SlideShare une entreprise Scribd logo
1  sur  24
Rehab & Maint. HMA Overlays 1
HMA Overlays
Over PCC Pavements
Flexible Pavement Maintenance and
Rehabilitation
Rehab & Maint. HMA Overlays 2
Slab Preparation Techniques
• Crack and seat (JPCP)
• Break and seat (JRCP)
• Rubblize (JPCP, JRCP, CRCP)
• Saw and seal
Rehab & Maint. HMA Overlays 3
PCC
Reflection Cracking
• By far, the biggest
problem in HMA
overlays of PCC
pavement
• Caused by movement
at PCC joints and
cracks
Load-
induced
movement
Joint Closes
HMA
Slabs Contract Joint Opens
Slabs Expand
Reflection crack
Rehab & Maint. HMA Overlays 4
Cracking and Seating
• Shortens effective slab length
• Standard practice in many States
• Not “generally” recommended for use on poor
subgrades
• Design methods (overlay thickness)
Rehab & Maint. HMA Overlays 5
Cracking and Seating
Overlay
Subgrade Soil
Subbase Firm Foundation
Crack
s
Short slab
length (~2’)
Good
granular
interlock
Rehab & Maint. HMA Overlays 6
Cracking and Seating
Rehab & Maint. HMA Overlays 7
Cracking and Seating
Rehab & Maint. HMA Overlays 8
Cracking and Seating - crack
pattern
Rehab & Maint. HMA Overlays 9
Cracking and Seating
Rehab & Maint. HMA Overlays 10
What is rubblization?
• Fracturing:
– Eliminates slab action
– Destroys bond between concrete and
steel
• Rubblized base responds as a tightly
keyed, interlocked high-density, unbound
layer
– Layer cannot crack; already fractured
Rehab & Maint. HMA Overlays 11
Why Rubblize?
• Fracturing PCC to segments less than 9”
precludes reflection of:
– Joints
– Cracks
– Faults
• Production Rates up to 1 lane-mile/day
Rehab & Maint. HMA Overlays 12
HMA
PCC
Larger Pieces = Larger Movement = Cracking
Rehab & Maint. HMA Overlays 13
HMA
PCC
Smaller Pieces = Smaller Movement = No Cracking
Rehab & Maint. HMA Overlays 14
Benefits
• Time savings
–Choose work hours
–High production rates
• Economic Savings
–Reduce user delay costs
–Reduce construction costs
Rehab & Maint. HMA Overlays 15
• Environmentally friendly
–Reduce landfill
–Reduce fuel consumption/air pollution
• Smoothness
–Eliminate reflection cracking/faulting
Benefits (continued)
Rehab & Maint. HMA Overlays 16
Construction Procedure
• Install/replace existing edge drainage system as
required
• Remove existing overlay (if present)
• Remove existing HMA patches, replace with
aggregate base as required
• Fracture the concrete pavement
• Roll
• Place HMA overlay (multiple lifts)
Rehab & Maint. HMA Overlays 17
Resonant Pavement Breaker
Rehab & Maint. HMA Overlays 18
Multi-Head Breaker (MHB)
Rehab & Maint. HMA Overlays 19
Rolling
Rehab & Maint. HMA Overlays 20
Particle Size
• PCC fractured into 9
in.-minus pieces
• Most pieces are 1- 4
in. diameter
• Aggregate interlock
maintained beneath
surface
• Rolling knits together
surface particles
Rehab & Maint. HMA Overlays 21
Sawing and Sealing Joints
• Concede appearance of reflection cracking
• Objective: control rate of deterioration
• Reduces spalling of reflection cracks
• Candidates should have well-defined joints
• Sawcut must be directly above the
• underlying joint
Rehab & Maint. HMA Overlays 22
Sawing and Sealing Joints
Reflection crack
Overlay
Old pavement
Sealant
Initial sawcut
1/3 depth
Horizontal
opening
Joint reservoir
Subgrade
Vertical
differential
movement
Rehab & Maint. HMA Overlays 23
Sawing and Sealing Joints
Rehab & Maint. HMA Overlays 24
Questions?

Contenu connexe

Tendances

Asphalt pavement maintenace techniques and equipments for mongolia 02282012 eng
Asphalt pavement maintenace techniques and equipments for mongolia 02282012 engAsphalt pavement maintenace techniques and equipments for mongolia 02282012 eng
Asphalt pavement maintenace techniques and equipments for mongolia 02282012 engBayar Tsend
 
Intro to offshore drilling
Intro to offshore drilling Intro to offshore drilling
Intro to offshore drilling amrhaggag
 
WRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsWRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsMitaliShelke
 
Q922+de1+l07 v1
Q922+de1+l07 v1Q922+de1+l07 v1
Q922+de1+l07 v1AFATous
 
Pavement skid resistance
Pavement skid resistancePavement skid resistance
Pavement skid resistanceHai Vo
 
L-02 Analysis and Design of One-Way Slab System B & White.pdf
L-02 Analysis and Design of One-Way Slab System B & White.pdfL-02 Analysis and Design of One-Way Slab System B & White.pdf
L-02 Analysis and Design of One-Way Slab System B & White.pdfBhooth2
 
Selection of Alignment & importance of track drainage
Selection of Alignment & importance of track drainageSelection of Alignment & importance of track drainage
Selection of Alignment & importance of track drainageRAMPRASAD KUMAWAT
 
Design of two way slab
Design of two way slabDesign of two way slab
Design of two way slabsarani_reza
 
10 131130044745-phpapp02
10 131130044745-phpapp0210 131130044745-phpapp02
10 131130044745-phpapp02Motto Mal
 
Typical road structure cross section details
Typical road structure cross section detailsTypical road structure cross section details
Typical road structure cross section detailsAglaia Connect
 
Maintenance & repair of steel bridges
Maintenance & repair of steel bridgesMaintenance & repair of steel bridges
Maintenance & repair of steel bridgesnaveen kumar
 
One way slab and two way slab- Difference between
One way slab and two way slab- Difference betweenOne way slab and two way slab- Difference between
One way slab and two way slab- Difference betweenCivil Insider
 
WRE II canal structures
WRE II canal structuresWRE II canal structures
WRE II canal structuresMitaliShelke
 
Halliburton cementing presentation
Halliburton cementing presentationHalliburton cementing presentation
Halliburton cementing presentationBoubenia ali
 
footing
footingfooting
footingillpa
 

Tendances (20)

Asphalt pavement maintenace techniques and equipments for mongolia 02282012 eng
Asphalt pavement maintenace techniques and equipments for mongolia 02282012 engAsphalt pavement maintenace techniques and equipments for mongolia 02282012 eng
Asphalt pavement maintenace techniques and equipments for mongolia 02282012 eng
 
Intro to offshore drilling
Intro to offshore drilling Intro to offshore drilling
Intro to offshore drilling
 
Casing design
Casing designCasing design
Casing design
 
WRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsWRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity dams
 
Q922+de1+l07 v1
Q922+de1+l07 v1Q922+de1+l07 v1
Q922+de1+l07 v1
 
Pavement skid resistance
Pavement skid resistancePavement skid resistance
Pavement skid resistance
 
10.01.03.162
10.01.03.16210.01.03.162
10.01.03.162
 
Cementation
CementationCementation
Cementation
 
L-02 Analysis and Design of One-Way Slab System B & White.pdf
L-02 Analysis and Design of One-Way Slab System B & White.pdfL-02 Analysis and Design of One-Way Slab System B & White.pdf
L-02 Analysis and Design of One-Way Slab System B & White.pdf
 
HYDRAULIC FLEX SET LINER HANGER
HYDRAULIC FLEX SET LINER HANGER HYDRAULIC FLEX SET LINER HANGER
HYDRAULIC FLEX SET LINER HANGER
 
Selection of Alignment & importance of track drainage
Selection of Alignment & importance of track drainageSelection of Alignment & importance of track drainage
Selection of Alignment & importance of track drainage
 
Box culvert
Box culvertBox culvert
Box culvert
 
Design of two way slab
Design of two way slabDesign of two way slab
Design of two way slab
 
10 131130044745-phpapp02
10 131130044745-phpapp0210 131130044745-phpapp02
10 131130044745-phpapp02
 
Typical road structure cross section details
Typical road structure cross section detailsTypical road structure cross section details
Typical road structure cross section details
 
Maintenance & repair of steel bridges
Maintenance & repair of steel bridgesMaintenance & repair of steel bridges
Maintenance & repair of steel bridges
 
One way slab and two way slab- Difference between
One way slab and two way slab- Difference betweenOne way slab and two way slab- Difference between
One way slab and two way slab- Difference between
 
WRE II canal structures
WRE II canal structuresWRE II canal structures
WRE II canal structures
 
Halliburton cementing presentation
Halliburton cementing presentationHalliburton cementing presentation
Halliburton cementing presentation
 
footing
footingfooting
footing
 

En vedette

Block 14 Superpave Mix Design 13
Block 14 Superpave Mix Design 13Block 14 Superpave Mix Design 13
Block 14 Superpave Mix Design 13Chris Yarnell
 
Block 10 superpave agg requirements 13
Block 10 superpave agg requirements 13Block 10 superpave agg requirements 13
Block 10 superpave agg requirements 13Chris Yarnell
 
Block 25 Control Charts 13
Block 25   Control Charts 13Block 25   Control Charts 13
Block 25 Control Charts 13Chris Yarnell
 
Block 13 Mix design Historical 13
Block 13 Mix design Historical 13Block 13 Mix design Historical 13
Block 13 Mix design Historical 13Chris Yarnell
 
Rigid pavement distress
Rigid pavement distress Rigid pavement distress
Rigid pavement distress Ankit Sarkar
 

En vedette (9)

Block 14 Superpave Mix Design 13
Block 14 Superpave Mix Design 13Block 14 Superpave Mix Design 13
Block 14 Superpave Mix Design 13
 
Superpavemixdesign
Superpavemixdesign Superpavemixdesign
Superpavemixdesign
 
Block 4 SP 14
Block 4 SP 14Block 4 SP 14
Block 4 SP 14
 
Block 10 superpave agg requirements 13
Block 10 superpave agg requirements 13Block 10 superpave agg requirements 13
Block 10 superpave agg requirements 13
 
Block 25 Control Charts 13
Block 25   Control Charts 13Block 25   Control Charts 13
Block 25 Control Charts 13
 
Block 6 SP 14
Block 6 SP 14Block 6 SP 14
Block 6 SP 14
 
Block 3 SP 14
Block 3 SP 14Block 3 SP 14
Block 3 SP 14
 
Block 13 Mix design Historical 13
Block 13 Mix design Historical 13Block 13 Mix design Historical 13
Block 13 Mix design Historical 13
 
Rigid pavement distress
Rigid pavement distress Rigid pavement distress
Rigid pavement distress
 

Similaire à Block 33 HMA Overlays c SP 13

High performance concrete project
High performance concrete projectHigh performance concrete project
High performance concrete projectakhil reddy
 
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...Nick Bentley
 
2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...
2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...
2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...California Asphalt Pavement Association
 
Nebraska Precast Concrete Pavement
Nebraska Precast Concrete PavementNebraska Precast Concrete Pavement
Nebraska Precast Concrete PavementJill Reeves
 
CE 533 Chapter 21.pptx
CE 533 Chapter 21.pptxCE 533 Chapter 21.pptx
CE 533 Chapter 21.pptxMarcWorld
 
Your Score 1420Not bad. Your score means youre slightly bette.docx
Your Score 1420Not bad. Your score means youre slightly bette.docxYour Score 1420Not bad. Your score means youre slightly bette.docx
Your Score 1420Not bad. Your score means youre slightly bette.docxodiliagilby
 
Amtrak: Soil Stabilization for High Speed
Amtrak: Soil Stabilization for High Speed Amtrak: Soil Stabilization for High Speed
Amtrak: Soil Stabilization for High Speed Hilit Noy
 
PCC Pavement: Repair vs. Overlay vs. Reconstruction
PCC Pavement: Repair vs. Overlay vs. ReconstructionPCC Pavement: Repair vs. Overlay vs. Reconstruction
PCC Pavement: Repair vs. Overlay vs. ReconstructionJill Reeves
 
Maintaining Access on Concrete Overlay Projects
Maintaining Access on Concrete Overlay ProjectsMaintaining Access on Concrete Overlay Projects
Maintaining Access on Concrete Overlay ProjectsJill Reeves
 
maintenance and rehabilitation of pavements by Roshan .ppt
maintenance and rehabilitation of pavements by Roshan .pptmaintenance and rehabilitation of pavements by Roshan .ppt
maintenance and rehabilitation of pavements by Roshan .pptRoshani Shahi
 
Exxon-Limiter Redesign-Reaming and Hole Conditioning 09-14-19.ppt
Exxon-Limiter Redesign-Reaming and Hole Conditioning 09-14-19.pptExxon-Limiter Redesign-Reaming and Hole Conditioning 09-14-19.ppt
Exxon-Limiter Redesign-Reaming and Hole Conditioning 09-14-19.pptssuseraa800d
 
Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)SSudhaVelan
 
Essentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersEssentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersjose bonifacio de souza leite cuadros
 
Sne closure turf presentation combined
Sne closure turf presentation combinedSne closure turf presentation combined
Sne closure turf presentation combinedMassRecycle .
 

Similaire à Block 33 HMA Overlays c SP 13 (20)

2022 Spring Educational Workshop presentation on QA for CIR and CCPR
2022 Spring Educational Workshop presentation on QA for CIR and CCPR2022 Spring Educational Workshop presentation on QA for CIR and CCPR
2022 Spring Educational Workshop presentation on QA for CIR and CCPR
 
2022 presentation on effective pavement program management by the UCPRC
2022 presentation on effective pavement program management by the UCPRC2022 presentation on effective pavement program management by the UCPRC
2022 presentation on effective pavement program management by the UCPRC
 
High performance concrete project
High performance concrete projectHigh performance concrete project
High performance concrete project
 
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
 
2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...
2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...
2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...
 
Nebraska Precast Concrete Pavement
Nebraska Precast Concrete PavementNebraska Precast Concrete Pavement
Nebraska Precast Concrete Pavement
 
Contech Slotted Drain for Commercial Markets
Contech Slotted Drain for Commercial MarketsContech Slotted Drain for Commercial Markets
Contech Slotted Drain for Commercial Markets
 
Hans Ho: Pavement maintenance challenges and opportunities
Hans Ho: Pavement maintenance challenges and opportunitiesHans Ho: Pavement maintenance challenges and opportunities
Hans Ho: Pavement maintenance challenges and opportunities
 
FRC Pavements
FRC PavementsFRC Pavements
FRC Pavements
 
CE 533 Chapter 21.pptx
CE 533 Chapter 21.pptxCE 533 Chapter 21.pptx
CE 533 Chapter 21.pptx
 
2016 apwa ch pres cir and fdr 4 20-16
2016 apwa ch pres cir and fdr 4 20-162016 apwa ch pres cir and fdr 4 20-16
2016 apwa ch pres cir and fdr 4 20-16
 
Your Score 1420Not bad. Your score means youre slightly bette.docx
Your Score 1420Not bad. Your score means youre slightly bette.docxYour Score 1420Not bad. Your score means youre slightly bette.docx
Your Score 1420Not bad. Your score means youre slightly bette.docx
 
Amtrak: Soil Stabilization for High Speed
Amtrak: Soil Stabilization for High Speed Amtrak: Soil Stabilization for High Speed
Amtrak: Soil Stabilization for High Speed
 
PCC Pavement: Repair vs. Overlay vs. Reconstruction
PCC Pavement: Repair vs. Overlay vs. ReconstructionPCC Pavement: Repair vs. Overlay vs. Reconstruction
PCC Pavement: Repair vs. Overlay vs. Reconstruction
 
Maintaining Access on Concrete Overlay Projects
Maintaining Access on Concrete Overlay ProjectsMaintaining Access on Concrete Overlay Projects
Maintaining Access on Concrete Overlay Projects
 
maintenance and rehabilitation of pavements by Roshan .ppt
maintenance and rehabilitation of pavements by Roshan .pptmaintenance and rehabilitation of pavements by Roshan .ppt
maintenance and rehabilitation of pavements by Roshan .ppt
 
Exxon-Limiter Redesign-Reaming and Hole Conditioning 09-14-19.ppt
Exxon-Limiter Redesign-Reaming and Hole Conditioning 09-14-19.pptExxon-Limiter Redesign-Reaming and Hole Conditioning 09-14-19.ppt
Exxon-Limiter Redesign-Reaming and Hole Conditioning 09-14-19.ppt
 
Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)
 
Essentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersEssentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designers
 
Sne closure turf presentation combined
Sne closure turf presentation combinedSne closure turf presentation combined
Sne closure turf presentation combined
 

Plus de Chris Yarnell

Block 24 Obtaining Samples 13
Block 24   Obtaining Samples 13Block 24   Obtaining Samples 13
Block 24 Obtaining Samples 13Chris Yarnell
 
Block 23 Sampling - Theory 13
Block 23   Sampling - Theory 13Block 23   Sampling - Theory 13
Block 23 Sampling - Theory 13Chris Yarnell
 
Block 22 basic concepts
Block 22   basic conceptsBlock 22   basic concepts
Block 22 basic conceptsChris Yarnell
 
Block 21 Background 13
Block 21   Background 13Block 21   Background 13
Block 21 Background 13Chris Yarnell
 
Block 26 Acceptance 13
Block 26   Acceptance 13Block 26   Acceptance 13
Block 26 Acceptance 13Chris Yarnell
 
Asphalt Plant Presentation - Guest Speaker
Asphalt Plant Presentation - Guest SpeakerAsphalt Plant Presentation - Guest Speaker
Asphalt Plant Presentation - Guest SpeakerChris Yarnell
 
Block 20 Types of Rollers 13
Block 20   Types of Rollers 13Block 20   Types of Rollers 13
Block 20 Types of Rollers 13Chris Yarnell
 
Block 19 Compacitons Background 13
Block 19   Compacitons Background 13Block 19   Compacitons Background 13
Block 19 Compacitons Background 13Chris Yarnell
 
Block 18 Placement 13
Block 18   Placement 13Block 18   Placement 13
Block 18 Placement 13Chris Yarnell
 
Block 17 Delivery aka Trucking 13
Block 17   Delivery aka Trucking 13Block 17   Delivery aka Trucking 13
Block 17 Delivery aka Trucking 13Chris Yarnell
 
Block 16 Drum Plants 13
Block 16   Drum Plants 13Block 16   Drum Plants 13
Block 16 Drum Plants 13Chris Yarnell
 
Block 15 Batch Plants 13
Block 15   Batch Plants 13Block 15   Batch Plants 13
Block 15 Batch Plants 13Chris Yarnell
 

Plus de Chris Yarnell (20)

Block 5 SP 14
Block 5 SP 14Block 5 SP 14
Block 5 SP 14
 
Block 2 SP 14
Block 2 SP 14Block 2 SP 14
Block 2 SP 14
 
Block 1 SP 14
Block 1 SP 14Block 1 SP 14
Block 1 SP 14
 
Block 32 SP 13
Block 32  SP 13Block 32  SP 13
Block 32 SP 13
 
Block 31 SP 13
Block 31   SP 13Block 31   SP 13
Block 31 SP 13
 
Block 30 SP 13
Block 30   SP 13Block 30   SP 13
Block 30 SP 13
 
Block 29 SP 13
Block 29   SP 13Block 29   SP 13
Block 29 SP 13
 
Block 28 Sp 13
Block 28   Sp 13Block 28   Sp 13
Block 28 Sp 13
 
Block 24 Obtaining Samples 13
Block 24   Obtaining Samples 13Block 24   Obtaining Samples 13
Block 24 Obtaining Samples 13
 
Block 23 Sampling - Theory 13
Block 23   Sampling - Theory 13Block 23   Sampling - Theory 13
Block 23 Sampling - Theory 13
 
Block 22 basic concepts
Block 22   basic conceptsBlock 22   basic concepts
Block 22 basic concepts
 
Block 21 Background 13
Block 21   Background 13Block 21   Background 13
Block 21 Background 13
 
Block 26 Acceptance 13
Block 26   Acceptance 13Block 26   Acceptance 13
Block 26 Acceptance 13
 
Asphalt Plant Presentation - Guest Speaker
Asphalt Plant Presentation - Guest SpeakerAsphalt Plant Presentation - Guest Speaker
Asphalt Plant Presentation - Guest Speaker
 
Block 20 Types of Rollers 13
Block 20   Types of Rollers 13Block 20   Types of Rollers 13
Block 20 Types of Rollers 13
 
Block 19 Compacitons Background 13
Block 19   Compacitons Background 13Block 19   Compacitons Background 13
Block 19 Compacitons Background 13
 
Block 18 Placement 13
Block 18   Placement 13Block 18   Placement 13
Block 18 Placement 13
 
Block 17 Delivery aka Trucking 13
Block 17   Delivery aka Trucking 13Block 17   Delivery aka Trucking 13
Block 17 Delivery aka Trucking 13
 
Block 16 Drum Plants 13
Block 16   Drum Plants 13Block 16   Drum Plants 13
Block 16 Drum Plants 13
 
Block 15 Batch Plants 13
Block 15   Batch Plants 13Block 15   Batch Plants 13
Block 15 Batch Plants 13
 

Dernier

EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersPeter Horsten
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...Operational Excellence Consulting
 
Send Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSendBig4
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsIndiaMART InterMESH Limited
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterJamesConcepcion7
 
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdfChris Skinner
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerAggregage
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckHajeJanKamps
 
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryEffective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryWhittensFineJewelry1
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Planetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifePlanetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifeBhavana Pujan Kendra
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxappkodes
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
WSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdfWSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdfJamesConcepcion7
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
Supercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsSupercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsGOKUL JS
 
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...ssuserf63bd7
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdfMintel Group
 

Dernier (20)

EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exporters
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
 
Send Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.com
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan Dynamics
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare Newsletter
 
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon Harmer
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deck
 
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryEffective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
WAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdfWAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdf
 
Planetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifePlanetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in Life
 
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptxThe Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptx
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
WSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdfWSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdf
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Supercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsSupercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebs
 
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
 

Block 33 HMA Overlays c SP 13

  • 1. Rehab & Maint. HMA Overlays 1 HMA Overlays Over PCC Pavements Flexible Pavement Maintenance and Rehabilitation
  • 2. Rehab & Maint. HMA Overlays 2 Slab Preparation Techniques • Crack and seat (JPCP) • Break and seat (JRCP) • Rubblize (JPCP, JRCP, CRCP) • Saw and seal
  • 3. Rehab & Maint. HMA Overlays 3 PCC Reflection Cracking • By far, the biggest problem in HMA overlays of PCC pavement • Caused by movement at PCC joints and cracks Load- induced movement Joint Closes HMA Slabs Contract Joint Opens Slabs Expand Reflection crack
  • 4. Rehab & Maint. HMA Overlays 4 Cracking and Seating • Shortens effective slab length • Standard practice in many States • Not “generally” recommended for use on poor subgrades • Design methods (overlay thickness)
  • 5. Rehab & Maint. HMA Overlays 5 Cracking and Seating Overlay Subgrade Soil Subbase Firm Foundation Crack s Short slab length (~2’) Good granular interlock
  • 6. Rehab & Maint. HMA Overlays 6 Cracking and Seating
  • 7. Rehab & Maint. HMA Overlays 7 Cracking and Seating
  • 8. Rehab & Maint. HMA Overlays 8 Cracking and Seating - crack pattern
  • 9. Rehab & Maint. HMA Overlays 9 Cracking and Seating
  • 10. Rehab & Maint. HMA Overlays 10 What is rubblization? • Fracturing: – Eliminates slab action – Destroys bond between concrete and steel • Rubblized base responds as a tightly keyed, interlocked high-density, unbound layer – Layer cannot crack; already fractured
  • 11. Rehab & Maint. HMA Overlays 11 Why Rubblize? • Fracturing PCC to segments less than 9” precludes reflection of: – Joints – Cracks – Faults • Production Rates up to 1 lane-mile/day
  • 12. Rehab & Maint. HMA Overlays 12 HMA PCC Larger Pieces = Larger Movement = Cracking
  • 13. Rehab & Maint. HMA Overlays 13 HMA PCC Smaller Pieces = Smaller Movement = No Cracking
  • 14. Rehab & Maint. HMA Overlays 14 Benefits • Time savings –Choose work hours –High production rates • Economic Savings –Reduce user delay costs –Reduce construction costs
  • 15. Rehab & Maint. HMA Overlays 15 • Environmentally friendly –Reduce landfill –Reduce fuel consumption/air pollution • Smoothness –Eliminate reflection cracking/faulting Benefits (continued)
  • 16. Rehab & Maint. HMA Overlays 16 Construction Procedure • Install/replace existing edge drainage system as required • Remove existing overlay (if present) • Remove existing HMA patches, replace with aggregate base as required • Fracture the concrete pavement • Roll • Place HMA overlay (multiple lifts)
  • 17. Rehab & Maint. HMA Overlays 17 Resonant Pavement Breaker
  • 18. Rehab & Maint. HMA Overlays 18 Multi-Head Breaker (MHB)
  • 19. Rehab & Maint. HMA Overlays 19 Rolling
  • 20. Rehab & Maint. HMA Overlays 20 Particle Size • PCC fractured into 9 in.-minus pieces • Most pieces are 1- 4 in. diameter • Aggregate interlock maintained beneath surface • Rolling knits together surface particles
  • 21. Rehab & Maint. HMA Overlays 21 Sawing and Sealing Joints • Concede appearance of reflection cracking • Objective: control rate of deterioration • Reduces spalling of reflection cracks • Candidates should have well-defined joints • Sawcut must be directly above the • underlying joint
  • 22. Rehab & Maint. HMA Overlays 22 Sawing and Sealing Joints Reflection crack Overlay Old pavement Sealant Initial sawcut 1/3 depth Horizontal opening Joint reservoir Subgrade Vertical differential movement
  • 23. Rehab & Maint. HMA Overlays 23 Sawing and Sealing Joints
  • 24. Rehab & Maint. HMA Overlays 24 Questions?

Notes de l'éditeur

  1. HMA mixtures are routinely used to overlay PCC pavements. The following slides describe construction processes that are used.
  2. These are the four procedures used. The first two are basically the same process except one is used for Jointed Plane Concrete Pavement (JPCP) and the other is used for Jointed Reinforced Concrete Pavement (JRCP).
  3. The most common form of distress in HMA overlays of PCC is reflection cracking. This is a result of the concrete slabs contracting and expanding with temperature changes, which cause the joints and cracks to open and close. This opening and closing causes a crack to form in the HMA directly over the opening in the concrete. Also, if the concrete slabs are not firmly seated on the underlying material, traffic loads going over the joints will cause the joints to move up and down vertically. This movement will cause shearing in the asphalt over the joint and create a reflection crack.
  4. The concept behind cracking and seating and breaking and seating is to shorten the slab length and therefore the amount of force transferred to the overlay from the movement of the slabs.
  5. The goal is to break the slab through the entire pavement structure. But, load transfer still exists through the aggregate interlock that will form around the cracks.
  6. This is a machine used for the process. It is basically a large guillotine that rises and falls and cracks the pavement slabs.
  7. The surface of the pavement after the guillotine has gone over it.
  8. The crack pattern from cracking and seating.
  9. After the pavement has been cracked and seated it should be proof rolled with a large pneumatic roller.
  10. Rubblization eliminates slab action by 1) destroying the geometry of the slab and 2) seating the concrete firmly against the underlying subbase or soil. It also breaks the bond between the concrete and any steel present in the slab, eliminating detrimental effects caused by corrosion of the steel and further reducing the ability of the concrete to act as a mass. The rubblized concrete responds as a tightly packed, high-density granular material. The rough, hard particles provide an internal friction to resist rutting while the lack of tension prevents cracking.
  11. Fracturing the surface of the concrete to a relatively small size means that features and problems in the old concrete surface such as joints, cracks and faults cannot reappear in the HMA overlay. This prolongs the life of the overlay and helps to ensure a smooth pavement. Production rates with rubblization are up to 1 lane-mile per day, much faster than other types of PCC rehabilitation. This means lower construction costs and less inconvenience to road users, giving substance to the slogan “Get In, Get Out, Stay Out.”
  12. The more concrete there is to expand and contract as the temperature changes, the greater the movement of the slab, and the greater the opening of joints and cracks. (Presenter: Hit enter to show progress of movement and widening of PCC joint and reflection crack.)
  13. Rubblization reduces the size of concrete pieces so that the expansion and contraction causes a minimum of movement. The space between the fractured pieces moves less so that the cracks are not reflected through the surface. And, because the process seats the pieces of concrete, reflection cracking through shearing at the joints does not occur.
  14. In addition to better HMA overlay performance, rubblization offers savings in terms of flexibility for construction time. So, if paving during rush hour is prohibitive due to traffic volume, construction can be moved to off-peak hours. And, because production rates of up to 1 mile/day can be achieved, the road can be rehabilitated quickly. Rubblization with an HMA overlay means economic savings to both users and agencies. Because of the speed of construction, users may avoid costly delays. Construction costs are reduced due to the speed of construction, the ability to leave the old PCC in place, and the lower cost of HMA placement.
  15. Rubblization leaves the PCC material in place so landfill space is conserved and haul trucks do not contribute to air pollution and fuel consumption. The problems in the existing PCC associated with cracking and faulting will not appear in the new HMA surface, ensuring a smooth ride.
  16. The construction process is straight forward. First concerns about subsurface drainage should be addressed by placing edge drains in the pavement if they are needed. If there is an existing HMA overlay, it should be milled off. Any HMA patches in the concrete should be removed and replaced with aggregate base material as needed. The point is to give uniformity to the pavement support and ensure proper drainage. The concrete is fractured using either a multiple head breaker or a resonant breaker. The rubblized material is then compacted using a combination of rollers to ensure that the concrete pieces are seated and locked together. And, finally, the required thickness of an HMA overlay is placed over the top.
  17. The Resonant Pavement Breaker (RPB) uses a low-amplitude 2000-pound force applied at a frequency of 44 cycles per second to fracture the concrete pavement.
  18. The multi-head breaker (MHB) has a number of hammers mounted laterally in pairs. Half of the hammers are located in a forward row and the rest are diagonally arranged in a rear row so that breakage occurs continuously from side to side. The MHB is capable of rubblizing a 13-foot lane in one pass.
  19. Once the rubblization is complete, a 10-ton steel wheel vibratory roller is used to pack the loose rubble together initially. This is usually followed by one or two passes of a pneumatic roller. Finally, the material is rolled for one or two more passes by a vibratory roller just before the first lift of HMA.
  20. Most specifications allow for a maximum particle size of 6 to 9 inches in the top part of the concrete slab. The majority of the concrete particles are in the range of 1 to 4 inches. Aggregate interlock is maintained in the concrete because the subsurface particles are only fractured, not reoriented. The rolling after rubblization helps to knit the surface particles together and seat the bottom of the concrete firmly against the underlying material.