SlideShare une entreprise Scribd logo
1  sur  14
Télécharger pour lire hors ligne
!
!
EcoHydraulic,Engineering,Homework,5,
Engineered(Log(Jam(Design(
Coral(West((Feburary(11,(2015(
!
PROBLEM,STATEMENT(
! Opal!Creek!Ancient!Forest!Center!is!facing!lateral!erosion!on!a!steep!stream!
bank!toe.!!It!is!desirable!to!build!an!engineered!log!jam!(ELJ)!structure!to!prevent!
further!lateral!erosion.!!Seven!locally!sourced!Doug!Fir!trees!will!be!used!at!no!cost!
to!build!the!structure.!!The!logs!will!be!an!average!35!feet!in!length!with!root!wads!
intact.!It!is!requested!by!the!property!owner!that!the!bank!be!protected!up!to!the!25!
RYI.!!!
! The!method!for!designing!an!EJL!incorporates!a!factor!of!safety!(FOS)!of!at!
least!2.0!for!all!calculations.!!The!factor!of!safety!in!this!instance!is!high!due!to!the!
unpredictable!and!complex!nature!of!the!structure!and!its!surroundings.!!It!is!
imperative!for!the!owner!to!use!a!high!FOS,!regardless!of!extra!cost.!!Catastrophic!
failure!can!cause!flooding!and!other!high!costs!to!the!owner.!The!buoyancy!FOS!will!
affect!the!size!and!number!of!boulders!used!to!stabilize!the!structure!against!the!
force!of!buoyancy.!!The!sliding!FOS!is!the!determining!factor!for!calculating!the!
effective!obstructed!area!by!the!ELJ.!!The!Froude!number!is!utilized!to!estimate!
scour!depths,!which!are!important!for!creek!fauna!habitat!but!can!also!cause!failure!
in!the!structure.!
! Using!the!ELJ!Calculator!and!Rock!Density!Cost!Spreadsheets!
recommendations!were!provided.!!It!is!recommended!that!there!be!three!base,!two!
stacked,!and!two!top!members!of!the!ELJ.!!There!are!more!logs!as!base!members!are!
recommended!to!keep!more!of!the!structure!in!contact!with!the!bed!in!order!to!
promote!scour!and!pool!formation.!!!
In!order!to!keep!the!structure!stabilized!fourRfoot!boulders!are!suggested!
with!a!total!of!25!boulders!evenly!distributed!throughout!the!structure.!!These!
recommendations!provide!a!buoyancy!FOS!of!2.0!with!a!cost!of!$1,380!for!the!
boulders.!!Utilizing!the!Sliding!FOS!spreadsheet,!the!effective!waterway!area!
obstructed!by!the!EJL!was!calculated!to!get!a!FOS!above!2.0.!!This!area!was!
calculated!to!be!138Rft2.!!!
Last,!the!Froude!number!was!used!to!estimate!scour!depths!caused!by!the!
ELJ.!It!was!calculated!that!for!Froude!numbers!0.3!and!1.2,!the!scour!depths!were!of!
considerable!concern!and!action!should!be!taken!to!decrease!these!values.!!!
!
Example!of!ELJ:!
!
a) Recommendations!for!base,!stacked,!and!top!members!(Buoyancy!FOS!Sheet):!
o Log!Characteristics:!
! Root!Wad!Diameter!=!5’!
! Root!Wad!Length!=!2.5’!
! Proportion!of!Voids!=!20%!
! Stem!Diameter!=!2.8’!
! Average!Length!=!35’!
o I!recommend!3!key!“base”!members,!2!stacked!“middle”!members,!and!2!top!
members.!!The!factor!of!safety!can!be!used!as!a!design!criterion!to!ensure!
that!the!logjam!will!not!float!and!be!sufficient!against!the!force!of!buoyancy.!
More!logs!as!base!members!are!recommended!to!keep!more!of!the!structure!
in!contact!with!the!bed!in!order!to!promote!scour!and!pool!formation.!
b) Boulder!size!and!number!recommendation!(Buoyancy!FOS!Sheet!&!Rock!
Density!Cost!Sheet):!
o I!recommend!boulders!4!feet!in!size.!!According!to!the!table!below,!2!foot!
boulders!would!be!less!expensive,!however,!due!to!the!vast!amount!of!
boulders!needed!to!provide!a!factor!of!safety!of!2!and!the!likelihood!of!
boulders!shifting!due!to!forces!such!as!buoyancy!and!sliding,!one!should!
consider!a!larger!boulder.!!With!the!fourRfoot!boulder,!I!recommend!that!13!
be!submerged!and!12!be!above!water.!!Balancing!the!boulders!throughout!
the!structure!should!create!stability!in!the!case!of!a!flood!or!other!fast!
changes!in!flow.!!
!
!
!
!
!
!
!
!
!
Boulder
Size (ft) Cost ($)
1 $1,372.50
2 $1,345.50
3 $1,398.00
4 $1,382.50
5 $1,402.70
6 $1,492.00
7 $1,481.00
8 $1,768.40
9 $1,888.50
10 $1,727.00
o !
c) !Effective!obstructed!(by!ELJ)!area!recommendation!(Sliding!FOS!Sheet):!
o Simple!estimation!of!effective!waterway!area!obstructed!by!ELJ:!
3 2.8!!" ∗ 35!!" = 295!!"!
!
o This!is!a!rough!estimation,!not!taking!into!effect!unique!root!wad!shape,!
changing!tree!diameter,!and!the!fact!that!some!layers!of!the!logjam!would!be!
perpendicular!against!flow.!!With!this!estimated!area!obstructed,!the!factor!
of!safety!for!sliding!is!1.2.!!
o If!we!were!to!calculate!the!estimated!area!obstructed!with!the!middle!tree!
layer!being!perpendicular!to!flow:!
! Bottom!Layer:!
3(2.8!!") ∗ 2.8!!" = 24!!"!
!
! Middle!Layer:!
2.8!!" ∗ !35!!" = 98!!"!
!
! Top!Layer:!
2(2.8!!") ∗ 2.8!!" = 16!!"!
!
! Total:!138!ft2!
! Factor!of!Safety!=!3.0!
d) Froude!Number!Calculations!and!Scour!Depth:!
o Fr!=!0.3!!
! Scour!Depth!=!19!feet!
o Fr!=!1.2!
! Scour!Depth!29!feet!
o These!scour!depths!are!of!considerable!concern!considering!that!they!are!
both!deeper!than!the!ELJ!is!tall.!!The!Froude!number!is!velocity!over!the!
wave!celerity.!At!values!above!one,!the!flow!is!considered!to!be!supercritical!
with!a!fast!rapid!flow.!!While,!values!below!one!are!considered!to!be!
subcritical!with!a!slower,!tranquil!flow.!Rapid!supercritical!flow!is!going!to!
hug!the!stream!bank!and!create!considerably!more!scour!than!a!slower!flow.!
The!denominator!of!the!Froude!number!has!the!value!of!hydraulic!depth.!!As!
depth!increases,!the!Froude!number!decreases!and!becomes!a!more!
desirable!value.!!If!possible,!I!recommend!considering!constructing!a!ELJ!in!a!
deeper!part!of!the!river!so!scour!will!not!be!such!a!large!issue.!!!
KEY "BASE" MEMBERS
Number of Logs with Rootwads NL = 3
Specific Gravity of Large Wood SL = 0.50 specific gravity
Average Rootwad Diameter DRW = 5 feet Wood Volume = 255 cubic feet per member
Average Rootwad Length LRW = 2.5 feet
Proportion of Voids in Rootwad p = 0.2 decimal %
Tree Stem Average Diameter DTS = 2.8 feet
Tree Stem Average Length LTS = 35 feet FBL = 23,843 pounds
STACKED "MIDDLE" MEMBERS
Number of Logs with Rootwads NL = 2
Specific Gravity of Large Wood SL = 0.50
Average Rootwad Diameter DRW = 5 feet Wood Volume = 255 cubic feet per member
Average Rootwad Length LRW = 2.5 feet
Proportion of Voids in Rootwad p = 0.2 decimal %
Tree Stem Average Diameter DTS = 2.8 feet
Tree Stem Average Length LTS = 35 feet FBL = 15,896 pounds
TOP MEMBERS
Number of Logs with Rootwads NL = 2
Specific Gravity of Large Wood SL = 0.50
Average Rootwad Diameter DRW = 5 feet Wood Volume = 255 cubic feet per member
Average Rootwad Length LRW = 2.5 feet
Proportion of Voids in Rootwad p = 0.2 decimal %
Tree Stem Average Diameter DTS = 2.8 feet
Tree Stem Average Length LTS = 35 feet FBL = 15,896 pounds
BOULDER BALLAST
Specific Gravity of Boulders SS = 2.65
equivalent Diameter of Boulder DB = 4.0 feet
Number of Boulders Submerged NB = 13
Number of Boulders above water level NBU = 12 W' = 3,450 (pounds) effective weight per submerged boulder
W = 5,541 (pounds) weight per boulder
Total Effective Weight for all Boulders = 111,339 pounds
FACTOR OF SAFETY: BUOYANCY
FSB = 2.0
Buoyancy Calculations for Engineered Log Jam
Spreadsheet developed by Scott Wright, P.E. - NRCS Oregon - revision 1.2
Methodology based on a physics approach and information adapted from D'aoust & Millar (2000).
The designer should attain a minimum factor of safety of 2.0 for the ELJ and the ELJ should act as a fully connected structure.
A simplified approach is used to estimate buoyancy where the logs and ballast boulders in the log jam are fully submerged. In addition, the log jam and boulders act as a
composite structure and are assumed fully connected. Water velocity inside the log jam is highly turbulent and near zero, therefore vertical uplift forces are assumed negligible.
A minimum factor of safety against buoyancy should be 1.5 with an ideal F.O.S. greater than 2.0.
LLw
RWRWTSTS
BL NSgp
LDLD
F ⋅−⋅##
$
%
&&
'
(
−⋅+= )1()1(
44
22
ρ
ππ
)1(
6
3
−⋅=# Sw
B
Sg
D
W ρ
π
∑
∑ "+
=
BL
B
F
WW
FS
)(
LLw
RWRWTSTS
BL NSgp
LDLD
F ⋅−⋅##
$
%
&&
'
(
−⋅+= )1()1(
44
22
ρ
ππ
LLw
RWRWTSTS
BL NSgp
LDLD
F ⋅−⋅##
$
%
&&
'
(
−⋅+= )1()1(
44
22
ρ
ππ
Douglas-fir, intermediate
Douglas-fir, intermediate
Douglas-fir, intermediate
Rock Unit Weight 165.0 lb/ft^3
Water Unit Weight 62.4 lb/ft^4
Rock Specific Gravity 2.7
Size (ft) 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0
Volume 0.5 4.2 14.1 33.5 65.4 113.0 179.5 267.9 381.5 523.3
Weight lbs 86.4 690.8 2331.5 5526.4 10793.8 18651.6 29618.1 44211.2 62949.2 86350.0
Weight ton 0.0 0.3 1.2 2.8 5.4 9.3 14.8 22.1 31.5 43.2
Cost/ton 20.0
Cost/rock 0.9 6.9 23.3 55.3 107.9 186.5 296.2 442.1 629.5 863.5
60 3 ft. 1398.9
30 5 ft 3238.1
4637.0
Cross-sectional area from HEC-RAS output, upstream of ELJ A = 1840 sq. ft.
Effective waterway area obstructed by ELJ AELJ = 138 sq. ft.
Drag Coeff. CD = 1.3
Max Stream Velocity at ELJ V = 8.00 fps
Type of streambed sediment Gravel
Ф = 35 degrees
APPARENT DRAG COEFFICIENT
CD
app
= 1.52
FD = 13016 pounds
Friction Factor of Logs on streambed f = 0.70 tangent of internal angle of streambed material
FF = ( W' - FBL - FLB ) f = 39,005 pounds
FSS = 3.0
FACTOR OF SAFETY: SLIDING
Horizontal Drag Force on ELJ
Sliding Calculations for Engineered Log Jams
Ballasted by Boulders
Spreadsheet developed by Scott Wright, P.E. - NRCS Oregon - revision 1.0
Horizontal Streambed Friction Resistance on ELJ
Calculations make several simplifying assumptions including 1) no resistance from burial of ELJ elements, 2) ELJ is
a solid structure, 3) frictional resistance is based on streambed material and normal force, and 4) ELJ is fully submerged.
wELJ
app
DD
V
ACF ρ⋅⋅⋅=
2
2
∑
∑=
DB
F
S
F
F
FS
A
A
Bwhere
B
C
C ELJDapp
D =
−
= 2
)1(
!
!
!
EcoHydraulic,Engineering,
Stable!Channel!Design!
Coral!West!Feburary!19,!2015!
!
PROBLEM,STATEMENT!
The!city!of!Corvallis!is!in!need!of!a!bypass!channel!to!divert!dangerous!
flood!flows!around!the!city.!The!channel!is!going!to!be!on!a!slope!of!0.012.!!
The!median!bed=material!size!is!given!to!be!55mm!(D50)!with!a!Manning’s!n!of!
0.03.!!The!flow!rate!is!known!to!be!35!m3/s.!!
! Two!approaches!were!taken!to!estimate!two!different!channel!
dimensions.!!The!first!approach!utilizes!the!USBR!tractive!force!figure!to!
identify!the!critical!shear!stress!for!the!given!D50!grain!size.!Using!the!shear!
stress!equation,!the!depth!was!found.!!Width!of!the!channel!was!calculated!
using!the!Manning’s!Equation.!!
! The!second!approach!applied!the!Hjulstrom!Diagram!to!identify!the!
velocity!in!order!to!avoid!erosion!and!sedimentation.!!The!velocity!is!then!
used!in!the!Manning’s!Equation!to!find!the!second!channel!dimensions.!!
! The!USBR!tractive!force!figure!yields!a!critical!shear!stress!of!4!kg/m2.!!
The!shear!stress!diagram!yields!a!depth!of!0.3!meters.!!Utilizing!the!Manning’s!
equation!give!a!width!of!12.4!meters.!!The!velocity!with!these!dimensions!is!
about!9.4!m/s.!!According!to!the!Hjulstrom!Diagram,!this!velocity!will!most!
likely!have!erosion!of!particles!from!bed.!!
! Using!the!Hjulstrom!Diagram,!the!optimal!velocity!is!around!3.5!m/s.!!
The!resultant!estimated!diameter!of!the!channel!has!a!width!of!7.2m!and!a!
depth!of!1.4m.!These!results!will!avoid!issues!pertaining!to!erosion!and!
deposition!in!the!bed.!!However,!the!depth!may!have!issues!because!of!the!
high!resulting!shear!stress.!
! Risks!of!erosion!and!deposition!in!a!flood!bypass!are!severe!and!should!
be!avoided.!Both!erosion!and!deposition!can!cause!failure!by!changing!the!
boundary!conditions.!Erosion!can!cause!unraveling!of!the!channel!and!a!
factor!of!safety!should!be!built!into!the!procedure.!!One!possible!way!to!avoid!
erosion!is!to!line!the!channel!with!grass.!!!
! It!is!suggested!that!the!City!of!Corvallis!utilize!the!dimensions!found!
with!the!Hjustrom!Diagram.!!The!channel!should!be!lined!with!a!suitable!
grass!to!prevent!erosion!and!a!factor!of!safety!should!be!utilized!to!ensure!the!
shear!stress!would!not!cause!failure!to!the!channel.!!
Considering!a!rectangular!channel:!
!
!
Critical!Shear!Stress!Approach!
1) Critical!Shear!Stress!for!given!grain!size=!4500!g/m2
!(0.0098N/g)!=!44!N/m2!
!
2) Calculate!y!using!! = !"#,!! =
!
!"
=
(!
!"
!!)(
!.!!
!! )
(!"#$
!
!!)(!.!"#)
= !0.3!!"#"$%!
!
!
a. Where:!
!!(Shear!Stress)!=!4!kg/m2!!
!!(Water!Density)!=!9810!N/m3
!
S!(Slope)!=!0.012!
!
3) Calculate!Width:!!
!
Manning’s!Equation:!
! = !" =!
! ∗ !
!
! ∗ !
!
!
!
!
! ∗ !
!
! =
! ∗ !
!
!
!
= 9.6!
given!values:!
! = 35
!!
!
!
! = 0.012!
! = 0.03!
! = 0.3!!!
!
! = ! ∗ !!
! =
!
!"
=
! ∗ !
! + 2!
!
0.3b ∗ (
0.3!
! + 0.6
)!/!
= 9.6!
∴ b = !12.4!meters!
!
!
Therefore,!according!to!USBR!tractive!force!figure!the!critical!shear!stress!is!!4V
kg/m2
.!!Utilizing!Manning’s!equation!the!resultant!dimensions!of!the!channel!is!
0.3!meters!deep!and!12.4!meters!wide.!!!
!
!
!
!
!
!
!
!
!
!
!
!
!
Critical!Velocity!Approach!
!
4) Critical!Velocity!is!between!2!and!5!m/s!according!to!this!Hjulstrom!Diagram!
(~3.5!m/s).!!
!
5) Calculating!Width!
a. Manning’s!equation!!
! =!
!!
!
!!
!
!
!
!
!!!
!
!
!
!
!
= !! =
3.5 ∗ 0.03
0. 012
!
!
!
!
≅ 1!!
Q = VA!
A =
Q
V
=
35
!!
s
3.5
!
!
= 10!!
!
R =!
!
!"
=
10!!
!"
= 1!
WP = 10m!
!
One!possible!area!of!the!channel!is!a!width!of!7.2!m!and!a!depth!of!1.4!m.!!
!
!
!
EcoHydraulic,Engineering,
Comparing*Discharge*Estimates*
Coral*West*Febuaray*26,*2015*
!
PROBLEM,STATEMENT*
! The!discharge!on!Oak!Creek!needs!to!be!established!for!management!
purposes.!!Three!techniques!will!be!used!to!find!the!most!reliable!value!in!cubic!feet!
per!second!(cfs).!!The!first!technique!is!directly!measuring!velocity!using!a!current!
meter.!!This!method!is!commonly!used!within!the!USGS!and!will!provide!data!for!the!
second!technique,!which!is!using!an!empirical!formula!known!as!Manning’s!
Equation.!!The!third!technique!utilizes!rating!curves!established!over!30!years!of!
recorded!stage!measurements.!!!
! Using!a!Price!AA!meter!is!a!tool!to!find!current!data!on!a!river.!!The!process!
involves!going!out!to!the!river,!and!collecting!data!in!small!sections.!!The!data!is!then!
manipulated!to!find!total!discharge.!!The!area!collected!from!the!field!is!then!used!to!
find!the!wetted!perimeter.!!The!wetted!perimeter,!slope,!and!Manning’s!n!of!the!
river!is!then!used!to!calculate!discharge!with!Manning’s!Equation.!!Data!from!rating!
curve!is!established!over!time!to!record!a!relationship!between!stage!and!
corresponding!discharge!in!the!river.!!
!
! The!results!from!the!three!techniques!are!listed!in!the!table:!
Technique*
Discharge*
(cfs)*
Price*AA*
meter* 20*
Manning's*
Equation* 20*
Rating*
Curves* 18*
Mean* 19.33333333*
Standard*
Deviation* 1.15*
!
! The!Price!AA!meter!and!Manning’s!Equation!seem!to!be!the!most!reliable!
methods.!!They!are!empirical!and!based!on!current!data!of!the!stream.!!I!believe!that!
the!rating!curve!method!is!the!least!reliable!because!the!stageNdischarge!
relationship!could!change!over!time!due!to!erosion!and!deposition!of!sediment.!!
!
!
!
point*
distance*
from*left*
edge*of*
water*(ft)*
Depth*from*
water*
surface*(ft)*
Area*(ft2
)*
C*(number*
of*clicks*per*
60*seconds)*
Velocity*(ft/s)*
discharge*
(ft3
/s)*
1* 9.2* 1.2* 1.44* 4* 0.164786667* 0.2372928*
2* 10.4* 1.3* 1.56* 9* 0.34852* 0.5436912*
3* 11.6* 1.3* 1.56* 5* 0.201533333* 0.314392*
4* 12.8* 1.4* 1.68* 18* 0.67924* 1.1411232*
5* 14* 1.7* 2.04* 52* 1.928626667* 3.9343984*
6* 15.2* 1.7* 2.04* 54* 2.00212* 4.0843248*
7* 16.4* 2* 2.4* 50* 1.855133333* 4.45232*
8* 17.6* 2.1* 2.52* 33* 1.23044* 3.1007088*
9* 18.6* 2.3* 2.3* 26* 0.973213333* 2.238390667*
10* 20.5* 0.3* 0.57* 0* 0.0178* 0.010146*
* * * * *
Total*
Discharge* 20.05678787*
!
*Areas!shaded!in!grey!are!calculated,!all!other!values!are!measured.!
!
!
XNaxis!is!depth!in!feet!
!
Example!Calculations:!
!
Area:!
! = !"#$%&'(!!"#$!!"#$!!"#!!!"!!"#$% ∗ !!"#ℎ!!"#$!!"#$%!!"#$%&'!
!! = 10.4 − 9.2 !" ∗ 1.2!" = 1.44!"!
!
!
Velocity:!
! = 2.2048 ∗ !"#$%&!!"!!"#!$%!!"#!!"#$%& + 0.0178!
0!
0.5!
1!
1.5!
2!
2.5!
distance!
from!left!
edge!of!
water!(ft)! 9.2! 10.4! 11.6! 12.8! 14! 15.2! 16.4! 17.6! 18.6! 20.5!
River&Cross&Section&
!! = 2.2048 ∗
9
60
+ 0.0178 = 0.35
!"
!
!
Discharge:!
! = !"#$ ∗ !"#$%&'(!
!! = 1.44!"!
∗ 0.43852
!"
!
= 0.54
!"!
!
!!
Manning’s!Equation!
!
!
!
!
!
Average*
Depth*(ft)* 1.53*
Width*(ft)* 20.5*
Total*Area*
(ft)* 18.11*
P*(ft)* 23.56*
S* 0.001*
n* 0.035*
R*(ft)* 0.77*
Q*(ft^3/s)* 20.5*
!
Rating!Curves!
!
o For!Z>0.85’:!!Q(cfs)!=4.2902(Z^!1.6965)!
o For!Z<0.85’:!!Q(cfs)!=7.1228(Z^1.7513)!
Using!the!deepest!part!of!the!channel,!Z!=!1.7!ft!
!
! !"# = !4.2902 2.3!"!.!"!#
= 18.37
!"!
!
!
!

Contenu connexe

En vedette

Administrar. configuración
Administrar. configuraciónAdministrar. configuración
Administrar. configuraciónEmagister
 
Campaña publicidad para Manhattan Beauty Salon & Spa, Universidad Dr. José Ma...
Campaña publicidad para Manhattan Beauty Salon & Spa, Universidad Dr. José Ma...Campaña publicidad para Manhattan Beauty Salon & Spa, Universidad Dr. José Ma...
Campaña publicidad para Manhattan Beauty Salon & Spa, Universidad Dr. José Ma...Wiliam Alexander Hernández
 
Plan de Marketing DIgital para un centro de estética y adelgazamiento
Plan de Marketing DIgital para un centro de estética y adelgazamientoPlan de Marketing DIgital para un centro de estética y adelgazamiento
Plan de Marketing DIgital para un centro de estética y adelgazamientoRafael Trucios Maza
 
Proyecto de marketing online para un SPA
Proyecto de marketing online para un SPAProyecto de marketing online para un SPA
Proyecto de marketing online para un SPARafael Trucios Maza
 

En vedette (9)

Administrar. configuración
Administrar. configuraciónAdministrar. configuración
Administrar. configuración
 
Proyecto cosmeticos
Proyecto cosmeticosProyecto cosmeticos
Proyecto cosmeticos
 
Práctica #6
Práctica #6Práctica #6
Práctica #6
 
Campaña publicidad para Manhattan Beauty Salon & Spa, Universidad Dr. José Ma...
Campaña publicidad para Manhattan Beauty Salon & Spa, Universidad Dr. José Ma...Campaña publicidad para Manhattan Beauty Salon & Spa, Universidad Dr. José Ma...
Campaña publicidad para Manhattan Beauty Salon & Spa, Universidad Dr. José Ma...
 
Plan de marketing online - IPAE
Plan de marketing online - IPAEPlan de marketing online - IPAE
Plan de marketing online - IPAE
 
Plan de Marketing DIgital para un centro de estética y adelgazamiento
Plan de Marketing DIgital para un centro de estética y adelgazamientoPlan de Marketing DIgital para un centro de estética y adelgazamiento
Plan de Marketing DIgital para un centro de estética y adelgazamiento
 
Household wiring
Household wiringHousehold wiring
Household wiring
 
Proyecto de marketing online para un SPA
Proyecto de marketing online para un SPAProyecto de marketing online para un SPA
Proyecto de marketing online para un SPA
 
Beena
BeenaBeena
Beena
 

Similaire à BEE 312 Portfolio Final

Strengthening metallic shells with frp against buckling cice2008
Strengthening metallic shells with frp against buckling cice2008Strengthening metallic shells with frp against buckling cice2008
Strengthening metallic shells with frp against buckling cice2008Yara Mouna
 
formation evaluation for reservoir engineering
formation evaluation for reservoir engineeringformation evaluation for reservoir engineering
formation evaluation for reservoir engineeringmohammedsaaed1
 
Hydrogeological assessment of two important wetlands (GDEs) in Hodgson's Wetl...
Hydrogeological assessment of two important wetlands (GDEs) in Hodgson's Wetl...Hydrogeological assessment of two important wetlands (GDEs) in Hodgson's Wetl...
Hydrogeological assessment of two important wetlands (GDEs) in Hodgson's Wetl...getnathans
 
WS-D1-CEWRE_PPT.pdf
WS-D1-CEWRE_PPT.pdfWS-D1-CEWRE_PPT.pdf
WS-D1-CEWRE_PPT.pdfssuserca460e
 
Design and Construction of Jetties
Design and Construction of JettiesDesign and Construction of Jetties
Design and Construction of JettiesLeopoldo Pineda
 
ÖNCEL AKADEMİ: SOLID EARTH GEOPHYSICS
ÖNCEL AKADEMİ: SOLID EARTH GEOPHYSICSÖNCEL AKADEMİ: SOLID EARTH GEOPHYSICS
ÖNCEL AKADEMİ: SOLID EARTH GEOPHYSICSAli Osman Öncel
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)theijes
 
The International Journal of Engineering and Science (The IJES)
 The International Journal of Engineering and Science (The IJES) The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)theijes
 
F021203036039
F021203036039F021203036039
F021203036039theijes
 
Spatial distribution and environmental geochemistry of zinc metal in water an...
Spatial distribution and environmental geochemistry of zinc metal in water an...Spatial distribution and environmental geochemistry of zinc metal in water an...
Spatial distribution and environmental geochemistry of zinc metal in water an...Javier Quesada Duque
 
Electrical resistivity sounding for subsurface delineation and evaluation of ...
Electrical resistivity sounding for subsurface delineation and evaluation of ...Electrical resistivity sounding for subsurface delineation and evaluation of ...
Electrical resistivity sounding for subsurface delineation and evaluation of ...Alexander Decker
 
Barnett et al. 2017 ESR
Barnett et al. 2017 ESRBarnett et al. 2017 ESR
Barnett et al. 2017 ESRTom Newton
 
K0364062067
K0364062067K0364062067
K0364062067theijes
 
The Road to Saqqara ( Jack-up units and Move )
The Road to Saqqara ( Jack-up units and Move )The Road to Saqqara ( Jack-up units and Move )
The Road to Saqqara ( Jack-up units and Move )Kamel Elsayed
 

Similaire à BEE 312 Portfolio Final (20)

Strengthening metallic shells with frp against buckling cice2008
Strengthening metallic shells with frp against buckling cice2008Strengthening metallic shells with frp against buckling cice2008
Strengthening metallic shells with frp against buckling cice2008
 
formation evaluation for reservoir engineering
formation evaluation for reservoir engineeringformation evaluation for reservoir engineering
formation evaluation for reservoir engineering
 
Hydrogeological assessment of two important wetlands (GDEs) in Hodgson's Wetl...
Hydrogeological assessment of two important wetlands (GDEs) in Hodgson's Wetl...Hydrogeological assessment of two important wetlands (GDEs) in Hodgson's Wetl...
Hydrogeological assessment of two important wetlands (GDEs) in Hodgson's Wetl...
 
LGM_Mixing.pdf
LGM_Mixing.pdfLGM_Mixing.pdf
LGM_Mixing.pdf
 
WS-D1-CEWRE_PPT.pdf
WS-D1-CEWRE_PPT.pdfWS-D1-CEWRE_PPT.pdf
WS-D1-CEWRE_PPT.pdf
 
Design and Construction of Jetties
Design and Construction of JettiesDesign and Construction of Jetties
Design and Construction of Jetties
 
ÖNCEL AKADEMİ: SOLID EARTH GEOPHYSICS
ÖNCEL AKADEMİ: SOLID EARTH GEOPHYSICSÖNCEL AKADEMİ: SOLID EARTH GEOPHYSICS
ÖNCEL AKADEMİ: SOLID EARTH GEOPHYSICS
 
Tidal
TidalTidal
Tidal
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
 
The International Journal of Engineering and Science (The IJES)
 The International Journal of Engineering and Science (The IJES) The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
 
F021203036039
F021203036039F021203036039
F021203036039
 
Spatial distribution and environmental geochemistry of zinc metal in water an...
Spatial distribution and environmental geochemistry of zinc metal in water an...Spatial distribution and environmental geochemistry of zinc metal in water an...
Spatial distribution and environmental geochemistry of zinc metal in water an...
 
Electrical resistivity sounding for subsurface delineation and evaluation of ...
Electrical resistivity sounding for subsurface delineation and evaluation of ...Electrical resistivity sounding for subsurface delineation and evaluation of ...
Electrical resistivity sounding for subsurface delineation and evaluation of ...
 
Spawning stock and recruitment relationship in North Sea cod shaped by food a...
Spawning stock and recruitment relationship in North Sea cod shaped by food a...Spawning stock and recruitment relationship in North Sea cod shaped by food a...
Spawning stock and recruitment relationship in North Sea cod shaped by food a...
 
formation evaluation
formation evaluationformation evaluation
formation evaluation
 
September 1 - 0130 - Johnathan Witter
September 1 - 0130 - Johnathan WitterSeptember 1 - 0130 - Johnathan Witter
September 1 - 0130 - Johnathan Witter
 
Barnett et al. 2017 ESR
Barnett et al. 2017 ESRBarnett et al. 2017 ESR
Barnett et al. 2017 ESR
 
K0364062067
K0364062067K0364062067
K0364062067
 
The Road to Saqqara ( Jack-up units and Move )
The Road to Saqqara ( Jack-up units and Move )The Road to Saqqara ( Jack-up units and Move )
The Road to Saqqara ( Jack-up units and Move )
 
Aoc sediment update_part2
Aoc sediment update_part2Aoc sediment update_part2
Aoc sediment update_part2
 

BEE 312 Portfolio Final