Schedule Design – Planning for
                  Schedule Development

“Scheduling
                              Chris Carson, PSP
    With
                     Corporate Director of Project Controls
the Masters”
                              Alpha Corporation
                     Chris.carson@alphacorporation.com
                                757-342-5524
Schedule Design

               Why design a schedule?
                  A schedule meets the criteria for a “project” in itself
                  A schedule is a guideline or plan for a project
                  A schedule provides a a methodical approach for a project
                  Keeps the schedule development on track
“Scheduling
    With          Prevents rework due to late understanding of needs
the Masters”      Allows buy-in from end users prior to Development
                  Makes the schedule development session much more
                  meaningful
                  Documents the assumptions and intention of the schedule
                      For reviewer and approver
                      For future reference
                      To facilitate changes in schedulers
                      Place to capture Lessons Learned

                                                                                                                     2
                                                          PMI College of Scheduling
                            “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design

               Scope of Design vs. Development
                  Design – Conceptualizing the schedule
                     Planning
                     Starting with the end in mind
                     Providing concept of final product
“Scheduling
                     Creating organizational structure to fulfill the concept
    With
the Masters”
                  Development - Building the schedule
                     Input activities
                     Input logic
                     Input durations
                     Review for design compliance
                     Review for CPM methodology best practices
                     Quality control

                                                                                                                    3
                                                         PMI College of Scheduling
                           “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design - Background
               • Design vs. Development – How PMI & PMBOK handles it?
                  – PMBOK identifies six Project Time Management
                    processes, usually defined as part of the project
                    lifecycle, Section 2.1 of PMBOK.
                        Activity Definition.
                        Activity Sequencing.
                        Activity Resource Estimating.
“Scheduling             Activity Duration Estimating.
    With                Schedule Development.
                        Schedule Control.
the Masters”
                  – These processes are preceded by a planning effort by
                    the project management team, which is part of PMBOK’s
                    “Develop Project Management Plan”, PMBOK Section 4.3
                    (which sets the format and establishes criteria for
                    developing the project schedule).
                  – These processes are documented in what PMBOK calls a
                    Schedule Management Plan, which is contained in the
                    project management plan, in the introduction to Section
                    4.3, Project Integration Management.
                                                                                                                           4
                                                                PMI College of Scheduling
                                  “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design - Background
               •   PMBOK Process Inputs.
                    – The inputs for the different Time Management Processes are
                      listed as:
                           Activity list.
                           Product description.
                           Mandatory dependencies.
                           Discretionary dependencies.
                           External dependencies.
“Scheduling                Resource requirements.
    With                   Resource capabilities.
                           Historical information.
the Masters”
                           Identified risks.
                           Constraints.
                           Assumptions.
                    – All of these items, along with the Schedule Management Plan,
                      are part of Schedule Design, but PMBOK does not offer clear
                      definition and delineation of Schedule Design.
                    – The Time Management Processes do not include Schedule
                      Design.


                                                                                                                            5
                                                                 PMI College of Scheduling
                                   “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design - Background

               • Design vs. Development – why
                 emphasize the distinction?
                 – Design tends to be ignored in favor of jumping
“Scheduling
                   right into development.
    With
                      Many schedulers elect to begin creating activities
the Masters”
                      instead of Designing.
                      Work is subsequently repetitive, with lots of
                      potential for rework.
                      Results tend to be disorganized.
               • Avoid planning mistakes and problems.

                                                                                                                    6
                                                         PMI College of Scheduling
                           “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design

               • Avoid planning mistakes and problems



“Scheduling
    With
the Masters”




                                                                                                                    7
                                                         PMI College of Scheduling
                           “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design
                      • Lack of Good Area Definition preventing activity
                        closeout:



“Scheduling
    With
the Masters”
                          Hinders
                          productivity
Areas are so              analysis, good
broadly defined           cost loading,
that activities sit       accurate as-
at nearly
                          built dates.
complete for
large parts of the
project.
                                                                                                                                8
                                                                     PMI College of Scheduling
                                       “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design
                   • Inconsistency in level of detail throughout
                     trades:



“Scheduling
    With
the Masters”

Some trades
are heavily
developed
while others
are left with
summary-level
activities only.
                                                                                                                          9
                                                               PMI College of Scheduling
                                 “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design

               Documentation and use of Schedule Design
                 Create a book or binder
                 Use the highest level of checklist outline items as tabs
                 Use the book as basis for schedule submittal
“Scheduling
                 documentation
    With
                 Keep the book current during project
the Masters”
                 Use the book for handoff between schedulers
                 Share a copy of the book with superintendent/PM
               Timing
                 Must be done prior to Schedule Development



                                                                                                                   10
                                                        PMI College of Scheduling
                          “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design Checklist

               Project Description
                 Reference Documents
                    Contract
                    Project Drawings
“Scheduling         Specifications
    With
                    Scheduling Specification
the Masters”
                    Notice to Proceed or Release Letter
                    Any Owner produced master schedule
                    Liquidated Damages schedule
                    Area Designation Plan
                    Sequencing plan
                    Estimate & quantity surveys/bills of materials


                                                                                                                11
                                                     PMI College of Scheduling
                       “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design Checklist -
               Schedule Specification – General Contents.




“Scheduling
    With
the Masters”




                                                                                                                     12
                                                          PMI College of Scheduling
                            “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design Checklist

               Team Players
                 Organizational Chart (OBS)
                 Who are Schedule Users?
                    Who has Input
“Scheduling
                    Who Updates
    With
                    Who Checks for Accuracy
the Masters”
                    Who Reviews
                    Who approves
                 Identify Responsibility Assignment Matrix (RAM)




                                                                                                                 13
                                                      PMI College of Scheduling
                        “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design Checklist
               Organizational Breakdown Structure.


“Scheduling
    With
the Masters”




                                                                       From: DOE Training “EVM Tutorial – WBS”
                                                                       by Booze-Allen-Hamilton


                                                                                                                 14
                                                     PMI College of Scheduling
                       “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design

               RAM Example (based on PMBOK RACI Chart)



“Scheduling
    With
the Masters”




                                                                                                                  15
                                                       PMI College of Scheduling
                         “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design Checklist

               Software Identification
                 Specific software
                     Required minimum and versions allowed
                 Enterprise specific issues
“Scheduling
                     Users identified
    With
                     Schedules used for import or data source
the Masters”
                     Levels of access
                     Validation process
                     For master schedules, establish data dates




                                                                                                                 16
                                                      PMI College of Scheduling
                        “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design Checklist

               Work Product
                  What the Schedule can be used for (purpose)
                  Reports Generated from the Schedule
                      Who receives reports
                      List of reports
“Scheduling
                      Samples of reports
    With
                  Glossary/Lexicon of ambiguous terms
the Masters”
               Schedule Outline
                  Key Activities being tracked
                  Client Milestones
                  Long Lead Items
                  WBS Structure
                  Other Contracts on Project

                                                                                                                   17
                                                        PMI College of Scheduling
                          “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design

               Reporting



“Scheduling
    With
the Masters”




                                                                                                                18
                                                     PMI College of Scheduling
                       “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design Checklist

               Work Package Development.
                   By Contract.
                   As assigned by Client.

“Scheduling
               VI. Work Packages
    With
               Division 2 and 5 Specifications require the following Work
the Masters”
                   Packages:
               –   Superstructure Waterproofing
               –   Corrosion Protection of Structural Steelwork
               –   Movements and Tolerances Specification for Structural Steel
               –   Structural Steel Superstructure
               –   Cast in Place Concrete



                                                                                                                      19
                                                           PMI College of Scheduling
                             “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design Checklist

               Level of Detail
                  Determine approach:
                     Bottom-up (starting with detailed activities)
                     Top-down (starting with summary schedule)
“Scheduling          Both (prepare Top-down, then Bottom-up)
    With
                  Identify frequency of updates
the Masters”
                  Establish smallest activity duration range




                                                                                                                  20
                                                       PMI College of Scheduling
                         “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design Checklist

               Codes Dictionary
                  For tracking and monitoring work:
                      Work Phase
                      Structure
                      Area
“Scheduling
                      Floor or Station
    With
                      Location.
the Masters”
                  For Project Management:
                      Responsibility
                      Work Shifts
                      Costs
                      Resource
                      Specification
                      Change management


                                                                                                                   21
                                                        PMI College of Scheduling
                          “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design Checklist
               Calendars
                 Establish number needed
                 Define calendars and application
               Costs & Resources
                 Estimate & correlation to cost loading
                 Bill of Quantities & use in resources
“Scheduling
                 Resource Crew descriptions
    With
                 Equipment descriptions
the Masters”
                 How actual production will be monitored
                 Earned Value Management System
               Narrative Basis & Assumptions
                 Procedure Used to create the Schedule
                 Definitions/lexicon
                 Description of sequence of work per structure

                                                                                                                  22
                                                       PMI College of Scheduling
                         “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design Checklist

               Example of Calendar Section:

               •   Calendars are defined as follows:
                   –   Calendar 1 – 24 hours a day, 7 days a week.
“Scheduling
                   –   Calendar 2 – 24 hours a day, only Fridays off. (This is the Default
    With
                       Calendar.)
the Masters”
                   –   Calendar 3 – Night Shift, only Fridays off.
                   –   Calendar 4 – Night Shift, 24 hours a day, 7 days a week.
                   –   Please note that 01140/1.9.a. requires that the Contractor notify the
                       Client regarding multiple shifts, etc. This has been accomplished
                       by using Day and Night sift calendars as well as by incorporating
                       multiple crew codes into the Program. (For more on Crews, please
                       refer to the Resources section of this report.)



                                                                                                                             23
                                                                  PMI College of Scheduling
                                    “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design Checklist
                            Example of Lexicon
               General Notes Regarding this Report:
               •   “Program,” “Programme,” and “Baseline CPM,” and “Schedule” all
                   have the same definition and are used interchangeably.
               •   “Snagging” and “Punch-out” have the same definition and are
                   used interchangeably.
“Scheduling    •   “Fixed” and “Rough-in” have roughly the same definition. For
                   clarification purposes, “Fixed” has been used in this Program.
    With
the Masters”   •   “Conventional concrete” is defined as post-tension poured-in-
                   place concrete.
               •   “Wild Air” is defined as a stage in construction, for which the
                   building is closed in by perimeter walls and ventilation has
                   started. (Ventilation only, not complete environmental controls or
                   functioning air conditioning.) This term is used in lieu of
                   “environmental controls,” or “drying –in” as wet weather is not a
                   real factor in Dubai.
               •   “Raft” construction consists of the foundation including but not
                   limited to piles, grade beams, footers, and slab-on-grade.
                                                                                                                          24
                                                               PMI College of Scheduling
                                 “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design

               Narrative Basis



“Scheduling
    With
the Masters”




                                                                                                                25
                                                     PMI College of Scheduling
                       “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design Checklist

               Risks & Constructability
                 Brainstorming of issues
                     Known problems (threats)
                     Provisional Items
“Scheduling          Predicted Problems
    With
                     Lessons Learned
the Masters”
                     Outside influences
                     Site condition concerns
                     Opportunities
                 Develop Risk Management Plan
                     Initial process during baseline schedule development
                     Process for use during updates


                                                                                                                 26
                                                      PMI College of Scheduling
                        “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design

               Risk Management Plan
               – Based on PMBOK




“Scheduling
    With
the Masters”




                                                                                                                    27
                                                         PMI College of Scheduling
                           “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design Checklist

               Weather planning
                 Expected adverse weather
                 Identify source or specification requirement
                 Identify methodology
“Scheduling
                 Identify accounting method for actual weather
    With
the Masters”




                                                                                                                28
                                                     PMI College of Scheduling
                       “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design Checklist

               Time Contingencies
                 Amounts
                 Specific trade (from risk management plan)
                 Specific contractor contingency
                 How carried
“Scheduling
                 Use historical data for reference
    With
the Masters”                                                 Time Performance Ratio

                           12.0
                           10.0
                            8.0
                     TPR




                            6.0
                            4.0
                            2.0
                            0.0




                                        ev s
                                                 ry




                                                  s
                                                 ry




                                                ws




                                                 nt
                                                  e




                                      E l ca l
                                    / W fing




                                                   l
                                   E q hes
                                       ar ls
                                                rk
                                                in




                                               ca
                                                g

                                               or
                                               et



                                               a
                                             on




                                              nt
                                              m




                                  Fu me
                                            wo




                                             in
                                            do




                                            ni

                                            tri
                                            et




                                            at
                                            cr




                                          pe

                                          oo
                                          Ad




                                            s



                                         ish
                                         as




                                         ha

                                         ec
                                         te




                                         M




                                         ni

                                          p
                                        on




                                         in
                                       R




                                       ui
                                      Fi
                                      M
                                      Si




                                      rn



                                     ec
                                     El
                                      C




                                     C




                                  M
                                 rs
                              oo
                            D


                                                                                       Type of Work

                                                                                                                      29
                                                           PMI College of Scheduling
                             “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design Checklist

                                                   Establish Update process
                                                        Frequency
                                                        Data request and transmission
                                                        Validation
“Scheduling
                                                        Process flowchart
    With
the Masters”

               Collect Admin                       Verify All
               Progress Data                         Data


 Request for     Collect Field               Status             Update                   Compare to
 Update Data     Progress Data              Schedule            Schedule                  Baseline


                               Identify Contract
                                  Changes




                                                                                                                                                                    30
                                                                                                         PMI College of Scheduling
                                                                           “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design Checklist

               Change Management process
                 Notification requirements
                 Methodology allowed
                 Process flowchart
“Scheduling
    With
the Masters”




                                                                                                                31
                                                     PMI College of Scheduling
                       “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Collect Admin                        Verify All
                   Progress Data                         Data

                                                                                                                                                                     No
     Request for     Collect Field                Status                Update                            Compare to                               Critical Path
     Update Data     Progress Data               Schedule              Schedule                            Baseline                                  Delay?


                                                                                                                                                             Yes
                                   Identify Contract
                                      Changes

                                                                                                                                               Identify Previous
                                                                                                                                                    Period
                                                                                                                                                 Critical Path
                                                                                                                                                                                Publish
                 Research                                                                                                                                                       Updated
                                         Quantify             Identify Causal                        Identify Changes
               Documents For                                                                                                                                                    Schedule
                                          Delays              Delay Activities                        To Critical Path
               Driving Delays

“Scheduling
                                                                                                            Is the
    With Assess                          Any                     Perform                                   Owner
                                                       Yes                                                                               Yes
                                                                                                                                                                    Prepare
         Responsibility               Concurrent             Concurrent Delay                            Responsible
the Masters”Delays                                                                                                                                                  Recovery
          For                          Delays?                  Analysis                                  For Delay?
                                                                                                                                                                    Schedule

                                                No
                                                                                                                        No
                                                                                                                                                                Resolve
                                                                                                                                                              Subcontractor
                                                                                                            Is a
                                                                Is the
                                                                                                                                                              Contributions
                                                                                          No                                             No
                                     Verify Single                                                      Subcontractor
                                                               Owner
                                     Source Delay                                                       Responsible
                                                             Responsible
                                     Responsibility                                                      For Delay?
                                                              For Delay?
                                                                                                                                                       Discuss Delay &
                                                                                                                                                        Mitigation with
                                                                                                                          Yes
                                                                                                                                                        Subcontractor
                                                                         Yes
         Proposed Schedule Update
         With Change Management                                                                                                  Discuss Delay                         Prepare Delay
                                                                                                                                  & Mitigation                           Analysis
                                                                                                                                  With Owner                          & Change Order
                                                                                                                                                                                       32
                                                                                            PMI College of Scheduling
                                                              “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design Checklist

               Recovery process
                 Identify what logic changes are acceptable without
                 formal approval
                 Identify what constitutes a Revision requiring
“Scheduling      approval
    With
                 Provide process description or flow chart
the Masters”




                                                                                                                33
                                                     PMI College of Scheduling
                       “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design Checklist

               18. Dispute resolution process
                  1.   Review program for claims avoidance
                       1.   Reinforce planning for claims avoidance
                       2.   Identify specific program for claims avoidance during
“Scheduling                 schedule updates and change management
    With          2.   Identify steps if change management process fails or
the Masters”
                       stalls
                  3.   Follow specifications
                  4.   Provide time frames for stages in process
                  5.   Provide process description or flow chart




                                                                                                                        34
                                                             PMI College of Scheduling
                               “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design

               Conclusion
               •   For success in Schedule Development,
                   Schedule Design should be a completely
                   different process
“Scheduling
    With
               •   Process done prior to Development
the Masters”
               •   Process and results documented
               •   Documentation done in formal Schedule
                   Design Book
               •   Book used to provide continuity between
                   schedulers or project managers

                                                                                                                    35
                                                         PMI College of Scheduling
                           “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design

               • Resources
                 – See Lance Stephenson’s “Schedule Basis
                   Memorandum” paper, also addresses schedule levels
                 – See AACEi’s Total Cost Management
“Scheduling
                 – See PMBOK for Risk Management process
    With
               • Recommendations
the Masters”
                 – Get involved with the CoS SEI Project developing Best
                   Practices and Guidelines for Scheduling
                 – Get involved with AACEi and the Recommended
                   Practices development
                 – Get involved with CMAA in the Time Management
                   development

                                                                                                                      36
                                                           PMI College of Scheduling
                             “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design

                                          Questions?

                        Recommendations?
“Scheduling
    With
                                      War Stories?
the Masters”


                                                 Gripes?




                                                                                                        37
                                             PMI College of Scheduling
               “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Schedule Design – Planning for
                  Schedule Development
“Scheduling
    With                                          Chris Carson, PSP
the Masters”
                         Corporate Director of Project Controls
                                  Alpha Corporation
                            101 West Main Street, Suite 715
                                   Norfolk, VA 23510
                                 757-533-9368 Office
                                 757-342-5524 Mobile
                         Chris.carson@alphacorporation.com


                                                                                                            38
                                                 PMI College of Scheduling
                   “PMI” is a registered trade and service mark of the Project Management Institute, Inc.

More Related Content

What's hot

Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2Chris Carson
 
Dynamic Scheduling for Shutdowns and Turnarounds
Dynamic Scheduling for Shutdowns and TurnaroundsDynamic Scheduling for Shutdowns and Turnarounds
Dynamic Scheduling for Shutdowns and TurnaroundsEJ (Ted) Lister
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleGlen Alleman
 
Project planning
Project planning Project planning
Project planning Dereje Jima
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery SchedulingChris Carson
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMIChris Carson
 
Schedule Design AACE
Schedule Design AACESchedule Design AACE
Schedule Design AACEChris Carson
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlM Maged Hegazy, LLM, MBA, CCP, P3O
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckSHAZEBALIKHAN1
 
DCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdfDCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdfKarim Ragab
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...ijtsrd
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpChris Carson
 

What's hot (20)

Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Dynamic Scheduling for Shutdowns and Turnarounds
Dynamic Scheduling for Shutdowns and TurnaroundsDynamic Scheduling for Shutdowns and Turnarounds
Dynamic Scheduling for Shutdowns and Turnarounds
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
 
Project planning
Project planning Project planning
Project planning
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
Project Estimation
Project EstimationProject Estimation
Project Estimation
 
Schedule Design AACE
Schedule Design AACESchedule Design AACE
Schedule Design AACE
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality Check
 
DCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdfDCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdf
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls Pp
 

Viewers also liked

CRUDE-OIL BLEND SCHEDULING OPTIMIZATION OF AN INDUSTRIAL-SIZED REFINERY: A DI...
CRUDE-OIL BLEND SCHEDULING OPTIMIZATION OF AN INDUSTRIAL-SIZED REFINERY: A DI...CRUDE-OIL BLEND SCHEDULING OPTIMIZATION OF AN INDUSTRIAL-SIZED REFINERY: A DI...
CRUDE-OIL BLEND SCHEDULING OPTIMIZATION OF AN INDUSTRIAL-SIZED REFINERY: A DI...Brenno Menezes
 
Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsGalala University
 
Oil-Refinery Planning & Scheduling Optimization
Oil-Refinery Planning & Scheduling OptimizationOil-Refinery Planning & Scheduling Optimization
Oil-Refinery Planning & Scheduling OptimizationAlkis Vazacopoulos
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 
Steel building Graded Unit Civil Engineering Project HND Project Glasgow Kel...
Steel building Graded Unit  Civil Engineering Project HND Project Glasgow Kel...Steel building Graded Unit  Civil Engineering Project HND Project Glasgow Kel...
Steel building Graded Unit Civil Engineering Project HND Project Glasgow Kel...Tehmas Saeed
 
Fnbe0115 Integrated - awesome
Fnbe0115 Integrated - awesomeFnbe0115 Integrated - awesome
Fnbe0115 Integrated - awesomeMuhammad Nazmi
 
Crude-Oil Scheduling Technology: moving from simulation to optimization
Crude-Oil Scheduling Technology: moving from simulation to optimizationCrude-Oil Scheduling Technology: moving from simulation to optimization
Crude-Oil Scheduling Technology: moving from simulation to optimizationBrenno Menezes
 
Distillation Blending and Cutpoint Temperature Optimization (DBCTO) in Schedu...
Distillation Blending and Cutpoint Temperature Optimization (DBCTO) in Schedu...Distillation Blending and Cutpoint Temperature Optimization (DBCTO) in Schedu...
Distillation Blending and Cutpoint Temperature Optimization (DBCTO) in Schedu...Brenno Menezes
 
Strategic brand management
Strategic brand managementStrategic brand management
Strategic brand managementRiddhima Kartik
 
Energy resource management
Energy resource managementEnergy resource management
Energy resource managementRiddhima Kartik
 
Design Patterns For 70% Of Programmers In The World
Design Patterns For 70% Of Programmers In The WorldDesign Patterns For 70% Of Programmers In The World
Design Patterns For 70% Of Programmers In The WorldSaurabh Moody
 
Distillation Blending and Cutpoint Temperature Optimization in Scheduling Ope...
Distillation Blending and Cutpoint Temperature Optimization in Scheduling Ope...Distillation Blending and Cutpoint Temperature Optimization in Scheduling Ope...
Distillation Blending and Cutpoint Temperature Optimization in Scheduling Ope...Brenno Menezes
 
Crude-Oil Blend Scheduling Optimization: An Application with Multi-Million D...
Crude-Oil Blend Scheduling Optimization:  An Application with Multi-Million D...Crude-Oil Blend Scheduling Optimization:  An Application with Multi-Million D...
Crude-Oil Blend Scheduling Optimization: An Application with Multi-Million D...Alkis Vazacopoulos
 
Enercept Power Point[1]
Enercept Power Point[1]Enercept Power Point[1]
Enercept Power Point[1]cezitelli
 
Design and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadDesign and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadgopichand's
 
Profit Impact of Market Strategies (PIMS)
Profit Impact of Market Strategies (PIMS)Profit Impact of Market Strategies (PIMS)
Profit Impact of Market Strategies (PIMS)Nurul Aqilah
 
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRODESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PROAli Meer
 
Multistorey building
Multistorey buildingMultistorey building
Multistorey buildingRahul
 

Viewers also liked (20)

CRUDE-OIL BLEND SCHEDULING OPTIMIZATION OF AN INDUSTRIAL-SIZED REFINERY: A DI...
CRUDE-OIL BLEND SCHEDULING OPTIMIZATION OF AN INDUSTRIAL-SIZED REFINERY: A DI...CRUDE-OIL BLEND SCHEDULING OPTIMIZATION OF AN INDUSTRIAL-SIZED REFINERY: A DI...
CRUDE-OIL BLEND SCHEDULING OPTIMIZATION OF AN INDUSTRIAL-SIZED REFINERY: A DI...
 
5case
5case5case
5case
 
Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction Documents
 
Oil-Refinery Planning & Scheduling Optimization
Oil-Refinery Planning & Scheduling OptimizationOil-Refinery Planning & Scheduling Optimization
Oil-Refinery Planning & Scheduling Optimization
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Steel building Graded Unit Civil Engineering Project HND Project Glasgow Kel...
Steel building Graded Unit  Civil Engineering Project HND Project Glasgow Kel...Steel building Graded Unit  Civil Engineering Project HND Project Glasgow Kel...
Steel building Graded Unit Civil Engineering Project HND Project Glasgow Kel...
 
Fnbe0115 Integrated - awesome
Fnbe0115 Integrated - awesomeFnbe0115 Integrated - awesome
Fnbe0115 Integrated - awesome
 
Crude-Oil Scheduling Technology: moving from simulation to optimization
Crude-Oil Scheduling Technology: moving from simulation to optimizationCrude-Oil Scheduling Technology: moving from simulation to optimization
Crude-Oil Scheduling Technology: moving from simulation to optimization
 
Distillation Blending and Cutpoint Temperature Optimization (DBCTO) in Schedu...
Distillation Blending and Cutpoint Temperature Optimization (DBCTO) in Schedu...Distillation Blending and Cutpoint Temperature Optimization (DBCTO) in Schedu...
Distillation Blending and Cutpoint Temperature Optimization (DBCTO) in Schedu...
 
Strategic brand management
Strategic brand managementStrategic brand management
Strategic brand management
 
Energy resource management
Energy resource managementEnergy resource management
Energy resource management
 
Design Patterns For 70% Of Programmers In The World
Design Patterns For 70% Of Programmers In The WorldDesign Patterns For 70% Of Programmers In The World
Design Patterns For 70% Of Programmers In The World
 
Distillation Blending and Cutpoint Temperature Optimization in Scheduling Ope...
Distillation Blending and Cutpoint Temperature Optimization in Scheduling Ope...Distillation Blending and Cutpoint Temperature Optimization in Scheduling Ope...
Distillation Blending and Cutpoint Temperature Optimization in Scheduling Ope...
 
Crude-Oil Blend Scheduling Optimization: An Application with Multi-Million D...
Crude-Oil Blend Scheduling Optimization:  An Application with Multi-Million D...Crude-Oil Blend Scheduling Optimization:  An Application with Multi-Million D...
Crude-Oil Blend Scheduling Optimization: An Application with Multi-Million D...
 
Enercept Power Point[1]
Enercept Power Point[1]Enercept Power Point[1]
Enercept Power Point[1]
 
Design and analasys of a g+2 residential building
Design and analasys of a g+2 residential building Design and analasys of a g+2 residential building
Design and analasys of a g+2 residential building
 
Design and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadDesign and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staad
 
Profit Impact of Market Strategies (PIMS)
Profit Impact of Market Strategies (PIMS)Profit Impact of Market Strategies (PIMS)
Profit Impact of Market Strategies (PIMS)
 
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRODESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
 
Multistorey building
Multistorey buildingMultistorey building
Multistorey building
 

Similar to Schedule Design PMI

Business PMO & IT Pmo What Is The Difference
Business PMO & IT Pmo What Is The DifferenceBusiness PMO & IT Pmo What Is The Difference
Business PMO & IT Pmo What Is The DifferenceStefan Rank
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion SchedulesChris Carson
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationChris Carson
 
Pmp pmi - training - project management certificate programme
Pmp   pmi - training - project management certificate programmePmp   pmi - training - project management certificate programme
Pmp pmi - training - project management certificate programmeYOUSUF KHAN
 
QFH Consulting Capabilities
QFH Consulting CapabilitiesQFH Consulting Capabilities
QFH Consulting CapabilitiesQuinn Harry
 
Macrosolutions PMDome Workshop (en)
Macrosolutions PMDome Workshop (en)Macrosolutions PMDome Workshop (en)
Macrosolutions PMDome Workshop (en)Macrosolutions SA
 
Project management in pharmaceutical generic industry basics and standards
Project management in pharmaceutical generic industry basics and standardsProject management in pharmaceutical generic industry basics and standards
Project management in pharmaceutical generic industry basics and standardsJayesh Khatri
 
IMT Lecture:Creating Project Plans To Focus Product Development.Mm Biztel 13 ...
IMT Lecture:Creating Project Plans To Focus Product Development.Mm Biztel 13 ...IMT Lecture:Creating Project Plans To Focus Product Development.Mm Biztel 13 ...
IMT Lecture:Creating Project Plans To Focus Product Development.Mm Biztel 13 ...Djadja Sardjana
 
Considerations in Selecting and Protecting Your IT Investment
Considerations in Selecting and Protecting Your IT InvestmentConsiderations in Selecting and Protecting Your IT Investment
Considerations in Selecting and Protecting Your IT InvestmentHelene Heller, PMP
 
Macrosolutions Training: Planning and Monitoring Projects with Microsoft Proj...
Macrosolutions Training: Planning and Monitoring Projects with Microsoft Proj...Macrosolutions Training: Planning and Monitoring Projects with Microsoft Proj...
Macrosolutions Training: Planning and Monitoring Projects with Microsoft Proj...Macrosolutions SA
 
Macrosolutions Training: Project Time Management
Macrosolutions Training: Project Time ManagementMacrosolutions Training: Project Time Management
Macrosolutions Training: Project Time ManagementMacrosolutions SA
 
Project Management Methodology
Project Management MethodologyProject Management Methodology
Project Management MethodologyC.Y Wong
 
Project management best practices
Project management best practicesProject management best practices
Project management best practiceswalkerswu
 
Cadence Presentation Eng 2011
Cadence Presentation Eng 2011Cadence Presentation Eng 2011
Cadence Presentation Eng 2011FrankKooijmans
 
Macrosolutions Training: Project Scope Management
Macrosolutions Training: Project Scope ManagementMacrosolutions Training: Project Scope Management
Macrosolutions Training: Project Scope ManagementMacrosolutions SA
 
Spp Careers 501 Project Management
Spp Careers 501 Project ManagementSpp Careers 501 Project Management
Spp Careers 501 Project Managementclarkbonilla
 
Macrosolutions Training: Project Management: Establishing Competitive Advantages
Macrosolutions Training: Project Management: Establishing Competitive AdvantagesMacrosolutions Training: Project Management: Establishing Competitive Advantages
Macrosolutions Training: Project Management: Establishing Competitive AdvantagesMacrosolutions SA
 
Macrosolutions Training: Project Management for Executives
Macrosolutions Training: Project Management for ExecutivesMacrosolutions Training: Project Management for Executives
Macrosolutions Training: Project Management for ExecutivesMacrosolutions SA
 

Similar to Schedule Design PMI (20)

Business PMO & IT Pmo What Is The Difference
Business PMO & IT Pmo What Is The DifferenceBusiness PMO & IT Pmo What Is The Difference
Business PMO & IT Pmo What Is The Difference
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan Presentation
 
Pmp pmi - training - project management certificate programme
Pmp   pmi - training - project management certificate programmePmp   pmi - training - project management certificate programme
Pmp pmi - training - project management certificate programme
 
QFH Consulting Capabilities
QFH Consulting CapabilitiesQFH Consulting Capabilities
QFH Consulting Capabilities
 
Macrosolutions PMDome Workshop (en)
Macrosolutions PMDome Workshop (en)Macrosolutions PMDome Workshop (en)
Macrosolutions PMDome Workshop (en)
 
Project management in pharmaceutical generic industry basics and standards
Project management in pharmaceutical generic industry basics and standardsProject management in pharmaceutical generic industry basics and standards
Project management in pharmaceutical generic industry basics and standards
 
IMT Lecture:Creating Project Plans To Focus Product Development.Mm Biztel 13 ...
IMT Lecture:Creating Project Plans To Focus Product Development.Mm Biztel 13 ...IMT Lecture:Creating Project Plans To Focus Product Development.Mm Biztel 13 ...
IMT Lecture:Creating Project Plans To Focus Product Development.Mm Biztel 13 ...
 
Resolving TIAs
Resolving TIAsResolving TIAs
Resolving TIAs
 
Considerations in Selecting and Protecting Your IT Investment
Considerations in Selecting and Protecting Your IT InvestmentConsiderations in Selecting and Protecting Your IT Investment
Considerations in Selecting and Protecting Your IT Investment
 
Macrosolutions Training: Planning and Monitoring Projects with Microsoft Proj...
Macrosolutions Training: Planning and Monitoring Projects with Microsoft Proj...Macrosolutions Training: Planning and Monitoring Projects with Microsoft Proj...
Macrosolutions Training: Planning and Monitoring Projects with Microsoft Proj...
 
Macrosolutions Training: Project Time Management
Macrosolutions Training: Project Time ManagementMacrosolutions Training: Project Time Management
Macrosolutions Training: Project Time Management
 
Project Management Methodology
Project Management MethodologyProject Management Methodology
Project Management Methodology
 
Project management best practices
Project management best practicesProject management best practices
Project management best practices
 
Cadence Presentation Eng 2011
Cadence Presentation Eng 2011Cadence Presentation Eng 2011
Cadence Presentation Eng 2011
 
Macrosolutions Training: Project Scope Management
Macrosolutions Training: Project Scope ManagementMacrosolutions Training: Project Scope Management
Macrosolutions Training: Project Scope Management
 
PMO 101
PMO 101PMO 101
PMO 101
 
Spp Careers 501 Project Management
Spp Careers 501 Project ManagementSpp Careers 501 Project Management
Spp Careers 501 Project Management
 
Macrosolutions Training: Project Management: Establishing Competitive Advantages
Macrosolutions Training: Project Management: Establishing Competitive AdvantagesMacrosolutions Training: Project Management: Establishing Competitive Advantages
Macrosolutions Training: Project Management: Establishing Competitive Advantages
 
Macrosolutions Training: Project Management for Executives
Macrosolutions Training: Project Management for ExecutivesMacrosolutions Training: Project Management for Executives
Macrosolutions Training: Project Management for Executives
 

More from Chris Carson

Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop ConferenceChris Carson
 
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesChris Carson
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry SchedulingChris Carson
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodChris Carson
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotChris Carson
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminChris Carson
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesChris Carson
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...Chris Carson
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesChris Carson
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful MediationChris Carson
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule RevisionsChris Carson
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex ProjectChris Carson
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesChris Carson
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - AirportChris Carson
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse WeatherChris Carson
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony MistakesChris Carson
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor SchedulingChris Carson
 

More from Chris Carson (20)

Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop Conference
 
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation Schedules
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry Scheduling
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis Method
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does Not
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract Admin
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
 
Claims Triage
Claims TriageClaims Triage
Claims Triage
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel Schedules
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful Mediation
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex Project
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual Schedules
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - Airport
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse Weather
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony Mistakes
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor Scheduling
 

Recently uploaded

8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCR8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCRashishs7044
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in PhilippinesDavidSamuel525586
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditNhtLNguyn9
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxsaniyaimamuddin
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 

Recently uploaded (20)

Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCR8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCR
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in Philippines
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal audit
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 

Schedule Design PMI

  • 1. Schedule Design – Planning for Schedule Development “Scheduling Chris Carson, PSP With Corporate Director of Project Controls the Masters” Alpha Corporation Chris.carson@alphacorporation.com 757-342-5524
  • 2. Schedule Design Why design a schedule? A schedule meets the criteria for a “project” in itself A schedule is a guideline or plan for a project A schedule provides a a methodical approach for a project Keeps the schedule development on track “Scheduling With Prevents rework due to late understanding of needs the Masters” Allows buy-in from end users prior to Development Makes the schedule development session much more meaningful Documents the assumptions and intention of the schedule For reviewer and approver For future reference To facilitate changes in schedulers Place to capture Lessons Learned 2 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 3. Schedule Design Scope of Design vs. Development Design – Conceptualizing the schedule Planning Starting with the end in mind Providing concept of final product “Scheduling Creating organizational structure to fulfill the concept With the Masters” Development - Building the schedule Input activities Input logic Input durations Review for design compliance Review for CPM methodology best practices Quality control 3 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 4. Schedule Design - Background • Design vs. Development – How PMI & PMBOK handles it? – PMBOK identifies six Project Time Management processes, usually defined as part of the project lifecycle, Section 2.1 of PMBOK. Activity Definition. Activity Sequencing. Activity Resource Estimating. “Scheduling Activity Duration Estimating. With Schedule Development. Schedule Control. the Masters” – These processes are preceded by a planning effort by the project management team, which is part of PMBOK’s “Develop Project Management Plan”, PMBOK Section 4.3 (which sets the format and establishes criteria for developing the project schedule). – These processes are documented in what PMBOK calls a Schedule Management Plan, which is contained in the project management plan, in the introduction to Section 4.3, Project Integration Management. 4 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 5. Schedule Design - Background • PMBOK Process Inputs. – The inputs for the different Time Management Processes are listed as: Activity list. Product description. Mandatory dependencies. Discretionary dependencies. External dependencies. “Scheduling Resource requirements. With Resource capabilities. Historical information. the Masters” Identified risks. Constraints. Assumptions. – All of these items, along with the Schedule Management Plan, are part of Schedule Design, but PMBOK does not offer clear definition and delineation of Schedule Design. – The Time Management Processes do not include Schedule Design. 5 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 6. Schedule Design - Background • Design vs. Development – why emphasize the distinction? – Design tends to be ignored in favor of jumping “Scheduling right into development. With Many schedulers elect to begin creating activities the Masters” instead of Designing. Work is subsequently repetitive, with lots of potential for rework. Results tend to be disorganized. • Avoid planning mistakes and problems. 6 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 7. Schedule Design • Avoid planning mistakes and problems “Scheduling With the Masters” 7 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 8. Schedule Design • Lack of Good Area Definition preventing activity closeout: “Scheduling With the Masters” Hinders productivity Areas are so analysis, good broadly defined cost loading, that activities sit accurate as- at nearly built dates. complete for large parts of the project. 8 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 9. Schedule Design • Inconsistency in level of detail throughout trades: “Scheduling With the Masters” Some trades are heavily developed while others are left with summary-level activities only. 9 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 10. Schedule Design Documentation and use of Schedule Design Create a book or binder Use the highest level of checklist outline items as tabs Use the book as basis for schedule submittal “Scheduling documentation With Keep the book current during project the Masters” Use the book for handoff between schedulers Share a copy of the book with superintendent/PM Timing Must be done prior to Schedule Development 10 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 11. Schedule Design Checklist Project Description Reference Documents Contract Project Drawings “Scheduling Specifications With Scheduling Specification the Masters” Notice to Proceed or Release Letter Any Owner produced master schedule Liquidated Damages schedule Area Designation Plan Sequencing plan Estimate & quantity surveys/bills of materials 11 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 12. Schedule Design Checklist - Schedule Specification – General Contents. “Scheduling With the Masters” 12 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 13. Schedule Design Checklist Team Players Organizational Chart (OBS) Who are Schedule Users? Who has Input “Scheduling Who Updates With Who Checks for Accuracy the Masters” Who Reviews Who approves Identify Responsibility Assignment Matrix (RAM) 13 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 14. Schedule Design Checklist Organizational Breakdown Structure. “Scheduling With the Masters” From: DOE Training “EVM Tutorial – WBS” by Booze-Allen-Hamilton 14 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 15. Schedule Design RAM Example (based on PMBOK RACI Chart) “Scheduling With the Masters” 15 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 16. Schedule Design Checklist Software Identification Specific software Required minimum and versions allowed Enterprise specific issues “Scheduling Users identified With Schedules used for import or data source the Masters” Levels of access Validation process For master schedules, establish data dates 16 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 17. Schedule Design Checklist Work Product What the Schedule can be used for (purpose) Reports Generated from the Schedule Who receives reports List of reports “Scheduling Samples of reports With Glossary/Lexicon of ambiguous terms the Masters” Schedule Outline Key Activities being tracked Client Milestones Long Lead Items WBS Structure Other Contracts on Project 17 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 18. Schedule Design Reporting “Scheduling With the Masters” 18 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 19. Schedule Design Checklist Work Package Development. By Contract. As assigned by Client. “Scheduling VI. Work Packages With Division 2 and 5 Specifications require the following Work the Masters” Packages: – Superstructure Waterproofing – Corrosion Protection of Structural Steelwork – Movements and Tolerances Specification for Structural Steel – Structural Steel Superstructure – Cast in Place Concrete 19 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 20. Schedule Design Checklist Level of Detail Determine approach: Bottom-up (starting with detailed activities) Top-down (starting with summary schedule) “Scheduling Both (prepare Top-down, then Bottom-up) With Identify frequency of updates the Masters” Establish smallest activity duration range 20 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 21. Schedule Design Checklist Codes Dictionary For tracking and monitoring work: Work Phase Structure Area “Scheduling Floor or Station With Location. the Masters” For Project Management: Responsibility Work Shifts Costs Resource Specification Change management 21 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 22. Schedule Design Checklist Calendars Establish number needed Define calendars and application Costs & Resources Estimate & correlation to cost loading Bill of Quantities & use in resources “Scheduling Resource Crew descriptions With Equipment descriptions the Masters” How actual production will be monitored Earned Value Management System Narrative Basis & Assumptions Procedure Used to create the Schedule Definitions/lexicon Description of sequence of work per structure 22 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 23. Schedule Design Checklist Example of Calendar Section: • Calendars are defined as follows: – Calendar 1 – 24 hours a day, 7 days a week. “Scheduling – Calendar 2 – 24 hours a day, only Fridays off. (This is the Default With Calendar.) the Masters” – Calendar 3 – Night Shift, only Fridays off. – Calendar 4 – Night Shift, 24 hours a day, 7 days a week. – Please note that 01140/1.9.a. requires that the Contractor notify the Client regarding multiple shifts, etc. This has been accomplished by using Day and Night sift calendars as well as by incorporating multiple crew codes into the Program. (For more on Crews, please refer to the Resources section of this report.) 23 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 24. Schedule Design Checklist Example of Lexicon General Notes Regarding this Report: • “Program,” “Programme,” and “Baseline CPM,” and “Schedule” all have the same definition and are used interchangeably. • “Snagging” and “Punch-out” have the same definition and are used interchangeably. “Scheduling • “Fixed” and “Rough-in” have roughly the same definition. For clarification purposes, “Fixed” has been used in this Program. With the Masters” • “Conventional concrete” is defined as post-tension poured-in- place concrete. • “Wild Air” is defined as a stage in construction, for which the building is closed in by perimeter walls and ventilation has started. (Ventilation only, not complete environmental controls or functioning air conditioning.) This term is used in lieu of “environmental controls,” or “drying –in” as wet weather is not a real factor in Dubai. • “Raft” construction consists of the foundation including but not limited to piles, grade beams, footers, and slab-on-grade. 24 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 25. Schedule Design Narrative Basis “Scheduling With the Masters” 25 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 26. Schedule Design Checklist Risks & Constructability Brainstorming of issues Known problems (threats) Provisional Items “Scheduling Predicted Problems With Lessons Learned the Masters” Outside influences Site condition concerns Opportunities Develop Risk Management Plan Initial process during baseline schedule development Process for use during updates 26 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 27. Schedule Design Risk Management Plan – Based on PMBOK “Scheduling With the Masters” 27 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 28. Schedule Design Checklist Weather planning Expected adverse weather Identify source or specification requirement Identify methodology “Scheduling Identify accounting method for actual weather With the Masters” 28 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 29. Schedule Design Checklist Time Contingencies Amounts Specific trade (from risk management plan) Specific contractor contingency How carried “Scheduling Use historical data for reference With the Masters” Time Performance Ratio 12.0 10.0 8.0 TPR 6.0 4.0 2.0 0.0 ev s ry s ry ws nt e E l ca l / W fing l E q hes ar ls rk in ca g or et a on nt m Fu me wo in do ni tri et at cr pe oo Ad s ish as ha ec te M ni p on in R ui Fi M Si rn ec El C C M rs oo D Type of Work 29 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 30. Schedule Design Checklist Establish Update process Frequency Data request and transmission Validation “Scheduling Process flowchart With the Masters” Collect Admin Verify All Progress Data Data Request for Collect Field Status Update Compare to Update Data Progress Data Schedule Schedule Baseline Identify Contract Changes 30 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 31. Schedule Design Checklist Change Management process Notification requirements Methodology allowed Process flowchart “Scheduling With the Masters” 31 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 32. Collect Admin Verify All Progress Data Data No Request for Collect Field Status Update Compare to Critical Path Update Data Progress Data Schedule Schedule Baseline Delay? Yes Identify Contract Changes Identify Previous Period Critical Path Publish Research Updated Quantify Identify Causal Identify Changes Documents For Schedule Delays Delay Activities To Critical Path Driving Delays “Scheduling Is the With Assess Any Perform Owner Yes Yes Prepare Responsibility Concurrent Concurrent Delay Responsible the Masters”Delays Recovery For Delays? Analysis For Delay? Schedule No No Resolve Subcontractor Is a Is the Contributions No No Verify Single Subcontractor Owner Source Delay Responsible Responsible Responsibility For Delay? For Delay? Discuss Delay & Mitigation with Yes Subcontractor Yes Proposed Schedule Update With Change Management Discuss Delay Prepare Delay & Mitigation Analysis With Owner & Change Order 32 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 33. Schedule Design Checklist Recovery process Identify what logic changes are acceptable without formal approval Identify what constitutes a Revision requiring “Scheduling approval With Provide process description or flow chart the Masters” 33 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 34. Schedule Design Checklist 18. Dispute resolution process 1. Review program for claims avoidance 1. Reinforce planning for claims avoidance 2. Identify specific program for claims avoidance during “Scheduling schedule updates and change management With 2. Identify steps if change management process fails or the Masters” stalls 3. Follow specifications 4. Provide time frames for stages in process 5. Provide process description or flow chart 34 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 35. Schedule Design Conclusion • For success in Schedule Development, Schedule Design should be a completely different process “Scheduling With • Process done prior to Development the Masters” • Process and results documented • Documentation done in formal Schedule Design Book • Book used to provide continuity between schedulers or project managers 35 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 36. Schedule Design • Resources – See Lance Stephenson’s “Schedule Basis Memorandum” paper, also addresses schedule levels – See AACEi’s Total Cost Management “Scheduling – See PMBOK for Risk Management process With • Recommendations the Masters” – Get involved with the CoS SEI Project developing Best Practices and Guidelines for Scheduling – Get involved with AACEi and the Recommended Practices development – Get involved with CMAA in the Time Management development 36 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 37. Schedule Design Questions? Recommendations? “Scheduling With War Stories? the Masters” Gripes? 37 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 38. Schedule Design – Planning for Schedule Development “Scheduling With Chris Carson, PSP the Masters” Corporate Director of Project Controls Alpha Corporation 101 West Main Street, Suite 715 Norfolk, VA 23510 757-533-9368 Office 757-342-5524 Mobile Chris.carson@alphacorporation.com 38 PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc.