Army Radar Approach
Control
(ARAC)
Project Update
October 4, 2016
Agenda
 Project Update
 Financial Update
 Summary and Questions
ARAC
 DEAAG
 Awarded April 4, 2016
 Funding Available September 1, 2016
 Funding Agreements
 Garrison – Fort Hood April 1, 2016
 KEDC – August 9, 2016
 Project
 Design Began April 18, 2016 / Completed August 4, 2016
 Bid Let August 21, 2016 / Bid Opening September 15, 2016
 Construction Award / Start
 TACROF
 Installation Start – September 12, 2016 / Operational October 10, 2016
 Equipment / Data Transfer – on going
ARAC Facility
ARAC Controller Stations
TACROF Arrival / Set-Up
ARAC West View
TACROF Positioned
TACROF Controller Stations
TACROF
Equipment /
Cable
Install
Financial Update
Funding Summary
CITY OF KILLEEN - AVIATION
Expenses - 528-0505-521.57-81
ARAC
PROJECT FUNDING AMOUNT: $5,000,000
Date of Request Vendor Invoice No. Expended USAG-FT KEDC DEAAG Grant Request Amt. Remaining Bal.
1,000,000.00 525,000.00 3,475,000 5,000,000
06/17/16 Garver 16181082-1 63,380.00 936,620.00 - - 63,380 4,936,620
06/24/16 Garver 16181082-2 82,620.00 854,000.00 - - 82,620 4,854,000
08/05/16 Garver 16181082-3 26,775.00 827,225.00 - - 26,775 4,827,225
09/01/16 Garver 16181082-4 78,690.00 748,535.00 - - 78,690 4,748,535
09/09/16 KAYA Assoc. 0000023703 12,000.00 736,535.00 - - 12,000 4,736,535
Supplemental Agreement (SA) Summary
ARAC – Professional Services Agreement
Garver $477,260
SA # Vendor Reason Request Updated Contract Amt % Change in Contract
1 Garver Additions to Specifications to meet DoD / FH requirements, Environmental 21,700 498,960 4.6
Study (asbestos, mold, etc.)
2 Garver Add disabled parking design to plans, redesign plans to meet FH Network 7,500 506,460 6.1
Enterprise Center requirements
3 Garver Add full-time resident project representative 62,710 569,170 19.26
Schedule
Milestone Date Comment
Design Complete August 03 On time
Construction Documents August 19 On time
Bidding Process
Advertised August 21 On time
Opening September 15 On time
Council Approval October 11
Notice of Award October 12
Contracts Executed October 21
Notice to Proceed October 24
Construction October 24 Scheduled for completion
Aug 31,2017
Summary
 ARAC
 TACROF
 Financial Update
 Schedule Update
Questions?

Contenu connexe

Tendances

Tendances (19)

Formats of Cost and Financial Control Reports
Formats of Cost and Financial Control ReportsFormats of Cost and Financial Control Reports
Formats of Cost and Financial Control Reports
 
Preston County Tax Parcel Mapping
Preston County Tax Parcel MappingPreston County Tax Parcel Mapping
Preston County Tax Parcel Mapping
 
CLB 007
CLB 007CLB 007
CLB 007
 
Sacs otc 2012
Sacs otc 2012Sacs otc 2012
Sacs otc 2012
 
ERDENEBAT 374-2
ERDENEBAT 374-2ERDENEBAT 374-2
ERDENEBAT 374-2
 
DAINFERN - WESTERN SKYLIGHT
DAINFERN - WESTERN SKYLIGHTDAINFERN - WESTERN SKYLIGHT
DAINFERN - WESTERN SKYLIGHT
 
Brown and root
Brown and rootBrown and root
Brown and root
 
Concrete Delivery Ticket Process
Concrete Delivery Ticket ProcessConcrete Delivery Ticket Process
Concrete Delivery Ticket Process
 
Innovation of Coal Seam Gas Well-Construction Process in Australia:
Innovation of Coal Seam Gas Well-Construction Process in Australia:Innovation of Coal Seam Gas Well-Construction Process in Australia:
Innovation of Coal Seam Gas Well-Construction Process in Australia:
 
RPAS Topographic Survey at Dun Laoghaire Town Centre and Harbour - European c...
RPAS Topographic Survey at Dun Laoghaire Town Centre and Harbour - European c...RPAS Topographic Survey at Dun Laoghaire Town Centre and Harbour - European c...
RPAS Topographic Survey at Dun Laoghaire Town Centre and Harbour - European c...
 
Mintis_Dimitris_dm476_Chemical Engineering_Wessex Water PLC_Poster_14-15 v3
Mintis_Dimitris_dm476_Chemical Engineering_Wessex Water PLC_Poster_14-15 v3Mintis_Dimitris_dm476_Chemical Engineering_Wessex Water PLC_Poster_14-15 v3
Mintis_Dimitris_dm476_Chemical Engineering_Wessex Water PLC_Poster_14-15 v3
 
Petrochemical Infographic
Petrochemical InfographicPetrochemical Infographic
Petrochemical Infographic
 
WRY-Managment Certificates
WRY-Managment CertificatesWRY-Managment Certificates
WRY-Managment Certificates
 
Inverted heading calibration
Inverted heading calibrationInverted heading calibration
Inverted heading calibration
 
A b testing
A b testingA b testing
A b testing
 
Document160383
Document160383Document160383
Document160383
 
AAT 2007
AAT 2007AAT 2007
AAT 2007
 
GTS Brochure
GTS BrochureGTS Brochure
GTS Brochure
 
PCAPP Update 25 June 2014
PCAPP Update 25 June 2014PCAPP Update 25 June 2014
PCAPP Update 25 June 2014
 

En vedette

Continuous Update Project Overview (Conference: Diet and cancer: from prevent...
Continuous Update Project Overview (Conference: Diet and cancer: from prevent...Continuous Update Project Overview (Conference: Diet and cancer: from prevent...
Continuous Update Project Overview (Conference: Diet and cancer: from prevent...World Cancer Research Fund International
 
Business development and enterprise (update) 1
Business development and enterprise (update) 1Business development and enterprise (update) 1
Business development and enterprise (update) 1ahzilah
 
FrontRunner South Project Update Oct 2011
FrontRunner South Project Update Oct 2011FrontRunner South Project Update Oct 2011
FrontRunner South Project Update Oct 2011Utah Transit Authority
 
7.15.15 RCTC 91 Project Update
7.15.15 RCTC 91 Project Update 7.15.15 RCTC 91 Project Update
7.15.15 RCTC 91 Project Update City of Corona
 
GlassFish & Java EE Business Update @ CEJUG
GlassFish & Java EE Business Update @ CEJUGGlassFish & Java EE Business Update @ CEJUG
GlassFish & Java EE Business Update @ CEJUGArun Gupta
 
I-74 Corridor Project Update - Iowa Department of Transportation
I-74 Corridor Project Update - Iowa Department of TransportationI-74 Corridor Project Update - Iowa Department of Transportation
I-74 Corridor Project Update - Iowa Department of TransportationIowa Department of Transportation
 
IBM Global Business Services Cloud Update
IBM Global Business Services Cloud UpdateIBM Global Business Services Cloud Update
IBM Global Business Services Cloud UpdateIBMADI
 
Edison International Business Update - February 2017
Edison International Business Update - February 2017Edison International Business Update - February 2017
Edison International Business Update - February 2017EdisonInternational
 
Land Development Update-February 11, 2016
Land Development Update-February 11, 2016Land Development Update-February 11, 2016
Land Development Update-February 11, 2016Fairfax County
 
Luxury for Millennials
Luxury for MillennialsLuxury for Millennials
Luxury for MillennialsMindSwarms
 
Intelligent Transportation System (ITS) Project Update
Intelligent Transportation System (ITS) Project UpdateIntelligent Transportation System (ITS) Project Update
Intelligent Transportation System (ITS) Project UpdateFairfax County
 
Sponsorship Presentation [3]
Sponsorship  Presentation [3]Sponsorship  Presentation [3]
Sponsorship Presentation [3]guest45108e
 

En vedette (16)

XCP Project Update
XCP Project UpdateXCP Project Update
XCP Project Update
 
Continuous Update Project Overview (Conference: Diet and cancer: from prevent...
Continuous Update Project Overview (Conference: Diet and cancer: from prevent...Continuous Update Project Overview (Conference: Diet and cancer: from prevent...
Continuous Update Project Overview (Conference: Diet and cancer: from prevent...
 
Business development and enterprise (update) 1
Business development and enterprise (update) 1Business development and enterprise (update) 1
Business development and enterprise (update) 1
 
FrontRunner South Project Update Oct 2011
FrontRunner South Project Update Oct 2011FrontRunner South Project Update Oct 2011
FrontRunner South Project Update Oct 2011
 
7.15.15 RCTC 91 Project Update
7.15.15 RCTC 91 Project Update 7.15.15 RCTC 91 Project Update
7.15.15 RCTC 91 Project Update
 
GlassFish & Java EE Business Update @ CEJUG
GlassFish & Java EE Business Update @ CEJUGGlassFish & Java EE Business Update @ CEJUG
GlassFish & Java EE Business Update @ CEJUG
 
The Continuous Update Project: Introduction to the Project
The Continuous Update Project: Introduction to the ProjectThe Continuous Update Project: Introduction to the Project
The Continuous Update Project: Introduction to the Project
 
I-74 Corridor Project Update - Iowa Department of Transportation
I-74 Corridor Project Update - Iowa Department of TransportationI-74 Corridor Project Update - Iowa Department of Transportation
I-74 Corridor Project Update - Iowa Department of Transportation
 
Business Update
Business UpdateBusiness Update
Business Update
 
IBM Global Business Services Cloud Update
IBM Global Business Services Cloud UpdateIBM Global Business Services Cloud Update
IBM Global Business Services Cloud Update
 
Edison International Business Update - February 2017
Edison International Business Update - February 2017Edison International Business Update - February 2017
Edison International Business Update - February 2017
 
Land Development Update-February 11, 2016
Land Development Update-February 11, 2016Land Development Update-February 11, 2016
Land Development Update-February 11, 2016
 
Luxury for Millennials
Luxury for MillennialsLuxury for Millennials
Luxury for Millennials
 
Intelligent Transportation System (ITS) Project Update
Intelligent Transportation System (ITS) Project UpdateIntelligent Transportation System (ITS) Project Update
Intelligent Transportation System (ITS) Project Update
 
Research report
Research reportResearch report
Research report
 
Sponsorship Presentation [3]
Sponsorship  Presentation [3]Sponsorship  Presentation [3]
Sponsorship Presentation [3]
 

Similaire à DS-16-147 DEAAG Project Update

IPP Utility Scale Solar PV Project Development Roadmap
IPP Utility Scale Solar PV Project Development RoadmapIPP Utility Scale Solar PV Project Development Roadmap
IPP Utility Scale Solar PV Project Development RoadmapFadi Maalouf, PMP
 
UK offshore wind vision of the market and technology development Giles Hundl...
UK offshore wind  vision of the market and technology development Giles Hundl...UK offshore wind  vision of the market and technology development Giles Hundl...
UK offshore wind vision of the market and technology development Giles Hundl...BVG Associates
 
OW_13092023_EN_www.pdf
OW_13092023_EN_www.pdfOW_13092023_EN_www.pdf
OW_13092023_EN_www.pdfBaltic Wind
 
OW_13092023_EN_www.pptx
OW_13092023_EN_www.pptxOW_13092023_EN_www.pptx
OW_13092023_EN_www.pptxBaltic Wind
 
Cw 2016 investor day final
Cw 2016 investor day finalCw 2016 investor day final
Cw 2016 investor day finalq4curtisswright
 
Kalyan Chunchu Resume
Kalyan Chunchu Resume Kalyan Chunchu Resume
Kalyan Chunchu Resume Kalyan Chunchu
 
RDS as at 160527
RDS as at 160527RDS as at 160527
RDS as at 160527Rob Smith
 
Myanmar East Asia and Pacific National Electrification Project - Procurement ...
Myanmar East Asia and Pacific National Electrification Project - Procurement ...Myanmar East Asia and Pacific National Electrification Project - Procurement ...
Myanmar East Asia and Pacific National Electrification Project - Procurement ...MYO AUNG Myanmar
 
77565239 13-cost-benefit-analysis
77565239 13-cost-benefit-analysis77565239 13-cost-benefit-analysis
77565239 13-cost-benefit-analysiskeruks
 
Alan Duncan's All Energy 2017 Offshore wind: the importance of the supply chain
Alan Duncan's All Energy 2017 Offshore wind: the importance of the supply chainAlan Duncan's All Energy 2017 Offshore wind: the importance of the supply chain
Alan Duncan's All Energy 2017 Offshore wind: the importance of the supply chainBVG Associates
 
IRPT Energy Commodities Presentation
IRPT Energy Commodities Presentation IRPT Energy Commodities Presentation
IRPT Energy Commodities Presentation PLG Consulting
 
IRPT Energy Commodities presentation 04242017
IRPT Energy Commodities presentation 04242017IRPT Energy Commodities presentation 04242017
IRPT Energy Commodities presentation 04242017Taylor Robinson
 
From Upstream to Downstream: Opportunities and Challenges for Rail
From Upstream to Downstream: Opportunities and Challenges for RailFrom Upstream to Downstream: Opportunities and Challenges for Rail
From Upstream to Downstream: Opportunities and Challenges for RailPLG Consulting
 
NRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATIONNRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATIONElliott Molnar
 

Similaire à DS-16-147 DEAAG Project Update (20)

IPP Utility Scale Solar PV Project Development Roadmap
IPP Utility Scale Solar PV Project Development RoadmapIPP Utility Scale Solar PV Project Development Roadmap
IPP Utility Scale Solar PV Project Development Roadmap
 
ESSP support to LPV implementation
ESSP support to LPV implementationESSP support to LPV implementation
ESSP support to LPV implementation
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
UK offshore wind vision of the market and technology development Giles Hundl...
UK offshore wind  vision of the market and technology development Giles Hundl...UK offshore wind  vision of the market and technology development Giles Hundl...
UK offshore wind vision of the market and technology development Giles Hundl...
 
OW_13092023_EN_www.pdf
OW_13092023_EN_www.pdfOW_13092023_EN_www.pdf
OW_13092023_EN_www.pdf
 
OW_13092023_EN_www.pptx
OW_13092023_EN_www.pptxOW_13092023_EN_www.pptx
OW_13092023_EN_www.pptx
 
Cw 2016 investor day final
Cw 2016 investor day finalCw 2016 investor day final
Cw 2016 investor day final
 
Kalyan Chunchu Resume
Kalyan Chunchu Resume Kalyan Chunchu Resume
Kalyan Chunchu Resume
 
QPR-1 draft.pptx
QPR-1 draft.pptxQPR-1 draft.pptx
QPR-1 draft.pptx
 
RDS as at 160527
RDS as at 160527RDS as at 160527
RDS as at 160527
 
Myanmar East Asia and Pacific National Electrification Project - Procurement ...
Myanmar East Asia and Pacific National Electrification Project - Procurement ...Myanmar East Asia and Pacific National Electrification Project - Procurement ...
Myanmar East Asia and Pacific National Electrification Project - Procurement ...
 
77565239 13-cost-benefit-analysis
77565239 13-cost-benefit-analysis77565239 13-cost-benefit-analysis
77565239 13-cost-benefit-analysis
 
Alan Duncan's All Energy 2017 Offshore wind: the importance of the supply chain
Alan Duncan's All Energy 2017 Offshore wind: the importance of the supply chainAlan Duncan's All Energy 2017 Offshore wind: the importance of the supply chain
Alan Duncan's All Energy 2017 Offshore wind: the importance of the supply chain
 
Sakil-resume
Sakil-resumeSakil-resume
Sakil-resume
 
Target
TargetTarget
Target
 
IRPT Energy Commodities Presentation
IRPT Energy Commodities Presentation IRPT Energy Commodities Presentation
IRPT Energy Commodities Presentation
 
IRPT Energy Commodities presentation 04242017
IRPT Energy Commodities presentation 04242017IRPT Energy Commodities presentation 04242017
IRPT Energy Commodities presentation 04242017
 
Enhancing performance using a programme dashboard
Enhancing performance using a programme dashboard Enhancing performance using a programme dashboard
Enhancing performance using a programme dashboard
 
From Upstream to Downstream: Opportunities and Challenges for Rail
From Upstream to Downstream: Opportunities and Challenges for RailFrom Upstream to Downstream: Opportunities and Challenges for Rail
From Upstream to Downstream: Opportunities and Challenges for Rail
 
NRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATIONNRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATION
 

Plus de CityofKilleen

RS-17-047 - Committee Membership
RS-17-047 - Committee MembershipRS-17-047 - Committee Membership
RS-17-047 - Committee MembershipCityofKilleen
 
RS-17-035 - Sale of Real Property
RS-17-035 - Sale of Real PropertyRS-17-035 - Sale of Real Property
RS-17-035 - Sale of Real PropertyCityofKilleen
 
RS-17-031 - Quarterly Investment Report Presentation
RS-17-031 - Quarterly Investment Report PresentationRS-17-031 - Quarterly Investment Report Presentation
RS-17-031 - Quarterly Investment Report PresentationCityofKilleen
 
RS-17-030 - Annual Audit Report
RS-17-030 - Annual Audit ReportRS-17-030 - Annual Audit Report
RS-17-030 - Annual Audit ReportCityofKilleen
 
PH-17-021 - Auditing Services Budget Amendment
PH-17-021 - Auditing Services Budget AmendmentPH-17-021 - Auditing Services Budget Amendment
PH-17-021 - Auditing Services Budget AmendmentCityofKilleen
 
DS-17-048 - Killeen Visioning Session
DS-17-048 - Killeen Visioning SessionDS-17-048 - Killeen Visioning Session
DS-17-048 - Killeen Visioning SessionCityofKilleen
 
DS-17-046 - Policy for Citizen Appointments
DS-17-046 - Policy for Citizen AppointmentsDS-17-046 - Policy for Citizen Appointments
DS-17-046 - Policy for Citizen AppointmentsCityofKilleen
 
DS-17-043 - Parks Master Plan
DS-17-043 - Parks Master PlanDS-17-043 - Parks Master Plan
DS-17-043 - Parks Master PlanCityofKilleen
 
DS-17-044 - Quarterly Finance Report
DS-17-044 - Quarterly Finance ReportDS-17-044 - Quarterly Finance Report
DS-17-044 - Quarterly Finance ReportCityofKilleen
 
DS-17-038 Election Signs on City Property
DS-17-038 Election Signs on City PropertyDS-17-038 Election Signs on City Property
DS-17-038 Election Signs on City PropertyCityofKilleen
 
DS-17-037 Red Light Program
DS-17-037 Red Light ProgramDS-17-037 Red Light Program
DS-17-037 Red Light ProgramCityofKilleen
 
DS-17-041 Process for Making Recommendations for Citizen Appointments
DS-17-041 Process for Making Recommendations for Citizen AppointmentsDS-17-041 Process for Making Recommendations for Citizen Appointments
DS-17-041 Process for Making Recommendations for Citizen AppointmentsCityofKilleen
 
DS-17-035 Audit Process
DS-17-035 Audit ProcessDS-17-035 Audit Process
DS-17-035 Audit ProcessCityofKilleen
 
DS-17-030 CDBG Priorities
DS-17-030 CDBG PrioritiesDS-17-030 CDBG Priorities
DS-17-030 CDBG PrioritiesCityofKilleen
 
DS-17-021 Animal Shelter
DS-17-021 Animal ShelterDS-17-021 Animal Shelter
DS-17-021 Animal ShelterCityofKilleen
 
DS-17-020 Vision 2030 2.0
DS-17-020 Vision 2030 2.0DS-17-020 Vision 2030 2.0
DS-17-020 Vision 2030 2.0CityofKilleen
 
Killeen Parks Master Plan
Killeen Parks Master PlanKilleen Parks Master Plan
Killeen Parks Master PlanCityofKilleen
 
DS-17-014 City Council Chambers Concept
DS-17-014 City Council Chambers ConceptDS-17-014 City Council Chambers Concept
DS-17-014 City Council Chambers ConceptCityofKilleen
 
DS-17-012 MUD Update
DS-17-012 MUD UpdateDS-17-012 MUD Update
DS-17-012 MUD UpdateCityofKilleen
 
2012 Water & Wastewater Master Plan
2012 Water & Wastewater Master Plan2012 Water & Wastewater Master Plan
2012 Water & Wastewater Master PlanCityofKilleen
 

Plus de CityofKilleen (20)

RS-17-047 - Committee Membership
RS-17-047 - Committee MembershipRS-17-047 - Committee Membership
RS-17-047 - Committee Membership
 
RS-17-035 - Sale of Real Property
RS-17-035 - Sale of Real PropertyRS-17-035 - Sale of Real Property
RS-17-035 - Sale of Real Property
 
RS-17-031 - Quarterly Investment Report Presentation
RS-17-031 - Quarterly Investment Report PresentationRS-17-031 - Quarterly Investment Report Presentation
RS-17-031 - Quarterly Investment Report Presentation
 
RS-17-030 - Annual Audit Report
RS-17-030 - Annual Audit ReportRS-17-030 - Annual Audit Report
RS-17-030 - Annual Audit Report
 
PH-17-021 - Auditing Services Budget Amendment
PH-17-021 - Auditing Services Budget AmendmentPH-17-021 - Auditing Services Budget Amendment
PH-17-021 - Auditing Services Budget Amendment
 
DS-17-048 - Killeen Visioning Session
DS-17-048 - Killeen Visioning SessionDS-17-048 - Killeen Visioning Session
DS-17-048 - Killeen Visioning Session
 
DS-17-046 - Policy for Citizen Appointments
DS-17-046 - Policy for Citizen AppointmentsDS-17-046 - Policy for Citizen Appointments
DS-17-046 - Policy for Citizen Appointments
 
DS-17-043 - Parks Master Plan
DS-17-043 - Parks Master PlanDS-17-043 - Parks Master Plan
DS-17-043 - Parks Master Plan
 
DS-17-044 - Quarterly Finance Report
DS-17-044 - Quarterly Finance ReportDS-17-044 - Quarterly Finance Report
DS-17-044 - Quarterly Finance Report
 
DS-17-038 Election Signs on City Property
DS-17-038 Election Signs on City PropertyDS-17-038 Election Signs on City Property
DS-17-038 Election Signs on City Property
 
DS-17-037 Red Light Program
DS-17-037 Red Light ProgramDS-17-037 Red Light Program
DS-17-037 Red Light Program
 
DS-17-041 Process for Making Recommendations for Citizen Appointments
DS-17-041 Process for Making Recommendations for Citizen AppointmentsDS-17-041 Process for Making Recommendations for Citizen Appointments
DS-17-041 Process for Making Recommendations for Citizen Appointments
 
DS-17-035 Audit Process
DS-17-035 Audit ProcessDS-17-035 Audit Process
DS-17-035 Audit Process
 
DS-17-030 CDBG Priorities
DS-17-030 CDBG PrioritiesDS-17-030 CDBG Priorities
DS-17-030 CDBG Priorities
 
DS-17-021 Animal Shelter
DS-17-021 Animal ShelterDS-17-021 Animal Shelter
DS-17-021 Animal Shelter
 
DS-17-020 Vision 2030 2.0
DS-17-020 Vision 2030 2.0DS-17-020 Vision 2030 2.0
DS-17-020 Vision 2030 2.0
 
Killeen Parks Master Plan
Killeen Parks Master PlanKilleen Parks Master Plan
Killeen Parks Master Plan
 
DS-17-014 City Council Chambers Concept
DS-17-014 City Council Chambers ConceptDS-17-014 City Council Chambers Concept
DS-17-014 City Council Chambers Concept
 
DS-17-012 MUD Update
DS-17-012 MUD UpdateDS-17-012 MUD Update
DS-17-012 MUD Update
 
2012 Water & Wastewater Master Plan
2012 Water & Wastewater Master Plan2012 Water & Wastewater Master Plan
2012 Water & Wastewater Master Plan
 

Dernier

Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlEdouardHusson
 
SMART BANGLADESH I PPTX I SLIDE IShovan Prita Paul.pptx
SMART BANGLADESH  I    PPTX   I    SLIDE   IShovan Prita Paul.pptxSMART BANGLADESH  I    PPTX   I    SLIDE   IShovan Prita Paul.pptx
SMART BANGLADESH I PPTX I SLIDE IShovan Prita Paul.pptxShovan Prita Paul .
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxSwastiRanjanNayak
 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterChristina Parmionova
 
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...robinsonayot
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30JSchaus & Associates
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)NAP Global Network
 
2024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 312024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 31JSchaus & Associates
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfSamirsinh Parmar
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learningNAP Global Network
 
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakurbest call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha ThakurSUHANI PANDEY
 
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...tanu pandey
 
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...tanu pandey
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Call Girls in Nagpur High Profile
 
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...SUHANI PANDEY
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'NAP Global Network
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...nservice241
 
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...SUHANI PANDEY
 

Dernier (20)

Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
SMART BANGLADESH I PPTX I SLIDE IShovan Prita Paul.pptx
SMART BANGLADESH  I    PPTX   I    SLIDE   IShovan Prita Paul.pptxSMART BANGLADESH  I    PPTX   I    SLIDE   IShovan Prita Paul.pptx
SMART BANGLADESH I PPTX I SLIDE IShovan Prita Paul.pptx
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptx
 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - Poster
 
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)
 
2024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 312024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 31
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
 
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition PlansSustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learning
 
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakurbest call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
 
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
 
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
 
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
 
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
 

DS-16-147 DEAAG Project Update

  • 2. Agenda  Project Update  Financial Update  Summary and Questions
  • 3. ARAC  DEAAG  Awarded April 4, 2016  Funding Available September 1, 2016  Funding Agreements  Garrison – Fort Hood April 1, 2016  KEDC – August 9, 2016  Project  Design Began April 18, 2016 / Completed August 4, 2016  Bid Let August 21, 2016 / Bid Opening September 15, 2016  Construction Award / Start  TACROF  Installation Start – September 12, 2016 / Operational October 10, 2016  Equipment / Data Transfer – on going
  • 11. Financial Update Funding Summary CITY OF KILLEEN - AVIATION Expenses - 528-0505-521.57-81 ARAC PROJECT FUNDING AMOUNT: $5,000,000 Date of Request Vendor Invoice No. Expended USAG-FT KEDC DEAAG Grant Request Amt. Remaining Bal. 1,000,000.00 525,000.00 3,475,000 5,000,000 06/17/16 Garver 16181082-1 63,380.00 936,620.00 - - 63,380 4,936,620 06/24/16 Garver 16181082-2 82,620.00 854,000.00 - - 82,620 4,854,000 08/05/16 Garver 16181082-3 26,775.00 827,225.00 - - 26,775 4,827,225 09/01/16 Garver 16181082-4 78,690.00 748,535.00 - - 78,690 4,748,535 09/09/16 KAYA Assoc. 0000023703 12,000.00 736,535.00 - - 12,000 4,736,535 Supplemental Agreement (SA) Summary ARAC – Professional Services Agreement Garver $477,260 SA # Vendor Reason Request Updated Contract Amt % Change in Contract 1 Garver Additions to Specifications to meet DoD / FH requirements, Environmental 21,700 498,960 4.6 Study (asbestos, mold, etc.) 2 Garver Add disabled parking design to plans, redesign plans to meet FH Network 7,500 506,460 6.1 Enterprise Center requirements 3 Garver Add full-time resident project representative 62,710 569,170 19.26
  • 12. Schedule Milestone Date Comment Design Complete August 03 On time Construction Documents August 19 On time Bidding Process Advertised August 21 On time Opening September 15 On time Council Approval October 11 Notice of Award October 12 Contracts Executed October 21 Notice to Proceed October 24 Construction October 24 Scheduled for completion Aug 31,2017
  • 13. Summary  ARAC  TACROF  Financial Update  Schedule Update Questions?