BUDGETS & CASHFLOWS

Sample Exam Q1
When a main contractor is forecasting his turnover for the coming year, before an overall
picture can be arrived at, he must take account of all current and potential work.

   (a) Compare a list of the different types of projects which should be taken into
       account and critically evaluate the importance of each project type in the overall
       turnover calculation.
   (b) Critically explore why a main contractor needs to forecast his turnover for the
       current year including what problem areas he may face when compiling his data.

Ans:
(a)
Current Contracts:             Work in progress/ contracts part complete / Signed contracts not
                               yet started
These are definite contracts for which the value of is, definite and known.

Probable Contracts:           Phased works - 2nd, 3rd Phase / Negotiated / Private Development

Possible Contracts:           Incoming Tenders / Client Base / Prequalification / Negotiation

Tender Conversion Rates:      Analysis of tender success rates / ratio 1:4 etc / Historical
                              data / turnover & proit / experience / project suitability /
                              expansion programme

Information Collection:
Current Project Value + Probable Project Value +
Possible Project Value (tender Conversions) =
- Basis for Turnover Forecast
- Profit Forecast
- Overheads allocation
- Possible shortfalls


(b) To determine staff levels for coming year and thus wages and salary expenses.
       To determine if he can cover overheads or needs to make cuts
       To determine if downsizing needs to be considered
       To determine if borrowing or overdraft facilities need to be arranged or amended

       Problems when compiling data include:
         o Only current work is definite, rest is not guaranteed
         o Probable/possible contracts are reliant on economic climate which is vague
         o Tendering is unpredictable
Sample Exam Q2
      (a) Describe in detail the methods used by main contractor to isolate the profit
          amount in a newly awarded contract.
      (b) In your opinion, how can profit margins on a project change from tender
          submission to contract award?
Ans:
(a)
      o   Start with the original tender
      o   Check tendered prelims & profit
      o   Do sub-contractor analysis (possible increase in profit on packages once awarded)
      o   Reprice materials
      o   Consider positives & negatives – Risk Assessment
      o   Full preliminaries assessment

(b)
      o   Better buying on subcontractor packages & materials
      o   Errors
      o   Variations
      o   Claims
      o   Over-spend on prelims

Sample Exam Q3
(a) What is a cashflow forecast and how is it completed?
(b) How is a cashflow forecast beneficial both to the Main Contractor and the client?

Ans:
(a) A cash flow forecast is a schedule or graph which plots the amount of turnover on a
given project against actual programme dates. This can also be described as an S-curve.
The programme of works and the priced BOQ is used when compiling a cashflow
forecast.

(b) Benefits:            Contractor                  Client
                         - Dates for incoming monies - Estimate dates for outgoing monies
                         - Bank Reference            - Know when need to draw down
                                                     Money
                         - Check performance

Sample Exam Q4
Once a tender has been awarded to a main contractor, why is it useful for him to prepare
a preliminaries budget for the contract and how is this budget used?

Ans:
   The preliminary costs on a contract are a particular area where a job can go wrong
      Prelims can often be under-estimated at tender stage
      Often more supervision may be needed thus increasing costs
      The contract can run over on programme thus increasing prelims also

INTERIM VALUATIONS

Sample Exam Q5
   (a) Why are interim valuations of such importance to a main contractor?
   (b) What are the main components of an interim valuation?

Ans:
(a)
- Important to ensure full and timely payment for work carried out
- Interim valuation may be only source or income for contractor to fund building
  operation
- Vital for main contractors cashflow
- RIAI Clause 35, IEI Clause 60 - covers interim payment policy

(b)
Valuation should be gross value of work less retention, advance payments and amount
due on previous interim cert
Following should be included in valuation:
     Preliminaries
     Measured Works
     Valuation of architects instructions or variations
     Remeasurement of provisional items, prime cost sums and provisional quantities
     Valuation of nominated sub-contractors and suppliers
     Unfixed material son site and where allowed materials off site
     Fluctuations, where allowed within contract provisions

Sample Exam Q6

What are the different formats used for compiling an interim valuation and give examples
where different formats are used?

Ans:
Stage Payment Method:
       o Usually used when constructing units of a similar nature ie housing project
       o Must understand how project will be construction before establishing stage
          descriptions
       o Produce a schedule in line with programme
       o BOQ forms basis foe compiling stage value
       o Valuations simple to complete by ticking off completed units or percentage
          complete
Individual Item Assessment Method:
    o Usually used for once off project type eg: factory etc
    o Scroll through BOQ item by item and put percentage complete or site
       measurement against each item


Sample Exam Q7

How are preliminaries dealt with when compiling an interim valuation?

Ans:
Several formats for including prelims on valuation:
- Really dependant on level of detail given when tendering
- Can be priced against each item – sub divided into time related and fixed
- Lump sum based on % of work done basis
- Lump sum divided evenly among interim valuation dates

Agreement on prelims should be made prior to or at first interim valuation
Lump sum divided evenly among months can result in under payment as in early stages
there is large portion expended on site set up. Contractor may decide to font load to cover
this early expense.
Prelims:
Advantage: guaranteed a block of money every valuation
Disadvantage: If BOQ under-measured or lot of variations at BOQ rates, then prelims
may overrun

Undervaluing prelims:
Commercial decision to run with high BOQ rates and only small figure for prelims
Advantage: High BOQ rates for remeasures and variations
Disadvantage: Money against prelims will not cover actual – if little work done on site
then low valuation

Sample Exam Q8

(a) Is a main contractor entitled to payment for unfixed materials on and off site?

(b) In your opinion is this of importance to the main contractor?

Ans:
(a) Contracts generally allow for payment of unfixed material on site if:
       - Not brought to site prematurely
       - Adequately stored
       - Protect from weather

       Payment for material off site is at the sole discretion of the architect.
- Agreement should be made prior to manufacture
       - Proof of ownership may be required by client – vesting certificate
       - Materials will have to be set apart from other materials and marked with
         employers name

(b) Payment for these materials are important to contractors as:
          o They can account for a large % of an interim valuation value
          o Has a major effect on a contractors cashflow
          o Long lead in times means early ordering and thus parting with money far
              in advance of fixing on site
          o Material may have to be ordered in full loads and then used intermittently

FINAL ACCOUNTS / VARIATIONS
Sample Exam Q9

What are the key components of a final account submission?
Ans:
Included in Final Account:
     Preliminaries
     Measured Works
     Valuation of architects instructions or variations
     Remeasurement of provisional items, prime cost sums and provisional quantities
     Valuation of nominated sub-contractors and suppliers
     Fluctuations, where allowed within contract provisions

Preparation:
                             Contract Sum (Excl VAT)

Omissions:                   - PC Sums
                             - Provisional Sums
                             - Provisional Quantity Items
                             - Valuation of omitted work resulting from architects instructions
                             - Agreed deductions due to defects etc

Additions:                   - Agreed totals for nominated subbies & suppliers including
                               attendances & profit
                             - Valuation of variations
                             - Valuation of expended provisional sums and approximate
                               quantities
                             - Amounts established under loss and expense

                             - Price fluctuations is applicable
                             - 50% retention
Sample Exam Q10

(a) What are the variations and where do they occur?
(c) What are the four main methods of pricing variations?

Ans:
(a) “A variation is defined as the alteration or modification of the design, quality or
    quantity of the works” Ivor Seeley

Variations and extras occur when:
           o There is a discrepancy between the contract drawings/BOQ/architects
               instruction etc
           o Complying with statutory requirements
           o Alterations to design, quality or quantity of work
           o Restoration works in making good damage
Should get architects instruction of CVI, agree costs before commencing, keep records

(b) Four methods of pricing variations include:
                          1. BOQ rates – similar work
                          2. Adjusted BOQ rates – if similar work but different
                             conditions
                          3. Build Up New Rate – no similar work in BOQ
                          4. Dayworks – impossible to measure or foresee

SUB-CONTRACTORS
Sample Exam Q10

Why is it common for main contractors to subcontract a large percentage of their work?
Include what you perceive to be the advantages and disadvantages.

Ans:
Advantages:
   o Pass the potential risk on to others
   o No obligation in respect to long term employment – lower costs – no labour
      disputes
   o Non-productive overtime eliminated
   o Reduced problems with standing time due to inclement weather
   o Specialist areas covered
   o Cost certainty / possible savings i.e. plant

Disadvantages:
   o Contractor must monitor quality of subbies work
   o Contractor is fully responsible for subbies work, quality, programme and cost
   o Contractors reputation can be damaged by poor performance subbies
   o Disputes with subbies often arise
Sample Exam Q11

When a sub contractor submits a quotation for a given work package, there may be issues
surrounding the price which will have to be taken into account when the Commercial
Manager is analysing that quotation.

Outline what issues may arise, and also factors other than price which should be taken
into account when procuring a subcontractor.

Ans:
   o   Price may be incomplete
   o   Specification may be qualified – ie not pricing what you are supposed to
   o   Subcontractor may have inserted his own conditions
   o   Price may be subject to huge attendance

Other factors:
   o Unable to meet programme
   o Poor record on quality
   o No expertise
   o Too much work on at current time
   o No supervision
   o Reputation for EOT’s and/or disputes

Sample Exam Q12

   (a) Draw a flow chart mapping the procedures carried out by a commercial manager
       from subcontractor procurement to final account.
   (b) Give a brief narrative on various forms used when carrying out the above
       procedures.

Ans:

                            PROCUREMENT SCHEDULE

                              INVITATION TO TENDER

                   ANALYSE SUB-CONTRACTOR QUOTATIONS

                                PRE-ORDER MEETING

                          PLACE ORDER/SUB-CONTRACT

                           PAYMENTS & CERTIFICATES
FINAL CERT/ REMEASURE

Procurement schedule
                           o   Project broken down into work packages
                           o   Key dates inserted
                           o   Projected start and completion dates from programme entered
                           o   Actual dates eventually recorded
                           o   Document updated throughout project

Invitation to Tender Includes:
                          o Site location
                          o Names of consultant and employer
                          o Main contract and sub contract conditions
                          o Fixed or fluctuating price
                          o Schedule of applicable dayworks
                          o Return date
                          o Site access
                          o Contract period for main contract
                          o Start date and duration of subcontract works
                          o Discount levels required
                          o Details of attendances

Analyse Sub Contractor Price
                        o Price important but not only criteria for award
                        o Returned quotations compared against BOQ rates
                        o All returned quotes analysed
                        o Checked item by item
                        o Could be priced differently ie lump sum, rates etc
                        o Compare like with like

Sub Contract Order:
                           o   Full schedule of BOQ items
                           o   Schedule of drawings sent at tender stage
                           o   Dates for commencement and completion
                           o   Full price including any discounts etc
                           o   Pre-contract correspondence
                           o   Project specific details such as retention etc

Sub Contractor Payments:
                           o QS must monitor/access/and sanction all payments
                           o Subbie valuations should coincide with main contract
                             valuations
                           o Can help main contactor with their valuation and CVR’s
o Should check cumulative payments do not exceed order
                           and if so
Overpayment, because:
                         o   Work carried out without instruction
                         o   Additional works not recorded
                         o   Misrepresentation of agreement
                         o   Dayworks

Sub Contractor Final Account
                        o Agree measures
                        o Agree variations
                        o Deduct counter charges
                        o Retention
                        o Final Certificate

COST VALUE RECONCILATIONS (CVR’s)

Sample Exam Q13

CVR’s - How are they used?

Ans:

   o Used to compare the actual costs allocated to a project against the value of works
     carried out, measured and valued at contract rates plus the value of materials on
     site
   o Basically monitors project performance in terms of labour, plant, materials etc
     against original tender figures – flags over runs
   o Can be used to compare projects profitability/turnover against budgeted or
     forecasted figures
   o Can be used when assessing tenders on similar projects

Sample Exam Q14

Cost Value Reconciliations can take a substantial amount of time to compile. Some
commentators advise that they are of limited use and costly to compile. Critically
evaluate the use of CVR’s advising on the key components that make them up.

Ans:

Key Components:
   o Value of work to a specific date
   o Actual costs – adjusted with accruals
   o Profit / Loss
o Can be used to monitor the performance of the contract

ESTIMATING

Sample Exam Q14

When compiling a labour rate for an item of work, the estimator has to consider a number
of factors along with the basis wage rate. What are these factors?

Ans:

   1.   Guaranteed minimum CIF wage
   2.   Guaranteed Bonus
   3.   Guaranteed week (inclement weather allowance)
   4.   Public & Annual holidays
   5.   Non productive overtime worked as company policy
   6.   Additional payments – lunch money , travel allowance, tool allowance etc
   7.   PRSI
   8.   Levies – CIF Pension, Health Levy, Sick Pay etc

Sample Exam Q15

When ordering materials for any given project, is it good practice to base the order on
quantities in the BOQ? Give reasons for your answer.

Ans:

No as:
- Quantities may be incorrect in BOQ
- Quantities are measured net (don’t include laps / don’t allow for waste / cutting etc)
- Materials may only come in certain lengths or sizes
- Site measure is essential

Sample Exam Q16

As a commercial manager with a large main contractor, you have been asked by the
Financial controller to outline the advantages and disadvantages of hiring plant. Advise.

Ans:           (Same as Scenario Lecture 10B)

Advantages of hiring plant:
   • Low maintenance costs – plant hire co. maintains and repairs
   • Contractors money not tied up in expensive plant – so cash flow not effected!
   • Easy to return idle plant when insufficient work available
•   Plant hire company will supply skilled operatives/drivers and contractor does not
       have permanent operator wages to pay
   •   Can hire for the minimum period necessary

Disadvantages of hiring plant:
   • Hired plant is more expensive than owned plant over lifetime of machine
   • You don’t own the plant – money paid out
   • Particular machines may not be available from the hire company when needed
   • Possible problems with standing time – still have to pay even if machine not being
      used i.e. in bad weather
   • No tax benefits – cannot write off capital allowance against tax

Sample Exam Q17

Calculate a rate per m2 for 100mm of blockwork wall.

Blockwork; 100mm thick; in cement mortar (1:3) block size 440x215x100mm

Constants
Blocks                                       10nr/m2 of blockwork
Mortar                                       0.007m3/m2 of blockwork
Blocklayer                                   0.4 hours/m2 of blockwork
Labourer                                     0.2 hours/m2 of blockwork

Costs
Labourer                                     €18 per hour
Blocklayer                                   €28 per hour
Blocks                                       €500 per thousand
Mortar                                       €100 per m3
Waste on Blocks                              5%
Waste on Mortar                              15%
Profit & Overheads                           10%

Ans:

Materials
Blocks        10nr/m2        €500/1000x10=        €5.00 + 5%      =       € 5.25
Mortar                       €100 per m3 x 0.007= €0.7 + 15%      =       € 0.805

Labour
Blocklayer                   0.4hrs x €28                         =       €11.20
Labourer                     0.2 hrs x €18                        =       € 3.60

Sub Total                                                                 €20.855
+ P & O @ 12%                                                             €2.086
TOTAL                         Rate per m2 of Blockwork                     €22.94

VARIATIONS & DAYWORKS

Sample Exam Q20

If you are the project manager on a medium sized contract and the client enters the site
and instructs you to change the skirtings on the building from red deal to oak, how do you
handle this request?

Ans:           (Same as Scenario – Lecture 13)

   1) Firstly you advise the client that you cannot proceed without an architect’s
      instruction.
   2) You make contact with the architect and advise him of the request
   3) You or the commercial manager compile a cost for the variation – include a
      restocking charge from the supplier for taking back unusable materials
   4) Do not proceed without an architect’s instruction
   5) Confirmation of verbal instruction in some cases may be issued in writing

CLAIMS

Sample Exam Q21

The various standard forms of contract used on both building & civil engineering projects
generally contain clauses relation to Extension of Time claims from the main contractor.
Give a critically evaluation of Extension of Time claims made by the Main contractor
under the following headings:

   (a) Key criteria for an Extension of Time claim
   (b) Good practice on the main contractor’s side in relation to compiling an Extension
       of Time claim.
Ans:

(a) Key Criteria:
 - Contractor submits written notification to architect
 - Cause of delay
 - Relevant events
 - Architect advises employer
 - Architect makes assessment

(b) Good Practice:
 - Regular contract review meetings
 - Notice in form of short simple letter
-   Delay schedule
-   Delay plotted on contractors programme
-   Accurate records should be kept incl photos and site records of labour and plant as
    staff may not still be employed by end of contract

DISPUTE RESOLUTION

Sample Exam Q22

Litigation is the most effective way to resolve a construction dispute – Discuss.

Why might litigation be the best way?
Why would other ways be better?
Do you agree with hypothesis?


COST PLANS

Sample Exam Q23

Explain the term “Cost Plan” and how it is used in the Construction industry?

Ans:

A cost plan is a detailed estimate of the value of works generally based on priced
approximate quantities of building elements.
- Gives client an idea of costs – basis for budget
- Can be basis for              Budget
                                Value Management
                                Value Engineering
                                Cashflow forecasts
- Can be used for bank requirements

Contenu connexe

Tendances

Wb consultant 4a
Wb consultant 4aWb consultant 4a
Wb consultant 4aJoy Irman
 
Tenders in professional practice
Tenders in professional practiceTenders in professional practice
Tenders in professional practiceAditya Sanyal
 
Cpm ch 2tender
Cpm ch 2tenderCpm ch 2tender
Cpm ch 2tenderneharajpl
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionWaleed Liaqat
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.Abhishek kumar maurya
 
Prolongation cost calculation
Prolongation cost  calculation Prolongation cost  calculation
Prolongation cost calculation R.R.G.S Bandara
 
Civil tenders and contracts spce
Civil tenders and contracts spceCivil tenders and contracts spce
Civil tenders and contracts spceirkportal
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts finalFitBlar Mit
 
Tendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessTendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessPrateek Kashyap
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Kipcon Inc.
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Processarpantripathi2
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction CostingManish Kandpal
 
conceptual estimate
conceptual estimateconceptual estimate
conceptual estimateViVi Ariani
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Preparation of bill sandeep
Preparation of bill sandeepPreparation of bill sandeep
Preparation of bill sandeepSandeep Yadav
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkDaniel Ross
 
Construction Documents
Construction DocumentsConstruction Documents
Construction DocumentsAllan Berry
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 

Tendances (20)

Wb consultant 4a
Wb consultant 4aWb consultant 4a
Wb consultant 4a
 
Tenders in professional practice
Tenders in professional practiceTenders in professional practice
Tenders in professional practice
 
Cpm ch 2tender
Cpm ch 2tenderCpm ch 2tender
Cpm ch 2tender
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
 
Prolongation cost calculation
Prolongation cost  calculation Prolongation cost  calculation
Prolongation cost calculation
 
Civil tenders and contracts spce
Civil tenders and contracts spceCivil tenders and contracts spce
Civil tenders and contracts spce
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts final
 
Tendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessTendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award Process
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Process
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction Costing
 
ACH 216 Lecture 04b (Bidding) Part 2
ACH 216 Lecture 04b (Bidding) Part 2ACH 216 Lecture 04b (Bidding) Part 2
ACH 216 Lecture 04b (Bidding) Part 2
 
conceptual estimate
conceptual estimateconceptual estimate
conceptual estimate
 
Construction contract
Construction contract Construction contract
Construction contract
 
Preparation of bill sandeep
Preparation of bill sandeepPreparation of bill sandeep
Preparation of bill sandeep
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
uap doc 207-208
uap doc 207-208uap doc 207-208
uap doc 207-208
 

En vedette

Water efficiency paul boylan
Water efficiency   paul boylanWater efficiency   paul boylan
Water efficiency paul boylanCKMCforstudents
 
Sustainable design and build revision
Sustainable design and build revisionSustainable design and build revision
Sustainable design and build revisionCKMCforstudents
 
Us gsa (1992) value engineering program guide for design and construction -...
Us gsa (1992)   value engineering program guide for design and construction -...Us gsa (1992)   value engineering program guide for design and construction -...
Us gsa (1992) value engineering program guide for design and construction -...Wan Yusoff Wan Mahmood
 
Soil retention systems revision notes
Soil retention systems revision notesSoil retention systems revision notes
Soil retention systems revision notesCKMCforstudents
 
Timber frame construction
Timber frame constructionTimber frame construction
Timber frame constructionCKMCforstudents
 
Advanced Construction Technology Project
Advanced Construction Technology ProjectAdvanced Construction Technology Project
Advanced Construction Technology ProjectCKMCforstudents
 

En vedette (11)

Water efficiency
Water efficiencyWater efficiency
Water efficiency
 
Water efficiency paul boylan
Water efficiency   paul boylanWater efficiency   paul boylan
Water efficiency paul boylan
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Green roofs pres
Green roofs presGreen roofs pres
Green roofs pres
 
Sustainable design and build revision
Sustainable design and build revisionSustainable design and build revision
Sustainable design and build revision
 
Orgstructures
OrgstructuresOrgstructures
Orgstructures
 
Us gsa (1992) value engineering program guide for design and construction -...
Us gsa (1992)   value engineering program guide for design and construction -...Us gsa (1992)   value engineering program guide for design and construction -...
Us gsa (1992) value engineering program guide for design and construction -...
 
MMC Revision Notes
MMC Revision NotesMMC Revision Notes
MMC Revision Notes
 
Soil retention systems revision notes
Soil retention systems revision notesSoil retention systems revision notes
Soil retention systems revision notes
 
Timber frame construction
Timber frame constructionTimber frame construction
Timber frame construction
 
Advanced Construction Technology Project
Advanced Construction Technology ProjectAdvanced Construction Technology Project
Advanced Construction Technology Project
 

Similaire à Questions in notes

Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A SeminarPang Khai Shuen
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Bhalindra Bath - projects & M&A law
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZmianmohsinmumtazshb
 
Construction management 2
Construction management 2Construction management 2
Construction management 2smumbahelp
 
Quantity Surveyor - Riyas AM
Quantity Surveyor - Riyas AMQuantity Surveyor - Riyas AM
Quantity Surveyor - Riyas AMMohamed Riyaz
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract formskohwenqi
 
Capacity building - Yolanda Taylor, World Bank
Capacity building - Yolanda Taylor, World BankCapacity building - Yolanda Taylor, World Bank
Capacity building - Yolanda Taylor, World BankOECD Governance
 
Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Browne Jacobson LLP
 
Cbb 512 assignment_1
Cbb 512 assignment_1Cbb 512 assignment_1
Cbb 512 assignment_1Maatla Moadi
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Melvin Lim
 
Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference CBIZ, Inc.
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureHASMANIRA
 

Similaire à Questions in notes (20)

Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A Seminar
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...
 
Tiffany
TiffanyTiffany
Tiffany
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
 
Pmc hitesh
Pmc hiteshPmc hitesh
Pmc hitesh
 
Construction management 2
Construction management 2Construction management 2
Construction management 2
 
Practice notes for_quantity_surveyors_fi
Practice notes for_quantity_surveyors_fiPractice notes for_quantity_surveyors_fi
Practice notes for_quantity_surveyors_fi
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Quantity Surveyor - Riyas AM
Quantity Surveyor - Riyas AMQuantity Surveyor - Riyas AM
Quantity Surveyor - Riyas AM
 
Session 6 gdas pmp study group presentation
Session 6   gdas pmp study group presentationSession 6   gdas pmp study group presentation
Session 6 gdas pmp study group presentation
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Capacity building - Yolanda Taylor, World Bank
Capacity building - Yolanda Taylor, World BankCapacity building - Yolanda Taylor, World Bank
Capacity building - Yolanda Taylor, World Bank
 
Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...
 
Cbb 512 assignment_1
Cbb 512 assignment_1Cbb 512 assignment_1
Cbb 512 assignment_1
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
 
Pre Bid Risk Assessment
Pre Bid Risk AssessmentPre Bid Risk Assessment
Pre Bid Risk Assessment
 
Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
 
TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment Structure
 

Plus de CKMCforstudents

DT117/4 Sustainable design and build revision
DT117/4 Sustainable design and build revisionDT117/4 Sustainable design and build revision
DT117/4 Sustainable design and build revisionCKMCforstudents
 
Wood fuel presentation(davido s)
Wood fuel presentation(davido s)Wood fuel presentation(davido s)
Wood fuel presentation(davido s)CKMCforstudents
 
Timber frame construction presentation`gr
Timber frame construction presentation`grTimber frame construction presentation`gr
Timber frame construction presentation`grCKMCforstudents
 
Thermal imaging mark ensor
Thermal imaging mark ensorThermal imaging mark ensor
Thermal imaging mark ensorCKMCforstudents
 
Sustainable drainage systems (autosaved)(tg)
Sustainable drainage systems (autosaved)(tg)Sustainable drainage systems (autosaved)(tg)
Sustainable drainage systems (autosaved)(tg)CKMCforstudents
 
Subs above ground thomas geoghegan
Subs above ground thomas geogheganSubs above ground thomas geoghegan
Subs above ground thomas geogheganCKMCforstudents
 
Presentation solar panels martin
Presentation solar panels  martinPresentation solar panels  martin
Presentation solar panels martinCKMCforstudents
 
Photovoltaics (pv’s)keiran byrne
Photovoltaics (pv’s)keiran byrnePhotovoltaics (pv’s)keiran byrne
Photovoltaics (pv’s)keiran byrneCKMCforstudents
 
Passive construction presentation dc
Passive construction presentation dcPassive construction presentation dc
Passive construction presentation dcCKMCforstudents
 

Plus de CKMCforstudents (19)

DT117/4 Sustainable design and build revision
DT117/4 Sustainable design and build revisionDT117/4 Sustainable design and build revision
DT117/4 Sustainable design and build revision
 
Green roofs pres
Green roofs presGreen roofs pres
Green roofs pres
 
Air tightness
Air tightnessAir tightness
Air tightness
 
Biomass
BiomassBiomass
Biomass
 
Wood fuel presentation(davido s)
Wood fuel presentation(davido s)Wood fuel presentation(davido s)
Wood fuel presentation(davido s)
 
Wood fuel presentation
Wood fuel presentationWood fuel presentation
Wood fuel presentation
 
Water efficiency
Water efficiencyWater efficiency
Water efficiency
 
Water efficiency
Water efficiencyWater efficiency
Water efficiency
 
Timber frame construction presentation`gr
Timber frame construction presentation`grTimber frame construction presentation`gr
Timber frame construction presentation`gr
 
Thermal imaging mark ensor
Thermal imaging mark ensorThermal imaging mark ensor
Thermal imaging mark ensor
 
Sustainable drainage systems (autosaved)(tg)
Sustainable drainage systems (autosaved)(tg)Sustainable drainage systems (autosaved)(tg)
Sustainable drainage systems (autosaved)(tg)
 
Subs above ground thomas geoghegan
Subs above ground thomas geogheganSubs above ground thomas geoghegan
Subs above ground thomas geoghegan
 
Solar panels (nr)
Solar panels (nr)Solar panels (nr)
Solar panels (nr)
 
Seai presentation sr
Seai presentation srSeai presentation sr
Seai presentation sr
 
Seai
SeaiSeai
Seai
 
Presentation solar panels martin
Presentation solar panels  martinPresentation solar panels  martin
Presentation solar panels martin
 
Photovoltaics(k byrne)
Photovoltaics(k byrne)Photovoltaics(k byrne)
Photovoltaics(k byrne)
 
Photovoltaics (pv’s)keiran byrne
Photovoltaics (pv’s)keiran byrnePhotovoltaics (pv’s)keiran byrne
Photovoltaics (pv’s)keiran byrne
 
Passive construction presentation dc
Passive construction presentation dcPassive construction presentation dc
Passive construction presentation dc
 

Questions in notes

  • 1. BUDGETS & CASHFLOWS Sample Exam Q1 When a main contractor is forecasting his turnover for the coming year, before an overall picture can be arrived at, he must take account of all current and potential work. (a) Compare a list of the different types of projects which should be taken into account and critically evaluate the importance of each project type in the overall turnover calculation. (b) Critically explore why a main contractor needs to forecast his turnover for the current year including what problem areas he may face when compiling his data. Ans: (a) Current Contracts: Work in progress/ contracts part complete / Signed contracts not yet started These are definite contracts for which the value of is, definite and known. Probable Contracts: Phased works - 2nd, 3rd Phase / Negotiated / Private Development Possible Contracts: Incoming Tenders / Client Base / Prequalification / Negotiation Tender Conversion Rates: Analysis of tender success rates / ratio 1:4 etc / Historical data / turnover & proit / experience / project suitability / expansion programme Information Collection: Current Project Value + Probable Project Value + Possible Project Value (tender Conversions) = - Basis for Turnover Forecast - Profit Forecast - Overheads allocation - Possible shortfalls (b) To determine staff levels for coming year and thus wages and salary expenses. To determine if he can cover overheads or needs to make cuts To determine if downsizing needs to be considered To determine if borrowing or overdraft facilities need to be arranged or amended Problems when compiling data include: o Only current work is definite, rest is not guaranteed o Probable/possible contracts are reliant on economic climate which is vague o Tendering is unpredictable
  • 2. Sample Exam Q2 (a) Describe in detail the methods used by main contractor to isolate the profit amount in a newly awarded contract. (b) In your opinion, how can profit margins on a project change from tender submission to contract award? Ans: (a) o Start with the original tender o Check tendered prelims & profit o Do sub-contractor analysis (possible increase in profit on packages once awarded) o Reprice materials o Consider positives & negatives – Risk Assessment o Full preliminaries assessment (b) o Better buying on subcontractor packages & materials o Errors o Variations o Claims o Over-spend on prelims Sample Exam Q3 (a) What is a cashflow forecast and how is it completed? (b) How is a cashflow forecast beneficial both to the Main Contractor and the client? Ans: (a) A cash flow forecast is a schedule or graph which plots the amount of turnover on a given project against actual programme dates. This can also be described as an S-curve. The programme of works and the priced BOQ is used when compiling a cashflow forecast. (b) Benefits: Contractor Client - Dates for incoming monies - Estimate dates for outgoing monies - Bank Reference - Know when need to draw down Money - Check performance Sample Exam Q4 Once a tender has been awarded to a main contractor, why is it useful for him to prepare a preliminaries budget for the contract and how is this budget used? Ans:
  • 3. The preliminary costs on a contract are a particular area where a job can go wrong  Prelims can often be under-estimated at tender stage  Often more supervision may be needed thus increasing costs  The contract can run over on programme thus increasing prelims also INTERIM VALUATIONS Sample Exam Q5 (a) Why are interim valuations of such importance to a main contractor? (b) What are the main components of an interim valuation? Ans: (a) - Important to ensure full and timely payment for work carried out - Interim valuation may be only source or income for contractor to fund building operation - Vital for main contractors cashflow - RIAI Clause 35, IEI Clause 60 - covers interim payment policy (b) Valuation should be gross value of work less retention, advance payments and amount due on previous interim cert Following should be included in valuation:  Preliminaries  Measured Works  Valuation of architects instructions or variations  Remeasurement of provisional items, prime cost sums and provisional quantities  Valuation of nominated sub-contractors and suppliers  Unfixed material son site and where allowed materials off site  Fluctuations, where allowed within contract provisions Sample Exam Q6 What are the different formats used for compiling an interim valuation and give examples where different formats are used? Ans: Stage Payment Method: o Usually used when constructing units of a similar nature ie housing project o Must understand how project will be construction before establishing stage descriptions o Produce a schedule in line with programme o BOQ forms basis foe compiling stage value o Valuations simple to complete by ticking off completed units or percentage complete
  • 4. Individual Item Assessment Method: o Usually used for once off project type eg: factory etc o Scroll through BOQ item by item and put percentage complete or site measurement against each item Sample Exam Q7 How are preliminaries dealt with when compiling an interim valuation? Ans: Several formats for including prelims on valuation: - Really dependant on level of detail given when tendering - Can be priced against each item – sub divided into time related and fixed - Lump sum based on % of work done basis - Lump sum divided evenly among interim valuation dates Agreement on prelims should be made prior to or at first interim valuation Lump sum divided evenly among months can result in under payment as in early stages there is large portion expended on site set up. Contractor may decide to font load to cover this early expense. Prelims: Advantage: guaranteed a block of money every valuation Disadvantage: If BOQ under-measured or lot of variations at BOQ rates, then prelims may overrun Undervaluing prelims: Commercial decision to run with high BOQ rates and only small figure for prelims Advantage: High BOQ rates for remeasures and variations Disadvantage: Money against prelims will not cover actual – if little work done on site then low valuation Sample Exam Q8 (a) Is a main contractor entitled to payment for unfixed materials on and off site? (b) In your opinion is this of importance to the main contractor? Ans: (a) Contracts generally allow for payment of unfixed material on site if: - Not brought to site prematurely - Adequately stored - Protect from weather Payment for material off site is at the sole discretion of the architect.
  • 5. - Agreement should be made prior to manufacture - Proof of ownership may be required by client – vesting certificate - Materials will have to be set apart from other materials and marked with employers name (b) Payment for these materials are important to contractors as: o They can account for a large % of an interim valuation value o Has a major effect on a contractors cashflow o Long lead in times means early ordering and thus parting with money far in advance of fixing on site o Material may have to be ordered in full loads and then used intermittently FINAL ACCOUNTS / VARIATIONS Sample Exam Q9 What are the key components of a final account submission? Ans: Included in Final Account:  Preliminaries  Measured Works  Valuation of architects instructions or variations  Remeasurement of provisional items, prime cost sums and provisional quantities  Valuation of nominated sub-contractors and suppliers  Fluctuations, where allowed within contract provisions Preparation: Contract Sum (Excl VAT) Omissions: - PC Sums - Provisional Sums - Provisional Quantity Items - Valuation of omitted work resulting from architects instructions - Agreed deductions due to defects etc Additions: - Agreed totals for nominated subbies & suppliers including attendances & profit - Valuation of variations - Valuation of expended provisional sums and approximate quantities - Amounts established under loss and expense - Price fluctuations is applicable - 50% retention Sample Exam Q10 (a) What are the variations and where do they occur?
  • 6. (c) What are the four main methods of pricing variations? Ans: (a) “A variation is defined as the alteration or modification of the design, quality or quantity of the works” Ivor Seeley Variations and extras occur when: o There is a discrepancy between the contract drawings/BOQ/architects instruction etc o Complying with statutory requirements o Alterations to design, quality or quantity of work o Restoration works in making good damage Should get architects instruction of CVI, agree costs before commencing, keep records (b) Four methods of pricing variations include: 1. BOQ rates – similar work 2. Adjusted BOQ rates – if similar work but different conditions 3. Build Up New Rate – no similar work in BOQ 4. Dayworks – impossible to measure or foresee SUB-CONTRACTORS Sample Exam Q10 Why is it common for main contractors to subcontract a large percentage of their work? Include what you perceive to be the advantages and disadvantages. Ans: Advantages: o Pass the potential risk on to others o No obligation in respect to long term employment – lower costs – no labour disputes o Non-productive overtime eliminated o Reduced problems with standing time due to inclement weather o Specialist areas covered o Cost certainty / possible savings i.e. plant Disadvantages: o Contractor must monitor quality of subbies work o Contractor is fully responsible for subbies work, quality, programme and cost o Contractors reputation can be damaged by poor performance subbies o Disputes with subbies often arise
  • 7. Sample Exam Q11 When a sub contractor submits a quotation for a given work package, there may be issues surrounding the price which will have to be taken into account when the Commercial Manager is analysing that quotation. Outline what issues may arise, and also factors other than price which should be taken into account when procuring a subcontractor. Ans: o Price may be incomplete o Specification may be qualified – ie not pricing what you are supposed to o Subcontractor may have inserted his own conditions o Price may be subject to huge attendance Other factors: o Unable to meet programme o Poor record on quality o No expertise o Too much work on at current time o No supervision o Reputation for EOT’s and/or disputes Sample Exam Q12 (a) Draw a flow chart mapping the procedures carried out by a commercial manager from subcontractor procurement to final account. (b) Give a brief narrative on various forms used when carrying out the above procedures. Ans: PROCUREMENT SCHEDULE INVITATION TO TENDER ANALYSE SUB-CONTRACTOR QUOTATIONS PRE-ORDER MEETING PLACE ORDER/SUB-CONTRACT PAYMENTS & CERTIFICATES
  • 8. FINAL CERT/ REMEASURE Procurement schedule o Project broken down into work packages o Key dates inserted o Projected start and completion dates from programme entered o Actual dates eventually recorded o Document updated throughout project Invitation to Tender Includes: o Site location o Names of consultant and employer o Main contract and sub contract conditions o Fixed or fluctuating price o Schedule of applicable dayworks o Return date o Site access o Contract period for main contract o Start date and duration of subcontract works o Discount levels required o Details of attendances Analyse Sub Contractor Price o Price important but not only criteria for award o Returned quotations compared against BOQ rates o All returned quotes analysed o Checked item by item o Could be priced differently ie lump sum, rates etc o Compare like with like Sub Contract Order: o Full schedule of BOQ items o Schedule of drawings sent at tender stage o Dates for commencement and completion o Full price including any discounts etc o Pre-contract correspondence o Project specific details such as retention etc Sub Contractor Payments: o QS must monitor/access/and sanction all payments o Subbie valuations should coincide with main contract valuations o Can help main contactor with their valuation and CVR’s
  • 9. o Should check cumulative payments do not exceed order and if so Overpayment, because: o Work carried out without instruction o Additional works not recorded o Misrepresentation of agreement o Dayworks Sub Contractor Final Account o Agree measures o Agree variations o Deduct counter charges o Retention o Final Certificate COST VALUE RECONCILATIONS (CVR’s) Sample Exam Q13 CVR’s - How are they used? Ans: o Used to compare the actual costs allocated to a project against the value of works carried out, measured and valued at contract rates plus the value of materials on site o Basically monitors project performance in terms of labour, plant, materials etc against original tender figures – flags over runs o Can be used to compare projects profitability/turnover against budgeted or forecasted figures o Can be used when assessing tenders on similar projects Sample Exam Q14 Cost Value Reconciliations can take a substantial amount of time to compile. Some commentators advise that they are of limited use and costly to compile. Critically evaluate the use of CVR’s advising on the key components that make them up. Ans: Key Components: o Value of work to a specific date o Actual costs – adjusted with accruals o Profit / Loss
  • 10. o Can be used to monitor the performance of the contract ESTIMATING Sample Exam Q14 When compiling a labour rate for an item of work, the estimator has to consider a number of factors along with the basis wage rate. What are these factors? Ans: 1. Guaranteed minimum CIF wage 2. Guaranteed Bonus 3. Guaranteed week (inclement weather allowance) 4. Public & Annual holidays 5. Non productive overtime worked as company policy 6. Additional payments – lunch money , travel allowance, tool allowance etc 7. PRSI 8. Levies – CIF Pension, Health Levy, Sick Pay etc Sample Exam Q15 When ordering materials for any given project, is it good practice to base the order on quantities in the BOQ? Give reasons for your answer. Ans: No as: - Quantities may be incorrect in BOQ - Quantities are measured net (don’t include laps / don’t allow for waste / cutting etc) - Materials may only come in certain lengths or sizes - Site measure is essential Sample Exam Q16 As a commercial manager with a large main contractor, you have been asked by the Financial controller to outline the advantages and disadvantages of hiring plant. Advise. Ans: (Same as Scenario Lecture 10B) Advantages of hiring plant: • Low maintenance costs – plant hire co. maintains and repairs • Contractors money not tied up in expensive plant – so cash flow not effected! • Easy to return idle plant when insufficient work available
  • 11. Plant hire company will supply skilled operatives/drivers and contractor does not have permanent operator wages to pay • Can hire for the minimum period necessary Disadvantages of hiring plant: • Hired plant is more expensive than owned plant over lifetime of machine • You don’t own the plant – money paid out • Particular machines may not be available from the hire company when needed • Possible problems with standing time – still have to pay even if machine not being used i.e. in bad weather • No tax benefits – cannot write off capital allowance against tax Sample Exam Q17 Calculate a rate per m2 for 100mm of blockwork wall. Blockwork; 100mm thick; in cement mortar (1:3) block size 440x215x100mm Constants Blocks 10nr/m2 of blockwork Mortar 0.007m3/m2 of blockwork Blocklayer 0.4 hours/m2 of blockwork Labourer 0.2 hours/m2 of blockwork Costs Labourer €18 per hour Blocklayer €28 per hour Blocks €500 per thousand Mortar €100 per m3 Waste on Blocks 5% Waste on Mortar 15% Profit & Overheads 10% Ans: Materials Blocks 10nr/m2 €500/1000x10= €5.00 + 5% = € 5.25 Mortar €100 per m3 x 0.007= €0.7 + 15% = € 0.805 Labour Blocklayer 0.4hrs x €28 = €11.20 Labourer 0.2 hrs x €18 = € 3.60 Sub Total €20.855 + P & O @ 12% €2.086
  • 12. TOTAL Rate per m2 of Blockwork €22.94 VARIATIONS & DAYWORKS Sample Exam Q20 If you are the project manager on a medium sized contract and the client enters the site and instructs you to change the skirtings on the building from red deal to oak, how do you handle this request? Ans: (Same as Scenario – Lecture 13) 1) Firstly you advise the client that you cannot proceed without an architect’s instruction. 2) You make contact with the architect and advise him of the request 3) You or the commercial manager compile a cost for the variation – include a restocking charge from the supplier for taking back unusable materials 4) Do not proceed without an architect’s instruction 5) Confirmation of verbal instruction in some cases may be issued in writing CLAIMS Sample Exam Q21 The various standard forms of contract used on both building & civil engineering projects generally contain clauses relation to Extension of Time claims from the main contractor. Give a critically evaluation of Extension of Time claims made by the Main contractor under the following headings: (a) Key criteria for an Extension of Time claim (b) Good practice on the main contractor’s side in relation to compiling an Extension of Time claim. Ans: (a) Key Criteria: - Contractor submits written notification to architect - Cause of delay - Relevant events - Architect advises employer - Architect makes assessment (b) Good Practice: - Regular contract review meetings - Notice in form of short simple letter
  • 13. - Delay schedule - Delay plotted on contractors programme - Accurate records should be kept incl photos and site records of labour and plant as staff may not still be employed by end of contract DISPUTE RESOLUTION Sample Exam Q22 Litigation is the most effective way to resolve a construction dispute – Discuss. Why might litigation be the best way? Why would other ways be better? Do you agree with hypothesis? COST PLANS Sample Exam Q23 Explain the term “Cost Plan” and how it is used in the Construction industry? Ans: A cost plan is a detailed estimate of the value of works generally based on priced approximate quantities of building elements. - Gives client an idea of costs – basis for budget - Can be basis for Budget Value Management Value Engineering Cashflow forecasts - Can be used for bank requirements