SlideShare une entreprise Scribd logo
1  sur  46
Télécharger pour lire hors ligne
•   Coastal and offshore resource infrastructure development is occurring in a time of increasing
    reliance on our coasts and oceans to provide ecosystem services to humans – ie food, air and
    water.

•   An already strained ecosystem is at an increased risk of not delivering these ecosystem
    services to humans into the future due to factors such as climate change, population increase,
    and pollution from the increasing globalisation of society and the economy.

•   Without ecologically sustainable economic development and use of coastal and ocean energy
    resources that provides an economic buffer in transitioning to renewable energy into the
    future we cannot hope to adapt and minimise the impact of global and local environmental
    change on society.

•   The development of Environmental Plans provides for a risk-based approach to sustainability
    and the complex relationship between people, resources and the natural world that ensures
    industry is accountable for its actions in providing services to humans.

•   Under the OPGGS Act 2006, the 2009 Environment Regulations follow the Principles of
    Ecologically sustainable economic development (Reg 3). Where a petroleum activity is being
    carried out (Reg 4(1)) an EP must be submitted.




                                                                                                     1
•   The 2 main components of an EP are:
           - environmental assessment (planning phase); and
           - implementation strategy (operational phase).

•   The 2009 Regulations governing submission and acceptance of EP’s are consistent with
    system-based approaches described in AS/NZS standards ISO 14001 Environmental
    Management Systems and ISO 31000 Risk Management – Principles and Guidelines.

•   An EP should capture:
                 - a description of the activity, environment, regulations, impacts and risks and
    detail the impacts and risk of the activity. It should evaluate and demonstrate that impacts and
    risks are acceptable and reduced to               ALARP. It should define performance objectives
    and standards and measurement criteria that capture performance and monitoring
    requirements. It should include consultation, an implementation strategy and any additional
    content required.

•   The complexity of coastal and ocean resource development can be represented in Chevron’s
    Wheatstone project, bringing ashore LNG from offshore wells and associated infrastructure.

•   At every stage of exploration, construction and operation, environmental impacts have to be
    managed and the potential for significant and often cumulative adverse effects mitigated
    against.

•   Drilling, installing equipment and production facilities, seismic surveying, pipe laying,
    dredging, trenching, rock piling, or servicing and maintaining production infrastructure and its
    use - they all have an existing or potential impact on the surrounding environment.




                                                                                                       2
•   This presentation will cover (see PowerPoint)

•   The presentation focuses in particular on the regulatory environment and approvals process
    in regard to preparation, assessment and acceptance of EP’s as in force plans.

•   An EP has to demonstrate compliance with the criteria in Reg 11(1):

        (1) The Regulator must accept the environment plan if there are reasonable grounds for
        believing that the plan:
         (a) is appropriate for the nature and scale of the activity or proposed use; and
         (b) demonstrates that the environmental impacts and risks of the activity will be reduced
        to as low as reasonably practicable; and
         (c) demonstrates that the environmental impacts and risks of the activity will be of an
        acceptable level; and
         (d) provides for appropriate environmental performance objectives, environmental
        performance standards and measurement criteria; and
         (e) includes an appropriate implementation strategy and monitoring, recording and
        reporting arrangements; and
         (f) for the requirement mentioned in paragraph 16 (b) — demonstrates that:
                   (i) the operator has carried out the consultations required by Division 2.2A; and
                   (ii) the measures (if any) that the operator has adopted, or proposes to adopt,
        because of the consultations are appropriate; and
         (g) complies with the Act and the regulations.




                                                                                                       3
•   Also covered (see PowerPoint)

•   In particular, the presentation covers the components of assurance and compliance and how
    this relates to the need to demonstrate a risk-based approach to resource developments.

•   Division 2.3 of the Environment Regulations outlines the EP development process in a
    coherent and systematic way. This approach provides a strong link to risk management
    systems developed by
•   recognised bodies such as ISO and AS/NZS.

•   EP environmental assessment: The environmental assessment component of an EP is
    focused around a process to demonstrate that environmental impacts and risks are of an
    acceptable level and ALARP.

•   EP implementation strategy: The core elements are:
        1. measures to ensure environmental performance objectives and environmental
           standards are met
        2. systems, practices and procedures to ensure impacts and risks are continuously
           reduced to ALARP
        3. chain of command, including roles and responsibilities
        4. measures to ensure personnel are competent and trained
        5. provisions for monitoring, auditing, management of non-conformance and review
        6. provisions for the maintenance of accurate quantitative records of emissions and
           discharges
        7. an OSCP including emergency response and testing arrangements
        8. provisions for ongoing consultation




                                                                                                4
•   The aim of this presentation (see PowerPoint)

•   Specifically, the presentation’s objective relates to how to prepare an EP that covers off all the
    content requirements while also being structured in such a way as to meet assessment
    criteria.

•   The regulatory process and elements provide a framework that allows operators to apply a
    systematic approach to meeting the EP requirements of the Environment Regulations.

•   The EP process step to “Describe” [sub-regulations 13(1) and (2)] applies to the elements
    “activity” and “environment”. So, to meet the regulatory requirements, an EP must “Describe
    the Activity” and “Describe the Environment” as laid out in the Environment Regulations.




                                                                                                         5
•   In considering EP’s feedback on the new regulatory arrangements for EP’s, and EP’s in
    general was obtained by liaising with operator HSE specialists.

•   The approach the regulator takes in administering the regulations was also considered
    against content requirements to gain insight into how this approach impacts the activity
    operator when preparing an EP.

•   The EP process and key elements include:

        1. Describe 4(1), 5, 6, 11(1) 13(1), 13(2), 13(5): Activity, Environment, Requirements,
           Acceptable level(s)
        2. Detail 4(1), 8(1), 13(3): Impacts and risks
        3. Evaluate and demonstrate 4(1), 11(1),13(3), 13(3A), 14(3): Impacts and risks –
           acceptable level(s), Impacts and risks - ALARP
        4. Define 3(b), 4(1), 11(1), 13(4): Environmental performance objectives, Environmental
           performance standards, Measurement criteria
        5. Consultation 11(1), 11(8), 11A, 14(9), 16(b): Stakeholder consultation
        6. Implementation strategy 14

        7. Additional content requirements (Regulations 15, 16, 26, 26A, 26AA,26B, 29 &29A)
           that must be reflected in an EP.




                                                                                                  6
•   Evidence of need covers off 4 key areas, these being (see PowerPoint).

•   The Environment Regulations are:
       1. objective-based, where general requirements are provided. The operator is
           responsible for determining their approach to meeting these requirements;
       2. risk-based, where a central part of the EP is the assessment and management of the
           environmental impacts and risks of the activity;
       3. performance-based, where appropriate environmental performance objectives and
           environmental performance standards are in place that have measurement criteria to
           determine if they are being met; and
       4. system-based, where a structured risk management process is applied to developing
           the EP which shows the continual and iterative steps that are followed to assess and
           manage environmental impacts and risks effectively.

•   The operator of an activity owns the EP. NOPSEMA’s role is one of assessing and deciding to
    ‘accept’ or ‘refuse to accept’ the operator’s EP and subsequently monitoring the operator’s
    continued compliance with the EP.




                                                                                                  7
•   The object of the Environment Regulations, as set out in Regulation 3, is to ensure that
    petroleum activities are carried out in a manner that is consistent with the principles of
    ecologically sustainable
    development; and in accordance with an EP that has appropriate environmental performance
    objectives, standards and measurement criteria for determining whether the objectives and
    standards
    have been met.

•   The context behind the evidence of need to address the complexities of EP preparation and
    approaches to acceptance can be divided into 9 key points, these being (see PowerPoint).




                                                                                                 8
•   For an EP to be accepted, the operator must address the regulatory requirements in a way
    that provides NOPSEMA with reasonable grounds to believe that the requirements have
    been, or will be, met. This
    should be supported by well-documented evidence.

•   To determine if an EP meets the requirements, operators should consider:
        1.      Does the EP clearly demonstrate that the criteria in Regulation 11(1) have been
            met?
        2.      Is the demonstration supported by adequately justified statements?
        3.      Are all statements made to support the demonstration sufficiently supported by
            evidence or appropriate references, such that NOPSEMA can reasonably determine
            their accuracy and reliability?
        4.      Is a clear basis provided for environmental performance objectives, environmental
            performance standards and measurement criteria and are they appropriate to: the
            protection of the affected environment, identified environmental impacts and risks and
            their related control measures?
        5.      Are the environmental performance objectives and environmental performance
            standards specific and measurable (e.g. S.M.A.R.T. - specific, measurable,
            achievable, relevant, time-based)?
        6.      Is it clearly demonstrated how, when, where and why control measures will be
            implemented, monitored and reported against?
        7.      Does the implementation strategy include the specific systems, practices and
            procedures that describe how environmental performance will be measured over the
            life of the activity?
        8.      Does the implementation strategy clearly demonstrate the systems that are in place
            to implement, check and review activities (including management measures) in
            compliance with the EP?




                                                                                                     9
•   The types of coastal and offshore construction activities requiring an EP may consist of:
       1. Dredging – deepening shipping channels, sediment and rock piling for ports and
            wharfs, marina’s, land reclamation
       2. Trenching – burying pipelines into the seafloor, burying or overlaying coastal areas
            such as beaches, intertidal areas, mangroves
       3. Construction – infrastructure development for energy projects, wharfs, wells, pipes,
            processing, transport etc
       4. Production – various types of production including subsea, floating LNG, manned and
            unmanned WHP’s etc
       5. Seismic surveys -

•   The environmental assessment component of an EP is focused around a process to
    demonstrate that environmental impacts and risks are of an acceptable level and ALARP.
    Environmental performance objectives and environmental performance standards, and their
    measurement criteria, are defined and set respectively to ensure overall environmental
    performance is maintained at the defined acceptable and ALARP levels.

•   The implementation strategy core elements required to meet this are:
       1.    measures to ensure environmental performance objectives and environmental
           standards are met
       2.    systems, practices and procedures to ensure impacts and risks are continuously
           reduced to ALARP
       3.    chain of command, including roles and responsibilities
       4.    measures to ensure personnel are competent and trained
       5.    provisions for monitoring, auditing, management of non-conformance and review
       6.    provisions for the maintenance of accurate quantitative records of emissions and
           discharges
       7.    an OSCP including emergency response and testing arrangements
       8.    provisions for ongoing consultation




                                                                                                 10
•   All these types of activities require preparation of an EP where although the context is
    different, it has to meet the same assessment criteria.

•   Unravelling the complexity of such arrangements regarding EP content and preparation will
    assist in understanding how to simplify approaches to acceptance of an EP as an in force
    plan.

•   The Environment Regulations simply reflect the “plan – do – check – act” cycle that is the
    basis of a systematic approach to environmental management. The Environment Regulations
    provide a framework in which this basic process is conducted and are designed to ensure
    appropriate and sufficient oversight. Consequently, the Environment Regulations provide the
    basic process and critical steps against which operators need to demonstrate their
    compliance with the regulatory requirements including the “plan – do – check – act” cycle.




                                                                                                  11
•   Requirements regarding the content of an EP appear relatively straight forward at first glance
    and should include (see PowerPoint). The process for developing an EP can be described as
    having two distinct components – the environmental assessment and the implementation
    strategy.




                                                                                                     12
•   However, the manner in which an EP is prepared is not easily discernable and left to the
    operator to decide. Neither the regulations nor the regulator outlines any specific
    requirements as to the approach that should be taken in preparing or presenting the required
    content.

•   The key process steps (describe, detail, evaluate and demonstrate, define, consultation and
    implementation strategy) that are provided for in the Environment Regulations for developing
    an EP.

•   The Environment Regulations also include the particular elements that these process steps
    relate to, and which further describe the EP requirements of the Environment Regulations.




                                                                                                   13
•   The regulations do outline what an EP is assessed against, but bridging the gap between
    required content and alignment with the regulations for assessment successfully depends on
    how content is structured and presented. Here required content is covered in more detail and
    then related to document preparation for assessment.

•   Relevant Regulations Assessed Against are:
        1. Activity: 4(1) (definition of activity), 5, 6, 11(1)(a), 13(1)(a-d)
        2. Environment: 4(1) (definition of environment), 11(1)(a), 13(2) (a)(b)
        3. Other legal requirements: 13(5) (a)(b), 11(1)(a)
        4. Acceptable levels of impacts and risks: 11(1)(c) (also see section 3.6 “Evaluate and
            Demonstrate: Impacts and Risks - Acceptable Level”)
        5. Impacts and Risks: 4(1) (definition of environmental impact), 13(3)(a), 8(1)
        6. Evaluate and demonstrate impacts and risks: 4(1) (definition of environmental
            impact), 11(1)(c), 13(3)(b), 13(3A)(a)(b)
        7. Evaluate and demonstrate impacts and risk are ALARP: 11 (1) (b), 14 (3)
        8. Define Environmental Performance Objectives: 3(b)(i)(ii), 4(1) (definition of
            environment, environmental performance, environmental performance objective and
            recordable incident), 11(1)(d), 13 (4)(a)(b)(c)
        9. Define Environmental Performance Standards: 3 (b)(i)(ii), 4(1) (definition of
            environmental performance standard and recordable incident), 11(1)(d), 13
            (4)(a)(b)(c)
        10. Define Measreument Criteria: 3 (b)(i)(ii), 4(1) (definition of environmental
            performance objective and environmental performance standard), 11(1)(d), 13
            (4)(a)(b)(c)
        11. Stakeholder Consultation: 11(1)(f), 11(8)(a)(vi), 11A, 14(9), 16(b)
        12. Implementation Strategy: 14(1-10)
        13. Additional Content Requirements: 15, 16, 26, 26A, 26AA & 26B, 29, 29A




                                                                                                   14
•   Perhaps a key aspect underpinning EP content is the requirement to demonstrate
    consultation (see PowerPoint).

•   The EP must include details of the consultation conducted during the development of the EP
    [11(1)(f)] and also include a plan for ongoing consultation during the operational phase [14(9)].
        1. The EP must demonstrate that the operator has carried out the required consultations
             in the required manner [11(f)(i)].
        2. The EP must demonstrate that the measures (if any) that the operator has adopted,
             or proposes to adopt, as a result of the consultations are appropriate [11(f)(ii)].
        3. For consultation in the course of preparing the EP, the operator must consult relevant
             persons [11A].
        4. The EP must contain a report on all consultations between the operator and a
             relevant person [16(b)] and that report has specific requirements [16(b)(i-iv)].
        5. The implementation strategy must contain a plan for appropriate consultation on an
             ongoing basis with relevant stakeholders (Commonwealth, state or territory
             authorities and other interested persons
        6. or organisations) during the operational phase of the activity [14(9)].
        7. Consultation in preparation of an EP may help inform the operator about what is
             considered to be an ‘acceptable level’ of environmental impact and risk.
        8. The consultation must be appropriate for the nature and scale of the activity in that all
             persons whose functions, interests or activities may be affected by the activity must
             be consulted.




                                                                                                        15
•   The operator should consider and provide a reasonable basis for determining who they
    consider to be ‘relevant persons’ and define these in the EP. While “relevant person” is
    described in the Environment
•   Regulations, the operator must determine in the context of nature and scale of the activity,
    which persons may be relevant and whose functions, interests or activities may be affected by
    the activities
•   to be carried out under the EP.

•   Stakeholders can consist of any person, organisation, ethnic group or industry that may
    potentially be adversely affected by an activity. Examples are:
        1. Fishing industry
        2. Aquaculture industry
        3. Indigenous people
        4. Conservation groups
        5. Recreational user groups
        6. Government (matters of national interest)
        7. Public
        8. Military




                                                                                                    16
•   Of particular importance is the requirement for consultation regarding development of an Oil
    Spill Contingency Plan. Evidence of this consultation has to be shown in the preparation of an
    EP.

•   It is essential to liaise with those involved in implementing the National Plan, which is aligned
    with MARPOL requirements for spill response, escalation, and a 3-tiered approach to dealing
    with an unplanned event. This is covered in more detail later (see section 2.4.1, 2.4.2, 2.4.3).

•   In cases where it is appropriate to the nature and scale of an activity, operators could
    undertake consultation for a range of petroleum activities on a strategic basis. The submission
    for each activity
    would need to demonstrate that this action was appropriate and that each identified relevant
    person had sufficient time and information to make an informed assessment of the potential
    impacts of the
    specific activity on their functions, interests or activities.




                                                                                                        17
•   When an activity has the potential to impact on matters of national interest a referral to the
    Minister of Resources, Energy and Tourism has to be made for assessment. It is a
    requirement under the Environmental Protection, Biodiversity and Conservation Act 1999 (see
    PowerPoint).




                                                                                                     18
•   Assessments are made from (see PowerPoint).

•   The EP must describe the regulatory and other requirements that apply to the activity and are
    relevant to the environmental management of the activity. Requirements should be included
    as part of the context of the activity to help understand the regulatory and other requirements
    that may influence the way in which an activity is assessed and managed by the operator.

•   Requirements include other approvals, legislative requirements or conditions that may apply
    to the specific activity.




                                                                                                      19
•   An Environmental Impact Statement has to be prepared that addresses the effects of the
    activity or project. Key to an EIS is that it provides for alternatives and an opportunity for
    public participation or consultation. Also key is that the Minister must refer the EIS to the
    Environmental Protection Agency for assessment.

•   Activities that have the potential to impact on sensitive areas may include:
        1. Oil and Gas Exploration and production near MPA’s and Marine Park coral reefs,
             deep ocean habitats, nursery grounds etc
        2. Oil and Gas Exploration and production near whale migration routes
        3. Oil and Gas Exploration and production near turtle nesting sites
        4. Coastal processing facility development and associated wharf/port structure near
             culturally significant sites
        5. Coastal processing facility development and associated wharf/port structure near
             MPA’s or marine parks
        6. Operations near or in commercial fishing areas
        7. Vessel or facility movement and / or subsea construction biofouling and introduced
             marine pests or native invaders




                                                                                                     20
•   EP requirements could include amongst other things: relevant laws, codes, standards,
    agreements, treaties, conventions or practices that apply to the jurisdiction that the activity
    takes place in, or other
    jurisdictions, that may be relevant to the activity.

•   The description of requirements should not just be presented as a list of requirements, but
    should provide details of which requirements are relevant to the specific activity in the EP and
    how they apply to the activity. The description of requirements forms part of the context of the
    activity and influences the assessment and management of the activity, and the development
    of environmental performance objectives and environmental performance standards.

•   These requirements should be taken into account in establishing, implementing and
    maintaining environmental management of the activity. Requirements that are not relevant to
    the environmental management of the activity do not need to be included.




                                                                                                       21
•   Commonwealth environmental regulatory reform is underway to streamline the approvals
    process and provide for one application and assessment process, particularly in dealing with
    biodiversity offsetting for mining and energy development.

•   This will limit the burden on the proponent in preparing submissions for assessment and
    referral for matters of national significance.




                                                                                                   22
•   Alongside commonwealth regulatory reform the WA EPA under the Environmental Protection
    Act 1986 allows for environmental offsets to be incorporated into the EIA process as part of
    preparation of an EIS for referral. ie activities potentially impacting on matters of national
    significance can be ‘offset’.




                                                                                                     23
•   One of the most important features of an EP is the implementation strategy, which provides
    assurance to the regulator that all necessary precautions have been taken to ensure that any
    potential or existing impacts have been reduced to As Low As Reasonable Practicable
    (ALARP). As a function of this strategy the proponent has to show in any referral that they are
    able to manage such impacts.

•   The implementation strategy includes specific requirements [Reg 14 (4-10)] that must be
    addressed in the EP for the duration of the proposed activity. These include: chain of
    command, responsibilities, training
    and competence, monitoring, auditing, management of non-conformance and review of
    environmental performance and the implementation strategy, quantitative records of
    emissions and discharges, an OSCP, consultation and regulatory compliance.

•   An OSCP must be included as a component of the implementation strategy. The OSCP must
    contain specific emergency response and testing arrangements that are appropriate to the
    impacts and risk of the activity under emergency conditions.




                                                                                                      24
•   The implementation strategy must provide for appropriate consultation with relevant
    government agencies, relevant interested persons and organisations for the life of the activity
    or five-year EP review period. (see section 3.11: Consultation)

•   A critical element of this strategy is the Oil Spill Contingency Plan. Being a ‘operational’
    document it provides the necessary detail that ensures compliance with EP assessment
    criteria. An OSCP brings together a wide range of EP components, from EIA and baselines
    studies where knowledge is lacking, to Zone of Potential Impact (ZPI) modelling and
    responses to an unplanned event offshore and onshore.

•   Provisions for periodic review of environmental performance and the effectiveness of the
    implementation strategy should be detailed. This review cycle should allow the operator to
    determine if the measures, systems, practices and procedures of the implementation strategy
    have been effective in ensuring that performance objectives and environmental performance
    standards have been met and that impacts and risks are consistently being managed to
    acceptable levels and reduced to ALARP as defined in the EP.




                                                                                                      25
•   In preparing an OSCP consideration should be given to (see PowerPoint)




                                                                             26
•   Sources of spill events can be from activities where unplanned events occur, such as:

        1. A collision, grounding or foundering
        2. A well blowout
        3. A pipeline incident

•   Causes may be related to any number of events, but the circumstances surrounding them are
    always viewed from a risk and safety assessment perspective. Irrespective of the source, the
    impacts have a commonality about them that is directly related to the scale of the event.

•   Right side of the slide shows the position of the Montara blowout and associated oil slick. Left
    side shows vessel incidents and associated oil slicks. Circumstances surrounding the source
    of the event interact with the nature of the environment and determine the scale of impact.




                                                                                                       27
•   Impacts can be broadly defined as those occurring offshore and at sea and those that affect the coastline, whether
    originating from offshore, coastal or onshore.
•   Offshore: depending on the scale of the event it has the potential to affect entire food webs. For example the
    Montara blowout cumulative impact on the environment was the size of the state of West Virginia. Over such broad
    spatial scales Oil type, toxicity (PAH’s), viscosity, specific gravity, aging and weathering have significant implications
    for the degree of temporal impact (impact over time) on localised offshore primary production and flora and fauna.
•   Impacts of a major event include:
        1. Transient fish, invertebrate, turtle and mammal populations can be smothered, gill fouled and/or ingest
              weathered oil.
        2. Consumption and accumulation up the food chain can occur – localised collapse of food web due to
              inhibition of primary production because of photoinhibition and altered behaviour (phytoplankton and
              zooplankton populations).
        3. Deep ocean impacts from event aged fuel breakup and deposition to the deep ocean seafloor via the
              carbon cycle.
        4. Abundance in biogenic sediments and accumulation through benthic primary producer food chain in deep
              ocean habitats – effect unknown.
        5. Upwelling and re suspension due to seasonal cycling, long term disruption to food webs and trophic
              structure across broad spatial scales.




                                                                                                                                 28
•   Onshore: impacts onshore are immediately more obvious and pronounced and can be initially
    related to smothering of marine fauna and flora. Initial impact of uptake of toxic PAH’s on
    aquatic health depends on the rate of weathering and type of organism. Ie filter feeder,
    infauna, epibenthic, carnivore, herbivore and whether they are a bird, mammal, crustacean,
    mollusc, echinoderm etc and the manner in which they reproduce (broadcast spawner,
    brooder, etc).

•   Different habitats will mediate an organisms response to an oil slick and may include:
         1. Surf zone beaches – accumulation through successive tidal cycles, increased
            breakup and aging, smothering and seeping into sub layers of sand.
         2. Rocky coastline – topographically complex means accumulation of weathered oil is
            more difficult to get rid of and effects may be long-lasting in this regard.
         3. Mangroves – almost impossible to remove trapped oil without removing forest.
            Breakdown may be faster though because of the nature of mangroves and
            entrapment and binding up of sediment.
         4. Harbour and other estuaries – ecologically very sensitive, especially if already heavily
            modified due to anthropogenic activities. Oil can become trapped between tidal cycles
            and never wash out, depending on degree of flushing.

•   Long-term impacts include the sub-lethal and chronic effect of toxicity (PAH’s and endocrine
    disruption), reproductive inhibition, and recruitment failure, population change and dislocation.
    Often unintended consequences occur ie larval supply to other unaffected areas etc, or
    nursery grounds for local populations wiped out, esp. fish.




                                                                                                        29
•   A key aspect of preparing an EP is to show how an activity will be monitored and how any
    potential impact will be assessed. To meet this requirement it is essential that the risk
    assessment process has been addressed in preparing the EP and that evidence of this has
    been provided. Measurement criteria must be developed and standards also developed to
    demonstrate compliance with the EP and its requirements.

•   Some operators may integrate the preparation of an EP within an existing Environmental
    Management System (EMS) and its certification or development under ISO14001.

•   ISO 14001 is an internationally accepted standard that sets out how you can go about putting
    in place an effective Environmental Management System (EMS). The standard is designed to
    address the delicate balance between maintaining profitability and reducing environmental
    impact; with the commitment of the entire organization, it can enable the achievement of both
    objectives.

•   What’s in ISO 14001:

        1.   General requirements
        2.   Environmental policy
        3.   Planning implementation and operation
        4.   Checking and corrective action
        5.   Management review




                                                                                                    30
•   The risk assessment process is in alignment with AS/NZS ISO31000 which replaces AS/NZS
    4360. Risk assessment has to include identifying the risks, analysing likelihood and
    consequence, prioritising the risks, and risk treatment.

•   It is a requirement by NOPSEMA for environmental risk assessment to address both inherent
    risk with no controls in place and to show that the post-treatment risk has been reduced to
    tolerable or with additional controls in place to As Low As Reasonable Practicable (ALARP).

•   A great software programme now available to achieve this is PHA Pro 8, which allows the
    user to enter a risk matrix which is then linked to the spreadsheet used during a workshop.




                                                                                                  31
•   Risk is defined as the ‘effect of uncertainty on objectives’ (AS/NZS ISO 31000:2009). The
    objectives can be financial, health and safety, environmental and so on. The risk management
    process involves the following steps, as given in ISO 31000:2009:

        1. setting objectives and establishing the context of the risk assessment;
        2. identifying the risks;
        3. analysing the risks to determine the level of risk, which is defined as the combination
           of the consequences and likelihood of the risk;
        4. evaluating the risk, to decide if a risk is acceptable, tolerable or intolerable /
           unacceptable;
        5. treating the risks, focusing on those risks which are intolerable; and
        6. monitoring and review, to continuously refine and improve the assessment and risk
           treatments.




                                                                                                     32
•   A typical risk matrix against which activities are assessed consists of:

        1. A scale of severity and associated consequences in terms of people, property and the
           environment
        2. A scale of the frequency of occurrence with associated definitions
        3. The response matrix showing whether the risk is low/tolerable, medium/ALARP, or
           high/intolerable

•   Provisions for monitoring environmental performance and the implementation strategy against
    performance standards and objectives identified through the risk assessment process
    throughout the operational phase of the activity must be included. Monitoring should be
    sufficient to identify deviation in environmental performance from the levels set in the EP. The
    frequency and type of monitoring should be appropriate to the nature and scale of the activity.




                                                                                                       33
•   Monitoring programmes need to address both the potential for proximate operational
    environmental impacts while providing assurance that in the event of a major spill or other
    event the wider environment has been considered.

•   A monitoring plan needs to take into account the potential for spills to come ashore, account
    for lack of information by conducting baseline studies, and providing for ongoing monitoring. It
    also has to consider that in the event of a spill a rapid response survey can be conducted both
    in proximity to the spill and other areas where a spill is likely to come ashore.

•   Real time monitoring is also crucial, especially in terms of met-ocean data, and modelling and
    prediction of downstream events and impacts from a spill.




                                                                                                       34
•   Baseline studies and modelling requires careful consideration of sampling and survey design
    to achieve a balance between reliability and cost.

•   Before, After, Control, Impact designs optimise the opportunity to detect any potential
    environmental impact, the details of which are the subject of an entirely separate seminar.

•   Needless to say that the natural world is full of background ‘noise’, which can easily mask the
    ability to detect impacts if sampling designs do not adequately account for this ‘noise’.

•   The chance of false negatives is relatively high and requires rigorous power analysis and
    testing to minimise or limit this from occurring should a result show no impact. ie there really
    was NO impact!

•   A complimentary sampling regime may involve real time integrated monitoring, which
    provides a rigorous picture of an area over time but may have limited use spatially depending
    on cost. However, it may be quite useful for operational monitoring.




                                                                                                       35
•   Advances in Radiotelemetry mean technology, hardware, and software is becoming available
    to use remotely for real time monitoring in environments that are often difficult to work in.

•   May involve time-lapse video of the seafloor and water column, sensors for sampling water
    parameters, sea surface variables, seabed shifts and disturbance etc.

•   Able to detect changes in habitat composition, community composition, fauna behaviour,
    seawater nutrient levels, turbidity and current, seawater chemical composition etc.




                                                                                                    36
•   All arriving international vessels are required to manage their ballast water in accordance with
    the Australian ballast water management requirements. The DAFF website provides further
    information to assist operators comply with the requirements.

•   A comprehensive set of domestic ballast water management arrangements are being
    developed under the National System to complement the existing requirements for
    international vessels. These arrangements will be consistent with the International Maritime
    Organization’s International Convention for the Control and Management of Ships' Ballast
    Water and Sediments, which Australia has signed subject to ratification.

•   The risk of the petroleum production and exploration industry spreading marine pests is
    highest when vessels, immersible equipment and infrastructure:
        1. are heavily biofouled and organisms such as mussels, oysters, seaweeds and
            seasquirts are visible
        2. are moved to a new area after spending long periods either stationary or at low
            speeds (including undergoing dockside upgrades)
        3. have areas without antifouling coating or the coating is inappropriate for vessel use,
            aged or worn.




                                                                                                       37
•   Risk can be reduced by incorporating practices that minimise the build up of biofouling into your routine
    cleaning and maintenance programs. The 'National biofouling management guidance for the petroleum
    production and exploration industry' document outlines practical recommendations for operators on
    managing biofouling on petroleum related vessels, equipment and infrastructure. These
    recommendations have been developed in conjunction with the petroleum production and exploration
    industry and apply to the following vessel types:

        1.   offshore support vessels including utility support vessels, platform supply vessels and anchor
             handling tug supply vessels
        2.   mobile offshore drilling units including jack-up units, drilling barges and semi-submersible ships
        3.   crew transfer vessels
        4.   diving support vessels
        5.   accommodation vessels
        6.   seismic survey vessels
        7.   landing craft
        8.   pipelay ships and barges
        9.   floating production, storage and offloading vessels (FPSO) and floating storage and offloading
             vessels (FSO).

•   Operators of oil tankers and gas carriers should refer to the 'National biofouling management guidelines
    for commercial vessels' for guidance on managing biofouling. Operators of heavy lift vessels and
    dredges (including rock dumping ships) should refer to the 'National biofouling management guidance
    for non-trading vessels' for further information on managing biofouling. The 'National biofouling
    management guidance for the petroleum production and exploration industry' also inlcudes information
    on biofouling management of submersible equipment and infrastructure.




                                                                                                                  38
•   Monitoring programmes may consider:
       1. Permanent sea surface sensors
       2. Permanent satellites and GIS
       3. Permanent seafloor sensors
       4. Water column deployed and towed equipment
       5. Periodic remote surveys
       6. Periodic surveys
       7. Predictive modelling
       8. Structures, fouling and marine pest management




                                                           39
•   Key elements contributing to an EP need to be bought together in a coherent and succinct
    manner for submission and assessment against the regulations and acceptance as an ‘in
    force’ plan.




                                                                                               40
•   Key in preparing the EP structure is to provide evidence of assurance and compliance (see
    PowerPoint).
•   Provisions for management of non-conformance must also be detailed in the implementation
    strategy.
•   These provisions should allow sufficient information to be collected to fulfil regulatory
    requirements for reporting of recordable and reportable incidents to the regulator and to
    ensure that any corrective and preventative actions are implemented.
•   Provisions for periodic review of environmental performance and the effectiveness of the
    implementation strategy should be detailed.
•   This review cycle should allow the operator to determine if the measures, systems, practices
    and procedures of the implementation strategy have been effective in ensuring that
    performance objectives and environmental performance standards have been met and that
    impacts and risks are consistently being managed to acceptable levels and reduced to
    ALARP as defined in the EP.




                                                                                                   41
•   To recap on the regulations, the key to successful assessment is under division 2.2 and 2.3 of
    the 2009 regulations (see PowerPoint). Key aspects related to successful assessment also
    include:
         1. The EP must include arrangements for recording, monitoring and reporting a
             sufficient level of information to allow the operator to demonstrate to the regulator that
             all of the environmental performance objectives and environmental performance
             standards in the EP have been met.
         2. Reporting arrangements must address reportable incidents, recordable incidents and
             routine environmental performance reporting.
         3. The EP must include details of all the reportable environmental incidents that may
             arise from the proposed activity.
         4. Intervals for environmental performance reporting in accordance with the Regulations
             must be provided in the EP such that they can be agreed to by the regulator.
         5. he EP must detail the arrangements put in place by the operator for notification of the
             relevant state or territory minister of the commencement of drilling or seismic survey
             activities if those activities may       have an effect on a community in the activity
             area.
         6. The EP must contain a statement of the operator’s corporate environmental policy.
         7. The EP must contain a report on consultations (see section 3.11: Consultation).
         8. The EP must address the specific requirements for the discharge and testing of
             produced formation water.




                                                                                                          42
•   In bringing these elements together, the assessment criteria and regulations can be matched
    against submission structure by following the Safety Case Approach to submissions and
    approvals (see PowerPoint).




                                                                                                  43
44
45
•   What does the future hold:

•   Alignment with EMS ISO 14001 both from a regulator and operator perspective. Future
    legislation and government policy objectives may seek to reflect this arrangement.

•   Environmental impact is becoming an increasingly important issue across the globe, with
    pressure to minimize that impact coming from a number of sources: local and national
    governments, regulators, trade associations, customers, employees and shareholders. Social
    pressures are also building up from the growing array of interested parties, such as
    consumer, environmental and minority non-governmental organizations (NGOs), academia
    and neighbours.

•   So ISO 14001 is relevant to every organization, including:
        1. Single site to large multi-national companies
        2. High risk companies to low risk service organizations
        3. Manufacturing, process and the service industries; including local governments
        4. All industry sectors including public and private sectors
        5. Original equipment manufacturers and their suppliers




                                                                                                 46

Contenu connexe

Tendances

A Critical Post Operational Review: Environmental Impact Assessment for Jebel...
A Critical Post Operational Review: Environmental Impact Assessment for Jebel...A Critical Post Operational Review: Environmental Impact Assessment for Jebel...
A Critical Post Operational Review: Environmental Impact Assessment for Jebel...Hydrologic Science, llc.
 
Misa Going Green V3
Misa Going Green V3Misa Going Green V3
Misa Going Green V3kmayfield
 
Srivastav, Piyush, NAQS Environmental Experts, Crash Course in PSD Permitting...
Srivastav, Piyush, NAQS Environmental Experts, Crash Course in PSD Permitting...Srivastav, Piyush, NAQS Environmental Experts, Crash Course in PSD Permitting...
Srivastav, Piyush, NAQS Environmental Experts, Crash Course in PSD Permitting...Kevin Perry
 
Sustainable Management Criteria BMP December 2017
Sustainable Management Criteria BMP December 2017Sustainable Management Criteria BMP December 2017
Sustainable Management Criteria BMP December 2017Val King
 
14 epi-e-dn v.1.01(draft)
14 epi-e-dn v.1.01(draft)14 epi-e-dn v.1.01(draft)
14 epi-e-dn v.1.01(draft)Paul Robere
 
November 05 Luncheon Talk
November 05 Luncheon TalkNovember 05 Luncheon Talk
November 05 Luncheon Talkcpans
 
Evaluating and Developing of Water Resources Quality Monitoring Program Imple...
Evaluating and Developing of Water Resources Quality Monitoring Program Imple...Evaluating and Developing of Water Resources Quality Monitoring Program Imple...
Evaluating and Developing of Water Resources Quality Monitoring Program Imple...IJERD Editor
 
8.3.4 Subnational adaptation
8.3.4 Subnational adaptation8.3.4 Subnational adaptation
8.3.4 Subnational adaptationNAP Events
 

Tendances (12)

Environmental Quality Assurance -- a primer
Environmental Quality Assurance -- a primerEnvironmental Quality Assurance -- a primer
Environmental Quality Assurance -- a primer
 
A Critical Post Operational Review: Environmental Impact Assessment for Jebel...
A Critical Post Operational Review: Environmental Impact Assessment for Jebel...A Critical Post Operational Review: Environmental Impact Assessment for Jebel...
A Critical Post Operational Review: Environmental Impact Assessment for Jebel...
 
Misa Going Green V3
Misa Going Green V3Misa Going Green V3
Misa Going Green V3
 
Srivastav, Piyush, NAQS Environmental Experts, Crash Course in PSD Permitting...
Srivastav, Piyush, NAQS Environmental Experts, Crash Course in PSD Permitting...Srivastav, Piyush, NAQS Environmental Experts, Crash Course in PSD Permitting...
Srivastav, Piyush, NAQS Environmental Experts, Crash Course in PSD Permitting...
 
Sustainable Management Criteria BMP December 2017
Sustainable Management Criteria BMP December 2017Sustainable Management Criteria BMP December 2017
Sustainable Management Criteria BMP December 2017
 
14 epi-e-dn v.1.01(draft)
14 epi-e-dn v.1.01(draft)14 epi-e-dn v.1.01(draft)
14 epi-e-dn v.1.01(draft)
 
November 05 Luncheon Talk
November 05 Luncheon TalkNovember 05 Luncheon Talk
November 05 Luncheon Talk
 
Evaluating and Developing of Water Resources Quality Monitoring Program Imple...
Evaluating and Developing of Water Resources Quality Monitoring Program Imple...Evaluating and Developing of Water Resources Quality Monitoring Program Imple...
Evaluating and Developing of Water Resources Quality Monitoring Program Imple...
 
dairy_peir_final_cert
dairy_peir_final_certdairy_peir_final_cert
dairy_peir_final_cert
 
8.3.4 Subnational adaptation
8.3.4 Subnational adaptation8.3.4 Subnational adaptation
8.3.4 Subnational adaptation
 
Reclamation Requirements
Reclamation RequirementsReclamation Requirements
Reclamation Requirements
 
EMS Clause 4.5
EMS Clause 4.5EMS Clause 4.5
EMS Clause 4.5
 

En vedette

4. act. aprendizaje teniendo claro el problema slide share
4. act. aprendizaje  teniendo claro el problema slide share4. act. aprendizaje  teniendo claro el problema slide share
4. act. aprendizaje teniendo claro el problema slide sharepromocioncomunitaria
 
Exposición solar en trabajos rurales
Exposición solar en trabajos ruralesExposición solar en trabajos rurales
Exposición solar en trabajos ruralesmerycre
 
Rapport taga fait à charny 2001
Rapport taga fait à charny 2001Rapport taga fait à charny 2001
Rapport taga fait à charny 2001CleanUpSanimax
 
Tecnología e informática
Tecnología e informáticaTecnología e informática
Tecnología e informáticaRosmery Cardona
 
Meet the teacher pp
Meet the teacher ppMeet the teacher pp
Meet the teacher ppjmilne7
 
Carl bozzuto seminar
Carl bozzuto seminarCarl bozzuto seminar
Carl bozzuto seminarirvn82
 
303013 2 act_2_reconocimiento_unidad_1
303013 2 act_2_reconocimiento_unidad_1303013 2 act_2_reconocimiento_unidad_1
303013 2 act_2_reconocimiento_unidad_1jcorreat
 
Power point presentation of sar
Power point presentation of sarPower point presentation of sar
Power point presentation of sarHemlata Singh
 
Estado Bolivar
Estado BolivarEstado Bolivar
Estado Bolivarkte_fabity
 
E tutorial - tax payer registration and login
E tutorial - tax payer registration and loginE tutorial - tax payer registration and login
E tutorial - tax payer registration and loginPSPCL
 
Geneticahumana 090327125556-phpapp01
Geneticahumana 090327125556-phpapp01Geneticahumana 090327125556-phpapp01
Geneticahumana 090327125556-phpapp01Elton Volitzki
 
Transmision neuromuscular y acoplamiento excitacion contracción - semana 2
Transmision neuromuscular y acoplamiento excitacion  contracción - semana 2Transmision neuromuscular y acoplamiento excitacion  contracción - semana 2
Transmision neuromuscular y acoplamiento excitacion contracción - semana 2JAIME ANDRES GUTIERREZ QUINTERO
 
Event Management Plan
Event Management PlanEvent Management Plan
Event Management PlanNatia Seegars
 
Detección de Necesidades de Capacitación
Detección de Necesidades de CapacitaciónDetección de Necesidades de Capacitación
Detección de Necesidades de CapacitaciónHek Rod
 
La plataforma fracking ez araba llama a movilizarse el 21 de febrero a las 11...
La plataforma fracking ez araba llama a movilizarse el 21 de febrero a las 11...La plataforma fracking ez araba llama a movilizarse el 21 de febrero a las 11...
La plataforma fracking ez araba llama a movilizarse el 21 de febrero a las 11...Crónicas del despojo
 

En vedette (20)

4. act. aprendizaje teniendo claro el problema slide share
4. act. aprendizaje  teniendo claro el problema slide share4. act. aprendizaje  teniendo claro el problema slide share
4. act. aprendizaje teniendo claro el problema slide share
 
Exposición solar en trabajos rurales
Exposición solar en trabajos ruralesExposición solar en trabajos rurales
Exposición solar en trabajos rurales
 
Gbi
GbiGbi
Gbi
 
La informatica
La informaticaLa informatica
La informatica
 
Rapport taga fait à charny 2001
Rapport taga fait à charny 2001Rapport taga fait à charny 2001
Rapport taga fait à charny 2001
 
Tecnología e informática
Tecnología e informáticaTecnología e informática
Tecnología e informática
 
Tuto anillos
Tuto anillosTuto anillos
Tuto anillos
 
Meet the teacher pp
Meet the teacher ppMeet the teacher pp
Meet the teacher pp
 
Carl bozzuto seminar
Carl bozzuto seminarCarl bozzuto seminar
Carl bozzuto seminar
 
303013 2 act_2_reconocimiento_unidad_1
303013 2 act_2_reconocimiento_unidad_1303013 2 act_2_reconocimiento_unidad_1
303013 2 act_2_reconocimiento_unidad_1
 
Contracción del musculo esquelético semana 2
Contracción del musculo esquelético   semana 2Contracción del musculo esquelético   semana 2
Contracción del musculo esquelético semana 2
 
Power point presentation of sar
Power point presentation of sarPower point presentation of sar
Power point presentation of sar
 
Estado Bolivar
Estado BolivarEstado Bolivar
Estado Bolivar
 
E tutorial - tax payer registration and login
E tutorial - tax payer registration and loginE tutorial - tax payer registration and login
E tutorial - tax payer registration and login
 
Geneticahumana 090327125556-phpapp01
Geneticahumana 090327125556-phpapp01Geneticahumana 090327125556-phpapp01
Geneticahumana 090327125556-phpapp01
 
Transmision neuromuscular y acoplamiento excitacion contracción - semana 2
Transmision neuromuscular y acoplamiento excitacion  contracción - semana 2Transmision neuromuscular y acoplamiento excitacion  contracción - semana 2
Transmision neuromuscular y acoplamiento excitacion contracción - semana 2
 
Event Management Plan
Event Management PlanEvent Management Plan
Event Management Plan
 
Contracción y excitación del músculo liso semana 2
Contracción y excitación del músculo liso   semana 2Contracción y excitación del músculo liso   semana 2
Contracción y excitación del músculo liso semana 2
 
Detección de Necesidades de Capacitación
Detección de Necesidades de CapacitaciónDetección de Necesidades de Capacitación
Detección de Necesidades de Capacitación
 
La plataforma fracking ez araba llama a movilizarse el 21 de febrero a las 11...
La plataforma fracking ez araba llama a movilizarse el 21 de febrero a las 11...La plataforma fracking ez araba llama a movilizarse el 21 de febrero a las 11...
La plataforma fracking ez araba llama a movilizarse el 21 de febrero a las 11...
 

Similaire à Accompanying notes for ep seminar presentation version 2 morgan mar 2013

EMP Procedure in Malaysia_32.pdf
EMP Procedure in Malaysia_32.pdfEMP Procedure in Malaysia_32.pdf
EMP Procedure in Malaysia_32.pdfliyana239733
 
Ep seminar presentation version 2 morgan mar 2013
Ep seminar presentation version 2 morgan mar 2013Ep seminar presentation version 2 morgan mar 2013
Ep seminar presentation version 2 morgan mar 2013Andrew Morgan
 
UNIT – I ptpg final (2).ppt
UNIT – I ptpg final (2).pptUNIT – I ptpg final (2).ppt
UNIT – I ptpg final (2).pptkrpnath1
 
Llb i el u 4.3 environment audit
Llb i el u 4.3 environment auditLlb i el u 4.3 environment audit
Llb i el u 4.3 environment auditRai University
 
Project hse plan kikeh spar
Project hse plan kikeh sparProject hse plan kikeh spar
Project hse plan kikeh sparAbdul Yusof
 
Green Building and Technology Unit 3
Green Building and Technology Unit 3Green Building and Technology Unit 3
Green Building and Technology Unit 3Chaitanya Nagare
 
ENVIRONMENTAL COMPLIANCE AUDITS TAILORED FOR UGANDA: NAVIGATING ENVIRONMENTAL...
ENVIRONMENTAL COMPLIANCE AUDITS TAILORED FOR UGANDA: NAVIGATING ENVIRONMENTAL...ENVIRONMENTAL COMPLIANCE AUDITS TAILORED FOR UGANDA: NAVIGATING ENVIRONMENTAL...
ENVIRONMENTAL COMPLIANCE AUDITS TAILORED FOR UGANDA: NAVIGATING ENVIRONMENTAL...Semakula Allan Kinene
 
Environment management system series ISO 14000
Environment management system series ISO 14000Environment management system series ISO 14000
Environment management system series ISO 14000Shubham Inder
 
ENVIRONMENTAL AUDITING
ENVIRONMENTAL AUDITINGENVIRONMENTAL AUDITING
ENVIRONMENTAL AUDITINGJames Nyaga
 
LIFE CYCLE ASSESSMENT POWERPOINT SLIDES. PPT
LIFE CYCLE ASSESSMENT POWERPOINT SLIDES. PPTLIFE CYCLE ASSESSMENT POWERPOINT SLIDES. PPT
LIFE CYCLE ASSESSMENT POWERPOINT SLIDES. PPTThinagaranNManiam1
 
ISO14001 KCR
ISO14001 KCRISO14001 KCR
ISO14001 KCRGary Wong
 
Environmentalaudit 121004114859-phpapp02(2)
Environmentalaudit 121004114859-phpapp02(2)Environmentalaudit 121004114859-phpapp02(2)
Environmentalaudit 121004114859-phpapp02(2)AlfredTakuraGijima
 

Similaire à Accompanying notes for ep seminar presentation version 2 morgan mar 2013 (20)

EMP Procedure in Malaysia_32.pdf
EMP Procedure in Malaysia_32.pdfEMP Procedure in Malaysia_32.pdf
EMP Procedure in Malaysia_32.pdf
 
Ep seminar presentation version 2 morgan mar 2013
Ep seminar presentation version 2 morgan mar 2013Ep seminar presentation version 2 morgan mar 2013
Ep seminar presentation version 2 morgan mar 2013
 
EIA process
EIA processEIA process
EIA process
 
Module2
Module2 Module2
Module2
 
UNIT – I ptpg final (2).ppt
UNIT – I ptpg final (2).pptUNIT – I ptpg final (2).ppt
UNIT – I ptpg final (2).ppt
 
Llb i el u 4.3 environment audit
Llb i el u 4.3 environment auditLlb i el u 4.3 environment audit
Llb i el u 4.3 environment audit
 
Project hse plan kikeh spar
Project hse plan kikeh sparProject hse plan kikeh spar
Project hse plan kikeh spar
 
Green Building and Technology Unit 3
Green Building and Technology Unit 3Green Building and Technology Unit 3
Green Building and Technology Unit 3
 
ems.ppt
ems.pptems.ppt
ems.ppt
 
ENVIRONMENTAL COMPLIANCE AUDITS TAILORED FOR UGANDA: NAVIGATING ENVIRONMENTAL...
ENVIRONMENTAL COMPLIANCE AUDITS TAILORED FOR UGANDA: NAVIGATING ENVIRONMENTAL...ENVIRONMENTAL COMPLIANCE AUDITS TAILORED FOR UGANDA: NAVIGATING ENVIRONMENTAL...
ENVIRONMENTAL COMPLIANCE AUDITS TAILORED FOR UGANDA: NAVIGATING ENVIRONMENTAL...
 
Environmental Audit
Environmental AuditEnvironmental Audit
Environmental Audit
 
Environment management system series ISO 14000
Environment management system series ISO 14000Environment management system series ISO 14000
Environment management system series ISO 14000
 
Ecw 579 week 13
Ecw 579 week 13Ecw 579 week 13
Ecw 579 week 13
 
ENVIRONMENTAL AUDITING
ENVIRONMENTAL AUDITINGENVIRONMENTAL AUDITING
ENVIRONMENTAL AUDITING
 
LIFE CYCLE ASSESSMENT POWERPOINT SLIDES. PPT
LIFE CYCLE ASSESSMENT POWERPOINT SLIDES. PPTLIFE CYCLE ASSESSMENT POWERPOINT SLIDES. PPT
LIFE CYCLE ASSESSMENT POWERPOINT SLIDES. PPT
 
ISO14001 KCR
ISO14001 KCRISO14001 KCR
ISO14001 KCR
 
EIA Process
EIA ProcessEIA Process
EIA Process
 
eia.ppt
eia.ppteia.ppt
eia.ppt
 
eia.ppt
eia.ppteia.ppt
eia.ppt
 
Environmentalaudit 121004114859-phpapp02(2)
Environmentalaudit 121004114859-phpapp02(2)Environmentalaudit 121004114859-phpapp02(2)
Environmentalaudit 121004114859-phpapp02(2)
 

Accompanying notes for ep seminar presentation version 2 morgan mar 2013

  • 1. Coastal and offshore resource infrastructure development is occurring in a time of increasing reliance on our coasts and oceans to provide ecosystem services to humans – ie food, air and water. • An already strained ecosystem is at an increased risk of not delivering these ecosystem services to humans into the future due to factors such as climate change, population increase, and pollution from the increasing globalisation of society and the economy. • Without ecologically sustainable economic development and use of coastal and ocean energy resources that provides an economic buffer in transitioning to renewable energy into the future we cannot hope to adapt and minimise the impact of global and local environmental change on society. • The development of Environmental Plans provides for a risk-based approach to sustainability and the complex relationship between people, resources and the natural world that ensures industry is accountable for its actions in providing services to humans. • Under the OPGGS Act 2006, the 2009 Environment Regulations follow the Principles of Ecologically sustainable economic development (Reg 3). Where a petroleum activity is being carried out (Reg 4(1)) an EP must be submitted. 1
  • 2. The 2 main components of an EP are: - environmental assessment (planning phase); and - implementation strategy (operational phase). • The 2009 Regulations governing submission and acceptance of EP’s are consistent with system-based approaches described in AS/NZS standards ISO 14001 Environmental Management Systems and ISO 31000 Risk Management – Principles and Guidelines. • An EP should capture: - a description of the activity, environment, regulations, impacts and risks and detail the impacts and risk of the activity. It should evaluate and demonstrate that impacts and risks are acceptable and reduced to ALARP. It should define performance objectives and standards and measurement criteria that capture performance and monitoring requirements. It should include consultation, an implementation strategy and any additional content required. • The complexity of coastal and ocean resource development can be represented in Chevron’s Wheatstone project, bringing ashore LNG from offshore wells and associated infrastructure. • At every stage of exploration, construction and operation, environmental impacts have to be managed and the potential for significant and often cumulative adverse effects mitigated against. • Drilling, installing equipment and production facilities, seismic surveying, pipe laying, dredging, trenching, rock piling, or servicing and maintaining production infrastructure and its use - they all have an existing or potential impact on the surrounding environment. 2
  • 3. This presentation will cover (see PowerPoint) • The presentation focuses in particular on the regulatory environment and approvals process in regard to preparation, assessment and acceptance of EP’s as in force plans. • An EP has to demonstrate compliance with the criteria in Reg 11(1): (1) The Regulator must accept the environment plan if there are reasonable grounds for believing that the plan: (a) is appropriate for the nature and scale of the activity or proposed use; and (b) demonstrates that the environmental impacts and risks of the activity will be reduced to as low as reasonably practicable; and (c) demonstrates that the environmental impacts and risks of the activity will be of an acceptable level; and (d) provides for appropriate environmental performance objectives, environmental performance standards and measurement criteria; and (e) includes an appropriate implementation strategy and monitoring, recording and reporting arrangements; and (f) for the requirement mentioned in paragraph 16 (b) — demonstrates that: (i) the operator has carried out the consultations required by Division 2.2A; and (ii) the measures (if any) that the operator has adopted, or proposes to adopt, because of the consultations are appropriate; and (g) complies with the Act and the regulations. 3
  • 4. Also covered (see PowerPoint) • In particular, the presentation covers the components of assurance and compliance and how this relates to the need to demonstrate a risk-based approach to resource developments. • Division 2.3 of the Environment Regulations outlines the EP development process in a coherent and systematic way. This approach provides a strong link to risk management systems developed by • recognised bodies such as ISO and AS/NZS. • EP environmental assessment: The environmental assessment component of an EP is focused around a process to demonstrate that environmental impacts and risks are of an acceptable level and ALARP. • EP implementation strategy: The core elements are: 1. measures to ensure environmental performance objectives and environmental standards are met 2. systems, practices and procedures to ensure impacts and risks are continuously reduced to ALARP 3. chain of command, including roles and responsibilities 4. measures to ensure personnel are competent and trained 5. provisions for monitoring, auditing, management of non-conformance and review 6. provisions for the maintenance of accurate quantitative records of emissions and discharges 7. an OSCP including emergency response and testing arrangements 8. provisions for ongoing consultation 4
  • 5. The aim of this presentation (see PowerPoint) • Specifically, the presentation’s objective relates to how to prepare an EP that covers off all the content requirements while also being structured in such a way as to meet assessment criteria. • The regulatory process and elements provide a framework that allows operators to apply a systematic approach to meeting the EP requirements of the Environment Regulations. • The EP process step to “Describe” [sub-regulations 13(1) and (2)] applies to the elements “activity” and “environment”. So, to meet the regulatory requirements, an EP must “Describe the Activity” and “Describe the Environment” as laid out in the Environment Regulations. 5
  • 6. In considering EP’s feedback on the new regulatory arrangements for EP’s, and EP’s in general was obtained by liaising with operator HSE specialists. • The approach the regulator takes in administering the regulations was also considered against content requirements to gain insight into how this approach impacts the activity operator when preparing an EP. • The EP process and key elements include: 1. Describe 4(1), 5, 6, 11(1) 13(1), 13(2), 13(5): Activity, Environment, Requirements, Acceptable level(s) 2. Detail 4(1), 8(1), 13(3): Impacts and risks 3. Evaluate and demonstrate 4(1), 11(1),13(3), 13(3A), 14(3): Impacts and risks – acceptable level(s), Impacts and risks - ALARP 4. Define 3(b), 4(1), 11(1), 13(4): Environmental performance objectives, Environmental performance standards, Measurement criteria 5. Consultation 11(1), 11(8), 11A, 14(9), 16(b): Stakeholder consultation 6. Implementation strategy 14 7. Additional content requirements (Regulations 15, 16, 26, 26A, 26AA,26B, 29 &29A) that must be reflected in an EP. 6
  • 7. Evidence of need covers off 4 key areas, these being (see PowerPoint). • The Environment Regulations are: 1. objective-based, where general requirements are provided. The operator is responsible for determining their approach to meeting these requirements; 2. risk-based, where a central part of the EP is the assessment and management of the environmental impacts and risks of the activity; 3. performance-based, where appropriate environmental performance objectives and environmental performance standards are in place that have measurement criteria to determine if they are being met; and 4. system-based, where a structured risk management process is applied to developing the EP which shows the continual and iterative steps that are followed to assess and manage environmental impacts and risks effectively. • The operator of an activity owns the EP. NOPSEMA’s role is one of assessing and deciding to ‘accept’ or ‘refuse to accept’ the operator’s EP and subsequently monitoring the operator’s continued compliance with the EP. 7
  • 8. The object of the Environment Regulations, as set out in Regulation 3, is to ensure that petroleum activities are carried out in a manner that is consistent with the principles of ecologically sustainable development; and in accordance with an EP that has appropriate environmental performance objectives, standards and measurement criteria for determining whether the objectives and standards have been met. • The context behind the evidence of need to address the complexities of EP preparation and approaches to acceptance can be divided into 9 key points, these being (see PowerPoint). 8
  • 9. For an EP to be accepted, the operator must address the regulatory requirements in a way that provides NOPSEMA with reasonable grounds to believe that the requirements have been, or will be, met. This should be supported by well-documented evidence. • To determine if an EP meets the requirements, operators should consider: 1. Does the EP clearly demonstrate that the criteria in Regulation 11(1) have been met? 2. Is the demonstration supported by adequately justified statements? 3. Are all statements made to support the demonstration sufficiently supported by evidence or appropriate references, such that NOPSEMA can reasonably determine their accuracy and reliability? 4. Is a clear basis provided for environmental performance objectives, environmental performance standards and measurement criteria and are they appropriate to: the protection of the affected environment, identified environmental impacts and risks and their related control measures? 5. Are the environmental performance objectives and environmental performance standards specific and measurable (e.g. S.M.A.R.T. - specific, measurable, achievable, relevant, time-based)? 6. Is it clearly demonstrated how, when, where and why control measures will be implemented, monitored and reported against? 7. Does the implementation strategy include the specific systems, practices and procedures that describe how environmental performance will be measured over the life of the activity? 8. Does the implementation strategy clearly demonstrate the systems that are in place to implement, check and review activities (including management measures) in compliance with the EP? 9
  • 10. The types of coastal and offshore construction activities requiring an EP may consist of: 1. Dredging – deepening shipping channels, sediment and rock piling for ports and wharfs, marina’s, land reclamation 2. Trenching – burying pipelines into the seafloor, burying or overlaying coastal areas such as beaches, intertidal areas, mangroves 3. Construction – infrastructure development for energy projects, wharfs, wells, pipes, processing, transport etc 4. Production – various types of production including subsea, floating LNG, manned and unmanned WHP’s etc 5. Seismic surveys - • The environmental assessment component of an EP is focused around a process to demonstrate that environmental impacts and risks are of an acceptable level and ALARP. Environmental performance objectives and environmental performance standards, and their measurement criteria, are defined and set respectively to ensure overall environmental performance is maintained at the defined acceptable and ALARP levels. • The implementation strategy core elements required to meet this are: 1. measures to ensure environmental performance objectives and environmental standards are met 2. systems, practices and procedures to ensure impacts and risks are continuously reduced to ALARP 3. chain of command, including roles and responsibilities 4. measures to ensure personnel are competent and trained 5. provisions for monitoring, auditing, management of non-conformance and review 6. provisions for the maintenance of accurate quantitative records of emissions and discharges 7. an OSCP including emergency response and testing arrangements 8. provisions for ongoing consultation 10
  • 11. All these types of activities require preparation of an EP where although the context is different, it has to meet the same assessment criteria. • Unravelling the complexity of such arrangements regarding EP content and preparation will assist in understanding how to simplify approaches to acceptance of an EP as an in force plan. • The Environment Regulations simply reflect the “plan – do – check – act” cycle that is the basis of a systematic approach to environmental management. The Environment Regulations provide a framework in which this basic process is conducted and are designed to ensure appropriate and sufficient oversight. Consequently, the Environment Regulations provide the basic process and critical steps against which operators need to demonstrate their compliance with the regulatory requirements including the “plan – do – check – act” cycle. 11
  • 12. Requirements regarding the content of an EP appear relatively straight forward at first glance and should include (see PowerPoint). The process for developing an EP can be described as having two distinct components – the environmental assessment and the implementation strategy. 12
  • 13. However, the manner in which an EP is prepared is not easily discernable and left to the operator to decide. Neither the regulations nor the regulator outlines any specific requirements as to the approach that should be taken in preparing or presenting the required content. • The key process steps (describe, detail, evaluate and demonstrate, define, consultation and implementation strategy) that are provided for in the Environment Regulations for developing an EP. • The Environment Regulations also include the particular elements that these process steps relate to, and which further describe the EP requirements of the Environment Regulations. 13
  • 14. The regulations do outline what an EP is assessed against, but bridging the gap between required content and alignment with the regulations for assessment successfully depends on how content is structured and presented. Here required content is covered in more detail and then related to document preparation for assessment. • Relevant Regulations Assessed Against are: 1. Activity: 4(1) (definition of activity), 5, 6, 11(1)(a), 13(1)(a-d) 2. Environment: 4(1) (definition of environment), 11(1)(a), 13(2) (a)(b) 3. Other legal requirements: 13(5) (a)(b), 11(1)(a) 4. Acceptable levels of impacts and risks: 11(1)(c) (also see section 3.6 “Evaluate and Demonstrate: Impacts and Risks - Acceptable Level”) 5. Impacts and Risks: 4(1) (definition of environmental impact), 13(3)(a), 8(1) 6. Evaluate and demonstrate impacts and risks: 4(1) (definition of environmental impact), 11(1)(c), 13(3)(b), 13(3A)(a)(b) 7. Evaluate and demonstrate impacts and risk are ALARP: 11 (1) (b), 14 (3) 8. Define Environmental Performance Objectives: 3(b)(i)(ii), 4(1) (definition of environment, environmental performance, environmental performance objective and recordable incident), 11(1)(d), 13 (4)(a)(b)(c) 9. Define Environmental Performance Standards: 3 (b)(i)(ii), 4(1) (definition of environmental performance standard and recordable incident), 11(1)(d), 13 (4)(a)(b)(c) 10. Define Measreument Criteria: 3 (b)(i)(ii), 4(1) (definition of environmental performance objective and environmental performance standard), 11(1)(d), 13 (4)(a)(b)(c) 11. Stakeholder Consultation: 11(1)(f), 11(8)(a)(vi), 11A, 14(9), 16(b) 12. Implementation Strategy: 14(1-10) 13. Additional Content Requirements: 15, 16, 26, 26A, 26AA & 26B, 29, 29A 14
  • 15. Perhaps a key aspect underpinning EP content is the requirement to demonstrate consultation (see PowerPoint). • The EP must include details of the consultation conducted during the development of the EP [11(1)(f)] and also include a plan for ongoing consultation during the operational phase [14(9)]. 1. The EP must demonstrate that the operator has carried out the required consultations in the required manner [11(f)(i)]. 2. The EP must demonstrate that the measures (if any) that the operator has adopted, or proposes to adopt, as a result of the consultations are appropriate [11(f)(ii)]. 3. For consultation in the course of preparing the EP, the operator must consult relevant persons [11A]. 4. The EP must contain a report on all consultations between the operator and a relevant person [16(b)] and that report has specific requirements [16(b)(i-iv)]. 5. The implementation strategy must contain a plan for appropriate consultation on an ongoing basis with relevant stakeholders (Commonwealth, state or territory authorities and other interested persons 6. or organisations) during the operational phase of the activity [14(9)]. 7. Consultation in preparation of an EP may help inform the operator about what is considered to be an ‘acceptable level’ of environmental impact and risk. 8. The consultation must be appropriate for the nature and scale of the activity in that all persons whose functions, interests or activities may be affected by the activity must be consulted. 15
  • 16. The operator should consider and provide a reasonable basis for determining who they consider to be ‘relevant persons’ and define these in the EP. While “relevant person” is described in the Environment • Regulations, the operator must determine in the context of nature and scale of the activity, which persons may be relevant and whose functions, interests or activities may be affected by the activities • to be carried out under the EP. • Stakeholders can consist of any person, organisation, ethnic group or industry that may potentially be adversely affected by an activity. Examples are: 1. Fishing industry 2. Aquaculture industry 3. Indigenous people 4. Conservation groups 5. Recreational user groups 6. Government (matters of national interest) 7. Public 8. Military 16
  • 17. Of particular importance is the requirement for consultation regarding development of an Oil Spill Contingency Plan. Evidence of this consultation has to be shown in the preparation of an EP. • It is essential to liaise with those involved in implementing the National Plan, which is aligned with MARPOL requirements for spill response, escalation, and a 3-tiered approach to dealing with an unplanned event. This is covered in more detail later (see section 2.4.1, 2.4.2, 2.4.3). • In cases where it is appropriate to the nature and scale of an activity, operators could undertake consultation for a range of petroleum activities on a strategic basis. The submission for each activity would need to demonstrate that this action was appropriate and that each identified relevant person had sufficient time and information to make an informed assessment of the potential impacts of the specific activity on their functions, interests or activities. 17
  • 18. When an activity has the potential to impact on matters of national interest a referral to the Minister of Resources, Energy and Tourism has to be made for assessment. It is a requirement under the Environmental Protection, Biodiversity and Conservation Act 1999 (see PowerPoint). 18
  • 19. Assessments are made from (see PowerPoint). • The EP must describe the regulatory and other requirements that apply to the activity and are relevant to the environmental management of the activity. Requirements should be included as part of the context of the activity to help understand the regulatory and other requirements that may influence the way in which an activity is assessed and managed by the operator. • Requirements include other approvals, legislative requirements or conditions that may apply to the specific activity. 19
  • 20. An Environmental Impact Statement has to be prepared that addresses the effects of the activity or project. Key to an EIS is that it provides for alternatives and an opportunity for public participation or consultation. Also key is that the Minister must refer the EIS to the Environmental Protection Agency for assessment. • Activities that have the potential to impact on sensitive areas may include: 1. Oil and Gas Exploration and production near MPA’s and Marine Park coral reefs, deep ocean habitats, nursery grounds etc 2. Oil and Gas Exploration and production near whale migration routes 3. Oil and Gas Exploration and production near turtle nesting sites 4. Coastal processing facility development and associated wharf/port structure near culturally significant sites 5. Coastal processing facility development and associated wharf/port structure near MPA’s or marine parks 6. Operations near or in commercial fishing areas 7. Vessel or facility movement and / or subsea construction biofouling and introduced marine pests or native invaders 20
  • 21. EP requirements could include amongst other things: relevant laws, codes, standards, agreements, treaties, conventions or practices that apply to the jurisdiction that the activity takes place in, or other jurisdictions, that may be relevant to the activity. • The description of requirements should not just be presented as a list of requirements, but should provide details of which requirements are relevant to the specific activity in the EP and how they apply to the activity. The description of requirements forms part of the context of the activity and influences the assessment and management of the activity, and the development of environmental performance objectives and environmental performance standards. • These requirements should be taken into account in establishing, implementing and maintaining environmental management of the activity. Requirements that are not relevant to the environmental management of the activity do not need to be included. 21
  • 22. Commonwealth environmental regulatory reform is underway to streamline the approvals process and provide for one application and assessment process, particularly in dealing with biodiversity offsetting for mining and energy development. • This will limit the burden on the proponent in preparing submissions for assessment and referral for matters of national significance. 22
  • 23. Alongside commonwealth regulatory reform the WA EPA under the Environmental Protection Act 1986 allows for environmental offsets to be incorporated into the EIA process as part of preparation of an EIS for referral. ie activities potentially impacting on matters of national significance can be ‘offset’. 23
  • 24. One of the most important features of an EP is the implementation strategy, which provides assurance to the regulator that all necessary precautions have been taken to ensure that any potential or existing impacts have been reduced to As Low As Reasonable Practicable (ALARP). As a function of this strategy the proponent has to show in any referral that they are able to manage such impacts. • The implementation strategy includes specific requirements [Reg 14 (4-10)] that must be addressed in the EP for the duration of the proposed activity. These include: chain of command, responsibilities, training and competence, monitoring, auditing, management of non-conformance and review of environmental performance and the implementation strategy, quantitative records of emissions and discharges, an OSCP, consultation and regulatory compliance. • An OSCP must be included as a component of the implementation strategy. The OSCP must contain specific emergency response and testing arrangements that are appropriate to the impacts and risk of the activity under emergency conditions. 24
  • 25. The implementation strategy must provide for appropriate consultation with relevant government agencies, relevant interested persons and organisations for the life of the activity or five-year EP review period. (see section 3.11: Consultation) • A critical element of this strategy is the Oil Spill Contingency Plan. Being a ‘operational’ document it provides the necessary detail that ensures compliance with EP assessment criteria. An OSCP brings together a wide range of EP components, from EIA and baselines studies where knowledge is lacking, to Zone of Potential Impact (ZPI) modelling and responses to an unplanned event offshore and onshore. • Provisions for periodic review of environmental performance and the effectiveness of the implementation strategy should be detailed. This review cycle should allow the operator to determine if the measures, systems, practices and procedures of the implementation strategy have been effective in ensuring that performance objectives and environmental performance standards have been met and that impacts and risks are consistently being managed to acceptable levels and reduced to ALARP as defined in the EP. 25
  • 26. In preparing an OSCP consideration should be given to (see PowerPoint) 26
  • 27. Sources of spill events can be from activities where unplanned events occur, such as: 1. A collision, grounding or foundering 2. A well blowout 3. A pipeline incident • Causes may be related to any number of events, but the circumstances surrounding them are always viewed from a risk and safety assessment perspective. Irrespective of the source, the impacts have a commonality about them that is directly related to the scale of the event. • Right side of the slide shows the position of the Montara blowout and associated oil slick. Left side shows vessel incidents and associated oil slicks. Circumstances surrounding the source of the event interact with the nature of the environment and determine the scale of impact. 27
  • 28. Impacts can be broadly defined as those occurring offshore and at sea and those that affect the coastline, whether originating from offshore, coastal or onshore. • Offshore: depending on the scale of the event it has the potential to affect entire food webs. For example the Montara blowout cumulative impact on the environment was the size of the state of West Virginia. Over such broad spatial scales Oil type, toxicity (PAH’s), viscosity, specific gravity, aging and weathering have significant implications for the degree of temporal impact (impact over time) on localised offshore primary production and flora and fauna. • Impacts of a major event include: 1. Transient fish, invertebrate, turtle and mammal populations can be smothered, gill fouled and/or ingest weathered oil. 2. Consumption and accumulation up the food chain can occur – localised collapse of food web due to inhibition of primary production because of photoinhibition and altered behaviour (phytoplankton and zooplankton populations). 3. Deep ocean impacts from event aged fuel breakup and deposition to the deep ocean seafloor via the carbon cycle. 4. Abundance in biogenic sediments and accumulation through benthic primary producer food chain in deep ocean habitats – effect unknown. 5. Upwelling and re suspension due to seasonal cycling, long term disruption to food webs and trophic structure across broad spatial scales. 28
  • 29. Onshore: impacts onshore are immediately more obvious and pronounced and can be initially related to smothering of marine fauna and flora. Initial impact of uptake of toxic PAH’s on aquatic health depends on the rate of weathering and type of organism. Ie filter feeder, infauna, epibenthic, carnivore, herbivore and whether they are a bird, mammal, crustacean, mollusc, echinoderm etc and the manner in which they reproduce (broadcast spawner, brooder, etc). • Different habitats will mediate an organisms response to an oil slick and may include: 1. Surf zone beaches – accumulation through successive tidal cycles, increased breakup and aging, smothering and seeping into sub layers of sand. 2. Rocky coastline – topographically complex means accumulation of weathered oil is more difficult to get rid of and effects may be long-lasting in this regard. 3. Mangroves – almost impossible to remove trapped oil without removing forest. Breakdown may be faster though because of the nature of mangroves and entrapment and binding up of sediment. 4. Harbour and other estuaries – ecologically very sensitive, especially if already heavily modified due to anthropogenic activities. Oil can become trapped between tidal cycles and never wash out, depending on degree of flushing. • Long-term impacts include the sub-lethal and chronic effect of toxicity (PAH’s and endocrine disruption), reproductive inhibition, and recruitment failure, population change and dislocation. Often unintended consequences occur ie larval supply to other unaffected areas etc, or nursery grounds for local populations wiped out, esp. fish. 29
  • 30. A key aspect of preparing an EP is to show how an activity will be monitored and how any potential impact will be assessed. To meet this requirement it is essential that the risk assessment process has been addressed in preparing the EP and that evidence of this has been provided. Measurement criteria must be developed and standards also developed to demonstrate compliance with the EP and its requirements. • Some operators may integrate the preparation of an EP within an existing Environmental Management System (EMS) and its certification or development under ISO14001. • ISO 14001 is an internationally accepted standard that sets out how you can go about putting in place an effective Environmental Management System (EMS). The standard is designed to address the delicate balance between maintaining profitability and reducing environmental impact; with the commitment of the entire organization, it can enable the achievement of both objectives. • What’s in ISO 14001: 1. General requirements 2. Environmental policy 3. Planning implementation and operation 4. Checking and corrective action 5. Management review 30
  • 31. The risk assessment process is in alignment with AS/NZS ISO31000 which replaces AS/NZS 4360. Risk assessment has to include identifying the risks, analysing likelihood and consequence, prioritising the risks, and risk treatment. • It is a requirement by NOPSEMA for environmental risk assessment to address both inherent risk with no controls in place and to show that the post-treatment risk has been reduced to tolerable or with additional controls in place to As Low As Reasonable Practicable (ALARP). • A great software programme now available to achieve this is PHA Pro 8, which allows the user to enter a risk matrix which is then linked to the spreadsheet used during a workshop. 31
  • 32. Risk is defined as the ‘effect of uncertainty on objectives’ (AS/NZS ISO 31000:2009). The objectives can be financial, health and safety, environmental and so on. The risk management process involves the following steps, as given in ISO 31000:2009: 1. setting objectives and establishing the context of the risk assessment; 2. identifying the risks; 3. analysing the risks to determine the level of risk, which is defined as the combination of the consequences and likelihood of the risk; 4. evaluating the risk, to decide if a risk is acceptable, tolerable or intolerable / unacceptable; 5. treating the risks, focusing on those risks which are intolerable; and 6. monitoring and review, to continuously refine and improve the assessment and risk treatments. 32
  • 33. A typical risk matrix against which activities are assessed consists of: 1. A scale of severity and associated consequences in terms of people, property and the environment 2. A scale of the frequency of occurrence with associated definitions 3. The response matrix showing whether the risk is low/tolerable, medium/ALARP, or high/intolerable • Provisions for monitoring environmental performance and the implementation strategy against performance standards and objectives identified through the risk assessment process throughout the operational phase of the activity must be included. Monitoring should be sufficient to identify deviation in environmental performance from the levels set in the EP. The frequency and type of monitoring should be appropriate to the nature and scale of the activity. 33
  • 34. Monitoring programmes need to address both the potential for proximate operational environmental impacts while providing assurance that in the event of a major spill or other event the wider environment has been considered. • A monitoring plan needs to take into account the potential for spills to come ashore, account for lack of information by conducting baseline studies, and providing for ongoing monitoring. It also has to consider that in the event of a spill a rapid response survey can be conducted both in proximity to the spill and other areas where a spill is likely to come ashore. • Real time monitoring is also crucial, especially in terms of met-ocean data, and modelling and prediction of downstream events and impacts from a spill. 34
  • 35. Baseline studies and modelling requires careful consideration of sampling and survey design to achieve a balance between reliability and cost. • Before, After, Control, Impact designs optimise the opportunity to detect any potential environmental impact, the details of which are the subject of an entirely separate seminar. • Needless to say that the natural world is full of background ‘noise’, which can easily mask the ability to detect impacts if sampling designs do not adequately account for this ‘noise’. • The chance of false negatives is relatively high and requires rigorous power analysis and testing to minimise or limit this from occurring should a result show no impact. ie there really was NO impact! • A complimentary sampling regime may involve real time integrated monitoring, which provides a rigorous picture of an area over time but may have limited use spatially depending on cost. However, it may be quite useful for operational monitoring. 35
  • 36. Advances in Radiotelemetry mean technology, hardware, and software is becoming available to use remotely for real time monitoring in environments that are often difficult to work in. • May involve time-lapse video of the seafloor and water column, sensors for sampling water parameters, sea surface variables, seabed shifts and disturbance etc. • Able to detect changes in habitat composition, community composition, fauna behaviour, seawater nutrient levels, turbidity and current, seawater chemical composition etc. 36
  • 37. All arriving international vessels are required to manage their ballast water in accordance with the Australian ballast water management requirements. The DAFF website provides further information to assist operators comply with the requirements. • A comprehensive set of domestic ballast water management arrangements are being developed under the National System to complement the existing requirements for international vessels. These arrangements will be consistent with the International Maritime Organization’s International Convention for the Control and Management of Ships' Ballast Water and Sediments, which Australia has signed subject to ratification. • The risk of the petroleum production and exploration industry spreading marine pests is highest when vessels, immersible equipment and infrastructure: 1. are heavily biofouled and organisms such as mussels, oysters, seaweeds and seasquirts are visible 2. are moved to a new area after spending long periods either stationary or at low speeds (including undergoing dockside upgrades) 3. have areas without antifouling coating or the coating is inappropriate for vessel use, aged or worn. 37
  • 38. Risk can be reduced by incorporating practices that minimise the build up of biofouling into your routine cleaning and maintenance programs. The 'National biofouling management guidance for the petroleum production and exploration industry' document outlines practical recommendations for operators on managing biofouling on petroleum related vessels, equipment and infrastructure. These recommendations have been developed in conjunction with the petroleum production and exploration industry and apply to the following vessel types: 1. offshore support vessels including utility support vessels, platform supply vessels and anchor handling tug supply vessels 2. mobile offshore drilling units including jack-up units, drilling barges and semi-submersible ships 3. crew transfer vessels 4. diving support vessels 5. accommodation vessels 6. seismic survey vessels 7. landing craft 8. pipelay ships and barges 9. floating production, storage and offloading vessels (FPSO) and floating storage and offloading vessels (FSO). • Operators of oil tankers and gas carriers should refer to the 'National biofouling management guidelines for commercial vessels' for guidance on managing biofouling. Operators of heavy lift vessels and dredges (including rock dumping ships) should refer to the 'National biofouling management guidance for non-trading vessels' for further information on managing biofouling. The 'National biofouling management guidance for the petroleum production and exploration industry' also inlcudes information on biofouling management of submersible equipment and infrastructure. 38
  • 39. Monitoring programmes may consider: 1. Permanent sea surface sensors 2. Permanent satellites and GIS 3. Permanent seafloor sensors 4. Water column deployed and towed equipment 5. Periodic remote surveys 6. Periodic surveys 7. Predictive modelling 8. Structures, fouling and marine pest management 39
  • 40. Key elements contributing to an EP need to be bought together in a coherent and succinct manner for submission and assessment against the regulations and acceptance as an ‘in force’ plan. 40
  • 41. Key in preparing the EP structure is to provide evidence of assurance and compliance (see PowerPoint). • Provisions for management of non-conformance must also be detailed in the implementation strategy. • These provisions should allow sufficient information to be collected to fulfil regulatory requirements for reporting of recordable and reportable incidents to the regulator and to ensure that any corrective and preventative actions are implemented. • Provisions for periodic review of environmental performance and the effectiveness of the implementation strategy should be detailed. • This review cycle should allow the operator to determine if the measures, systems, practices and procedures of the implementation strategy have been effective in ensuring that performance objectives and environmental performance standards have been met and that impacts and risks are consistently being managed to acceptable levels and reduced to ALARP as defined in the EP. 41
  • 42. To recap on the regulations, the key to successful assessment is under division 2.2 and 2.3 of the 2009 regulations (see PowerPoint). Key aspects related to successful assessment also include: 1. The EP must include arrangements for recording, monitoring and reporting a sufficient level of information to allow the operator to demonstrate to the regulator that all of the environmental performance objectives and environmental performance standards in the EP have been met. 2. Reporting arrangements must address reportable incidents, recordable incidents and routine environmental performance reporting. 3. The EP must include details of all the reportable environmental incidents that may arise from the proposed activity. 4. Intervals for environmental performance reporting in accordance with the Regulations must be provided in the EP such that they can be agreed to by the regulator. 5. he EP must detail the arrangements put in place by the operator for notification of the relevant state or territory minister of the commencement of drilling or seismic survey activities if those activities may have an effect on a community in the activity area. 6. The EP must contain a statement of the operator’s corporate environmental policy. 7. The EP must contain a report on consultations (see section 3.11: Consultation). 8. The EP must address the specific requirements for the discharge and testing of produced formation water. 42
  • 43. In bringing these elements together, the assessment criteria and regulations can be matched against submission structure by following the Safety Case Approach to submissions and approvals (see PowerPoint). 43
  • 44. 44
  • 45. 45
  • 46. What does the future hold: • Alignment with EMS ISO 14001 both from a regulator and operator perspective. Future legislation and government policy objectives may seek to reflect this arrangement. • Environmental impact is becoming an increasingly important issue across the globe, with pressure to minimize that impact coming from a number of sources: local and national governments, regulators, trade associations, customers, employees and shareholders. Social pressures are also building up from the growing array of interested parties, such as consumer, environmental and minority non-governmental organizations (NGOs), academia and neighbours. • So ISO 14001 is relevant to every organization, including: 1. Single site to large multi-national companies 2. High risk companies to low risk service organizations 3. Manufacturing, process and the service industries; including local governments 4. All industry sectors including public and private sectors 5. Original equipment manufacturers and their suppliers 46