of contractual provisions in managing construction failure is aimed to be evaluated. Moreover, the new scope of contractual provision for managing structural failure should be provided. Thus, the objectives consist of identifying the state of art of the existing provisions in managing construction failure and identifying the limitation of the current provisions in managing construction failure. It tries to suggest new scopes of provision that should be included in contract document in Malaysia. 2. Method of study In the first step, it is focusing only on provisions in contract document such as PWD 203/203A, IEM1989, CIDB 2000, PAM2006 and FIDIC conditions (red book) which related to construction failure. The comparative table has been extracted and developed based on the clauses in aforementioned contract documents. The comparative table projects the factors which are covered in the scope of different provisions in Malaysian and international contract documents. In general, there are a lot of case laws in construction industries consist of various cases mainly caused by disputes and breach of contracts due to the failure event. Ten case studies from Malaysian construction industry extracted from official document of Malaysian central curt. All the case studies have been investigated, and several limitations due to insurance provision and others are identified and categorized precisely. The structured interview has been carried out. This interview consists of ten questions in parallel to the study objectives, which focuses on the contract limitations and new scope of contract provisions. The aim of this interview is to identify the relevant clauses and limitations of contract provisions. The interview session for this study was conducted with ten professionals who are tolerantly dedicated in their respective field. They have wide knowledge and experience in managing construction failure of more than three years. Their profession backgrounds consist of Civil Engineers, Lawyers and Quantity Surveyors. Out of ten interviewees, five of them are Civil Engineers from local authority and consultant firms. Three interviewees represent Quantity Surveyors from the developers, and other two are the law practitioners. The study is continued by the questionnaire survey developed based on the information gathered in previous interview session. The design of the questionnaire is purposely to achieve the second and third objectives, which are oriented to identify any limitations and the potential of new scope to be considered in the contract provisions. Respondents were required to rate the information provided in terms of several choices. The questionnaire was established in three steps. In the first step, respondents presented their personal information including the field of their profession. In the next step, the respondents identify any constraints in the contract document based on the information collected in literature search and interview. Respondents are required to respond on all information by stating their level of agreement based on five ordinal measures known as Likert Scale from one (1) to five (5) according to specified level. The last section in this questionnaire requires respondents to state their level of agreement on which the new scope is suitable to be considered in current contract documents. There were eight potential new scopes identified from the literature search and interview. According to the scale, questionnaire rating is following the five-point scale described previously and converted into relative important indices for each factor. These indices are adopting the Relative Index (RI) ranking technique based on equation 1 (Kometa et al., 1994). 24
  • 4. European Journal of Business and Management www.iiste.org ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online) Vol 4, No.1, 2012 n(1) ×1 + n(2) × 2 + n(3) × 3 + n(4) × 4 + n(5) × 5 RI = (1) Ntotal × 5 Where n(i) is the number of responses with scale, i (i=1,..., 5) and N is the total number of responses to each question. The maximum value for RI is 1, and the minimum is 0.2 accordingly. Moreover, Mann- Whitney U Test as a non parametric analysis has been employed to illustrate any significant differences between two independent samples regarding to different professions as engineers and non-engineers. Totally, 30 questionnaires have been collected from respondents. The frequency distribution is 66.7 percent for engineers versus 33.3 percent for non-engineers. 3. Result and discussions 3.1 Literatures and Interview According to the comparative research on different contract document, the provisions could be categorized in two categories. First are the related provisions, which are mentioned about managing structural failure straight forward. These provisions are defined in table 1 among all 5 aforementioned contractual documents. ‘Table 1 here’ The second category is regarding to the provisions, which are related to managing structural failures by their effects. These provisions try to contribute solutions regarding to minor effect of structural failures. Table 2 defines these provisions in different contractual documents. ‘Table 2 here’ Based on the results of the interview, 90% of the respondents had been engaged with structural failure previously and among all the respondent 70% of them agree with the lack of the adequacy of provisions in managing structural failure. All the experts appointed clause 44 as the most affected provision in the event of construction failure. Since the 70% of experts have faced with problems in the current guideline in managing structural failure, the need of improvement of the guideline is perceived. However, 60% of interviewees agree with this issue. Furthermore, most of the experts agree for adding the new scope regarding to managing construction failure. The reasons for adding the new scope consist of protecting the client’s right, improving quality, to suit current construction scenario and minimizing construction dispute with scope, which is easy to understand based on experts’ idea. Table 3 tries to identify and summarise the panel of experts’ idea on each of the questions. ‘Table 3 here’ 3.2 The Limitations of Current Provisions in Managing Construction Failure Based on the questionnaire survey nine factors are introduced that lead to limitation in the contract provisions. Four factors record the highest RI among the others. The first rank is the default parties refused to cooperate in managing construction failure after the contractual period is over. Although the RI value (0.81) for first rank is similar with second rank, the frequency on agreed and strongly agreed in the first factor is higher. Second rank is the need of third party to continue the work if failure happened. Followed by the 3rd rank (RI=79) which is the lack of knowledge from parties involved about relevant applicable laws and provisions. Factor with rank 4 also shares a similar RI value (0.79) with 3rd factor, which is the inconsistency with other standards. The reason is current governing laws, and contract provisions to use redundant legal expressions. Table 4 summarizes the results of the questionnaire for limitations of current provisions. ‘Table 4 here’ Since the respondents are categorized in two groups, which are engineers and non-engineers such as lawyer and Quantity Surveyors (QS), table five shows, there is not any significant difference between the ideas on probable causes that lead to limitation in contract documents of these two groups based on Mann-Whitney 25
  • 5. European Journal of Business and Management www.iiste.org ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online) Vol 4, No.1, 2012 test. The results show, there is not any significant different between different groups’ ideas as P values > 0.05 for all factors. Both groups seem to share a similar idea upon these causes. ‘Table 5 here’ 3.3 Effects due to the Limitation of Contractual Provisions The effects during the construction and after the handovers of the project are being considered to evaluate the impact of limitations in contractual provisions. Table 6 shows seven effects of limitations stated in questionnaire and 20 respondents of the engineer group are responding thoroughly. Decreased in project quality is being identified as the most preferable cause due to the limitations of contractual provisions. It records the highest RI value (0.84) compare to other causes. Followed by increased in project costs (RI=0.79). “Disputes between parties involved” and “delay in completion schedule” (RI=0.78) also mostly preferable by the engineers. ‘Table 6 here’ Table 7 shows the responses from non engineering group. They give aggressive responds towards the limitation effects during construction. Their Relative Index value is the highest (RI=0.86) for “increasing in project cost”, “decreased in project quality” and also “disrespectful aroused from parties involve”. This can be assumed that non engineer emphasis more on the effects of contractual provisions itself compared to engineer group. ‘Table 7 here’ After indicating the limitations, the effects during construction also are identified to show the impact from the limitation of contractual provisions. Table 8 shows that these two groups have similar ideas on “the delay in payment and decreased of project quality”. However, they don’t share the similar idea for “disrespectful from parties involved” as a limitation since the P value is 0.042 < 0.05. ‘Table 8 here’ Table 9 shows the causes due to the contractual limitations after the project handovers. According to highest RI value (0.81), “low quality of completed project” is the most important factor in engineers’ side of view. This also would “bring bad images to the client or employer who owns that project” which get the 3rd rank (RI=0.77) between respondents’ answer. ‘Table 9 here’ Table 10 shows that majority of non engineer group agreed that contract limitations cause “low quality of a completed project” (RI=0.92). Then, “disputes would be occurred between parties involved” get second rank with RI=0.86. Finally, the 3rd rank achieved by “bring bad images to clients as their credibility”. ‘Table 10 here’ It is also an emphasis on the issues taking place after the handover of construction projects to the client, for instance “the certified completed building”. There are significant differences between the ideas of an engineer and non engineer group. This can be seen in table 11, where the P value is 0.015 on “clients do not have rights to request any action from the contractor after the project handover” and 0.004 on “the client cannot claim as the contract period is already expired”. Hence, this responds is being assumed with a higher impression from the engineer group as they practice the construction activities compared to non engineer who mostly relied on the theory and assumptions from previous cases. ‘Table 11 here’ 3.4 Suggestion of New Scope of Provisions to be Included in Contract Documents This suggestion is combining all these two groups’ ideas. They state their level of agreement due to the suggestion provided in the questionnaires. The result shows 53.33% of the total respondents agree on the suggestion of new scopes. Other 30% are strongly agreed due this suggestion. Only 16.67% of the total respondents are neither disagree nor agree with the suggestions. Hence, table 12 below shows the frequency of each suggestion. First rank indicates that most respondents agreed to this factor “there should be detail and proper procedures of claim issuance 26
  • 6. European Journal of Business and Management www.iiste.org ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online) Vol 4, No.1, 2012 to resolve matters arising” (RI=0.85). It is followed by the suggestion on separated clause of construction failure due to its scope of an event (RI=0.84). Same RI value recorded on specific clauses related to managing the failure events. ‘Table 12 here’ 4. Conclusions Majority of the respondents shared similar ideas about the lack of adequacy for contractual provisions. Either engineers or non engineers are giving strong agreement based on the results except for certain factors. Decreasing the project quality and increasing the project cost are two main effects due to limitations in the contractual provisions during the construction period. From the survey, certain questions are agreed mostly by non engineer group based on their professional point of view; in contrast to the practitioners in construction industry who are directly involved in managing construction failure. Thus, the survey also shows that most of the respondents agree, there are limitations when using the contract documents. Both engineer and non engineer group giving a positive responds to the suggestion of modifying the new scope in contractual provisions. This scope should follow certain principals as: - Clear procedure; - Simplicity; - Clear classification; - Ensure effectiveness; - Extending duration of applicability; - Developing the guideline. There is a gap between theory from non engineering group and practice from the engineering group. However, neither of them sufficiently explains underlying reasons to this gap. Further research is recommended due to these issues as might help in finding that reasons. Acknowledgements References ALLEN, D. E. 2010. Structural failures due to human error : what research to do? Risk, Structural Engineering and Human Error : Proceedings of the 2nd University Symposium on Structural Technology and Risk. Waterloo, Ont. Canada. AMBROSE, J. 1993. Building Structures, Canada, John Wiley & Sons. ASHWORTH, A. 2001. Contractual Procedures in the Construction Industry, England, Pearson Education Limited. BRACKEN, W. C. & RODA, T. A. 2007. Establishing Protocols for Catastrophe Damage Assessments of Multiple Buildings, ASCE. CARPER, K. L. 1986. Forensic Engineering: Learning from Failures, New York, NY, ASCE. CHAN, M. 2011. Fatigue: the most critical accident risk in oil and gas construction. Construction Management and Economics, 29, 341-353. FRÜHWALD, E. & THELANDERSSON, S. 2008. Design of safe timber structures - How can we learn from structural failures in concrete, steel and timber? 10th World Conference on Timber Engineering. Miyazaki, Japan. HALL, M. & TOMKINS, C. 2001. A cost of quality analysis of a building project: towards a complete methodology for design and build. Construction Management and Economics, 19, 727-740. 27
  • 7. European Journal of Business and Management www.iiste.org ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online) Vol 4, No.1, 2012 HATUSH, Z. & SKITMORE, M. 1997. Assessment and evaluation of contractor data against client goals using PERT approach. Construction Management and Economics, 15, 327-340. IYER, K. C. & SATYANARAYANA, K. N. 2002. Final and Binding Power Clauses in Indian Construction Contract. International Journal of Project Management, 20, 13-22. JACOB FELD, K. L. C. 1997. Construction failure, Canada, John Wiley and Sons. JANNEY, J. R. 1986. Guide to investigation of structural failures, with editorial revisions incorporated, Unite State, ASCE Publications. KAMINETZKY, D. 1976. Structural Failures and How to Prevent Them. Civil Engineering—ASCE, 46, 60-63. KOMETA, S. T., OLOMOLAIYE, P. O. & HARRIS, F. C. 1994. Attributes of UK construction clients influencing project consultants' performance. Construction Management and Economics [CONSTR. MANAGE. ECON.], 12, 433-443. KREMERS, J., RIETJENS, B., VOORDIJK, H. & DE BOER, S. J. 2010. Construction contracting and civil–military interaction. Construction Management and Economics, 28, 871-883. LARYEA, S. 2011. Quality of tender documents: case studies from the UK. Construction Management and Economics, 29, 275-286. LEVANDER, E., ENGSTRÖM, S., SARDÉN, Y. & STEHN, L. 2011. Construction clients’ ability to manage uncertainty and equivocality. Construction Management and Economics, 29, 753-764. MESSERVEY, T. B. 2007. Integration of Structural Health Monitoring into the Design, Assessment, and Management of Civil Infrastructure. Ph.D, University of Pavia. NEO, M. 2005. Construction Defects: Your Rights and Remedies, Singapore, Sweet & Maxwell Asia. PAN, N. F. 2006. Evaluation of building performance using fuzzy FTA. Construction Management and Economics, 24, 1241-1252. RUSSELL, J. S., HANCHER, D. E. & SKIBNIEWSKI, M. J. 1992. Contractor prequalification data for construction owners. Construction Management and Economics, 10, 117-135. Soetanto, R., & Dainty, A. R. J. 2009. Integrating uncertainty management in strategic planning practice. In (pp. 309-319). Seattle, WA. Sang, K. J. C., Dainty, A. R. J., & Ison, S. G. 2007. Gender: A risk factor for occupational stress in the architectural profession? Construction Management and Economics, 25, 1305-1317. YATES, J. K. & LOCKLEY, E. E. 2002. Documenting and Analyzing Construction Failures, ASCE. 28
  • 8. European Journal of Business and Management www.iiste.org ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online) Vol 4, No.1, 2012 Table 1. Related Provisions to failure management in different contact documents PWD 203/203A PAM Contract IEM FIDIC CIDB 2000 (Rev.2007) 2006 1989 (International) 1) Clause 13 1) Clause 3.5 Urgent 1) Clause 15.0 Practical 1) Clause 3 Scope of 1) Clause 20.1 Performance Bond(PB)/Performance Repairs Completion and defects the Contract Contractor Guarantee Sum(PGS): Clause 13.1(a), 2) Clause 7 General Liability: Clause 15.1, 2) Clause 32 responsibility until Clause 13.3, Clause 13.5 Obligations of The Clause 15.3, Clause 15.4, Indemnities to Taking Over 2) Clause 14.0 Contractor: Clause 7.1: Clause 15.5, Clause 15.6 Employer in Respect of Certificate Indemnity in Respect of Personal Injuries Contractor’s General 2) Clause 18.0 Injury to Personal Injuries and 2) Clause 20.2 and Damage to Property: Clause 14.1 Responsibilities. Person or Loss and/or Damage to Property Contractor 3) Clause 18.0 3) Clause 12 Setting Out: Damage of Property and 3) Clause 33 Insurance responsibility for loss Insurance of Works: Clause 18.1: Taking Clause 12.2: Errors in Indemnity to Employer: Against Personal and damage to the of Insurance, Clause 18.3: Payment of Setting out Clause 18.2 Injuries and Damage to satisfaction of the Insurance in the Event of any 4) Clause 15.7 Defects 3) Clause 19.0 Insurance Property Engineer with his own Loss/damage during Progress of the Against Injury to Person 4) Clause 34 Insurance cost 4) Clause 40.0 Works and Loss and/or Damage of Works 3) Clause 40(1) Damages for Non-Completion: Clause 5) Clause 20.3 Access for to Property: Clause 19.1 5) Clause 37 Suspension of Work: 40.1, Clause 40.2 Remedial work 4) Clause 20.A Insurance Performance Bond: (a) (b) & (d) 5) Clause 43.0 of New Buildings/ Works & (d) 4) Clause 21.1 Delay and Extension of Time: Clause 6,7) Clause 24(1), – By the Contractor: 6) Clause 40 Damages Contractor 43.1 24(3)(b) Extension of Clause 20.A.1 for Non-Completion responsibilities for 6) Clause 45.0 Time 5) Clause 20.B Insurance insurance Investigation by the Government and of New Buildings/Works 7) Clause 43 5) Clause 44.1 EOT Other Persons in Case of Accident, 8) Clause 26 Non- – By the Employer: Delay and Extension of 6) Clause 49(1) Failure or Other Event. Completion and Damages Clause 20.B.1 Time (EOT): (d) Defects Liability 7) Clause 48.0 For Delay in Completion: 6) Clause 22.0 Damages 8) Clause 45 Defects Period: (a) & (b) Defects After Completion: Clause 48.1: Clause 26.2:Damages for for Non-Completion: After Completion: (a) Completion of outstanding Work and non Completion, Clause Clause 22.1, Clause 22.2 & (e) Remedying Defects. Clause 48.2: Default 26.3:Employer’s rights 7) Clause 23.0 Extension in Remedying Defects.Clause 48.3: for Damages at Law of Time (EOT): Clause Diminution of Works. Clause 48.4: 9) Clause 27 Defects 23.1 Certificate of Completion of Making Liability After Good Defects Completion 8) Clause 50.0 10) Clause 27.5 Suspension of Works: Clause 50.1: Contractor To Search Suspension and Resumption of Works. Clause 50.2: Extension of Time (EOT) Table 2. Semi-related provisions in different contract documents PWD 203/203A PAM Contract IEM FIDIC CIDB 2000 (Rev.2007) 2006 1989 (International) 1) Clause 3.1 Duties of S.O 1) Clause 1 Definitions and 1) Clause 1.0 Contractor’s 1) Clause 4 Work to be to 1) Clause 22.1 and S.O’s Representative Interpretation: Clause 1.1: Obligations: Clause 1.2: Satisfaction of Engineer Damage to Persons and 2) Clause 4.0 S.O’s Rights to Definitions Temporary Work and 2) Clause 5 Engineer’s Property Take Action The All Risk Insurance Construction Method Instruction (EI) 2) Clause 22.3 3) Clause 5.0 S.O’s 2) Clause 3 Superintending 2) Clause 5.0 Levels and 3) Clause 13 Setting Out Employer indemnify the Instructions: Clause 5.1(g) Officer’s Instructions: Setting Out of The 4) Clause 51 Contractor 4) Clause 6.0 Scope of Clause 3.1: Compliance with Works: Clause 5.1 Termination of 3) Clause 40.1 Contract: Clause 6.3 the S.O’s Instruction (SOI) 3) Clause 7.0 Royalties Contractor’s Employment Contractor can recover 5) Clause 7.0 Contract Sum 3) Clause 4.8 Consequences and Intellectual Property extra cost due to suspend 6) Clause 10.1 Obligations of of Delay in Supplying Rights: Clause 7.1 the work progress the Contractor: (f), (j) Further Drawings 4) Clause 25.0 4) Clause 50.1 7) Clause 15.0 Insurance 4) Clause 7.3 Contractor’s Determination of Engineer may instruct the Against Personal Injuries and Responsibility for Sub- Contractor’s Employment Contractor with copy to Damage to Property: Clause Contractors by Employer: Clause 25.1 the Employer to search if 15.1: Taking Insurance (b), 5) Clause 18.0 Other (a), (b) & (f) any defects, shrinkage or Clause 15.5: Loss or Damage Contractors: Clause 18.2 5) Clause 37.0 other fault in the works Occasioned by Insured Risk Performance Bond (PB): appears prior to the end (c) Clause 37.3 of DLP. 8) Clause 19.0 Setting Out : Clause 19.3 9) Clause 22.0 Design: Clause 22.2: Design Guarantee Bond (b) 10) Clause 31. Final Account and Payment Certificate Clause 31.3 11) Clause 32.0 Effect of 29
  • 9. European Journal of Business and Management www.iiste.org ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online) Vol 4, No.1, 2012 S.O’s Certificates 12) Clause 38.0 Possession of Site: Clause 38.4 13) Clause 39.0 Completion of Works: Clause 39.3 (b) 14) Clause 57.0 Effect of Force Majeure: Clause 57.1 Table 3. Results of interview with professionals No. Interview Questions Responses Q1 Do you have any experiences in handling matters like 90% answered ‘yes’ construction failure before? 10% answered ‘no’ Q2 Can you please explain about your role in managing the 40% answered ‘supervise construction work’ construction failure? 30% answered ‘checking, inspecting and evaluating the material and method used in project’ 20% answered ‘managing claim’ 10% answered ‘in charge in remedial work’ Q3 From your knowledge, which provisions in contract 100% answered ‘Clause 44’ document is the most affected in the event of 40% answered ‘Clause48’ construction failure? 30% answered ’Clause 45’ 30% answered ‘Clause 50’ 20% answered ‘Clause 10’ Q4 Do you think that current provisions in standard form 70% answered ‘no’ are adequate in managing construction failure? 30% answered ‘yes’ Q5 If the relevant provisions are limited, are there any 70% answered ’yes-available laws and contract acts’ related laws that can be referred to? 10% answered ‘yes-Engineer code of ethics’ 20% answered ‘not sure’ Q6 In your opinion, are there any problems with current 70% answered ‘yes’ and 30% answered ‘no’ guideline in managing construction failure? Q7 Do you think there necessary to improve the current 60% answered ‘yes’, 30% answered ‘no’, and 20% answered ‘not sure’ provision? Q8 As a professional directly / indirectly involved in the 50% answered ‘review by expertise often’ and 30% answered ‘not construction, would you like to propose the new scope necessary’ of the provisions of the contract, in order to make it 10% answered ‘add provisions of claim procedure’ and 10% answered ‘provision of third party’ more sufficient? Q9 Why did you think this new scope is necessary in - To protect client’s rights - Emphasis on quality control of managing that event? - To suit with current project construction - To gain respect from party scenario involve -- Easy to understand - To minimize construction disputes Q10 Lastly, what you can conclude on the overall - still lacking in direct - do not have right provision for performance of current contract documents? information managing failure after contract - provision for re-construct of period existing - still need to be improved building still not available - provisions should be revised by right expertise 30
  • 10. European Journal of Business and Management www.iiste.org ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online) Vol 4, No.1, 2012 Table 4. The frequency of responses in the limitations Limitations Likert Scale Total Relative Rank Index Frequency (RI) 1 2 3 4 5 Default parties refused to cooperate during failure event. 3 22 5 30 0.81 1 The need of third party to continue the works if failure 1 4 17 8 30 0.81 2 occurred. Lack of knowledge about relevant applicable laws and 1 1 3 19 6 30 0.79 3 provisions. There is an inconsistency with other standards. 9 14 7 30 0.79 4 Unable to use the contract provisions as they lack of 2 8 11 9 30 0.78 5 guidance and experiences. Misinterpret the true intent of contract provisions. 3 7 14 6 30 0.75 6 Discrepancies in contract document (between drawing and 3 9 14 4 30 0.73 7 specifications in particular) which may lead to the failure. Default parties make unreasonable claim’s amount as 1 4 10 15 30 0.66 8 there is no details procedures in issuing a claim. Although current provisions have been superseded, they 4 17 9 30 0.63 9 prefer to use old form. Notes: 1. Scale used: 1=Strongly disagree, 2=Disagree, 3=Neither Disagree nor Agree, 4= Agree, 5=Strongly Agree Table5. Mann Whitney U Test for the limitations Lack of Misinterpret the Unable to use the Default parties knowledge about true intent of contract refused to relevant contract provisions as they cooperate applicable laws provisions. lack of guidance during failure and provisions. and experiences. event. Mann-Whitney U 79.000 81.500 64.500 92.000 Wilcoxon W 289.000 291.500 274.500 147.000 Asymp. Sig. (2-tailed) .282 .385 .101 .650 Table 6. Frequency of responses from engineer group regarding to the effects during construction Cause due limitations Likert Scale Total Relative Rank during construction Frequency Index 1 2 3 4 5 (RI) Decreased in project 1 13 6 20 0.84 1 quality Increased in project cost 5 11 4 20 0.79 2 Dispute between parties 3 16 1 20 0.78 3 involved Delay in completion 6 10 4 20 0.78 4 schedule Decreased in productivity 5 13 2 20 0.77 5 Disrespectful from 7 11 2 20 0.75 6 31
  • 11. European Journal of Business and Management www.iiste.org ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online) Vol 4, No.1, 2012 parties involve regarding to the contractual provisions effectiveness. Delay in payment 2 8 7 3 20 0.69 7 Notes: 1. Scale used: 1=Strongly disagree, 2=Disagree, 3=Neither Disagree nor Agree, 4= Agree, 5=Strongly Agree 32
  • 12. European Journal of Business and Management www.iiste.org ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online) Vol 4, No.1, 2012 Table 7. Responses from non engineer group regarding to the effects during construction Cause due Limitations Likert Scale Total Relative Rank during construction Frequency Index 1 2 3 4 5 (RI) Increased in project cost 1 4 5 10 0.86 1 Decreased in project 1 5 4 10 0.86 2 quality Disrespectful from 1 5 4 10 0.86 3 parties involve regarding to the contractual provisions effectiveness. Delay in completion 1 1 3 5 10 0.84 4 schedule Dispute between parties 1 7 2 10 0.82 5 involved Delay in payment 2 5 3 10 0.82 6 Decreased in productivity 2 1 4 3 10 0.76 7 Table 8. Mann Whitney U Test for both groups regarding to the effects during construction Delay in Decreased in Disrespectful payment project from parties quality involve regarding to the contractual provisions effectiveness. Mann-Whitney U 65.000 93.500 58.000 Wilcoxon W 275.000 303.500 268.000 Asymp. Sig. (2- .103 .741 0.042 tailed) 33
  • 13. European Journal of Business and Management www.iiste.org ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online) Vol 4, No.1, 2012 Table 9. Responses from engineer group for causes due to the contractual limitations after the project handovers Cause due Limitations Likert Scale Total Relative Rank after project handover Frequency Index 1 2 3 4 5 (RI) Low quality of 1 3 10 6 20 0.81 1 completed projects Bring bad images to 7 5 8 20 0.81 2 Client Disputes between the 6 11 3 20 0.77 3 parties involved. Client cannot claim the 3 9 5 3 20 0.68 4 contractor as the contract period is already expired. Client does not have 2 2 6 7 3 20 0.67 5 rights to request from the contractor to make good of defects. Client has to suffer the 2 2 6 7 3 20 0.67 6 loss caused by the failure alone. Table 10. Responses from non engineer group for contract limitations cause after handovers Cause due Limitations Likert Scale Total Relative Rank after project handover Frequency Index 1 2 3 4 5 (RI) Low quality of 4 6 10 0.92 1 completed projects Disputes between the 1 5 4 10 0.86 2 parties involved. Bring bad images to 2 5 3 10 0.82 3 Client Client has to suffer the 4 2 4 10 0.60 4 loss caused by the failure alone. Client does not have 1 6 2 1 10 0.46 5 rights to request from the contractor to make good of defects. 34
  • 14. European Journal of Business and Management www.iiste.org ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online) Vol 4, No.1, 2012 Client cannot claim the 1 5 4 10 0.46 6 contractor as the contract period is already expired. 35
  • 15. European Journal of Business and Management www.iiste.org ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online) Vol 4, No.1, 2012 Table 11. Mann Whitney U Test for both groups for contract limitations cause after handovers Client does not Bring bad Client cannot have rights to images to claim the request from Client contractor as the contractor the contract to make good period is of defects. already expired. Mann-Whitney U 46.500 97.500 37.500 Wilcoxon W 101.500 307.500 92.500 Asymp. Sig. (2-tailed) .015 .907 .004 36
  • 16. European Journal of Business and Management www.iiste.org ISSN 2222-1905 (Paper) ISSN 2222-2839 (Online) Vol 4, No.1, 2012 Table 12. List of suggestions for the new scope Suggestion of the new scopes in Likert Scale Total Relative Rank contract provisions Frequency Index 1 2 3 4 5 (RI) The detail and proper procedures of 3 16 11 30 0.85 1 claim issuance to resolve matters arising. The relevant provisions of 4 16 10 30 0.84 2 construction failure should be stated in separate clause due to its scope of event. There should be a specific clauses in 4 16 10 30 0.84 3 the contract related to managing construction failure. Each matter in provisions should be 7 15 8 30 0.81 4 reviewed by related expertise to enhance its effectiveness. The needs for client and parties to 7 15 8 30 0.81 5 understand the contractual provisions thoroughly. The clause related to managing 7 15 8 30 0.81 6 failure in contract document must be made to enforce reasonable period of DLP. The default party should be liable if 1 5 18 6 30 0.79 7 the failure happened due to its work. It should completely being charged. A specific agencies or bodies must 1 10 15 4 30 0.75 8 be existed for the party involved to set guideline in resolving that matters. 37
  • 17. International Journals Call for Paper The IISTE, a U.S. publisher, is currently hosting the academic journals listed below. The peer review process of the following journals usually takes LESS THAN 14 business days and IISTE usually publishes a qualified article within 30 days. Authors should send their full paper to the following email address. More information can be found in the IISTE website : www.iiste.org Business, Economics, Finance and Management PAPER SUBMISSION EMAIL European Journal of Business and Management EJBM@iiste.org Research Journal of Finance and Accounting RJFA@iiste.org Journal of Economics and Sustainable Development JESD@iiste.org Information and Knowledge Management IKM@iiste.org Developing Country Studies DCS@iiste.org Industrial Engineering Letters IEL@iiste.org Physical Sciences, Mathematics and Chemistry PAPER SUBMISSION EMAIL Journal of Natural Sciences Research JNSR@iiste.org Chemistry and Materials Research CMR@iiste.org Mathematical Theory and Modeling MTM@iiste.org Advances in Physics Theories and Applications APTA@iiste.org Chemical and Process Engineering Research CPER@iiste.org Engineering, Technology and Systems PAPER SUBMISSION EMAIL Computer Engineering and Intelligent Systems CEIS@iiste.org Innovative Systems Design and Engineering ISDE@iiste.org Journal of Energy Technologies and Policy JETP@iiste.org Information and Knowledge Management IKM@iiste.org Control Theory and Informatics CTI@iiste.org Journal of Information Engineering and Applications JIEA@iiste.org Industrial Engineering Letters IEL@iiste.org Network and Complex Systems NCS@iiste.org Environment, Civil, Materials Sciences PAPER SUBMISSION EMAIL Journal of Environment and Earth Science JEES@iiste.org Civil and Environmental Research CER@iiste.org Journal of Natural Sciences Research JNSR@iiste.org Civil and Environmental Research CER@iiste.org Life Science, Food and Medical Sciences PAPER SUBMISSION EMAIL Journal of Natural Sciences Research JNSR@iiste.org Journal of Biology, Agriculture and Healthcare JBAH@iiste.org Food Science and Quality Management FSQM@iiste.org Chemistry and Materials Research CMR@iiste.org Education, and other Social Sciences PAPER SUBMISSION EMAIL Journal of Education and Practice JEP@iiste.org Journal of Law, Policy and Globalization JLPG@iiste.org Global knowledge sharing: New Media and Mass Communication NMMC@iiste.org EBSCO, Index Copernicus, Ulrich's Journal of Energy Technologies and Policy JETP@iiste.org Periodicals Directory, JournalTOCS, PKP Historical Research Letter HRL@iiste.org Open Archives Harvester, Bielefeld Academic Search Engine, Elektronische Public Policy and Administration Research PPAR@iiste.org Zeitschriftenbibliothek EZB, Open J-Gate, International Affairs and Global Strategy IAGS@iiste.org OCLC WorldCat, Universe Digtial Library , Research on Humanities and Social Sciences RHSS@iiste.org NewJour, Google Scholar. Developing Country Studies DCS@iiste.org IISTE is member of CrossRef. All journals Arts and Design Studies ADS@iiste.org have high IC Impact Factor Values (ICV).