SlideShare une entreprise Scribd logo
1  sur  6
Télécharger pour lire hors ligne
Journal of Energy Technologies and Policy                                                       www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.2, No.4, 2012


           Improving Power Distribution Efficiency On Power Lines
                                  Charles Ndungu1* , Livingstone Ngoo1,2 , John Nderu1,2
       1. School of Engineering, Jomo Kenyatta University of Agriculture and Technology, PO box 62000, Nairobi,
                                                         Kenya
         2. School of Engineering, Multimedia University College of Kenya, PO box 62000, Nairobi, Kenya
                                                    *
                                                    cndungu03@yahoo.com

Abstract
This paper discusses the power factor of transmission and distribution lines for selected power utility substations.
The choice of selection of lines was based on the nature of the load and the status of the loading. The data collected
and analyzed revealed that some feeder lines at most of substations are distributing active power at low PF below the
grid threshold limit. Feeder lines mainly supplying domestic loads have their PF generally low and on the other hand,
it was found that feeder lines supplying industrial loads have power factor well above the statutory limit. It is
concluded that it is imperative to compensate the reactive current on feeder lines supplying mainly domestic loads in
the vicinity of the loads i.e. near the distribution transformers to improve the power factor of these feeder lines in
order to increase distribution efficiency and improve the voltage profile.

Keywords: Reactive power, VAr compensator, Power factor, Energy meter, Feeder lines

1. Introduction

Reactive power is a parameter that is associated with power factor that provides the power distribution efficiency and
voltage stability of the system on transmission or distribution lines. Most of power quality problems can be mitigated
by adequate control of reactive power. It has been proved that reactive power has major correlation with the voltage
stability [1]. To minimize the negative effects of low power factor on power distribution on the feeder lines, it is
imperative to compensate the reactive power at point of demand. National grid is obliged (Grid code requirements)
to secure the transmission network to a closely defined voltage and stability criteria. The reactive power output under
steady state conditions should be fully available within the voltage range        5%. This can be achieved through
innovative circuit arrangement, transformers on load tap changer, or shunt VAr compensation [2] and [4].
Power factor is an important aspect to consider in an ac circuit. When the power factor (lagging or leading) is less
than one it means that the transmission or distribution system has to carry more current than would be necessary with
zero reactance in the system to deliver the same amount (real) power to the resistive load [3].

From this work it is concluded that there is need to enhance the existing voltage stabilizing mechanism (on load tap
changer) by installing shunt fixed capacitors or variable capacitors depending on reactive power demand. This
should be done especially on the feeders and transmission lines supplying domestic loads with substantial loads to
improve the power factor and voltage stability.

 2. Research Methodology

The data was collected on randomly sampled transmission and distribution lines at selected substations; substations
A, B and C . Instantaneous power factor was captured as recorded by energy meters at intervals of four hours each
day on different transmission and distribution lines for period of two weeks; one week per month for two consecutive
months. For ease of data interpretation and analysis, the data was grouped into highest and lowest instantaneous
power factor (IPF) recorded and the time of the day it occurred.


2.1 Criteria for selecting the feeder lines
Feeder lines were selected based on the type of the load (domestic, industrial or mixed) and magnitude of loading
(slightly, moderately or heavily loaded). The amount of load was deduced by the maximum active demand (kW)


                                                          1
Journal of Energy Technologies and Policy                                                         www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.2, No.4, 2012

recorded by the energy meter, which determined whether the feeder is slightly, moderate, or heavily loaded.

2.2 Results obtained
The duration of data collection was based by the fact that for substantial change of reactive power demand, there is
no likelihood of substantial increase/ decrease of the load connected to the line as it was shown from national load
profile that capturing of data at interval of four hours period will suffice as change of the load is gradual rather than
instantaneous.
The data obtained is presented in both table and graphical forms. Time is categorized as day (08:00 – 18:00 hours)
and night (18:00 – 08:00 hours) and the minimum and maximum IPF the energy meter recorded. The aim was to note
what time of the day the feeder or transmission line has highest or lowest power factor. Based on the frequency of
occurrence, the line was deduced as having low or high power factor. Considering the first column of the table 1
(transmission 1), 0.93 was the lowest IPF recorded by the meter during the day and 0.97 was the highest IPF
recorded on Monday night.
The aggregate power factors captured were as depicted in tables (1), (2) and (3) hereunder.

3. Data analysis
The IPF captured reveals that the amount of reactive power delivered by the transmission and distribution lines
primarily depend on the nature of the loads. This can be deduced by considering each of the feeder lines as follow.

i)    Industrial Loads

Lines supplying industrial loads were noted have almost unity power factor at all the sampled substations. This is
presumed to be due to the availability of VAr compensators installed at large power consumers hence relieving the
lines delivering the reactive power from the source.

ii) Domestic loads

Lines supplying domestic loads have low power factor as there is no VAr compensation at domestic and small power
end users. This implies that the reactive power required by these loads, which are mostly non-linear, have to be
delivered by the transmission and distribution lines. It is worth noting that low IPF occurs mainly during the day time
as numerous non –linear loads (such as computers, printers, scanner/ photocopiers) are used during the day hence
raising the demand of reactive power. The feeder lines at substation C with power factor below 0.7 are distributing
the active power at efficiency below 50%. This implies that more than half of technical losses on these lines are
caused by reactive current.

iii) Mixed load lines

The data collected clearly shows that lines supplying both domestic and small scale industrial loads (mixed) have
relatively low power factor, but higher than lines dominated by domestic loads. It is worth mentioning that low
power factor occurs during the night and weekend. This can be attributed to dominance of domestic loads as some of
the small scale industries are closed at night and such industries usually have miniature power factor correction
capacitors for compensation of reactive power during the day on weekdays.


3.    Conclusion and recommendation

 The analysis of the data obtained in this work leads to the following conclusions;
   i. It was observed that some of transmission and feeder lines are supplying the active power at low efficiency
        (low power factor) and especially lines supplying domestic loads. The most affected lines were those
        supplying domestic and mixed loads due to numerous non-linear and inductive loads whose reactive power
        is delivered from the source.

     ii.   To minimize the losses and negative effects of reactive power in the power system, it is imperative to take a
           mitigation measure to compensate the reactive power at the point of demand. This can be realized by



                                                            2
Journal of Energy Technologies and Policy                                                                      www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.2, No.4, 2012

           installation of Fixed VAr compensator (shunt power factor correction capacitor) at lines supplying mainly
           domestic loads.


References

    Feng Dong, (2005). Improving Voltage Stability by Reactive Power Reserve Management. IEEE Trans. On
    power systems, Vol. 20 No.1

    Gerardo Escobar et al, (2001). Reactive Power and Unbalance Compensation using STATCOM with
    Dissipativity – based control. IEEE Transactions on control system technology, vol. 9, No. 5.

    Hong Chen, (2008). Practices of Reactive Power Management and Compensation. IEEE General meeting.

    Lu. F.C and Hsu Y, (1995). Reactive Power / Voltage Control in a Distribution Substation Using Dynamic
    Programming. IEE Proc – Gener Transm. Distribution, Vol. 142 No.6.

    First Author (Charles Ndung’u) BORN AT NYADARUA DISTRICT IN 1974. JOIN PRIMARY SCHOOL IN
    1982 TO 1989. ENROLLED IN SECONDARY EDUCATION IN 1990 TO 1993. JOINED MOI UNIVERSITY
    AT ELDORET (KENYA) IN 1995 TO UNDERTAKE BSC OF ELECTRICAL AND TELCOMMUNICATIONS
    ENGINEERING AND GRADUATED IN 2000. COMPLETED A MSC IN CONTROL ENGINEERING AT
    JOMO KENYATTA UNIVERSITY OF AGRICULTURE AND TECHNOLOGY (KENYA) IN MARCH 2012.
    Currently working with Kenya Power as energy meter and transmission engineer. The area of study is power
    quality: harmonic distortions, reactive power compensation and power factor improvement
    Second Author (John Nderu) BORN AT MURANGA DISTRICT IN 1964. OBTAINED BSC AND MSC IN
    ELECTRICAL AND ELECTRONIC ENGINEERING AT TOTTORI UNIVERSITY (JAPAN) IN 1993 AND
    1995 RESPECTIVELY AND PHD IN THE SAME AREA AT KYUSHU INSTITUTE OF TECHNOLOGY
    JAPAN. HIS CURRENTLY ASSOCIATE PROFESSOR IN ELECTRICAL AND ELECTRONIC
    ENGINEERING AT JOMO KENYATTA UNIVERSITY OF AGRICULTURE AND TECHNOLOGY KENYA.
    Area of interest is on effect of harmonics on the power system and methods of mitigation. In additional
    application of magnetostrictive amorphous wires in sensing , and electronic load controller for mini -hydro
    generators



Table 1. Instantaneous power factor captured at substation A

   Day of the week     Monday:        Tuesday: min    Wednesday:         Thursday:      Friday: min    Saturday:      Sunday: min

                       min and max    and max (time   min and max        min and max    and     max    min and max    and      max

                       (time          captured)       (time              (time          (time          (time          (time

                       captured)                      captured)          captured)      captured)      captured)      captured)

   Transmission1       0.93 (Day)     0.93 (Day)      0.94 (Day)         0.95 (Night)   0.96 (Day)     0.95 (Day)     0.96 (Day)

   (Industrial load)   0.97 (Night)   0.97 (Day)      0.96 (Day)         0.97 (Day)     0.97 (Day)     0.96 (Day)     0.97 (Day)


   Line 1 (Mixed       0.93 (Night)   0.96 (Day)      0.93 (Day)         0.94 (Night)   0.95 (Night)   0.95 (Day)     0.95 (Night)

   load)               0.98 (Day)     0.97 (Day)      0.98 (Night)       0.97 (Day)     0.97 (Day)     0.96 (Day)     0.97 (Day)



From the table 1, the lines power distribution efficiency is high due to availability of numerous industries with Var
compensators. This also implies that the technical losses for these lines are less as they mostly carry active power.


                                                                     3
Journal of Energy Technologies and Policy                                                                          www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.2, No.4, 2012

Table 2. Instantaneous power factor captured at substation B

   Feeder / Day       Monday:        Tuesday: min      Wednesday:            Thursday:      Friday: min    Saturday:      Sunday: min

                      min and max    and         max   min   and      max    min and max    and     max    min and max    and      max

                      (time          (time             (time captured)       (time          (time          (time          (time

                      captured)      captured)                               captured)      captured)      captured)      captured)

   Transmission1      0.87 (Day)     0.87 (Day)        0.84 (Night)          0.91 (Day)     0.91 (Night)   0.89 (Day)     0.91 (Day)

   (Mixed loads)      0.94 (Night)   0.93 (Day)        0.92 (Night)          0.93 (Night)   0.93 (Day)     0.93 (Day)     0.94 (Night)


   Line 1 (Mixed      0.91 (Night)   0.87 (Day)        0.91 (Night)          0.90 (Night)   0.92 (Night)   0.91 (Night)   0.92 (Day)

   loads)             0.94 (Night)   0.95 (Day)        0.94 (Night)          0.95 (Day)     0.94 (Day)     0.94 (Night)   0.96 (Day)

   Line2              0.92 (Night)   0.88 (Day)        0.89 (Night)          0.91 (Night)   0.91 (Day)     0.91 (Day)     0.92 (Day)

   (Domestic )        0.94 (Day)     0.93 (Night)      0.92 (Night)          0.93 (Night)   0.93 (Night)   0.95 (Day)     0.94 (Day)




From the table 2, it is noted that transmission 1 with mixed loads and line 2 carrying mainly domestic loads have the
power factor relatively below 0.9. Domestic loads reactive current are usually not compensated and hence the line
has to carry that current from the source. Line 1 with mixed loads was found to have relatively low power factor
during the day as compared at night. It is presumed that during the night, the compact fluorescence bulbs which are
inherently associated with leading power factor improve the line power factor.



Table 3. Instantaneous power factor captured at substation C

   Feeder / Day       Monday:        Tuesday: min      Wednesday:            Thursday:      Friday: min    Saturday:      Sunday: min

                      min and max    and         max   min   and      max    min and max    and     max    min and max    and      max

                      (time          (time             (time captured)       (time          (time          (time          (time

                      captured)      captured)                               captured)      captured)      captured)      captured)

   Transmission1      0.65 (Day)     0.65 (Day)        0.65 (Night)          0.65 (Day)     0.64 (Night)   0.65 (Day)     0.64 (Day)

   (Domestic)         0.66 (Night)   0.68 (Night)      0.66 (Day)            0.66 (Night)   0.65 (Day)     0.65 (Night)   0.65 (Night)

   Line           1   0.98 (Night)   0.98 (Night)      0.98 (Both)           0.98 (Both)    0.98 (Both)    0.98 (Day)     0.98 (Day)

   (industrial)       0.99 (Day)     0.99 (Day)        0.98 (Both)           0.98 (Both)    0.98 (Both)    0.99 (Night)   0.99 (Night)

   Line           2   0.78 (Night)   0.76 (Night)      0.80 (Night)          0.78 (Night)   0.76 (Night)   0.78 (Night)   0.76 (Day)

   (Mixed)            0.80 (Day)     0.82 (Day)        0.82 (Day)            0.81 (Day)     0.83 (Day)     0.80 (Day)     0.80 (Night)




From Table 3, transmission 1 which is dominated by domestic loads such as TV sets, fridge, air conditioners and
computer was found to transmit the active power at low power factor. The technical losses on this line, 50% is due to
reactive current transmitted on the conductors and transformers. These lines dominated by domestic non –linear



                                                                         4
Journal of Energy Technologies and Policy                                                     www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.2, No.4, 2012

loads usually trip due to overloaded which causes the power outage. As mentioned earlier, lines supplying industrial
loads are having a good power factor as reactive power is compensated at the vicinity of demand. This is because the
large power consumers are compelled to compensate the reactive power otherwise are penalized (power factor
surcharge penalty).




                             Figure 1. Varitions of power factor for a period of one day

The relationship between the power factor and nature of the load from the data collected is shown as a graph in
Figure (1).
From figure (1), it is seen that the power factor and hence the efficiency of the line is determined by the dominant
loads. Industrial loads maintain feeder power factor well above the statutory limit due to the installation of VAr
compensators at the point of demand. Contrary, domestic loads cause the line to carry more reactive power hence
lower the line power factor. Also, it is clear from the graph that when the feeder line is supplying mixed loads (and
the domestic loads dominate the line which is mostly during the night and weekend), the line power factor is same as
the line with domestic loads (two graphs intersect).




                                                         5
This academic article was published by The International Institute for Science,
Technology and Education (IISTE). The IISTE is a pioneer in the Open Access
Publishing service based in the U.S. and Europe. The aim of the institute is
Accelerating Global Knowledge Sharing.

More information about the publisher can be found in the IISTE’s homepage:
http://www.iiste.org


The IISTE is currently hosting more than 30 peer-reviewed academic journals and
collaborating with academic institutions around the world. Prospective authors of
IISTE journals can find the submission instruction on the following page:
http://www.iiste.org/Journals/

The IISTE editorial team promises to the review and publish all the qualified
submissions in a fast manner. All the journals articles are available online to the
readers all over the world without financial, legal, or technical barriers other than
those inseparable from gaining access to the internet itself. Printed version of the
journals is also available upon request of readers and authors.

IISTE Knowledge Sharing Partners

EBSCO, Index Copernicus, Ulrich's Periodicals Directory, JournalTOCS, PKP Open
Archives Harvester, Bielefeld Academic Search Engine, Elektronische
Zeitschriftenbibliothek EZB, Open J-Gate, OCLC WorldCat, Universe Digtial
Library , NewJour, Google Scholar

Contenu connexe

Tendances

Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...
Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...
Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...Pradeep Avanigadda
 
Enhancement in Power Quality With Grid Interconnection of Renewable Energy So...
Enhancement in Power Quality With Grid Interconnection of Renewable Energy So...Enhancement in Power Quality With Grid Interconnection of Renewable Energy So...
Enhancement in Power Quality With Grid Interconnection of Renewable Energy So...IJERA Editor
 
Power Quality Improvement of Grid Interconnection of renewable Energy Based D...
Power Quality Improvement of Grid Interconnection of renewable Energy Based D...Power Quality Improvement of Grid Interconnection of renewable Energy Based D...
Power Quality Improvement of Grid Interconnection of renewable Energy Based D...IJERA Editor
 
Minimization of Overall Losses of a Distribution System under Contingency Con...
Minimization of Overall Losses of a Distribution System under Contingency Con...Minimization of Overall Losses of a Distribution System under Contingency Con...
Minimization of Overall Losses of a Distribution System under Contingency Con...paperpublications3
 
Improved Power Quality by using STATCOM Under Various Loading Conditions
Improved Power Quality by using STATCOM Under Various Loading ConditionsImproved Power Quality by using STATCOM Under Various Loading Conditions
Improved Power Quality by using STATCOM Under Various Loading ConditionsIJMTST Journal
 
Impact of Positive Sequence Admittance and Negative Sequence Conductance of D...
Impact of Positive Sequence Admittance and Negative Sequence Conductance of D...Impact of Positive Sequence Admittance and Negative Sequence Conductance of D...
Impact of Positive Sequence Admittance and Negative Sequence Conductance of D...ijtsrd
 
IRJET- Optimization of Loss Reduction using FACTS Device (SVC & STATCOM) ...
IRJET-  	  Optimization of Loss Reduction using FACTS Device (SVC & STATCOM) ...IRJET-  	  Optimization of Loss Reduction using FACTS Device (SVC & STATCOM) ...
IRJET- Optimization of Loss Reduction using FACTS Device (SVC & STATCOM) ...IRJET Journal
 
Power Quality Improvement at Distribution Level for Grid Connected Renewable ...
Power Quality Improvement at Distribution Level for Grid Connected Renewable ...Power Quality Improvement at Distribution Level for Grid Connected Renewable ...
Power Quality Improvement at Distribution Level for Grid Connected Renewable ...IJERA Editor
 
A comprehensive review on D-FACTS devices
A comprehensive review on D-FACTS devicesA comprehensive review on D-FACTS devices
A comprehensive review on D-FACTS devicesijtsrd
 
Introducing LQR-fuzzy for a dynamic multi area LFC-DR model
Introducing LQR-fuzzy for a dynamic multi area LFC-DR modelIntroducing LQR-fuzzy for a dynamic multi area LFC-DR model
Introducing LQR-fuzzy for a dynamic multi area LFC-DR modelIJECEIAES
 
Power Quality Enhancement using DSTATCOM by Immune Feedback Control Algorithm
Power Quality Enhancement using DSTATCOM by Immune Feedback Control AlgorithmPower Quality Enhancement using DSTATCOM by Immune Feedback Control Algorithm
Power Quality Enhancement using DSTATCOM by Immune Feedback Control Algorithmijtsrd
 
Hardware Implementation of Single Phase Power Factor Correction System using ...
Hardware Implementation of Single Phase Power Factor Correction System using ...Hardware Implementation of Single Phase Power Factor Correction System using ...
Hardware Implementation of Single Phase Power Factor Correction System using ...IAES-IJPEDS
 
Application of Unified Power Flow Controller in Nigeria Power System for Impr...
Application of Unified Power Flow Controller in Nigeria Power System for Impr...Application of Unified Power Flow Controller in Nigeria Power System for Impr...
Application of Unified Power Flow Controller in Nigeria Power System for Impr...ijtsrd
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)IJERD Editor
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD Editor
 

Tendances (19)

Dw33741745
Dw33741745Dw33741745
Dw33741745
 
Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...
Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...
Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...
 
Enhancement in Power Quality With Grid Interconnection of Renewable Energy So...
Enhancement in Power Quality With Grid Interconnection of Renewable Energy So...Enhancement in Power Quality With Grid Interconnection of Renewable Energy So...
Enhancement in Power Quality With Grid Interconnection of Renewable Energy So...
 
Power Quality Improvement of Grid Interconnection of renewable Energy Based D...
Power Quality Improvement of Grid Interconnection of renewable Energy Based D...Power Quality Improvement of Grid Interconnection of renewable Energy Based D...
Power Quality Improvement of Grid Interconnection of renewable Energy Based D...
 
Big Presentation
Big PresentationBig Presentation
Big Presentation
 
Minimization of Overall Losses of a Distribution System under Contingency Con...
Minimization of Overall Losses of a Distribution System under Contingency Con...Minimization of Overall Losses of a Distribution System under Contingency Con...
Minimization of Overall Losses of a Distribution System under Contingency Con...
 
Improved Power Quality by using STATCOM Under Various Loading Conditions
Improved Power Quality by using STATCOM Under Various Loading ConditionsImproved Power Quality by using STATCOM Under Various Loading Conditions
Improved Power Quality by using STATCOM Under Various Loading Conditions
 
Impact of Positive Sequence Admittance and Negative Sequence Conductance of D...
Impact of Positive Sequence Admittance and Negative Sequence Conductance of D...Impact of Positive Sequence Admittance and Negative Sequence Conductance of D...
Impact of Positive Sequence Admittance and Negative Sequence Conductance of D...
 
Power compensation for vector-based current control of a modular multilevel c...
Power compensation for vector-based current control of a modular multilevel c...Power compensation for vector-based current control of a modular multilevel c...
Power compensation for vector-based current control of a modular multilevel c...
 
IRJET- Optimization of Loss Reduction using FACTS Device (SVC & STATCOM) ...
IRJET-  	  Optimization of Loss Reduction using FACTS Device (SVC & STATCOM) ...IRJET-  	  Optimization of Loss Reduction using FACTS Device (SVC & STATCOM) ...
IRJET- Optimization of Loss Reduction using FACTS Device (SVC & STATCOM) ...
 
Power Quality Improvement at Distribution Level for Grid Connected Renewable ...
Power Quality Improvement at Distribution Level for Grid Connected Renewable ...Power Quality Improvement at Distribution Level for Grid Connected Renewable ...
Power Quality Improvement at Distribution Level for Grid Connected Renewable ...
 
A comprehensive review on D-FACTS devices
A comprehensive review on D-FACTS devicesA comprehensive review on D-FACTS devices
A comprehensive review on D-FACTS devices
 
Introducing LQR-fuzzy for a dynamic multi area LFC-DR model
Introducing LQR-fuzzy for a dynamic multi area LFC-DR modelIntroducing LQR-fuzzy for a dynamic multi area LFC-DR model
Introducing LQR-fuzzy for a dynamic multi area LFC-DR model
 
Power Quality Enhancement using DSTATCOM by Immune Feedback Control Algorithm
Power Quality Enhancement using DSTATCOM by Immune Feedback Control AlgorithmPower Quality Enhancement using DSTATCOM by Immune Feedback Control Algorithm
Power Quality Enhancement using DSTATCOM by Immune Feedback Control Algorithm
 
Hardware Implementation of Single Phase Power Factor Correction System using ...
Hardware Implementation of Single Phase Power Factor Correction System using ...Hardware Implementation of Single Phase Power Factor Correction System using ...
Hardware Implementation of Single Phase Power Factor Correction System using ...
 
Il2616361640
Il2616361640Il2616361640
Il2616361640
 
Application of Unified Power Flow Controller in Nigeria Power System for Impr...
Application of Unified Power Flow Controller in Nigeria Power System for Impr...Application of Unified Power Flow Controller in Nigeria Power System for Impr...
Application of Unified Power Flow Controller in Nigeria Power System for Impr...
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
 

Similaire à Improving power distribution efficiency on power lines

Optimization Technique for Power Quality Improvement using DSTATCOM Neural Ne...
Optimization Technique for Power Quality Improvement using DSTATCOM Neural Ne...Optimization Technique for Power Quality Improvement using DSTATCOM Neural Ne...
Optimization Technique for Power Quality Improvement using DSTATCOM Neural Ne...ijtsrd
 
Unified power quality conditioner for compensating power quality problem ad
Unified power quality conditioner for compensating power quality problem adUnified power quality conditioner for compensating power quality problem ad
Unified power quality conditioner for compensating power quality problem adIAEME Publication
 
IRJET- Improved Electrical Power Supply to Trans-Amadi Industrial Layout, Por...
IRJET- Improved Electrical Power Supply to Trans-Amadi Industrial Layout, Por...IRJET- Improved Electrical Power Supply to Trans-Amadi Industrial Layout, Por...
IRJET- Improved Electrical Power Supply to Trans-Amadi Industrial Layout, Por...IRJET Journal
 
Distribution Network Power Quality Improvement by D-STATCOM & DVR Under Vario...
Distribution Network Power Quality Improvement by D-STATCOM & DVR Under Vario...Distribution Network Power Quality Improvement by D-STATCOM & DVR Under Vario...
Distribution Network Power Quality Improvement by D-STATCOM & DVR Under Vario...IRJET Journal
 
07 22 sep15 8711 18507-2-sm -edit_FACT Device for Reactive Power Compensation...
07 22 sep15 8711 18507-2-sm -edit_FACT Device for Reactive Power Compensation...07 22 sep15 8711 18507-2-sm -edit_FACT Device for Reactive Power Compensation...
07 22 sep15 8711 18507-2-sm -edit_FACT Device for Reactive Power Compensation...IJPEDS-IAES
 
Reliability Indices Evaluation of a Real Time Rural Radial Distribution Feeder
Reliability Indices Evaluation of a Real Time Rural Radial Distribution FeederReliability Indices Evaluation of a Real Time Rural Radial Distribution Feeder
Reliability Indices Evaluation of a Real Time Rural Radial Distribution FeederIOSR Journals
 
Comparison of upqc and dvr in wind turbine fed fsig under asymmetric faults
Comparison of upqc and dvr in wind turbine fed fsig under asymmetric faultsComparison of upqc and dvr in wind turbine fed fsig under asymmetric faults
Comparison of upqc and dvr in wind turbine fed fsig under asymmetric faultselelijjournal
 
Grid Connected PV System with Power Quality Improvement Using Intelligent Con...
Grid Connected PV System with Power Quality Improvement Using Intelligent Con...Grid Connected PV System with Power Quality Improvement Using Intelligent Con...
Grid Connected PV System with Power Quality Improvement Using Intelligent Con...IJMTST Journal
 
A Novel Technique for Enhancing Active and Reactive Power Quality for Renewab...
A Novel Technique for Enhancing Active and Reactive Power Quality for Renewab...A Novel Technique for Enhancing Active and Reactive Power Quality for Renewab...
A Novel Technique for Enhancing Active and Reactive Power Quality for Renewab...IJMER
 
Various Custom Power Devices for Power Quality Improvement A Review
Various Custom Power Devices for Power Quality Improvement A ReviewVarious Custom Power Devices for Power Quality Improvement A Review
Various Custom Power Devices for Power Quality Improvement A Reviewijtsrd
 
Comparative of Conventional and Intelligence Controller based Hybrid Generati...
Comparative of Conventional and Intelligence Controller based Hybrid Generati...Comparative of Conventional and Intelligence Controller based Hybrid Generati...
Comparative of Conventional and Intelligence Controller based Hybrid Generati...IJERD Editor
 
Investigation of Power Quality Indices in Jordanian Distribution Grid
Investigation of Power Quality Indices in Jordanian Distribution GridInvestigation of Power Quality Indices in Jordanian Distribution Grid
Investigation of Power Quality Indices in Jordanian Distribution GridIOSRJEEE
 
Power System Operational Challenges from the Energy Transition
Power System Operational Challenges from the Energy TransitionPower System Operational Challenges from the Energy Transition
Power System Operational Challenges from the Energy TransitionPower System Operation
 
IRJET- Renewable Energy Hybrid Power System with Improvement of Power Quality...
IRJET- Renewable Energy Hybrid Power System with Improvement of Power Quality...IRJET- Renewable Energy Hybrid Power System with Improvement of Power Quality...
IRJET- Renewable Energy Hybrid Power System with Improvement of Power Quality...IRJET Journal
 
MINOR PROJECT gb 08 (3).pdf
MINOR PROJECT gb 08 (3).pdfMINOR PROJECT gb 08 (3).pdf
MINOR PROJECT gb 08 (3).pdfDrSabhyataSoni
 
Improved Controller for the Dual Topology of the Unified Power Quality Condit...
Improved Controller for the Dual Topology of the Unified Power Quality Condit...Improved Controller for the Dual Topology of the Unified Power Quality Condit...
Improved Controller for the Dual Topology of the Unified Power Quality Condit...IRJET Journal
 

Similaire à Improving power distribution efficiency on power lines (20)

Optimization Technique for Power Quality Improvement using DSTATCOM Neural Ne...
Optimization Technique for Power Quality Improvement using DSTATCOM Neural Ne...Optimization Technique for Power Quality Improvement using DSTATCOM Neural Ne...
Optimization Technique for Power Quality Improvement using DSTATCOM Neural Ne...
 
Unified power quality conditioner for compensating power quality problem ad
Unified power quality conditioner for compensating power quality problem adUnified power quality conditioner for compensating power quality problem ad
Unified power quality conditioner for compensating power quality problem ad
 
IRJET- Improved Electrical Power Supply to Trans-Amadi Industrial Layout, Por...
IRJET- Improved Electrical Power Supply to Trans-Amadi Industrial Layout, Por...IRJET- Improved Electrical Power Supply to Trans-Amadi Industrial Layout, Por...
IRJET- Improved Electrical Power Supply to Trans-Amadi Industrial Layout, Por...
 
Distribution Network Power Quality Improvement by D-STATCOM & DVR Under Vario...
Distribution Network Power Quality Improvement by D-STATCOM & DVR Under Vario...Distribution Network Power Quality Improvement by D-STATCOM & DVR Under Vario...
Distribution Network Power Quality Improvement by D-STATCOM & DVR Under Vario...
 
07 22 sep15 8711 18507-2-sm -edit_FACT Device for Reactive Power Compensation...
07 22 sep15 8711 18507-2-sm -edit_FACT Device for Reactive Power Compensation...07 22 sep15 8711 18507-2-sm -edit_FACT Device for Reactive Power Compensation...
07 22 sep15 8711 18507-2-sm -edit_FACT Device for Reactive Power Compensation...
 
Reliability Indices Evaluation of a Real Time Rural Radial Distribution Feeder
Reliability Indices Evaluation of a Real Time Rural Radial Distribution FeederReliability Indices Evaluation of a Real Time Rural Radial Distribution Feeder
Reliability Indices Evaluation of a Real Time Rural Radial Distribution Feeder
 
Comparison of upqc and dvr in wind turbine fed fsig under asymmetric faults
Comparison of upqc and dvr in wind turbine fed fsig under asymmetric faultsComparison of upqc and dvr in wind turbine fed fsig under asymmetric faults
Comparison of upqc and dvr in wind turbine fed fsig under asymmetric faults
 
Gr3412151231
Gr3412151231Gr3412151231
Gr3412151231
 
Grid Connected PV System with Power Quality Improvement Using Intelligent Con...
Grid Connected PV System with Power Quality Improvement Using Intelligent Con...Grid Connected PV System with Power Quality Improvement Using Intelligent Con...
Grid Connected PV System with Power Quality Improvement Using Intelligent Con...
 
B010240820
B010240820B010240820
B010240820
 
u.pdf
u.pdfu.pdf
u.pdf
 
Dw33741745
Dw33741745Dw33741745
Dw33741745
 
A Novel Technique for Enhancing Active and Reactive Power Quality for Renewab...
A Novel Technique for Enhancing Active and Reactive Power Quality for Renewab...A Novel Technique for Enhancing Active and Reactive Power Quality for Renewab...
A Novel Technique for Enhancing Active and Reactive Power Quality for Renewab...
 
Various Custom Power Devices for Power Quality Improvement A Review
Various Custom Power Devices for Power Quality Improvement A ReviewVarious Custom Power Devices for Power Quality Improvement A Review
Various Custom Power Devices for Power Quality Improvement A Review
 
Comparative of Conventional and Intelligence Controller based Hybrid Generati...
Comparative of Conventional and Intelligence Controller based Hybrid Generati...Comparative of Conventional and Intelligence Controller based Hybrid Generati...
Comparative of Conventional and Intelligence Controller based Hybrid Generati...
 
Investigation of Power Quality Indices in Jordanian Distribution Grid
Investigation of Power Quality Indices in Jordanian Distribution GridInvestigation of Power Quality Indices in Jordanian Distribution Grid
Investigation of Power Quality Indices in Jordanian Distribution Grid
 
Power System Operational Challenges from the Energy Transition
Power System Operational Challenges from the Energy TransitionPower System Operational Challenges from the Energy Transition
Power System Operational Challenges from the Energy Transition
 
IRJET- Renewable Energy Hybrid Power System with Improvement of Power Quality...
IRJET- Renewable Energy Hybrid Power System with Improvement of Power Quality...IRJET- Renewable Energy Hybrid Power System with Improvement of Power Quality...
IRJET- Renewable Energy Hybrid Power System with Improvement of Power Quality...
 
MINOR PROJECT gb 08 (3).pdf
MINOR PROJECT gb 08 (3).pdfMINOR PROJECT gb 08 (3).pdf
MINOR PROJECT gb 08 (3).pdf
 
Improved Controller for the Dual Topology of the Unified Power Quality Condit...
Improved Controller for the Dual Topology of the Unified Power Quality Condit...Improved Controller for the Dual Topology of the Unified Power Quality Condit...
Improved Controller for the Dual Topology of the Unified Power Quality Condit...
 

Plus de Alexander Decker

Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Alexander Decker
 
A validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale inA validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale inAlexander Decker
 
A usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesA usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesAlexander Decker
 
A universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksA universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksAlexander Decker
 
A unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dA unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dAlexander Decker
 
A trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceA trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceAlexander Decker
 
A transformational generative approach towards understanding al-istifham
A transformational  generative approach towards understanding al-istifhamA transformational  generative approach towards understanding al-istifham
A transformational generative approach towards understanding al-istifhamAlexander Decker
 
A time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaA time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaAlexander Decker
 
A therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenA therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenAlexander Decker
 
A theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksA theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksAlexander Decker
 
A systematic evaluation of link budget for
A systematic evaluation of link budget forA systematic evaluation of link budget for
A systematic evaluation of link budget forAlexander Decker
 
A synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabA synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabAlexander Decker
 
A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...Alexander Decker
 
A survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalA survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalAlexander Decker
 
A survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesA survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesAlexander Decker
 
A survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbA survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbAlexander Decker
 
A survey on challenges to the media cloud
A survey on challenges to the media cloudA survey on challenges to the media cloud
A survey on challenges to the media cloudAlexander Decker
 
A survey of provenance leveraged
A survey of provenance leveragedA survey of provenance leveraged
A survey of provenance leveragedAlexander Decker
 
A survey of private equity investments in kenya
A survey of private equity investments in kenyaA survey of private equity investments in kenya
A survey of private equity investments in kenyaAlexander Decker
 
A study to measures the financial health of
A study to measures the financial health ofA study to measures the financial health of
A study to measures the financial health ofAlexander Decker
 

Plus de Alexander Decker (20)

Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...
 
A validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale inA validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale in
 
A usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesA usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websites
 
A universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksA universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banks
 
A unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dA unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized d
 
A trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceA trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistance
 
A transformational generative approach towards understanding al-istifham
A transformational  generative approach towards understanding al-istifhamA transformational  generative approach towards understanding al-istifham
A transformational generative approach towards understanding al-istifham
 
A time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaA time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibia
 
A therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenA therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school children
 
A theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksA theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banks
 
A systematic evaluation of link budget for
A systematic evaluation of link budget forA systematic evaluation of link budget for
A systematic evaluation of link budget for
 
A synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabA synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjab
 
A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...
 
A survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalA survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incremental
 
A survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesA survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniques
 
A survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbA survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo db
 
A survey on challenges to the media cloud
A survey on challenges to the media cloudA survey on challenges to the media cloud
A survey on challenges to the media cloud
 
A survey of provenance leveraged
A survey of provenance leveragedA survey of provenance leveraged
A survey of provenance leveraged
 
A survey of private equity investments in kenya
A survey of private equity investments in kenyaA survey of private equity investments in kenya
A survey of private equity investments in kenya
 
A study to measures the financial health of
A study to measures the financial health ofA study to measures the financial health of
A study to measures the financial health of
 

Dernier

8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportMintel Group
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionMintel Group
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncrdollysharma2066
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 

Dernier (20)

8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample Report
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted Version
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 

Improving power distribution efficiency on power lines

  • 1. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.2, No.4, 2012 Improving Power Distribution Efficiency On Power Lines Charles Ndungu1* , Livingstone Ngoo1,2 , John Nderu1,2 1. School of Engineering, Jomo Kenyatta University of Agriculture and Technology, PO box 62000, Nairobi, Kenya 2. School of Engineering, Multimedia University College of Kenya, PO box 62000, Nairobi, Kenya * cndungu03@yahoo.com Abstract This paper discusses the power factor of transmission and distribution lines for selected power utility substations. The choice of selection of lines was based on the nature of the load and the status of the loading. The data collected and analyzed revealed that some feeder lines at most of substations are distributing active power at low PF below the grid threshold limit. Feeder lines mainly supplying domestic loads have their PF generally low and on the other hand, it was found that feeder lines supplying industrial loads have power factor well above the statutory limit. It is concluded that it is imperative to compensate the reactive current on feeder lines supplying mainly domestic loads in the vicinity of the loads i.e. near the distribution transformers to improve the power factor of these feeder lines in order to increase distribution efficiency and improve the voltage profile. Keywords: Reactive power, VAr compensator, Power factor, Energy meter, Feeder lines 1. Introduction Reactive power is a parameter that is associated with power factor that provides the power distribution efficiency and voltage stability of the system on transmission or distribution lines. Most of power quality problems can be mitigated by adequate control of reactive power. It has been proved that reactive power has major correlation with the voltage stability [1]. To minimize the negative effects of low power factor on power distribution on the feeder lines, it is imperative to compensate the reactive power at point of demand. National grid is obliged (Grid code requirements) to secure the transmission network to a closely defined voltage and stability criteria. The reactive power output under steady state conditions should be fully available within the voltage range 5%. This can be achieved through innovative circuit arrangement, transformers on load tap changer, or shunt VAr compensation [2] and [4]. Power factor is an important aspect to consider in an ac circuit. When the power factor (lagging or leading) is less than one it means that the transmission or distribution system has to carry more current than would be necessary with zero reactance in the system to deliver the same amount (real) power to the resistive load [3]. From this work it is concluded that there is need to enhance the existing voltage stabilizing mechanism (on load tap changer) by installing shunt fixed capacitors or variable capacitors depending on reactive power demand. This should be done especially on the feeders and transmission lines supplying domestic loads with substantial loads to improve the power factor and voltage stability. 2. Research Methodology The data was collected on randomly sampled transmission and distribution lines at selected substations; substations A, B and C . Instantaneous power factor was captured as recorded by energy meters at intervals of four hours each day on different transmission and distribution lines for period of two weeks; one week per month for two consecutive months. For ease of data interpretation and analysis, the data was grouped into highest and lowest instantaneous power factor (IPF) recorded and the time of the day it occurred. 2.1 Criteria for selecting the feeder lines Feeder lines were selected based on the type of the load (domestic, industrial or mixed) and magnitude of loading (slightly, moderately or heavily loaded). The amount of load was deduced by the maximum active demand (kW) 1
  • 2. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.2, No.4, 2012 recorded by the energy meter, which determined whether the feeder is slightly, moderate, or heavily loaded. 2.2 Results obtained The duration of data collection was based by the fact that for substantial change of reactive power demand, there is no likelihood of substantial increase/ decrease of the load connected to the line as it was shown from national load profile that capturing of data at interval of four hours period will suffice as change of the load is gradual rather than instantaneous. The data obtained is presented in both table and graphical forms. Time is categorized as day (08:00 – 18:00 hours) and night (18:00 – 08:00 hours) and the minimum and maximum IPF the energy meter recorded. The aim was to note what time of the day the feeder or transmission line has highest or lowest power factor. Based on the frequency of occurrence, the line was deduced as having low or high power factor. Considering the first column of the table 1 (transmission 1), 0.93 was the lowest IPF recorded by the meter during the day and 0.97 was the highest IPF recorded on Monday night. The aggregate power factors captured were as depicted in tables (1), (2) and (3) hereunder. 3. Data analysis The IPF captured reveals that the amount of reactive power delivered by the transmission and distribution lines primarily depend on the nature of the loads. This can be deduced by considering each of the feeder lines as follow. i) Industrial Loads Lines supplying industrial loads were noted have almost unity power factor at all the sampled substations. This is presumed to be due to the availability of VAr compensators installed at large power consumers hence relieving the lines delivering the reactive power from the source. ii) Domestic loads Lines supplying domestic loads have low power factor as there is no VAr compensation at domestic and small power end users. This implies that the reactive power required by these loads, which are mostly non-linear, have to be delivered by the transmission and distribution lines. It is worth noting that low IPF occurs mainly during the day time as numerous non –linear loads (such as computers, printers, scanner/ photocopiers) are used during the day hence raising the demand of reactive power. The feeder lines at substation C with power factor below 0.7 are distributing the active power at efficiency below 50%. This implies that more than half of technical losses on these lines are caused by reactive current. iii) Mixed load lines The data collected clearly shows that lines supplying both domestic and small scale industrial loads (mixed) have relatively low power factor, but higher than lines dominated by domestic loads. It is worth mentioning that low power factor occurs during the night and weekend. This can be attributed to dominance of domestic loads as some of the small scale industries are closed at night and such industries usually have miniature power factor correction capacitors for compensation of reactive power during the day on weekdays. 3. Conclusion and recommendation The analysis of the data obtained in this work leads to the following conclusions; i. It was observed that some of transmission and feeder lines are supplying the active power at low efficiency (low power factor) and especially lines supplying domestic loads. The most affected lines were those supplying domestic and mixed loads due to numerous non-linear and inductive loads whose reactive power is delivered from the source. ii. To minimize the losses and negative effects of reactive power in the power system, it is imperative to take a mitigation measure to compensate the reactive power at the point of demand. This can be realized by 2
  • 3. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.2, No.4, 2012 installation of Fixed VAr compensator (shunt power factor correction capacitor) at lines supplying mainly domestic loads. References Feng Dong, (2005). Improving Voltage Stability by Reactive Power Reserve Management. IEEE Trans. On power systems, Vol. 20 No.1 Gerardo Escobar et al, (2001). Reactive Power and Unbalance Compensation using STATCOM with Dissipativity – based control. IEEE Transactions on control system technology, vol. 9, No. 5. Hong Chen, (2008). Practices of Reactive Power Management and Compensation. IEEE General meeting. Lu. F.C and Hsu Y, (1995). Reactive Power / Voltage Control in a Distribution Substation Using Dynamic Programming. IEE Proc – Gener Transm. Distribution, Vol. 142 No.6. First Author (Charles Ndung’u) BORN AT NYADARUA DISTRICT IN 1974. JOIN PRIMARY SCHOOL IN 1982 TO 1989. ENROLLED IN SECONDARY EDUCATION IN 1990 TO 1993. JOINED MOI UNIVERSITY AT ELDORET (KENYA) IN 1995 TO UNDERTAKE BSC OF ELECTRICAL AND TELCOMMUNICATIONS ENGINEERING AND GRADUATED IN 2000. COMPLETED A MSC IN CONTROL ENGINEERING AT JOMO KENYATTA UNIVERSITY OF AGRICULTURE AND TECHNOLOGY (KENYA) IN MARCH 2012. Currently working with Kenya Power as energy meter and transmission engineer. The area of study is power quality: harmonic distortions, reactive power compensation and power factor improvement Second Author (John Nderu) BORN AT MURANGA DISTRICT IN 1964. OBTAINED BSC AND MSC IN ELECTRICAL AND ELECTRONIC ENGINEERING AT TOTTORI UNIVERSITY (JAPAN) IN 1993 AND 1995 RESPECTIVELY AND PHD IN THE SAME AREA AT KYUSHU INSTITUTE OF TECHNOLOGY JAPAN. HIS CURRENTLY ASSOCIATE PROFESSOR IN ELECTRICAL AND ELECTRONIC ENGINEERING AT JOMO KENYATTA UNIVERSITY OF AGRICULTURE AND TECHNOLOGY KENYA. Area of interest is on effect of harmonics on the power system and methods of mitigation. In additional application of magnetostrictive amorphous wires in sensing , and electronic load controller for mini -hydro generators Table 1. Instantaneous power factor captured at substation A Day of the week Monday: Tuesday: min Wednesday: Thursday: Friday: min Saturday: Sunday: min min and max and max (time min and max min and max and max min and max and max (time captured) (time (time (time (time (time captured) captured) captured) captured) captured) captured) Transmission1 0.93 (Day) 0.93 (Day) 0.94 (Day) 0.95 (Night) 0.96 (Day) 0.95 (Day) 0.96 (Day) (Industrial load) 0.97 (Night) 0.97 (Day) 0.96 (Day) 0.97 (Day) 0.97 (Day) 0.96 (Day) 0.97 (Day) Line 1 (Mixed 0.93 (Night) 0.96 (Day) 0.93 (Day) 0.94 (Night) 0.95 (Night) 0.95 (Day) 0.95 (Night) load) 0.98 (Day) 0.97 (Day) 0.98 (Night) 0.97 (Day) 0.97 (Day) 0.96 (Day) 0.97 (Day) From the table 1, the lines power distribution efficiency is high due to availability of numerous industries with Var compensators. This also implies that the technical losses for these lines are less as they mostly carry active power. 3
  • 4. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.2, No.4, 2012 Table 2. Instantaneous power factor captured at substation B Feeder / Day Monday: Tuesday: min Wednesday: Thursday: Friday: min Saturday: Sunday: min min and max and max min and max min and max and max min and max and max (time (time (time captured) (time (time (time (time captured) captured) captured) captured) captured) captured) Transmission1 0.87 (Day) 0.87 (Day) 0.84 (Night) 0.91 (Day) 0.91 (Night) 0.89 (Day) 0.91 (Day) (Mixed loads) 0.94 (Night) 0.93 (Day) 0.92 (Night) 0.93 (Night) 0.93 (Day) 0.93 (Day) 0.94 (Night) Line 1 (Mixed 0.91 (Night) 0.87 (Day) 0.91 (Night) 0.90 (Night) 0.92 (Night) 0.91 (Night) 0.92 (Day) loads) 0.94 (Night) 0.95 (Day) 0.94 (Night) 0.95 (Day) 0.94 (Day) 0.94 (Night) 0.96 (Day) Line2 0.92 (Night) 0.88 (Day) 0.89 (Night) 0.91 (Night) 0.91 (Day) 0.91 (Day) 0.92 (Day) (Domestic ) 0.94 (Day) 0.93 (Night) 0.92 (Night) 0.93 (Night) 0.93 (Night) 0.95 (Day) 0.94 (Day) From the table 2, it is noted that transmission 1 with mixed loads and line 2 carrying mainly domestic loads have the power factor relatively below 0.9. Domestic loads reactive current are usually not compensated and hence the line has to carry that current from the source. Line 1 with mixed loads was found to have relatively low power factor during the day as compared at night. It is presumed that during the night, the compact fluorescence bulbs which are inherently associated with leading power factor improve the line power factor. Table 3. Instantaneous power factor captured at substation C Feeder / Day Monday: Tuesday: min Wednesday: Thursday: Friday: min Saturday: Sunday: min min and max and max min and max min and max and max min and max and max (time (time (time captured) (time (time (time (time captured) captured) captured) captured) captured) captured) Transmission1 0.65 (Day) 0.65 (Day) 0.65 (Night) 0.65 (Day) 0.64 (Night) 0.65 (Day) 0.64 (Day) (Domestic) 0.66 (Night) 0.68 (Night) 0.66 (Day) 0.66 (Night) 0.65 (Day) 0.65 (Night) 0.65 (Night) Line 1 0.98 (Night) 0.98 (Night) 0.98 (Both) 0.98 (Both) 0.98 (Both) 0.98 (Day) 0.98 (Day) (industrial) 0.99 (Day) 0.99 (Day) 0.98 (Both) 0.98 (Both) 0.98 (Both) 0.99 (Night) 0.99 (Night) Line 2 0.78 (Night) 0.76 (Night) 0.80 (Night) 0.78 (Night) 0.76 (Night) 0.78 (Night) 0.76 (Day) (Mixed) 0.80 (Day) 0.82 (Day) 0.82 (Day) 0.81 (Day) 0.83 (Day) 0.80 (Day) 0.80 (Night) From Table 3, transmission 1 which is dominated by domestic loads such as TV sets, fridge, air conditioners and computer was found to transmit the active power at low power factor. The technical losses on this line, 50% is due to reactive current transmitted on the conductors and transformers. These lines dominated by domestic non –linear 4
  • 5. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.2, No.4, 2012 loads usually trip due to overloaded which causes the power outage. As mentioned earlier, lines supplying industrial loads are having a good power factor as reactive power is compensated at the vicinity of demand. This is because the large power consumers are compelled to compensate the reactive power otherwise are penalized (power factor surcharge penalty). Figure 1. Varitions of power factor for a period of one day The relationship between the power factor and nature of the load from the data collected is shown as a graph in Figure (1). From figure (1), it is seen that the power factor and hence the efficiency of the line is determined by the dominant loads. Industrial loads maintain feeder power factor well above the statutory limit due to the installation of VAr compensators at the point of demand. Contrary, domestic loads cause the line to carry more reactive power hence lower the line power factor. Also, it is clear from the graph that when the feeder line is supplying mixed loads (and the domestic loads dominate the line which is mostly during the night and weekend), the line power factor is same as the line with domestic loads (two graphs intersect). 5
  • 6. This academic article was published by The International Institute for Science, Technology and Education (IISTE). The IISTE is a pioneer in the Open Access Publishing service based in the U.S. and Europe. The aim of the institute is Accelerating Global Knowledge Sharing. More information about the publisher can be found in the IISTE’s homepage: http://www.iiste.org The IISTE is currently hosting more than 30 peer-reviewed academic journals and collaborating with academic institutions around the world. Prospective authors of IISTE journals can find the submission instruction on the following page: http://www.iiste.org/Journals/ The IISTE editorial team promises to the review and publish all the qualified submissions in a fast manner. All the journals articles are available online to the readers all over the world without financial, legal, or technical barriers other than those inseparable from gaining access to the internet itself. Printed version of the journals is also available upon request of readers and authors. IISTE Knowledge Sharing Partners EBSCO, Index Copernicus, Ulrich's Periodicals Directory, JournalTOCS, PKP Open Archives Harvester, Bielefeld Academic Search Engine, Elektronische Zeitschriftenbibliothek EZB, Open J-Gate, OCLC WorldCat, Universe Digtial Library , NewJour, Google Scholar