September | 2013 Ministry of
Finance
B R A Z I L I A N G O V E R N M E N T
Brazil’seconomic outlook and
investment opportunities
infrastructure
3
Ministry
of Finance
Foreword
Economic Outlook
Economic Development and Demand for Infrastructure
Capital Market Instruments
Highways
Railways
Ports
Airports
Oil and Gas
Electricity
Appendix – Main types of business organizations in Brazil
Useful Links
Glossary	
Summary
5
7
33
45
53
65
79
83
93
101
121
126
128
5
Ministry
of Finance
5
Foreword
Foreword
Brazil currently presents an enormous opportunity for investment in infrastructure.
The Brazilian economy has changed substantially over the last ten years. From 2003 to 2012, real GDP increased by
41 percent, real total wages by 65 percent and domestic retail sales by 119 percent. It was a period of consolidation
for the domestic market, based on income growth and social inclusion. The country is currently among the biggest
markets in the world. In the last decade, investments grew by 71 percent, above GDP growth rates, but they should
increase even further in order to become the new engine of economic development.
Eonomic growth has brought about challenges, particularly for the long term. Above all, Brazil needs to build up
and modernize its infrastructure.That is the reason why President Dilma Rousseff launched the Energy and Logistics
Investment Program in 2012, consisting of concessions for highways (7,500 km), railways (10,000 km), airports (Rio
de Janeiro and Belo Horizonte) and ports.The implementation of the Program will not only reduce costs and improve
competitiveness for all industries, but also keep Brazil on the sustainable growth path that has been a characteristic
of the Brazilian economy over the last decade.
In oil and gas, the 11th Bidding Round in May 2013 was very successful, and both the 12th Bidding Round and the
1st Round of the Pre-Salt Layer are scheduled for the end of 2013. In electricity, many auctions are being carried out
until2017forthegenerationof33,000MW(fromhydropower,windpowerandothersources)andtheinstallationof
21,000 km of transmission lines.
As far as short term perspectives are concerned, Brazil resumed economic growth in 2013, after a small period of
deceleration due to the deepening of the international crisis. In the second quarter, GDP grew 6.0 percent (quarter-
over-quarter, seasonally adjusted annual rate), one of the highest rates among G20 countries. The sustainability of
the economic recovery is supported by high levels of investment, which increased 9.0 percent in the second quarter
6
Ministry
of Finance
6
Foreword
of 2013 when compared to the second quarter of 2012. Furthermore, manufacturing shows signs of improvement,
after two years of difficulties brought about by the international crisis.
The outlook for the world economy, however, remains tenuous. Although there are signs of economic recovery in
developed countries, with demand picking up in some advanced countries, the turmoil created by the expectation
of tapering in U.S. monetary stimulus severely affected some emerging economies. World trade growth is still
disappointing, posing challenges for economies heavily dependent on foreign markets.
The Brazilian economy is prepared to face the challenges posed by the international economy. In addition to its
considerable size – 200 million people, mostly belonging to the middle social classes –, the domestic market has
beengrowing atanannualrateofover6percent inthelastfiveyears.Brazil’sbanksandfinancialmarketsareamong
the soundest and most dynamic in the world. International reserves of around US$ 370 billion vis-à-vis short term
foreigndebtofUS$40billiongivemonetaryauthoritiesthecapacitytointerveneifnecessary.In2012, foreigndirect
investmentinflowstoBrazilwereUS$65.3billion,thefourthlargestintheworld.Inthefirsthalfof2013,FDIinflows
amounted to US$ 30 billion.
After a decade of consolidation of the domestic market, Brazil is ready for another decade of growth, now supported
by investments, particularly in infrastructure. Private businesses and investors, both domestic and foreign, have the
opportunity to take part in this process.
Economic Outlook
8
Ministry
of Finance
8
EconomicOutlook
GDP, QoQ seasonally adjusted annual rate, in % change, second quarter 2013
The world economy in the second quarter of 2013
Source:InternationalMonetaryFund
(IMF)andBloomberg
Producedby:MinistryofFinance
Above 3%
Below or equal to 3%
Brazil
Chile
Russia
India
China
Indonesia
5.6
South
Korea4.5
Mexico
3.8
Canadá
Japan
United
kingdom
Italy
-1.2
-1.0
2.9
2.3
France
-1.3
-2.9
1.9
Germany
2.9
South Africa
Australia
USA
Canada
1.7
2.5
2.0
6.0
7.0
8.5
Turkey
2.4
Euro
area
1.2
3.0
9
Ministry
of Finance
9
EconomicOutlook
Purchasing Managers Index (PMI), manufacturing, in points
Slow recovery of advanced economies and China
Source:ISM(forUSA)andHSBC/Markit
Producedby:MinistryofFinance
40
42
44
46
48
50
52
54
56
58
60
Sep
2013
Jan
2013
Jul2012
Jan
2012
Jul2011
Jan
2011
Jul2010
Jan
2010
Aug
2009
USA
Euro Zone
China
51.2
51.1
55.7
10
Ministry
of Finance
10
EconomicOutlook
10-Year U.S.Treasury yields, in % per annum
Uncertainty about the tapering of the FED monetary stimulus may trigger exchange-rate and financial volatility in
emerging countries.
United States recovery: a double-edged sword
Source:Bloomberg
Producedby:MinistryofFinance
2.69
1.0
1.5
2.0
2.5
3.0
3.5
4.0
18
Sep
2013
Jan
2013
Jan
2012
Jan
2011
11
Ministry
of Finance
11
EconomicOutlook
Nominal exchange rate, in U.S. dollar/national currency, index (January 2007 = 100)
The long term appreciation of the Brazilian real has been partially reversed in 2013
Source:Bloomberg
Producedby:MinistryofFinance
60
90
120
150
17
Sep
2013
Jan
2013
Jan
2012
Jan
2011
Jan
2010
Jan
2009
Jan
2008
Jan
2007
94.1
69.7
70.8
72.9
85.8
Brazil
South
Africa
Mexico
India
Turkey
12
Ministry
of Finance
12
EconomicOutlook
In US$ million
Volatility did not affect the capital account of the balance of payments
*CentralBankofBrazilestimate
Source:CentralBankofBrazil
Producedby:MinistryofFinance
2012 2013 2013
July Jan-July July Jan-July Estimate*
Current Account -3,746 -28,990 -9,018 -52,472 -75,000
Financial Account 8,307 53,580 9,315 58,902 83,000
Direct Investment (net) 7,509 42,240 4,019 41,259
FDI 8,440 38,169 5,212 35,239 65,000
Portfolio Investment 1,343 3,707 3,898 17,981
Other Investments -588 7,537 1,418 -437
13
Ministry
of Finance
13
EconomicOutlook
Foreign direct investment in G-20 countries, 2012, in US$ billion
Confidence: high inflows of foreign direct investment
Source:UNCTAD
Producedby:MinistryofFinance
0
50
100
150
200
Japan
South
Africa
Germ
any
Italy
Korea
Saudi
Arabia
Turkey
M
exico
Indonesia
France
India
Canada
Russian
Federation
Australia
United
Kingdom
Brazil
China
United
States167.6
121.1
65.3
62.4
57.0
51.4
45.4
25.5
25.1
19.9
12.7
12.4
12.2
9.9
9.6
6.6
4.6
1.7
14
Ministry
of Finance
14
EconomicOutlook
Public sector net debt and General government gross debt, in % of GDP
Public sector net debt drops consistently and stable gross debt
*July2013
Source:CentralBankofBrazil
Producedby:MinistryofFinance
30
35
40
45
50
55
60
65
2013*
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002
60.4
54.8
50.6
48.4
47.3
45.5
38.5
42.1
39.2
36.4
35.2
34.1
Public Sector
Net Debt
General
Government
Gross Debt
56.4
58.0 57.4
60.9
54.2
58.7 59.4
53.4
15
Ministry
of Finance
15
EconomicOutlook
International reserves, in US$ billion (July 2013)
Brazil’s international reserves in a comfortable situation
*June2013
**May2013
***January2013
Source:Bloomberg
Producedby:MinistryofFinance
0
300
600
900
1,200
3,500
Italy
**
South
Africa
Australia
**
France
**
United
Kingdom
*
Germ
any
**
Indonesia
Turkey
Canada
M
exico
India
Korea
Brazil
Russia
***
SaudiArabia
**
Japan
China
*
252
168
106
104
93
72
62
56
46
39
36
480
3,497
1,188
685
374
330
16
Ministry
of Finance
16
EconomicOutlook
Reserves-to-imports of goods ratio, in %, July 2013
Brazil’s international reserves 58% above annual imports
*August2013
**June2013
Source:Bloomberg
Producedby:MinistryofFinance
0
50
100
150
200
Turkey
SouthAfrica
M
exico
Indonesia
India
Russia
**
Brazil*
China
**185%
158%
150%
56%
49%
44%
43%
42%
17
Ministry
of Finance
17
EconomicOutlook
Reserves-to-short term external debt ratio, in %, March 2013
Brazil’s international reserves much above external debt levels
Source:BloombergandInternational
MonetaryFund(IMF)
Producedby:MinistryofFinance
0
200
400
600
800
1,000
Turkey
Argentina
South
Africa
M
exico
Indonesia
India
China
Russia
Brazil
952% 572% 462% 303% 232% 229% 167% 108% 92%
18
Ministry
of Finance
18
EconomicOutlook
International reserves, in US$ billion
Brazil’s international reserves have not been changed even under international uncertainty
Source:CentralBankofBrazil
Producedby:MinistryofFinance
300
325
350
375
400
12
Sep
2013
Aug
2013
Jul2013
Jun
2013
M
ay
2013
Apr2013
M
ar2013
Feb
2013
Jan
2013
US$ 373.6 bn
19
Ministry
of Finance
19
EconomicOutlook
In billions of U.S. dollars and millions of contracts
The role of derivatives in Brazil: second largest market for interest-rate options and futures
*ForBrazil,indicatorsonlyinclude
futuresandoptionsoperations
** InChina,currencyderivativesarenot
traded(FXrestriction)
***TurkdexAnnualMarket
Statistics(AnnualFactBook2012)
Source:WorldFederationofExchanges
Producedby:MinistryofFinance
0
5,000
10,000
15,000
20,000
25,000
30,000
Turkey***
South
Africa
Russia
M
exico
Brazil*
25,212
241 58 38 0
Financial volume
traded in 2012
(US$ billion)
Number of
contracts traded
in 2012 (millions)
Brazil / BVMF* 25,212 501
Mexico /Mexder 241 31
Russia / Moscow Ex 58 21
South Africa / JSE 38 3
Singapore / SGX 0 1
India / NSE-BSE-MCX 0 0
Malaysia / Bursa Malaysia 0 0
China** 0 0
Turkey*** 0 0
US$ Billion
20
Ministry
of Finance
20
EconomicOutlook
In billions of U.S. dollars and millions of contracts
Sixth largest market for currency options and futures
*ForBrazil,indicatorsonlyinclude
futuresandoptionsoperations
** InChina,currencyderivatives
arenottraded(FXrestriction)
***TurkdexAnnualMarket
Statistics(AnnualFactBook2012)
Source:WorldFederationofExchanges
/FuturesIndustryAssociationMagazine
March2013
Producedby:MinistryofFinance
0
1,000
2,000
3,000
4,000
5,000
Turkey
***
South
Africa
M
éxico
Russia
India
Brazil*4,525
821
437
100
15
13
US$ BillionCurrency Options and Futures
Country
Financial volume
traded in 2012
(US$ billion)
Number of contracts (in millions)
traded in the same basis
(if contracts were all of USD 1,000)
Brazil / BVMF* 4,525 4,727
India / NSE-BSE-MCX 821 868
Russia / Moscow Ex 437 413
South Africa / JSE 15 17
Mexico /Mexder 100 98
Turkey /Turkdex *** 13 1
Malaysia / Bursa
Malaysia
0 -
China ** 0 -
Singapore / SGX 0 -
21
Ministry
of Finance
21
EconomicOutlook
Foreign exchange derivative transactions over spot transactions, in %
In Brazil, the large market for foreign exchange derivatives
stimulates companies to use currency hedging
Source:BankforInternational
Settlements(BIS)
Producedby:MinistryofFinance
0
50
100
150
200
250
300
350
400
450
Japan
Russia
Australia
Euro
M
exico
Canada
Global
United
States
United
Kingdom
South
Africa
Korea
India
China
Turkey
Brazil419%
347%
252%
247%
231%
207%
178%
175%
161%
161%
138%
137%
136%
134%
101%
22
Ministry
of Finance
22
EconomicOutlook
Current account, in % of GDP, second quarter of 2013
G20 emerging markets external sector
*Firstquarter2013
**Excludingtheoilaccount,the
Braziliancurrentaccountdeficitwould
be1.9%ofGDP.Therewasatemporary
delayintheregisterofthe2012
importsandtherewereseveralstops
formaintenanceinPetrobrasplatforms.
Additionally,delaysinthestartofnew
producingsystemsinthelastfewyears
andexistingproblemsinthepost-salt
systemsresultedinaslowdowninthe
domesticextractionofoilandgassince
2010.Allthesefactorsthatinterfered
intheBraziliantradebalancewillstart
toimprovesignificantlyinthesecond
halfof2013.Tennewplatformswillbe
startingoperationsin2013/2014,and
severalotherswillstartoperationsin
thefollowingyears,doublingproduction
until2020,accordingtoEIAestimate
Source:Bloomberg
Producedby:MinistryofFinance
-7
-6
-5
-4
-3
-2
-1
0
1
2
3
4
-5.9
Turkey*
South
Africa*
India*
Indonesia
Brazil
M
exico
China
Russia*
3.0 2.4
-1.3
-3.2
-3.3
-5.1 -5.8 -5.9
-1.9**
23
Ministry
of Finance
23
EconomicOutlook
Trade balance, total and ex-oil, in US$ billion
Oil and gasoline accounted for a large part of the decrease in trade surplus
*Ona12-monthbasisuptoJuly2013
Source:MinistryofDevelopment,
IndustryandTrade(MDIC)
Producedby:MinistryofFinance
0
10
20
30
40
2013*
2012
2011
2010
2009
12.5 19.5 26.2 26.0 19.325.3 20.2 29.8 19.4
4.5
Total balance
ex-oil and other
oil products
Total
balance
24
Ministry
of Finance
24
EconomicOutlook
Gross fixed capital formation, seasonally adjusted, in % QoQ
Despite difficulties, investments are recovering in Brazil
Source:BrazilianInstituteofGeography
andStatistics(IBGE)
Producedby:MinistryofFinance
-2
-1
0
1
2
3
4
5
2Q 20131Q 20134Q 20123Q 2012
1.5 4.7 3.6
-1.4
25
Ministry
of Finance
25
EconomicOutlook
Broad Consumer Price Index (IPCA), in %YoY
Inflation within the target range since 2004
*Averageforecastfor2013,according
totheCentralBankofBrazilmarket
researchonSeptember6,2013
Source:BrazilianInstituteofGeography
andStatistics(IBGE)andCentralBank
ofBrazil
Producedby:MinistryofFinance
2013*
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002
2001
2000
1999
Upper
Bound
Lower
Bound
Target
core
IPCA
5.85.86.55.94.35.94.55.77.69.312.57.76.08.9 3.1
26
Ministry
of Finance
26
EconomicOutlook
Consumer price index, in %YoY, August 2013
G20 emerging markets inflation
*July2013
**June2013
Source:Bloomberg
Producedby:MinistryofFinance
0
2
4
6
8
10
12
India
**
Indonesia
Turkey
Russia
South
Africa
*
Brazil
M
exico
China2.5
3.5
6.1
6.4
6.5
8.2
8.8
10.7
27
Ministry
of Finance
27
EconomicOutlook
In %, latest available data
Sound financial system
Source:InternationalMonetaryFund
(IMF)-FiscalSoundnessIndicators
Producedby:MinistryofFinanceSpain
Australia
India
Italy
Russia
Japan
South Korea
France
USA
United Kingdom
South Africa
Canada
Mexico
Brazil
Turkey
Germany
Italy
Spain
South Africa
Japan
France
United Kingdom
Australia
USA
India
Russia
Canada
Turkey
South Korea
Chile
Argentina
Mexico
Brazil
India
South Africa
United Kingdom
Australia
Mexico
Japan
Canada
Turkey
USA
Italy
Russia
South Korea
Germany
Brazil
Basel Index (Capital Adequacy)
(Provisions minus
Delinquencies)/Capital
Net Assets/
Short-term Liabilities
17.9
17.4
17.0
16.3
16.1
15.7
15.7
14.4
14.3
14.3
14.2
13.4
13.3
13.1
11.8
11.4
-3.1
-3.1
-5.9
-9.9
-12.1
-14.7
-15.5
-16.1
-19.4
-21.4
-23.6
-27.6
-73.7
10.0
9.0
2.8
0.6
183.1
140.8
111.3
87.6
80.1
77.4
76.4
56.3
51.3
47.3
43.5
38.0
33.0
27.0
28
Ministry
of Finance
28
EconomicOutlook
Real estate loans, annual growth rate, in %
Real estate loans have still huge opportunities of expansion in Brazil
Source:CentralBankofBrazil
Producedby:MinistryofFinance
0
10
20
30
40
50
60
70
Jul2013
Jan
2013
Jul2012
Jan
2012
Jul2011
Jan
2011
Jul2010
Jan
2010
Jul2009
Jan
2009
Jul2008
M
ar2008
34.0
Despite their growth, in July 2013 real
estate loans represented only 7.7% of
Brazil’s GDP, a much lower rate than in
developed countries and most
emerging economies
29
Ministry
of Finance
29
EconomicOutlook
Budget balance, in % of GDP
Brazil presents sound fiscal accounts
*IMFestimates
Source:InternationalMonetaryFund
(IMF)-FiscalMonitorand
CentralBankofBrazil
Producedby:MinistryofFinance
Primary Results Nominal Result
United States
Asia
Euro Zone
Latin America
Brazil
2006-2008
2010-2013*
United States
Asia
Euro Zone
Latin America
Brazil 2.6
1.3
-1.5
-1.5
-7.1
3.3
3.0
1.2
0.0
-1.9
-2.5
-2.3
-4.2
-3.0
-9.0
-2.8
-1.1
-1.4
-1.6
-3.8
2006-2008
2010-2013*
30
Ministry
of Finance
30
EconomicOutlook
10-year Brazilian Global bonds* and U.S.Treasury yields, in % per annum
Confidence: low spreads for sovereign bonds
*Yieldsatissuedate
Source:NationalTreasurySecretariat
(STN)
Producedby:MinistryofFinance
0.0
1.4
2.8
4.2
5.6
7.0
9
M
ay
2013
5
Sep
2012
3
Jan
2012
7
Jul2011
27
Jul2010
15
Apr2010
15
Dez2009
7
M
ay
2009
6
Jan
2009
U.S. Treasuries
Brazilian
sovereign bonds
6.1
5.8
4.8 5.0
4.5 4.2
3.4
2.7 2.82.4
3.3
3.6
3.9
3.0 3.1
1.9
1.6 1.8
31
Ministry
of Finance
31
EconomicOutlook
Non-resident share in federal public debt, in % of total DFPD*
Increasing number of non-resident investors in Brazilian public debt
*DomesticFederalPublicDebt
Source:NationalTreasurySecretariat
(STN)
Producedby:MinistryofFinance
0
2
4
6
8
10
12
14
16
18
1.8
2.0
2.1
2.7
4.5
4.7
4.9
5.2
5.0
5.1
5.3
5.5
5.9
6.2
6.3
6.4
7.6
7.7
7.5
6.7
6.8
7.2
7.1
6.9
6.6
6.4
6.5
6.7
6.6
6.9
7.8
8.4
8.4
8.8
9.7
9.8
10.2
9.9
10.0
10.6
10.6
11.2
11.5
11.5
11.3
11.4
11.8
11.4
11.4
11.3
11.5
11.1
11.6
11.8
11.3
11.4
11.4
11.3
11.9
11.9
12.1
12.3
12.3
12.2
13.2
13.3
13.4
13.8
13.9
13.7
14.4
14.3
14.8
14.6
14.4
14.5
15.5
Jul2013
M
ar2013
Nov
2012
Jul2012
M
ar2012
Nov
2011
Jul2011
M
ar2011
Nov
2010
Jul2010
M
ar2010
Nov
2009
Jul2009
M
ar2009
Nov
2008
Jul2008
M
ar2008
Nov
2007
Jul2007
M
ar2007
15.5
Economic Development
and Demand for
Infrastructure
34
Ministry
of Finance
EconomicDevelopmentand
DemandforInfrastructure
Broad retail sales, seasonally adjusted, in %YoY
Domestic market: dynamism of retail sales
*Ona12-monthbasisuptoJuly2013
Source:BrazilianInstituteofGeography
andStatistics(IBGE)
Producedby:MinistryofFinance
0
3
6
9
12
15
2013*
2012
2011
2010
2009
2008
2007
2006
2005
200411.1
3.1
6.4
13.6
9.9
6.8
12.2
6.6
8.0
5.8
35
Ministry
of Finance
EconomicDevelopmentand
DemandforInfrastructure
New formal jobs, in millions
Sustainable labor market ensures dynamic domestic demand
For2012and2013,updatesafterthe
officialreleasedateweretakeninto
consideration
*JanuarytoJuly2013
Source:MinistryofLaborand
Employment
Producedby:MinistryofFinance
0.0
0.5
1.0
1.5
2.0
2.5
3.0
2013*
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002
2001
2000
1999
1998
1997
1996
1995
0.1 0.1 0.3 0.4 0.5 1.2 1.0 1.5 0.9 1.9 1.8 1.9 2.5 1.8 1.8 2.9 2.2 1.3 0.9
19.90 million jobs
36
Ministry
of Finance
EconomicDevelopmentand
DemandforInfrastructure
Airline traffic, in millions of passengers
Increasing demand for infrastructure services: airline passengers
Source:NationalAgencyforCivil
Aviation(ANAC)
Producedby:MinistryofFinance
0
20
40
60
80
100
120
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002
2001
2000
101.4
92.6
77.2
62.8
56.0
52.1
47.7
44.1
35.7
33.4
35.9
36.0
34.0
2002-2012: 182.3% growth
37
Ministry
of Finance
EconomicDevelopmentand
DemandforInfrastructure
Brazilian trade flow (exports plus imports), in US$ billion
Growing external trade
*Ona12-monthbasis
uptoAugust2013
Source:MinistryofDevelopment,
IndustryandForeignTrade(MDIC)
Producedby:MinistryofFinance
0
100
200
300
400
500
2013*
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002
2001
2000
1999
1998
1997
1996
199596.4
101.0
112.7
108.8
97.2
111.0
113.9
107.7
121.5
159.5
192.1
229.2
281.3
370.9
280.7
383.7
482.3
465.7
474.7
2002-2012: 332.4% growth
38
Ministry
of Finance
EconomicDevelopmentand
DemandforInfrastructure
Total cargo handling in ports, in millions of tons
Significant growth in port trade volume
*Ona12-monthbasisuptoMarch2013
Source:NationalAgencyforWater
Transportation(ANTAQ)
Producedby:MinistryofFinance
500
550
600
650
700
750
800
850
900
950
2013*
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
570.8
620.7
649.4
692.8
754.7
768.3
732.9
833.9
885.6
904.0
902.9
2003-2012: 58.4% growth
39
Ministry
of Finance
EconomicDevelopmentand
DemandforInfrastructure
In thousand vehicles per km per year, on highways under concession
Vehicular traffic
*Estimatebasedonmonthly
averageuptoAugust2013
Source:BrazilianAssociationof
HighwayConcessionaires(ABCR)
Producedby:MinistryofFinance
0
20
40
60
80
100
120
2013*
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002
2001
2000
111
105
99
89
69
60
69
67
65
61
56
57
51
43
2002-2012: 86.6% growth
40
Ministry
of Finance
EconomicDevelopmentand
DemandforInfrastructure
New vehicles (buses, trucks, light commercial vehicles and cars), in million of vehicles
Vehicle sales more than doubled in ten years
*Ona12-monthbasis
uptoAugust2013
Source:BrazilianAssociationof
AutomotiveVehicleManufacturers
(ANFAVEA)
Producedby:MinistryofFinance
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
2013*
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002
4th
largest vehicle
market in the world
1.5
1.4
1.5
1.7
1.9
2.5
2.8
3.1
3.5
3.6
3.8
3.8
2002-2012: 153.5% growth
41
Ministry
of Finance
EconomicDevelopmentand
DemandforInfrastructure
Revenue tonne kilometers (RTKs), in billions
Railroad volumes
Source:NationalTransportation
Agency (ANTT)
Producedby:MinistryofFinance
130
164
198
232
266
300
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002168
182
203
221
232
258
271
244
278
291
298
2002-2012: 77.4% growth
42
Ministry
of Finance
EconomicDevelopmentand
DemandforInfrastructure
Brazilian grain harvest*, in millions of tons
Brazilian harvest in record figures
*Preliminarydata:subjecttochangeby
Conab/MAPA
**ConabestimatesinSeptember2013
Source:MinistryofAgriculture,
LivestockandFoodSupply(MAPA)
Producedby:MinistryofFinance
70
90
110
130
150
170
190
210
2012/2013**
2011/2012
2010/2011
2009/2010
2008/2009
2007/2008
2006/2007
2005/2006
2004/2005
2003/2004
2002/2003
2001/2002
2000/2001
100.3
96.8
123.2
119.1
114.7
122.5
131.8
144.1
135.1
149.3
162.8
166.2
187.1
43
Ministry
of Finance
EconomicDevelopmentand
DemandforInfrastructure
Brazil in the global ranking, by production and exports quantities, 2011
Agricultural leadership
Source:FoodandAgriculture
Organisation(FAO)
Producedby:MinistryofFinance
Orange Juice
Tobacco
Chicken
Whitesugar
Corn
Beans
Soybean
Processed beef
Coffee 1 1
1 1
1 1
1
1
1
2
2
2
2 2
2
3 3
16
Producer Exporter
Capital Market
Instruments
46
Ministry
of Finance
CapitalMarketInstruments
Howcannon-residentinvestorsnegotiatedebt securitiesandfundsinBrazil?
CMNResolution2,689ofyear2000,whichrulesoninvestmentsbynon-residentinvestorsin
thefinancialandcapitalmarketsofinvestment,providesallnecessaryinformation
Brazildoesnotimposetaxes
ontheinternationalremittanceofprofitsanddividends Producedby:MinistryofFinanceand
BrazilianDevelopmentBank(BNDES)
FinancialInstrumentsforInfrastructureInvestments
https://www3.bcb.gov.br/normativo/
detalharNormativo.do?method=deta
lharNormativo&N=100014927
• More Info:
CMNResolution2,689
47
Ministry
of Finance
CapitalMarketInstruments
FinancialInstrumentsforInfrastructureInvestments
Definition Benefitsfor
non-residentinvestors* Minimum Requirements
Investment Debentures and
Real Estate Receivables Certificates
• ZeroIncomeTaxRate(IR)
• ZeroTaxonFinancialOperations(IOF)
• Weightedaveragematurity:overfouryears.
• Return:CRIpaysinterestatafixedrateoratafloatingrate
peggedtoaninflationindexortheReferenceRate(TR).Totalor
partialuseofpost-fixedrateofinterestareforbidden.
• Norepurchase:bytheissuerorrelatedpartyinthefirsttwo
yearsafterissuanceandearlyliquidation,exceptincasestobe
regulatedbyBrazil’sNationalMonetaryCouncil(CMN).
• Requiredevidencedocuments: securityshouldbe
registeredwithclearinghousesdulyauthorizedbythe
CentralBankofBrazilortheBrazilianSecuritiesandExchange
Commission(CVM).
• Simplifiedprocedure:todemonstratethepurposeof
allocatingresourcesintothefuturepaymentorreimbursement
ofexpenses,costsorliabilitiesrelatedtoinvestmentprojects,
includingthoseaimedatR&D&I(research,developmentand
innovation).
• Noresalecommitment:undertakenbythebuyer.
• Yieldpaymentfrequency:ifany,itmustbeatleast180
daysapart.
• Debêntures de Investimento e Certificados de Recebíveis Imobiliários (CRI)
*Incaseofinvestmentsfromcountries
whicharenotsubjecttoa20%(orhigher)
incometaxrate(“taxhavens”),theabove
mentionedtaxbenefitsdonotapply,
unlessitisrelatedtoawealthfund
Producedby:MinistryofFinanceand
BrazilianDevelopmentBank(BNDES)
48
Ministry
of Finance
CapitalMarketInstruments
Definition Benefitsfornon-
-residentinvestors* Minimum Requirements
InvestmentFundin
CreditRights
• ZeroIncomeTaxRate(IR)
• ZeroTaxonFinancial
Operations(IOF)
• Termofduration:minimumofsixyears.
• Nopayment,fullyorpartially:ofprincipaloftheFund’squotasinthefirsttwoyearsfromthe
closingdateofthepublicofferingofthequotadistributionthatconstitutetheinitialassetsofthe
Fund,exceptincasesoftheFund’searlyliquidationmentionedintheFund’sregulation.
• Noacquisitionofquotas:bythesellerorbytheissuerorbyanypartiesrelatedtothem,except
incaseofsubordinatedquotasforpurposesofamortizationandwithdrawal.
• Amortizationplanofquotas:includingthosefromincorporatedyields,ifany,mustbeatleast
180(onehundredandeighty)daysapart.
• Requiredevidencedocuments:quotasmustbeadmittedtotradingonanorganizedsecurities
marketorregisteredwitharegistrysystemdulyauthorizedbytheCentralBankofBrazilorthe
BrazilianSecuritiesandExchangeCommission(CVM)undertheirrespectivejurisdiction.
• Simplifiedprocedure:todemonstratethepurposeofallocatingresourcesintoatransactionof
investmentprojects,includingthoseaimedatR&D&I.
• Mandatorypresenceofthefollowing:intheassignmentagreement,regulationandprospec-
tus,ifany,inamannertobedeterminedbyCVM:
•Goaloftheprojectorthebeneficiaryprojects;
•Estimatedbeginningandendperiodsor,forongoingprojects,descriptionofthecurrentstage
andestimatedendperiod;
•Estimatedvolumeoffinancialresourcesrequiredtocarryouttheprojectornotinitialized
projectsorforthecompletionofongoingprojects;
•Estimatedpercentageoffundstoberaisedwiththesellingofthecreditrightscomparedto
thefinancialresourcerequirementsofthebeneficiaryprojects.
• Fund’sequity:consistsofatleast85%(eighty-five)percentofcreditrightsand,fortheremaining
portion,offederalgovernmentsecurities,repurchaseagreementsbackedbygovernmentbondsor
mutualfundquotasthatinvestinfederalgovernmentbonds.
FinancialInstrumentsforInfrastructureInvestments
• Fundos de Investimento em Direitos Creditórios (FIDC)
*Incaseofinvestmentsfromcountries
whicharenotsubjecttoa20%(or
higher)incometaxrate(“taxhavens”),
theabovementionedtaxbenefitsdonot
apply,unlessitisrelatedtoawealthfund
Producedby:MinistryofFinanceand
BrazilianDevelopmentBank(BNDES)
49
Ministry
of Finance
CapitalMarketInstruments
Definition Benefitsfornon-
-residentinvestors* Minimum Requirements
Infrastructure
Debentures
• ZeroIncomeTaxRate(IR)
• ZeroTaxonFinancial
Operations(IOF)
• Issuance: must be between January 2011 and December 2015.
• Weighted average maturity: over four years.
• Return: Debentures pay interest at a fixed rate or at a floating rate pegged to an inflation index or the
Reference Rate (TR).Total or partial use of post-fixed rate of interest are forbidden.
• No repurchase: by the issuer or related party in the first two years after issuance and early liquidation,
except in cases to be regulated by Brazil’s National Monetary Council (CMN).
• Required evidence documents: security should be registered with clearing houses duly authorized
by the Central Bank of Brazil or the Brazilian Securities and Exchange Commission (CVM).
• Simplifiedprocedure:todemonstratethepurposeofallocatingresourcesintothefuturepaymentorreimburse-
mentofexpenses,costsorliabilitiesrelatedtoinvestmentprojects,includingthoseaimedatR&D&I.
• No resale commitment: undertaken by the buyer.
• Yield payment frequency: if any, it must be at least 180 days apart.
Projects Approval:
• Priority investment projects: to be implemented in the infrastructure area, or intensive economic
production in research, development, and innovation. Also, according to the Decree n. 7,603 of year 2011,
projects should have:
• Approval Ordinance: issued and approved by the Ministry responsible for that sector
• Focus on deployment, expansion, maintenance, recovery, adaptation or modernization processes in
the following sectors:
• Specific Purpose Companies (SPE): for management and implementation.
• Issuer: dealer or grantee or authorized contractors or lessee.
•Logisticsandtransportation •Broadcasting
•Urbanmobility •Basicsanitationand
•Energy 	 •Irrigation
•Telecommunications
FinancialInstrumentsforInfrastructureInvestments
• Debêntures de Infraestrutura
*Incaseofinvestmentsfrom
countrieswhicharenotsubject
toa20%(orhigher)incometax
rate(“taxhavens”),theabove
mentionedtaxbenefitsdonotapply,
unlessitisrelatedtoawealthfund
Producedby:MinistryofFinanceand
BrazilianDevelopmentBank(BNDES)
50
Ministry
of Finance
CapitalMarketInstruments
Definition Benefitsfor
non-residentinvestors* Minimum Requirements
Brazilian Infrastructure
Bonds Investment Funds
• ZeroIncomeTaxRate(IR)
• ZeroTaxonFinancialOperations(IOF)
• Concentrationininvestments:mustholdatleast67%(sixty-
-seven)percentoftheFund’snetworthwithinthefirsttwoyears
and85%(eighty-five)percentintheremainingyears.
• FundofFunds(FIC)investments:mustholdatleast95%
(ninety-five)percentofFICnetworthintheInfrastructureBonds
InvestmentFund’squota.
FinancialInstrumentsforInfrastructureInvestments
• Fundos de Debêntures Incentivados
Producedby:MinistryofFinanceand
BrazilianDevelopmentBank(BNDES)
51
Ministry
of Finance
CapitalMarketInstruments
Producedby:MinistryofFinanceand
BrazilianDevelopmentBank(BNDES)
FinancialInstrumentsforInfrastructureInvestments
http://www.bcb.gov.br/pre/normati-
vos/res/2011/pdf/res_3947_v1_O.
pdf
Decree 7,632/11
http://www.planalto.gov.br/
ccivil_03/_Ato2011-2014/2011/
Decreto/D7632.htm
http://www.planalto.gov.br/
ccivil_03/_Ato2011-2014/2011/Lei/
L12431.htm
http://www.planalto.gov.br/
ccivil_03/_Ato2011-2014/2012/Lei/
L12715.htm#art71
http://portal.anbima.com.br/Pages/
home.aspx
• More Info (useful links):
Law12,431ofyear2011
Law12,715ofyear2012
BrazilianFinancialand
CapitalMarketsAssociation
CMNResolution3,974of
year2011
Decree7,632ofyear2011
Highways
54
Ministry
of Finance
Highways
Highway Concessions
Highways
Updatedinformationavailableat
www.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
7
2
6
9
5
4
1
3
PA MA
PE
BA
TO
MT
ES
MG
GO
MS
SP
PR
SC
RS
Açailãndia
Sinop
Palmas
Parnamirim
Lucas do Rio Verde
Cuiabá
Recife
Maceió
Aracaju
Salvador
Porto Seguro
Mucurí
Vitória
Campos
Além Paraíba
Divisa Alegre
Mafra
Maracaju
Estrela
D’Oeste
Rio de
Janeiro
Belo
Horizonte
São Paulo
Santos
Campo
Grande
Uruaçu
Brasília
Rio Grande
Juíz de Fora
Anápolis
Goiânia
Feira de Santana
BR-116
BR-050
BR-262
BR-040
BR-153
BR-163
BR-262
BR-060
BR-101
BR-153
BR-163
Belém
2
1
3
5
4
6
8
7
9
BR-116/MG
BR-040/MG-GO-DF
BR-101/BA
BR-262/MG-ES
BR-050/GO-MG
BR-153/GO-TO
BR-163/MT
BR-163/MS
BR-060/153/262/DF-GO-MG
8
55
Ministry
of Finance
Highways
Auction Concluded
on September 18th
Road Concession – BR-050: from Cristalina (GO) (BR-040 entry point) to MG/SP border
Object Demand Criteria
• Section:	BR-050, Entry Point of BR-
040/GO (Cristalina) – Border w/ MG/SP
• Total Length: 426 km
• Length to be widened: 219 km
The project includes widening,
maintenance and operation of the
highway. Other widening projects are
also planned to happen, including the
construction of 9 km of side roads.
Demand Projection (AADT):
2014 (54,232), 2019 (62,790), 2024
(76,046).
Connects Brasilia, the state of São
Paulo and the South Region of the
country, crossing an important
agricultural and wholesale retail
center - the Minas Gerais triangle.
Term: 30 years
Criteria: lowest tariff
Economic and
Financial Modeling
CAPEX*: US$ 1.3 billion
OPEX: US$ 869 million
Financing conditions:
Term: 25 years (Grace period: 5 years)
Rate: TJLP** + 2%a.a.
Real leveraged IRR: up to 16%
per year, in real terms.
Debt to equity ratio: 70% / 30%
Equity support: up to 49% of SPE***
or holding’s share capital
(Institutions: public banks and
pension funds)
Environmental licensing: State-
owned EPL is in charge of obtaining
Previous License (LP) and Installation
License (LI) of duplication works
MT
TO
GO
MS
PR
SP
MG
RJ
ES
BA
BR-153
BR-060
BR-050
São
Paulo
Palmas
Curitiba
Goiânia
Uberaba
Uberlândia
Catalão
Cristalina
Brasília
Highway BR-050 GO/MG
To be awarded
BR-040
Rio de Janeiro
Vitória
*Withoutbenefitsandindirect
expenses
**TJLP-LongTermInterestRate,
currently5%p.a.
***SpecialPurposeEntity
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
Updatedinformationavailableat
www.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
56
Ministry
of Finance
Highways
Road Concession – BR-040: Brasília (DF) – Juiz de Fora (MG)
Object Demand Criteria
• Section: BR-040, Juiz de Fora (MG) – Entry
point of BR-251 (Brasília - DF)
• Total Length: 937 km
• Length to be widened: 715 km
The project includes widening, maintenance
and operation of the highway. Other
widening projects are also planned to
happen, including the construction of side
roads between Luziania and Brasilia.
Demand Projection: under study
Connects two important economic
centers in Brazil - Rio de Janeiro and
Belo Horizonte - to the fourth most
populous city and the highest GDP
per capita in the country - Brasilia.
It is the main route for supply of
coal to steel parks.
ConcessionTerm: 30 years
Number ofToll Plazas: 11
Criteria: lowest tariff
Economic and Financial
Modeling
Financing conditions:
Term: 25 years (Grace period: 5 years)
Rate:TJLP* + 2%a.a.
Real leveraged IRR: up to 16% per
year, in real terms.
Debttoequityratio:upto70%/30%
Equity support: up to 49% of SPE**
or holding’s share capital
(Institutions: public banks and
pension funds)
Environmental licensing: State-
owned EPL is in charge of obtaining
Previous License (LP) and Installation
License (LI) of duplication works
GO
PR
SP
MG
RJ
ES
Brasília
Luziânia
Sete Lagoas Belo Horizonte
Juiz de Fora
BR-381
BR-040
Highway BR-040
MG/GO/DF
To be awardedGranted Section
180 Km
São Paulo
Curitiba
Rio de
Janeiro
*TJLP-LongTermInterestRate,
currently5%p.a.
**SpecialPurposeEntity
Updatedinformationavailableat
www.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
57
Ministry
of Finance
Highways
RoadConcession–BR-116:fromBA/MGborder(DivisaAlegre)toMG/RJborder(AlémParaíba)
Object Demand Criteria
• Section:	BR-116, RJ/MG Border (Além
Paraíba) - MG/BA Border (Divisa Alegre)
• Total Length: 817 km
• Length to be widened: 817 km
The project includes widening, maintenance
and operation of the highway. Other
widening projects are also planned, including
the construction of 27 km of side roads.
Demand Projection: under study
Connects two important economic
centers in Brazil - Rio de Janeiro
and Salvador – across eastern
Minas Gerais.
ConcessionTerm: 30 years
Number ofToll Plazas: 8
Criteria: lowest tariff
Economic and Financial
Modeling
Financing conditions:
Term: 25 years (Grace period: 5 years)
Rate:TJLP* + 2%a.a.
Real leveraged IRR: up to 16% per
year, in real terms.
Debttoequityratio:upto70%/30%
Equity support: up to 49% of SPE**
or holding’s share capital
(Institutions: public banks and
pension funds)
Environmental licensing: State-
owned EPL is in charge of obtaining
Previous License (LP) and Installation
License (LI) of duplication works
GO
SP
MG
RJ
ES
BA
BR-116
São
Paulo Rio de
Janeiro
Divisa Alegre
Teófilo Otoni
Gov. Valadares
Muriaé
Além Paraíba
Salvador
Highway
BR-116 MG
To be awarded
*TJLP-LongTermInterestRate,
currently5%p.a.
**SpecialPurposeEntity
Updatedinformationavailableat
www.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
58
Ministry
of Finance
Highways
Road Concession – BR-101:
from the entry point of BR-324 (BA) to the entry point of the BA-698 (Mucuri)
Object Demand Criteria
• Section:	 BR-101, Entry Point of BA-698
(Mucuri) – Entry Point of. BR-324/BA
• Total Length: 772 km
• Length to be widened: 551.3 km
The project includes widening,
maintenance and operation of the
highway. Other widening projects are
also planned to happen, including the
construction of 67 km of side roads.
Demand Projection (AADT): 2014
(57,392), 2019 (71,312),
2024 (87,140).
ConnectsthesoutherncoastofBahia
tothestatesofEspíritoSantoandRio
deJaneiro.BR-101isaveryimportant
roadconnectingthenortheastwiththe
southeastandsouthernregionsalong
thecoastalline,wherelivesagreat
shareofBrazilianpopulation.Important
portsarealsoconnectedbythisroad.
ConcessionTerm: 30 years
Number ofToll Plazas: 9
Criteria: lowest tariff
Economic and
Financial Modeling
CAPEX*: US$ 2.2 billion
OPEX: US$ 1.3 billion
Financing conditions:
Term: 25 years (Grace period: 5 years)
Rate:TJLP** + 2%a.a.
Real leveraged IRR: up to 16%
per year, in real terms.
Debttoequityratio:upto70%/30%
Equity support: up to 49% of
SPE*** or holding’s share capital
(Institutions: public banks and
pension funds)
Environmental licensing: State-
owned EPL is in charge of obtaining
Previous License (LP) and Installation
License (LI) of duplication works
TO
GO
SP
MG
RJ
ES
BA
Salvador
Rio de
Janeiro
BR-101
BR-116
BR-381
BR-262
Belo
Horizonte
Vitória
MucuríJoão
Monlevade
São
Paulo
Highway BR-101 BA
To be awarded
*Withoutbenefitsandindirect
expenses
**TJLP-LongTermInterestRate,
currently5%p.a.
***SpecialPurposeEntity
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
Updatedinformationavailableat
www.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
59
Ministry
of Finance
Highways
Road Concession – BR-262: from the entry point of BR-381 (J. Monlevade) to the entry
point of BR-101/ES
Object Demand Criteria
• Section:	 BR-262, Entry Point of BR-381
(J. Monlevade) – Entry Point of BR-101/ES
• Total Length: 377 km
• Length to be widened: 196.4 km
The project includes widening, maintenance
and operation of the highway. Other
widening projects are also plannedw,
including the construction of a ringroad and
13 km of side roads.
Demand Projection (AADT):
2014 (7,549), 2019 (9,297),
2024 (11,388)
The state of Minas Gerais (MG)
has the third largest population
in Brazil.This road gives access to
the ports of the state of Espirito
Santo, the main gateway to MG
exports and imports, constituting
an alternative route for the flow of
MG production.
ConcessionTerm: 30 years
Number ofToll Plazas: 5
Criteria: lowest tariff
Economic and
Financial Modeling
CAPEX*: US$ 916 million
OPEX: US$ 739 million
Financing conditions:
Term: 25 years (Grace period: 5 years)
Rate:TJLP** + 2%a.a.
Real leveraged IRR: up to 16%
per year, in real terms.
Debttoequityratio:upto70%/30%
Equity support: up to 49% of SPE***
or holding’s share capital
(Institutions: public banks and
pension funds)
Environmental licensing: State-
owned EPL is in charge of obtaining
Previous License (LP) and Installation
License (LI) of duplication works
TO
GO
SP
MG
RJ
ES
BA
Salvador
Rio de
Janeiro
BR-101
BR-116
BR-381
BR-262
Belo
Horizonte
Vitória
Mucurí
São
Paulo
Highway
BR-262 ES/MG
To be awarded
João
Monlevade
Governador
Valadares
*Withoutbenefitsandindirect
expenses
**TJLP-LongTermInterestRate,
currently5%p.a.
***SpecialPurposeEntity
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
Updatedinformationavailableat
www.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
60
Ministry
of Finance
Highways
RoadConcession–BR-153:fromPalmas(TO)toAnápolis(GO)(BR-060entrypoint)
Object Demand Criteria
• Section:	 BR-153, Anápolis (Entry
Point of BR-060/GO) - Entry Point of
TO-080;TO-080, Entry Point of
BR-060/GO- Palmas
• Total Length: 814 km
• Length to be widened: 769.5 km
The project includes widening,
maintenance and operation of the
highway. Other widening projects
are also planned, including the
construction of 10 km of side roads.
Demand Projection (AADT): 2014
(99,926), 2019 (119,627), 2024 (146,113).
ConnectsPalmas,Goiâniaandthesoutheast
ofthecountry,crossingamajorBrazilian
agriculturalpole.Palmasisthegeographical
centerofthecountry,withthevocation
tobecomeanimportanthub.BR-153is
themainroadtoreachthecityofManaus
fromotherregions,benefitingfromthe
heavytrafficofManausFreeZone,which
concentratesBrazilianelectronicproduction,
amongotherimportantindustries.
ConcessionTerm: 30 years.
Number ofToll Plazas: 11.
Criteria: lowest tariff.
Economic and
Financial Modeling
CAPEX*: US$ 3.0 billion
OPEX: US$ 1.4 billion
Financing conditions:
Term: 25 years (Grace period: 5 years)
Rate:TJLP** + 2%a.a.
Real leveraged IRR: up to 16%
per year, in real terms.
Debt to equity ratio: 70% / 30%
Equity support: up to 49% of
SPE*** or holding’s share capital
(Institutions: public banks and
pension funds)
Environmental licensing: State-
owned EPL is in charge of obtaining
Previous License (LP) and Installation
License (LI) of duplication works
MT
TO
GO
MS
SP
MG
RJ
ES
BA
Palmas
Gurupi
Uruaçu
Anápolis
BR-153
TO-080
BR-060
BR-040
BR-050
BR-262
BR-153
Highway
BR-153 GO/TO
To be awarded
*Withoutbenefitsandindirect
expenses
**TJLP-LongTermInterestRate,
currently5%p.a.
***SpecialPurposeEntity
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
Updatedinformationavailableat
www.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
61
Ministry
of Finance
Highways
Road Concession – BR-060 (DF/GO), BR-153 (GO/MG) and BR-262 (MG)
Object Demand Criteria
• Section:	BR-060, Entry Point of BR-251 (DF) –
Entry Point of BR-153/GO; BR-153, Entry Point of BR-
060/GO – Entry Point of Br-262/MG; BR-262, Entry
Point of BR-153/MG – Entry Point of BR-381 (Betim)
• Total Length: 1,177 km
•Lengthtobewidened:648km
The project includes widening, maintenance and
operation of the highway. Other widening projects
are also planned, including the construction of 27
km of side roads and ringroad in Goiânia.
Demand Projection
(AADT): 2014 (160,374),
2019 (195,551), 2024
(238,453).
Connects Brasília, Goiânia,
Uberaba and Belo Horizonte,
crossing a major Brazilian
agricultural pole.
Term: 30 years.
Number ofToll Plazas: 11.
Criteria: lowest tariff.
Economic and
Financial Modeling
CAPEX*: US$ 3.9 billion
OPEX: US$ 1.8 billion
Financing conditions:
Term: 25 years (Grace period: 5
years)
Rate:TJLP** + 2%a.a.
Real leveraged IRR: up to 16%
per year, in real terms.
Debttoequityratio:upto70%/30%
Equity support: up to 49% of
SPE*** or holding’s share capital
(Institutions: public banks and
pension funds)
Environmental licensing: State-
owned EPL is in charge of obtaining
Previous License (LP) and Installation
License (LI) of duplication works
MT
TO
GO
MS
SP
MG
RJ
ES
BA
Palmas
Gurupi
Uruaçu
Anápolis
BR-153
TO-080
BR-060
BR-040
BR-050
BR-262
BR-153
Highway BR-060/153/262
DF/GO/TO
To be awarded
*Withoutbenefitsandindirect
expenses
**TJLP-LongTermInterestRate,
currently5%p.a.
***SpecialPurposeEntity
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
Updatedinformationavailableat
www.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
62
Ministry
of Finance
Highways
Road Concession – BR-163: from MT/MS border to MS/PR border
Object Demand Criteria
• Section:	 BR-163, Border MT/MS – Border
w/ MS/PR
• Total Length: 847 km
• Length to be widened: 807 km
The project includes widening, maintenance
and operation of the highway. Other
widening projects are also planned.
Demand Projection: under study
Connects Cuiabá, Campo Grande
and the Southeast/South Regions
of Brazil, constituting an alternative
route for the flow of Brazilian
agricultural production.
Term: 30 years.
Criteria: lowest tariff.
Economic and
Financial Modeling
CAPEX*: US$ 2.8 billion
OPEX: US$ 1.3 billion
Financing conditions:
Term: 25 years (Grace period: 5 years)
Rate:TJLP** + 2%a.a.
Real leveraged IRR: up to 16%
per year, in real terms.
Debttoequityratio:upto70%/30%
Equity support: up to 49% of SPE***
or holding’s share capital
(Institutions: public banks and
pension funds)
Environmental licensing: State-
owned EPL is in charge of obtaining
Previous License (LP) and Installation
License (LI) of duplication works
MT
TO
GO
MS
PR
SP
MG
RJ
ES
BA
Curitiba
Cuiabá
Campo Grande
Nova Alvorada
Dourados
BR-163
BR-364
BR-262
BR-267
Highway BR-163
/267/262 MS
BR-163
To be awarded
*Withoutbenefitsandindirect
expenses
**TJLP-LongTermInterestRate,
currently5%p.a.
***SpecialPurposeEntity
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
Updatedinformationavailableat
www.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
63
Ministry
of Finance
Highways
Road Concession – BR-163: from Sinop (MT) to MT/MS border
Object Demand Criteria
• Section: BR-163, Sinop – Border MT/MS
• Total Length: 851 km
• Length to be widened: 453 km
The project includes widening, maintenance
and operation of the highway. Other
widening projects are also planned, including
20 km of ringroad (in 5 different cities) and
44 km of side roads.
Demand Projection (AADT):
2014 (5,815), 2019 (7,140), 2024
(8,757)
Connects Sinop, Cuiabá, Campo
Grande and the North/Southeast/
South Regions of Brazil, crossing
an important Brazilian agricultural
production.
Term: 30 years
Number ofToll Plazas: 9
Criteria: lowest tariff
Economic and
Financial Modeling
CAPEX*: US$ 2.7 billion
OPEX: US$ 1.4 billion
Financing conditions:
Term: 25 years (Grace period: 5 years)
Rate:TJLP** + 2%a.a.
Real leveraged IRR: up to 16%
per year, in real terms
Debttoequityratio:upto70%/30%
Equity support: up to 49% of SPE***
or holding’s share capital
(Institutions: public banks and
pension funds)
Environmental licensing: State-
owned EPL is in charge of obtaining
Previous License (LP) and Installation
License (LI) of duplication works
MT
TO
GO
MS
PR
SP
MG
RJ
ES
BA
Goiânia
Curitiba
Cuiabá
Campo Grande
BR-163
BR-364
BR-262
BR-267
Posto Gil
Rondonópolis
Sinop
BR-163
Highway BR-163 MT
To be awarded
*Withoutbenefitsandindirect
expenses
**TJLP-LongTermInterestRate,
currently5%p.a.
***SpecialPurposeEntity
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
Updatedinformationavailableat
www.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
Railways
66
Ministry
of Finance
Railways
Railway Network
Exploited rail network
PIL - Rail Network
(11,000 km) – to be awarded
StructuringWaterways
PAC – Rail network
New railways – Studies
underway
Updatedinformationavailableat
www.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
Pacific
Link
Pacific
Link
Santarém
Manaus
Porto Velho
Belém /
V. Conde
Rio Grande
Santos
Itaguaí
Rio de Janeiro
Vitória
Ilhéus
Salvador
Suape
Pecém
Itaqui
Aratu
S F. Sul
Paranaguá
Itajaí / Navegantes
Estrela
d’Oeste
Figueirópolis
Estreito
Lucas do Rio
Verde Uruaçu
Belo Horizonte
Eliseu
Martins
Barreiras
Rondonópolis
Açailândia
Salgueiro
Parnamirim
Maracaju
67
Ministry
of Finance
Railways
Railway Concession: São Paulo rail beltway (“Ferroanel”) and access to Santos seaport
Object Demand Concession characteristics Financing Conditions
The North Ferroanel will
surround the metropolitan
region of São Paulo,
connecting Santos to Jundiaí.
It will increase the rail cargo
capacity and alleviate the
traffic in the city.
Section:
Jundiaí-Manuel Feio; Riberão
Pires-Evangelista de Souza;
access to Santos Seaport
Allows offsetting the transportation of
cargo and passengers from other means of
transporation in the São Paulo Metropolitan
Region and optimizes railway access to Santos
Seaport.
Build, operate and transfer
Railinfrastructurebuilderand
manager:Concessionforrailway
exploitation,comprising:construction,
maintenance,signalingandcomunications
systems,andtrafficcontrol.
ConcessionTerm: 35 years
Construction to be completed up to the
5th year of the concession term.
RiskMitigation:DemandRisk
(Guaranteedpurchaseof100%ofrailway
operationalcapacityavailability);Socio-
environmentalandExpropriationRisks
(EnvironmentalandExpropriationcostsand
chargeslimitedtovaluespre-establishedin
concessioncontracts).
Environmental licensing: State-owned
EPL is responsible for obtaining Previous
License (LP) and will give support for
obtaining the Installation Licence (LI) of
construction works.
Term: 30 years
(Grace period: 5 years)
Rate:TJLP* + 1%a.a.
Real leveraged IRR:
up to 16% per year, in real terms.
Upfront payment of revenues due
to operational capacity availability,
in equivalent value of 15% of total
referential CAPEX.
Equity support: up to 49% of
SPE** or holding’s share capital
(Institutions: public banks and
pension funds).
Canguera
Amador
BuenoMarinque
Evangelista
de Souza
Santos
Pereque
Itaquaciara
Perus
Eng Manoel Feio
Suzano
Rio Grande
da Serra
Ipiranga
Lapa
Jundiaí
Northern Ferroanel (SP)
To be awarded
SP
Santos
Seaport
*TJLP-LongTermInterestRate,
currently5%p.a.
**SpecialPurposeEntity
Updatedinformationavailable
atwww.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
68
Ministry
of Finance
Railways
Object Demand Concession characteristics Financing Conditions
Section: Lucas do RioVerde
- Campinorte and Palmas -
Anápolis
Extension: 1,920 km
InterconnectsBrazil’sMidwestRegiontothe
SoutheastandNortheast,providingrailway
transportationtoproductioncenterslocated
inthemidwestandtheoutflowthroughthe
North-SouthRailway.
Build, operate and transfer
Estimated CAPEX: US$3.65billion
Railinfrastructurebuilderand
manager:Concessionforrailway
exploitation,comprising:construction,
maintenance,signalingandcomunications
systems,andtrafficcontrol.
ConcessionTerm: 35 years
Construction to be completed up to the
5th year of the concession term.
RiskMitigation:DemandRisk
(Guaranteedpurchaseof100%ofrailway
operationalcapacityavailability);Socio-
environmentalandExpropriationRisks
(EnvironmentalandExpropriationcostsand
chargeslimitedtovaluespre-establishedin
concessioncontracts).
Environmental licensing: State-owned
EPL is responsible for obtaining Previous
License (LP) and will give support for
obtaining the Installation Licence (LI) of
construction works.
Term: 30 years
(Grace period: 5 years)
Rate:TJLP* + 1%a.a.
Real leveraged IRR:
up to 16% per year, in real terms.
Upfront payment of revenues due
to operational capacity availability,
in equivalent value of 15% of total
referential CAPEX.
Equity support: up to 49% of
SPE** or holding’s share capital
(Institutions: public banks and
pension funds).
Railway Concession: from Lucas do RioVerde (MT)
to Campinorte (GO) and from Palmas (TO) to Anápolis (GO)
MT
TO
GO
MS
SP
MG
RJ
ES
BA
Palmas
Campinorte
Anápolis
Lucas do Rio Verde
Concession: Lucas do Rio Verde
- Campinorte and Palmas - Anápolis
To be awarded
*TJLP-LongTermInterestRate,
currently5%p.a.
**SpecialPurposeEntity
Updatedinformationavailable
atwww.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
69
Ministry
of Finance
Railways
Object Demand Concession characteristics Financing Conditions
Section: Açailândia -
Vila do Conde
Extension: 457 km
Interconnects the Midwest Region to
the North and the port ofVila do Conde,
completing the north stretch of the North-
South Railway, allowing the production and
outflow of grains, minerals and oil products
through the port ofVila do Conde
Build, operate and transfer
Estimated CAPEX: US$ 1.39 billion
Rail infrastructure builder and
manager: Concession for railway
exploitation, comprising: construction,
maintenance, signaling and
comunications systems, and traffic
control.
ConcessionTerm: 35 years
Construction to be completed up to the
5th year of the concession term.
Risk Mitigation: Demand Risk
(Guaranteed purchase of 100% of
railway operational capacity availability);
Socio-environmental and Expropriation
Risks (Environmental and Expropriation
costs and charges limited to values pre-
established in concession contracts).
Environmental licensing: State-owned
EPL is responsible for obtaining Previous
License (LP) and will give support for
obtaining the Installation Licence (LI) of
construction works.
Term: 30 years
(Grace period: 5 years)
Rate:TJLP* + 1%a.a.
Real leveraged IRR:
up to 16% per year, in real terms.
Upfront payment of revenues due
to operational capacity availability,
in equivalent value of 15% of total
referential CAPEX.
Equity support: up to 49% of
SPE** or holding’s share capital
(Institutions: public banks and
pension funds).
Railway Concession: from Açailândia (MA) toVila do Conde (PA)
TO
MA
PA
Belém
Açailândia
Carajás
Vila do
Conde Port
Itaqui
Port
Concession:
Açailândia - Vila do Conde
To be awarded
*TJLP-LongTermInterestRate,
currently5%p.a.
**SpecialPurposeEntity
Updatedinformationavailable
atwww.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
70
Ministry
of Finance
Railways
Object Demand Concession characteristics Financing Conditions
Section: 	 OuroVerde de
Goiás – Dourados
Extension: 1,339 km
Expands the North-South Railway and
reaches important production centers of
grains.
Build, operate and transfer
Estimated CAPEX: US$ 1.78 billion
Rail infrastructure builder and
manager: Concession for railway
exploitation, comprising: construction,
maintenance, signaling and
comunications systems, and traffic
control.
ConcessionTerm: 35 years
Construction to be completed up to the
5th year of the concession term.
Risk Mitigation: Demand Risk
(Guaranteed purchase of 100% of
railway operational capacity availability);
Socio-environmental and Expropriation
Risks (Environmental and Expropriation
costs and charges limited to values pre-
established in concession contracts).
Environmental licensing: State-owned
EPL is responsible for obtaining Previous
License (LP) and will give support for
obtaining the Installation Licence (LI) of
construction works.
Term: 30 years
(Grace period: 5 years)
Rate:TJLP* + 1%a.a.
Real leveraged IRR:
up to 16% per year, in real terms.
Upfront payment of revenues due
to operational capacity availability,
in equivalent value of 15% of total
referential CAPEX.
Equity support: up to 49% of
SPE** or holding’s share capital
(Institutions: public banks and
pension funds).
Railway Concession:
OuroVerde de Goiás (GO) – Estrela D’Oeste (SP) – Panorama (SP) – Dourados (MS)
Concession:
Ouro Verde de Goiás - Dourados
To be awarded
Ouro Verde de Goiás
Goiânia
Campo Grande
Dourados
Panorama
Andradina
Estrela d’Oeste
GO
MS
*TJLP-LongTermInterestRate,
currently5%p.a.
**SpecialPurposeEntity
Updatedinformationavailable
atwww.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
71
Ministry
of Finance
Railways
Object Demand Concession characteristics Financing Conditions
Section: 	 Belo Horizonte -
Candeias
Extension: 1,350 km
Createsnewpossibilitiesfortransportofgeneral
cargobetweenthesoutheastandnortheast
regions,refocusingontheuseofrailwaystothe
developmentoftheinternalmarket.
Build, operate and transfer
Estimated CAPEX: US$ 4.80 billion
Rail infrastructure builder and
manager: Concession for railway
exploitation, comprising: construction,
maintenance, signaling and
comunications systems, and traffic
control.
ConcessionTerm: 35 years
Construction to be completed up to the
5th year of the concession term.
Risk Mitigation: Demand Risk
(Guaranteed purchase of 100% of
railway operational capacity availability);
Socio-environmental and Expropriation
Risks (Environmental and Expropriation
costs and charges limited to values pre-
established in concession contracts).
Environmental licensing: State-owned
EPL is responsible for obtaining Previous
License (LP) and will give support for
obtaining the Installation Licence (LI) of
construction works.
Term: 30 years
(Grace period: 5 years)
Rate:TJLP* + 1%a.a.
Real leveraged IRR:
up to 16% per year, in real terms.
Upfront payment of revenues due
to operational capacity availability,
in equivalent value of 15% of total
referential CAPEX.
Equity support: up to 49% of
SPE** or holding’s share capital
(Institutions: public banks and
pension funds).
Railway Concession: from Belo Horizonte (MG) to Candeias (BA)
GO
SP
MG
RJ
ES
BA
Concession:
Belo Horizonte - Candeias
To be awarded
Salvador
Candeias
Corinto
Salvador
Port
Aratu
Port
Belmonte
Port Terminal
Brumado
Caetité
Belo
Horizonte
Ilhéus Port
*TJLP-LongTermInterestRate,
currently5%p.a.
**SpecialPurposeEntity
Updatedinformationavailable
atwww.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
72
Ministry
of Finance
Railways
Object Demand Concession characteristics Financing Conditions
Section: Rio de Janeiro -Vila
Velha
Extension: 572 km
Integrates the port of Rio de Janeiro and its
Terminals to the Ports ofVitória eTubarão,
creating new logistic possibilities for the
movement of cargo.
Build, operate and transfer
Estimated CAPEX: US$ 1.52 billion
Rail infrastructure builder and
manager: Concession for railway
exploitation, comprising: construction,
maintenance, signaling and
comunications systems, and traffic
control.
ConcessionTerm: 35 years
Construction to be completed up to the
5th year of the concession term.
Risk Mitigation: Demand Risk
(Guaranteed purchase of 100% of
railway operational capacity availability);
Socio-environmental and Expropriation
Risks (Environmental and Expropriation
costs and charges limited to values pre-
established in concession contracts).
Environmental licensing: State-owned
EPL is responsible for obtaining Previous
License (LP) and will give support for
obtaining the Installation Licence (LI) of
construction works.
Term: 30 years
(Grace period: 5 years)
Rate:TJLP* + 1%a.a.
Real leveraged IRR:
up to 16% per year, in real terms.
Upfront payment of revenues due
to operational capacity availability,
in equivalent value of 15% of total
referential CAPEX.
Equity support: up to 49% of
SPE** or holding’s share capital
(Institutions: public banks and
pension funds).
Railway Concession: from Rio de Janeiro (RJ) toVilaVelha (ES)
MG
RJ
ES
Concession:
Nova Iguaçu - Vila Velha
To be awarded
Vitória
Vila Velha
Campos dos
Goitaguazes
Formosa
Beach
Tubarão
Port
Vitória
Port
Niterói Port
Rio de Janeiro Port
Ponta UBU
Port Terminal
Açu
Port
Terminal
Macaé
Port Terminal
Rio de
Janeiro
Barra do Piraí
Duque de Caixias
Port Terminal
Nova
Iguaçú
*TJLP-LongTermInterestRate,
currently5%p.a.
**SpecialPurposeEntity
Updatedinformationavailable
atwww.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
73
Ministry
of Finance
Railways
Object Demand Concession characteristics Financing Conditions
Section: Anápolis – Corinto
– Campos
Extension: 1,706 km
Createsnewpossibilitiesfortheoutflowofgrains
andmineralsfromproductioncentersthrough
mainports.
Build, operate and transfer
Estimated CAPEX: US$ 7.80 billion
Rail infrastructure builder and
manager: Concession for railway
exploitation, comprising: construction,
maintenance, signaling and
comunications systems, and traffic
control.
ConcessionTerm: 35 years
Construction to be completed up to the
5th year of the concession term.
Risk Mitigation: Demand Risk
(Guaranteed purchase of 100% of
railway operational capacity availability);
Socio-environmental and Expropriation
Risks (Environmental and Expropriation
costs and charges limited to values pre-
established in concession contracts).
Environmental licensing: State-owned
EPL is responsible for obtaining Previous
License (LP) and will give support for
obtaining the Installation Licence (LI) of
construction works.
Term: 30 years
(Grace period: 5 years)
Rate:TJLP* + 1%a.a.
Real leveraged IRR:
up to 16% per year, in real terms.
Upfront payment of revenues due
to operational capacity availability,
in equivalent value of 15% of total
referential CAPEX.
Equity support: up to 49% of
SPE** or holding’s share capital
(Institutions: public banks and
pension funds).
Railway Concession: from Corinto (MG) to Campos (RJ)
GO
SP
MG
RJ
ES
BA
Uruaçu
Concession:
Uruaçu - Campos
Ilhéus
Port
Corinto
Brumado
Vitória
Vitória
Port
Açu
Port Terminal
Belo Horizonte
Intendente Câmara
Campos
Bernardo Sião
To be awarded
Anápolis
*TJLP-LongTermInterestRate,
currently5%p.a.
**SpecialPurposeEntity
Updatedinformationavailable
atwww.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
74
Ministry
of Finance
Railways
Object Demand Concession characteristics Financing Conditions
Section: Feira de Santana –
Ipojuca
Extension: 893 km
Modernizes the northeastern railway network,
linking the major ports and markets
Build, operate and transfer
Estimated CAPEX: US$ 3.78 billion
Rail infrastructure builder and
manager: Concession for railway
exploitation, comprising: construction,
maintenance, signaling and
comunications systems, and traffic
control.
ConcessionTerm: 35 years
Construction to be completed up to the
5th year of the concession term.
Risk Mitigation: Demand Risk
(Guaranteed purchase of 100% of
railway operational capacity availability);
Socio-environmental and Expropriation
Risks (Environmental and Expropriation
costs and charges limited to values pre-
established in concession contracts).
Environmental licensing: State-owned
EPL is responsible for obtaining Previous
License (LP) and will give support for
obtaining the Installation Licence (LI) of
construction works.
Term: 30 years
(Grace period: 5 years)
Rate:TJLP* + 1%a.a.
Real leveraged IRR:
up to 16% per year, in real terms.
Upfront payment of revenues due
to operational capacity availability,
in equivalent value of 15% of total
referential CAPEX.
Equity support: up to 49% of
SPE** or holding’s share capital
(Institutions: public banks and
pension funds).
Railway Concession: from Feira de Santana (BA) to Ipojuca (PE)
BA
SE
AL
PE
PB
Concession:
Feira de Santana - Ipojuca
To be awarded
Recife
Maceió
Aracajú
Salvador
Porto de Recife
Porto de Suape
Porto de Maceió
Terminal Portuário
de Atalaia Velha
Porto de SalvadorPorto de
Aratu
Salgueiro
*TJLP-LongTermInterestRate,
currently5%p.a.
**SpecialPurposeEntity
Updatedinformationavailable
atwww.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
75
Ministry
of Finance
Railways
Object Demand Concession characteristics Financing Conditions
Section: Lapa – Paranaguá
Extension: 150 km
Expands and modernizes rail access to the
port of Paranaguá.
Build, operate and transfer
Estimated CAPEX: US$ 1.17 billion
Rail infrastructure builder and
manager: Concession for railway
exploitation, comprising: construction,
maintenance, signaling and
comunications systems, and traffic
control.
ConcessionTerm: 35 years
Construction to be completed up to the
5th year of the concession term.
Risk Mitigation: Demand Risk
(Guaranteed purchase of 100% of
railway operational capacity availability);
Socio-environmental and Expropriation
Risks (Environmental and Expropriation
costs and charges limited to values pre-
established in concession contracts).
Environmental licensing: State-owned
EPL is responsible for obtaining Previous
License (LP) and will give support for
obtaining the Installation Licence (LI) of
construction works.
Term: 30 years
(Grace period: 5 years)
Rate:TJLP* + 1%a.a.
Real leveraged IRR:
up to 16% per year, in real terms.
Upfront payment of revenues due
to operational capacity availability,
in equivalent value of 15% of total
referential CAPEX.
Equity support: up to 49% of
SPE** or holding’s share capital
(Institutions: public banks and
pension funds).
Railway Concession: from Lapa (PR) to Paranaguá (PR)
MS
PR
SC
RS
SP
RJ
Concession:
Lapa – Paranaguá
Porto Alegre
Florianópolis
Rio Grande
Port
Pelotas Port
Laguna Port
Imbituba Port
Itajaí Port
Paranaguá Port
São Sebastião
Port
Guaíba
Port Terminal
Duque de
Caxias Port
Terminal
Cascavel
Lapa
Maracaju Panorama
São Paulo
Rio de Janeiro
Curitiba
Eng. Bley
Mafra
Campo Alto
do Sul
Chapecó
Santos
Port
To be awarded
*TJLP-LongTermInterestRate,
currently5%p.a.
**SpecialPurposeEntity
Updatedinformationavailable
atwww.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
76
Ministry
of Finance
Railways
Object Demand Concession characteristics Financing Conditions
Section: Maracaju – Lapa
Extension: 989 km
Creates new logistics possibilities for the
outflow of grains and other cargo from
production centers through the Port of
Paranaguá.
Build, operate and transfer
Estimated CAPEX: US$ 3.13 billion
Rail infrastructure builder and
manager: Concession for railway
exploitation, comprising: construction,
maintenance, signaling and
comunications systems, and traffic
control.
ConcessionTerm: 35 years
Construction to be completed up to the
5th year of the concession term.
Risk Mitigation: Demand Risk
(Guaranteed purchase of 100% of
railway operational capacity availability);
Socio-environmental and Expropriation
Risks (Environmental and Expropriation
costs and charges limited to values pre-
established in concession contracts).
Environmental licensing: State-owned
EPL is responsible for obtaining Previous
License (LP) and will give support for
obtaining the Installation Licence (LI) of
construction works.
Term: 30 years
(Grace period: 5 years)
Rate:TJLP* + 1%a.a.
Real leveraged IRR:
up to 16% per year, in real terms.
Upfront payment of revenues due
to operational capacity availability,
in equivalent value of 15% of total
referential CAPEX.
Equity support: up to 49% of
SPE** or holding’s share capital
(Institutions: public banks and
pension funds).
Railway Concession: from Maracajú (MS) to Lapa (PR)
MS
PR
SC
RS
SP
RJ
Concession:
Lapa – Paranagua
Porto Alegre
Florianópolis
Rio Grande
Port
Pelotas Port
Laguna Port
Imbituba Port
Itajaí Port
Paranaguá Port
São Sebastião
Port
Guaíba
Port Terminal
Duque de
Caxias Port
Terminal
Cascavel
Lapa
Maracaju Panorama
São Paulo
Rio de Janeiro
Curitiba
Eng. Bley
Mafra
Campo Alto
do Sul
Chapecó
Santos
Port
To be awarded
*TJLP-LongTermInterestRate,
currently5%p.a.
**SpecialPurposeEntity
Updatedinformationavailable
atwww.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
77
Ministry
of Finance
Railways
Object Demand Concession characteristics Financing Conditions
Section: Mairinque – Rio
Grande
Extension: 1,667 km
Creates new logistics possibilities for the flow
of cargo between Sao Paulo and the South
Region of Brazil, linking production and
consumption centers.
Build, operate and transfer
Estimated CAPEX: US$ 10.73 billion
Rail infrastructure builder and
manager: Concession for railway
exploitation, comprising: construction,
maintenance, signaling and
comunications systems, and traffic
control.
ConcessionTerm: 35 years
Construction to be completed up to the
5th year of the concession term.
Risk Mitigation: Demand Risk
(Guaranteed purchase of 100% of
railway operational capacity availability);
Socio-environmental and Expropriation
Risks (Environmental and Expropriation
costs and charges limited to values pre-
established in concession contracts).
Environmental licensing: State-owned
EPL is responsible for obtaining Previous
License (LP) and will give support for
obtaining the Installation Licence (LI) of
construction works.
Term: 30 years
(Grace period: 5 years)
Rate:TJLP* + 1%a.a.
Real leveraged IRR:
up to 16% per year, in real terms.
Upfront payment of revenues due
to operational capacity availability,
in equivalent value of 15% of total
referential CAPEX.
Equity support: up to 49% of
SPE** or holding’s share capital
(Institutions: public banks and
pension funds).
Railway Concession: from Mairinque (SP) to Rio Grande (RS)
MS
PR
SC
RS
SP
RJ
Concession: Mairinque
– Rio Grande
Porto Alegre
Florianópolis
Rio Grande
Port
Pelotas Port
Laguna Port
Imbituba Port
Itajaí
Port
Paranaguá
Port
São
Sebastião
Port
Guaíba
Port Terminal
Duque de
Caxias Port
Terminal
Cascavel
Forno
Port
Maracaju Panorama
São Paulo
Rio de Janeiro
Mairinque
Eng. Bley
Mafra
Campo Alto
do Sul
Chapecó
Santos
Port
To be awarded
*TJLP-LongTermInterestRate,
currently5%p.a.
**SpecialPurposeEntity
Updatedinformationavailable
atwww.logisticsbrazil.gov.br
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
78
Ministry
of Finance
Railways
Study in Progress
Railway Concession – High-SpeedTrain (TAV)
Rio de Janeiro - São Paulo - Campinas 1st
Phase
Physical Description
Section: Rio de Janeiro - São Paulo - Campinas
Extension: 511 km
The High-SpeedTrain Rio de Janeiro – Campinas will be the first high speed rail service in Brazil.The first phase includes the
concession of the operation and maintenance of the system, supply and assembly of operational (signalling, electrification
and telecommunication) and safety systems, rolling stock and acoustic protection, and technology transfer.
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
Viracopos
Galeão
Guarulhos
São Paulo
Campinas
Rio de Janeiro
Ports
80
Ministry
of Finance
Seaports
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
Major Brazilian Ports
Macapá
Belém/Miramar/Outeiros
Itaqui
Pecém
Cabedelo
Suape/Recife
Maceió
Aratu/Salvador
Porto Sul/Ilhéus
Vitória
Itaguaí/Rio De Janeiro
Santos/São Sebastião
Paranaguá/Antonia
Itajaí/Imbituba/São Francisco do Sul
Porto Alegre
Rio Grande
Vila do
Conde
Santarém
Manaus/
Itacoatiara
Porto Velho
81
Ministry
of Finance
Seaports
Port Investment Program - Bidding Blocks
Block Ports Estimated
Investment
Increase
Capacity Auction
Block 1
31 terminals at: Santos, Outeiro,
Santarém, Belém, Miramar andVila
do Conde Ports
US$ 1.5 bi
27 million
tons/year
Dec 2013
Block Ports Public Consultation Auction
Block 2
44 terminals at: Paranaguá, Antoni-
na, Salvador, Aratu and São Sebastião
Ports
Sep 2013 Jan 2014
Block 3
36 terminals at: Cabedelo, Fortale-
za, Itaqui, Macapá, Recife and Suape
Ports
Oct 2013 Feb 2014
Block 4
28 terminals at: Itaqui, Niterói, Rio
de Janeiro, Itajaí, São Francisco do Sul,
Rio Grande, Porto Alegre andVitória
Ports
Nov 2013 Mar 2014
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
Source:SpecialSecretariatofPorts
Producedby:MinistryofFinance
82
Ministry
of Finance
Seaports
Port Investment Program
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
Source:NationalLogistics&Planning
Company(EPL)
Producedby:MinistryofFinance
Conditions to public ports
•	 Terminals at public ports will be leased through public auction
Main Features
•	 25-year term, renewable only once
Standardized biddings conducted through
auction by ANTAQ
ContractualTerms (requirements)
•	 Minimutm Investments
•	 Minimum productivity
•	 Minimum static capacity
Selection Criteria
Terminal in verticalized chains or with
healthy competition environment
•	 Bidding for greater handling capacity
•	 Induction of new investments
Terminals with features of provision of
services to third parties
•	 Bidding for lowest tariff
•	 Reduction of port costs
•	 Guarantee of isonomic access to users 
Conditions to private ports
•	 Terminalsatprivateportsmaybeleasedwithoutapublicauction,shoulditsconstructionnotconflict
with another port or terminal, existing or planed.There are 62 private terminals that should obtain
its lease in the next months, with a estimated investment of US$ 7.5 billion
Airports
84
Ministry
of Finance
Airports
Source:CivilAviationSecretariat(SAC)
Producedby:MinistryofFinance
Major Brazilian Airports
Brasília
Goiânia
Boa Vista
Tabatinga
Cruzeiro do Sul
Rio Branco
Tefé
Porto Velho
Manaus
Santarém
Altamira
Macapá
Belém (Val de Cans)
Belém (Júlio César)
Marabá
Palmas
Cuiabá
Corumbá Campo Grande
Ponta Porã
Foz do Iguaçú
Uruguaiana
Bagé
Porto Alegre
Pelotas
Criciúma
Florianópolis
Navegantes
Joinville
Curitiba (Afonso Pena)
SP (Congonhas)
Curitiba
(baracher)
SP (Campos de Marte)
Londrina
Uberaba
Uberlândia
RJ (Jacarepaguá)
RJ Santos Dumont
Macaé
Campos dos Goytacazes
Vitória
Montes Claros
Petrolina
Juazeiro
do Norte
Fortaleza
Parnaíba
Guarulhos
RJ (Galeão)
Campinas
SJ dos Campos
Teresina
Imperatriz
Carajás
Campina
Grande
Paulo
Afonso
Ilhéus
Salvador
Aracajú
Natal
João Pessoa
Recife
Maceió
Confins
BH (Carlos Prates)
BH (Pampulha)
15.000.001 to 30.100.000 (3)
5.000.001 to 15.000.000 (9)
1.000.001 to 5.000.000 (15)
5000.001 to 1.000.000 (7)
100.001 to 500.000 (19)
Up to 100.000 (13)
Passengers per year
Concessions to be granted :
Galeão (Rio de Janeiro)
Confins (Belo Horizonte)
Concessions already
granted :
Guarulhos (São Paulo)
Viracopos (São Paulo)
Brasília
85
Ministry
of Finance
Airports
Airport Investment Program
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
Source:CivilAviationSecretariat(SAC)
Producedby:MinistryofFinance
Airport International
Pax - 2012
Domestic
Pax - 2012
Estimated
Investment Auction Concession
Term Situation
Guarulhos
International
(GRU)
11,387,443 20,958,079 US$ 3.1 billion Feb 2012 20 years Granted
Viracopos
International
(VCP)
75,610 8,627,690 US$ 5.1 billion Feb 2012 30 years Granted
Brasilia
International
(BSB)
409,975 15,419,553 US$ 1.8 billion Feb 2012 25 years Granted
Galeão
International
(GIG)
4,190,433 12,973,780 US$ 2.45 billion Nov 2013 25 years
To be
Granted
Confins
International
(CNF)
443,955 9,834,536 US$ 1.52 billion Nov 2013 30 years
To be
Granted
86
Ministry
of Finance
Airports
Schedule for the concessions of Galeão and Confins airports
2013
Release of
Auction
Notices
TCU* and
Public Hearings AuctionStudies
May
Jun
Jul
Aug
Sep
Nov
*TCU-FederalCourtofAuditors
Source:CivilAviationSecretariat(SAC)
Producedby:MinistryofFinance
87
Ministry
of Finance
Airports
Galeão - Summary Chart
Galeão - Summary Chart
Airport Area: 17,881,697m²
Area for Apron: 712,895 m2
Aircraft Capacity:
-T1: 19 boarding gates + 12 remote positions
-T2: 19 boarding gates + 12 remote positions
- 15 positions for cargo aircraft
PassengerTerminals:
Capacity: 17.4 million Pass/Yr
Area:	 T1 - 147,834 m²
	 T2 - 132,847 m²
Parking: 4,310 parking spaces
CargoTerminal: 46,500 m²
Cargo Movements: 87,876 ton
Staff Employees: 958
Number of Passengers, in million
Passenger Profile (2012), in million
Int
Dom
13.0
4.2
0
6
12
18
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2011-2012: 17.5%
Average Growth = 16%
Source:CivilAviationSecretariat(SAC)
Producedby:MinistryofFinance
88
Ministry
of Finance
Airports
Galeão – Financial Conditions
Object:
•	 Expansion, maintenance and operation of the Antônio Carlos Jobim International Airport
(Galeão Airport) with a total area of 17,880,000 m2
Contract criteria:
•	 Term: 25 years
•	 Consortium:INFRAERO,thegovernmentownedcompany,willhold49%oftheConcessionairecapital;
private leveraged (51%)
•	 Periodic review of the capex program and Investment triggers
•	 Bidding Criteria: highest bid + variable fee
•	 Minimum bid: US$ 2.09 billion
•	 Variable fee: 5% of the gross revenue
•	 CAPEX: US$ 2.45 billion
•	 Project IRR: 6.63% p.a.
•	 OPEX: US$ 4.63 billion
Financing conditions*:
•	 Credit term: 14 years
•	 Grace period: 2 years
•	 Debt: up to 80% of the capex
•	 Interest Rate: TJLP (currently at 5%) + 0.9% + risk spread (0.46% to 3.57%) per year
*BNDESfinancingconditionsapplied
toairportsalreadygranted(Guarulhos,
ViracoposandBrasília).
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
Source:CivilAviationSecretariat(SAC)
Producedby:MinistryofFinance
89
Ministry
of Finance
Airports
Galeão- Estimated Demand
10
30
50
70
2038203320232013
60.3
50.1
34.5
19.2
MillionPassengers
Source:CivilAviationSecretariat(SAC)
Producedby:MinistryofFinance
Year 2013 2023 2033 2038
Passengers 19,269,199 34,537,602 50,138,243 60,365,874
90
Ministry
of Finance
Airports
Confins - Summary Chart
Confins - Summary Chart
Airport Area: 15,010,000 m²
Area for Apron: 211,437 m2
Aircraft Capacity:
Apron 1: 9 boarding gates + 9 remote positions
Apron 2: 7 positions for general aviation + 1 helipad
Apron 3: 2-4 positions for general aviation
PassengerTerminal:
Capacity: 10.3 million Pass/Year
Area: T1 - 60,305 m²
Vehicle Parking : 2,005 parking spaces
CargoTerminal: 9,880 m²
Cargo Movements: 27,163 ton
Staff Employees: 344
Number of Passengers, in million
Passenger Profile (2012) , in million
Int
Dom 9.8
0.4
2011-2012: 9.5%
Average Growth = 46.3%
Migration of
Pampulha to
Confins
0
4
8
12
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
Source:CivilAviationSecretariat(SAC)
Producedby:MinistryofFinance
91
Ministry
of Finance
Airports
Cofins - Financial Conditions
Object:
•	 Expansion, maintenance and operation of theTancredo Neves International Airport
(Confins Airport) with a total area of 15,010,000 m2
Contract criteria:
•	 Term: 30 years
•	 Consortium: INFRAERO, the government owned company, will hold 49% of the Concessionaire
capital; private leveraged (51%)
•	 Periodic review of the capex program and Investment triggers
•	 Bidding Criteria: highest bid + variable fee
•	 Minimum bid: US$ 476.5 million
•	 Variable fee: 5% of the gross revenue
•	 CAPEX: US$ 1.52 billion
•	 Project IRR: 6.63% p.a.
•	 OPEX: US$ 1.57 billion
Financing conditions*:
•	 Credit term: 14 years
•	 Grace period: 2 years
•	 Debt: up to 80% of the capex
•	 Interest Rate:TJLP (currently at 5%) + 0.9% + risk spread (0.46% to 3.57%) per year
*BNDESfinancingconditionsapplied
toairportsalreadygranted(Guarulhos,
ViracoposandBrasília)
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
Source:CivilAviationSecretariat(SAC)
Producedby:MinistryofFinance
92
Ministry
of Finance
Airports
Confins – Estimated Demand
5
14
23
32
41
50
2043203320232013
28.1
18.1
10.9
43.3
MillionPassengers
Year 2013 2023 2033 2043
Passengers 10,993,890 18,162,209 28,165,165 43,334,690
Source:CivilAviationSecretariat(SAC)
Producedby:MinistryofFinance
Oil and Gas
94
Ministry
of Finance
OilandGas
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
Source:NationalAgencyofPetroleum,
NaturalGasandBiofuels(ANP)and
MinistryofMinesandEnergy(MME)
Producedby:MinistryofFinance
11th
Round – Bidding Results (May 2013)
•	 142 bought blocks, from 289 offered at the auction
•	 US$ 1.22 billion in signature bonus
•	 US$ 3.0 billion in the Minimum Exploratory Program commitment
•	 Local Content offers indicates good possibilities for execution of the previous
commitments regarding earlier bidding rounds
•	 30 companies bought blocks at the bidding round
	 - 18 companies from 11 different countries
95
Ministry
of Finance
OilandGas
Source:NationalAgencyofPetroleum,
NaturalGasandBiofuels(ANP)and
MinistryofMinesandEnergy(MME)
Producedby:MinistryofFinance
11th
Round – Bidding Result (May 2013)
Brasília
Pernambuco-Paraíba
Barreirinhas
Pará-Maranhão
Amazonas River Mouth
Ceará
Parnaíba
Tucano and
Reconcavo Basins
Potiguar Onshore
Basin
Potiguar Offshore
Espírito Santo
Onshore/Offshore
Brought Blocks
Offered but not sold
Offshore
Sedimentary Basin
Pre-Salt Limit
96
Ministry
of Finance
OilandGas
Source:NationalAgencyofPetroleum,
NaturalGasandBiofuels(ANP)and
MinistryofMinesandEnergy(MME)
Producedby:MinistryofFinance
11th
Round – Bidding Result (May 2013)
Sedimentary basin State Bought Blocks Area (km2
)
Sergipe-Alagoas onshore AL 11 320.89
Foz do Amazonas AP 14 10,543.55
Pernambuco-Paraíba
PB 1 476.95
PE 3 1,776.23
Tucano Sul BA 21 3,789.67
Espírito Santo offshore ES 6 4,328.40
Espírito Santo onshore ES 6 178.73
Recôncavo BA 15 443.13
Ceará CE 6 3,642.32
Potiguar offshore
CE 3 2,303.23
RN 1 767.38
Potiguar onshore RN 14 411.80
Barreirinhas MA 19 9,997.40
Pará-Maranhão
MA 2 1,538.57
PA 0 -
Parnaíba (onshore)
PI 14 42,143.81
MA 6 17,620.43
TOTAL 11 142 100,282.49
97
Ministry
of Finance
OilandGas
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
Source:NationalAgencyofPetroleum,
NaturalGasandBiofuels(ANP)and
MinistryofMinesandEnergy(MME)
Producedby:MinistryofFinance
1st
Round of production sharing – Pre-Salt layer
Date: October 21, 2013
Area name: Libra
•	 1,548 sq km
•	 Deep water of Santos Basin
•	 Well with tested oil discovery
•	 Estimative of 42 billion bbl of oil in situ, indicating recovery of 8 to 12 billion barrels
Signature Bonus: R$ 15 billion (~US$ 6.5 billion)
Judgement criteria: Percentage of profit oil for the Government
(minimum of 40% in average along the contract period)
Local Content
•	 37% at Exploratory Phase
•	 From 55% to 65% at Production Development Phase
Jul
Sep
Oct21st
Dec
2013
Preliminary
auction
notice,
areas
and data
Release
of auction
notice Auction
Contract
Signature
98
Ministry
of Finance
OilandGas
Source:NationalAgencyofPetroleum,
NaturalGasandBiofuels(ANP)and
MinistryofMinesandEnergy(MME)
Producedby:MinistryofFinance
Brazil Pre-Salt layer – Bidding under production sharing regime
Pre-Salt
Boundaries
Estimated Recoverable
Volumes
Libra
8 to 12 bi boeFranco
2.0 to 5.5 bi boe
Florim
0.1 to 0.4 bi boe
Sul de Guará
0.1 to 0.3 bi boe
Peroba
1.1 to 1.8 bi boe
South and NE of Tupi
0.5 to 0.7 bi boe
Iara Surroundings
0.6 to 0.8 bi boe
Lula
8.3 bi boe
Iara
3 to 4 bi boeSapinhoá
2.1 bi boe
Pão de Açúcar
1.2 bi boe
Parque das Baleias
1.5 to 2 bi boe
Rio de Janeiro
São Paulo
Espirito Santo
Proved Reserves
(2012): 18.2 bi boe
Granted area: 42 thousand sq km (28%)
Cession area: 3.74 thousand sq km (2,5%)
Estimated Volumes (06/2013)
28.5 to 39.1 billion boe
• At the Pre-Salt evaluated areas, expected recoverable volumes could reach twice the
actual proved reserves
99
Ministry
of Finance
OilandGas
Source:NationalAgencyofPetroleum,
NaturalGasandBiofuels(ANP)and
MinistryofMinesandEnergy(MME)
Producedby:MinistryofFinance
12Th
Bidding Round: auction scheduled for November, 2013
Concession of areas under rules and terms established by Law 9,478/1997
Focus on natural gas – conventional and unconventional resources
Blocks: 240
•	 164,500 km²
•	 7 Sedimentary Basins
Bidding judgment criteria:
•	 Signature Bonus (40%) - Minimum for each block in the Auction Notice
•	 Minimum Exploratory Program (40%)
•	 Local Content (20%) - Minimum and maximum values in Auction Notice
100
Ministry
of Finance
OilandGas
Source:NationalAgencyofPetroleum,
NaturalGasandBiofuels(ANP)and
MinistryofMinesandEnergy(MME)
Producedby:MinistryofFinance
Areas with potential for non-conventional resources
Oil and Gas in Brazil
Sedimentary Basin
Tacutu
Solimões
Acre
Madre de Dios
Amazonas
Alto Tapajós
Parecis
Pantanal
Paraná
Camamu-Almada
Parnaíba
Barreirinhas
Bananal
São
Francisco
Recôncavo
Amazonas River Mouth
Pará-Maranhão
Potiguar
Rio do Peixe
Pernambuco-Paraíba
Sergipe-AlagoasTucano
Espírito Santo
Campos
Santos
Electricity
102
Ministry
of Finance
Electricity
Brazilian investments in the electricity sector auctions – 2013 to 2017
Estimated Expansion Investments (US$ billion)
Power 33,288 MW 53.1
Transmission 21,164 km 11.0
Total 64.1
• Electricity transmission lines
• Power to be contracted
Auction Length (Km) Investment (US$ billion)*
2013 4,745 2.4
2014-2017
Approved Projects 11,846 6.0
Other Projects 4,573 2.6
Total 21,164 11.0
Sources Capacity (MW) Investment (US$ billion)
Hydro 21,689 35.4
Other Renewable Sources
(Wind, Biomass and Small Hydro)
10,099 16.4
Thermal 1,500 1.3
Total 33,288 53.1
Source:EnergyResearchOffice(EPE)
Producedby:MinistryofFinance
*Includingestimatedinvestmentin
substations
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
103
Ministry
of Finance
Electricity
Source:EnergyResearchOffice(EPE)
Producedby:MinistryofFinance
Electricity Auctions
• Modalities
• New Energy Auctions A-3 and A-5: servicing expected demand growth
• Reserve auctions: ensuring greater security of supply
• Structuring Project Auctions: special conditions
• Bidders
• Public or private companies
• National or foreign companies
•Winners
• Lowest bid
• Winners of the new energy auctions sign long-term contracts (15 to 30 years) with distributors and
receive concessions (in the case of hydropower plants)
• Indexation
• IPCA (Consumer Price Index)
• Financing
• Use of the PPA (Power Purchase Agreement) as collateral for project financing by the BNDES
• Risk mitigation
• Only projects with prior environmental licenses are auctioned off
104
Ministry
of Finance
Electricity
HPP-HydroPowerPlant
ANEEL-NationalElectricityAgency
Source:EnergyResearchOffice(EPE)
Producedby:MinistryofFinance
Maintechnicalrequirementsforparticipationintheelectricityauctions
Type
ANEEL
Registry
Prior
Environmental
License
Access
Information
Energy
Production
Certification
Proof of
Right of Local
Use
Proof of
Availability
Water
Use Grant
Wind Power
Plant
X X X X X
Hydroelectric
Plant (HPP and
small Hydro)
X X X X
Thermoelectric
Plant (Biomass
and fossil)
X X X X X X
• A project’s technical and environmental viability must be ensured to participate in the electricity auction
• Several requirements must be met to prove viability, such as:
105
Ministry
of Finance
Electricity
Main financial requirements for
participating in electricity auctions and for signing power contracts
• Bid guarantees due to ANEEL
• Foreachprojecteligibletoparticipateintheauction,biddersmustsubmitbidguaranteesduetoANEEL
1. For Projects without grants: 1% of the investment value
2. For Projects with grants: US$ 870 per lot of energy to be offered
(1 lot = 0.1 average MW)
• Assurance of Faithful Execution of Contract
•The auction winners must collect 5% of the investment value declared to the EPE
•The warranties will decrease in value as the construction phase of the power plant advances
AverageMW(MWm)–EnergyUnit
(8,760MWhoveranyearlyperiod)
Source:EnergyResearchOffice(EPE)
Producedby:MinistryofFinance
106
Ministry
of Finance
Electricity
BNDES FINEM (Financing to Enterprises) Financial Aspects
Hydro Power Plant
(HPP)
Thermal Power Plant
(TPP)
Wind, Biomass and
Small Hydro
• Current credit conditions:
• Leverage: up to 70%;
• Amortization period: up to 20
years;
• Grace period: up to 6 months after
commercial operation date;
• Interest rate:TJLP**+0.9%+credit
risk spread.
• Current credit conditions:
• Leverage: up to 70% (60% coal),
should observe DSCR* ≥ 1.2;
• Amortization period: up to 16 years;
• Grace period: up to 6 months after
commercial operation date;
• Interest rate:TJLP**+0.9% +credit
risk spread.
• Current credit conditions:
• Leverage: up to 80%, should
observe DSCR * ≥1.2;
• Amortization period up to 20 years
(16 years for wind);
• Grace period: up to 6 months after
commercial operation date;
• Interest rate:TJLP**+0.9%+credit
risk spread.
*DSCR:debtservicecoverageratio
**TJLP:LongTermInterest
Tax,currently5.0%
Source:National Bank of Economic
and Social Development (BNDES)–
ConsultationinJan/2013
Producedby:MinistryofFinance
107
Ministry
of Finance
Electricity
Source:EnergyResearchOffice(EPE)
Producedby:MinistryofFinance
Electricity Auctions: main results
• August 2013 Reserve Auction
• August 2013 Power Auction
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
Type
Projects able to bid Auction Results
Bid Capacity
(MW)
Number of
Participants
Bid Capacity (MW)
Number of
Participants
Total Amount
(US$ million)
Wind Power Plant 8,999 377 1,505 66 2,373
Type
Projects able to bid Auction Results
Bid Capacity
(MW)
Number of
Participants
Bid Capacity
(MW)
Number of
Participants
Total Amount
(US$ million)
Biomass 919 16 647 9 815
Coal 1,840 3 - - -
HPP (less than 50 MW) 376 16 219 9 586
HPP SINOP 400 1 400 1 773
Total 3,535 36 1,266 19 2,174
Number of Auctions Projects Capacity (MW) Investment (US$ billion)
23 490 60,892 100
• Consolidated results of new energy auctions from 2005 to 2012
108
Ministry
of Finance
Electricity
Source:EnergyResearchOffice(EPE)
Producedby:MinistryofFinance
Hydropower Expansion: 2013 electricity auctions
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
• November 2013 Auction
• Hydropower Expansion: December 2013 auction
Type
Projects able to bid
Bid Capacity (MW) Number of Participants
Wind Power
Plant
15,042 629
Solar 2,838 119
Small Hydro 295 16
Biogas 39 2
Biomass 504 15
Natural Gas 469 2
Total 19,187 783
Auction
Hydropower
Plant
River/State
Capacity
(MW)
Total Capacity
(MW)
Estimated Investments
(US$ billion, constant
prices, Dec/2012)
2013
São Manoel Teles Pires/ MT-PA 700
1,021 1.8
Cachoeira Parnaíba/ PI 63
Ribeiro Gonçalves Parnaíba/ PI 113
Itaocara Paraíba do Sul/RJ 145
109
Ministry
of Finance
Electricity
Source:EnergyResearchOffice(EPE)
Producedby:MinistryofFinance
Hydropower Expansion: auctions from 2014 to 2017
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
Auction
Hydropower
Plant
River/State
Capacity
(MW)
Total Capacity
(MW)
Estimated Investments
(US$ billion, constant prices, Dec/2012)
2014
Davinópolis Paranaíba/ MG-GO 74
7,495 11.3
Foz do Piquiri Piquiri/ PR 93.2
Ercilândia Piquiri/ PR 87.1
S LuízTapajós Tapajós/ PA 6,133
Água Limpa Das mortes/ MT 380
Comissário Piquiri/ PR 105
Foz Piquiri Piquiri/ PR 101
Telêmaco Borba Tibagi/ PR 109
Paranhos Chopim/PR 63
Tabajara Ji-Paraná/RO 350
2015
Jatobá Tapajós/PA 2,336
3,249 5.4Castanheira Arinos/ MT 192
Itapiranga Uruguai/SC-RS 721
2016
Torixoréu Araguaia/ GO-MT 408
1,117 2.3
Bem Querer Branco/ RR 709
2017
Riacho Seco S. Francisco / PE-BA 276
8,407 13.7
Salto Augusto Baixo Juruena/ MT-AM 1,461
S. Simão
Alto Juruena/
MT-AM
3,509
Pompeu S. Francisco / MG 209
Marabá Tocantins / PA-MA 2,160
Prainha Aripuanã/ AM 792
Total 20,268 32.7
110
Ministry
of Finance
Electricity
HPP São Manoel - Fact sheet
•Teles Pires River
• Capacity: 700 MW
• Firm Energy: 400 average MW
• Number of generating units: 5
• Gross Head: 23.9 m
• Spillway Crest: 165 m.
• Max normal water level (reservoir): 161 m
• Normal water level downstream: 138.2 m
• Reservoir Area (normal water levels) ~ 70.8 km²
		
Estimated Investment
US$ 1.0 billion
Indigenous Land Cayabi
0 2,5 5 10 15 20
N
Legend
HPP São Manoel
HPP São Manoel Reservoir
0 2,5 5 10 15 20
Declared Indigenous Land
State border line
MATO GROSSO
Novo Planeta
Paulão
Mutum
HPP São Manoel
PARÁ
Source:EnergyResearchOffice(EPE)
Producedby:MinistryofFinance
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
111
Ministry
of Finance
Electricity
Source:EnergyResearchOffice(EPE)
Producedby:MinistryofFinance
The development of wind power in Brazil
• Operating and contracted capacity
•To be contracted in 2013-2017 auctions
0
2000
4000
6000
8000
10000
10,130
8,846
7,882
5,197
2,189
1,750
1,417
927
607337248237292322
2017
2016
2015
2014
2013
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
MW
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
Capacity
(MW)
Investment
(US$ billion)
4,215 7.7
112
Ministry
of Finance
Electricity
Source:EnergyResearchOffice(EPE)
Producedby:MinistryofFinance
The development of bioelectricity in Brazil
• Operating and contracted capacity
• To be contracted in 2013-2017 auctions
0
2,000
4,000
6,000
8,000
10,000
2017
2016
2015
2014
2013
2012
2011
2010
2009
2008
2007
2006
2005
1,755
2,584 2,590
3,910
4,969
6,822
7,874 8,081
8,936 9,035 9,035 9,085 9,185
MW
Capacity
(MW)
Investment
(US$ billion)
2,513 2.4
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
113
Ministry
of Finance
Electricity
Source:EnergyResearchOffice(EPE)
Producedby:MinistryofFinance
Other energy sources to be contracted in 2013 – 2017 auctions
• Small hydropower plants
• Additional expansions depend on the effective exploration of unconventional gas
• Thermal power stations
Capacity
(MW)
Investment
(US$ billion)
1,500 1.3
Capacity
(MW)
Investment
(US$ billion)
1,000 2.6
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
114
Ministry
of Finance
Electricity
Source:EnergyResearchOffice(EPE)
Producedby:MinistryofFinance
Transmission Line Auctions
• Bidders
• Legal Entities: National or Foreign
• Equity Funds: alone or in a consortium
• Clearance
• Clearance after auctions and publication of winning bids
•Winners
• Bidder with lowest Allowed Annual Revenue (RAP)
•Winners will sign long-term contracts (30 years)
• Regulated contracts
• Indexation by IPCA (Consumer Price Index)
• Contracts submitted to the Periodic Rate Reviews
• Financing
• RAP as collateral for financing by the BNDES
115
Ministry
of Finance
Electricity
Source:EnergyResearchOffice(EPE)
Producedby:MinistryofFinance
Transmission Line Auctions: sequence of events
-2.8
Public Notice of Auction
ANEEL approval of technical
capacity of the winners of the auction
TL Auction Winners deliver
documentation to ANEEL
Celebration of concession contract
between winner and ANEEL
Auction held at BM&FBOVESPA
Approval of Auction Results
Auction application and bid
guarantees due to ANEEL Accepted bid guarantee
instruments: cash deposit,
surety bond, bank guarantee,
Brazilian Government Bonds
(1% of estimated investment)
Replacement of bid guarantees
with the guarantee of faithful
execution of the contract
(5% of estimated investment)
116
Ministry
of Finance
Electricity
BNDES FINEM (Financing to Enterprises) Financial Aspects
• Access to financing available to national and international companies with head offices and
management in Brazil, and legal entities of public law
• Current credit conditions:
• Leverage: up to 70%
• Total Loan Period: up to 14 years
• Grace period: up to 6 months after commercial operation date.
• Interest rate:TJLP*+1.3%+credit risk spread
Source:EnergyResearchOffice(EPE)
Producedby:MinistryofFinance
*TJLP:LongTermInterestTax,
currently5.0%
117
Ministry
of Finance
Electricity
Source:EnergyResearchOffice(EPE)
and National Electricity Agency(ANEEL)
Producedby:MinistryofFinance
Transmission Line Past Auctions: main results
• Transmission Line Auction of Dec, 2012: Main Results
• Number of applicants: 15 (includes state-owned companies, private groups, 4 foreign groups,
and equity funds)
• TotalTL** tendered: 3,822 Km
• Estimated investment: US$ 1.7 billion
• Average discount: 21.7%
• Stiff competition: for example, in“500 kV Estreito - Itabirito”transmission line auction, there
were 305 bids that resulted in a 16.6% discount
*currentvalues
**TL–TransmissionLine
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
• Consolidated results of auctions from 2000 to 2012
Number of Auctions Length (km)
Investment
(US$ billion) (*)
24 51,000 13.9
118
Ministry
of Finance
Electricity
Source:EnergyResearchOffice(EPE)
Producedby:MinistryofFinance
Main Projects: north-southeast expansion
Physical Description Goals
• Main section: Connects the North
and Southeast Region, with DC Link
between the states of Pará and Minas
Gerais
• Length:
• 2,050 km on Direct Current
• 2,244 km on Alternating
Current
• Promotes interconnection between two major
subsystems, enabling the exchange of electricity
between regions North and Southeast.
• Increase of 4,000 MW in exchange capacity
between the North and Southeast Regions
Financial Aspects
• ConcessionTerm: 30 years
• Estimated Investment: US$ 2.6 billion
Project Requirements
• TLs in Direct Current: 800 kV
• Increases in Existing System
• Bidding in 2013
• Winning Bidder: the lowest RAP (Allowed
Annual Revenue)
(2)
(2)
800 KV DC
2,050 Km
Bipole 1
500 KV AC
2,244 Km
Terminal Minas
TOCANTINS
Miracema
Colinas
Itacaúnas
MATO GROSSO
GOIÁS
Paraupebas
PARÁ
MARANHÃO
Xingo
Picuruí
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
119
Ministry
of Finance
Electricity
MainTL Projects to be Auctioned in 2013
2nd
semester 2013 - transmission lines (EPE proposal)
Estimated Investment of
US$ 2.4 billion (*)
Source:EnergyResearchOffice(EPE)
Producedby:MinistryofFinance
*Includesestimatedinvestmentin
substations
InthefirsthalfofSeptember2013,
theaverageexchangeratewas
approximatelyUS$1= R$2.30
Associated Projects Projects State
Voltage
(kV)
Length
(Km)
Investment
(US$ billion)
To meet electricity demand growth
TL Itabirito 2 –Vespasiano 2, CS MG 500 90
0.1TL Barro Alto – Itapaci, C2 GO 230 68
TL Candiota (Presidente Médici) – Bagé 2 RS 230 50
Expansion S/SE TL Itatiba – Bateias SP/PR 500 390 0.2
Expansion before Belo Monte
TL Marimbondo II - Campinas SP 500 370
0.3TL Araraquara 2 - Itatiba, CS SP 500 198
TL Araraquara 2 - Fernão Dias, CS SP 500 240
ExpansionoftheInterconnectionN/SE TL Xingu –Terminal Minas 800 kV (CC – Bipolo 1) PA/SP 800 2,050 1.3
To meet electricity demand growth
TL 230 kV Miranda – Chapadinha II C1 MA 230 140
0.3
TL 230 kV Coelho Neto – Chapadinha II C1 MA 230 78
TL 230 kVVila do Conde -Tomé-Açu C2 PA 230 120
TL 230 kV Imperatriz – Porto Franco C2 MA 230 111
TL 230 kV Ribeiro Gonçalves – Balsas C2 MA 230 95
TL 230 kVTrindade – Firminópolis GO 230 88
Integration of isolated systems TL Rio Branco – Feijó AC 230 357 0.2
TL Feijõ – Cruzeiro do Sul AC 230 300
Total 4,745 2.4
Apresentação do ministro Guido Mantega no Seminário Empresarial Oportunidades em Infraestrutura no Brasil
Apresentação do ministro Guido Mantega no Seminário Empresarial Oportunidades em Infraestrutura no Brasil
Apresentação do ministro Guido Mantega no Seminário Empresarial Oportunidades em Infraestrutura no Brasil
Apresentação do ministro Guido Mantega no Seminário Empresarial Oportunidades em Infraestrutura no Brasil
Apresentação do ministro Guido Mantega no Seminário Empresarial Oportunidades em Infraestrutura no Brasil
Apresentação do ministro Guido Mantega no Seminário Empresarial Oportunidades em Infraestrutura no Brasil
Apresentação do ministro Guido Mantega no Seminário Empresarial Oportunidades em Infraestrutura no Brasil
Apresentação do ministro Guido Mantega no Seminário Empresarial Oportunidades em Infraestrutura no Brasil
Apresentação do ministro Guido Mantega no Seminário Empresarial Oportunidades em Infraestrutura no Brasil
Apresentação do ministro Guido Mantega no Seminário Empresarial Oportunidades em Infraestrutura no Brasil
Apresentação do ministro Guido Mantega no Seminário Empresarial Oportunidades em Infraestrutura no Brasil

Contenu connexe

Tendances

Potential Sectors for Investment in Bangladesh
Potential Sectors for Investment in BangladeshPotential Sectors for Investment in Bangladesh
Potential Sectors for Investment in BangladeshKhan Mohd Eshtiaque
 
Colombia presentation for 2019
Colombia presentation for 2019Colombia presentation for 2019
Colombia presentation for 2019ProColombia
 
D2112228
D2112228D2112228
D2112228aijbm
 
The euromoney-saudi-arabia-conference-2013
The euromoney-saudi-arabia-conference-2013The euromoney-saudi-arabia-conference-2013
The euromoney-saudi-arabia-conference-2013Aranca
 
Reasons Why it is Beneficial to Invest in Republic of Kosovo
Reasons Why it is Beneficial to Invest in Republic of KosovoReasons Why it is Beneficial to Invest in Republic of Kosovo
Reasons Why it is Beneficial to Invest in Republic of Kosovonakije.kida
 
Foreign Direct Investments into Ukraine
Foreign Direct Investments into UkraineForeign Direct Investments into Ukraine
Foreign Direct Investments into UkraineEasyBusiness
 
Fdi growth in india
Fdi growth in indiaFdi growth in india
Fdi growth in indiaAvni Sharma
 
Dr Dev Kambhampati | Doing Business in Brazil - 2013 Country Commercial Guide...
Dr Dev Kambhampati | Doing Business in Brazil - 2013 Country Commercial Guide...Dr Dev Kambhampati | Doing Business in Brazil - 2013 Country Commercial Guide...
Dr Dev Kambhampati | Doing Business in Brazil - 2013 Country Commercial Guide...Dr Dev Kambhampati
 
Colombia presentation 2018
Colombia presentation 2018Colombia presentation 2018
Colombia presentation 2018ProColombia
 
Georgia's Search for Liberty AEI June 2009
Georgia's Search for Liberty AEI June 2009Georgia's Search for Liberty AEI June 2009
Georgia's Search for Liberty AEI June 2009Lado Gurgenidze
 
COLOMBIA Presentation
COLOMBIA Presentation COLOMBIA Presentation
COLOMBIA Presentation ProColombia
 
Colombia Presentation march 2019
Colombia Presentation march 2019Colombia Presentation march 2019
Colombia Presentation march 2019ProColombia
 
Business proposal for Construction industry of UAE
Business proposal for Construction industry of UAEBusiness proposal for Construction industry of UAE
Business proposal for Construction industry of UAEKratiJain53
 
FDI in Argentina-International Business Environment
FDI in Argentina-International Business Environment FDI in Argentina-International Business Environment
FDI in Argentina-International Business Environment Sandeep Patel
 
Impact of Foreign Debt on Economic Growth in Zimbabwe
Impact of Foreign Debt on Economic Growth in ZimbabweImpact of Foreign Debt on Economic Growth in Zimbabwe
Impact of Foreign Debt on Economic Growth in Zimbabweiosrjce
 
Joint Venture in Bangladesh
Joint Venture in BangladeshJoint Venture in Bangladesh
Joint Venture in BangladeshMonir Hossain
 

Tendances (19)

Potential Sectors for Investment in Bangladesh
Potential Sectors for Investment in BangladeshPotential Sectors for Investment in Bangladesh
Potential Sectors for Investment in Bangladesh
 
Colombia presentation for 2019
Colombia presentation for 2019Colombia presentation for 2019
Colombia presentation for 2019
 
D2112228
D2112228D2112228
D2112228
 
Fdi
FdiFdi
Fdi
 
The euromoney-saudi-arabia-conference-2013
The euromoney-saudi-arabia-conference-2013The euromoney-saudi-arabia-conference-2013
The euromoney-saudi-arabia-conference-2013
 
Reasons Why it is Beneficial to Invest in Republic of Kosovo
Reasons Why it is Beneficial to Invest in Republic of KosovoReasons Why it is Beneficial to Invest in Republic of Kosovo
Reasons Why it is Beneficial to Invest in Republic of Kosovo
 
Foreign Direct Investments into Ukraine
Foreign Direct Investments into UkraineForeign Direct Investments into Ukraine
Foreign Direct Investments into Ukraine
 
Fdi growth in india
Fdi growth in indiaFdi growth in india
Fdi growth in india
 
Dr Dev Kambhampati | Doing Business in Brazil - 2013 Country Commercial Guide...
Dr Dev Kambhampati | Doing Business in Brazil - 2013 Country Commercial Guide...Dr Dev Kambhampati | Doing Business in Brazil - 2013 Country Commercial Guide...
Dr Dev Kambhampati | Doing Business in Brazil - 2013 Country Commercial Guide...
 
Colombia presentation 2018
Colombia presentation 2018Colombia presentation 2018
Colombia presentation 2018
 
Georgia's Search for Liberty AEI June 2009
Georgia's Search for Liberty AEI June 2009Georgia's Search for Liberty AEI June 2009
Georgia's Search for Liberty AEI June 2009
 
75 i chronicle
75 i chronicle75 i chronicle
75 i chronicle
 
COLOMBIA Presentation
COLOMBIA Presentation COLOMBIA Presentation
COLOMBIA Presentation
 
Colombia Presentation march 2019
Colombia Presentation march 2019Colombia Presentation march 2019
Colombia Presentation march 2019
 
Country overview
Country overviewCountry overview
Country overview
 
Business proposal for Construction industry of UAE
Business proposal for Construction industry of UAEBusiness proposal for Construction industry of UAE
Business proposal for Construction industry of UAE
 
FDI in Argentina-International Business Environment
FDI in Argentina-International Business Environment FDI in Argentina-International Business Environment
FDI in Argentina-International Business Environment
 
Impact of Foreign Debt on Economic Growth in Zimbabwe
Impact of Foreign Debt on Economic Growth in ZimbabweImpact of Foreign Debt on Economic Growth in Zimbabwe
Impact of Foreign Debt on Economic Growth in Zimbabwe
 
Joint Venture in Bangladesh
Joint Venture in BangladeshJoint Venture in Bangladesh
Joint Venture in Bangladesh
 

Similaire à Apresentação do ministro Guido Mantega no Seminário Empresarial Oportunidades em Infraestrutura no Brasil

February 2013 - No clear view of the future
February 2013 - No clear view of the futureFebruary 2013 - No clear view of the future
February 2013 - No clear view of the futureFGV Brazil
 
EY Attractiveness Report Brazil Capturing The Momentum August 2012
EY Attractiveness Report Brazil Capturing The Momentum August 2012EY Attractiveness Report Brazil Capturing The Momentum August 2012
EY Attractiveness Report Brazil Capturing The Momentum August 2012Stephan Kuester
 
Threats to the development of brazil and how to overcome them
Threats to the development of brazil and how to overcome themThreats to the development of brazil and how to overcome them
Threats to the development of brazil and how to overcome themFernando Alcoforado
 
Lagos real estate investment report Q4 2012 - Q1 2013
Lagos real estate investment report Q4 2012 -  Q1 2013Lagos real estate investment report Q4 2012 -  Q1 2013
Lagos real estate investment report Q4 2012 - Q1 2013Munachi C Okoye
 
Cambodia's outlook brief for 2013 possibilities and policy priorities for s...
Cambodia's outlook brief for 2013   possibilities and policy priorities for s...Cambodia's outlook brief for 2013   possibilities and policy priorities for s...
Cambodia's outlook brief for 2013 possibilities and policy priorities for s...Solina Yean
 
Saudi Arabia on the Move - An Aranca Special Report 2013
Saudi Arabia on the Move - An Aranca Special Report 2013Saudi Arabia on the Move - An Aranca Special Report 2013
Saudi Arabia on the Move - An Aranca Special Report 2013Srinivas Macha
 
2018 Nigeria Real Estate Market Outlook
2018 Nigeria Real Estate Market Outlook2018 Nigeria Real Estate Market Outlook
2018 Nigeria Real Estate Market OutlookAyo Ibaru
 
Cooperation between Bangladesh and Canada
Cooperation between Bangladesh and CanadaCooperation between Bangladesh and Canada
Cooperation between Bangladesh and CanadaMohammad Monir Hossan
 
Cooperation between Bangladesh and Canada
Cooperation between Bangladesh and CanadaCooperation between Bangladesh and Canada
Cooperation between Bangladesh and CanadaMohammad Monir Hossan
 
January 2013 - Rio’s state and city family grant model
January 2013 - Rio’s state and city family grant modelJanuary 2013 - Rio’s state and city family grant model
January 2013 - Rio’s state and city family grant modelFGV Brazil
 
The impact of covid-19 in Bangladesh a case study on economic sector
The impact of covid-19 in Bangladesh a case study on economic sectorThe impact of covid-19 in Bangladesh a case study on economic sector
The impact of covid-19 in Bangladesh a case study on economic sectorShaksly Snail
 
Official EIBTM 2013 Trends Watch Report by Rob Davidson
Official EIBTM 2013 Trends Watch Report by Rob DavidsonOfficial EIBTM 2013 Trends Watch Report by Rob Davidson
Official EIBTM 2013 Trends Watch Report by Rob DavidsonRob Davidson
 
The prospects and challenges of Bangladesh Economy
The prospects and challenges of Bangladesh EconomyThe prospects and challenges of Bangladesh Economy
The prospects and challenges of Bangladesh EconomyMohammad Monir Hossan
 
Bangladesh Economy: Prospects & Challenges
Bangladesh Economy: Prospects & ChallengesBangladesh Economy: Prospects & Challenges
Bangladesh Economy: Prospects & ChallengesMohammad Monir Hossan
 
External and internal economic vulnerabilities of brazilian economy and how ...
External and internal  economic vulnerabilities of brazilian economy and how ...External and internal  economic vulnerabilities of brazilian economy and how ...
External and internal economic vulnerabilities of brazilian economy and how ...Fernando Alcoforado
 
Whither “7 Percent Club” of Economies - A Review of FY2012 and Outlook for FY...
Whither “7 Percent Club” of Economies - A Review of FY2012 and Outlook for FY...Whither “7 Percent Club” of Economies - A Review of FY2012 and Outlook for FY...
Whither “7 Percent Club” of Economies - A Review of FY2012 and Outlook for FY...The Growth Institute
 

Similaire à Apresentação do ministro Guido Mantega no Seminário Empresarial Oportunidades em Infraestrutura no Brasil (20)

Brazil's Economic Outlook and Infrastructure Investment Opportunities
Brazil's Economic Outlook and Infrastructure Investment OpportunitiesBrazil's Economic Outlook and Infrastructure Investment Opportunities
Brazil's Economic Outlook and Infrastructure Investment Opportunities
 
Brazilian Economic Outlook | 17 Edition (Dec/2012)
Brazilian Economic Outlook | 17 Edition (Dec/2012)Brazilian Economic Outlook | 17 Edition (Dec/2012)
Brazilian Economic Outlook | 17 Edition (Dec/2012)
 
February 2013 - No clear view of the future
February 2013 - No clear view of the futureFebruary 2013 - No clear view of the future
February 2013 - No clear view of the future
 
EY Attractiveness Report Brazil Capturing The Momentum August 2012
EY Attractiveness Report Brazil Capturing The Momentum August 2012EY Attractiveness Report Brazil Capturing The Momentum August 2012
EY Attractiveness Report Brazil Capturing The Momentum August 2012
 
Vidhu assignment
Vidhu assignmentVidhu assignment
Vidhu assignment
 
Threats to the development of brazil and how to overcome them
Threats to the development of brazil and how to overcome themThreats to the development of brazil and how to overcome them
Threats to the development of brazil and how to overcome them
 
Lagos real estate investment report Q4 2012 - Q1 2013
Lagos real estate investment report Q4 2012 -  Q1 2013Lagos real estate investment report Q4 2012 -  Q1 2013
Lagos real estate investment report Q4 2012 - Q1 2013
 
Cambodia's outlook brief for 2013 possibilities and policy priorities for s...
Cambodia's outlook brief for 2013   possibilities and policy priorities for s...Cambodia's outlook brief for 2013   possibilities and policy priorities for s...
Cambodia's outlook brief for 2013 possibilities and policy priorities for s...
 
Saudi Arabia on the Move - An Aranca Special Report 2013
Saudi Arabia on the Move - An Aranca Special Report 2013Saudi Arabia on the Move - An Aranca Special Report 2013
Saudi Arabia on the Move - An Aranca Special Report 2013
 
2018 Nigeria Real Estate Market Outlook
2018 Nigeria Real Estate Market Outlook2018 Nigeria Real Estate Market Outlook
2018 Nigeria Real Estate Market Outlook
 
Cooperation between Bangladesh and Canada
Cooperation between Bangladesh and CanadaCooperation between Bangladesh and Canada
Cooperation between Bangladesh and Canada
 
Cooperation between Bangladesh and Canada
Cooperation between Bangladesh and CanadaCooperation between Bangladesh and Canada
Cooperation between Bangladesh and Canada
 
January 2013 - Rio’s state and city family grant model
January 2013 - Rio’s state and city family grant modelJanuary 2013 - Rio’s state and city family grant model
January 2013 - Rio’s state and city family grant model
 
The impact of covid-19 in Bangladesh a case study on economic sector
The impact of covid-19 in Bangladesh a case study on economic sectorThe impact of covid-19 in Bangladesh a case study on economic sector
The impact of covid-19 in Bangladesh a case study on economic sector
 
Fdi brazil
Fdi  brazilFdi  brazil
Fdi brazil
 
Official EIBTM 2013 Trends Watch Report by Rob Davidson
Official EIBTM 2013 Trends Watch Report by Rob DavidsonOfficial EIBTM 2013 Trends Watch Report by Rob Davidson
Official EIBTM 2013 Trends Watch Report by Rob Davidson
 
The prospects and challenges of Bangladesh Economy
The prospects and challenges of Bangladesh EconomyThe prospects and challenges of Bangladesh Economy
The prospects and challenges of Bangladesh Economy
 
Bangladesh Economy: Prospects & Challenges
Bangladesh Economy: Prospects & ChallengesBangladesh Economy: Prospects & Challenges
Bangladesh Economy: Prospects & Challenges
 
External and internal economic vulnerabilities of brazilian economy and how ...
External and internal  economic vulnerabilities of brazilian economy and how ...External and internal  economic vulnerabilities of brazilian economy and how ...
External and internal economic vulnerabilities of brazilian economy and how ...
 
Whither “7 Percent Club” of Economies - A Review of FY2012 and Outlook for FY...
Whither “7 Percent Club” of Economies - A Review of FY2012 and Outlook for FY...Whither “7 Percent Club” of Economies - A Review of FY2012 and Outlook for FY...
Whither “7 Percent Club” of Economies - A Review of FY2012 and Outlook for FY...
 

Plus de Palácio do Planalto

Proposta de Política Nacional de Educação em Tempo Integral
Proposta de Política Nacional de Educação em Tempo IntegralProposta de Política Nacional de Educação em Tempo Integral
Proposta de Política Nacional de Educação em Tempo IntegralPalácio do Planalto
 
Novo Ensino Médio - Escolas em Tempo Integral
Novo Ensino Médio -  Escolas em Tempo IntegralNovo Ensino Médio -  Escolas em Tempo Integral
Novo Ensino Médio - Escolas em Tempo IntegralPalácio do Planalto
 
Plano Safra da Agricultura Familiar 2016/17
Plano Safra da Agricultura Familiar 2016/17Plano Safra da Agricultura Familiar 2016/17
Plano Safra da Agricultura Familiar 2016/17Palácio do Planalto
 
Defesa da presidenta Dilma Rousseff apresentada por José Eduardo Cardozo na C...
Defesa da presidenta Dilma Rousseff apresentada por José Eduardo Cardozo na C...Defesa da presidenta Dilma Rousseff apresentada por José Eduardo Cardozo na C...
Defesa da presidenta Dilma Rousseff apresentada por José Eduardo Cardozo na C...Palácio do Planalto
 
Manifesto das Defensoras e Defensores Públicos Brasileiros em Defesa do Estad...
Manifesto das Defensoras e Defensores Públicos Brasileiros em Defesa do Estad...Manifesto das Defensoras e Defensores Públicos Brasileiros em Defesa do Estad...
Manifesto das Defensoras e Defensores Públicos Brasileiros em Defesa do Estad...Palácio do Planalto
 
Manifesto da Advocacia Pernambucana pela Democracia
Manifesto da Advocacia Pernambucana pela DemocraciaManifesto da Advocacia Pernambucana pela Democracia
Manifesto da Advocacia Pernambucana pela DemocraciaPalácio do Planalto
 
Manifesto das Advogadas e Advogados Capizabas pela Democracia
Manifesto das Advogadas e Advogados Capizabas pela DemocraciaManifesto das Advogadas e Advogados Capizabas pela Democracia
Manifesto das Advogadas e Advogados Capizabas pela DemocraciaPalácio do Planalto
 
Manifesto das Professoras e Professores, Técnicas e Técnicos e Alunas e Aluno...
Manifesto das Professoras e Professores, Técnicas e Técnicos e Alunas e Aluno...Manifesto das Professoras e Professores, Técnicas e Técnicos e Alunas e Aluno...
Manifesto das Professoras e Professores, Técnicas e Técnicos e Alunas e Aluno...Palácio do Planalto
 
Nota pública da Associação | Advogadas e Advogados Públicos para a Democracia...
Nota pública da Associação | Advogadas e Advogados Públicos para a Democracia...Nota pública da Associação | Advogadas e Advogados Públicos para a Democracia...
Nota pública da Associação | Advogadas e Advogados Públicos para a Democracia...Palácio do Planalto
 
Manifesto dos Advogados e Advogadas pela Democracia, Justiça e Cidadania (ADJC)
Manifesto dos Advogados e Advogadas pela Democracia, Justiça e Cidadania (ADJC)Manifesto dos Advogados e Advogadas pela Democracia, Justiça e Cidadania (ADJC)
Manifesto dos Advogados e Advogadas pela Democracia, Justiça e Cidadania (ADJC)Palácio do Planalto
 
Nota de repúdio a decisão do Conselho Federal da OAB em favor do impeachment ...
Nota de repúdio a decisão do Conselho Federal da OAB em favor do impeachment ...Nota de repúdio a decisão do Conselho Federal da OAB em favor do impeachment ...
Nota de repúdio a decisão do Conselho Federal da OAB em favor do impeachment ...Palácio do Planalto
 
Manifesto da Rede Nacional de Advogadas e Advogados Populares-RENAP e a Artic...
Manifesto da Rede Nacional de Advogadas e Advogados Populares-RENAP e a Artic...Manifesto da Rede Nacional de Advogadas e Advogados Populares-RENAP e a Artic...
Manifesto da Rede Nacional de Advogadas e Advogados Populares-RENAP e a Artic...Palácio do Planalto
 
Manifesto em defesa da ordem jurídica e da democracia
Manifesto em defesa da ordem jurídica e da democraciaManifesto em defesa da ordem jurídica e da democracia
Manifesto em defesa da ordem jurídica e da democraciaPalácio do Planalto
 
Nota Pública: Não se combate corrupção corrompendo a Constituição
Nota Pública: Não se combate corrupção corrompendo a ConstituiçãoNota Pública: Não se combate corrupção corrompendo a Constituição
Nota Pública: Não se combate corrupção corrompendo a ConstituiçãoPalácio do Planalto
 

Plus de Palácio do Planalto (20)

Proposta de Política Nacional de Educação em Tempo Integral
Proposta de Política Nacional de Educação em Tempo IntegralProposta de Política Nacional de Educação em Tempo Integral
Proposta de Política Nacional de Educação em Tempo Integral
 
Novo Ensino Médio - Escolas em Tempo Integral
Novo Ensino Médio -  Escolas em Tempo IntegralNovo Ensino Médio -  Escolas em Tempo Integral
Novo Ensino Médio - Escolas em Tempo Integral
 
30 dias de governo Temer
30 dias de governo Temer30 dias de governo Temer
30 dias de governo Temer
 
Meta Fiscal
Meta FiscalMeta Fiscal
Meta Fiscal
 
Plano Safra da Agricultura Familiar 2016/17
Plano Safra da Agricultura Familiar 2016/17Plano Safra da Agricultura Familiar 2016/17
Plano Safra da Agricultura Familiar 2016/17
 
Apresentação - Mais Médicos
Apresentação - Mais MédicosApresentação - Mais Médicos
Apresentação - Mais Médicos
 
Hora do Enem
Hora do EnemHora do Enem
Hora do Enem
 
Defesa da presidenta Dilma Rousseff apresentada por José Eduardo Cardozo na C...
Defesa da presidenta Dilma Rousseff apresentada por José Eduardo Cardozo na C...Defesa da presidenta Dilma Rousseff apresentada por José Eduardo Cardozo na C...
Defesa da presidenta Dilma Rousseff apresentada por José Eduardo Cardozo na C...
 
Minha Casa Minha Vida 3
Minha Casa Minha Vida 3Minha Casa Minha Vida 3
Minha Casa Minha Vida 3
 
Manifesto das Defensoras e Defensores Públicos Brasileiros em Defesa do Estad...
Manifesto das Defensoras e Defensores Públicos Brasileiros em Defesa do Estad...Manifesto das Defensoras e Defensores Públicos Brasileiros em Defesa do Estad...
Manifesto das Defensoras e Defensores Públicos Brasileiros em Defesa do Estad...
 
Manifesto da Advocacia Pernambucana pela Democracia
Manifesto da Advocacia Pernambucana pela DemocraciaManifesto da Advocacia Pernambucana pela Democracia
Manifesto da Advocacia Pernambucana pela Democracia
 
Manifesto das Advogadas e Advogados Capizabas pela Democracia
Manifesto das Advogadas e Advogados Capizabas pela DemocraciaManifesto das Advogadas e Advogados Capizabas pela Democracia
Manifesto das Advogadas e Advogados Capizabas pela Democracia
 
Manifesto das Professoras e Professores, Técnicas e Técnicos e Alunas e Aluno...
Manifesto das Professoras e Professores, Técnicas e Técnicos e Alunas e Aluno...Manifesto das Professoras e Professores, Técnicas e Técnicos e Alunas e Aluno...
Manifesto das Professoras e Professores, Técnicas e Técnicos e Alunas e Aluno...
 
Nota pública da Associação | Advogadas e Advogados Públicos para a Democracia...
Nota pública da Associação | Advogadas e Advogados Públicos para a Democracia...Nota pública da Associação | Advogadas e Advogados Públicos para a Democracia...
Nota pública da Associação | Advogadas e Advogados Públicos para a Democracia...
 
Manifesto dos Advogados e Advogadas pela Democracia, Justiça e Cidadania (ADJC)
Manifesto dos Advogados e Advogadas pela Democracia, Justiça e Cidadania (ADJC)Manifesto dos Advogados e Advogadas pela Democracia, Justiça e Cidadania (ADJC)
Manifesto dos Advogados e Advogadas pela Democracia, Justiça e Cidadania (ADJC)
 
Nota de repúdio a decisão do Conselho Federal da OAB em favor do impeachment ...
Nota de repúdio a decisão do Conselho Federal da OAB em favor do impeachment ...Nota de repúdio a decisão do Conselho Federal da OAB em favor do impeachment ...
Nota de repúdio a decisão do Conselho Federal da OAB em favor do impeachment ...
 
Manifesto da OAB Federal
Manifesto da OAB FederalManifesto da OAB Federal
Manifesto da OAB Federal
 
Manifesto da Rede Nacional de Advogadas e Advogados Populares-RENAP e a Artic...
Manifesto da Rede Nacional de Advogadas e Advogados Populares-RENAP e a Artic...Manifesto da Rede Nacional de Advogadas e Advogados Populares-RENAP e a Artic...
Manifesto da Rede Nacional de Advogadas e Advogados Populares-RENAP e a Artic...
 
Manifesto em defesa da ordem jurídica e da democracia
Manifesto em defesa da ordem jurídica e da democraciaManifesto em defesa da ordem jurídica e da democracia
Manifesto em defesa da ordem jurídica e da democracia
 
Nota Pública: Não se combate corrupção corrompendo a Constituição
Nota Pública: Não se combate corrupção corrompendo a ConstituiçãoNota Pública: Não se combate corrupção corrompendo a Constituição
Nota Pública: Não se combate corrupção corrompendo a Constituição
 

Dernier

NO1 Certified Amil Baba In Lahore Kala Jadu In Lahore Best Amil In Lahore Ami...
NO1 Certified Amil Baba In Lahore Kala Jadu In Lahore Best Amil In Lahore Ami...NO1 Certified Amil Baba In Lahore Kala Jadu In Lahore Best Amil In Lahore Ami...
NO1 Certified Amil Baba In Lahore Kala Jadu In Lahore Best Amil In Lahore Ami...Amil baba
 
《加拿大本地办假证-寻找办理Dalhousie毕业证和达尔豪斯大学毕业证书的中介代理》
《加拿大本地办假证-寻找办理Dalhousie毕业证和达尔豪斯大学毕业证书的中介代理》《加拿大本地办假证-寻找办理Dalhousie毕业证和达尔豪斯大学毕业证书的中介代理》
《加拿大本地办假证-寻找办理Dalhousie毕业证和达尔豪斯大学毕业证书的中介代理》rnrncn29
 
Economic Risk Factor Update: April 2024 [SlideShare]
Economic Risk Factor Update: April 2024 [SlideShare]Economic Risk Factor Update: April 2024 [SlideShare]
Economic Risk Factor Update: April 2024 [SlideShare]Commonwealth
 
project management information system lecture notes
project management information system lecture notesproject management information system lecture notes
project management information system lecture notesongomchris
 
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...Amil baba
 
Unveiling Business Expansion Trends in 2024
Unveiling Business Expansion Trends in 2024Unveiling Business Expansion Trends in 2024
Unveiling Business Expansion Trends in 2024Champak Jhagmag
 
Overview of Inkel Unlisted Shares Price.
Overview of Inkel Unlisted Shares Price.Overview of Inkel Unlisted Shares Price.
Overview of Inkel Unlisted Shares Price.Precize Formely Leadoff
 
AnyConv.com__FSS Advance Retail & Distribution - 15.06.17.ppt
AnyConv.com__FSS Advance Retail & Distribution - 15.06.17.pptAnyConv.com__FSS Advance Retail & Distribution - 15.06.17.ppt
AnyConv.com__FSS Advance Retail & Distribution - 15.06.17.pptPriyankaSharma89719
 
Stock Market Brief Deck for "this does not happen often".pdf
Stock Market Brief Deck for "this does not happen often".pdfStock Market Brief Deck for "this does not happen often".pdf
Stock Market Brief Deck for "this does not happen often".pdfMichael Silva
 
2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGecko2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGeckoCoinGecko
 
Economics, Commerce and Trade Management: An International Journal (ECTIJ)
Economics, Commerce and Trade Management: An International Journal (ECTIJ)Economics, Commerce and Trade Management: An International Journal (ECTIJ)
Economics, Commerce and Trade Management: An International Journal (ECTIJ)ECTIJ
 
Bladex 1Q24 Earning Results Presentation
Bladex 1Q24 Earning Results PresentationBladex 1Q24 Earning Results Presentation
Bladex 1Q24 Earning Results PresentationBladex
 
Role of Information and technology in banking and finance .pptx
Role of Information and technology in banking and finance .pptxRole of Information and technology in banking and finance .pptx
Role of Information and technology in banking and finance .pptxNarayaniTripathi2
 
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACTGOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACTharshitverma1762
 
The Inspirational Story of Julio Herrera Velutini - Global Finance Leader
The Inspirational Story of Julio Herrera Velutini - Global Finance LeaderThe Inspirational Story of Julio Herrera Velutini - Global Finance Leader
The Inspirational Story of Julio Herrera Velutini - Global Finance LeaderArianna Varetto
 
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...Henry Tapper
 
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdfBPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdfHenry Tapper
 
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办fqiuho152
 
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证jdkhjh
 

Dernier (20)

NO1 Certified Amil Baba In Lahore Kala Jadu In Lahore Best Amil In Lahore Ami...
NO1 Certified Amil Baba In Lahore Kala Jadu In Lahore Best Amil In Lahore Ami...NO1 Certified Amil Baba In Lahore Kala Jadu In Lahore Best Amil In Lahore Ami...
NO1 Certified Amil Baba In Lahore Kala Jadu In Lahore Best Amil In Lahore Ami...
 
《加拿大本地办假证-寻找办理Dalhousie毕业证和达尔豪斯大学毕业证书的中介代理》
《加拿大本地办假证-寻找办理Dalhousie毕业证和达尔豪斯大学毕业证书的中介代理》《加拿大本地办假证-寻找办理Dalhousie毕业证和达尔豪斯大学毕业证书的中介代理》
《加拿大本地办假证-寻找办理Dalhousie毕业证和达尔豪斯大学毕业证书的中介代理》
 
Economic Risk Factor Update: April 2024 [SlideShare]
Economic Risk Factor Update: April 2024 [SlideShare]Economic Risk Factor Update: April 2024 [SlideShare]
Economic Risk Factor Update: April 2024 [SlideShare]
 
project management information system lecture notes
project management information system lecture notesproject management information system lecture notes
project management information system lecture notes
 
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
 
Unveiling Business Expansion Trends in 2024
Unveiling Business Expansion Trends in 2024Unveiling Business Expansion Trends in 2024
Unveiling Business Expansion Trends in 2024
 
Overview of Inkel Unlisted Shares Price.
Overview of Inkel Unlisted Shares Price.Overview of Inkel Unlisted Shares Price.
Overview of Inkel Unlisted Shares Price.
 
AnyConv.com__FSS Advance Retail & Distribution - 15.06.17.ppt
AnyConv.com__FSS Advance Retail & Distribution - 15.06.17.pptAnyConv.com__FSS Advance Retail & Distribution - 15.06.17.ppt
AnyConv.com__FSS Advance Retail & Distribution - 15.06.17.ppt
 
Stock Market Brief Deck for "this does not happen often".pdf
Stock Market Brief Deck for "this does not happen often".pdfStock Market Brief Deck for "this does not happen often".pdf
Stock Market Brief Deck for "this does not happen often".pdf
 
Q1 2024 Newsletter | Financial Synergies Wealth Advisors
Q1 2024 Newsletter | Financial Synergies Wealth AdvisorsQ1 2024 Newsletter | Financial Synergies Wealth Advisors
Q1 2024 Newsletter | Financial Synergies Wealth Advisors
 
2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGecko2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGecko
 
Economics, Commerce and Trade Management: An International Journal (ECTIJ)
Economics, Commerce and Trade Management: An International Journal (ECTIJ)Economics, Commerce and Trade Management: An International Journal (ECTIJ)
Economics, Commerce and Trade Management: An International Journal (ECTIJ)
 
Bladex 1Q24 Earning Results Presentation
Bladex 1Q24 Earning Results PresentationBladex 1Q24 Earning Results Presentation
Bladex 1Q24 Earning Results Presentation
 
Role of Information and technology in banking and finance .pptx
Role of Information and technology in banking and finance .pptxRole of Information and technology in banking and finance .pptx
Role of Information and technology in banking and finance .pptx
 
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACTGOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
 
The Inspirational Story of Julio Herrera Velutini - Global Finance Leader
The Inspirational Story of Julio Herrera Velutini - Global Finance LeaderThe Inspirational Story of Julio Herrera Velutini - Global Finance Leader
The Inspirational Story of Julio Herrera Velutini - Global Finance Leader
 
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
 
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdfBPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
 
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
 
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
 

Apresentação do ministro Guido Mantega no Seminário Empresarial Oportunidades em Infraestrutura no Brasil

  • 1. September | 2013 Ministry of Finance B R A Z I L I A N G O V E R N M E N T Brazil’seconomic outlook and investment opportunities infrastructure
  • 2.
  • 3. 3 Ministry of Finance Foreword Economic Outlook Economic Development and Demand for Infrastructure Capital Market Instruments Highways Railways Ports Airports Oil and Gas Electricity Appendix – Main types of business organizations in Brazil Useful Links Glossary Summary 5 7 33 45 53 65 79 83 93 101 121 126 128
  • 4.
  • 5. 5 Ministry of Finance 5 Foreword Foreword Brazil currently presents an enormous opportunity for investment in infrastructure. The Brazilian economy has changed substantially over the last ten years. From 2003 to 2012, real GDP increased by 41 percent, real total wages by 65 percent and domestic retail sales by 119 percent. It was a period of consolidation for the domestic market, based on income growth and social inclusion. The country is currently among the biggest markets in the world. In the last decade, investments grew by 71 percent, above GDP growth rates, but they should increase even further in order to become the new engine of economic development. Eonomic growth has brought about challenges, particularly for the long term. Above all, Brazil needs to build up and modernize its infrastructure.That is the reason why President Dilma Rousseff launched the Energy and Logistics Investment Program in 2012, consisting of concessions for highways (7,500 km), railways (10,000 km), airports (Rio de Janeiro and Belo Horizonte) and ports.The implementation of the Program will not only reduce costs and improve competitiveness for all industries, but also keep Brazil on the sustainable growth path that has been a characteristic of the Brazilian economy over the last decade. In oil and gas, the 11th Bidding Round in May 2013 was very successful, and both the 12th Bidding Round and the 1st Round of the Pre-Salt Layer are scheduled for the end of 2013. In electricity, many auctions are being carried out until2017forthegenerationof33,000MW(fromhydropower,windpowerandothersources)andtheinstallationof 21,000 km of transmission lines. As far as short term perspectives are concerned, Brazil resumed economic growth in 2013, after a small period of deceleration due to the deepening of the international crisis. In the second quarter, GDP grew 6.0 percent (quarter- over-quarter, seasonally adjusted annual rate), one of the highest rates among G20 countries. The sustainability of the economic recovery is supported by high levels of investment, which increased 9.0 percent in the second quarter
  • 6. 6 Ministry of Finance 6 Foreword of 2013 when compared to the second quarter of 2012. Furthermore, manufacturing shows signs of improvement, after two years of difficulties brought about by the international crisis. The outlook for the world economy, however, remains tenuous. Although there are signs of economic recovery in developed countries, with demand picking up in some advanced countries, the turmoil created by the expectation of tapering in U.S. monetary stimulus severely affected some emerging economies. World trade growth is still disappointing, posing challenges for economies heavily dependent on foreign markets. The Brazilian economy is prepared to face the challenges posed by the international economy. In addition to its considerable size – 200 million people, mostly belonging to the middle social classes –, the domestic market has beengrowing atanannualrateofover6percent inthelastfiveyears.Brazil’sbanksandfinancialmarketsareamong the soundest and most dynamic in the world. International reserves of around US$ 370 billion vis-à-vis short term foreigndebtofUS$40billiongivemonetaryauthoritiesthecapacitytointerveneifnecessary.In2012, foreigndirect investmentinflowstoBrazilwereUS$65.3billion,thefourthlargestintheworld.Inthefirsthalfof2013,FDIinflows amounted to US$ 30 billion. After a decade of consolidation of the domestic market, Brazil is ready for another decade of growth, now supported by investments, particularly in infrastructure. Private businesses and investors, both domestic and foreign, have the opportunity to take part in this process.
  • 8. 8 Ministry of Finance 8 EconomicOutlook GDP, QoQ seasonally adjusted annual rate, in % change, second quarter 2013 The world economy in the second quarter of 2013 Source:InternationalMonetaryFund (IMF)andBloomberg Producedby:MinistryofFinance Above 3% Below or equal to 3% Brazil Chile Russia India China Indonesia 5.6 South Korea4.5 Mexico 3.8 Canadá Japan United kingdom Italy -1.2 -1.0 2.9 2.3 France -1.3 -2.9 1.9 Germany 2.9 South Africa Australia USA Canada 1.7 2.5 2.0 6.0 7.0 8.5 Turkey 2.4 Euro area 1.2 3.0
  • 9. 9 Ministry of Finance 9 EconomicOutlook Purchasing Managers Index (PMI), manufacturing, in points Slow recovery of advanced economies and China Source:ISM(forUSA)andHSBC/Markit Producedby:MinistryofFinance 40 42 44 46 48 50 52 54 56 58 60 Sep 2013 Jan 2013 Jul2012 Jan 2012 Jul2011 Jan 2011 Jul2010 Jan 2010 Aug 2009 USA Euro Zone China 51.2 51.1 55.7
  • 10. 10 Ministry of Finance 10 EconomicOutlook 10-Year U.S.Treasury yields, in % per annum Uncertainty about the tapering of the FED monetary stimulus may trigger exchange-rate and financial volatility in emerging countries. United States recovery: a double-edged sword Source:Bloomberg Producedby:MinistryofFinance 2.69 1.0 1.5 2.0 2.5 3.0 3.5 4.0 18 Sep 2013 Jan 2013 Jan 2012 Jan 2011
  • 11. 11 Ministry of Finance 11 EconomicOutlook Nominal exchange rate, in U.S. dollar/national currency, index (January 2007 = 100) The long term appreciation of the Brazilian real has been partially reversed in 2013 Source:Bloomberg Producedby:MinistryofFinance 60 90 120 150 17 Sep 2013 Jan 2013 Jan 2012 Jan 2011 Jan 2010 Jan 2009 Jan 2008 Jan 2007 94.1 69.7 70.8 72.9 85.8 Brazil South Africa Mexico India Turkey
  • 12. 12 Ministry of Finance 12 EconomicOutlook In US$ million Volatility did not affect the capital account of the balance of payments *CentralBankofBrazilestimate Source:CentralBankofBrazil Producedby:MinistryofFinance 2012 2013 2013 July Jan-July July Jan-July Estimate* Current Account -3,746 -28,990 -9,018 -52,472 -75,000 Financial Account 8,307 53,580 9,315 58,902 83,000 Direct Investment (net) 7,509 42,240 4,019 41,259 FDI 8,440 38,169 5,212 35,239 65,000 Portfolio Investment 1,343 3,707 3,898 17,981 Other Investments -588 7,537 1,418 -437
  • 13. 13 Ministry of Finance 13 EconomicOutlook Foreign direct investment in G-20 countries, 2012, in US$ billion Confidence: high inflows of foreign direct investment Source:UNCTAD Producedby:MinistryofFinance 0 50 100 150 200 Japan South Africa Germ any Italy Korea Saudi Arabia Turkey M exico Indonesia France India Canada Russian Federation Australia United Kingdom Brazil China United States167.6 121.1 65.3 62.4 57.0 51.4 45.4 25.5 25.1 19.9 12.7 12.4 12.2 9.9 9.6 6.6 4.6 1.7
  • 14. 14 Ministry of Finance 14 EconomicOutlook Public sector net debt and General government gross debt, in % of GDP Public sector net debt drops consistently and stable gross debt *July2013 Source:CentralBankofBrazil Producedby:MinistryofFinance 30 35 40 45 50 55 60 65 2013* 2012 2011 2010 2009 2008 2007 2006 2005 2004 2003 2002 60.4 54.8 50.6 48.4 47.3 45.5 38.5 42.1 39.2 36.4 35.2 34.1 Public Sector Net Debt General Government Gross Debt 56.4 58.0 57.4 60.9 54.2 58.7 59.4 53.4
  • 15. 15 Ministry of Finance 15 EconomicOutlook International reserves, in US$ billion (July 2013) Brazil’s international reserves in a comfortable situation *June2013 **May2013 ***January2013 Source:Bloomberg Producedby:MinistryofFinance 0 300 600 900 1,200 3,500 Italy ** South Africa Australia ** France ** United Kingdom * Germ any ** Indonesia Turkey Canada M exico India Korea Brazil Russia *** SaudiArabia ** Japan China * 252 168 106 104 93 72 62 56 46 39 36 480 3,497 1,188 685 374 330
  • 16. 16 Ministry of Finance 16 EconomicOutlook Reserves-to-imports of goods ratio, in %, July 2013 Brazil’s international reserves 58% above annual imports *August2013 **June2013 Source:Bloomberg Producedby:MinistryofFinance 0 50 100 150 200 Turkey SouthAfrica M exico Indonesia India Russia ** Brazil* China **185% 158% 150% 56% 49% 44% 43% 42%
  • 17. 17 Ministry of Finance 17 EconomicOutlook Reserves-to-short term external debt ratio, in %, March 2013 Brazil’s international reserves much above external debt levels Source:BloombergandInternational MonetaryFund(IMF) Producedby:MinistryofFinance 0 200 400 600 800 1,000 Turkey Argentina South Africa M exico Indonesia India China Russia Brazil 952% 572% 462% 303% 232% 229% 167% 108% 92%
  • 18. 18 Ministry of Finance 18 EconomicOutlook International reserves, in US$ billion Brazil’s international reserves have not been changed even under international uncertainty Source:CentralBankofBrazil Producedby:MinistryofFinance 300 325 350 375 400 12 Sep 2013 Aug 2013 Jul2013 Jun 2013 M ay 2013 Apr2013 M ar2013 Feb 2013 Jan 2013 US$ 373.6 bn
  • 19. 19 Ministry of Finance 19 EconomicOutlook In billions of U.S. dollars and millions of contracts The role of derivatives in Brazil: second largest market for interest-rate options and futures *ForBrazil,indicatorsonlyinclude futuresandoptionsoperations ** InChina,currencyderivativesarenot traded(FXrestriction) ***TurkdexAnnualMarket Statistics(AnnualFactBook2012) Source:WorldFederationofExchanges Producedby:MinistryofFinance 0 5,000 10,000 15,000 20,000 25,000 30,000 Turkey*** South Africa Russia M exico Brazil* 25,212 241 58 38 0 Financial volume traded in 2012 (US$ billion) Number of contracts traded in 2012 (millions) Brazil / BVMF* 25,212 501 Mexico /Mexder 241 31 Russia / Moscow Ex 58 21 South Africa / JSE 38 3 Singapore / SGX 0 1 India / NSE-BSE-MCX 0 0 Malaysia / Bursa Malaysia 0 0 China** 0 0 Turkey*** 0 0 US$ Billion
  • 20. 20 Ministry of Finance 20 EconomicOutlook In billions of U.S. dollars and millions of contracts Sixth largest market for currency options and futures *ForBrazil,indicatorsonlyinclude futuresandoptionsoperations ** InChina,currencyderivatives arenottraded(FXrestriction) ***TurkdexAnnualMarket Statistics(AnnualFactBook2012) Source:WorldFederationofExchanges /FuturesIndustryAssociationMagazine March2013 Producedby:MinistryofFinance 0 1,000 2,000 3,000 4,000 5,000 Turkey *** South Africa M éxico Russia India Brazil*4,525 821 437 100 15 13 US$ BillionCurrency Options and Futures Country Financial volume traded in 2012 (US$ billion) Number of contracts (in millions) traded in the same basis (if contracts were all of USD 1,000) Brazil / BVMF* 4,525 4,727 India / NSE-BSE-MCX 821 868 Russia / Moscow Ex 437 413 South Africa / JSE 15 17 Mexico /Mexder 100 98 Turkey /Turkdex *** 13 1 Malaysia / Bursa Malaysia 0 - China ** 0 - Singapore / SGX 0 -
  • 21. 21 Ministry of Finance 21 EconomicOutlook Foreign exchange derivative transactions over spot transactions, in % In Brazil, the large market for foreign exchange derivatives stimulates companies to use currency hedging Source:BankforInternational Settlements(BIS) Producedby:MinistryofFinance 0 50 100 150 200 250 300 350 400 450 Japan Russia Australia Euro M exico Canada Global United States United Kingdom South Africa Korea India China Turkey Brazil419% 347% 252% 247% 231% 207% 178% 175% 161% 161% 138% 137% 136% 134% 101%
  • 22. 22 Ministry of Finance 22 EconomicOutlook Current account, in % of GDP, second quarter of 2013 G20 emerging markets external sector *Firstquarter2013 **Excludingtheoilaccount,the Braziliancurrentaccountdeficitwould be1.9%ofGDP.Therewasatemporary delayintheregisterofthe2012 importsandtherewereseveralstops formaintenanceinPetrobrasplatforms. Additionally,delaysinthestartofnew producingsystemsinthelastfewyears andexistingproblemsinthepost-salt systemsresultedinaslowdowninthe domesticextractionofoilandgassince 2010.Allthesefactorsthatinterfered intheBraziliantradebalancewillstart toimprovesignificantlyinthesecond halfof2013.Tennewplatformswillbe startingoperationsin2013/2014,and severalotherswillstartoperationsin thefollowingyears,doublingproduction until2020,accordingtoEIAestimate Source:Bloomberg Producedby:MinistryofFinance -7 -6 -5 -4 -3 -2 -1 0 1 2 3 4 -5.9 Turkey* South Africa* India* Indonesia Brazil M exico China Russia* 3.0 2.4 -1.3 -3.2 -3.3 -5.1 -5.8 -5.9 -1.9**
  • 23. 23 Ministry of Finance 23 EconomicOutlook Trade balance, total and ex-oil, in US$ billion Oil and gasoline accounted for a large part of the decrease in trade surplus *Ona12-monthbasisuptoJuly2013 Source:MinistryofDevelopment, IndustryandTrade(MDIC) Producedby:MinistryofFinance 0 10 20 30 40 2013* 2012 2011 2010 2009 12.5 19.5 26.2 26.0 19.325.3 20.2 29.8 19.4 4.5 Total balance ex-oil and other oil products Total balance
  • 24. 24 Ministry of Finance 24 EconomicOutlook Gross fixed capital formation, seasonally adjusted, in % QoQ Despite difficulties, investments are recovering in Brazil Source:BrazilianInstituteofGeography andStatistics(IBGE) Producedby:MinistryofFinance -2 -1 0 1 2 3 4 5 2Q 20131Q 20134Q 20123Q 2012 1.5 4.7 3.6 -1.4
  • 25. 25 Ministry of Finance 25 EconomicOutlook Broad Consumer Price Index (IPCA), in %YoY Inflation within the target range since 2004 *Averageforecastfor2013,according totheCentralBankofBrazilmarket researchonSeptember6,2013 Source:BrazilianInstituteofGeography andStatistics(IBGE)andCentralBank ofBrazil Producedby:MinistryofFinance 2013* 2012 2011 2010 2009 2008 2007 2006 2005 2004 2003 2002 2001 2000 1999 Upper Bound Lower Bound Target core IPCA 5.85.86.55.94.35.94.55.77.69.312.57.76.08.9 3.1
  • 26. 26 Ministry of Finance 26 EconomicOutlook Consumer price index, in %YoY, August 2013 G20 emerging markets inflation *July2013 **June2013 Source:Bloomberg Producedby:MinistryofFinance 0 2 4 6 8 10 12 India ** Indonesia Turkey Russia South Africa * Brazil M exico China2.5 3.5 6.1 6.4 6.5 8.2 8.8 10.7
  • 27. 27 Ministry of Finance 27 EconomicOutlook In %, latest available data Sound financial system Source:InternationalMonetaryFund (IMF)-FiscalSoundnessIndicators Producedby:MinistryofFinanceSpain Australia India Italy Russia Japan South Korea France USA United Kingdom South Africa Canada Mexico Brazil Turkey Germany Italy Spain South Africa Japan France United Kingdom Australia USA India Russia Canada Turkey South Korea Chile Argentina Mexico Brazil India South Africa United Kingdom Australia Mexico Japan Canada Turkey USA Italy Russia South Korea Germany Brazil Basel Index (Capital Adequacy) (Provisions minus Delinquencies)/Capital Net Assets/ Short-term Liabilities 17.9 17.4 17.0 16.3 16.1 15.7 15.7 14.4 14.3 14.3 14.2 13.4 13.3 13.1 11.8 11.4 -3.1 -3.1 -5.9 -9.9 -12.1 -14.7 -15.5 -16.1 -19.4 -21.4 -23.6 -27.6 -73.7 10.0 9.0 2.8 0.6 183.1 140.8 111.3 87.6 80.1 77.4 76.4 56.3 51.3 47.3 43.5 38.0 33.0 27.0
  • 28. 28 Ministry of Finance 28 EconomicOutlook Real estate loans, annual growth rate, in % Real estate loans have still huge opportunities of expansion in Brazil Source:CentralBankofBrazil Producedby:MinistryofFinance 0 10 20 30 40 50 60 70 Jul2013 Jan 2013 Jul2012 Jan 2012 Jul2011 Jan 2011 Jul2010 Jan 2010 Jul2009 Jan 2009 Jul2008 M ar2008 34.0 Despite their growth, in July 2013 real estate loans represented only 7.7% of Brazil’s GDP, a much lower rate than in developed countries and most emerging economies
  • 29. 29 Ministry of Finance 29 EconomicOutlook Budget balance, in % of GDP Brazil presents sound fiscal accounts *IMFestimates Source:InternationalMonetaryFund (IMF)-FiscalMonitorand CentralBankofBrazil Producedby:MinistryofFinance Primary Results Nominal Result United States Asia Euro Zone Latin America Brazil 2006-2008 2010-2013* United States Asia Euro Zone Latin America Brazil 2.6 1.3 -1.5 -1.5 -7.1 3.3 3.0 1.2 0.0 -1.9 -2.5 -2.3 -4.2 -3.0 -9.0 -2.8 -1.1 -1.4 -1.6 -3.8 2006-2008 2010-2013*
  • 30. 30 Ministry of Finance 30 EconomicOutlook 10-year Brazilian Global bonds* and U.S.Treasury yields, in % per annum Confidence: low spreads for sovereign bonds *Yieldsatissuedate Source:NationalTreasurySecretariat (STN) Producedby:MinistryofFinance 0.0 1.4 2.8 4.2 5.6 7.0 9 M ay 2013 5 Sep 2012 3 Jan 2012 7 Jul2011 27 Jul2010 15 Apr2010 15 Dez2009 7 M ay 2009 6 Jan 2009 U.S. Treasuries Brazilian sovereign bonds 6.1 5.8 4.8 5.0 4.5 4.2 3.4 2.7 2.82.4 3.3 3.6 3.9 3.0 3.1 1.9 1.6 1.8
  • 31. 31 Ministry of Finance 31 EconomicOutlook Non-resident share in federal public debt, in % of total DFPD* Increasing number of non-resident investors in Brazilian public debt *DomesticFederalPublicDebt Source:NationalTreasurySecretariat (STN) Producedby:MinistryofFinance 0 2 4 6 8 10 12 14 16 18 1.8 2.0 2.1 2.7 4.5 4.7 4.9 5.2 5.0 5.1 5.3 5.5 5.9 6.2 6.3 6.4 7.6 7.7 7.5 6.7 6.8 7.2 7.1 6.9 6.6 6.4 6.5 6.7 6.6 6.9 7.8 8.4 8.4 8.8 9.7 9.8 10.2 9.9 10.0 10.6 10.6 11.2 11.5 11.5 11.3 11.4 11.8 11.4 11.4 11.3 11.5 11.1 11.6 11.8 11.3 11.4 11.4 11.3 11.9 11.9 12.1 12.3 12.3 12.2 13.2 13.3 13.4 13.8 13.9 13.7 14.4 14.3 14.8 14.6 14.4 14.5 15.5 Jul2013 M ar2013 Nov 2012 Jul2012 M ar2012 Nov 2011 Jul2011 M ar2011 Nov 2010 Jul2010 M ar2010 Nov 2009 Jul2009 M ar2009 Nov 2008 Jul2008 M ar2008 Nov 2007 Jul2007 M ar2007 15.5
  • 32.
  • 33. Economic Development and Demand for Infrastructure
  • 34. 34 Ministry of Finance EconomicDevelopmentand DemandforInfrastructure Broad retail sales, seasonally adjusted, in %YoY Domestic market: dynamism of retail sales *Ona12-monthbasisuptoJuly2013 Source:BrazilianInstituteofGeography andStatistics(IBGE) Producedby:MinistryofFinance 0 3 6 9 12 15 2013* 2012 2011 2010 2009 2008 2007 2006 2005 200411.1 3.1 6.4 13.6 9.9 6.8 12.2 6.6 8.0 5.8
  • 35. 35 Ministry of Finance EconomicDevelopmentand DemandforInfrastructure New formal jobs, in millions Sustainable labor market ensures dynamic domestic demand For2012and2013,updatesafterthe officialreleasedateweretakeninto consideration *JanuarytoJuly2013 Source:MinistryofLaborand Employment Producedby:MinistryofFinance 0.0 0.5 1.0 1.5 2.0 2.5 3.0 2013* 2012 2011 2010 2009 2008 2007 2006 2005 2004 2003 2002 2001 2000 1999 1998 1997 1996 1995 0.1 0.1 0.3 0.4 0.5 1.2 1.0 1.5 0.9 1.9 1.8 1.9 2.5 1.8 1.8 2.9 2.2 1.3 0.9 19.90 million jobs
  • 36. 36 Ministry of Finance EconomicDevelopmentand DemandforInfrastructure Airline traffic, in millions of passengers Increasing demand for infrastructure services: airline passengers Source:NationalAgencyforCivil Aviation(ANAC) Producedby:MinistryofFinance 0 20 40 60 80 100 120 2012 2011 2010 2009 2008 2007 2006 2005 2004 2003 2002 2001 2000 101.4 92.6 77.2 62.8 56.0 52.1 47.7 44.1 35.7 33.4 35.9 36.0 34.0 2002-2012: 182.3% growth
  • 37. 37 Ministry of Finance EconomicDevelopmentand DemandforInfrastructure Brazilian trade flow (exports plus imports), in US$ billion Growing external trade *Ona12-monthbasis uptoAugust2013 Source:MinistryofDevelopment, IndustryandForeignTrade(MDIC) Producedby:MinistryofFinance 0 100 200 300 400 500 2013* 2012 2011 2010 2009 2008 2007 2006 2005 2004 2003 2002 2001 2000 1999 1998 1997 1996 199596.4 101.0 112.7 108.8 97.2 111.0 113.9 107.7 121.5 159.5 192.1 229.2 281.3 370.9 280.7 383.7 482.3 465.7 474.7 2002-2012: 332.4% growth
  • 38. 38 Ministry of Finance EconomicDevelopmentand DemandforInfrastructure Total cargo handling in ports, in millions of tons Significant growth in port trade volume *Ona12-monthbasisuptoMarch2013 Source:NationalAgencyforWater Transportation(ANTAQ) Producedby:MinistryofFinance 500 550 600 650 700 750 800 850 900 950 2013* 2012 2011 2010 2009 2008 2007 2006 2005 2004 2003 570.8 620.7 649.4 692.8 754.7 768.3 732.9 833.9 885.6 904.0 902.9 2003-2012: 58.4% growth
  • 39. 39 Ministry of Finance EconomicDevelopmentand DemandforInfrastructure In thousand vehicles per km per year, on highways under concession Vehicular traffic *Estimatebasedonmonthly averageuptoAugust2013 Source:BrazilianAssociationof HighwayConcessionaires(ABCR) Producedby:MinistryofFinance 0 20 40 60 80 100 120 2013* 2012 2011 2010 2009 2008 2007 2006 2005 2004 2003 2002 2001 2000 111 105 99 89 69 60 69 67 65 61 56 57 51 43 2002-2012: 86.6% growth
  • 40. 40 Ministry of Finance EconomicDevelopmentand DemandforInfrastructure New vehicles (buses, trucks, light commercial vehicles and cars), in million of vehicles Vehicle sales more than doubled in ten years *Ona12-monthbasis uptoAugust2013 Source:BrazilianAssociationof AutomotiveVehicleManufacturers (ANFAVEA) Producedby:MinistryofFinance 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 2013* 2012 2011 2010 2009 2008 2007 2006 2005 2004 2003 2002 4th largest vehicle market in the world 1.5 1.4 1.5 1.7 1.9 2.5 2.8 3.1 3.5 3.6 3.8 3.8 2002-2012: 153.5% growth
  • 41. 41 Ministry of Finance EconomicDevelopmentand DemandforInfrastructure Revenue tonne kilometers (RTKs), in billions Railroad volumes Source:NationalTransportation Agency (ANTT) Producedby:MinistryofFinance 130 164 198 232 266 300 2012 2011 2010 2009 2008 2007 2006 2005 2004 2003 2002168 182 203 221 232 258 271 244 278 291 298 2002-2012: 77.4% growth
  • 42. 42 Ministry of Finance EconomicDevelopmentand DemandforInfrastructure Brazilian grain harvest*, in millions of tons Brazilian harvest in record figures *Preliminarydata:subjecttochangeby Conab/MAPA **ConabestimatesinSeptember2013 Source:MinistryofAgriculture, LivestockandFoodSupply(MAPA) Producedby:MinistryofFinance 70 90 110 130 150 170 190 210 2012/2013** 2011/2012 2010/2011 2009/2010 2008/2009 2007/2008 2006/2007 2005/2006 2004/2005 2003/2004 2002/2003 2001/2002 2000/2001 100.3 96.8 123.2 119.1 114.7 122.5 131.8 144.1 135.1 149.3 162.8 166.2 187.1
  • 43. 43 Ministry of Finance EconomicDevelopmentand DemandforInfrastructure Brazil in the global ranking, by production and exports quantities, 2011 Agricultural leadership Source:FoodandAgriculture Organisation(FAO) Producedby:MinistryofFinance Orange Juice Tobacco Chicken Whitesugar Corn Beans Soybean Processed beef Coffee 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 3 3 16 Producer Exporter
  • 44.
  • 46. 46 Ministry of Finance CapitalMarketInstruments Howcannon-residentinvestorsnegotiatedebt securitiesandfundsinBrazil? CMNResolution2,689ofyear2000,whichrulesoninvestmentsbynon-residentinvestorsin thefinancialandcapitalmarketsofinvestment,providesallnecessaryinformation Brazildoesnotimposetaxes ontheinternationalremittanceofprofitsanddividends Producedby:MinistryofFinanceand BrazilianDevelopmentBank(BNDES) FinancialInstrumentsforInfrastructureInvestments https://www3.bcb.gov.br/normativo/ detalharNormativo.do?method=deta lharNormativo&N=100014927 • More Info: CMNResolution2,689
  • 47. 47 Ministry of Finance CapitalMarketInstruments FinancialInstrumentsforInfrastructureInvestments Definition Benefitsfor non-residentinvestors* Minimum Requirements Investment Debentures and Real Estate Receivables Certificates • ZeroIncomeTaxRate(IR) • ZeroTaxonFinancialOperations(IOF) • Weightedaveragematurity:overfouryears. • Return:CRIpaysinterestatafixedrateoratafloatingrate peggedtoaninflationindexortheReferenceRate(TR).Totalor partialuseofpost-fixedrateofinterestareforbidden. • Norepurchase:bytheissuerorrelatedpartyinthefirsttwo yearsafterissuanceandearlyliquidation,exceptincasestobe regulatedbyBrazil’sNationalMonetaryCouncil(CMN). • Requiredevidencedocuments: securityshouldbe registeredwithclearinghousesdulyauthorizedbythe CentralBankofBrazilortheBrazilianSecuritiesandExchange Commission(CVM). • Simplifiedprocedure:todemonstratethepurposeof allocatingresourcesintothefuturepaymentorreimbursement ofexpenses,costsorliabilitiesrelatedtoinvestmentprojects, includingthoseaimedatR&D&I(research,developmentand innovation). • Noresalecommitment:undertakenbythebuyer. • Yieldpaymentfrequency:ifany,itmustbeatleast180 daysapart. • Debêntures de Investimento e Certificados de Recebíveis Imobiliários (CRI) *Incaseofinvestmentsfromcountries whicharenotsubjecttoa20%(orhigher) incometaxrate(“taxhavens”),theabove mentionedtaxbenefitsdonotapply, unlessitisrelatedtoawealthfund Producedby:MinistryofFinanceand BrazilianDevelopmentBank(BNDES)
  • 48. 48 Ministry of Finance CapitalMarketInstruments Definition Benefitsfornon- -residentinvestors* Minimum Requirements InvestmentFundin CreditRights • ZeroIncomeTaxRate(IR) • ZeroTaxonFinancial Operations(IOF) • Termofduration:minimumofsixyears. • Nopayment,fullyorpartially:ofprincipaloftheFund’squotasinthefirsttwoyearsfromthe closingdateofthepublicofferingofthequotadistributionthatconstitutetheinitialassetsofthe Fund,exceptincasesoftheFund’searlyliquidationmentionedintheFund’sregulation. • Noacquisitionofquotas:bythesellerorbytheissuerorbyanypartiesrelatedtothem,except incaseofsubordinatedquotasforpurposesofamortizationandwithdrawal. • Amortizationplanofquotas:includingthosefromincorporatedyields,ifany,mustbeatleast 180(onehundredandeighty)daysapart. • Requiredevidencedocuments:quotasmustbeadmittedtotradingonanorganizedsecurities marketorregisteredwitharegistrysystemdulyauthorizedbytheCentralBankofBrazilorthe BrazilianSecuritiesandExchangeCommission(CVM)undertheirrespectivejurisdiction. • Simplifiedprocedure:todemonstratethepurposeofallocatingresourcesintoatransactionof investmentprojects,includingthoseaimedatR&D&I. • Mandatorypresenceofthefollowing:intheassignmentagreement,regulationandprospec- tus,ifany,inamannertobedeterminedbyCVM: •Goaloftheprojectorthebeneficiaryprojects; •Estimatedbeginningandendperiodsor,forongoingprojects,descriptionofthecurrentstage andestimatedendperiod; •Estimatedvolumeoffinancialresourcesrequiredtocarryouttheprojectornotinitialized projectsorforthecompletionofongoingprojects; •Estimatedpercentageoffundstoberaisedwiththesellingofthecreditrightscomparedto thefinancialresourcerequirementsofthebeneficiaryprojects. • Fund’sequity:consistsofatleast85%(eighty-five)percentofcreditrightsand,fortheremaining portion,offederalgovernmentsecurities,repurchaseagreementsbackedbygovernmentbondsor mutualfundquotasthatinvestinfederalgovernmentbonds. FinancialInstrumentsforInfrastructureInvestments • Fundos de Investimento em Direitos Creditórios (FIDC) *Incaseofinvestmentsfromcountries whicharenotsubjecttoa20%(or higher)incometaxrate(“taxhavens”), theabovementionedtaxbenefitsdonot apply,unlessitisrelatedtoawealthfund Producedby:MinistryofFinanceand BrazilianDevelopmentBank(BNDES)
  • 49. 49 Ministry of Finance CapitalMarketInstruments Definition Benefitsfornon- -residentinvestors* Minimum Requirements Infrastructure Debentures • ZeroIncomeTaxRate(IR) • ZeroTaxonFinancial Operations(IOF) • Issuance: must be between January 2011 and December 2015. • Weighted average maturity: over four years. • Return: Debentures pay interest at a fixed rate or at a floating rate pegged to an inflation index or the Reference Rate (TR).Total or partial use of post-fixed rate of interest are forbidden. • No repurchase: by the issuer or related party in the first two years after issuance and early liquidation, except in cases to be regulated by Brazil’s National Monetary Council (CMN). • Required evidence documents: security should be registered with clearing houses duly authorized by the Central Bank of Brazil or the Brazilian Securities and Exchange Commission (CVM). • Simplifiedprocedure:todemonstratethepurposeofallocatingresourcesintothefuturepaymentorreimburse- mentofexpenses,costsorliabilitiesrelatedtoinvestmentprojects,includingthoseaimedatR&D&I. • No resale commitment: undertaken by the buyer. • Yield payment frequency: if any, it must be at least 180 days apart. Projects Approval: • Priority investment projects: to be implemented in the infrastructure area, or intensive economic production in research, development, and innovation. Also, according to the Decree n. 7,603 of year 2011, projects should have: • Approval Ordinance: issued and approved by the Ministry responsible for that sector • Focus on deployment, expansion, maintenance, recovery, adaptation or modernization processes in the following sectors: • Specific Purpose Companies (SPE): for management and implementation. • Issuer: dealer or grantee or authorized contractors or lessee. •Logisticsandtransportation •Broadcasting •Urbanmobility •Basicsanitationand •Energy •Irrigation •Telecommunications FinancialInstrumentsforInfrastructureInvestments • Debêntures de Infraestrutura *Incaseofinvestmentsfrom countrieswhicharenotsubject toa20%(orhigher)incometax rate(“taxhavens”),theabove mentionedtaxbenefitsdonotapply, unlessitisrelatedtoawealthfund Producedby:MinistryofFinanceand BrazilianDevelopmentBank(BNDES)
  • 50. 50 Ministry of Finance CapitalMarketInstruments Definition Benefitsfor non-residentinvestors* Minimum Requirements Brazilian Infrastructure Bonds Investment Funds • ZeroIncomeTaxRate(IR) • ZeroTaxonFinancialOperations(IOF) • Concentrationininvestments:mustholdatleast67%(sixty- -seven)percentoftheFund’snetworthwithinthefirsttwoyears and85%(eighty-five)percentintheremainingyears. • FundofFunds(FIC)investments:mustholdatleast95% (ninety-five)percentofFICnetworthintheInfrastructureBonds InvestmentFund’squota. FinancialInstrumentsforInfrastructureInvestments • Fundos de Debêntures Incentivados Producedby:MinistryofFinanceand BrazilianDevelopmentBank(BNDES)
  • 52.
  • 54. 54 Ministry of Finance Highways Highway Concessions Highways Updatedinformationavailableat www.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance 7 2 6 9 5 4 1 3 PA MA PE BA TO MT ES MG GO MS SP PR SC RS Açailãndia Sinop Palmas Parnamirim Lucas do Rio Verde Cuiabá Recife Maceió Aracaju Salvador Porto Seguro Mucurí Vitória Campos Além Paraíba Divisa Alegre Mafra Maracaju Estrela D’Oeste Rio de Janeiro Belo Horizonte São Paulo Santos Campo Grande Uruaçu Brasília Rio Grande Juíz de Fora Anápolis Goiânia Feira de Santana BR-116 BR-050 BR-262 BR-040 BR-153 BR-163 BR-262 BR-060 BR-101 BR-153 BR-163 Belém 2 1 3 5 4 6 8 7 9 BR-116/MG BR-040/MG-GO-DF BR-101/BA BR-262/MG-ES BR-050/GO-MG BR-153/GO-TO BR-163/MT BR-163/MS BR-060/153/262/DF-GO-MG 8
  • 55. 55 Ministry of Finance Highways Auction Concluded on September 18th Road Concession – BR-050: from Cristalina (GO) (BR-040 entry point) to MG/SP border Object Demand Criteria • Section: BR-050, Entry Point of BR- 040/GO (Cristalina) – Border w/ MG/SP • Total Length: 426 km • Length to be widened: 219 km The project includes widening, maintenance and operation of the highway. Other widening projects are also planned to happen, including the construction of 9 km of side roads. Demand Projection (AADT): 2014 (54,232), 2019 (62,790), 2024 (76,046). Connects Brasilia, the state of São Paulo and the South Region of the country, crossing an important agricultural and wholesale retail center - the Minas Gerais triangle. Term: 30 years Criteria: lowest tariff Economic and Financial Modeling CAPEX*: US$ 1.3 billion OPEX: US$ 869 million Financing conditions: Term: 25 years (Grace period: 5 years) Rate: TJLP** + 2%a.a. Real leveraged IRR: up to 16% per year, in real terms. Debt to equity ratio: 70% / 30% Equity support: up to 49% of SPE*** or holding’s share capital (Institutions: public banks and pension funds) Environmental licensing: State- owned EPL is in charge of obtaining Previous License (LP) and Installation License (LI) of duplication works MT TO GO MS PR SP MG RJ ES BA BR-153 BR-060 BR-050 São Paulo Palmas Curitiba Goiânia Uberaba Uberlândia Catalão Cristalina Brasília Highway BR-050 GO/MG To be awarded BR-040 Rio de Janeiro Vitória *Withoutbenefitsandindirect expenses **TJLP-LongTermInterestRate, currently5%p.a. ***SpecialPurposeEntity InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 Updatedinformationavailableat www.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 56. 56 Ministry of Finance Highways Road Concession – BR-040: Brasília (DF) – Juiz de Fora (MG) Object Demand Criteria • Section: BR-040, Juiz de Fora (MG) – Entry point of BR-251 (Brasília - DF) • Total Length: 937 km • Length to be widened: 715 km The project includes widening, maintenance and operation of the highway. Other widening projects are also planned to happen, including the construction of side roads between Luziania and Brasilia. Demand Projection: under study Connects two important economic centers in Brazil - Rio de Janeiro and Belo Horizonte - to the fourth most populous city and the highest GDP per capita in the country - Brasilia. It is the main route for supply of coal to steel parks. ConcessionTerm: 30 years Number ofToll Plazas: 11 Criteria: lowest tariff Economic and Financial Modeling Financing conditions: Term: 25 years (Grace period: 5 years) Rate:TJLP* + 2%a.a. Real leveraged IRR: up to 16% per year, in real terms. Debttoequityratio:upto70%/30% Equity support: up to 49% of SPE** or holding’s share capital (Institutions: public banks and pension funds) Environmental licensing: State- owned EPL is in charge of obtaining Previous License (LP) and Installation License (LI) of duplication works GO PR SP MG RJ ES Brasília Luziânia Sete Lagoas Belo Horizonte Juiz de Fora BR-381 BR-040 Highway BR-040 MG/GO/DF To be awardedGranted Section 180 Km São Paulo Curitiba Rio de Janeiro *TJLP-LongTermInterestRate, currently5%p.a. **SpecialPurposeEntity Updatedinformationavailableat www.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 57. 57 Ministry of Finance Highways RoadConcession–BR-116:fromBA/MGborder(DivisaAlegre)toMG/RJborder(AlémParaíba) Object Demand Criteria • Section: BR-116, RJ/MG Border (Além Paraíba) - MG/BA Border (Divisa Alegre) • Total Length: 817 km • Length to be widened: 817 km The project includes widening, maintenance and operation of the highway. Other widening projects are also planned, including the construction of 27 km of side roads. Demand Projection: under study Connects two important economic centers in Brazil - Rio de Janeiro and Salvador – across eastern Minas Gerais. ConcessionTerm: 30 years Number ofToll Plazas: 8 Criteria: lowest tariff Economic and Financial Modeling Financing conditions: Term: 25 years (Grace period: 5 years) Rate:TJLP* + 2%a.a. Real leveraged IRR: up to 16% per year, in real terms. Debttoequityratio:upto70%/30% Equity support: up to 49% of SPE** or holding’s share capital (Institutions: public banks and pension funds) Environmental licensing: State- owned EPL is in charge of obtaining Previous License (LP) and Installation License (LI) of duplication works GO SP MG RJ ES BA BR-116 São Paulo Rio de Janeiro Divisa Alegre Teófilo Otoni Gov. Valadares Muriaé Além Paraíba Salvador Highway BR-116 MG To be awarded *TJLP-LongTermInterestRate, currently5%p.a. **SpecialPurposeEntity Updatedinformationavailableat www.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 58. 58 Ministry of Finance Highways Road Concession – BR-101: from the entry point of BR-324 (BA) to the entry point of the BA-698 (Mucuri) Object Demand Criteria • Section: BR-101, Entry Point of BA-698 (Mucuri) – Entry Point of. BR-324/BA • Total Length: 772 km • Length to be widened: 551.3 km The project includes widening, maintenance and operation of the highway. Other widening projects are also planned to happen, including the construction of 67 km of side roads. Demand Projection (AADT): 2014 (57,392), 2019 (71,312), 2024 (87,140). ConnectsthesoutherncoastofBahia tothestatesofEspíritoSantoandRio deJaneiro.BR-101isaveryimportant roadconnectingthenortheastwiththe southeastandsouthernregionsalong thecoastalline,wherelivesagreat shareofBrazilianpopulation.Important portsarealsoconnectedbythisroad. ConcessionTerm: 30 years Number ofToll Plazas: 9 Criteria: lowest tariff Economic and Financial Modeling CAPEX*: US$ 2.2 billion OPEX: US$ 1.3 billion Financing conditions: Term: 25 years (Grace period: 5 years) Rate:TJLP** + 2%a.a. Real leveraged IRR: up to 16% per year, in real terms. Debttoequityratio:upto70%/30% Equity support: up to 49% of SPE*** or holding’s share capital (Institutions: public banks and pension funds) Environmental licensing: State- owned EPL is in charge of obtaining Previous License (LP) and Installation License (LI) of duplication works TO GO SP MG RJ ES BA Salvador Rio de Janeiro BR-101 BR-116 BR-381 BR-262 Belo Horizonte Vitória MucuríJoão Monlevade São Paulo Highway BR-101 BA To be awarded *Withoutbenefitsandindirect expenses **TJLP-LongTermInterestRate, currently5%p.a. ***SpecialPurposeEntity InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 Updatedinformationavailableat www.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 59. 59 Ministry of Finance Highways Road Concession – BR-262: from the entry point of BR-381 (J. Monlevade) to the entry point of BR-101/ES Object Demand Criteria • Section: BR-262, Entry Point of BR-381 (J. Monlevade) – Entry Point of BR-101/ES • Total Length: 377 km • Length to be widened: 196.4 km The project includes widening, maintenance and operation of the highway. Other widening projects are also plannedw, including the construction of a ringroad and 13 km of side roads. Demand Projection (AADT): 2014 (7,549), 2019 (9,297), 2024 (11,388) The state of Minas Gerais (MG) has the third largest population in Brazil.This road gives access to the ports of the state of Espirito Santo, the main gateway to MG exports and imports, constituting an alternative route for the flow of MG production. ConcessionTerm: 30 years Number ofToll Plazas: 5 Criteria: lowest tariff Economic and Financial Modeling CAPEX*: US$ 916 million OPEX: US$ 739 million Financing conditions: Term: 25 years (Grace period: 5 years) Rate:TJLP** + 2%a.a. Real leveraged IRR: up to 16% per year, in real terms. Debttoequityratio:upto70%/30% Equity support: up to 49% of SPE*** or holding’s share capital (Institutions: public banks and pension funds) Environmental licensing: State- owned EPL is in charge of obtaining Previous License (LP) and Installation License (LI) of duplication works TO GO SP MG RJ ES BA Salvador Rio de Janeiro BR-101 BR-116 BR-381 BR-262 Belo Horizonte Vitória Mucurí São Paulo Highway BR-262 ES/MG To be awarded João Monlevade Governador Valadares *Withoutbenefitsandindirect expenses **TJLP-LongTermInterestRate, currently5%p.a. ***SpecialPurposeEntity InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 Updatedinformationavailableat www.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 60. 60 Ministry of Finance Highways RoadConcession–BR-153:fromPalmas(TO)toAnápolis(GO)(BR-060entrypoint) Object Demand Criteria • Section: BR-153, Anápolis (Entry Point of BR-060/GO) - Entry Point of TO-080;TO-080, Entry Point of BR-060/GO- Palmas • Total Length: 814 km • Length to be widened: 769.5 km The project includes widening, maintenance and operation of the highway. Other widening projects are also planned, including the construction of 10 km of side roads. Demand Projection (AADT): 2014 (99,926), 2019 (119,627), 2024 (146,113). ConnectsPalmas,Goiâniaandthesoutheast ofthecountry,crossingamajorBrazilian agriculturalpole.Palmasisthegeographical centerofthecountry,withthevocation tobecomeanimportanthub.BR-153is themainroadtoreachthecityofManaus fromotherregions,benefitingfromthe heavytrafficofManausFreeZone,which concentratesBrazilianelectronicproduction, amongotherimportantindustries. ConcessionTerm: 30 years. Number ofToll Plazas: 11. Criteria: lowest tariff. Economic and Financial Modeling CAPEX*: US$ 3.0 billion OPEX: US$ 1.4 billion Financing conditions: Term: 25 years (Grace period: 5 years) Rate:TJLP** + 2%a.a. Real leveraged IRR: up to 16% per year, in real terms. Debt to equity ratio: 70% / 30% Equity support: up to 49% of SPE*** or holding’s share capital (Institutions: public banks and pension funds) Environmental licensing: State- owned EPL is in charge of obtaining Previous License (LP) and Installation License (LI) of duplication works MT TO GO MS SP MG RJ ES BA Palmas Gurupi Uruaçu Anápolis BR-153 TO-080 BR-060 BR-040 BR-050 BR-262 BR-153 Highway BR-153 GO/TO To be awarded *Withoutbenefitsandindirect expenses **TJLP-LongTermInterestRate, currently5%p.a. ***SpecialPurposeEntity InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 Updatedinformationavailableat www.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 61. 61 Ministry of Finance Highways Road Concession – BR-060 (DF/GO), BR-153 (GO/MG) and BR-262 (MG) Object Demand Criteria • Section: BR-060, Entry Point of BR-251 (DF) – Entry Point of BR-153/GO; BR-153, Entry Point of BR- 060/GO – Entry Point of Br-262/MG; BR-262, Entry Point of BR-153/MG – Entry Point of BR-381 (Betim) • Total Length: 1,177 km •Lengthtobewidened:648km The project includes widening, maintenance and operation of the highway. Other widening projects are also planned, including the construction of 27 km of side roads and ringroad in Goiânia. Demand Projection (AADT): 2014 (160,374), 2019 (195,551), 2024 (238,453). Connects Brasília, Goiânia, Uberaba and Belo Horizonte, crossing a major Brazilian agricultural pole. Term: 30 years. Number ofToll Plazas: 11. Criteria: lowest tariff. Economic and Financial Modeling CAPEX*: US$ 3.9 billion OPEX: US$ 1.8 billion Financing conditions: Term: 25 years (Grace period: 5 years) Rate:TJLP** + 2%a.a. Real leveraged IRR: up to 16% per year, in real terms. Debttoequityratio:upto70%/30% Equity support: up to 49% of SPE*** or holding’s share capital (Institutions: public banks and pension funds) Environmental licensing: State- owned EPL is in charge of obtaining Previous License (LP) and Installation License (LI) of duplication works MT TO GO MS SP MG RJ ES BA Palmas Gurupi Uruaçu Anápolis BR-153 TO-080 BR-060 BR-040 BR-050 BR-262 BR-153 Highway BR-060/153/262 DF/GO/TO To be awarded *Withoutbenefitsandindirect expenses **TJLP-LongTermInterestRate, currently5%p.a. ***SpecialPurposeEntity InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 Updatedinformationavailableat www.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 62. 62 Ministry of Finance Highways Road Concession – BR-163: from MT/MS border to MS/PR border Object Demand Criteria • Section: BR-163, Border MT/MS – Border w/ MS/PR • Total Length: 847 km • Length to be widened: 807 km The project includes widening, maintenance and operation of the highway. Other widening projects are also planned. Demand Projection: under study Connects Cuiabá, Campo Grande and the Southeast/South Regions of Brazil, constituting an alternative route for the flow of Brazilian agricultural production. Term: 30 years. Criteria: lowest tariff. Economic and Financial Modeling CAPEX*: US$ 2.8 billion OPEX: US$ 1.3 billion Financing conditions: Term: 25 years (Grace period: 5 years) Rate:TJLP** + 2%a.a. Real leveraged IRR: up to 16% per year, in real terms. Debttoequityratio:upto70%/30% Equity support: up to 49% of SPE*** or holding’s share capital (Institutions: public banks and pension funds) Environmental licensing: State- owned EPL is in charge of obtaining Previous License (LP) and Installation License (LI) of duplication works MT TO GO MS PR SP MG RJ ES BA Curitiba Cuiabá Campo Grande Nova Alvorada Dourados BR-163 BR-364 BR-262 BR-267 Highway BR-163 /267/262 MS BR-163 To be awarded *Withoutbenefitsandindirect expenses **TJLP-LongTermInterestRate, currently5%p.a. ***SpecialPurposeEntity InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 Updatedinformationavailableat www.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 63. 63 Ministry of Finance Highways Road Concession – BR-163: from Sinop (MT) to MT/MS border Object Demand Criteria • Section: BR-163, Sinop – Border MT/MS • Total Length: 851 km • Length to be widened: 453 km The project includes widening, maintenance and operation of the highway. Other widening projects are also planned, including 20 km of ringroad (in 5 different cities) and 44 km of side roads. Demand Projection (AADT): 2014 (5,815), 2019 (7,140), 2024 (8,757) Connects Sinop, Cuiabá, Campo Grande and the North/Southeast/ South Regions of Brazil, crossing an important Brazilian agricultural production. Term: 30 years Number ofToll Plazas: 9 Criteria: lowest tariff Economic and Financial Modeling CAPEX*: US$ 2.7 billion OPEX: US$ 1.4 billion Financing conditions: Term: 25 years (Grace period: 5 years) Rate:TJLP** + 2%a.a. Real leveraged IRR: up to 16% per year, in real terms Debttoequityratio:upto70%/30% Equity support: up to 49% of SPE*** or holding’s share capital (Institutions: public banks and pension funds) Environmental licensing: State- owned EPL is in charge of obtaining Previous License (LP) and Installation License (LI) of duplication works MT TO GO MS PR SP MG RJ ES BA Goiânia Curitiba Cuiabá Campo Grande BR-163 BR-364 BR-262 BR-267 Posto Gil Rondonópolis Sinop BR-163 Highway BR-163 MT To be awarded *Withoutbenefitsandindirect expenses **TJLP-LongTermInterestRate, currently5%p.a. ***SpecialPurposeEntity InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 Updatedinformationavailableat www.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 64.
  • 66. 66 Ministry of Finance Railways Railway Network Exploited rail network PIL - Rail Network (11,000 km) – to be awarded StructuringWaterways PAC – Rail network New railways – Studies underway Updatedinformationavailableat www.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance Pacific Link Pacific Link Santarém Manaus Porto Velho Belém / V. Conde Rio Grande Santos Itaguaí Rio de Janeiro Vitória Ilhéus Salvador Suape Pecém Itaqui Aratu S F. Sul Paranaguá Itajaí / Navegantes Estrela d’Oeste Figueirópolis Estreito Lucas do Rio Verde Uruaçu Belo Horizonte Eliseu Martins Barreiras Rondonópolis Açailândia Salgueiro Parnamirim Maracaju
  • 67. 67 Ministry of Finance Railways Railway Concession: São Paulo rail beltway (“Ferroanel”) and access to Santos seaport Object Demand Concession characteristics Financing Conditions The North Ferroanel will surround the metropolitan region of São Paulo, connecting Santos to Jundiaí. It will increase the rail cargo capacity and alleviate the traffic in the city. Section: Jundiaí-Manuel Feio; Riberão Pires-Evangelista de Souza; access to Santos Seaport Allows offsetting the transportation of cargo and passengers from other means of transporation in the São Paulo Metropolitan Region and optimizes railway access to Santos Seaport. Build, operate and transfer Railinfrastructurebuilderand manager:Concessionforrailway exploitation,comprising:construction, maintenance,signalingandcomunications systems,andtrafficcontrol. ConcessionTerm: 35 years Construction to be completed up to the 5th year of the concession term. RiskMitigation:DemandRisk (Guaranteedpurchaseof100%ofrailway operationalcapacityavailability);Socio- environmentalandExpropriationRisks (EnvironmentalandExpropriationcostsand chargeslimitedtovaluespre-establishedin concessioncontracts). Environmental licensing: State-owned EPL is responsible for obtaining Previous License (LP) and will give support for obtaining the Installation Licence (LI) of construction works. Term: 30 years (Grace period: 5 years) Rate:TJLP* + 1%a.a. Real leveraged IRR: up to 16% per year, in real terms. Upfront payment of revenues due to operational capacity availability, in equivalent value of 15% of total referential CAPEX. Equity support: up to 49% of SPE** or holding’s share capital (Institutions: public banks and pension funds). Canguera Amador BuenoMarinque Evangelista de Souza Santos Pereque Itaquaciara Perus Eng Manoel Feio Suzano Rio Grande da Serra Ipiranga Lapa Jundiaí Northern Ferroanel (SP) To be awarded SP Santos Seaport *TJLP-LongTermInterestRate, currently5%p.a. **SpecialPurposeEntity Updatedinformationavailable atwww.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 68. 68 Ministry of Finance Railways Object Demand Concession characteristics Financing Conditions Section: Lucas do RioVerde - Campinorte and Palmas - Anápolis Extension: 1,920 km InterconnectsBrazil’sMidwestRegiontothe SoutheastandNortheast,providingrailway transportationtoproductioncenterslocated inthemidwestandtheoutflowthroughthe North-SouthRailway. Build, operate and transfer Estimated CAPEX: US$3.65billion Railinfrastructurebuilderand manager:Concessionforrailway exploitation,comprising:construction, maintenance,signalingandcomunications systems,andtrafficcontrol. ConcessionTerm: 35 years Construction to be completed up to the 5th year of the concession term. RiskMitigation:DemandRisk (Guaranteedpurchaseof100%ofrailway operationalcapacityavailability);Socio- environmentalandExpropriationRisks (EnvironmentalandExpropriationcostsand chargeslimitedtovaluespre-establishedin concessioncontracts). Environmental licensing: State-owned EPL is responsible for obtaining Previous License (LP) and will give support for obtaining the Installation Licence (LI) of construction works. Term: 30 years (Grace period: 5 years) Rate:TJLP* + 1%a.a. Real leveraged IRR: up to 16% per year, in real terms. Upfront payment of revenues due to operational capacity availability, in equivalent value of 15% of total referential CAPEX. Equity support: up to 49% of SPE** or holding’s share capital (Institutions: public banks and pension funds). Railway Concession: from Lucas do RioVerde (MT) to Campinorte (GO) and from Palmas (TO) to Anápolis (GO) MT TO GO MS SP MG RJ ES BA Palmas Campinorte Anápolis Lucas do Rio Verde Concession: Lucas do Rio Verde - Campinorte and Palmas - Anápolis To be awarded *TJLP-LongTermInterestRate, currently5%p.a. **SpecialPurposeEntity Updatedinformationavailable atwww.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 69. 69 Ministry of Finance Railways Object Demand Concession characteristics Financing Conditions Section: Açailândia - Vila do Conde Extension: 457 km Interconnects the Midwest Region to the North and the port ofVila do Conde, completing the north stretch of the North- South Railway, allowing the production and outflow of grains, minerals and oil products through the port ofVila do Conde Build, operate and transfer Estimated CAPEX: US$ 1.39 billion Rail infrastructure builder and manager: Concession for railway exploitation, comprising: construction, maintenance, signaling and comunications systems, and traffic control. ConcessionTerm: 35 years Construction to be completed up to the 5th year of the concession term. Risk Mitigation: Demand Risk (Guaranteed purchase of 100% of railway operational capacity availability); Socio-environmental and Expropriation Risks (Environmental and Expropriation costs and charges limited to values pre- established in concession contracts). Environmental licensing: State-owned EPL is responsible for obtaining Previous License (LP) and will give support for obtaining the Installation Licence (LI) of construction works. Term: 30 years (Grace period: 5 years) Rate:TJLP* + 1%a.a. Real leveraged IRR: up to 16% per year, in real terms. Upfront payment of revenues due to operational capacity availability, in equivalent value of 15% of total referential CAPEX. Equity support: up to 49% of SPE** or holding’s share capital (Institutions: public banks and pension funds). Railway Concession: from Açailândia (MA) toVila do Conde (PA) TO MA PA Belém Açailândia Carajás Vila do Conde Port Itaqui Port Concession: Açailândia - Vila do Conde To be awarded *TJLP-LongTermInterestRate, currently5%p.a. **SpecialPurposeEntity Updatedinformationavailable atwww.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 70. 70 Ministry of Finance Railways Object Demand Concession characteristics Financing Conditions Section: OuroVerde de Goiás – Dourados Extension: 1,339 km Expands the North-South Railway and reaches important production centers of grains. Build, operate and transfer Estimated CAPEX: US$ 1.78 billion Rail infrastructure builder and manager: Concession for railway exploitation, comprising: construction, maintenance, signaling and comunications systems, and traffic control. ConcessionTerm: 35 years Construction to be completed up to the 5th year of the concession term. Risk Mitigation: Demand Risk (Guaranteed purchase of 100% of railway operational capacity availability); Socio-environmental and Expropriation Risks (Environmental and Expropriation costs and charges limited to values pre- established in concession contracts). Environmental licensing: State-owned EPL is responsible for obtaining Previous License (LP) and will give support for obtaining the Installation Licence (LI) of construction works. Term: 30 years (Grace period: 5 years) Rate:TJLP* + 1%a.a. Real leveraged IRR: up to 16% per year, in real terms. Upfront payment of revenues due to operational capacity availability, in equivalent value of 15% of total referential CAPEX. Equity support: up to 49% of SPE** or holding’s share capital (Institutions: public banks and pension funds). Railway Concession: OuroVerde de Goiás (GO) – Estrela D’Oeste (SP) – Panorama (SP) – Dourados (MS) Concession: Ouro Verde de Goiás - Dourados To be awarded Ouro Verde de Goiás Goiânia Campo Grande Dourados Panorama Andradina Estrela d’Oeste GO MS *TJLP-LongTermInterestRate, currently5%p.a. **SpecialPurposeEntity Updatedinformationavailable atwww.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 71. 71 Ministry of Finance Railways Object Demand Concession characteristics Financing Conditions Section: Belo Horizonte - Candeias Extension: 1,350 km Createsnewpossibilitiesfortransportofgeneral cargobetweenthesoutheastandnortheast regions,refocusingontheuseofrailwaystothe developmentoftheinternalmarket. Build, operate and transfer Estimated CAPEX: US$ 4.80 billion Rail infrastructure builder and manager: Concession for railway exploitation, comprising: construction, maintenance, signaling and comunications systems, and traffic control. ConcessionTerm: 35 years Construction to be completed up to the 5th year of the concession term. Risk Mitigation: Demand Risk (Guaranteed purchase of 100% of railway operational capacity availability); Socio-environmental and Expropriation Risks (Environmental and Expropriation costs and charges limited to values pre- established in concession contracts). Environmental licensing: State-owned EPL is responsible for obtaining Previous License (LP) and will give support for obtaining the Installation Licence (LI) of construction works. Term: 30 years (Grace period: 5 years) Rate:TJLP* + 1%a.a. Real leveraged IRR: up to 16% per year, in real terms. Upfront payment of revenues due to operational capacity availability, in equivalent value of 15% of total referential CAPEX. Equity support: up to 49% of SPE** or holding’s share capital (Institutions: public banks and pension funds). Railway Concession: from Belo Horizonte (MG) to Candeias (BA) GO SP MG RJ ES BA Concession: Belo Horizonte - Candeias To be awarded Salvador Candeias Corinto Salvador Port Aratu Port Belmonte Port Terminal Brumado Caetité Belo Horizonte Ilhéus Port *TJLP-LongTermInterestRate, currently5%p.a. **SpecialPurposeEntity Updatedinformationavailable atwww.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 72. 72 Ministry of Finance Railways Object Demand Concession characteristics Financing Conditions Section: Rio de Janeiro -Vila Velha Extension: 572 km Integrates the port of Rio de Janeiro and its Terminals to the Ports ofVitória eTubarão, creating new logistic possibilities for the movement of cargo. Build, operate and transfer Estimated CAPEX: US$ 1.52 billion Rail infrastructure builder and manager: Concession for railway exploitation, comprising: construction, maintenance, signaling and comunications systems, and traffic control. ConcessionTerm: 35 years Construction to be completed up to the 5th year of the concession term. Risk Mitigation: Demand Risk (Guaranteed purchase of 100% of railway operational capacity availability); Socio-environmental and Expropriation Risks (Environmental and Expropriation costs and charges limited to values pre- established in concession contracts). Environmental licensing: State-owned EPL is responsible for obtaining Previous License (LP) and will give support for obtaining the Installation Licence (LI) of construction works. Term: 30 years (Grace period: 5 years) Rate:TJLP* + 1%a.a. Real leveraged IRR: up to 16% per year, in real terms. Upfront payment of revenues due to operational capacity availability, in equivalent value of 15% of total referential CAPEX. Equity support: up to 49% of SPE** or holding’s share capital (Institutions: public banks and pension funds). Railway Concession: from Rio de Janeiro (RJ) toVilaVelha (ES) MG RJ ES Concession: Nova Iguaçu - Vila Velha To be awarded Vitória Vila Velha Campos dos Goitaguazes Formosa Beach Tubarão Port Vitória Port Niterói Port Rio de Janeiro Port Ponta UBU Port Terminal Açu Port Terminal Macaé Port Terminal Rio de Janeiro Barra do Piraí Duque de Caixias Port Terminal Nova Iguaçú *TJLP-LongTermInterestRate, currently5%p.a. **SpecialPurposeEntity Updatedinformationavailable atwww.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 73. 73 Ministry of Finance Railways Object Demand Concession characteristics Financing Conditions Section: Anápolis – Corinto – Campos Extension: 1,706 km Createsnewpossibilitiesfortheoutflowofgrains andmineralsfromproductioncentersthrough mainports. Build, operate and transfer Estimated CAPEX: US$ 7.80 billion Rail infrastructure builder and manager: Concession for railway exploitation, comprising: construction, maintenance, signaling and comunications systems, and traffic control. ConcessionTerm: 35 years Construction to be completed up to the 5th year of the concession term. Risk Mitigation: Demand Risk (Guaranteed purchase of 100% of railway operational capacity availability); Socio-environmental and Expropriation Risks (Environmental and Expropriation costs and charges limited to values pre- established in concession contracts). Environmental licensing: State-owned EPL is responsible for obtaining Previous License (LP) and will give support for obtaining the Installation Licence (LI) of construction works. Term: 30 years (Grace period: 5 years) Rate:TJLP* + 1%a.a. Real leveraged IRR: up to 16% per year, in real terms. Upfront payment of revenues due to operational capacity availability, in equivalent value of 15% of total referential CAPEX. Equity support: up to 49% of SPE** or holding’s share capital (Institutions: public banks and pension funds). Railway Concession: from Corinto (MG) to Campos (RJ) GO SP MG RJ ES BA Uruaçu Concession: Uruaçu - Campos Ilhéus Port Corinto Brumado Vitória Vitória Port Açu Port Terminal Belo Horizonte Intendente Câmara Campos Bernardo Sião To be awarded Anápolis *TJLP-LongTermInterestRate, currently5%p.a. **SpecialPurposeEntity Updatedinformationavailable atwww.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 74. 74 Ministry of Finance Railways Object Demand Concession characteristics Financing Conditions Section: Feira de Santana – Ipojuca Extension: 893 km Modernizes the northeastern railway network, linking the major ports and markets Build, operate and transfer Estimated CAPEX: US$ 3.78 billion Rail infrastructure builder and manager: Concession for railway exploitation, comprising: construction, maintenance, signaling and comunications systems, and traffic control. ConcessionTerm: 35 years Construction to be completed up to the 5th year of the concession term. Risk Mitigation: Demand Risk (Guaranteed purchase of 100% of railway operational capacity availability); Socio-environmental and Expropriation Risks (Environmental and Expropriation costs and charges limited to values pre- established in concession contracts). Environmental licensing: State-owned EPL is responsible for obtaining Previous License (LP) and will give support for obtaining the Installation Licence (LI) of construction works. Term: 30 years (Grace period: 5 years) Rate:TJLP* + 1%a.a. Real leveraged IRR: up to 16% per year, in real terms. Upfront payment of revenues due to operational capacity availability, in equivalent value of 15% of total referential CAPEX. Equity support: up to 49% of SPE** or holding’s share capital (Institutions: public banks and pension funds). Railway Concession: from Feira de Santana (BA) to Ipojuca (PE) BA SE AL PE PB Concession: Feira de Santana - Ipojuca To be awarded Recife Maceió Aracajú Salvador Porto de Recife Porto de Suape Porto de Maceió Terminal Portuário de Atalaia Velha Porto de SalvadorPorto de Aratu Salgueiro *TJLP-LongTermInterestRate, currently5%p.a. **SpecialPurposeEntity Updatedinformationavailable atwww.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 75. 75 Ministry of Finance Railways Object Demand Concession characteristics Financing Conditions Section: Lapa – Paranaguá Extension: 150 km Expands and modernizes rail access to the port of Paranaguá. Build, operate and transfer Estimated CAPEX: US$ 1.17 billion Rail infrastructure builder and manager: Concession for railway exploitation, comprising: construction, maintenance, signaling and comunications systems, and traffic control. ConcessionTerm: 35 years Construction to be completed up to the 5th year of the concession term. Risk Mitigation: Demand Risk (Guaranteed purchase of 100% of railway operational capacity availability); Socio-environmental and Expropriation Risks (Environmental and Expropriation costs and charges limited to values pre- established in concession contracts). Environmental licensing: State-owned EPL is responsible for obtaining Previous License (LP) and will give support for obtaining the Installation Licence (LI) of construction works. Term: 30 years (Grace period: 5 years) Rate:TJLP* + 1%a.a. Real leveraged IRR: up to 16% per year, in real terms. Upfront payment of revenues due to operational capacity availability, in equivalent value of 15% of total referential CAPEX. Equity support: up to 49% of SPE** or holding’s share capital (Institutions: public banks and pension funds). Railway Concession: from Lapa (PR) to Paranaguá (PR) MS PR SC RS SP RJ Concession: Lapa – Paranaguá Porto Alegre Florianópolis Rio Grande Port Pelotas Port Laguna Port Imbituba Port Itajaí Port Paranaguá Port São Sebastião Port Guaíba Port Terminal Duque de Caxias Port Terminal Cascavel Lapa Maracaju Panorama São Paulo Rio de Janeiro Curitiba Eng. Bley Mafra Campo Alto do Sul Chapecó Santos Port To be awarded *TJLP-LongTermInterestRate, currently5%p.a. **SpecialPurposeEntity Updatedinformationavailable atwww.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 76. 76 Ministry of Finance Railways Object Demand Concession characteristics Financing Conditions Section: Maracaju – Lapa Extension: 989 km Creates new logistics possibilities for the outflow of grains and other cargo from production centers through the Port of Paranaguá. Build, operate and transfer Estimated CAPEX: US$ 3.13 billion Rail infrastructure builder and manager: Concession for railway exploitation, comprising: construction, maintenance, signaling and comunications systems, and traffic control. ConcessionTerm: 35 years Construction to be completed up to the 5th year of the concession term. Risk Mitigation: Demand Risk (Guaranteed purchase of 100% of railway operational capacity availability); Socio-environmental and Expropriation Risks (Environmental and Expropriation costs and charges limited to values pre- established in concession contracts). Environmental licensing: State-owned EPL is responsible for obtaining Previous License (LP) and will give support for obtaining the Installation Licence (LI) of construction works. Term: 30 years (Grace period: 5 years) Rate:TJLP* + 1%a.a. Real leveraged IRR: up to 16% per year, in real terms. Upfront payment of revenues due to operational capacity availability, in equivalent value of 15% of total referential CAPEX. Equity support: up to 49% of SPE** or holding’s share capital (Institutions: public banks and pension funds). Railway Concession: from Maracajú (MS) to Lapa (PR) MS PR SC RS SP RJ Concession: Lapa – Paranagua Porto Alegre Florianópolis Rio Grande Port Pelotas Port Laguna Port Imbituba Port Itajaí Port Paranaguá Port São Sebastião Port Guaíba Port Terminal Duque de Caxias Port Terminal Cascavel Lapa Maracaju Panorama São Paulo Rio de Janeiro Curitiba Eng. Bley Mafra Campo Alto do Sul Chapecó Santos Port To be awarded *TJLP-LongTermInterestRate, currently5%p.a. **SpecialPurposeEntity Updatedinformationavailable atwww.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 77. 77 Ministry of Finance Railways Object Demand Concession characteristics Financing Conditions Section: Mairinque – Rio Grande Extension: 1,667 km Creates new logistics possibilities for the flow of cargo between Sao Paulo and the South Region of Brazil, linking production and consumption centers. Build, operate and transfer Estimated CAPEX: US$ 10.73 billion Rail infrastructure builder and manager: Concession for railway exploitation, comprising: construction, maintenance, signaling and comunications systems, and traffic control. ConcessionTerm: 35 years Construction to be completed up to the 5th year of the concession term. Risk Mitigation: Demand Risk (Guaranteed purchase of 100% of railway operational capacity availability); Socio-environmental and Expropriation Risks (Environmental and Expropriation costs and charges limited to values pre- established in concession contracts). Environmental licensing: State-owned EPL is responsible for obtaining Previous License (LP) and will give support for obtaining the Installation Licence (LI) of construction works. Term: 30 years (Grace period: 5 years) Rate:TJLP* + 1%a.a. Real leveraged IRR: up to 16% per year, in real terms. Upfront payment of revenues due to operational capacity availability, in equivalent value of 15% of total referential CAPEX. Equity support: up to 49% of SPE** or holding’s share capital (Institutions: public banks and pension funds). Railway Concession: from Mairinque (SP) to Rio Grande (RS) MS PR SC RS SP RJ Concession: Mairinque – Rio Grande Porto Alegre Florianópolis Rio Grande Port Pelotas Port Laguna Port Imbituba Port Itajaí Port Paranaguá Port São Sebastião Port Guaíba Port Terminal Duque de Caxias Port Terminal Cascavel Forno Port Maracaju Panorama São Paulo Rio de Janeiro Mairinque Eng. Bley Mafra Campo Alto do Sul Chapecó Santos Port To be awarded *TJLP-LongTermInterestRate, currently5%p.a. **SpecialPurposeEntity Updatedinformationavailable atwww.logisticsbrazil.gov.br Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance
  • 78. 78 Ministry of Finance Railways Study in Progress Railway Concession – High-SpeedTrain (TAV) Rio de Janeiro - São Paulo - Campinas 1st Phase Physical Description Section: Rio de Janeiro - São Paulo - Campinas Extension: 511 km The High-SpeedTrain Rio de Janeiro – Campinas will be the first high speed rail service in Brazil.The first phase includes the concession of the operation and maintenance of the system, supply and assembly of operational (signalling, electrification and telecommunication) and safety systems, rolling stock and acoustic protection, and technology transfer. Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance Viracopos Galeão Guarulhos São Paulo Campinas Rio de Janeiro
  • 79. Ports
  • 80. 80 Ministry of Finance Seaports Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance Major Brazilian Ports Macapá Belém/Miramar/Outeiros Itaqui Pecém Cabedelo Suape/Recife Maceió Aratu/Salvador Porto Sul/Ilhéus Vitória Itaguaí/Rio De Janeiro Santos/São Sebastião Paranaguá/Antonia Itajaí/Imbituba/São Francisco do Sul Porto Alegre Rio Grande Vila do Conde Santarém Manaus/ Itacoatiara Porto Velho
  • 81. 81 Ministry of Finance Seaports Port Investment Program - Bidding Blocks Block Ports Estimated Investment Increase Capacity Auction Block 1 31 terminals at: Santos, Outeiro, Santarém, Belém, Miramar andVila do Conde Ports US$ 1.5 bi 27 million tons/year Dec 2013 Block Ports Public Consultation Auction Block 2 44 terminals at: Paranaguá, Antoni- na, Salvador, Aratu and São Sebastião Ports Sep 2013 Jan 2014 Block 3 36 terminals at: Cabedelo, Fortale- za, Itaqui, Macapá, Recife and Suape Ports Oct 2013 Feb 2014 Block 4 28 terminals at: Itaqui, Niterói, Rio de Janeiro, Itajaí, São Francisco do Sul, Rio Grande, Porto Alegre andVitória Ports Nov 2013 Mar 2014 InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 Source:SpecialSecretariatofPorts Producedby:MinistryofFinance
  • 82. 82 Ministry of Finance Seaports Port Investment Program InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 Source:NationalLogistics&Planning Company(EPL) Producedby:MinistryofFinance Conditions to public ports • Terminals at public ports will be leased through public auction Main Features • 25-year term, renewable only once Standardized biddings conducted through auction by ANTAQ ContractualTerms (requirements) • Minimutm Investments • Minimum productivity • Minimum static capacity Selection Criteria Terminal in verticalized chains or with healthy competition environment • Bidding for greater handling capacity • Induction of new investments Terminals with features of provision of services to third parties • Bidding for lowest tariff • Reduction of port costs • Guarantee of isonomic access to users  Conditions to private ports • Terminalsatprivateportsmaybeleasedwithoutapublicauction,shoulditsconstructionnotconflict with another port or terminal, existing or planed.There are 62 private terminals that should obtain its lease in the next months, with a estimated investment of US$ 7.5 billion
  • 84. 84 Ministry of Finance Airports Source:CivilAviationSecretariat(SAC) Producedby:MinistryofFinance Major Brazilian Airports Brasília Goiânia Boa Vista Tabatinga Cruzeiro do Sul Rio Branco Tefé Porto Velho Manaus Santarém Altamira Macapá Belém (Val de Cans) Belém (Júlio César) Marabá Palmas Cuiabá Corumbá Campo Grande Ponta Porã Foz do Iguaçú Uruguaiana Bagé Porto Alegre Pelotas Criciúma Florianópolis Navegantes Joinville Curitiba (Afonso Pena) SP (Congonhas) Curitiba (baracher) SP (Campos de Marte) Londrina Uberaba Uberlândia RJ (Jacarepaguá) RJ Santos Dumont Macaé Campos dos Goytacazes Vitória Montes Claros Petrolina Juazeiro do Norte Fortaleza Parnaíba Guarulhos RJ (Galeão) Campinas SJ dos Campos Teresina Imperatriz Carajás Campina Grande Paulo Afonso Ilhéus Salvador Aracajú Natal João Pessoa Recife Maceió Confins BH (Carlos Prates) BH (Pampulha) 15.000.001 to 30.100.000 (3) 5.000.001 to 15.000.000 (9) 1.000.001 to 5.000.000 (15) 5000.001 to 1.000.000 (7) 100.001 to 500.000 (19) Up to 100.000 (13) Passengers per year Concessions to be granted : Galeão (Rio de Janeiro) Confins (Belo Horizonte) Concessions already granted : Guarulhos (São Paulo) Viracopos (São Paulo) Brasília
  • 85. 85 Ministry of Finance Airports Airport Investment Program InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 Source:CivilAviationSecretariat(SAC) Producedby:MinistryofFinance Airport International Pax - 2012 Domestic Pax - 2012 Estimated Investment Auction Concession Term Situation Guarulhos International (GRU) 11,387,443 20,958,079 US$ 3.1 billion Feb 2012 20 years Granted Viracopos International (VCP) 75,610 8,627,690 US$ 5.1 billion Feb 2012 30 years Granted Brasilia International (BSB) 409,975 15,419,553 US$ 1.8 billion Feb 2012 25 years Granted Galeão International (GIG) 4,190,433 12,973,780 US$ 2.45 billion Nov 2013 25 years To be Granted Confins International (CNF) 443,955 9,834,536 US$ 1.52 billion Nov 2013 30 years To be Granted
  • 86. 86 Ministry of Finance Airports Schedule for the concessions of Galeão and Confins airports 2013 Release of Auction Notices TCU* and Public Hearings AuctionStudies May Jun Jul Aug Sep Nov *TCU-FederalCourtofAuditors Source:CivilAviationSecretariat(SAC) Producedby:MinistryofFinance
  • 87. 87 Ministry of Finance Airports Galeão - Summary Chart Galeão - Summary Chart Airport Area: 17,881,697m² Area for Apron: 712,895 m2 Aircraft Capacity: -T1: 19 boarding gates + 12 remote positions -T2: 19 boarding gates + 12 remote positions - 15 positions for cargo aircraft PassengerTerminals: Capacity: 17.4 million Pass/Yr Area: T1 - 147,834 m² T2 - 132,847 m² Parking: 4,310 parking spaces CargoTerminal: 46,500 m² Cargo Movements: 87,876 ton Staff Employees: 958 Number of Passengers, in million Passenger Profile (2012), in million Int Dom 13.0 4.2 0 6 12 18 2012 2011 2010 2009 2008 2007 2006 2005 2004 2003 2011-2012: 17.5% Average Growth = 16% Source:CivilAviationSecretariat(SAC) Producedby:MinistryofFinance
  • 88. 88 Ministry of Finance Airports Galeão – Financial Conditions Object: • Expansion, maintenance and operation of the Antônio Carlos Jobim International Airport (Galeão Airport) with a total area of 17,880,000 m2 Contract criteria: • Term: 25 years • Consortium:INFRAERO,thegovernmentownedcompany,willhold49%oftheConcessionairecapital; private leveraged (51%) • Periodic review of the capex program and Investment triggers • Bidding Criteria: highest bid + variable fee • Minimum bid: US$ 2.09 billion • Variable fee: 5% of the gross revenue • CAPEX: US$ 2.45 billion • Project IRR: 6.63% p.a. • OPEX: US$ 4.63 billion Financing conditions*: • Credit term: 14 years • Grace period: 2 years • Debt: up to 80% of the capex • Interest Rate: TJLP (currently at 5%) + 0.9% + risk spread (0.46% to 3.57%) per year *BNDESfinancingconditionsapplied toairportsalreadygranted(Guarulhos, ViracoposandBrasília). InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 Source:CivilAviationSecretariat(SAC) Producedby:MinistryofFinance
  • 89. 89 Ministry of Finance Airports Galeão- Estimated Demand 10 30 50 70 2038203320232013 60.3 50.1 34.5 19.2 MillionPassengers Source:CivilAviationSecretariat(SAC) Producedby:MinistryofFinance Year 2013 2023 2033 2038 Passengers 19,269,199 34,537,602 50,138,243 60,365,874
  • 90. 90 Ministry of Finance Airports Confins - Summary Chart Confins - Summary Chart Airport Area: 15,010,000 m² Area for Apron: 211,437 m2 Aircraft Capacity: Apron 1: 9 boarding gates + 9 remote positions Apron 2: 7 positions for general aviation + 1 helipad Apron 3: 2-4 positions for general aviation PassengerTerminal: Capacity: 10.3 million Pass/Year Area: T1 - 60,305 m² Vehicle Parking : 2,005 parking spaces CargoTerminal: 9,880 m² Cargo Movements: 27,163 ton Staff Employees: 344 Number of Passengers, in million Passenger Profile (2012) , in million Int Dom 9.8 0.4 2011-2012: 9.5% Average Growth = 46.3% Migration of Pampulha to Confins 0 4 8 12 2012 2011 2010 2009 2008 2007 2006 2005 2004 2003 Source:CivilAviationSecretariat(SAC) Producedby:MinistryofFinance
  • 91. 91 Ministry of Finance Airports Cofins - Financial Conditions Object: • Expansion, maintenance and operation of theTancredo Neves International Airport (Confins Airport) with a total area of 15,010,000 m2 Contract criteria: • Term: 30 years • Consortium: INFRAERO, the government owned company, will hold 49% of the Concessionaire capital; private leveraged (51%) • Periodic review of the capex program and Investment triggers • Bidding Criteria: highest bid + variable fee • Minimum bid: US$ 476.5 million • Variable fee: 5% of the gross revenue • CAPEX: US$ 1.52 billion • Project IRR: 6.63% p.a. • OPEX: US$ 1.57 billion Financing conditions*: • Credit term: 14 years • Grace period: 2 years • Debt: up to 80% of the capex • Interest Rate:TJLP (currently at 5%) + 0.9% + risk spread (0.46% to 3.57%) per year *BNDESfinancingconditionsapplied toairportsalreadygranted(Guarulhos, ViracoposandBrasília) InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 Source:CivilAviationSecretariat(SAC) Producedby:MinistryofFinance
  • 92. 92 Ministry of Finance Airports Confins – Estimated Demand 5 14 23 32 41 50 2043203320232013 28.1 18.1 10.9 43.3 MillionPassengers Year 2013 2023 2033 2043 Passengers 10,993,890 18,162,209 28,165,165 43,334,690 Source:CivilAviationSecretariat(SAC) Producedby:MinistryofFinance
  • 94. 94 Ministry of Finance OilandGas InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 Source:NationalAgencyofPetroleum, NaturalGasandBiofuels(ANP)and MinistryofMinesandEnergy(MME) Producedby:MinistryofFinance 11th Round – Bidding Results (May 2013) • 142 bought blocks, from 289 offered at the auction • US$ 1.22 billion in signature bonus • US$ 3.0 billion in the Minimum Exploratory Program commitment • Local Content offers indicates good possibilities for execution of the previous commitments regarding earlier bidding rounds • 30 companies bought blocks at the bidding round - 18 companies from 11 different countries
  • 95. 95 Ministry of Finance OilandGas Source:NationalAgencyofPetroleum, NaturalGasandBiofuels(ANP)and MinistryofMinesandEnergy(MME) Producedby:MinistryofFinance 11th Round – Bidding Result (May 2013) Brasília Pernambuco-Paraíba Barreirinhas Pará-Maranhão Amazonas River Mouth Ceará Parnaíba Tucano and Reconcavo Basins Potiguar Onshore Basin Potiguar Offshore Espírito Santo Onshore/Offshore Brought Blocks Offered but not sold Offshore Sedimentary Basin Pre-Salt Limit
  • 96. 96 Ministry of Finance OilandGas Source:NationalAgencyofPetroleum, NaturalGasandBiofuels(ANP)and MinistryofMinesandEnergy(MME) Producedby:MinistryofFinance 11th Round – Bidding Result (May 2013) Sedimentary basin State Bought Blocks Area (km2 ) Sergipe-Alagoas onshore AL 11 320.89 Foz do Amazonas AP 14 10,543.55 Pernambuco-Paraíba PB 1 476.95 PE 3 1,776.23 Tucano Sul BA 21 3,789.67 Espírito Santo offshore ES 6 4,328.40 Espírito Santo onshore ES 6 178.73 Recôncavo BA 15 443.13 Ceará CE 6 3,642.32 Potiguar offshore CE 3 2,303.23 RN 1 767.38 Potiguar onshore RN 14 411.80 Barreirinhas MA 19 9,997.40 Pará-Maranhão MA 2 1,538.57 PA 0 - Parnaíba (onshore) PI 14 42,143.81 MA 6 17,620.43 TOTAL 11 142 100,282.49
  • 97. 97 Ministry of Finance OilandGas InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 Source:NationalAgencyofPetroleum, NaturalGasandBiofuels(ANP)and MinistryofMinesandEnergy(MME) Producedby:MinistryofFinance 1st Round of production sharing – Pre-Salt layer Date: October 21, 2013 Area name: Libra • 1,548 sq km • Deep water of Santos Basin • Well with tested oil discovery • Estimative of 42 billion bbl of oil in situ, indicating recovery of 8 to 12 billion barrels Signature Bonus: R$ 15 billion (~US$ 6.5 billion) Judgement criteria: Percentage of profit oil for the Government (minimum of 40% in average along the contract period) Local Content • 37% at Exploratory Phase • From 55% to 65% at Production Development Phase Jul Sep Oct21st Dec 2013 Preliminary auction notice, areas and data Release of auction notice Auction Contract Signature
  • 98. 98 Ministry of Finance OilandGas Source:NationalAgencyofPetroleum, NaturalGasandBiofuels(ANP)and MinistryofMinesandEnergy(MME) Producedby:MinistryofFinance Brazil Pre-Salt layer – Bidding under production sharing regime Pre-Salt Boundaries Estimated Recoverable Volumes Libra 8 to 12 bi boeFranco 2.0 to 5.5 bi boe Florim 0.1 to 0.4 bi boe Sul de Guará 0.1 to 0.3 bi boe Peroba 1.1 to 1.8 bi boe South and NE of Tupi 0.5 to 0.7 bi boe Iara Surroundings 0.6 to 0.8 bi boe Lula 8.3 bi boe Iara 3 to 4 bi boeSapinhoá 2.1 bi boe Pão de Açúcar 1.2 bi boe Parque das Baleias 1.5 to 2 bi boe Rio de Janeiro São Paulo Espirito Santo Proved Reserves (2012): 18.2 bi boe Granted area: 42 thousand sq km (28%) Cession area: 3.74 thousand sq km (2,5%) Estimated Volumes (06/2013) 28.5 to 39.1 billion boe • At the Pre-Salt evaluated areas, expected recoverable volumes could reach twice the actual proved reserves
  • 99. 99 Ministry of Finance OilandGas Source:NationalAgencyofPetroleum, NaturalGasandBiofuels(ANP)and MinistryofMinesandEnergy(MME) Producedby:MinistryofFinance 12Th Bidding Round: auction scheduled for November, 2013 Concession of areas under rules and terms established by Law 9,478/1997 Focus on natural gas – conventional and unconventional resources Blocks: 240 • 164,500 km² • 7 Sedimentary Basins Bidding judgment criteria: • Signature Bonus (40%) - Minimum for each block in the Auction Notice • Minimum Exploratory Program (40%) • Local Content (20%) - Minimum and maximum values in Auction Notice
  • 100. 100 Ministry of Finance OilandGas Source:NationalAgencyofPetroleum, NaturalGasandBiofuels(ANP)and MinistryofMinesandEnergy(MME) Producedby:MinistryofFinance Areas with potential for non-conventional resources Oil and Gas in Brazil Sedimentary Basin Tacutu Solimões Acre Madre de Dios Amazonas Alto Tapajós Parecis Pantanal Paraná Camamu-Almada Parnaíba Barreirinhas Bananal São Francisco Recôncavo Amazonas River Mouth Pará-Maranhão Potiguar Rio do Peixe Pernambuco-Paraíba Sergipe-AlagoasTucano Espírito Santo Campos Santos
  • 102. 102 Ministry of Finance Electricity Brazilian investments in the electricity sector auctions – 2013 to 2017 Estimated Expansion Investments (US$ billion) Power 33,288 MW 53.1 Transmission 21,164 km 11.0 Total 64.1 • Electricity transmission lines • Power to be contracted Auction Length (Km) Investment (US$ billion)* 2013 4,745 2.4 2014-2017 Approved Projects 11,846 6.0 Other Projects 4,573 2.6 Total 21,164 11.0 Sources Capacity (MW) Investment (US$ billion) Hydro 21,689 35.4 Other Renewable Sources (Wind, Biomass and Small Hydro) 10,099 16.4 Thermal 1,500 1.3 Total 33,288 53.1 Source:EnergyResearchOffice(EPE) Producedby:MinistryofFinance *Includingestimatedinvestmentin substations InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30
  • 103. 103 Ministry of Finance Electricity Source:EnergyResearchOffice(EPE) Producedby:MinistryofFinance Electricity Auctions • Modalities • New Energy Auctions A-3 and A-5: servicing expected demand growth • Reserve auctions: ensuring greater security of supply • Structuring Project Auctions: special conditions • Bidders • Public or private companies • National or foreign companies •Winners • Lowest bid • Winners of the new energy auctions sign long-term contracts (15 to 30 years) with distributors and receive concessions (in the case of hydropower plants) • Indexation • IPCA (Consumer Price Index) • Financing • Use of the PPA (Power Purchase Agreement) as collateral for project financing by the BNDES • Risk mitigation • Only projects with prior environmental licenses are auctioned off
  • 104. 104 Ministry of Finance Electricity HPP-HydroPowerPlant ANEEL-NationalElectricityAgency Source:EnergyResearchOffice(EPE) Producedby:MinistryofFinance Maintechnicalrequirementsforparticipationintheelectricityauctions Type ANEEL Registry Prior Environmental License Access Information Energy Production Certification Proof of Right of Local Use Proof of Availability Water Use Grant Wind Power Plant X X X X X Hydroelectric Plant (HPP and small Hydro) X X X X Thermoelectric Plant (Biomass and fossil) X X X X X X • A project’s technical and environmental viability must be ensured to participate in the electricity auction • Several requirements must be met to prove viability, such as:
  • 105. 105 Ministry of Finance Electricity Main financial requirements for participating in electricity auctions and for signing power contracts • Bid guarantees due to ANEEL • Foreachprojecteligibletoparticipateintheauction,biddersmustsubmitbidguaranteesduetoANEEL 1. For Projects without grants: 1% of the investment value 2. For Projects with grants: US$ 870 per lot of energy to be offered (1 lot = 0.1 average MW) • Assurance of Faithful Execution of Contract •The auction winners must collect 5% of the investment value declared to the EPE •The warranties will decrease in value as the construction phase of the power plant advances AverageMW(MWm)–EnergyUnit (8,760MWhoveranyearlyperiod) Source:EnergyResearchOffice(EPE) Producedby:MinistryofFinance
  • 106. 106 Ministry of Finance Electricity BNDES FINEM (Financing to Enterprises) Financial Aspects Hydro Power Plant (HPP) Thermal Power Plant (TPP) Wind, Biomass and Small Hydro • Current credit conditions: • Leverage: up to 70%; • Amortization period: up to 20 years; • Grace period: up to 6 months after commercial operation date; • Interest rate:TJLP**+0.9%+credit risk spread. • Current credit conditions: • Leverage: up to 70% (60% coal), should observe DSCR* ≥ 1.2; • Amortization period: up to 16 years; • Grace period: up to 6 months after commercial operation date; • Interest rate:TJLP**+0.9% +credit risk spread. • Current credit conditions: • Leverage: up to 80%, should observe DSCR * ≥1.2; • Amortization period up to 20 years (16 years for wind); • Grace period: up to 6 months after commercial operation date; • Interest rate:TJLP**+0.9%+credit risk spread. *DSCR:debtservicecoverageratio **TJLP:LongTermInterest Tax,currently5.0% Source:National Bank of Economic and Social Development (BNDES)– ConsultationinJan/2013 Producedby:MinistryofFinance
  • 107. 107 Ministry of Finance Electricity Source:EnergyResearchOffice(EPE) Producedby:MinistryofFinance Electricity Auctions: main results • August 2013 Reserve Auction • August 2013 Power Auction InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 Type Projects able to bid Auction Results Bid Capacity (MW) Number of Participants Bid Capacity (MW) Number of Participants Total Amount (US$ million) Wind Power Plant 8,999 377 1,505 66 2,373 Type Projects able to bid Auction Results Bid Capacity (MW) Number of Participants Bid Capacity (MW) Number of Participants Total Amount (US$ million) Biomass 919 16 647 9 815 Coal 1,840 3 - - - HPP (less than 50 MW) 376 16 219 9 586 HPP SINOP 400 1 400 1 773 Total 3,535 36 1,266 19 2,174 Number of Auctions Projects Capacity (MW) Investment (US$ billion) 23 490 60,892 100 • Consolidated results of new energy auctions from 2005 to 2012
  • 108. 108 Ministry of Finance Electricity Source:EnergyResearchOffice(EPE) Producedby:MinistryofFinance Hydropower Expansion: 2013 electricity auctions InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 • November 2013 Auction • Hydropower Expansion: December 2013 auction Type Projects able to bid Bid Capacity (MW) Number of Participants Wind Power Plant 15,042 629 Solar 2,838 119 Small Hydro 295 16 Biogas 39 2 Biomass 504 15 Natural Gas 469 2 Total 19,187 783 Auction Hydropower Plant River/State Capacity (MW) Total Capacity (MW) Estimated Investments (US$ billion, constant prices, Dec/2012) 2013 São Manoel Teles Pires/ MT-PA 700 1,021 1.8 Cachoeira Parnaíba/ PI 63 Ribeiro Gonçalves Parnaíba/ PI 113 Itaocara Paraíba do Sul/RJ 145
  • 109. 109 Ministry of Finance Electricity Source:EnergyResearchOffice(EPE) Producedby:MinistryofFinance Hydropower Expansion: auctions from 2014 to 2017 InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 Auction Hydropower Plant River/State Capacity (MW) Total Capacity (MW) Estimated Investments (US$ billion, constant prices, Dec/2012) 2014 Davinópolis Paranaíba/ MG-GO 74 7,495 11.3 Foz do Piquiri Piquiri/ PR 93.2 Ercilândia Piquiri/ PR 87.1 S LuízTapajós Tapajós/ PA 6,133 Água Limpa Das mortes/ MT 380 Comissário Piquiri/ PR 105 Foz Piquiri Piquiri/ PR 101 Telêmaco Borba Tibagi/ PR 109 Paranhos Chopim/PR 63 Tabajara Ji-Paraná/RO 350 2015 Jatobá Tapajós/PA 2,336 3,249 5.4Castanheira Arinos/ MT 192 Itapiranga Uruguai/SC-RS 721 2016 Torixoréu Araguaia/ GO-MT 408 1,117 2.3 Bem Querer Branco/ RR 709 2017 Riacho Seco S. Francisco / PE-BA 276 8,407 13.7 Salto Augusto Baixo Juruena/ MT-AM 1,461 S. Simão Alto Juruena/ MT-AM 3,509 Pompeu S. Francisco / MG 209 Marabá Tocantins / PA-MA 2,160 Prainha Aripuanã/ AM 792 Total 20,268 32.7
  • 110. 110 Ministry of Finance Electricity HPP São Manoel - Fact sheet •Teles Pires River • Capacity: 700 MW • Firm Energy: 400 average MW • Number of generating units: 5 • Gross Head: 23.9 m • Spillway Crest: 165 m. • Max normal water level (reservoir): 161 m • Normal water level downstream: 138.2 m • Reservoir Area (normal water levels) ~ 70.8 km² Estimated Investment US$ 1.0 billion Indigenous Land Cayabi 0 2,5 5 10 15 20 N Legend HPP São Manoel HPP São Manoel Reservoir 0 2,5 5 10 15 20 Declared Indigenous Land State border line MATO GROSSO Novo Planeta Paulão Mutum HPP São Manoel PARÁ Source:EnergyResearchOffice(EPE) Producedby:MinistryofFinance InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30
  • 111. 111 Ministry of Finance Electricity Source:EnergyResearchOffice(EPE) Producedby:MinistryofFinance The development of wind power in Brazil • Operating and contracted capacity •To be contracted in 2013-2017 auctions 0 2000 4000 6000 8000 10000 10,130 8,846 7,882 5,197 2,189 1,750 1,417 927 607337248237292322 2017 2016 2015 2014 2013 2012 2011 2010 2009 2008 2007 2006 2005 2004 2003 MW InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 Capacity (MW) Investment (US$ billion) 4,215 7.7
  • 112. 112 Ministry of Finance Electricity Source:EnergyResearchOffice(EPE) Producedby:MinistryofFinance The development of bioelectricity in Brazil • Operating and contracted capacity • To be contracted in 2013-2017 auctions 0 2,000 4,000 6,000 8,000 10,000 2017 2016 2015 2014 2013 2012 2011 2010 2009 2008 2007 2006 2005 1,755 2,584 2,590 3,910 4,969 6,822 7,874 8,081 8,936 9,035 9,035 9,085 9,185 MW Capacity (MW) Investment (US$ billion) 2,513 2.4 InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30
  • 113. 113 Ministry of Finance Electricity Source:EnergyResearchOffice(EPE) Producedby:MinistryofFinance Other energy sources to be contracted in 2013 – 2017 auctions • Small hydropower plants • Additional expansions depend on the effective exploration of unconventional gas • Thermal power stations Capacity (MW) Investment (US$ billion) 1,500 1.3 Capacity (MW) Investment (US$ billion) 1,000 2.6 InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30
  • 114. 114 Ministry of Finance Electricity Source:EnergyResearchOffice(EPE) Producedby:MinistryofFinance Transmission Line Auctions • Bidders • Legal Entities: National or Foreign • Equity Funds: alone or in a consortium • Clearance • Clearance after auctions and publication of winning bids •Winners • Bidder with lowest Allowed Annual Revenue (RAP) •Winners will sign long-term contracts (30 years) • Regulated contracts • Indexation by IPCA (Consumer Price Index) • Contracts submitted to the Periodic Rate Reviews • Financing • RAP as collateral for financing by the BNDES
  • 115. 115 Ministry of Finance Electricity Source:EnergyResearchOffice(EPE) Producedby:MinistryofFinance Transmission Line Auctions: sequence of events -2.8 Public Notice of Auction ANEEL approval of technical capacity of the winners of the auction TL Auction Winners deliver documentation to ANEEL Celebration of concession contract between winner and ANEEL Auction held at BM&FBOVESPA Approval of Auction Results Auction application and bid guarantees due to ANEEL Accepted bid guarantee instruments: cash deposit, surety bond, bank guarantee, Brazilian Government Bonds (1% of estimated investment) Replacement of bid guarantees with the guarantee of faithful execution of the contract (5% of estimated investment)
  • 116. 116 Ministry of Finance Electricity BNDES FINEM (Financing to Enterprises) Financial Aspects • Access to financing available to national and international companies with head offices and management in Brazil, and legal entities of public law • Current credit conditions: • Leverage: up to 70% • Total Loan Period: up to 14 years • Grace period: up to 6 months after commercial operation date. • Interest rate:TJLP*+1.3%+credit risk spread Source:EnergyResearchOffice(EPE) Producedby:MinistryofFinance *TJLP:LongTermInterestTax, currently5.0%
  • 117. 117 Ministry of Finance Electricity Source:EnergyResearchOffice(EPE) and National Electricity Agency(ANEEL) Producedby:MinistryofFinance Transmission Line Past Auctions: main results • Transmission Line Auction of Dec, 2012: Main Results • Number of applicants: 15 (includes state-owned companies, private groups, 4 foreign groups, and equity funds) • TotalTL** tendered: 3,822 Km • Estimated investment: US$ 1.7 billion • Average discount: 21.7% • Stiff competition: for example, in“500 kV Estreito - Itabirito”transmission line auction, there were 305 bids that resulted in a 16.6% discount *currentvalues **TL–TransmissionLine InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 • Consolidated results of auctions from 2000 to 2012 Number of Auctions Length (km) Investment (US$ billion) (*) 24 51,000 13.9
  • 118. 118 Ministry of Finance Electricity Source:EnergyResearchOffice(EPE) Producedby:MinistryofFinance Main Projects: north-southeast expansion Physical Description Goals • Main section: Connects the North and Southeast Region, with DC Link between the states of Pará and Minas Gerais • Length: • 2,050 km on Direct Current • 2,244 km on Alternating Current • Promotes interconnection between two major subsystems, enabling the exchange of electricity between regions North and Southeast. • Increase of 4,000 MW in exchange capacity between the North and Southeast Regions Financial Aspects • ConcessionTerm: 30 years • Estimated Investment: US$ 2.6 billion Project Requirements • TLs in Direct Current: 800 kV • Increases in Existing System • Bidding in 2013 • Winning Bidder: the lowest RAP (Allowed Annual Revenue) (2) (2) 800 KV DC 2,050 Km Bipole 1 500 KV AC 2,244 Km Terminal Minas TOCANTINS Miracema Colinas Itacaúnas MATO GROSSO GOIÁS Paraupebas PARÁ MARANHÃO Xingo Picuruí InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30
  • 119. 119 Ministry of Finance Electricity MainTL Projects to be Auctioned in 2013 2nd semester 2013 - transmission lines (EPE proposal) Estimated Investment of US$ 2.4 billion (*) Source:EnergyResearchOffice(EPE) Producedby:MinistryofFinance *Includesestimatedinvestmentin substations InthefirsthalfofSeptember2013, theaverageexchangeratewas approximatelyUS$1= R$2.30 Associated Projects Projects State Voltage (kV) Length (Km) Investment (US$ billion) To meet electricity demand growth TL Itabirito 2 –Vespasiano 2, CS MG 500 90 0.1TL Barro Alto – Itapaci, C2 GO 230 68 TL Candiota (Presidente Médici) – Bagé 2 RS 230 50 Expansion S/SE TL Itatiba – Bateias SP/PR 500 390 0.2 Expansion before Belo Monte TL Marimbondo II - Campinas SP 500 370 0.3TL Araraquara 2 - Itatiba, CS SP 500 198 TL Araraquara 2 - Fernão Dias, CS SP 500 240 ExpansionoftheInterconnectionN/SE TL Xingu –Terminal Minas 800 kV (CC – Bipolo 1) PA/SP 800 2,050 1.3 To meet electricity demand growth TL 230 kV Miranda – Chapadinha II C1 MA 230 140 0.3 TL 230 kV Coelho Neto – Chapadinha II C1 MA 230 78 TL 230 kVVila do Conde -Tomé-Açu C2 PA 230 120 TL 230 kV Imperatriz – Porto Franco C2 MA 230 111 TL 230 kV Ribeiro Gonçalves – Balsas C2 MA 230 95 TL 230 kVTrindade – Firminópolis GO 230 88 Integration of isolated systems TL Rio Branco – Feijó AC 230 357 0.2 TL Feijõ – Cruzeiro do Sul AC 230 300 Total 4,745 2.4