Team C Group Project

1

ITEC 640 Section 9081 Semester 1309
Group Project – Team C
Brian Palmer
Pamela Rich
Zach Salwen
Marcus Taite
Rahul Tanwar
DUE DATE: December 8, 2013
University of Maryland University College
Team C Group Project

2

October 15, 2013
Mr. Joe Smith
Riptide Swim Team
101 Main Street
Bristow, VA 20136
RE: Website for Riptide Swim Team
Dear Mr. Smith,
Thank you for providing Team C Consultants with the opportunity to develop a website to
support the Riptide Swim Team. Our expertise in providing quality web solutions to local
businesses will enable us to provide the swim team with a solution that will meet, or hopefully
exceed, your expectations. As discussed during the meeting last week, Team C Consultants is
pleased to provide the project plan proposal to support this effort. We have structured our
proposal with the following sections
I.
II.
III.

Statement of Need
Project Definition
Approach and Project Plan

It is our desire to establish a long-term relationship with the Riptide Swim Team. We are
committed to developing a partnership that will continue to meet all needs as they evolve. We
hope this will be the first of many opportunities to serve you.
I.

Statement of Need
It is understood that the Riptide Swim Team is in need of a web site. As the team has grown

over the past two years, the current method of emailing practice and meet schedules has become
inefficient for the coaches and is not the optimal way for parents and swimmers to receive this
information. Additionally, as a result of winning the state championship last year, the greater
community has a strong interest in supporting the team by attending the meets and cheering on
Team C Group Project

3

the local swimmers. The swim team is lacking a solution for communicating the meet schedule
and results to the community at large.
Given the outstanding performance of the swimmers, the swim team wants to promote their
successes by posting swim meet results and pictures on a website. This will help provide the
swimmers with greater visibility beyond the local community and could allow college recruiters
to learn about and follow the swimmers. This will also help promote the fun and excitement of
team swimming and could help to increase membership.
We understand the site needs to be fully functionally no later than the end of January 2014 to
support the Spring swim season, which begins on February 15. The site is to be launched with a
basic set of functions, but needs to have the ability to scale as new requirements are identified
and the number of users grows. It is important that future enhancements can be easily added to
current functionality, without requiring major architectural changes. Content must be
maintainable internally, without reliance on Team C Consultants to add or change content. The
site must be intuitive and inviting, with a modern look.
II.

Project Definition

Project Description
Team C Consultants is prepared to develop ‘Project Swim Lane’ (PSL) to meet the needs of
the Riptide Swim team. The purpose of this project is to create a website that is attractive,
informative, and engaging for the coaches, swimmers, parents and the local community. The
website will function as a platform for providing information to children between the ages of 6
and 18, and/or their parents, who have an interest in joining the swim team. This website will
also provide information regarding the scheduled swim practices and meets and will post results
and photos from the meets.
Team C Group Project
Project Scope
● To design, develop and implement an interactive website using Web 2.0 technologies to
enable users to get timely information, add content and share with other members of the
swim team and the community
● To develop a website that is accessible to the general public and allows visitors to sign up
and request additional information about the team
● To develop a database of users to store profile information and login credentials for
privileged site users
● To develop a database to store, retrieve and display scheduling information for practices,
scheduling information for swim meets and the results of swim meets.
● To develop a content file management system to effectively store, retrieve and display
picture images
● To provide administration capability to update the website with up-to-date information,
relevant content and manager users.
● To develop a website that is search engine optimized to drive traffic to the website
In Scope Requirements
1. Home Page
1.1. The website will provide a home page that is accessible to the public.
1.2. The home page will provide general information about the swim team and contact
information to get additional information.
1.3. The home page will include a navigation menu to access other pages on the site.
1.3.1. The navigation menu will be accessible on all pages.
1.4. The home page will provide the capability to request more information from the
coaching staff.
1.4.1. Any visitor to the site will have the ability to provide their name, phone number,
email and a message will be sent to the coaching staff to request additional
information.
2. Swim Meet Page
2.1. The website will include a Swim Meet page that is accessible to the public.

4
Team C Group Project

5

2.2. The Swim Meet page will provide a calendar that lists upcoming meets for the next 12
months.
2.2.1. Each swim meet calendar entry will include the date, time, location and events for
the meet.
2.3. The Swim Meet page will provide the capability to view results of the past 12 months
meets.
2.4. The Swim Meet page will provide the capability to view photos from swim meets.
2.4.1. The names of swimmers and coaches will be identified on the photos.
3. Swim Practice Page
3.1. The website will provide a Swim Practice page that is accessible to the public.
3.2. The Swim Practice page will provide a calendar that lists swim practices for the next 12
months.
3.2.1. Each swim practice calendar entry will include the date, time, location and notes
for the practice.
4. Photo Gallery
4.1. The website will include a Photo Gallery page that is accessible to the public.
4.1.1. The Photo Gallery page will identify the names of swimmers and coaches in the
photos.
5. Coaching Staff Page
5.1. The website will provide a Coaching Staff page that is accessible to the public and
provides a bio, photo and contact information for the coaching staff.
6. User Administration
6.1. The website will provide a user administration capability that provides registered admins
the ability to create, update and delete user ids.
6.1.1. Registered admins will have the ability to add, change and remove permissions
for every user id.
6.2. User Permissions to be assigned to user ids include:
6.2.1. Ability to create, update and delete text/content on each page
6.2.2. Ability to upload and remove photos on each page
Team C Group Project

6

6.2.3. Ability to upload and remove documents on each page
6.2.4. Ability to create, update and delete calendar events
6.2.5. Ability to access a page (e.g. the Photo Gallery, User Administration, etc.)
6.3. The website will require registered users to log on with a user id and password to access
restricted pages.
7. Content Administration
7.1. The website will include a Content Administration capability that allows registered users
to create, maintain and delete website content.
7.2. Users with Content Administration capabilities will have the ability to edit pages in an
easy use rich text editor.
7.2.1. The rich text editor will allow content administrators to add, change and format
text to be displayed on the pages.
7.2.2. The rich text editor will allow content administrators to upload photos and add
captions.
7.3. Content administrator will have the ability to upload documents.
7.4. Content administrator will have the ability to link to uploaded documents.
7.5. Content Administrator will have the ability to create, update and delete events on the
calendars.
7.6. Content Administrator permissions will determine which pages and calendars can be
updated.
8. System Requirements
8.1. The website will be accessible over HTTP using modern web browsers
8.2. The website will be compatible with PC or Apple browsers
8.3. The website will be hosted on a secure web server platform
8.4. The system will provide sufficient security access controls to ensure any private
information is stored securely on the hosted database servers.
8.5. The system will provide the capability to view and analyze website traffic and hits
reports and metrics
Team C Group Project

7

Out of Scope Requirements – deferred to a future phase
1. Parents Page
1.1. The website will include a Parents Page that is accessible only to registered users with
Parent permissions.
1.2. The Parents Page will provide a calendar that displays the volunteer schedule.
Measurable Organizational Value (MOV)
Develop and implement a functional website that will provide current information and
photos to all parents, children, and coaches, which will improve swim meet attendance by 20%
and increase membership registration by 25% within 12 months.
Project Stakeholders
The principal stakeholders for the PSL project plan are listed in Table 1.
Table 1: Principal Stakeholders

Stakeholder/
Title

Interest

Influence

Role

Team
Prospects

0

0

User

Team Coach

+1

5

Project
sponsor

Assistant
Coaches

+1

2

Content
Providers

+1

0

Parental
Association

+1

3

Potential Conflict

Objective
Find out
information about
joining the swim
team

Does not want the
parental
association's pet
project created just
yet.

Provide resources,
approvals, and
public support for
the project
Have their
information
displayed on the
team site

User

Manage site
information about
the swim team
Want the site to
feature a volunteer
schedule.

Help run swim
meets, work the
concession stand,
Team C Group Project

8

support the swim
team
Parents

0

0

User

Stay informed
about team events

Swimmers

0

0

User

Stay informed
about team events

Pamela Rich

+1

3

Project
manager

Lead and manage
the project so that it
achieves its MOV

Project Team

+1

2

Web
Developer
Graphic
Artist

Provide expertise to
complete the
project work

III. Approach and Project Plan
The project will follow a waterfall system development methodology and we will seek
approval at the end of each phase. The next phase will not begin without approval for the
preceding phase. A strong team of analysts has been selected to conduct requirements analysis
and support project planning. A seasoned web developer and graphics artist will build the site
and create all images to be placed on the site. This team has deep experience developing similar
sites for small businesses and community organizations. This team will be able to leverage
templates and processes developed and honed on other engagements to reduce the overall
development time and cost.
The project schedule will begin on October 21, 2013 and complete on January 17, 2014.
The website will launch on January 16, providing nearly a month of run time before the start of
the Spring swim season on February 15. The total cost of the project is $37,040.08.
Please find the detailed schedule and cost estimates below.
Team C Group Project

9

Resources
The team that will deliver PSL and their associated roles and rates are provided below:
Resources

Names

Rate

Project Manager

Pamela Rich

$39.01 hourly

Business Analysts

Brian Palmer
Zach Salwen
Marcus Taite
Rahul Tanwar

$38.31 hourly

Graphic Artist

Maria Jones

$21.22 hourly

Web Developer

Tim Smith

$30.05 hourly

Assumptions
● Appropriate levels of funding have been secured to meet the budget requirements of the
project.
● If the project does not secure adequate funding, the scope will have to be reduced.
● Resources with appropriate level of technical abilities are available for the duration of the
project.
● Riptide Swim Team resources will be available to review deliverables and approve
milestones as defined in the schedule. If approval is delayed, the project schedule may have
to be extended.
● Open source technologies are going to be used for the development of the website.
● Project will be initiated the Week of October 21st, 2013.
● Our rates are consistent with industry standards and can be validated on www.onetonline.org.
● Schedule is based on Standard American work calendars and includes Holidays of
Thanksgiving Day, Christmas Day and New Year’s Day.
● All changes in scope must be signed off on and approved by the project manager and client.
● The website will be expected to function properly in all major browsers: Internet Explorer
9+, Chrome, Firefox, Safari, and Opera.
Team C Group Project

10

Risks
● The parental association may use influence to expand the scope of the project and add their
requirements.
● If specific technology requirements are provided by project stakeholders, beyond what is
defined in this document, portions of the project may need to be outsourced if they require
technology outside the skillset of the web development tools with which the project team is
familiar.
● The graphic design must be approved by all stakeholders before development can begin.
● There is no guarantee that a website that meets all the criteria of the project scope will
achieve the project MOV, without support from the stakeholders. In order to improve swim
meet attendance and membership registration, the website will need to be promoted with
intended user base.
● Riptide Swim Team must keep information current and relevant to intended users, else site
usage may not meet expectations.
● The swim team will be modifying the website when posting meet results. This could
compromise the integrity of the system if users are not properly trained.
Project Schedule and Work Breakdown Structure
Team C Group Project

11
Team C Group Project

12

Project Cost by Activity

Project Cost by Resource
Resources

Rate

Number of Total Cost
Hours
Estimate

Pamela Rich

$39.01 hourly

272

$10,610.72

Brian Palmer

$38.31 hourly

112

$ 4,290.72

Zach Salwen

$38.31 hourly

176

$ 6,742.56

Marcus Taite

$38.31 hourly

104

$ 3,984.24

Rahul Tanwar

$38.31 hourly

168

$ 6,436.08

Maria Jones

$21.22 hourly

48

$ 1,018.56

Tim Smith

$30.05 hourly

104

$ 3,957.20
Team C Group Project

13

We welcome the opportunity to discuss the details of this proposal with you at our meeting later
this week. In the meantime, if you have any questions regarding the above information, please
contact me at +1-703-555-4534.

Sincerely,
William Jones
President
Team C Consultants

Contenu connexe

Tendances

Web-developmentInternship.docx
Web-developmentInternship.docxWeb-developmentInternship.docx
Web-developmentInternship.docxAditya patil
 
online Blood Bank management system
online Blood Bank management system online Blood Bank management system
online Blood Bank management system amarsajid
 
A Low-Cost IoT Application for the Urban Traffic of Vehicles, Based on Wirele...
A Low-Cost IoT Application for the Urban Traffic of Vehicles, Based on Wirele...A Low-Cost IoT Application for the Urban Traffic of Vehicles, Based on Wirele...
A Low-Cost IoT Application for the Urban Traffic of Vehicles, Based on Wirele...Fatima Qayyum
 
Feedback System in PHP
Feedback System in PHPFeedback System in PHP
Feedback System in PHPPrince Kumar
 
Srs hospital management
Srs hospital managementSrs hospital management
Srs hospital managementmaamir farooq
 
Employee Management System
Employee Management SystemEmployee Management System
Employee Management Systemvivek shah
 
College management
College managementCollege management
College managementanandhan30
 
Blood Bank System Peroject (website) Full Document
 Blood Bank System Peroject (website) Full Document  Blood Bank System Peroject (website) Full Document
Blood Bank System Peroject (website) Full Document DAV.PG COLLAGE
 
Software Project Management for 'Weather Forecasting using Data mining'
Software Project Management for 'Weather Forecasting using Data mining'Software Project Management for 'Weather Forecasting using Data mining'
Software Project Management for 'Weather Forecasting using Data mining'Rushikesh Mangrulkar
 
Final project presentation CSE
Final project presentation CSEFinal project presentation CSE
Final project presentation CSEHumayra Khanum
 
Business Requirement Specification
Business Requirement SpecificationBusiness Requirement Specification
Business Requirement Specificationsuhasreddy1
 
IRJET- Virtual Dietitian: An Android based Application to Provide Diet
IRJET-  	  Virtual Dietitian: An Android based Application to Provide DietIRJET-  	  Virtual Dietitian: An Android based Application to Provide Diet
IRJET- Virtual Dietitian: An Android based Application to Provide DietIRJET Journal
 
Gift 4 life v 1.1 (Blood Camp Management System)
Gift 4 life v 1.1 (Blood Camp Management System)Gift 4 life v 1.1 (Blood Camp Management System)
Gift 4 life v 1.1 (Blood Camp Management System)Parinda Rajapaksha
 
Blood Bank Management System
Blood Bank Management SystemBlood Bank Management System
Blood Bank Management SystemMariamKhan120
 
Computer Science Student Final attachment Logbook
Computer Science Student Final attachment Logbook Computer Science Student Final attachment Logbook
Computer Science Student Final attachment Logbook Paullaster Okoth
 
Blood Bank Management Information System [Web-Url: http://infobloodbank.somee...
Blood Bank Management Information System [Web-Url: http://infobloodbank.somee...Blood Bank Management Information System [Web-Url: http://infobloodbank.somee...
Blood Bank Management Information System [Web-Url: http://infobloodbank.somee...Showrav Mazumder
 
Updated black book ice cream parlour TYBSCIT Final year project in PDF
Updated black book ice cream parlour TYBSCIT Final year project in PDFUpdated black book ice cream parlour TYBSCIT Final year project in PDF
Updated black book ice cream parlour TYBSCIT Final year project in PDFYogeshDhamke2
 
Attendance management system project report.
Attendance management system project report.Attendance management system project report.
Attendance management system project report.Manoj Kumar
 

Tendances (20)

Web-developmentInternship.docx
Web-developmentInternship.docxWeb-developmentInternship.docx
Web-developmentInternship.docx
 
online Blood Bank management system
online Blood Bank management system online Blood Bank management system
online Blood Bank management system
 
A Low-Cost IoT Application for the Urban Traffic of Vehicles, Based on Wirele...
A Low-Cost IoT Application for the Urban Traffic of Vehicles, Based on Wirele...A Low-Cost IoT Application for the Urban Traffic of Vehicles, Based on Wirele...
A Low-Cost IoT Application for the Urban Traffic of Vehicles, Based on Wirele...
 
Feedback System in PHP
Feedback System in PHPFeedback System in PHP
Feedback System in PHP
 
Srs hospital management
Srs hospital managementSrs hospital management
Srs hospital management
 
Employee Management System
Employee Management SystemEmployee Management System
Employee Management System
 
College management
College managementCollege management
College management
 
Blood Bank System Peroject (website) Full Document
 Blood Bank System Peroject (website) Full Document  Blood Bank System Peroject (website) Full Document
Blood Bank System Peroject (website) Full Document
 
Software Project Management for 'Weather Forecasting using Data mining'
Software Project Management for 'Weather Forecasting using Data mining'Software Project Management for 'Weather Forecasting using Data mining'
Software Project Management for 'Weather Forecasting using Data mining'
 
Final project presentation CSE
Final project presentation CSEFinal project presentation CSE
Final project presentation CSE
 
Business Requirement Specification
Business Requirement SpecificationBusiness Requirement Specification
Business Requirement Specification
 
Net banking
Net banking Net banking
Net banking
 
IRJET- Virtual Dietitian: An Android based Application to Provide Diet
IRJET-  	  Virtual Dietitian: An Android based Application to Provide DietIRJET-  	  Virtual Dietitian: An Android based Application to Provide Diet
IRJET- Virtual Dietitian: An Android based Application to Provide Diet
 
Gift 4 life v 1.1 (Blood Camp Management System)
Gift 4 life v 1.1 (Blood Camp Management System)Gift 4 life v 1.1 (Blood Camp Management System)
Gift 4 life v 1.1 (Blood Camp Management System)
 
Blood Bank Management System
Blood Bank Management SystemBlood Bank Management System
Blood Bank Management System
 
Computer Science Student Final attachment Logbook
Computer Science Student Final attachment Logbook Computer Science Student Final attachment Logbook
Computer Science Student Final attachment Logbook
 
Use case of course registration system using LaTex
Use case of course registration system using LaTexUse case of course registration system using LaTex
Use case of course registration system using LaTex
 
Blood Bank Management Information System [Web-Url: http://infobloodbank.somee...
Blood Bank Management Information System [Web-Url: http://infobloodbank.somee...Blood Bank Management Information System [Web-Url: http://infobloodbank.somee...
Blood Bank Management Information System [Web-Url: http://infobloodbank.somee...
 
Updated black book ice cream parlour TYBSCIT Final year project in PDF
Updated black book ice cream parlour TYBSCIT Final year project in PDFUpdated black book ice cream parlour TYBSCIT Final year project in PDF
Updated black book ice cream parlour TYBSCIT Final year project in PDF
 
Attendance management system project report.
Attendance management system project report.Attendance management system project report.
Attendance management system project report.
 

Similaire à IT Project for Swim Team

Empowerment Technology for Subjectsssssss
Empowerment Technology for SubjectsssssssEmpowerment Technology for Subjectsssssss
Empowerment Technology for SubjectsssssssRouAnnNavarroza
 
Mateo Gardella IA Report for Sports for the Worlds Children
Mateo Gardella IA Report for Sports for the Worlds ChildrenMateo Gardella IA Report for Sports for the Worlds Children
Mateo Gardella IA Report for Sports for the Worlds ChildrenMateoGardella
 
online blogging system
online blogging systemonline blogging system
online blogging system001vaibhav
 
MOWCM RFP 12_22_11(1)
MOWCM RFP 12_22_11(1)MOWCM RFP 12_22_11(1)
MOWCM RFP 12_22_11(1)Melissa Kaiza
 
student innovation 2014
student innovation 2014student innovation 2014
student innovation 2014Freelancer
 
Even better departmental updates - October 2019
Even better   departmental updates - October 2019Even better   departmental updates - October 2019
Even better departmental updates - October 2019EmmaRimmer2
 
Even better departmental updates - october 2019
Even better departmental updates - october 2019Even better departmental updates - october 2019
Even better departmental updates - october 2019EmmaRimmer2
 
Webpage design full project of project management
Webpage design full project of project managementWebpage design full project of project management
Webpage design full project of project managementArefeen Hridoy
 
Nyc metro rid website development proposal
Nyc metro rid website development proposalNyc metro rid website development proposal
Nyc metro rid website development proposaldarylcrouse
 
Web content quality matters
Web content quality mattersWeb content quality matters
Web content quality mattersSiteimprove
 
DavinRunnerstrom_IAReport.pdf
DavinRunnerstrom_IAReport.pdfDavinRunnerstrom_IAReport.pdf
DavinRunnerstrom_IAReport.pdfDavin Runnerstrom
 
Inquiry and information_fluency_mini_lessons
Inquiry and information_fluency_mini_lessonsInquiry and information_fluency_mini_lessons
Inquiry and information_fluency_mini_lessonsCherelleR
 
Funcsp Open Health
Funcsp Open HealthFuncsp Open Health
Funcsp Open Healthwellunwell
 
Funcsp Open Health
Funcsp Open HealthFuncsp Open Health
Funcsp Open Healthwellunwell
 
Funcsp Open Health
Funcsp Open HealthFuncsp Open Health
Funcsp Open Healthwellunwell
 

Similaire à IT Project for Swim Team (20)

Empowerment Technology for Subjectsssssss
Empowerment Technology for SubjectsssssssEmpowerment Technology for Subjectsssssss
Empowerment Technology for Subjectsssssss
 
Mateo Gardella IA Report for Sports for the Worlds Children
Mateo Gardella IA Report for Sports for the Worlds ChildrenMateo Gardella IA Report for Sports for the Worlds Children
Mateo Gardella IA Report for Sports for the Worlds Children
 
online blogging system
online blogging systemonline blogging system
online blogging system
 
Sample Agenda
Sample AgendaSample Agenda
Sample Agenda
 
MOWCM RFP 12_22_11(1)
MOWCM RFP 12_22_11(1)MOWCM RFP 12_22_11(1)
MOWCM RFP 12_22_11(1)
 
Advance web Design
Advance web DesignAdvance web Design
Advance web Design
 
Presentation1
Presentation1Presentation1
Presentation1
 
student innovation 2014
student innovation 2014student innovation 2014
student innovation 2014
 
Web site proposal
Web site proposalWeb site proposal
Web site proposal
 
Even better departmental updates - October 2019
Even better   departmental updates - October 2019Even better   departmental updates - October 2019
Even better departmental updates - October 2019
 
Even better departmental updates - october 2019
Even better departmental updates - october 2019Even better departmental updates - october 2019
Even better departmental updates - october 2019
 
Webpage design full project of project management
Webpage design full project of project managementWebpage design full project of project management
Webpage design full project of project management
 
Nyc metro rid website development proposal
Nyc metro rid website development proposalNyc metro rid website development proposal
Nyc metro rid website development proposal
 
Presentation1 001
Presentation1 001Presentation1 001
Presentation1 001
 
Web content quality matters
Web content quality mattersWeb content quality matters
Web content quality matters
 
DavinRunnerstrom_IAReport.pdf
DavinRunnerstrom_IAReport.pdfDavinRunnerstrom_IAReport.pdf
DavinRunnerstrom_IAReport.pdf
 
Inquiry and information_fluency_mini_lessons
Inquiry and information_fluency_mini_lessonsInquiry and information_fluency_mini_lessons
Inquiry and information_fluency_mini_lessons
 
Funcsp Open Health
Funcsp Open HealthFuncsp Open Health
Funcsp Open Health
 
Funcsp Open Health
Funcsp Open HealthFuncsp Open Health
Funcsp Open Health
 
Funcsp Open Health
Funcsp Open HealthFuncsp Open Health
Funcsp Open Health
 

Dernier

NIST Cybersecurity Framework (CSF) 2.0 Workshop
NIST Cybersecurity Framework (CSF) 2.0 WorkshopNIST Cybersecurity Framework (CSF) 2.0 Workshop
NIST Cybersecurity Framework (CSF) 2.0 WorkshopBachir Benyammi
 
UiPath Solutions Management Preview - Northern CA Chapter - March 22.pdf
UiPath Solutions Management Preview - Northern CA Chapter - March 22.pdfUiPath Solutions Management Preview - Northern CA Chapter - March 22.pdf
UiPath Solutions Management Preview - Northern CA Chapter - March 22.pdfDianaGray10
 
IESVE Software for Florida Code Compliance Using ASHRAE 90.1-2019
IESVE Software for Florida Code Compliance Using ASHRAE 90.1-2019IESVE Software for Florida Code Compliance Using ASHRAE 90.1-2019
IESVE Software for Florida Code Compliance Using ASHRAE 90.1-2019IES VE
 
Comparing Sidecar-less Service Mesh from Cilium and Istio
Comparing Sidecar-less Service Mesh from Cilium and IstioComparing Sidecar-less Service Mesh from Cilium and Istio
Comparing Sidecar-less Service Mesh from Cilium and IstioChristian Posta
 
VoIP Service and Marketing using Odoo and Asterisk PBX
VoIP Service and Marketing using Odoo and Asterisk PBXVoIP Service and Marketing using Odoo and Asterisk PBX
VoIP Service and Marketing using Odoo and Asterisk PBXTarek Kalaji
 
Building AI-Driven Apps Using Semantic Kernel.pptx
Building AI-Driven Apps Using Semantic Kernel.pptxBuilding AI-Driven Apps Using Semantic Kernel.pptx
Building AI-Driven Apps Using Semantic Kernel.pptxUdaiappa Ramachandran
 
Meet the new FSP 3000 M-Flex800™
Meet the new FSP 3000 M-Flex800™Meet the new FSP 3000 M-Flex800™
Meet the new FSP 3000 M-Flex800™Adtran
 
Anypoint Code Builder , Google Pub sub connector and MuleSoft RPA
Anypoint Code Builder , Google Pub sub connector and MuleSoft RPAAnypoint Code Builder , Google Pub sub connector and MuleSoft RPA
Anypoint Code Builder , Google Pub sub connector and MuleSoft RPAshyamraj55
 
UiPath Studio Web workshop series - Day 6
UiPath Studio Web workshop series - Day 6UiPath Studio Web workshop series - Day 6
UiPath Studio Web workshop series - Day 6DianaGray10
 
Computer 10: Lesson 10 - Online Crimes and Hazards
Computer 10: Lesson 10 - Online Crimes and HazardsComputer 10: Lesson 10 - Online Crimes and Hazards
Computer 10: Lesson 10 - Online Crimes and HazardsSeth Reyes
 
ADOPTING WEB 3 FOR YOUR BUSINESS: A STEP-BY-STEP GUIDE
ADOPTING WEB 3 FOR YOUR BUSINESS: A STEP-BY-STEP GUIDEADOPTING WEB 3 FOR YOUR BUSINESS: A STEP-BY-STEP GUIDE
ADOPTING WEB 3 FOR YOUR BUSINESS: A STEP-BY-STEP GUIDELiveplex
 
The Data Metaverse: Unpacking the Roles, Use Cases, and Tech Trends in Data a...
The Data Metaverse: Unpacking the Roles, Use Cases, and Tech Trends in Data a...The Data Metaverse: Unpacking the Roles, Use Cases, and Tech Trends in Data a...
The Data Metaverse: Unpacking the Roles, Use Cases, and Tech Trends in Data a...Aggregage
 
Basic Building Blocks of Internet of Things.
Basic Building Blocks of Internet of Things.Basic Building Blocks of Internet of Things.
Basic Building Blocks of Internet of Things.YounusS2
 
UiPath Studio Web workshop series - Day 8
UiPath Studio Web workshop series - Day 8UiPath Studio Web workshop series - Day 8
UiPath Studio Web workshop series - Day 8DianaGray10
 
Introduction to Matsuo Laboratory (ENG).pptx
Introduction to Matsuo Laboratory (ENG).pptxIntroduction to Matsuo Laboratory (ENG).pptx
Introduction to Matsuo Laboratory (ENG).pptxMatsuo Lab
 
IaC & GitOps in a Nutshell - a FridayInANuthshell Episode.pdf
IaC & GitOps in a Nutshell - a FridayInANuthshell Episode.pdfIaC & GitOps in a Nutshell - a FridayInANuthshell Episode.pdf
IaC & GitOps in a Nutshell - a FridayInANuthshell Episode.pdfDaniel Santiago Silva Capera
 
COMPUTER 10: Lesson 7 - File Storage and Online Collaboration
COMPUTER 10: Lesson 7 - File Storage and Online CollaborationCOMPUTER 10: Lesson 7 - File Storage and Online Collaboration
COMPUTER 10: Lesson 7 - File Storage and Online Collaborationbruanjhuli
 
Linked Data in Production: Moving Beyond Ontologies
Linked Data in Production: Moving Beyond OntologiesLinked Data in Production: Moving Beyond Ontologies
Linked Data in Production: Moving Beyond OntologiesDavid Newbury
 

Dernier (20)

NIST Cybersecurity Framework (CSF) 2.0 Workshop
NIST Cybersecurity Framework (CSF) 2.0 WorkshopNIST Cybersecurity Framework (CSF) 2.0 Workshop
NIST Cybersecurity Framework (CSF) 2.0 Workshop
 
201610817 - edge part1
201610817 - edge part1201610817 - edge part1
201610817 - edge part1
 
UiPath Solutions Management Preview - Northern CA Chapter - March 22.pdf
UiPath Solutions Management Preview - Northern CA Chapter - March 22.pdfUiPath Solutions Management Preview - Northern CA Chapter - March 22.pdf
UiPath Solutions Management Preview - Northern CA Chapter - March 22.pdf
 
IESVE Software for Florida Code Compliance Using ASHRAE 90.1-2019
IESVE Software for Florida Code Compliance Using ASHRAE 90.1-2019IESVE Software for Florida Code Compliance Using ASHRAE 90.1-2019
IESVE Software for Florida Code Compliance Using ASHRAE 90.1-2019
 
Comparing Sidecar-less Service Mesh from Cilium and Istio
Comparing Sidecar-less Service Mesh from Cilium and IstioComparing Sidecar-less Service Mesh from Cilium and Istio
Comparing Sidecar-less Service Mesh from Cilium and Istio
 
VoIP Service and Marketing using Odoo and Asterisk PBX
VoIP Service and Marketing using Odoo and Asterisk PBXVoIP Service and Marketing using Odoo and Asterisk PBX
VoIP Service and Marketing using Odoo and Asterisk PBX
 
Building AI-Driven Apps Using Semantic Kernel.pptx
Building AI-Driven Apps Using Semantic Kernel.pptxBuilding AI-Driven Apps Using Semantic Kernel.pptx
Building AI-Driven Apps Using Semantic Kernel.pptx
 
Meet the new FSP 3000 M-Flex800™
Meet the new FSP 3000 M-Flex800™Meet the new FSP 3000 M-Flex800™
Meet the new FSP 3000 M-Flex800™
 
Anypoint Code Builder , Google Pub sub connector and MuleSoft RPA
Anypoint Code Builder , Google Pub sub connector and MuleSoft RPAAnypoint Code Builder , Google Pub sub connector and MuleSoft RPA
Anypoint Code Builder , Google Pub sub connector and MuleSoft RPA
 
UiPath Studio Web workshop series - Day 6
UiPath Studio Web workshop series - Day 6UiPath Studio Web workshop series - Day 6
UiPath Studio Web workshop series - Day 6
 
Computer 10: Lesson 10 - Online Crimes and Hazards
Computer 10: Lesson 10 - Online Crimes and HazardsComputer 10: Lesson 10 - Online Crimes and Hazards
Computer 10: Lesson 10 - Online Crimes and Hazards
 
20150722 - AGV
20150722 - AGV20150722 - AGV
20150722 - AGV
 
ADOPTING WEB 3 FOR YOUR BUSINESS: A STEP-BY-STEP GUIDE
ADOPTING WEB 3 FOR YOUR BUSINESS: A STEP-BY-STEP GUIDEADOPTING WEB 3 FOR YOUR BUSINESS: A STEP-BY-STEP GUIDE
ADOPTING WEB 3 FOR YOUR BUSINESS: A STEP-BY-STEP GUIDE
 
The Data Metaverse: Unpacking the Roles, Use Cases, and Tech Trends in Data a...
The Data Metaverse: Unpacking the Roles, Use Cases, and Tech Trends in Data a...The Data Metaverse: Unpacking the Roles, Use Cases, and Tech Trends in Data a...
The Data Metaverse: Unpacking the Roles, Use Cases, and Tech Trends in Data a...
 
Basic Building Blocks of Internet of Things.
Basic Building Blocks of Internet of Things.Basic Building Blocks of Internet of Things.
Basic Building Blocks of Internet of Things.
 
UiPath Studio Web workshop series - Day 8
UiPath Studio Web workshop series - Day 8UiPath Studio Web workshop series - Day 8
UiPath Studio Web workshop series - Day 8
 
Introduction to Matsuo Laboratory (ENG).pptx
Introduction to Matsuo Laboratory (ENG).pptxIntroduction to Matsuo Laboratory (ENG).pptx
Introduction to Matsuo Laboratory (ENG).pptx
 
IaC & GitOps in a Nutshell - a FridayInANuthshell Episode.pdf
IaC & GitOps in a Nutshell - a FridayInANuthshell Episode.pdfIaC & GitOps in a Nutshell - a FridayInANuthshell Episode.pdf
IaC & GitOps in a Nutshell - a FridayInANuthshell Episode.pdf
 
COMPUTER 10: Lesson 7 - File Storage and Online Collaboration
COMPUTER 10: Lesson 7 - File Storage and Online CollaborationCOMPUTER 10: Lesson 7 - File Storage and Online Collaboration
COMPUTER 10: Lesson 7 - File Storage and Online Collaboration
 
Linked Data in Production: Moving Beyond Ontologies
Linked Data in Production: Moving Beyond OntologiesLinked Data in Production: Moving Beyond Ontologies
Linked Data in Production: Moving Beyond Ontologies
 

IT Project for Swim Team

  • 1. Team C Group Project 1 ITEC 640 Section 9081 Semester 1309 Group Project – Team C Brian Palmer Pamela Rich Zach Salwen Marcus Taite Rahul Tanwar DUE DATE: December 8, 2013 University of Maryland University College
  • 2. Team C Group Project 2 October 15, 2013 Mr. Joe Smith Riptide Swim Team 101 Main Street Bristow, VA 20136 RE: Website for Riptide Swim Team Dear Mr. Smith, Thank you for providing Team C Consultants with the opportunity to develop a website to support the Riptide Swim Team. Our expertise in providing quality web solutions to local businesses will enable us to provide the swim team with a solution that will meet, or hopefully exceed, your expectations. As discussed during the meeting last week, Team C Consultants is pleased to provide the project plan proposal to support this effort. We have structured our proposal with the following sections I. II. III. Statement of Need Project Definition Approach and Project Plan It is our desire to establish a long-term relationship with the Riptide Swim Team. We are committed to developing a partnership that will continue to meet all needs as they evolve. We hope this will be the first of many opportunities to serve you. I. Statement of Need It is understood that the Riptide Swim Team is in need of a web site. As the team has grown over the past two years, the current method of emailing practice and meet schedules has become inefficient for the coaches and is not the optimal way for parents and swimmers to receive this information. Additionally, as a result of winning the state championship last year, the greater community has a strong interest in supporting the team by attending the meets and cheering on
  • 3. Team C Group Project 3 the local swimmers. The swim team is lacking a solution for communicating the meet schedule and results to the community at large. Given the outstanding performance of the swimmers, the swim team wants to promote their successes by posting swim meet results and pictures on a website. This will help provide the swimmers with greater visibility beyond the local community and could allow college recruiters to learn about and follow the swimmers. This will also help promote the fun and excitement of team swimming and could help to increase membership. We understand the site needs to be fully functionally no later than the end of January 2014 to support the Spring swim season, which begins on February 15. The site is to be launched with a basic set of functions, but needs to have the ability to scale as new requirements are identified and the number of users grows. It is important that future enhancements can be easily added to current functionality, without requiring major architectural changes. Content must be maintainable internally, without reliance on Team C Consultants to add or change content. The site must be intuitive and inviting, with a modern look. II. Project Definition Project Description Team C Consultants is prepared to develop ‘Project Swim Lane’ (PSL) to meet the needs of the Riptide Swim team. The purpose of this project is to create a website that is attractive, informative, and engaging for the coaches, swimmers, parents and the local community. The website will function as a platform for providing information to children between the ages of 6 and 18, and/or their parents, who have an interest in joining the swim team. This website will also provide information regarding the scheduled swim practices and meets and will post results and photos from the meets.
  • 4. Team C Group Project Project Scope ● To design, develop and implement an interactive website using Web 2.0 technologies to enable users to get timely information, add content and share with other members of the swim team and the community ● To develop a website that is accessible to the general public and allows visitors to sign up and request additional information about the team ● To develop a database of users to store profile information and login credentials for privileged site users ● To develop a database to store, retrieve and display scheduling information for practices, scheduling information for swim meets and the results of swim meets. ● To develop a content file management system to effectively store, retrieve and display picture images ● To provide administration capability to update the website with up-to-date information, relevant content and manager users. ● To develop a website that is search engine optimized to drive traffic to the website In Scope Requirements 1. Home Page 1.1. The website will provide a home page that is accessible to the public. 1.2. The home page will provide general information about the swim team and contact information to get additional information. 1.3. The home page will include a navigation menu to access other pages on the site. 1.3.1. The navigation menu will be accessible on all pages. 1.4. The home page will provide the capability to request more information from the coaching staff. 1.4.1. Any visitor to the site will have the ability to provide their name, phone number, email and a message will be sent to the coaching staff to request additional information. 2. Swim Meet Page 2.1. The website will include a Swim Meet page that is accessible to the public. 4
  • 5. Team C Group Project 5 2.2. The Swim Meet page will provide a calendar that lists upcoming meets for the next 12 months. 2.2.1. Each swim meet calendar entry will include the date, time, location and events for the meet. 2.3. The Swim Meet page will provide the capability to view results of the past 12 months meets. 2.4. The Swim Meet page will provide the capability to view photos from swim meets. 2.4.1. The names of swimmers and coaches will be identified on the photos. 3. Swim Practice Page 3.1. The website will provide a Swim Practice page that is accessible to the public. 3.2. The Swim Practice page will provide a calendar that lists swim practices for the next 12 months. 3.2.1. Each swim practice calendar entry will include the date, time, location and notes for the practice. 4. Photo Gallery 4.1. The website will include a Photo Gallery page that is accessible to the public. 4.1.1. The Photo Gallery page will identify the names of swimmers and coaches in the photos. 5. Coaching Staff Page 5.1. The website will provide a Coaching Staff page that is accessible to the public and provides a bio, photo and contact information for the coaching staff. 6. User Administration 6.1. The website will provide a user administration capability that provides registered admins the ability to create, update and delete user ids. 6.1.1. Registered admins will have the ability to add, change and remove permissions for every user id. 6.2. User Permissions to be assigned to user ids include: 6.2.1. Ability to create, update and delete text/content on each page 6.2.2. Ability to upload and remove photos on each page
  • 6. Team C Group Project 6 6.2.3. Ability to upload and remove documents on each page 6.2.4. Ability to create, update and delete calendar events 6.2.5. Ability to access a page (e.g. the Photo Gallery, User Administration, etc.) 6.3. The website will require registered users to log on with a user id and password to access restricted pages. 7. Content Administration 7.1. The website will include a Content Administration capability that allows registered users to create, maintain and delete website content. 7.2. Users with Content Administration capabilities will have the ability to edit pages in an easy use rich text editor. 7.2.1. The rich text editor will allow content administrators to add, change and format text to be displayed on the pages. 7.2.2. The rich text editor will allow content administrators to upload photos and add captions. 7.3. Content administrator will have the ability to upload documents. 7.4. Content administrator will have the ability to link to uploaded documents. 7.5. Content Administrator will have the ability to create, update and delete events on the calendars. 7.6. Content Administrator permissions will determine which pages and calendars can be updated. 8. System Requirements 8.1. The website will be accessible over HTTP using modern web browsers 8.2. The website will be compatible with PC or Apple browsers 8.3. The website will be hosted on a secure web server platform 8.4. The system will provide sufficient security access controls to ensure any private information is stored securely on the hosted database servers. 8.5. The system will provide the capability to view and analyze website traffic and hits reports and metrics
  • 7. Team C Group Project 7 Out of Scope Requirements – deferred to a future phase 1. Parents Page 1.1. The website will include a Parents Page that is accessible only to registered users with Parent permissions. 1.2. The Parents Page will provide a calendar that displays the volunteer schedule. Measurable Organizational Value (MOV) Develop and implement a functional website that will provide current information and photos to all parents, children, and coaches, which will improve swim meet attendance by 20% and increase membership registration by 25% within 12 months. Project Stakeholders The principal stakeholders for the PSL project plan are listed in Table 1. Table 1: Principal Stakeholders Stakeholder/ Title Interest Influence Role Team Prospects 0 0 User Team Coach +1 5 Project sponsor Assistant Coaches +1 2 Content Providers +1 0 Parental Association +1 3 Potential Conflict Objective Find out information about joining the swim team Does not want the parental association's pet project created just yet. Provide resources, approvals, and public support for the project Have their information displayed on the team site User Manage site information about the swim team Want the site to feature a volunteer schedule. Help run swim meets, work the concession stand,
  • 8. Team C Group Project 8 support the swim team Parents 0 0 User Stay informed about team events Swimmers 0 0 User Stay informed about team events Pamela Rich +1 3 Project manager Lead and manage the project so that it achieves its MOV Project Team +1 2 Web Developer Graphic Artist Provide expertise to complete the project work III. Approach and Project Plan The project will follow a waterfall system development methodology and we will seek approval at the end of each phase. The next phase will not begin without approval for the preceding phase. A strong team of analysts has been selected to conduct requirements analysis and support project planning. A seasoned web developer and graphics artist will build the site and create all images to be placed on the site. This team has deep experience developing similar sites for small businesses and community organizations. This team will be able to leverage templates and processes developed and honed on other engagements to reduce the overall development time and cost. The project schedule will begin on October 21, 2013 and complete on January 17, 2014. The website will launch on January 16, providing nearly a month of run time before the start of the Spring swim season on February 15. The total cost of the project is $37,040.08. Please find the detailed schedule and cost estimates below.
  • 9. Team C Group Project 9 Resources The team that will deliver PSL and their associated roles and rates are provided below: Resources Names Rate Project Manager Pamela Rich $39.01 hourly Business Analysts Brian Palmer Zach Salwen Marcus Taite Rahul Tanwar $38.31 hourly Graphic Artist Maria Jones $21.22 hourly Web Developer Tim Smith $30.05 hourly Assumptions ● Appropriate levels of funding have been secured to meet the budget requirements of the project. ● If the project does not secure adequate funding, the scope will have to be reduced. ● Resources with appropriate level of technical abilities are available for the duration of the project. ● Riptide Swim Team resources will be available to review deliverables and approve milestones as defined in the schedule. If approval is delayed, the project schedule may have to be extended. ● Open source technologies are going to be used for the development of the website. ● Project will be initiated the Week of October 21st, 2013. ● Our rates are consistent with industry standards and can be validated on www.onetonline.org. ● Schedule is based on Standard American work calendars and includes Holidays of Thanksgiving Day, Christmas Day and New Year’s Day. ● All changes in scope must be signed off on and approved by the project manager and client. ● The website will be expected to function properly in all major browsers: Internet Explorer 9+, Chrome, Firefox, Safari, and Opera.
  • 10. Team C Group Project 10 Risks ● The parental association may use influence to expand the scope of the project and add their requirements. ● If specific technology requirements are provided by project stakeholders, beyond what is defined in this document, portions of the project may need to be outsourced if they require technology outside the skillset of the web development tools with which the project team is familiar. ● The graphic design must be approved by all stakeholders before development can begin. ● There is no guarantee that a website that meets all the criteria of the project scope will achieve the project MOV, without support from the stakeholders. In order to improve swim meet attendance and membership registration, the website will need to be promoted with intended user base. ● Riptide Swim Team must keep information current and relevant to intended users, else site usage may not meet expectations. ● The swim team will be modifying the website when posting meet results. This could compromise the integrity of the system if users are not properly trained. Project Schedule and Work Breakdown Structure
  • 11. Team C Group Project 11
  • 12. Team C Group Project 12 Project Cost by Activity Project Cost by Resource Resources Rate Number of Total Cost Hours Estimate Pamela Rich $39.01 hourly 272 $10,610.72 Brian Palmer $38.31 hourly 112 $ 4,290.72 Zach Salwen $38.31 hourly 176 $ 6,742.56 Marcus Taite $38.31 hourly 104 $ 3,984.24 Rahul Tanwar $38.31 hourly 168 $ 6,436.08 Maria Jones $21.22 hourly 48 $ 1,018.56 Tim Smith $30.05 hourly 104 $ 3,957.20
  • 13. Team C Group Project 13 We welcome the opportunity to discuss the details of this proposal with you at our meeting later this week. In the meantime, if you have any questions regarding the above information, please contact me at +1-703-555-4534. Sincerely, William Jones President Team C Consultants