SlideShare une entreprise Scribd logo
1  sur  5
Télécharger pour lire hors ligne
Importance of Appropriate and Robust SLAs in Outsourcing
                  A Case Study of London Underground Limited



The Scene


London Underground Limited (LUL) outsourced its communications infrastructure and operations
through a Special Purpose Vehicle (SPV) called Citylink (through a PFI scheme). Citylink is
owned by the partner companies contributing to the project, including Thales, Motorola and Fluor
Daniel.



The Businesses Problems


As part of project Connect, LUL granted Citylink a licence to provide telecommunications services
to LUL for a period of 25 years. Citylink is allowed to charge a tariff for the provision of these
services, but it is a condition of the licence that the whole radio and transmission infrastructure of
the London Tube will be replaced.

Citylink has two primary sub-contractors. Flour Daniel is charged with the regeneration project
and the delivery of the new infrastructure. Thales Translink is responsible for the operation of the
services throughout the life of the project.

LUL was keen to establish robust Service Level Agreements (SLAs) to ensure that: the outsource
provider delivers services as required; is incentivised to improve performance; and that sanctions
are available where it fails to deliver as required.



The Business Solution


LUL set up a complex SLA structure that is imposed on Citylink. Citylink has passed this on,
where relevant to its sub-contractors. The purpose of the SLAs are to ensure that Citylink meets
all of its obligations to the project.

In the procurement specification, LUL allowed the bidders considerable freedom in constructing
their tariff, but insisted that its format and construction should be to a predetermined pattern. The
bidders could alter the relative parameters, but not the structure of the tariffs. Whilst some of the
tariff structure revolved about finance and indexation, much of it was controlled by the
requirements of the SLAs. This definition resulted in a large and complex formula that took all of
the aspects of pricing into account at one go.




Op2i Case Study – Setting appropriate and robust SLAs                                     Page 1 of 5
The Connect project was divided into two primary parts, one the replacement of the fibre
transmission infrastructure and the other the replacement of the radio infrastructure.

The contractor was allowed to charge for the provision of services by means of a tariff that was
controlled by a range of factors that included delivery of the new infrastructure as well as the
operational performance that was achieved throughout the life of the project.

For each of the main projects (transmission and radio) the tariff was forced to start low and then
increase in proportion to the rate of roll out of new infrastructure as the building programme
progressed. The intent was that over the long period of the licence, the contractor would be able
to obtain funding from the City to invest and that the profit on that investment would build up
towards the latter years in order to make the whole project attractive as an investment
proposition.

There are also two sanction elements over and above the performance SLAs, these are
Deficiency Points and Liquidated Damages. These operate in addition to the sanctions that are
imposed for failure to meet the performance / quality thresholds.




Op2i Case Study – Setting appropriate and robust SLAs                                 Page 2 of 5
Deficiency points are intended to ensure that basic procedures are kept up to scratch. Some 41
different procedural failures are defined in different areas of the operation of the project. These
include:

       Safety
       Quality
       Audit
       Contract management
       Contract programme
       Contract conditions
       Record keeping
       Service procedures

Each type of failure is allocated to a specific class, A, B or C. A Class A failure accrues 5
deficiency points, Class B 2 points and Class C 1 point.

Each failure can be ‘Redeemable’ or not. If redeemable then the contractor is given a period
within which to overcome the failure. If this fails then the deficiency points stand. Equally, each
type of failure can be classified as a ‘Withholding’ failure. This type of failure can give rise to
retention of some part of the payment from LUL until it is resolved. Further, there is a mechanistic
link to the tariff so that in addition to the penalties already described, there is a tariff penalty that
bears little relationship to the severity of the failure or the attempts that have been made to
correct it.

In imposing its Liquidated Damages, LUL first produced a set of tables that quantified the
earnings of the Tube for every 15-minute segment of the day for every line and station in respect
of
      Slow running and delay
      Speed restriction
      Partial line closure
      Late start up of depots
      Train cancellation
      Station closure
      Signal failure
      Reduced service

The tables that define these earning figures are extremely complex. The impact of every failure of
the telecommunications system is then analysed in terms of these parameters and penalties
extracted from the contractor that are in proportion to the loss of business caused by that failure.


Implementation

Performance SLAs

There are three aspects of performance that LUL recognises in its SLAs. Only two of them affect
the tariff:

       Performance
       Quality
       Capacity (this parameter is not linked to the tariff)

Performance always relates to Availability, Time to Repair and Number of Faults. Quality relates
to softer measures of performance and includes Key Performance Indicators (KPIs); Customer
care; cleaning, spares etc.



Op2i Case Study – Setting appropriate and robust SLAs                                       Page 3 of 5
Below this level, each project has sub services and the performance figures for each service vary,
but the structure of the SLAs does not.

Each service is defined in terms of a service category and a sub-category. Each sub-category
has a Quality of Service (QoS) definition. For each sub-category, there are three operational SLA
parameters specified, Target Availability, Maximum Time To Restore service and Maximum
failures per circuit per annum.

There are three Implementation parameters specified, and these are the average and maximum
days to Provide, Cease and Move a service and finally there are capacity measures (Capacity
utilised, Capacity installed and Maximum capacity).

The outsource provider must report against all these parameter on a four weekly basis.

Quality of Service measures apply to a number of parameters including:

       Key performance indicators
       Cleaning
       Customer care
       Spares
       etc

Operational SLAs

Their structure is described in more detail with typical figures for some of the parameters to show
how the SLAs are constructed. Again, this is not an exhaustive catalogue of the whole SLA
contract.

For the Target Availability parameter, services are divided into three categories:

       Safety related services (1)
       Business critical services (2)
       Other services (3)

Each service and sub-service then has an Availability target specified for each of these
categories and in the transmission class of services.

Reporting is required on a four weekly basis for the average availability, with a report on the
percentage of circuits not meeting the target as supplementary information.

A similar approach is taken with the Time To Restore service (TTR) parameter. Again the three
categories (1 – 3 above) apply, but in addition failures are divided into Actual Loss of Service and
Loss of a Redundant Service that puts the primary service in jeopardy.

The final Operational SLA parameter is Loss of Service per Circuit. This is a measure of the
reliability (MTBF) of the circuits.

Implementation SLAs

LUL divided these up by the type of location into which services are being provided. These are
defined as Office, Railway and Tunnel. For obvious reasons there are safety implications of
working on railway locations. Similarly tunnels are highly restricted as far as access is concerned
and the four-hour access window overnight can be oversubscribed. In addition, a distinction is
made between the provision of Infrastructure and the provision of services over existing
infrastructure


Op2i Case Study – Setting appropriate and robust SLAs                                   Page 4 of 5
Overriding SLA Factors

LUL require that the SLAs that apply to any third party provided services (e.g. from the incumbent
telecommunications operator) should be passed through Citylink unchanged.

To ensure that there are no elements of doubt, each service sub-category has a clearly defined
demarcation point that specifies where responsibility for the service changes from Citylink to LUL.

There are three other features of the LUL SLAs.

a) A general requirement placed on Citylink that its Network Management System must:

        Be capable of reporting down to individual circuit level
        Be capable of reporting current status
        Provide a remote access terminal for LUL users

b) A responsibility accepted by LUL to provide a ‘load’ prediction covering the period from 3 – 10
years ahead of the current date.

c) A clause that appears in similar form in each of the technology areas:
        “As part of the design process, the Contractor shall demonstrate by means of reliability
        and maintainability analysis, that the New Transmission Network [Radio network etc…] is
        capable of meeting the relevant Service Performance criteria given in this section of the
        specification”




                                 Op2i
         A Business Improvement Firm Specialising in Outsourcing

        Providing Advisory, Implementation, Brokerage and Managed
                            Outsourcing Solutions

                                     Contact@Op2i.com

                                        www.Op2i.com




Op2i Case Study – Setting appropriate and robust SLAs                                  Page 5 of 5

Contenu connexe

Tendances

Transmission congestion management in deregulated power system operations [ww...
Transmission congestion management in deregulated power system operations [ww...Transmission congestion management in deregulated power system operations [ww...
Transmission congestion management in deregulated power system operations [ww...WriteKraft Dissertations
 
Lte drivetest guideline with genex assistant
Lte drivetest guideline with genex assistantLte drivetest guideline with genex assistant
Lte drivetest guideline with genex assistantRay KHASTUR
 
C20 20090615-019-alu csfb-performance_enhance
C20 20090615-019-alu csfb-performance_enhanceC20 20090615-019-alu csfb-performance_enhance
C20 20090615-019-alu csfb-performance_enhanceEmmanuel Msumali
 
Rf optimisation
Rf optimisationRf optimisation
Rf optimisationAnto Radde
 
Xiamen caimore’s dtu applied in charging pile solution based on wireless moni...
Xiamen caimore’s dtu applied in charging pile solution based on wireless moni...Xiamen caimore’s dtu applied in charging pile solution based on wireless moni...
Xiamen caimore’s dtu applied in charging pile solution based on wireless moni...Cynthia Wang
 
Congestion Management Approaches in Deregulated Electricity Market: A Compreh...
Congestion Management Approaches in Deregulated Electricity Market: A Compreh...Congestion Management Approaches in Deregulated Electricity Market: A Compreh...
Congestion Management Approaches in Deregulated Electricity Market: A Compreh...Dr. Sudhir Kumar Srivastava
 

Tendances (7)

Transmission congestion management in deregulated power system operations [ww...
Transmission congestion management in deregulated power system operations [ww...Transmission congestion management in deregulated power system operations [ww...
Transmission congestion management in deregulated power system operations [ww...
 
Lte drivetest guideline with genex assistant
Lte drivetest guideline with genex assistantLte drivetest guideline with genex assistant
Lte drivetest guideline with genex assistant
 
C20 20090615-019-alu csfb-performance_enhance
C20 20090615-019-alu csfb-performance_enhanceC20 20090615-019-alu csfb-performance_enhance
C20 20090615-019-alu csfb-performance_enhance
 
Rf optimisation
Rf optimisationRf optimisation
Rf optimisation
 
telco
telcotelco
telco
 
Xiamen caimore’s dtu applied in charging pile solution based on wireless moni...
Xiamen caimore’s dtu applied in charging pile solution based on wireless moni...Xiamen caimore’s dtu applied in charging pile solution based on wireless moni...
Xiamen caimore’s dtu applied in charging pile solution based on wireless moni...
 
Congestion Management Approaches in Deregulated Electricity Market: A Compreh...
Congestion Management Approaches in Deregulated Electricity Market: A Compreh...Congestion Management Approaches in Deregulated Electricity Market: A Compreh...
Congestion Management Approaches in Deregulated Electricity Market: A Compreh...
 

En vedette

Challenges during Design and Construction of an Underground Chip Factory (Waf...
Challenges during Design and Construction of an Underground Chip Factory (Waf...Challenges during Design and Construction of an Underground Chip Factory (Waf...
Challenges during Design and Construction of an Underground Chip Factory (Waf...Helmut Wannenmacher
 
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...IEI GSC
 
SSH Tunneling Recipes
SSH Tunneling RecipesSSH Tunneling Recipes
SSH Tunneling RecipesOSOCO
 
The Use of GIS and GPS in Pipeline Permitting and Regulatory Compliance
The Use of GIS and GPS in Pipeline Permitting and Regulatory ComplianceThe Use of GIS and GPS in Pipeline Permitting and Regulatory Compliance
The Use of GIS and GPS in Pipeline Permitting and Regulatory Compliancewlgardnerjr
 
Tunneling Construction - NATM
Tunneling Construction - NATMTunneling Construction - NATM
Tunneling Construction - NATMluisaam
 
DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)Sukhdarshan Singh
 
UNDERWATER CONSTRUCTION
UNDERWATER CONSTRUCTIONUNDERWATER CONSTRUCTION
UNDERWATER CONSTRUCTIONHamsui Harold
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineeringAdil Shaikh
 
The tunnel powerpoint
The tunnel powerpointThe tunnel powerpoint
The tunnel powerpointishict
 
Underground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminarUnderground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminarPavan Kumar N
 
GIS and GPS - applications in civil engg
GIS and GPS - applications  in civil enggGIS and GPS - applications  in civil engg
GIS and GPS - applications in civil enggPundlik Rathod
 

En vedette (13)

Challenges during Design and Construction of an Underground Chip Factory (Waf...
Challenges during Design and Construction of an Underground Chip Factory (Waf...Challenges during Design and Construction of an Underground Chip Factory (Waf...
Challenges during Design and Construction of an Underground Chip Factory (Waf...
 
Golfgis English
Golfgis EnglishGolfgis English
Golfgis English
 
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
 
SSH Tunneling Recipes
SSH Tunneling RecipesSSH Tunneling Recipes
SSH Tunneling Recipes
 
The Use of GIS and GPS in Pipeline Permitting and Regulatory Compliance
The Use of GIS and GPS in Pipeline Permitting and Regulatory ComplianceThe Use of GIS and GPS in Pipeline Permitting and Regulatory Compliance
The Use of GIS and GPS in Pipeline Permitting and Regulatory Compliance
 
Tunneling Construction - NATM
Tunneling Construction - NATMTunneling Construction - NATM
Tunneling Construction - NATM
 
DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)
 
UNDERWATER CONSTRUCTION
UNDERWATER CONSTRUCTIONUNDERWATER CONSTRUCTION
UNDERWATER CONSTRUCTION
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineering
 
The tunnel powerpoint
The tunnel powerpointThe tunnel powerpoint
The tunnel powerpoint
 
Tunnelling
TunnellingTunnelling
Tunnelling
 
Underground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminarUnderground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminar
 
GIS and GPS - applications in civil engg
GIS and GPS - applications  in civil enggGIS and GPS - applications  in civil engg
GIS and GPS - applications in civil engg
 

Similaire à SLAs the heart of Outsourcing

CP_on_Review_of_Network_related_QoS
CP_on_Review_of_Network_related_QoSCP_on_Review_of_Network_related_QoS
CP_on_Review_of_Network_related_QoSSARJANA YADAV
 
An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...
An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...
An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...Cisco Canada
 
Basics of performance measurement in umts
Basics of performance measurement in umtsBasics of performance measurement in umts
Basics of performance measurement in umtsEkwere Udoh
 
Requirements of a Recovery Solution for Failure of Composite Web Services
Requirements of a Recovery Solution for Failure of Composite Web Services Requirements of a Recovery Solution for Failure of Composite Web Services
Requirements of a Recovery Solution for Failure of Composite Web Services dannyijwest
 
Optimization Services (2010)
Optimization Services (2010)Optimization Services (2010)
Optimization Services (2010)Marc Jadoul
 
Interconnect costing for mobile operators - ITU (RWG) Forum Bangkok 2005
Interconnect costing for mobile operators   - ITU (RWG) Forum Bangkok 2005Interconnect costing for mobile operators   - ITU (RWG) Forum Bangkok 2005
Interconnect costing for mobile operators - ITU (RWG) Forum Bangkok 2005Ahmad Nadeem Syed
 
A Profit Maximization Scheme with Guaranteed Quality of Service in Cloud Comp...
A Profit Maximization Scheme with Guaranteed Quality of Service in Cloud Comp...A Profit Maximization Scheme with Guaranteed Quality of Service in Cloud Comp...
A Profit Maximization Scheme with Guaranteed Quality of Service in Cloud Comp...1crore projects
 
A profit maximization scheme with guaranteed quality of service in cloud comp...
A profit maximization scheme with guaranteed quality of service in cloud comp...A profit maximization scheme with guaranteed quality of service in cloud comp...
A profit maximization scheme with guaranteed quality of service in cloud comp...Pvrtechnologies Nellore
 
A return to engineering a return to performance poster
A return to engineering a return to performance posterA return to engineering a return to performance poster
A return to engineering a return to performance posterMelissa Gaspari
 
Technical qo s and kpi lebanon
Technical qo s  and kpi lebanonTechnical qo s  and kpi lebanon
Technical qo s and kpi lebanonharoudaki
 
112/2009 1-
112/2009 1-112/2009 1-
112/2009 1-traoman
 
LEK - Rail industry cost and revenue sharing.pdf
LEK - Rail industry cost and revenue sharing.pdfLEK - Rail industry cost and revenue sharing.pdf
LEK - Rail industry cost and revenue sharing.pdfTorainYang
 
A framework for streamlining globally integrated services
A framework for streamlining globally integrated servicesA framework for streamlining globally integrated services
A framework for streamlining globally integrated servicesAli Elkhateb
 
ofgem_-_availability_model_update_-_final.pdf
ofgem_-_availability_model_update_-_final.pdfofgem_-_availability_model_update_-_final.pdf
ofgem_-_availability_model_update_-_final.pdfJoseValenzuela982948
 
ofgem_-_availability_model_update_-_final.pdf
ofgem_-_availability_model_update_-_final.pdfofgem_-_availability_model_update_-_final.pdf
ofgem_-_availability_model_update_-_final.pdfJoseValenzuela982948
 
Apq Qms Project Plan
Apq Qms Project PlanApq Qms Project Plan
Apq Qms Project PlanEng-Mohammad
 

Similaire à SLAs the heart of Outsourcing (20)

Call_Drop
Call_DropCall_Drop
Call_Drop
 
Call drop
Call dropCall drop
Call drop
 
CP_on_Review_of_Network_related_QoS
CP_on_Review_of_Network_related_QoSCP_on_Review_of_Network_related_QoS
CP_on_Review_of_Network_related_QoS
 
An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...
An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...
An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...
 
Basics of performance measurement in umts
Basics of performance measurement in umtsBasics of performance measurement in umts
Basics of performance measurement in umts
 
Requirements of a Recovery Solution for Failure of Composite Web Services
Requirements of a Recovery Solution for Failure of Composite Web Services Requirements of a Recovery Solution for Failure of Composite Web Services
Requirements of a Recovery Solution for Failure of Composite Web Services
 
Optimization Services (2010)
Optimization Services (2010)Optimization Services (2010)
Optimization Services (2010)
 
Converged & Efficient Licensing Framework
Converged & Efficient Licensing FrameworkConverged & Efficient Licensing Framework
Converged & Efficient Licensing Framework
 
Interconnect costing for mobile operators - ITU (RWG) Forum Bangkok 2005
Interconnect costing for mobile operators   - ITU (RWG) Forum Bangkok 2005Interconnect costing for mobile operators   - ITU (RWG) Forum Bangkok 2005
Interconnect costing for mobile operators - ITU (RWG) Forum Bangkok 2005
 
A Profit Maximization Scheme with Guaranteed Quality of Service in Cloud Comp...
A Profit Maximization Scheme with Guaranteed Quality of Service in Cloud Comp...A Profit Maximization Scheme with Guaranteed Quality of Service in Cloud Comp...
A Profit Maximization Scheme with Guaranteed Quality of Service in Cloud Comp...
 
A profit maximization scheme with guaranteed quality of service in cloud comp...
A profit maximization scheme with guaranteed quality of service in cloud comp...A profit maximization scheme with guaranteed quality of service in cloud comp...
A profit maximization scheme with guaranteed quality of service in cloud comp...
 
A return to engineering a return to performance poster
A return to engineering a return to performance posterA return to engineering a return to performance poster
A return to engineering a return to performance poster
 
Technical qo s and kpi lebanon
Technical qo s  and kpi lebanonTechnical qo s  and kpi lebanon
Technical qo s and kpi lebanon
 
Hillsborough County's Major Building Repairs and Maintenance Program
Hillsborough County's Major Building Repairs and Maintenance ProgramHillsborough County's Major Building Repairs and Maintenance Program
Hillsborough County's Major Building Repairs and Maintenance Program
 
112/2009 1-
112/2009 1-112/2009 1-
112/2009 1-
 
LEK - Rail industry cost and revenue sharing.pdf
LEK - Rail industry cost and revenue sharing.pdfLEK - Rail industry cost and revenue sharing.pdf
LEK - Rail industry cost and revenue sharing.pdf
 
A framework for streamlining globally integrated services
A framework for streamlining globally integrated servicesA framework for streamlining globally integrated services
A framework for streamlining globally integrated services
 
ofgem_-_availability_model_update_-_final.pdf
ofgem_-_availability_model_update_-_final.pdfofgem_-_availability_model_update_-_final.pdf
ofgem_-_availability_model_update_-_final.pdf
 
ofgem_-_availability_model_update_-_final.pdf
ofgem_-_availability_model_update_-_final.pdfofgem_-_availability_model_update_-_final.pdf
ofgem_-_availability_model_update_-_final.pdf
 
Apq Qms Project Plan
Apq Qms Project PlanApq Qms Project Plan
Apq Qms Project Plan
 

Plus de Dr Bharat Vagadia

Op2i Survey 2010 Exec Summary Final
Op2i Survey 2010 Exec Summary FinalOp2i Survey 2010 Exec Summary Final
Op2i Survey 2010 Exec Summary FinalDr Bharat Vagadia
 
Op2i Outsourcing Survey 2008 Exec Report
Op2i Outsourcing Survey 2008 Exec ReportOp2i Outsourcing Survey 2008 Exec Report
Op2i Outsourcing Survey 2008 Exec ReportDr Bharat Vagadia
 
Outsourcing Survey Findings - Snapshot
Outsourcing Survey Findings - SnapshotOutsourcing Survey Findings - Snapshot
Outsourcing Survey Findings - SnapshotDr Bharat Vagadia
 
The What, Why, How of Outsourcing and Offshoring
The What, Why, How of Outsourcing and OffshoringThe What, Why, How of Outsourcing and Offshoring
The What, Why, How of Outsourcing and OffshoringDr Bharat Vagadia
 
ICT Convergence driving growth in Outsourcing
ICT Convergence driving growth in OutsourcingICT Convergence driving growth in Outsourcing
ICT Convergence driving growth in OutsourcingDr Bharat Vagadia
 
Outsourcing Destinations Where to Offshore?
Outsourcing Destinations Where to Offshore?Outsourcing Destinations Where to Offshore?
Outsourcing Destinations Where to Offshore?Dr Bharat Vagadia
 

Plus de Dr Bharat Vagadia (7)

Op2i Survey 2010 Exec Summary Final
Op2i Survey 2010 Exec Summary FinalOp2i Survey 2010 Exec Summary Final
Op2i Survey 2010 Exec Summary Final
 
Legal Process Outsourcing
Legal Process OutsourcingLegal Process Outsourcing
Legal Process Outsourcing
 
Op2i Outsourcing Survey 2008 Exec Report
Op2i Outsourcing Survey 2008 Exec ReportOp2i Outsourcing Survey 2008 Exec Report
Op2i Outsourcing Survey 2008 Exec Report
 
Outsourcing Survey Findings - Snapshot
Outsourcing Survey Findings - SnapshotOutsourcing Survey Findings - Snapshot
Outsourcing Survey Findings - Snapshot
 
The What, Why, How of Outsourcing and Offshoring
The What, Why, How of Outsourcing and OffshoringThe What, Why, How of Outsourcing and Offshoring
The What, Why, How of Outsourcing and Offshoring
 
ICT Convergence driving growth in Outsourcing
ICT Convergence driving growth in OutsourcingICT Convergence driving growth in Outsourcing
ICT Convergence driving growth in Outsourcing
 
Outsourcing Destinations Where to Offshore?
Outsourcing Destinations Where to Offshore?Outsourcing Destinations Where to Offshore?
Outsourcing Destinations Where to Offshore?
 

Dernier

Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insightsseri bangash
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 

Dernier (20)

Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insights
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 

SLAs the heart of Outsourcing

  • 1. Importance of Appropriate and Robust SLAs in Outsourcing A Case Study of London Underground Limited The Scene London Underground Limited (LUL) outsourced its communications infrastructure and operations through a Special Purpose Vehicle (SPV) called Citylink (through a PFI scheme). Citylink is owned by the partner companies contributing to the project, including Thales, Motorola and Fluor Daniel. The Businesses Problems As part of project Connect, LUL granted Citylink a licence to provide telecommunications services to LUL for a period of 25 years. Citylink is allowed to charge a tariff for the provision of these services, but it is a condition of the licence that the whole radio and transmission infrastructure of the London Tube will be replaced. Citylink has two primary sub-contractors. Flour Daniel is charged with the regeneration project and the delivery of the new infrastructure. Thales Translink is responsible for the operation of the services throughout the life of the project. LUL was keen to establish robust Service Level Agreements (SLAs) to ensure that: the outsource provider delivers services as required; is incentivised to improve performance; and that sanctions are available where it fails to deliver as required. The Business Solution LUL set up a complex SLA structure that is imposed on Citylink. Citylink has passed this on, where relevant to its sub-contractors. The purpose of the SLAs are to ensure that Citylink meets all of its obligations to the project. In the procurement specification, LUL allowed the bidders considerable freedom in constructing their tariff, but insisted that its format and construction should be to a predetermined pattern. The bidders could alter the relative parameters, but not the structure of the tariffs. Whilst some of the tariff structure revolved about finance and indexation, much of it was controlled by the requirements of the SLAs. This definition resulted in a large and complex formula that took all of the aspects of pricing into account at one go. Op2i Case Study – Setting appropriate and robust SLAs Page 1 of 5
  • 2. The Connect project was divided into two primary parts, one the replacement of the fibre transmission infrastructure and the other the replacement of the radio infrastructure. The contractor was allowed to charge for the provision of services by means of a tariff that was controlled by a range of factors that included delivery of the new infrastructure as well as the operational performance that was achieved throughout the life of the project. For each of the main projects (transmission and radio) the tariff was forced to start low and then increase in proportion to the rate of roll out of new infrastructure as the building programme progressed. The intent was that over the long period of the licence, the contractor would be able to obtain funding from the City to invest and that the profit on that investment would build up towards the latter years in order to make the whole project attractive as an investment proposition. There are also two sanction elements over and above the performance SLAs, these are Deficiency Points and Liquidated Damages. These operate in addition to the sanctions that are imposed for failure to meet the performance / quality thresholds. Op2i Case Study – Setting appropriate and robust SLAs Page 2 of 5
  • 3. Deficiency points are intended to ensure that basic procedures are kept up to scratch. Some 41 different procedural failures are defined in different areas of the operation of the project. These include:  Safety  Quality  Audit  Contract management  Contract programme  Contract conditions  Record keeping  Service procedures Each type of failure is allocated to a specific class, A, B or C. A Class A failure accrues 5 deficiency points, Class B 2 points and Class C 1 point. Each failure can be ‘Redeemable’ or not. If redeemable then the contractor is given a period within which to overcome the failure. If this fails then the deficiency points stand. Equally, each type of failure can be classified as a ‘Withholding’ failure. This type of failure can give rise to retention of some part of the payment from LUL until it is resolved. Further, there is a mechanistic link to the tariff so that in addition to the penalties already described, there is a tariff penalty that bears little relationship to the severity of the failure or the attempts that have been made to correct it. In imposing its Liquidated Damages, LUL first produced a set of tables that quantified the earnings of the Tube for every 15-minute segment of the day for every line and station in respect of  Slow running and delay  Speed restriction  Partial line closure  Late start up of depots  Train cancellation  Station closure  Signal failure  Reduced service The tables that define these earning figures are extremely complex. The impact of every failure of the telecommunications system is then analysed in terms of these parameters and penalties extracted from the contractor that are in proportion to the loss of business caused by that failure. Implementation Performance SLAs There are three aspects of performance that LUL recognises in its SLAs. Only two of them affect the tariff:  Performance  Quality  Capacity (this parameter is not linked to the tariff) Performance always relates to Availability, Time to Repair and Number of Faults. Quality relates to softer measures of performance and includes Key Performance Indicators (KPIs); Customer care; cleaning, spares etc. Op2i Case Study – Setting appropriate and robust SLAs Page 3 of 5
  • 4. Below this level, each project has sub services and the performance figures for each service vary, but the structure of the SLAs does not. Each service is defined in terms of a service category and a sub-category. Each sub-category has a Quality of Service (QoS) definition. For each sub-category, there are three operational SLA parameters specified, Target Availability, Maximum Time To Restore service and Maximum failures per circuit per annum. There are three Implementation parameters specified, and these are the average and maximum days to Provide, Cease and Move a service and finally there are capacity measures (Capacity utilised, Capacity installed and Maximum capacity). The outsource provider must report against all these parameter on a four weekly basis. Quality of Service measures apply to a number of parameters including:  Key performance indicators  Cleaning  Customer care  Spares  etc Operational SLAs Their structure is described in more detail with typical figures for some of the parameters to show how the SLAs are constructed. Again, this is not an exhaustive catalogue of the whole SLA contract. For the Target Availability parameter, services are divided into three categories:  Safety related services (1)  Business critical services (2)  Other services (3) Each service and sub-service then has an Availability target specified for each of these categories and in the transmission class of services. Reporting is required on a four weekly basis for the average availability, with a report on the percentage of circuits not meeting the target as supplementary information. A similar approach is taken with the Time To Restore service (TTR) parameter. Again the three categories (1 – 3 above) apply, but in addition failures are divided into Actual Loss of Service and Loss of a Redundant Service that puts the primary service in jeopardy. The final Operational SLA parameter is Loss of Service per Circuit. This is a measure of the reliability (MTBF) of the circuits. Implementation SLAs LUL divided these up by the type of location into which services are being provided. These are defined as Office, Railway and Tunnel. For obvious reasons there are safety implications of working on railway locations. Similarly tunnels are highly restricted as far as access is concerned and the four-hour access window overnight can be oversubscribed. In addition, a distinction is made between the provision of Infrastructure and the provision of services over existing infrastructure Op2i Case Study – Setting appropriate and robust SLAs Page 4 of 5
  • 5. Overriding SLA Factors LUL require that the SLAs that apply to any third party provided services (e.g. from the incumbent telecommunications operator) should be passed through Citylink unchanged. To ensure that there are no elements of doubt, each service sub-category has a clearly defined demarcation point that specifies where responsibility for the service changes from Citylink to LUL. There are three other features of the LUL SLAs. a) A general requirement placed on Citylink that its Network Management System must:  Be capable of reporting down to individual circuit level  Be capable of reporting current status  Provide a remote access terminal for LUL users b) A responsibility accepted by LUL to provide a ‘load’ prediction covering the period from 3 – 10 years ahead of the current date. c) A clause that appears in similar form in each of the technology areas: “As part of the design process, the Contractor shall demonstrate by means of reliability and maintainability analysis, that the New Transmission Network [Radio network etc…] is capable of meeting the relevant Service Performance criteria given in this section of the specification” Op2i A Business Improvement Firm Specialising in Outsourcing Providing Advisory, Implementation, Brokerage and Managed Outsourcing Solutions Contact@Op2i.com www.Op2i.com Op2i Case Study – Setting appropriate and robust SLAs Page 5 of 5