THE MUMBAI MEGAPROJECT                                                                                          Rev 00



Re – Imagining The Mumbai
Metropolitan Region (MMR)




             “ The Future Landscape Of Mumbai " – A FLO Initiative

                                                  Supported by
                                                  Deutsche Bank
Bombay Chapter                                                                                                           The Nataraja Foundation
                 © Copyright   June ‘ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved    24th September ‘ 2011
NOTICES



1. LEGAL

This document is protected by Indian Copyright Law. Please quote your
source while referring to the ideas contained herein to avoid legal
action



2. CONCEPT COMPLETENESS

The Mumbai Megaproject is fully defined by two documents as follows :

1. This Presentation and …
2. Project Excel Workbook ( Excel Motherfile ) which contains all project calculations and
   financing details

City Authorities will need to go through both the documents to obtain a detailed understanding
about the subject matter presented.
                                                                                                                                         2

                                       © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
CONTENTS

  CENTRAL DEVELOPMENT CONCEPT
  EXECUTIVE SUMMARY
  MUMBAI : CURRENT STATUS
     Macro Urban “ Quality of Life ” Indicators
     Mumbai City : Current Status … In Pictures
     Showstoppers…Improper Governance,Huge Debt &Technical In-competence
  THE MUMBAI MEGAPROJECT 2014 – 2023
     Project Concepts … The 13 Major Concepts … of a total of 24 Unique Ideas
     Engineering, Procurement, Construction & Project Logistics Issues
  PROJECT STARTUP … ACTIVITIES TO INITIATE PROJECT
  GOVERNMENT SUPPORT REQUIRED
  MUMBAI 2024 … CITY OF THE 21st CENTURY

                                                                                                                                  3

                                © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
CENTRAL DEVELOPMENT CONCEPT




                                           Sarvodaya : “ The Rise Of All “




  Dubai & China Model                        Mumbai Megaproject Model



Mumbai Megaproject is based on Gandhiji’s “ Sarvodaya ” Model                                                                 4

                            © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
EXECUTIVE SUMMARY
1. Mumbai Mega-Project Macro Description
      An executable plan to totally re-build Mumbai in 9 – 10 years ( 2014 – 2023 )

      Free Housing…Based on Dwelling Concept, For 9 Million Slum Dwellers in Mumbai

      Creation Of Financial Centers & Other Amenities … 2 Financial Centres , Universities etc

      Transport : 210 Km of Underground Subway…60 % Reduction in Network Load

      Original Islands to be separated & Harbour to be Re-Developed into A Mega Port
      Executing Intelligent Urbanism Concepts “ Creating Large Open Spaces, Theatres,
      Cycling Corridors, Theme Parks and Large Public Spaces “.
 2. Proposed Additional Investments in Maharashtra State … Growth Catalysts
      Maharashtra High Speed Logistics Ring Corridor
           2700 Km , 6 Lane , High Speed Ring Road
           Mumbai – Nashik - Nagpur – Gadchiroli – Nanded – Pune – Mumbai … Bullet Train
      30,000 Check Dams to restore Water Table in Maharathwada & Vidharbha
      Plantation of 2.5 Million Hectares of Dense Forest + 7,000 Acres of Mangroves
      20,000 Acre Maharathwada Eco - SEZ + 4 Eco Cities in Tribal Areas
                                                                                                                                        5
Huge Development Project … Creation of 6 Million New Jobs in Maharashtra
                                      © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
EXECUTIVE SUMMARY
3. Project Macro Economic Impact
   Project Unlocks US $ 308 Billion of Value in Mumbai to Rebuild the City
   Mumbai GDP ($ 85 Bn) to triple by 2018, to exceed Singapore GDP @ $ 310.69 Billion by 2024
   Infrastructure Investment Multiplier effect on Maharashtra economy > US $ 500 Billion

   Project Repays Entire US $ 46 Billion Debt of Maharashtra State … Single Bullet Payment

   Project implements President Kalam’s PURA Concept … Stops Mass Migration To Cities
   by investing US $ 90 Billion in Healthcare & Education across Rural India
   Rural Maharashtra Impact : US $ 200 Billion … ( Achieve Gandhiji’s vision                        of Rural Growth )

4. Project Governance & Control Issues
   Project Execution & Control Imperatives to Minimize Funds Leakage :
        Mumbai Governance Structure needs more clarity
        Sophisticated IT Reporting System / Protocols to Execute Project … Zero Funds Leakage
        Transparent and Highly Centralized Procurement System for all Critical Items/ Contracts
        Two Stage International Bidding ( Stage I for Urban Designs, Stage II for EPC )
        Empowered Organization to Plan & Execute Project … Govt. Agencies to compete for
        Contracts on same terms as private sector under international competitive bidding
   Procurement Standards : World Bank / EU Tendering Procedures & Reporting Formats
                                                                                                                                           6
Project Brings Massive Development & Improves Governance in Maharashtra
                                         © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
MUMBAI : CURRENT STATUS




                                                                                                        7


        © Copyright   June ‘ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
MACRO URBAN “ QUALITY OF LIFE ”
INDICATORS

  Mumbai’s Population has exceeded 14 Million …Population density stands at
  28000 Persons / sq km … worlds highest
  Highest % of Population in Slums for any city globally … 72 %
  Quality of life … Dharavi has 800 People per Toilet .
                 … Local Transport Networks are stretched beyond limits
                 … Water and Power Shortage is Acute
  Huge differences in Incomes … Growing Social Tension
  City looks like a giant garbage dump … most filthy metropolis In India
  City Still Produces 5 % of India’s GDP … Under Severe Constraints
  Land and Property Prices have become unaffordable for most people and
  Businesses … New Businesses are avoiding Mumbai



 Mumbai City Is Dying … There can be no two opinions about this                                                                     8

                                  © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Mumbai City : Current Status … In Pictures




Mumbai Slum Population : 9.0 Million
Total Population       : 14.3 Million
Source : 2011 Census Projections , GOI

                                                                                                                                           9
72 % of Mumbai’s Population Lives like this in Slums
                                         © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Showstoppers
         For
Mumbai Re-Development




                                                                                                      10


       © Copyright   June ‘ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Showstopper 1 … Improper Governance

                                                                  Chief Minister
                                                                                                                   Report to
                              Vidhan Sabha                                                                       Central Govt.
                    Only 36 MLA’s out of 288 are From Mumbai



                              Mayor                Municipal Commissioner
                                              ( Not Answerable to Corporators )         Chairman
                                                                                   MMRDA / MHADA/ CIDCO

                                                  Mumbai Municipal                                              Central Govt
Vote in Elections




                                                                                    Parallel
                         Mayor’s Offce              Corporation                                                  Agencies
                      With No Executive Power                                    Govt. Agencies
                                                     ( MCGM )                                                Airports Authority,
                                                                             MMRDA / MHADA / CIDCO              Port Trusts,
                                                                                                                  Railways

                                227
                          Corporators           24 Wards , with large Population
                                                                                                   Source : Vote Mumbai Campaign




                                                                             No large Re-Development project is
                                                                             possible within current structure
Showstopper 2 … Maharashtra’s Huge Debt




  Debt of Maharashtra State currently stands at Rs 2.09 Lakh Crores ( 2011)


  Debt is projected to increase to Rs 2.31 Lakh Crores by March 2012


  This Huge Debt prevents State Govt from doing big projects




 Large projects are not possible unless Maharashtra’s debt is
 significantly reduced
                                                                                                                                 12

                                 © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Showstopper 3 … Technical Incompetence

Government Agencies Project Quality




 Very Serious Quality issues with Government Agencies Project Management
                                                                      13
 Skill Sets & Construction Work
                                      © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
THE MUMBAI MEGAROJECT


PROJECT CONCEPTS … THE 13 Major Concepts ( Out of 24 )




                      © Copyright   June ‘ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Concept 1 : Eastern Seaboard Re-location
            & Re- Development
                                                                                                        Port Traffic is Choking City’s
                                                                                                        Road and Rail network
                                                                                                        Mumbai Eastern Seaboard to be
                                                                                                        Re-Developed after Re-Locating :
                                                                                                        - Mumbai Port Trust, FCI, Railways
                                                             Housing for Urban Poor                     - RCF, BPCL & HPCL
                                                                                                        All Re-Located Facilities will be
                                                                                                        provided with financing for latest
                                                                                                        equipment and capacity expansion
                                                                                                        at a new location on land provided
                                                                                                        by Govt of Maharashtra.
                                                                                                        Relocation Critical in order to
                                                                                                        prevent possible disasters due to
                                                                                                        leakage of lethal      chemicals
                                                                                                        like Ammonia, Chlorine and to
                    Entire site to be raised 21 Ft                                                      avoid Crude Oil spills that are
                    ( Rising Oceans Concept ).
                    Followed by rest of Mumbai                                                          occurring frequently
                    by 2050 )
 Value Unlocked through Re-zoning : $ 70.45 Billion                                                     These Industries with huge toxic
 After providing for Entire Eastern Seaboard Re-Location and plant capacity
 expansion with latest technology and Environmental systems, including World                            chemical tanks are also prime
 class Employee Townships at New Locations in Maharashtra.
© Copyright   June ‘ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
                                                                                                        terror targets. Pose Serious Threat.
Concept 2 : Separation Of Islands




                                                                                  Concepts :
                                                                                  1. De-Congest City
                                                                                  2. Prevent Flooding
                                                                                     & Improve Sewage
                                                                                     Disposal
                                                                                  3. Use water transport
                                                                                        Unlock additional Value
                                                                                        Through Differential FSI’s
                                                                                        ( US $ 10 Billion )
                                                                                                                16
Original Islands To be Separated to De-Congest City and Prevent Flooding
                                © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Concept 3 : The Archipelago Concept

Dense Mangroves , 7,000 Acres, 56 Km X 500 Mts           4 Lane , Subsea Road Tunnels

                                                                       Archipelago concept involves creation
 Western Archipelago
 Group of 3 New Islands
                                                                       of 4 New Islands. This will achieve two
                                      Trans Harbour Link               objectives
                                          Logistics                    - Create Additional Amenities/Housing
                                          Super-Corridor
                                                                       - Allow Urban Equity Withdrawal
                                                                         for overall development of the
                                                                         state of Maharashtra & Nation
                                                                         through Massive    Projects in
                                                                         Education, Healthcare, Forestry
                                                                         & Endangered Species Conservation
                                        New Mumbai Port Trust ( 600 Acre Superport ). 2.7 Km X 0.9 Km
                                                                                     Hydraulic Model Studies including
                                                                                         Western Islands Project
                                                                                     Tidal Prism / Near Shore Current
                          New Eastern Island                                             Project Cost       : US $ 184.50 Billion
                                                                                     Assessments together                   with
                                                                                         Sales Realization : US $ 308.06 Billion
                          ( 6005 Acres 9.0 Km X 2.7 Km )
                          Financial Centre, Living Space,                            detailed      Environmental Impact
                                                                                         Net Surplus        : US $ 123.56 Billion
                          Entertainment Area                                         assessment survey Project +Others (40)
                                                                                        Inner Harbour Island      Needed to
200 Mts wide Channel New Naval Base ( 900 Acres ) 100 – 200                          confirm location and $ 332.10 + 40 Billion
                                                                                        Project Cost      : US configuration
                     Km south of Mumbai                                              of the islands. All:Islands to be 21 Ft
                                                                                        Sales Realization US $ 475.30 Billion
                                                                                     above MSL ( Rising Oceans103.20 Billion 17
                                                                                        Net Surplus      : US $ Concept )

Urban Equity Withdrawal Through Facility Creation : $ 226.76 Billion
                                                 © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Concept 4 : Slum Re-Habilitation & Decongestion
                           45 Storey Towers with
                           Regular Maintenance

                                         2018




Estimated Project Cost : US $ 65 Billion
                                                                       Dwelling units with 500 Sq Ft carpet
       Slum Transition                                                 area to house all existing 9 Million
       Accommodation                                                   slum residents In-Situ. Any additional
                                                                       Migration to be settled on MMR fringes.
                                                                       Mumbai to have proper & detailed
                                                                       census before scheme is launched.
                                                                       Mapping to UID Number          critical to
                                                                       check cheating.
                                                                       Specified Penalties for offenders … loss
                                                                       of house and work permit in Mumbai.
                         2011                                         High speed rail link to those who
                                                                      choose low rise           accommodation
                                                                      elsewhere in MMR as space is critical .
                                                                      Increasing FSI to 12–16 levels is critical
Megaproject has unique scheme for Slum Re-Habilitation. Zero Funds                                                                       18
Required From Govt. Of Maharashtra
                                         © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Slum Re-Development : Megaproject Scheme Vs. Govt. Scheme
SL.   Parameter        Current Govt. Schemes                          Mumbai Megaproject Scheme
No

1     Coverage         Case By Case Basis based on                    Blanket Scheme to cover all 9 Million Slum Dwellers
                       Slum Re-Habilitation Authority                 in Mumbai , based on Dwelling Concept
                       ( SRA ) Clearance
2     Proposed         269 Sq Ft per dwelling                         500 Sq Ft per Dwelling
      Carpet Area
3     Financing        Govt. Cross Subsidy Scheme.                    Mumbai Megaproject will bear entire US $ 65 Billion
                       Towers for Slum Dwellers on just               ( Rs 2,95,685 Crores ) Capex to provide Good Quality
                       20 % of Land Originally Occupied               Housing to all 9 Million Slumdwellers on Dwelling
                       by the Slum, Balance 80 % land                 Concept. Slum dwellers will keep 50 % of their land
                       given to Builder for commercial                and not just 20 % as in current Govt. Schemes. All
                       development. Example Forjett Hill              Accomodation will be provided In-Situ with No Re-
                       below Altamount Road and in                    Location ( Important ) . Megaproject will build
                       Chandivali near Powai                          commercial space on balance 50 % area, the rent from
                                                                      which will provide for maintenance of the buildings.
4     No of Floors     Most    Recent     Govt   Scheme               45 Storey Towers. All Construction will be High
                       provides for 20 Storey Towers                  Intensity Earthquake Resistant and of world class
                                                                      standard (40 % higher cost due to Civil/Mechanical ).

5     Childrens Play   Zero                                           First Six Floors in Each Tower will be reserved for
      Area                                                            Children Playing Area and For Healthcare and
                                                                      Education of Tower Residents.

6     Maintenance      Current Govt Scheme provides for         On Project Completion Megaproject Authority will fund
                       Maintenance of Buildings but it has      100 % of Maintenance (Estimated Cost = US $ 1.97
                       lot of grey areas and there is no        Billion / Year ( at the rate of Rs 40,000 / Dwelling /
                                                                year ). Finance will come from Rents as described
                       Accountability if later on money is                                                                                          19
                                                                above and from dividends on Megaproject Equity
                       Not released for Maintenance.            Investments. There will be Strict Monitoring of Costs.
                                                     © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Concept 5 : The Undersea Subway Ring



                                                                          Giant Tunnel Boring
                                                                          Machine

                                                               Wholly Underground Highspeed
                                                               Subway Rings to reduce transit
                                                               time from Goregaon to Uran to
                                                               30 Minutes  from 3 – 4 Hours
                                                               Currently.
                                                              New Navi Mumbai Airport will be
                                                              on the New Subway Ring
                                                                 Facilities Creation To Unlock
                                                                 Huge Value in MMR
                                                                 Megaproject to finance 75 % of
                                                                 PPP Ventue
                                             Approx. Project Capex : $ 34.29 Billion
                                                                                                                           20
Vastly Improved Communications Infrastructure to Augment Economic
Value Of MMR                 © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Concept 6A : Sewage Treatment System
                 ( New York Lookalike )


                                                      New Infrastructure to be built in MMR

                                                          12 Nos of 100 Mld of Sewage Treatment
                                                           plants
                                                          4 Nos of 100 Mld Industrial Effluent
                                                          Treatment plants
                                                           Five solid Waste & Plastic Incenerators
                                                           … to produce power
                                                           Three New & Large Landfills. Deonar
                                                           Landfill to be totally redesigned .
                                                           Methane gas to power 2,00,000 houses
                                                           Large New System of 75 ‘’ collection
                                                           headers / pipelines to be laid
                                                           throughout city ( 150 Km )
                                                           Solid biowaste to be processed into
                                                           Fertilizer
Megaproject to invest US $ 2.5 Billion in                                  21
                                          C02 to be sequestered / CO2 Business
Waste Treatment System Capex under PPP
                                    © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Concept 6B : Combination Of Technologies for
             Waste Disposal
 Today ( 2011 )                                                                                     2018




Estimated Project Cost : US $ 4 Billion
Megaproject To Catalyze Private Investment Through Strategic
                                                                                                                                     22
Investment In Waste Treatment & Power Generation Projects
                                     © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Concept 7: Unique PPP Scheme To Clean
           & Restore Mangroves
  Mangrove Destruction &
  Plastic Pollution
                                                                                                         2016




                              Today ( 2011 )




   Estimated Project Cost : US $ 300 Million
Megaproject To Provide Grant Of US $ 300 Million To the Bombay Natural
                                                                                                                                      23
History Society ( BNHS ) for Plantation of 7,000 Acres of Mangroves
                                      © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Concept 8 : The Central Park Concept




                                                       Re - zoning & Differential FSI’s
                                                       to allow for the development of
                                                       Parks within 10 minutes walking
                                                       distance from anywhere within
                                                       Mumbai City and Navi Mumbai
                                                       Special Cyclist Only Corridors
                                                       to be built along all arterial roads
                                                       and coastal roads
                                                       Excess Railway Land to be put to
                                                       Public Use through GOI Ordinance
                                                       Sales Proceeds to build Bullet Train24
Creation of Extensive System Of Interconnected Parks and Cycling Corridors
                               © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Concept 9 : Heritage Conservation




Abu Simbel ( Egypt ) Lookalike restoration for some structures ??

Megaproject to allocate US $ 600 Million For Heritage Conservation                                                                     25

                                       © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
ENGINEERING , PROCUREMENT , CONSTRUCTION
                    &
           PROJECT LOGISTICS




                © Copyright   June ‘ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Concept 10 : The 72 Contractor Territories


                                                                  - MMR to be divided into 72 squares
                                                                    for project execution purposes

                                                                  - These 72 Work Areas will be put out
                                                                    on International Competitive Bidding

                                                                  - The Megaproject will feature 12 design
                                                                    concepts and 12 Large projects

                                                                  - The worlds largest and Best Design
                                                                    firms will compete with local companies
                                                                    & Govt Agencies to develop & design
                                                                    concepts for each project area. The
                                                                    best conceptual designs will be
                                                                    awarded the detailed design contracts.
                                                                    Evaluation will be by a panel of
                                                                    global experts.

                                                                  - 72 Contractor Territories to be awarded
                                                                    to 12 Large Global Consortia with work
                                                                    Value of US $ 30 Billion Each. Indian
                                                                    Companies to compete on same terms
                                                                    as Foreign EPC Contractors

Megaproject Will Divide 72 Areas Into 12 Large Contractor Territories                                                          27
… With Contractor having Single Point Responsibility
                                 © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Concept 11 : Town Planning As a Biddable Item

   India produces just 200 Town Planners each year
   Total Townplanners Employed in India presently is 3300…for a total of 5600 Towns
   Govt. Agencies in Maharashtra do not have required number of Town Planners
   for Mumbai Megaproject
   Further there is large Scale Corruption in getting permissions and the city has
   grown in a totally un-planned manner
   There will therefore be a separate Town Planning Round , right at the beginning
   of the Mumbai Megaproject. Govt Agencies to Compete on Par with Private Players
   Megaproject Bidding Process Monitored by International Panel of Independent Experts
  Step 1                                   Step 2                            Step 3                         Step 4
Global Bidding Round              Global Bidding Round              Global Bidding Round              Go into Construction
for Mumbai Master                 for 12 Large Contractor           for 12 Large Contractor           Phase with Worlds
Plan                              Territories ( Design ) of         Territories ( EPC ) For           Best Designs at the
                                  US $ 30 Billion Each              each of 12 Winning                Lowest Possible
                                                                    Designs                           EPC Cost
World Bank / EU Contract Standards Applied to Above Process Will Deliver                                                       28
City of the 21st Century        © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Concept 12 : Highly Accountable / Visible Project
             System
    Politically Accountable Authority Required to spearhead Megaproject
    Megaproject CEO will be Construction Expert ( Either Indian / Foreign ) with
    Acknowledged Leadership In The Construction Industry Globally
    Megaproject Management / Construction Team to be hired from around the
    world based on expert skill sets
    All Contracts to be awarded after International Competitive Bidding
    Separate Bidding Rounds For Town Planning & EPC …World Bank / EU
    Standards
    All Project Activity to be controlled through Highly Advanced IT System which
    ensures three things :
        Visibility / Transparency
        Accountability & Measurement of Outcomes
        Preservation of Context
        Entire Decision Making Hierarchy To Be Mapped … Deviations will
        Trigger A System Alert                                                                                                      29
 Above Specified Advanced IT System is Critical to Project Execution…
                                    © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Project Scale                    11 Times Palm
                               Jumeirah (Dubai )

     5 Times                                                        Islands
      Three                            Bricks                        4 Nos
     Gorges                           9 Billion
       Dam
                       Concrete                                                                          Circumferance
                     27.2 mill. cum                                  Steel Piles                          of the Earth
                                                                    600,000 Nos

 Total Engg / Arch.
       Design                            The Mumbai                                        Pipelines
    Man hours                            Megaproject                                      40,000 kms
                                          2014 - 2023

                                                                                        Peak construction
  30,000                                                                                   man-power
Engineers               Structural steel                                                     450,000
  & 3000               10 Million Tonnes
Architects                                            Electrical &
for 3 years                                        Instrument cables
                                                      350,000 Kms                                                Earth To Moon
                   75 Eiffel                                                                                        Distance
                   Towers
 Construction Intensity : Rs 300 Crores / Day for 7 years … 24 X 7 non stop                                                               30
 ( Assuming first 3 years for Engineering / Design / Project Planning / Governance Issues )
                                          © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Concept 13 : Non–Invasive Construction Logistics




                                                                                                                                31
Project will have minimal impact on traffic & normal business activity
                                © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Megaproject Startup … Activities To Initiate Project

 BAR CHART

1. Govt. To Initate Re-Location Discussions with
   Mumbai Port Trust, RCF,HPCL & BPCL, FCI & Railways

2. Appoint Surveyors / Consultants For Alternative
   Sites for Port/Industrials which allow for expansion of
   capacities
3. Fast Track Issue of UID Numbers to All Residents of
   the MMR
4. Varification of Detailed Demographic Data & Property
   Holdings & Mapping this to UID's for All Of Dwellings
   within MMR
5. Appointment of Project CEO / Staff for Megaproject.                                                         Critical Senior Staff in Place
    Executive Search firms to be commissioned to recruit
    highly specialized planning and execution team of
   250 Project Managers, 2000 Engineers & 600 Architects
   / Townplanners from around the world
                                                                                                                         First Global Tender
6. State Govt. Provides suitable land to allow for
   expansion of Re-Located Industrials free of all
   encumbrances.Start Physical Relocation Of Industrials,
   Issue First Global Tender for New Port / Underground
   Subway, Master Plan etc


                                                                                                                                                   32

                                                   © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Government Support Required



   Megaproject needs politically accountable authority to spearhead project.

   State Government Needs to Order Relocation Of Harbour Based Industries
   & Mumbai Port Trust

   Project requires highly specialized team of owner managers ( 250 Project
   Managers , 2000 Engineers, 600 Architects / Townplanners Etc. Highly
   specialized construction team will need to be recruited internationally.

   One Time Grant of Rs 3000 Crores From JNNURM to finance Project
   Team Salaries




 Fully Empowered Political Authority Is Critical For Project Execution …
 Megaproject is Totally Self Financing After Initial JNNURM Grant of Rs 3000
                                                                           33
 Crores
                                  © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Mumbai 2024 … City Of The 21st Century




             A Slum
             School




                                                                                                                             34
Mumbai to be Business, Entertainment & Culture Hub of South Asia
                             © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
Mumbai Olympics 2024 ?




Can Mumbai Make A Bid For The 2024 Olympics ?                                                                               35

                            © Copyright   June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
THANK YOU
FOR YOUR ATTENTION




                                  Ashish Puntambekar
                                  Project Designer
                                  The Indian Education Megaproject
                                  & The Mumbai Megaproject
                                  www.nataraja.org.in
                                                                                                     36

     © Copyright   June ‘ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
                        ’

Contenu connexe

Tendances

Neighborhood planning in capital city of chandigarh an appraisal
Neighborhood planning in capital city of chandigarh  an appraisal Neighborhood planning in capital city of chandigarh  an appraisal
Neighborhood planning in capital city of chandigarh an appraisal JitKumarGupta1
 
Trasnportation system of mumbai
Trasnportation system of  mumbaiTrasnportation system of  mumbai
Trasnportation system of mumbaiYash Kotgirwar
 
Road Widening In Bangalore
Road Widening In BangaloreRoad Widening In Bangalore
Road Widening In Bangaloreguest9ab0ac5
 
TOD Karo - Challenges and Opportunities in Implementing TOD Principles in India
TOD Karo - Challenges and Opportunities in Implementing TOD Principles in IndiaTOD Karo - Challenges and Opportunities in Implementing TOD Principles in India
TOD Karo - Challenges and Opportunities in Implementing TOD Principles in IndiaWRI Ross Center for Sustainable Cities
 
Transit oriented development
Transit oriented developmentTransit oriented development
Transit oriented developmentPooja Jariwala
 
BRTS Ahmadabad, innovative project
BRTS Ahmadabad, innovative project BRTS Ahmadabad, innovative project
BRTS Ahmadabad, innovative project Ar Vandana Talikoti
 
Hindustan construction company
Hindustan construction companyHindustan construction company
Hindustan construction companyRaushan Pandey
 
ABIDe TF Public Consultation
ABIDe TF Public ConsultationABIDe TF Public Consultation
ABIDe TF Public ConsultationSuresh Ranganath
 
The Project Management of the Manhattan High Line
The Project Management of the Manhattan High LineThe Project Management of the Manhattan High Line
The Project Management of the Manhattan High Lineskipafew
 
Sustainable urban travel- brts ahmedabad,brts pune,suburban railway mumbai
Sustainable urban travel- brts ahmedabad,brts pune,suburban railway mumbaiSustainable urban travel- brts ahmedabad,brts pune,suburban railway mumbai
Sustainable urban travel- brts ahmedabad,brts pune,suburban railway mumbaiGargee Ghosh
 
IRJET- Mobility Planning for an Indian Pilgrimage City- A Case of Omkares...
IRJET-  	  Mobility Planning for an Indian Pilgrimage City- A Case of Omkares...IRJET-  	  Mobility Planning for an Indian Pilgrimage City- A Case of Omkares...
IRJET- Mobility Planning for an Indian Pilgrimage City- A Case of Omkares...IRJET Journal
 

Tendances (19)

Neighborhood planning in capital city of chandigarh an appraisal
Neighborhood planning in capital city of chandigarh  an appraisal Neighborhood planning in capital city of chandigarh  an appraisal
Neighborhood planning in capital city of chandigarh an appraisal
 
Trasnportation system of mumbai
Trasnportation system of  mumbaiTrasnportation system of  mumbai
Trasnportation system of mumbai
 
Road Widening In Bangalore
Road Widening In BangaloreRoad Widening In Bangalore
Road Widening In Bangalore
 
TOD in India
TOD in IndiaTOD in India
TOD in India
 
B2I
B2IB2I
B2I
 
Oco booklet gehl_itdp
Oco booklet gehl_itdpOco booklet gehl_itdp
Oco booklet gehl_itdp
 
TOD Karo - Challenges and Opportunities in Implementing TOD Principles in India
TOD Karo - Challenges and Opportunities in Implementing TOD Principles in IndiaTOD Karo - Challenges and Opportunities in Implementing TOD Principles in India
TOD Karo - Challenges and Opportunities in Implementing TOD Principles in India
 
Times of India - 24-Feb-2015
Times of India - 24-Feb-2015Times of India - 24-Feb-2015
Times of India - 24-Feb-2015
 
Transit oriented development
Transit oriented developmentTransit oriented development
Transit oriented development
 
Jnnurm uig overview
Jnnurm uig overviewJnnurm uig overview
Jnnurm uig overview
 
B2I
B2IB2I
B2I
 
BRTS Ahmadabad, innovative project
BRTS Ahmadabad, innovative project BRTS Ahmadabad, innovative project
BRTS Ahmadabad, innovative project
 
Hindustan construction company
Hindustan construction companyHindustan construction company
Hindustan construction company
 
ABIDe TF Public Consultation
ABIDe TF Public ConsultationABIDe TF Public Consultation
ABIDe TF Public Consultation
 
The Project Management of the Manhattan High Line
The Project Management of the Manhattan High LineThe Project Management of the Manhattan High Line
The Project Management of the Manhattan High Line
 
Managing Urban Expansion
Managing Urban ExpansionManaging Urban Expansion
Managing Urban Expansion
 
Sustainable urban travel- brts ahmedabad,brts pune,suburban railway mumbai
Sustainable urban travel- brts ahmedabad,brts pune,suburban railway mumbaiSustainable urban travel- brts ahmedabad,brts pune,suburban railway mumbai
Sustainable urban travel- brts ahmedabad,brts pune,suburban railway mumbai
 
IRJET- Mobility Planning for an Indian Pilgrimage City- A Case of Omkares...
IRJET-  	  Mobility Planning for an Indian Pilgrimage City- A Case of Omkares...IRJET-  	  Mobility Planning for an Indian Pilgrimage City- A Case of Omkares...
IRJET- Mobility Planning for an Indian Pilgrimage City- A Case of Omkares...
 
SIXSeoul13 Day 1: Seoul City - Won Soon Park
SIXSeoul13 Day 1: Seoul City - Won Soon Park SIXSeoul13 Day 1: Seoul City - Won Soon Park
SIXSeoul13 Day 1: Seoul City - Won Soon Park
 

Similaire à Mumbai megaproject presentation_24_september_2011

MMRDA All You Need To Know.pptx
MMRDA All You Need To Know.pptxMMRDA All You Need To Know.pptx
MMRDA All You Need To Know.pptxHonest Broker
 
Re New Mumbai by Arshad Balwa
Re New Mumbai by Arshad BalwaRe New Mumbai by Arshad Balwa
Re New Mumbai by Arshad BalwaArshadbalwa
 
Navi Mumbai is the world's largest planned city.pdf
Navi Mumbai is the world's largest planned city.pdfNavi Mumbai is the world's largest planned city.pdf
Navi Mumbai is the world's largest planned city.pdfyamunaNMH
 
Effectiveness of skywalks in mumbai
Effectiveness of skywalks in mumbaiEffectiveness of skywalks in mumbai
Effectiveness of skywalks in mumbaiSamik Roy
 
Mumbai megaproject urban_equity_withdrawal_plan
Mumbai megaproject urban_equity_withdrawal_planMumbai megaproject urban_equity_withdrawal_plan
Mumbai megaproject urban_equity_withdrawal_planMumbai_Megaproject
 
Pune Municipal Corporation: Municipal Bonds Case Study
Pune Municipal Corporation: Municipal Bonds Case StudyPune Municipal Corporation: Municipal Bonds Case Study
Pune Municipal Corporation: Municipal Bonds Case StudyAuctus Advisors Pvt Ltd
 
Responses to the mumbai megaproject cm maharashtra_and_mumbai_first
Responses to the mumbai megaproject cm maharashtra_and_mumbai_firstResponses to the mumbai megaproject cm maharashtra_and_mumbai_first
Responses to the mumbai megaproject cm maharashtra_and_mumbai_firstAshish Puntambekar
 
Mumbai heritage structures_preservation_programme
Mumbai heritage structures_preservation_programmeMumbai heritage structures_preservation_programme
Mumbai heritage structures_preservation_programmeMumbai_Megaproject
 
Making mumbai a_safer_city_the_mumbai_999_report
Making mumbai a_safer_city_the_mumbai_999_reportMaking mumbai a_safer_city_the_mumbai_999_report
Making mumbai a_safer_city_the_mumbai_999_reportMumbai_Megaproject
 
Trans harbour relocation_of_mumbai_port
Trans harbour relocation_of_mumbai_portTrans harbour relocation_of_mumbai_port
Trans harbour relocation_of_mumbai_portMumbai_Megaproject
 
Mumbai megaproject smart_city_blueprint
Mumbai megaproject smart_city_blueprintMumbai megaproject smart_city_blueprint
Mumbai megaproject smart_city_blueprintMumbai_Megaproject
 
Mumbai megaproject slum_re_development_megaproject
Mumbai megaproject slum_re_development_megaprojectMumbai megaproject slum_re_development_megaproject
Mumbai megaproject slum_re_development_megaprojectMumbai_Megaproject
 
Megaproject control system_communications_platform
Megaproject control system_communications_platformMegaproject control system_communications_platform
Megaproject control system_communications_platformMumbai_Megaproject
 
Wadhwa Wise City Concept-1.pdf
Wadhwa Wise City Concept-1.pdfWadhwa Wise City Concept-1.pdf
Wadhwa Wise City Concept-1.pdfssuser9aea942
 
The kuber heights_financial_centre
The kuber heights_financial_centreThe kuber heights_financial_centre
The kuber heights_financial_centreMumbai_Megaproject
 

Similaire à Mumbai megaproject presentation_24_september_2011 (20)

Cidco- NAVI MUMBAI
Cidco- NAVI MUMBAICidco- NAVI MUMBAI
Cidco- NAVI MUMBAI
 
MMRDA All You Need To Know.pptx
MMRDA All You Need To Know.pptxMMRDA All You Need To Know.pptx
MMRDA All You Need To Know.pptx
 
Re New Mumbai by Arshad Balwa
Re New Mumbai by Arshad BalwaRe New Mumbai by Arshad Balwa
Re New Mumbai by Arshad Balwa
 
Mumbai DP
Mumbai DPMumbai DP
Mumbai DP
 
Navi Mumbai is the world's largest planned city.pdf
Navi Mumbai is the world's largest planned city.pdfNavi Mumbai is the world's largest planned city.pdf
Navi Mumbai is the world's largest planned city.pdf
 
Effectiveness of skywalks in mumbai
Effectiveness of skywalks in mumbaiEffectiveness of skywalks in mumbai
Effectiveness of skywalks in mumbai
 
New mumbai
New mumbaiNew mumbai
New mumbai
 
Mumbai megaproject urban_equity_withdrawal_plan
Mumbai megaproject urban_equity_withdrawal_planMumbai megaproject urban_equity_withdrawal_plan
Mumbai megaproject urban_equity_withdrawal_plan
 
Pune Municipal Corporation: Municipal Bonds Case Study
Pune Municipal Corporation: Municipal Bonds Case StudyPune Municipal Corporation: Municipal Bonds Case Study
Pune Municipal Corporation: Municipal Bonds Case Study
 
Responses to the mumbai megaproject cm maharashtra_and_mumbai_first
Responses to the mumbai megaproject cm maharashtra_and_mumbai_firstResponses to the mumbai megaproject cm maharashtra_and_mumbai_first
Responses to the mumbai megaproject cm maharashtra_and_mumbai_first
 
Mumbai heritage structures_preservation_programme
Mumbai heritage structures_preservation_programmeMumbai heritage structures_preservation_programme
Mumbai heritage structures_preservation_programme
 
Making mumbai a_safer_city_the_mumbai_999_report
Making mumbai a_safer_city_the_mumbai_999_reportMaking mumbai a_safer_city_the_mumbai_999_report
Making mumbai a_safer_city_the_mumbai_999_report
 
Trans harbour relocation_of_mumbai_port
Trans harbour relocation_of_mumbai_portTrans harbour relocation_of_mumbai_port
Trans harbour relocation_of_mumbai_port
 
ppt. pptx
ppt.                                                 pptxppt.                                                 pptx
ppt. pptx
 
Mumbai megaproject smart_city_blueprint
Mumbai megaproject smart_city_blueprintMumbai megaproject smart_city_blueprint
Mumbai megaproject smart_city_blueprint
 
Sea link (2)
Sea link (2)Sea link (2)
Sea link (2)
 
Mumbai megaproject slum_re_development_megaproject
Mumbai megaproject slum_re_development_megaprojectMumbai megaproject slum_re_development_megaproject
Mumbai megaproject slum_re_development_megaproject
 
Megaproject control system_communications_platform
Megaproject control system_communications_platformMegaproject control system_communications_platform
Megaproject control system_communications_platform
 
Wadhwa Wise City Concept-1.pdf
Wadhwa Wise City Concept-1.pdfWadhwa Wise City Concept-1.pdf
Wadhwa Wise City Concept-1.pdf
 
The kuber heights_financial_centre
The kuber heights_financial_centreThe kuber heights_financial_centre
The kuber heights_financial_centre
 

Plus de The Nataraja Foundation

Vivekanand education megaproject_cover_letter_to_the_prime_minister_11_feb_2015
Vivekanand education megaproject_cover_letter_to_the_prime_minister_11_feb_2015Vivekanand education megaproject_cover_letter_to_the_prime_minister_11_feb_2015
Vivekanand education megaproject_cover_letter_to_the_prime_minister_11_feb_2015The Nataraja Foundation
 
Opex Financing Plan_Vivekananda_Education_Megaproject
Opex Financing Plan_Vivekananda_Education_MegaprojectOpex Financing Plan_Vivekananda_Education_Megaproject
Opex Financing Plan_Vivekananda_Education_MegaprojectThe Nataraja Foundation
 
Capex Financing Plan_Vivekananda_Education_Megaproject
Capex Financing Plan_Vivekananda_Education_MegaprojectCapex Financing Plan_Vivekananda_Education_Megaproject
Capex Financing Plan_Vivekananda_Education_MegaprojectThe Nataraja Foundation
 
Vivekanand Education Megaproject_Cover_Letter_To_The_Prime_Minister
Vivekanand Education Megaproject_Cover_Letter_To_The_Prime_MinisterVivekanand Education Megaproject_Cover_Letter_To_The_Prime_Minister
Vivekanand Education Megaproject_Cover_Letter_To_The_Prime_MinisterThe Nataraja Foundation
 
Opex Financing Plan_Vivekananda_Education_Megaproject
Opex Financing Plan_Vivekananda_Education_MegaprojectOpex Financing Plan_Vivekananda_Education_Megaproject
Opex Financing Plan_Vivekananda_Education_MegaprojectThe Nataraja Foundation
 
Rising rape in india why is it happening and_how_do we fix the problem
Rising rape in india why is it happening and_how_do we fix the problemRising rape in india why is it happening and_how_do we fix the problem
Rising rape in india why is it happening and_how_do we fix the problemThe Nataraja Foundation
 
Governance now article_rising_rape_and_the_role_of_the_planning_commission
Governance now article_rising_rape_and_the_role_of_the_planning_commissionGovernance now article_rising_rape_and_the_role_of_the_planning_commission
Governance now article_rising_rape_and_the_role_of_the_planning_commissionThe Nataraja Foundation
 
Rising crime and the role of the planning commission
Rising crime and the role of the planning commissionRising crime and the role of the planning commission
Rising crime and the role of the planning commissionThe Nataraja Foundation
 
The technology velocity_concept_in_clean_energy_project_design
The technology velocity_concept_in_clean_energy_project_designThe technology velocity_concept_in_clean_energy_project_design
The technology velocity_concept_in_clean_energy_project_designThe Nataraja Foundation
 
The indian primary_and_secondary_education_megaproject
The indian primary_and_secondary_education_megaprojectThe indian primary_and_secondary_education_megaproject
The indian primary_and_secondary_education_megaprojectThe Nataraja Foundation
 

Plus de The Nataraja Foundation (12)

Vivekanand education megaproject_cover_letter_to_the_prime_minister_11_feb_2015
Vivekanand education megaproject_cover_letter_to_the_prime_minister_11_feb_2015Vivekanand education megaproject_cover_letter_to_the_prime_minister_11_feb_2015
Vivekanand education megaproject_cover_letter_to_the_prime_minister_11_feb_2015
 
Opex Financing Plan_Vivekananda_Education_Megaproject
Opex Financing Plan_Vivekananda_Education_MegaprojectOpex Financing Plan_Vivekananda_Education_Megaproject
Opex Financing Plan_Vivekananda_Education_Megaproject
 
Capex Financing Plan_Vivekananda_Education_Megaproject
Capex Financing Plan_Vivekananda_Education_MegaprojectCapex Financing Plan_Vivekananda_Education_Megaproject
Capex Financing Plan_Vivekananda_Education_Megaproject
 
Vivekanand Education Megaproject_Cover_Letter_To_The_Prime_Minister
Vivekanand Education Megaproject_Cover_Letter_To_The_Prime_MinisterVivekanand Education Megaproject_Cover_Letter_To_The_Prime_Minister
Vivekanand Education Megaproject_Cover_Letter_To_The_Prime_Minister
 
Opex Financing Plan_Vivekananda_Education_Megaproject
Opex Financing Plan_Vivekananda_Education_MegaprojectOpex Financing Plan_Vivekananda_Education_Megaproject
Opex Financing Plan_Vivekananda_Education_Megaproject
 
Rising rape in india why is it happening and_how_do we fix the problem
Rising rape in india why is it happening and_how_do we fix the problemRising rape in india why is it happening and_how_do we fix the problem
Rising rape in india why is it happening and_how_do we fix the problem
 
Governance now article_rising_rape_and_the_role_of_the_planning_commission
Governance now article_rising_rape_and_the_role_of_the_planning_commissionGovernance now article_rising_rape_and_the_role_of_the_planning_commission
Governance now article_rising_rape_and_the_role_of_the_planning_commission
 
Rising crime and the role of the planning commission
Rising crime and the role of the planning commissionRising crime and the role of the planning commission
Rising crime and the role of the planning commission
 
Can we do better than The RTE Act ?
Can we do better than The RTE Act ?Can we do better than The RTE Act ?
Can we do better than The RTE Act ?
 
The technology velocity_concept_in_clean_energy_project_design
The technology velocity_concept_in_clean_energy_project_designThe technology velocity_concept_in_clean_energy_project_design
The technology velocity_concept_in_clean_energy_project_design
 
The indian primary_and_secondary_education_megaproject
The indian primary_and_secondary_education_megaprojectThe indian primary_and_secondary_education_megaproject
The indian primary_and_secondary_education_megaproject
 
Military and sainik_schools_letter
Military and sainik_schools_letterMilitary and sainik_schools_letter
Military and sainik_schools_letter
 

Dernier

Sobha Aranya Sector 80 Gurgaon E- Brochure.pdf
Sobha Aranya Sector 80 Gurgaon E- Brochure.pdfSobha Aranya Sector 80 Gurgaon E- Brochure.pdf
Sobha Aranya Sector 80 Gurgaon E- Brochure.pdffaheemali990101
 
Everything you ever Wanted to Know about Florida Property Tax Exemptions.pdf
Everything you ever Wanted to Know about Florida Property Tax Exemptions.pdfEverything you ever Wanted to Know about Florida Property Tax Exemptions.pdf
Everything you ever Wanted to Know about Florida Property Tax Exemptions.pdfTim Wilmath
 
Experion Elements Sector 45 Noida_Brochure.pdf.pdf
Experion Elements Sector 45 Noida_Brochure.pdf.pdfExperion Elements Sector 45 Noida_Brochure.pdf.pdf
Experion Elements Sector 45 Noida_Brochure.pdf.pdfkratirudram
 
Ajmera Prive at Juhu, Mumbai E-Brochure.pdf
Ajmera Prive at Juhu, Mumbai  E-Brochure.pdfAjmera Prive at Juhu, Mumbai  E-Brochure.pdf
Ajmera Prive at Juhu, Mumbai E-Brochure.pdfManishSaxena95
 
Shapoorji Spectra Sensorium Hinjewadi Pune | E-Brochure
Shapoorji Spectra Sensorium Hinjewadi Pune | E-BrochureShapoorji Spectra Sensorium Hinjewadi Pune | E-Brochure
Shapoorji Spectra Sensorium Hinjewadi Pune | E-BrochureOmanaConsulting
 
The Role of Mortgage Brokers in Retirement Housing: Key Considerations
The Role of Mortgage Brokers in Retirement Housing: Key ConsiderationsThe Role of Mortgage Brokers in Retirement Housing: Key Considerations
The Role of Mortgage Brokers in Retirement Housing: Key Considerationssunlite Mortgage
 
Kolte Patil Universe Hinjewadi Pune Brochure.pdf
Kolte Patil Universe Hinjewadi Pune Brochure.pdfKolte Patil Universe Hinjewadi Pune Brochure.pdf
Kolte Patil Universe Hinjewadi Pune Brochure.pdfPrachiRudram
 
Prestige Somerville Whitefield Bangalore E- Brochure.pdf
Prestige Somerville Whitefield Bangalore E- Brochure.pdfPrestige Somerville Whitefield Bangalore E- Brochure.pdf
Prestige Somerville Whitefield Bangalore E- Brochure.pdffaheemali990101
 
What Is Biophilic Design .pdf
What Is Biophilic Design            .pdfWhat Is Biophilic Design            .pdf
What Is Biophilic Design .pdfyamunaNMH
 
SVN Live 4.22.24 Weekly Property Broadcast
SVN Live 4.22.24 Weekly Property BroadcastSVN Live 4.22.24 Weekly Property Broadcast
SVN Live 4.22.24 Weekly Property BroadcastSVN International Corp.
 
LCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptx
LCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptxLCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptx
LCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptxTom Blefko
 
Prestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdf
Prestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdfPrestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdf
Prestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdffaheemali990101
 
A Brief History of Intangibles in Ad Valorem Taxation.pdf
A Brief History of Intangibles in Ad Valorem Taxation.pdfA Brief History of Intangibles in Ad Valorem Taxation.pdf
A Brief History of Intangibles in Ad Valorem Taxation.pdfTim Wilmath
 
Kumar Fireworks Hadapsar Link Road Pune Brochure.pdf
Kumar Fireworks Hadapsar Link Road Pune Brochure.pdfKumar Fireworks Hadapsar Link Road Pune Brochure.pdf
Kumar Fireworks Hadapsar Link Road Pune Brochure.pdfBabyrudram
 
Rustomjee The Panorama At Pali Hill, Bandra West, Mumbai - Brochure.pdf
Rustomjee The Panorama At Pali Hill, Bandra West, Mumbai - Brochure.pdfRustomjee The Panorama At Pali Hill, Bandra West, Mumbai - Brochure.pdf
Rustomjee The Panorama At Pali Hill, Bandra West, Mumbai - Brochure.pdfmonikasharma630
 
Ryan Mahoney - How Property Technology Is Altering the Real Estate Market
Ryan Mahoney - How Property Technology Is Altering the Real Estate MarketRyan Mahoney - How Property Technology Is Altering the Real Estate Market
Ryan Mahoney - How Property Technology Is Altering the Real Estate MarketRyan Mahoney
 
Choose Noida's Leading Architect
Choose    Noida's    Leading   ArchitectChoose    Noida's    Leading   Architect
Choose Noida's Leading ArchitectMM Design Studio
 
What-are-the-latest-modular-wardrobe-designs.pdf
What-are-the-latest-modular-wardrobe-designs.pdfWhat-are-the-latest-modular-wardrobe-designs.pdf
What-are-the-latest-modular-wardrobe-designs.pdfKams Designer Zone
 
Ebullient Investments Limited specializes in Building contractor
Ebullient Investments Limited specializes in Building contractorEbullient Investments Limited specializes in Building contractor
Ebullient Investments Limited specializes in Building contractorEbullient Investments Limited
 

Dernier (20)

Sobha Aranya Sector 80 Gurgaon E- Brochure.pdf
Sobha Aranya Sector 80 Gurgaon E- Brochure.pdfSobha Aranya Sector 80 Gurgaon E- Brochure.pdf
Sobha Aranya Sector 80 Gurgaon E- Brochure.pdf
 
Everything you ever Wanted to Know about Florida Property Tax Exemptions.pdf
Everything you ever Wanted to Know about Florida Property Tax Exemptions.pdfEverything you ever Wanted to Know about Florida Property Tax Exemptions.pdf
Everything you ever Wanted to Know about Florida Property Tax Exemptions.pdf
 
Experion Elements Sector 45 Noida_Brochure.pdf.pdf
Experion Elements Sector 45 Noida_Brochure.pdf.pdfExperion Elements Sector 45 Noida_Brochure.pdf.pdf
Experion Elements Sector 45 Noida_Brochure.pdf.pdf
 
Ajmera Prive at Juhu, Mumbai E-Brochure.pdf
Ajmera Prive at Juhu, Mumbai  E-Brochure.pdfAjmera Prive at Juhu, Mumbai  E-Brochure.pdf
Ajmera Prive at Juhu, Mumbai E-Brochure.pdf
 
Shapoorji Spectra Sensorium Hinjewadi Pune | E-Brochure
Shapoorji Spectra Sensorium Hinjewadi Pune | E-BrochureShapoorji Spectra Sensorium Hinjewadi Pune | E-Brochure
Shapoorji Spectra Sensorium Hinjewadi Pune | E-Brochure
 
The Role of Mortgage Brokers in Retirement Housing: Key Considerations
The Role of Mortgage Brokers in Retirement Housing: Key ConsiderationsThe Role of Mortgage Brokers in Retirement Housing: Key Considerations
The Role of Mortgage Brokers in Retirement Housing: Key Considerations
 
Kolte Patil Universe Hinjewadi Pune Brochure.pdf
Kolte Patil Universe Hinjewadi Pune Brochure.pdfKolte Patil Universe Hinjewadi Pune Brochure.pdf
Kolte Patil Universe Hinjewadi Pune Brochure.pdf
 
young call girls in Lajpat Nagar,🔝 9953056974 🔝 escort Service
young call girls in Lajpat Nagar,🔝 9953056974 🔝 escort Serviceyoung call girls in Lajpat Nagar,🔝 9953056974 🔝 escort Service
young call girls in Lajpat Nagar,🔝 9953056974 🔝 escort Service
 
Prestige Somerville Whitefield Bangalore E- Brochure.pdf
Prestige Somerville Whitefield Bangalore E- Brochure.pdfPrestige Somerville Whitefield Bangalore E- Brochure.pdf
Prestige Somerville Whitefield Bangalore E- Brochure.pdf
 
What Is Biophilic Design .pdf
What Is Biophilic Design            .pdfWhat Is Biophilic Design            .pdf
What Is Biophilic Design .pdf
 
SVN Live 4.22.24 Weekly Property Broadcast
SVN Live 4.22.24 Weekly Property BroadcastSVN Live 4.22.24 Weekly Property Broadcast
SVN Live 4.22.24 Weekly Property Broadcast
 
LCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptx
LCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptxLCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptx
LCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptx
 
Prestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdf
Prestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdfPrestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdf
Prestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdf
 
A Brief History of Intangibles in Ad Valorem Taxation.pdf
A Brief History of Intangibles in Ad Valorem Taxation.pdfA Brief History of Intangibles in Ad Valorem Taxation.pdf
A Brief History of Intangibles in Ad Valorem Taxation.pdf
 
Kumar Fireworks Hadapsar Link Road Pune Brochure.pdf
Kumar Fireworks Hadapsar Link Road Pune Brochure.pdfKumar Fireworks Hadapsar Link Road Pune Brochure.pdf
Kumar Fireworks Hadapsar Link Road Pune Brochure.pdf
 
Rustomjee The Panorama At Pali Hill, Bandra West, Mumbai - Brochure.pdf
Rustomjee The Panorama At Pali Hill, Bandra West, Mumbai - Brochure.pdfRustomjee The Panorama At Pali Hill, Bandra West, Mumbai - Brochure.pdf
Rustomjee The Panorama At Pali Hill, Bandra West, Mumbai - Brochure.pdf
 
Ryan Mahoney - How Property Technology Is Altering the Real Estate Market
Ryan Mahoney - How Property Technology Is Altering the Real Estate MarketRyan Mahoney - How Property Technology Is Altering the Real Estate Market
Ryan Mahoney - How Property Technology Is Altering the Real Estate Market
 
Choose Noida's Leading Architect
Choose    Noida's    Leading   ArchitectChoose    Noida's    Leading   Architect
Choose Noida's Leading Architect
 
What-are-the-latest-modular-wardrobe-designs.pdf
What-are-the-latest-modular-wardrobe-designs.pdfWhat-are-the-latest-modular-wardrobe-designs.pdf
What-are-the-latest-modular-wardrobe-designs.pdf
 
Ebullient Investments Limited specializes in Building contractor
Ebullient Investments Limited specializes in Building contractorEbullient Investments Limited specializes in Building contractor
Ebullient Investments Limited specializes in Building contractor
 

Mumbai megaproject presentation_24_september_2011

  • 1. THE MUMBAI MEGAPROJECT Rev 00 Re – Imagining The Mumbai Metropolitan Region (MMR) “ The Future Landscape Of Mumbai " – A FLO Initiative Supported by Deutsche Bank Bombay Chapter The Nataraja Foundation © Copyright June ‘ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved 24th September ‘ 2011
  • 2. NOTICES 1. LEGAL This document is protected by Indian Copyright Law. Please quote your source while referring to the ideas contained herein to avoid legal action 2. CONCEPT COMPLETENESS The Mumbai Megaproject is fully defined by two documents as follows : 1. This Presentation and … 2. Project Excel Workbook ( Excel Motherfile ) which contains all project calculations and financing details City Authorities will need to go through both the documents to obtain a detailed understanding about the subject matter presented. 2 © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 3. CONTENTS CENTRAL DEVELOPMENT CONCEPT EXECUTIVE SUMMARY MUMBAI : CURRENT STATUS Macro Urban “ Quality of Life ” Indicators Mumbai City : Current Status … In Pictures Showstoppers…Improper Governance,Huge Debt &Technical In-competence THE MUMBAI MEGAPROJECT 2014 – 2023 Project Concepts … The 13 Major Concepts … of a total of 24 Unique Ideas Engineering, Procurement, Construction & Project Logistics Issues PROJECT STARTUP … ACTIVITIES TO INITIATE PROJECT GOVERNMENT SUPPORT REQUIRED MUMBAI 2024 … CITY OF THE 21st CENTURY 3 © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 4. CENTRAL DEVELOPMENT CONCEPT Sarvodaya : “ The Rise Of All “ Dubai & China Model Mumbai Megaproject Model Mumbai Megaproject is based on Gandhiji’s “ Sarvodaya ” Model 4 © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 5. EXECUTIVE SUMMARY 1. Mumbai Mega-Project Macro Description An executable plan to totally re-build Mumbai in 9 – 10 years ( 2014 – 2023 ) Free Housing…Based on Dwelling Concept, For 9 Million Slum Dwellers in Mumbai Creation Of Financial Centers & Other Amenities … 2 Financial Centres , Universities etc Transport : 210 Km of Underground Subway…60 % Reduction in Network Load Original Islands to be separated & Harbour to be Re-Developed into A Mega Port Executing Intelligent Urbanism Concepts “ Creating Large Open Spaces, Theatres, Cycling Corridors, Theme Parks and Large Public Spaces “. 2. Proposed Additional Investments in Maharashtra State … Growth Catalysts Maharashtra High Speed Logistics Ring Corridor 2700 Km , 6 Lane , High Speed Ring Road Mumbai – Nashik - Nagpur – Gadchiroli – Nanded – Pune – Mumbai … Bullet Train 30,000 Check Dams to restore Water Table in Maharathwada & Vidharbha Plantation of 2.5 Million Hectares of Dense Forest + 7,000 Acres of Mangroves 20,000 Acre Maharathwada Eco - SEZ + 4 Eco Cities in Tribal Areas 5 Huge Development Project … Creation of 6 Million New Jobs in Maharashtra © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 6. EXECUTIVE SUMMARY 3. Project Macro Economic Impact Project Unlocks US $ 308 Billion of Value in Mumbai to Rebuild the City Mumbai GDP ($ 85 Bn) to triple by 2018, to exceed Singapore GDP @ $ 310.69 Billion by 2024 Infrastructure Investment Multiplier effect on Maharashtra economy > US $ 500 Billion Project Repays Entire US $ 46 Billion Debt of Maharashtra State … Single Bullet Payment Project implements President Kalam’s PURA Concept … Stops Mass Migration To Cities by investing US $ 90 Billion in Healthcare & Education across Rural India Rural Maharashtra Impact : US $ 200 Billion … ( Achieve Gandhiji’s vision of Rural Growth ) 4. Project Governance & Control Issues Project Execution & Control Imperatives to Minimize Funds Leakage : Mumbai Governance Structure needs more clarity Sophisticated IT Reporting System / Protocols to Execute Project … Zero Funds Leakage Transparent and Highly Centralized Procurement System for all Critical Items/ Contracts Two Stage International Bidding ( Stage I for Urban Designs, Stage II for EPC ) Empowered Organization to Plan & Execute Project … Govt. Agencies to compete for Contracts on same terms as private sector under international competitive bidding Procurement Standards : World Bank / EU Tendering Procedures & Reporting Formats 6 Project Brings Massive Development & Improves Governance in Maharashtra © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 7. MUMBAI : CURRENT STATUS 7 © Copyright June ‘ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 8. MACRO URBAN “ QUALITY OF LIFE ” INDICATORS Mumbai’s Population has exceeded 14 Million …Population density stands at 28000 Persons / sq km … worlds highest Highest % of Population in Slums for any city globally … 72 % Quality of life … Dharavi has 800 People per Toilet . … Local Transport Networks are stretched beyond limits … Water and Power Shortage is Acute Huge differences in Incomes … Growing Social Tension City looks like a giant garbage dump … most filthy metropolis In India City Still Produces 5 % of India’s GDP … Under Severe Constraints Land and Property Prices have become unaffordable for most people and Businesses … New Businesses are avoiding Mumbai Mumbai City Is Dying … There can be no two opinions about this 8 © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 9. Mumbai City : Current Status … In Pictures Mumbai Slum Population : 9.0 Million Total Population : 14.3 Million Source : 2011 Census Projections , GOI 9 72 % of Mumbai’s Population Lives like this in Slums © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 10. Showstoppers For Mumbai Re-Development 10 © Copyright June ‘ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 11. Showstopper 1 … Improper Governance Chief Minister Report to Vidhan Sabha Central Govt. Only 36 MLA’s out of 288 are From Mumbai Mayor Municipal Commissioner ( Not Answerable to Corporators ) Chairman MMRDA / MHADA/ CIDCO Mumbai Municipal Central Govt Vote in Elections Parallel Mayor’s Offce Corporation Agencies With No Executive Power Govt. Agencies ( MCGM ) Airports Authority, MMRDA / MHADA / CIDCO Port Trusts, Railways 227 Corporators 24 Wards , with large Population Source : Vote Mumbai Campaign No large Re-Development project is possible within current structure
  • 12. Showstopper 2 … Maharashtra’s Huge Debt Debt of Maharashtra State currently stands at Rs 2.09 Lakh Crores ( 2011) Debt is projected to increase to Rs 2.31 Lakh Crores by March 2012 This Huge Debt prevents State Govt from doing big projects Large projects are not possible unless Maharashtra’s debt is significantly reduced 12 © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 13. Showstopper 3 … Technical Incompetence Government Agencies Project Quality Very Serious Quality issues with Government Agencies Project Management 13 Skill Sets & Construction Work © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 14. THE MUMBAI MEGAROJECT PROJECT CONCEPTS … THE 13 Major Concepts ( Out of 24 ) © Copyright June ‘ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 15. Concept 1 : Eastern Seaboard Re-location & Re- Development Port Traffic is Choking City’s Road and Rail network Mumbai Eastern Seaboard to be Re-Developed after Re-Locating : - Mumbai Port Trust, FCI, Railways Housing for Urban Poor - RCF, BPCL & HPCL All Re-Located Facilities will be provided with financing for latest equipment and capacity expansion at a new location on land provided by Govt of Maharashtra. Relocation Critical in order to prevent possible disasters due to leakage of lethal chemicals like Ammonia, Chlorine and to Entire site to be raised 21 Ft avoid Crude Oil spills that are ( Rising Oceans Concept ). Followed by rest of Mumbai occurring frequently by 2050 ) Value Unlocked through Re-zoning : $ 70.45 Billion These Industries with huge toxic After providing for Entire Eastern Seaboard Re-Location and plant capacity expansion with latest technology and Environmental systems, including World chemical tanks are also prime class Employee Townships at New Locations in Maharashtra. © Copyright June ‘ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved terror targets. Pose Serious Threat.
  • 16. Concept 2 : Separation Of Islands Concepts : 1. De-Congest City 2. Prevent Flooding & Improve Sewage Disposal 3. Use water transport Unlock additional Value Through Differential FSI’s ( US $ 10 Billion ) 16 Original Islands To be Separated to De-Congest City and Prevent Flooding © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 17. Concept 3 : The Archipelago Concept Dense Mangroves , 7,000 Acres, 56 Km X 500 Mts 4 Lane , Subsea Road Tunnels Archipelago concept involves creation Western Archipelago Group of 3 New Islands of 4 New Islands. This will achieve two Trans Harbour Link objectives Logistics - Create Additional Amenities/Housing Super-Corridor - Allow Urban Equity Withdrawal for overall development of the state of Maharashtra & Nation through Massive Projects in Education, Healthcare, Forestry & Endangered Species Conservation New Mumbai Port Trust ( 600 Acre Superport ). 2.7 Km X 0.9 Km Hydraulic Model Studies including Western Islands Project Tidal Prism / Near Shore Current New Eastern Island Project Cost : US $ 184.50 Billion Assessments together with Sales Realization : US $ 308.06 Billion ( 6005 Acres 9.0 Km X 2.7 Km ) Financial Centre, Living Space, detailed Environmental Impact Net Surplus : US $ 123.56 Billion Entertainment Area assessment survey Project +Others (40) Inner Harbour Island Needed to 200 Mts wide Channel New Naval Base ( 900 Acres ) 100 – 200 confirm location and $ 332.10 + 40 Billion Project Cost : US configuration Km south of Mumbai of the islands. All:Islands to be 21 Ft Sales Realization US $ 475.30 Billion above MSL ( Rising Oceans103.20 Billion 17 Net Surplus : US $ Concept ) Urban Equity Withdrawal Through Facility Creation : $ 226.76 Billion © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 18. Concept 4 : Slum Re-Habilitation & Decongestion 45 Storey Towers with Regular Maintenance 2018 Estimated Project Cost : US $ 65 Billion Dwelling units with 500 Sq Ft carpet Slum Transition area to house all existing 9 Million Accommodation slum residents In-Situ. Any additional Migration to be settled on MMR fringes. Mumbai to have proper & detailed census before scheme is launched. Mapping to UID Number critical to check cheating. Specified Penalties for offenders … loss of house and work permit in Mumbai. 2011 High speed rail link to those who choose low rise accommodation elsewhere in MMR as space is critical . Increasing FSI to 12–16 levels is critical Megaproject has unique scheme for Slum Re-Habilitation. Zero Funds 18 Required From Govt. Of Maharashtra © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 19. Slum Re-Development : Megaproject Scheme Vs. Govt. Scheme SL. Parameter Current Govt. Schemes Mumbai Megaproject Scheme No 1 Coverage Case By Case Basis based on Blanket Scheme to cover all 9 Million Slum Dwellers Slum Re-Habilitation Authority in Mumbai , based on Dwelling Concept ( SRA ) Clearance 2 Proposed 269 Sq Ft per dwelling 500 Sq Ft per Dwelling Carpet Area 3 Financing Govt. Cross Subsidy Scheme. Mumbai Megaproject will bear entire US $ 65 Billion Towers for Slum Dwellers on just ( Rs 2,95,685 Crores ) Capex to provide Good Quality 20 % of Land Originally Occupied Housing to all 9 Million Slumdwellers on Dwelling by the Slum, Balance 80 % land Concept. Slum dwellers will keep 50 % of their land given to Builder for commercial and not just 20 % as in current Govt. Schemes. All development. Example Forjett Hill Accomodation will be provided In-Situ with No Re- below Altamount Road and in Location ( Important ) . Megaproject will build Chandivali near Powai commercial space on balance 50 % area, the rent from which will provide for maintenance of the buildings. 4 No of Floors Most Recent Govt Scheme 45 Storey Towers. All Construction will be High provides for 20 Storey Towers Intensity Earthquake Resistant and of world class standard (40 % higher cost due to Civil/Mechanical ). 5 Childrens Play Zero First Six Floors in Each Tower will be reserved for Area Children Playing Area and For Healthcare and Education of Tower Residents. 6 Maintenance Current Govt Scheme provides for On Project Completion Megaproject Authority will fund Maintenance of Buildings but it has 100 % of Maintenance (Estimated Cost = US $ 1.97 lot of grey areas and there is no Billion / Year ( at the rate of Rs 40,000 / Dwelling / year ). Finance will come from Rents as described Accountability if later on money is 19 above and from dividends on Megaproject Equity Not released for Maintenance. Investments. There will be Strict Monitoring of Costs. © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 20. Concept 5 : The Undersea Subway Ring Giant Tunnel Boring Machine Wholly Underground Highspeed Subway Rings to reduce transit time from Goregaon to Uran to 30 Minutes from 3 – 4 Hours Currently. New Navi Mumbai Airport will be on the New Subway Ring Facilities Creation To Unlock Huge Value in MMR Megaproject to finance 75 % of PPP Ventue Approx. Project Capex : $ 34.29 Billion 20 Vastly Improved Communications Infrastructure to Augment Economic Value Of MMR © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 21. Concept 6A : Sewage Treatment System ( New York Lookalike ) New Infrastructure to be built in MMR 12 Nos of 100 Mld of Sewage Treatment plants 4 Nos of 100 Mld Industrial Effluent Treatment plants Five solid Waste & Plastic Incenerators … to produce power Three New & Large Landfills. Deonar Landfill to be totally redesigned . Methane gas to power 2,00,000 houses Large New System of 75 ‘’ collection headers / pipelines to be laid throughout city ( 150 Km ) Solid biowaste to be processed into Fertilizer Megaproject to invest US $ 2.5 Billion in 21 C02 to be sequestered / CO2 Business Waste Treatment System Capex under PPP © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 22. Concept 6B : Combination Of Technologies for Waste Disposal Today ( 2011 ) 2018 Estimated Project Cost : US $ 4 Billion Megaproject To Catalyze Private Investment Through Strategic 22 Investment In Waste Treatment & Power Generation Projects © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 23. Concept 7: Unique PPP Scheme To Clean & Restore Mangroves Mangrove Destruction & Plastic Pollution 2016 Today ( 2011 ) Estimated Project Cost : US $ 300 Million Megaproject To Provide Grant Of US $ 300 Million To the Bombay Natural 23 History Society ( BNHS ) for Plantation of 7,000 Acres of Mangroves © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 24. Concept 8 : The Central Park Concept Re - zoning & Differential FSI’s to allow for the development of Parks within 10 minutes walking distance from anywhere within Mumbai City and Navi Mumbai Special Cyclist Only Corridors to be built along all arterial roads and coastal roads Excess Railway Land to be put to Public Use through GOI Ordinance Sales Proceeds to build Bullet Train24 Creation of Extensive System Of Interconnected Parks and Cycling Corridors © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 25. Concept 9 : Heritage Conservation Abu Simbel ( Egypt ) Lookalike restoration for some structures ?? Megaproject to allocate US $ 600 Million For Heritage Conservation 25 © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 26. ENGINEERING , PROCUREMENT , CONSTRUCTION & PROJECT LOGISTICS © Copyright June ‘ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 27. Concept 10 : The 72 Contractor Territories - MMR to be divided into 72 squares for project execution purposes - These 72 Work Areas will be put out on International Competitive Bidding - The Megaproject will feature 12 design concepts and 12 Large projects - The worlds largest and Best Design firms will compete with local companies & Govt Agencies to develop & design concepts for each project area. The best conceptual designs will be awarded the detailed design contracts. Evaluation will be by a panel of global experts. - 72 Contractor Territories to be awarded to 12 Large Global Consortia with work Value of US $ 30 Billion Each. Indian Companies to compete on same terms as Foreign EPC Contractors Megaproject Will Divide 72 Areas Into 12 Large Contractor Territories 27 … With Contractor having Single Point Responsibility © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 28. Concept 11 : Town Planning As a Biddable Item India produces just 200 Town Planners each year Total Townplanners Employed in India presently is 3300…for a total of 5600 Towns Govt. Agencies in Maharashtra do not have required number of Town Planners for Mumbai Megaproject Further there is large Scale Corruption in getting permissions and the city has grown in a totally un-planned manner There will therefore be a separate Town Planning Round , right at the beginning of the Mumbai Megaproject. Govt Agencies to Compete on Par with Private Players Megaproject Bidding Process Monitored by International Panel of Independent Experts Step 1 Step 2 Step 3 Step 4 Global Bidding Round Global Bidding Round Global Bidding Round Go into Construction for Mumbai Master for 12 Large Contractor for 12 Large Contractor Phase with Worlds Plan Territories ( Design ) of Territories ( EPC ) For Best Designs at the US $ 30 Billion Each each of 12 Winning Lowest Possible Designs EPC Cost World Bank / EU Contract Standards Applied to Above Process Will Deliver 28 City of the 21st Century © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 29. Concept 12 : Highly Accountable / Visible Project System Politically Accountable Authority Required to spearhead Megaproject Megaproject CEO will be Construction Expert ( Either Indian / Foreign ) with Acknowledged Leadership In The Construction Industry Globally Megaproject Management / Construction Team to be hired from around the world based on expert skill sets All Contracts to be awarded after International Competitive Bidding Separate Bidding Rounds For Town Planning & EPC …World Bank / EU Standards All Project Activity to be controlled through Highly Advanced IT System which ensures three things : Visibility / Transparency Accountability & Measurement of Outcomes Preservation of Context Entire Decision Making Hierarchy To Be Mapped … Deviations will Trigger A System Alert 29 Above Specified Advanced IT System is Critical to Project Execution… © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 30. Project Scale 11 Times Palm Jumeirah (Dubai ) 5 Times Islands Three Bricks 4 Nos Gorges 9 Billion Dam Concrete Circumferance 27.2 mill. cum Steel Piles of the Earth 600,000 Nos Total Engg / Arch. Design The Mumbai Pipelines Man hours Megaproject 40,000 kms 2014 - 2023 Peak construction 30,000 man-power Engineers Structural steel 450,000 & 3000 10 Million Tonnes Architects Electrical & for 3 years Instrument cables 350,000 Kms Earth To Moon 75 Eiffel Distance Towers Construction Intensity : Rs 300 Crores / Day for 7 years … 24 X 7 non stop 30 ( Assuming first 3 years for Engineering / Design / Project Planning / Governance Issues ) © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 31. Concept 13 : Non–Invasive Construction Logistics 31 Project will have minimal impact on traffic & normal business activity © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 32. Megaproject Startup … Activities To Initiate Project BAR CHART 1. Govt. To Initate Re-Location Discussions with Mumbai Port Trust, RCF,HPCL & BPCL, FCI & Railways 2. Appoint Surveyors / Consultants For Alternative Sites for Port/Industrials which allow for expansion of capacities 3. Fast Track Issue of UID Numbers to All Residents of the MMR 4. Varification of Detailed Demographic Data & Property Holdings & Mapping this to UID's for All Of Dwellings within MMR 5. Appointment of Project CEO / Staff for Megaproject. Critical Senior Staff in Place Executive Search firms to be commissioned to recruit highly specialized planning and execution team of 250 Project Managers, 2000 Engineers & 600 Architects / Townplanners from around the world First Global Tender 6. State Govt. Provides suitable land to allow for expansion of Re-Located Industrials free of all encumbrances.Start Physical Relocation Of Industrials, Issue First Global Tender for New Port / Underground Subway, Master Plan etc 32 © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 33. Government Support Required Megaproject needs politically accountable authority to spearhead project. State Government Needs to Order Relocation Of Harbour Based Industries & Mumbai Port Trust Project requires highly specialized team of owner managers ( 250 Project Managers , 2000 Engineers, 600 Architects / Townplanners Etc. Highly specialized construction team will need to be recruited internationally. One Time Grant of Rs 3000 Crores From JNNURM to finance Project Team Salaries Fully Empowered Political Authority Is Critical For Project Execution … Megaproject is Totally Self Financing After Initial JNNURM Grant of Rs 3000 33 Crores © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 34. Mumbai 2024 … City Of The 21st Century A Slum School 34 Mumbai to be Business, Entertainment & Culture Hub of South Asia © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 35. Mumbai Olympics 2024 ? Can Mumbai Make A Bid For The 2024 Olympics ? 35 © Copyright June ’ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved
  • 36. THANK YOU FOR YOUR ATTENTION Ashish Puntambekar Project Designer The Indian Education Megaproject & The Mumbai Megaproject www.nataraja.org.in 36 © Copyright June ‘ 2009 : Ashish Puntambekar, The Nataraja Foundation, Mumbai , All Rights Reserved ’