SlideShare une entreprise Scribd logo
1  sur  24
Télécharger pour lire hors ligne
The Iranian Nuclear Program
       Timelines, Data, and Estimates




                                Maseh Zarif
                     Deputy Director and Iran Team Lead
                         AEI Critical Threats Project
                                      Version 5.0
                                    NOVEMBER 2012
   Current as of NOV 21 2012 using data from IAEA report dated NOV 16 2012


                                www.criticalthreats.org
                        Copyright © 2012 by the AEI Critical Threats Project
November 2012 International Atomic Energy Agency (IAEA) Findings
Additional Centrifuge Installation
        Iran increased its enrichment capacity by installing additional centrifuges at its declared sites between
        August and November 2012. The hardened Fordow facility is now at maximum capacity (2,784
        centrifuges). Of the 2,784, 696 centrifuges are currently enriching at Fordow and 696 are ready to
        begin enriching immediately. The IAEA also noted the addition of first-generation and advanced
        centrifuges, the latter undergoing testing, at the Natanz facility.
Increasing Enriched Uranium Stockpiles
        Iran continues to produce low- (<5%) and medium-enriched (near 20%) uranium at historically high
        rates. It has now allocated roughly 40% of its medium-enriched uranium for conversion to reactor fuel
        plates; only a small fraction of the allocated material, however, has been packaged into fuel plates
        and placed into a reactor core as of August 2012.
Parchin Facility Inspection
        Iran continues to deny the IAEA access to the Parchin facility, where the agency believes Iran
        conducted experiments related to nuclear weapons development. The IAEA noted that, even if it is
        given access to the site, its ability to “conduct effective verification will have been seriously
        undermined” by physical disruption and sanitization undertaken by Iran at the facility in 2012.
Weaponization
        Iran continues to stonewall the IAEA regarding its weaponization activities. The agency reiterated its
        assessment of Iran’s work on nuclear weapons development: “the information indicates that, prior to
        the end of 2003 the activities took place under a structured program; that some continued after 2003;
        and that some may still be ongoing.”
Arak Reactor Timeline
        Iran told the IAEA that it will begin operating the Arak heavy water reactor later than previously
        planned. The reactor, now scheduled for an early 2014 launch, will provide Iran with a separate
        pathway to acquiring fissile material for nuclear weapons in the form of weapons-grade plutonium.

                                                                                                              Page 2
Status of Near-20% Enriched Uranium
Iran has enough near-20% enriched uranium with which to produce weapons-grade
uranium (WGU) for one warhead. Some of this material is currently stored in oxide
powder form, which can be converted back into a gas for weapons-grade enrichment.
                                                                  NEAR-20% ENRICHED URANIUM
                             141 kg needed to produce one warhead’s worth of WGU
                             156 kg produced as of November 2012 IAEA report (see pie chart for breakdown)
                             151.5 kg available in gas or oxide powder form (allocated for use in fuel plates for Tehran Research Reactor)

                                           3.4 kg                                                                        1.1 kg
                                 Converted into U3O8 fuel                                                        Enriched down to <4%
                                 plates and placed into or
                                 irradiated in reactor core
                                    (as of August 2012)



                      52 kg
                                                                                                                                                99.5 kg
               Fed into process for
                                                                                                                                          Stored as enriched
               conversion to U3O8
                                                                                                                                             uranium gas
               (available for WGU
                                                                                                                                       (available now for WGU
               production after re-
                                                                                                                                              production)
             conversion to gas form)*


                                                                                                                  Total near-20% enriched
                                                                                                                  uranium produced: 156 kg
*Methods for converting near-20% material in U3O8 form back into a gas “are standard processes in the nuclear industry and Iran uses them as part of its
uranium ore processing.”1 The conversion can be done using specialized facilities and can be accomplished in “days to weeks.”2 The near-20% LEU can
only be classified as unusable in a breakout once the fuel assemblies containing the U3O8 are inserted and irradiated in a reactor core. Only a small
fraction of Iran’s near-20% LEU in the form of U3O8 has been manufactured into fuel assemblies and placed into or irradiated in a reactor core (3.4 kg).

1) Gregory Jones, “Fueling the Tehran Research Reactor: Technical Considerations on the Risks and Benefits,” NPEC, October 12, 2009.
                                                                                                                                                                Page 3
2) Ibid.
Key Points
           IRAN’S ENRICHMENT CAPABILITIES ARE NO LONGER
      THE PRIMARY BOTTLENECK IN A NUCLEAR BREAKOUT SCENARIO

Iran can produce one bomb’s worth of fissile material faster than it likely can deploy a
functioning nuclear device. Tracking Iran’s uranium enrichment activities now addresses only
Iran’s intentions and the size of its projected arsenal.
    Obtaining fissile material in the form of weapons-grade uranium or plutonium is the most
    technically demanding step in acquiring a nuclear weapons capability. Designing an explosive
    device (consisting of non-nuclear components) and a delivery system for the device are
    comparatively less technically challenging. Those efforts can also proceed parallel to
    enrichment.

    Iran has the infrastructure and material to produce weapons-grade uranium. It has enough
    enriched uranium to produce fuel for six nuclear weapons after conversion to weapons-grade
    levels. Its expanding enrichment activities have significantly reduced the time required for it
    to produce weapons-grade uranium. The key accelerants for this shrinking timeline have
    been its growing stockpiles of low- and medium-enriched uranium, which is 90% of the way
    to weapons-grade uranium, and an increasing number of centrifuges enriching.



                                                                                                      Page 4
                                       Copyright © 2012 by the AEI Critical Threats Project
Nuclear Program Expansion
Iran will likely have enough near-20% enriched uranium to rapidly produce fissile
material for 2 nuclear weapons by late 2013 or early 2014.
Iran has installed many more centrifuges at the hardened Fordow facility than are now
actually spinning, providing a reserve and/or surge capacity that will be difficult for
Israel to destroy.
The installation of 2,088 additional centrifuges at Fordow since summer 2012 gives Iran
the ability to:

    produce near-weapons grade uranium (20% enrichment level) in larger quantities
    faster, providing rapidly-convertible feedstock for a small arsenal of nuclear
    weapons;

    convert near-weapons grade uranium into nuclear weapons fuel in a shorter
    amount of time.
Iran’s uranium enrichment is at historically high rates despite increasing sanctions and
damage to the Iranian economy.
Iran told the International Atomic Energy Agency (IAEA) that it plans to begin operating
the Arak heavy water reactor in early 2014 (it had previously planned commencement
for mid-to-late 2013). This reactor will be capable of producing two warheads’ worth of
weapons-grade plutonium per year once operational.

                                                                                           Page 5
Breakout Timelines
Time needed to produce fuel for 1 nuclear weapon:
   Iran needs 3.6 months to produce 25 kg of weapons-grade uranium and 1.9 months to
   produce weapons-grade uranium at the buried Fordow and pilot Natanz enrichment
   facilities.* It can cut these times significantly using the centrifuges installed but not
   yet operating at the Fordow facility.
   Iran needs 4-10.5 weeks to produce 25 kg of weapons-grade uranium and 1.5-5 weeks
   to produce 15 kg of weapons-grade uranium at the main Natanz enrichment facility.*
   The higher end of the range accounts for a three-step conversion process.
Estimates of the time Iran needs to build a nuclear device to use this fissile material are
generally longer than the timelines above.
The existence of undeclared (covert) enrichment sites would have a significant impact
on breakout estimates.
Evidence of significant Iranian enrichment beyond 20% will strongly suggest not only
that the decision to weaponize has been made, but also that the Iranians believe they
have (or will shortly have) a viable warhead.


*All enriched uranium figures are given in terms of solid uranium (where 1 kg uranium hexafluoride is equal to ~0.67 kg
elemental uranium). Estimates assume Natanz and Fordow are used with the operational capacity reflected in the November
2012 IAEA report. Iran may need 15-25 kg of weapons-grade uranium for an implosion-type bomb design depending on its
level of technical ability (high technical ability would require less material). See pages 18, 19, and 22 for further detail. Page 6
Iran has outfitted the hardened Fordow enrichment facility with 2,784 IR-1
centrifuges. This expansion gives Iran the capacity to produce near-20%
enriched uranium at a faster rate and the means to convert that stockpile
to weapons-grade uranium (WGU) more rapidly in a deeply buried site.


                             Time needed to produce WGU                                         Time needed to produce near-
                             for 1 warhead from near-20%                                          20% enriched uranium feed
                              enriched uranium at Fordow                                        for WGU for second warhead*

 Using 696 centrifuges
  currently enriching           4.7 MONTHS                                                        14 MONTHS
     Using 1,392
 centrifuges currently
 enriching and under            2.4 MONTHS                                                        8.6 MONTHS
        vacuum




    Using all 2,784
 centrifuges available
                                1.2 MONTHS                                                        4.7 MONTHS
*Assumes constant production of near-20% enriched uranium at smaller pilot facility at Natanz                                  Page 7
Iran’s Declared 3.5% Enriched Uranium Production at Natanz
 Assessment: Stuxnet derailed the 2009 Iranian effort to expand enrichment capability for roughly one year, but the enrichment expansion effort
 recovered in mid-2010. Neither direct actions nor sanctions have had a visible effect on the enrichment program. Even the Stuxnet success does not
 appear to have derailed the steady growth of the enriched uranium stockpile. Iran is running its highest number of centrifuges and production rates
 since the enrichment program began. It has produced enough enriched uranium since 2009 to fuel a small arsenal of nuclear weapons after
 conversion to weapons grade.

                                                                                                                      New U.S./                                                       Iranian
     Centrifuges                        Centrifuges                 3.5% LEU                                                                       Stuxnet                           Scientist
                                                                                                                       UN/EU
     enriching                          not                         produced                                                                      Launched                             Killed
                                                                                                                      sanctions
                                        enriching


                       10000                                                                                                                                                                     6000


                       9000

                                                                                                                                                                                                 5000
                       8000


                       7000
                                                                                                                                                                                                 4000

                       6000




                                                                                                                                                                                                        Kilograms LEU
       # centrifuges




                       5000                                                                                                                                                                      3000


                       4000

                                                                                                                                                                                                 2000
                       3000


                       2000
                                                                                                                                                                                                 1000

                       1000


                          0                                                                                                                                                                      0
                               Jan-09    Apr-09   Jul-09   Oct-09    Jan-10    Apr-10     Jul-10     Oct-10       Jan-11      Apr-11    Jul-11   Oct-11   Jan-12   Apr-12   Jul-12     Oct-12



Enrichment data source: IAEA                                                                                                                                                                         Page 8
                                                                                 Copyright © 2012 by the AEI Critical Threats Project
Near-20% Enriched Uranium Production and Projected Growth at Fordow/Natanz

                                                                                                                                          Amount needed for:
                   705
                                                                    ~20% enriched uranium
                                                                    production enough to produce
                                                                    WGU for three nuclear bombs by                                                       4
                   564                                                                                                                                weapons
                            Iran will have produced 282 kg          late 2013/early 2014. Iran would
                            ~20% enriched uranium by late           need to begin enriching gradually
Kilograms 19.75% LEU




                            2013/early 2014 under steady-state      in installed Fordow cascades to                                                      3
                   423
                            conditions--enough to produce           meet this threshold.                                                              weapons
                            WGU for two nuclear bombs
                   282      designed with a low level of                                                                                                 2
                            technical capability.                                                                                                     weapons


                   141                                                                                                                                      1
                                                                                                                                                          weapon
                                                                       156 kg
                                                                 (as of NOV 2012)
                       0
                       May-12         Jul-12         Oct-12             Jan-13                      May-13                  Jul-13   Oct-13      Jan-14


BLACK: Reported production
RED: Steady-state enrichment (a)
GREEN: Gradual enrichment expansion in available centrifuges at Fordow (b)
PURPLE: Rapid enrichment expansion at Fordow (c)
*The two lines for each colored scenario represent a range based on different calculations of demonstrated centrifuge efficiency.

(a) 1,024 centrifuges currently enriching (2 cascades with 328 total IR-1 centrifuges at PFEP and 4 cascades with 696 total IR-1 centrifuges at Fordow)
(b) Same as (a) but Iran begins turning on 2 additional cascades at Fordow every three months in DEC.
(c) Iran begins enriching in the 4 additional cascades under vacuum at Fordow in DEC. It will begin enriching in the 8 remaining cascades in JAN 2013.
                                                                                                                                                      Page 9
                                                                     Copyright © 2012 by the AEI Critical Threats Project
Key Upcoming Events
                                                                                                                        12/15/2013
                                                                                                     Approx. date by which Iran—at current rates—will
                                                                                                       produce enough near-20% enriched uranium
                                                                                                         to convert to WGU for a second warhead

                1/22/2013 - 2/12/2013              4/23/2013 - 5/14/2013                          7/30/2013 - 8/20/2013
              IAEA Inspection Window              IAEA Inspection Window                         IAEA Inspection Window




  12/1/2012   1/1/2013   2/1/2013   3/1/2013    4/1/2013   5/1/2013      6/1/2013         7/1/2013         8/1/2013   9/1/2013   10/1/2013   11/1/2013 12/1/2013      1/1/2014




                                                                                                                                                  Italicized dates are estimates;
                                                                                                                                                  bold dates are fixed
                                                                                                                                                  Listed inspection windows are
                                                                                                                                                  approximate. The IAEA may be
11/29/2012                          3/4/2013                            6/3/2013                                       9/9/2013                   conducting inspections outside
                                                                                                                                                  of these windows.
IAEA BOG                            IAEA BOG                           IAEA BOG                                       IAEA BOG
  meets                               meets                              meets                                          meets



          2/22/2013                             5/24/2013                                    8/30/2013
         IAEA Report                           IAEA Report                                  IAEA Report

  IAEA BOG = International Atomic
  Energy Agency Board of Governors
                                                                                                                                                                       Page 10
                                                              Copyright © 2012 by the AEI Critical Threats Project
Making an Atomic Bomb (Concept)
                               Acquire Weapons-grade                                                 Parallel processes          Design      Parallel processes   Acquire delivery
                                      Uranium                                                                                   warhead                               vehicle

                                                Centrifuge                                                                     Acquire weapon
                                                 cascade                                                                           design
   LEU gas                      Fed back into                produces                                  UF6 gas                                                             Shahab-3
(3.5% U-235)                                                                                        19.75% U-235                                                            missile




                                                                                    Fed back into
                   produces




                                                                                                                               Develop detonator
                                                                                                                                  technology
  Centrifuge                                                                                          Centrifuge
   cascade
                                        Two-step                                                       cascade
                                                                                                                                  Test design
                                        uranium
                 Fed through




                                                                                      produces
                                                                                                                                and engineering

                                       enrichment




                                                                                                                                      then
   UF6 gas                               process                                                      UF6 gas
 0.7% U-235                                                                                          90% U-235
                                                                                                                               Build weapon
                Converted to




                                                                                   Processed
                                                                                      into




                                                                                                                                Test weapon                  Mate warhead with
                                                                                                                                                               delivery vehicle
          Natural uranium                                              High-enriched
                                                                    elemental uranium
                                                                                                                                                             (Process complete)
                                                                  solid metal (90% U-235)
                                                                                                                                                                                Page 11
                                                                        Copyright © 2012 by the AEI Critical Threats Project
Making an Atomic Bomb (Status as of NOV 2012)




                                                          ay




                                                                                                                                          ay
                                                       w
                                 Acquire Weapons-grade                                                                             Design                            Acquire delivery




                                                                                                                                       w




                                                                                                                                                                          ne
                                                                                                       Parallel processes                       Parallel processes




                                                r




                                                                                                                                 r
                                             de
                                                                                                                                  warhead                                vehicle




                                                                                                                              de
                                        Uranium




                                                                                                                                                                        Do
                                           Un




                                                                                                                            Un
                                                  Centrifuge                                                                     Acquire weapon
                                                   cascade                                                                           design




                                                                                                ay
                                                                                                                                                                              Shahab-3




                                                                                    w
              ne




                                                                                                                                     ne




                                                                                                                                                                            ne
    LEU gas                       Fed back into                produces                                  UF6 gas




                                                                         r
 (3.5% U-235)                                                                                         19.75% U-235                                                             missile
            Do




                                                                                                                                   Do
                                                                      de




                                                                                                                                                                          Do
                                                                    Un
                                                                                      Fed back into
                     produces




                                    NB: All estimates of Iran’s                                                                  Develop detonator




                                                                                                                                               ay
                                    nuclear status and                                                                              technology




                                                                                                                                          w
   Centrifuge                       capabilities assume that                                            Centrifuge




                                                                                                                                      r
                                    there are no clandestine




                                                                                                                                   de
    cascade                                                                                              cascade
                                    facilities, and that the




                                                                                                                                 Un
                                    IAEA has full access to all                                                                     Test design
                   Fed through




                                                                                        produces
                                    declared facilities. The                                                                      and engineering
                                    first assumption is
                                    impossible to verify. The
                                                                                                      d




                                                                                                                                        then
                                                                                        te
                                    second assumption is
                                                                                     or
                  ne




    UF6 gas                         known to be false.                                                  UF6 gas
                                                                                   ep


  0.7% U-235
                Do




                                                                                                       90% U-235
                                                                             tr




                                                                                                                                 Build weapon




                                                                                                                                               d
                                                                                                                                            te
                                                                           No




                                                                                                                                         or
                  Converted to




                                                                                     Processed




                                                                                                                                       ep
                                                                                        into




                                                                                                                                    tr
                                                                                                                                  No                            Mate warhead with




                                                                                                                                                                               g
              ne




                                                                                                                                  Test weapon




                                                                                                                                                                             in
                                                                                                                                           g
                                                                                                      d




                                                                                                                                         in
            Do




                                                                                        te




                                                                                                                                                                  delivery vehicle




                                                                                                                                                                          ar
                                                                                     or




           Natural uranium                                                                                                            ar




                                                                                                                                                                        ep
                                                                                   ep




                                                                         High-enriched
                                                                                                                                                                (Process complete)
                                                                                                                                    ep




                                                                                                                                                                      Pr
                                                                             tr




                                                                      elemental uranium
                                                                                                                                  Pr
                                                                           No




                                                                    solid metal (90% U-235)
                                                                                                                                                                                    Page 12
                                                                          Copyright © 2012 by the AEI Critical Threats Project
Why Enrichment Accelerates at Higher Concentration of U-235

                                                         Centrifuge
   1,373 kg                                               cascade
                                                                                                               116 kg
      LEU gas                            Fed back into                 produces                                 UF6 gas
   (3.5% U-235)                                                                                              19.75% U-235
                                                         559 SWU                                                              The work and time required to




                                                                                             Fed back into
                                                          37 days                                                             enrich uranium from its natural
                             produces




                                                                                                                              concentration (0.7%) to 3.5%
      Centrifuge                         5,060 SWU                    115 SWU                                  Centrifuge
                                                                                                                              LEU is an order of magnitude
       cascade                            331 days                     8 days                                   cascade       greater than that required to
                                                                                                                              enrich 20% LEU to weapons-
                           Fed through




                                                                                               produces
                                                                                                                              grade concentrations (~90% U-
                                                                                                                              235).
   14,187 kg                                                                                                   15 kg          That is because centrifuges
       UF6 gas                                                                                                 UF6 gas
     0.7% U-235                                                                                               90% U-235
                                                                                                                              must spin more than 14,000 kg
                                                                                                                              of uranium ore to produce
                                                                                             Processed
                          Converted to




                                                                                                                              1,373 kg of 3.5% LEU, but only
                                                                                                into




                                                                                                                              116 kg of 20% LEU to produce
                                                                                                                              15 kg of weapons-grade
                                                                                                                              uranium.
                 Natural uranium
                                                                                   High-enriched
                                                                                elemental uranium
SWU = Separative work unit, a measure of the amount of effort
                                                                              solid metal (90% U-235)
required to process nuclear material. The SWU requirement is
used to determine the time needed to enrich uranium with a given
number of centrifuges operating at a given efficiency.                                                                                                   Page 13
                                                                       Copyright © 2012 by the AEI Critical Threats Project
Iran’s Declared Uranium Enrichment Facilities

Fordow Fuel Enrichment Plant (FFEP)
As of NOV 10 2012:
    696 IR-1 centrifuges producing near-
    20% LEU
    696 IR-1 centrifuges under vacuum and
    1392 IR-1 centrifuges not enriching
    Facility producing near-20% low-
    enriched uranium (LEU)
    464.3 kg 3.5% LEU converted to 64 kg
    near-20% LEU
    225 kg 3.5% LEU remaining from
    Natanz stockpile sent here*



Notes
* Calculated estimated based on




                                                                      145
amount IAEA reported has been
transferred from Natanz to Fordow



                                                                          km
                                                                                                           Natanz Fuel Enrichment Plant (FEP)
                                                                                                           As of NOV 2012:
                                                                                                               9156 IR-1 centrifuges producing <5%
                                                                                                               LEU
                                                                                                               1258 additional IR-1 centrifuges not
                                                                                                               enriching
                                                                                                               Facility producing 3.5% enriched LEU
                                    Pilot Fuel Enrichment Plant (PFEP)                                         4992 kg 3.5% LEU produced here
                                    As of NOV 2012:
                                        328 IR-1 centrifuges producing near-
                                        20% LEU
                                        176 IR-2m and 176 IR-4 centrifuges
                                        installed and intermittently fed
                                        Facility producing near-20% LEU
                                        788.6 kg 3.5% LEU converted to 92 kg                                                                              `
                                        near-20% LEU
                                        Unknown kg 3.5% LEU stored here
                                                                                                                                                      Page 14
                                                    Copyright © 2012 by the AEI Critical Threats Project
Natanz Enrichment Facilities

Pilot Fuel Enrichment Plant (PFEP)
As of NOV 2012:
    328 IR-1 centrifuges producing near-
    20% LEU                                                                                            Natanz Fuel Enrichment Plant (FEP)
    176 IR-2m and 176 IR-4 centrifuges                                                                 As of NOV 2012:
    installed and intermittently fed                                                                       9156 IR-1 centrifuges producing <5%
    Facility producing near-20% LEU                                                                        LEU
    788.6 kg 3.5% LEU converted to 92 kg                                                                   1258 additional IR-1 centrifuges not
    near-20% LEU                                                                                           enriching
    Unknown kg 3.5% LEU stored here                                                                        Facility producing 3.5% enriched LEU
                                                                                                           4992 kg 3.5% LEU produced here




                                                                                                       Underground halls under construction FEB 2003




                                                                                                                                                       Page 15
                                                Copyright © 2012 by the AEI Critical Threats Project
Fordow Enrichment Facility: Status and Construction
                    Image taken SEP 14 2012                                                      Image from MAR 24 2005 (Google Earth)




Pleiades, Apollo Mapping
                                                                                            Areas covered in 2005 appear as entrances to
                                                                                                                                           New above-
        Fordow Fuel Enrichment Plant (FFEP)                                                        underground facilities in 2009
                                                                                                                                             ground
        As of NOV 10 2012:                                                                                                                    facility
            696 IR-1 centrifuges producing near-                                                                                             appears
            20% LEU                                                                                                                         between
            696 IR-1 centrifuges under vacuum and                                                                                           2005 and
            1392 IR-1 centrifuges not enriching                                                                                                2009
            Facility producing near-20% low-
            enriched uranium (LEU)
                                                                             Ridgeline rises
            464.3 kg 3.5% LEU converted to 64 kg                           roughly 200 feet
            near-20% LEU                                                    from entrances
            225 kg 3.5% LEU remaining from
            Natanz stockpile sent here*
                                                                                to peak.


        Notes
        * Calculated estimated based on amount IAEA
        reported has been transferred from Natanz to
        Fordow                                                                                     Image from NOV 24 2009 (Google Earth)     Page 16
                                                       Copyright © 2012 by the AEI Critical Threats Project
Scope, Assumptions and Technical Points




                                          Page 17
Scope

This product is an exposition of the technical data contained in numerous
IAEA reports informed by the discussions of experts in the field of nuclear
proliferation. It is a work-in-progress in that it will be revised continuously
based on new information from the IAEA and other sources and on feedback
from readers.

We welcome your informed commentary on the technical considerations
presented in this document. Please send your comments, with references to
source-data or documentation, to INP@AEI.ORG.

This product does NOT contain policy recommendations. It is intended solely
to inform the policy community and the American public about the nature
and progress of the Iranian nuclear program.

This product does NOT assess Iran’s intentions to weaponize or to pursue
breakout scenarios. It is focused entirely on technical feasibility.


                                                                              Page 18
Breakout Scenarios
Worst-case
  The worst-case scenarios assume that Iran devotes all operational centrifuges at Natanz (as of NOV 2012) to
  producing first additional 19.75% LEU and then 90% highly-enriched uranium (HEU), ceasing production of 3.5%
  LEU. Such actions would be visible to inspectors and so would most likely occur between inspections. Iranian
  nuclear policy and strategy does not appear to be going down this road.
  The scenarios assume 9,156 centrifuges spinning (the number being fed uranium as of NOV 2012) operating with
  an efficiency of 0.9 separative work units (SWU)/centrifuge/year (roughly the efficiency they have demonstrated).
  15 kg requirement: Iran begins to race to breakout by producing 116 kg total of 19.75% LEU and then enriching
  that material to 90% HEU.
  25 kg requirement: Iran begins to race to breakout by producing 193 kg total of 19.75% LEU and then enriching
  that material to 90% HEU.
  If Iran breaks out using a three-step process, it would need to produce 240 kg total of 19.75% LEU in total, then
  enrich to 60% HEU and then to 90% HEU to yield 15 kg. Assuming Iran needs 25 kg 90% HEU, it would need to
  produce 399 kg total of 19.75% LEU before it could convert to 60% and then 90%.
  These calculations assume tails assays of 2.0% and 9.3% for the two steps in the first process and 2.0%, 12.0%, and
  41.1% for the three steps in the second process (see page 22). These data are derived from the Natanz facility; the
  Fordow installations are notably more efficient with lower tails assays.

Most Likely
  The 9,156 centrifuges being fed in the main cascade hall at Natanz continue to produce 3.5% LEU and are not
  diverted to higher-level enrichment. Iran uses 85 kg 19.75% LEU to produce 15 kg 90% HEU or continues enriching
  to 19.75% until it has amassed approximately 141 kg 19.75% LEU, which can yield 25 kg 90% HEU.
  Enrichment to 19.75% occurs in 4 cascades totaling 696 IR-1 centrifuges at Fordow (2 sets of 2 interconnected
  cascades) and 2 cascades totaling 328 IR-1 centrifuges at the Natanz PFEP (all currently operational).
  Enrichment from 19.75% to 90% occurs in 6 cascades at Fordow in one step using a tails assay of 4.6%. The
  difference in the tails between the worst-case and most likely breakout scenarios reflects the fact that the cascades
  at Fordow, like the ones at Natanz PFEP, are interconnected in pairs.


                                                                                                                    Page 19
                                             Copyright © 2012 by the AEI Critical Threats Project
Atomic Weapons Data
Small atomic weapons can be built from cores consisting of 10-25 kg of uranium enriched to 90% U-
235 (weapons-grade HEU). We use 15 kg and 25 kg to assess breakout timelines.
The explosive yield of a 15 kg core is on the close order of 15 kilotons.
Uranium can be enriched to HEU in a two-step or a three-step process.
Both processes begin by enriching natural uranium (0.7% U-235) to 3.5% LEU.
The two-step process enriches from 3.5% LEU to 19.75% LEU, and then from 19.75% LEU directly to
90% HEU.
The three-step process proceeds from 3.5% LEU to 19.75% LEU, from 19.75% LEU to 60% HEU, and
then from 60% HEU to 90% HEU.
The most important difference between these processes is the amount of LEU required initially—the
time required to enrich from 19.75% to 90% is virtually the same for either process.
The two-step process for producing 15 kg weapons-grade HEU requires 85 kg of 19.75% LEU using
interconnected cascades (such as at Fordow) or 116 kg using non-interconnected cascades (such as
those at Natanz). Producing 25 kg weapons-grade HEU in a two-step process requires 141 kg of
19.75% LEU using interconnected cascades or 193 kg using non-interconnected cascades. The three-
step process requires significantly more in non-interconnected cascades (such as at Natanz).
There is disagreement among experts about Iran’s ability to execute a two-step process with its
current technology and cascade configuration.
If Iran were forced to use a three-step process, the primary delay would result from the time
required to produce the additional 19.75% LEU, a factor that Iran could affect either by bringing more
centrifuge cascades online or by beginning to enrich with more efficient centrifuges, some of which
are already installed but not yet producing enriched uranium.



                                                                                                  Page 20
                                     Copyright © 2012 by the AEI Critical Threats Project
Comparison of Estimated Breakout Times
                                                                                                               1/16/2013
                      11/30/2012                                                                                                                                                   3/8/2013
                                                 12/18/2012                    12/25/2012                    15 kg 90% HEU
  11/20/2012    2-step at Natanz (15 kg)                                                                                                     2/1/2013                           25 kg 90% HEU
                                           2-step at Natanz (25 kg)      3-step at Natanz (15 kg)              At Fordow
     Start                                                                                                   + pilot Natanz           3-step at Natanz (25 kg)                    at Fordow
                                                                                                                                                                                 +pilot Natanz


AEI Critical Threats Project


                                                                                2/21/2013                                                                  RED boxes denote scenarios using all
          11/20/2012                      1/4/2013                         3-step at Natanz FEP,                                                           or majority of available cascades
             Start                2-step at Natanz FEP and               Fordow, and PFEP (20 kg)                                                          BLUE boxes denote scenarios not
                                 clandestine facility (20 kg)
                                                                                                                                                           using cascades in the main halls at
                                                                                                                                                           Natanz

Nonproliferation Policy
Education Center                                                                                                                                                 Note that some analyst estimates are
                11/20/2012                                                                                                                                       based on earlier IAEA reports and do
                   Start                            12/20/2012                                                                         3/5/2013
                                                                                                                                                                 not take account of the new
                                              2-step at Natanz (20 kg)                                                          3-step at Natanz (20 kg)         information. Assumptions, including
                                                                                                                                                                 efficiency rates and fissile material
                                                                                                                                                                 quantities, vary across the estimates.
Bipartisan Policy Center

                 11/20/2012
                    Start                                      1/19/2013                                                                      3/20/2013
                                                             25 kg 90% HEU                                                                  25 kg 90% HEU



Institute for Science and
  International Security
                 11/20/2012                                       1/7/2013                                                     2/27/2013
                    Start                                  Natanz 9,156 centrifuges                                  At Fordow with 1392 centrifuges
                                                               16 kg 90% HEU                                                 16 kg 90% HEU

Wisconsin Project on
Nuclear Arms Control

                                                                                                                                                                                                 Page 21
                                                                         Copyright © 2012 by the AEI Critical Threats Project
Projections for the February 2013 IAEA Report
 IR-1 centrifuges being fed at Natanz FEP: 9,156 (moderate confidence)

 Total 3.5% LEU produced at Natanz FEP: 5,567 kg (moderate confidence)*

 IR-1 centrifuges being fed for 19.75% enrichment at Natanz and Fordow: 1,024 (low confidence)

 Total 19.75% LEU produced at Natanz PFEP and Fordow FEP: 184.8 kg (moderate confidence)*

                                            PREVIOUS PROJECTIONS
 3.5% LEU
 We previously estimated that Iran would produce an additional 498 kg of 3.5% enriched uranium
 at Natanz during the last reporting period. The IAEA reported that Iran produced about 492 kg
 3.5% enriched uranium during the period.

 19.75% LEU
 We previously estimated that Iran would produce an additional 23 kg of 19.75% enriched uranium
 at Natanz and Fordow during the last reporting period. The IAEA reported that Iran produced
 about 29 kg 19.75% enriched uranium. The error is attributed to timing (our estimate was based
 on a November 4 measurement and the actual measurement took place on November 10-11) and
 increased production rate per centrifuge at Fordow.




*Assuming IAEA measurement on 11 FEB 2013                                                    Page 22
Sources
International Atomic Energy Agency (IAEA) – The IAEA publishes quarterly reports on Iran’s nuclear program and enrichment progress. Enriched uranium stockpile,
centrifuge count, potential inspection windows, and other technical data provided by the IAEA are used in our analysis to determine historical rates of production
and to serve as a basis for building projections. IAEA reports on Iran are available at http://www.iaea.org/newscenter/focus/iaeairan/iaea_reports.shtml.

World Information Service Project on Energy (WISE) – WISE provides a uranium enrichment calculator for calculating the separative work required to achieve specific
levels of U-235 concentration. The calculator uses manual inputs of feed, product, and tails figures to calculate separative work units (SWU). The resultant SWU
serves as the basis for calculating time requirements. This assessment uses the WISE calculator to determine the SWU required for enriching at various levels. The
online calculator is accessible at http://www.wise-uranium.org/nfcue.html.

Gregory Jones, Nonproliferation Education Policy Center (NPEC) – Gregory Jones provided the estimated tails percentage figures for enriching to weapons-grade
uranium levels for two-step and three-step batch recycling methods (starting with 3.5% LEU) at the Natanz FEP and two-step batch recycling (from 3.5%) at Natanz
PFEP/Fordow FEP, where cascades are interconnected. Jones has written that the technical assumption underlying an Iranian attempt to break out using two-step
batch recycling without reconfiguration (from 3.5%) may not be feasible. The alternative Iranian breakout approach he suggests, adding an intermediary step
between 19.75% and 90% enrichment, is one that we have relied on in our analysis. Jones’s analyses are available at http://www.npolicy.org/.

Jones has written that the process for Iran to convert the U3O8 enriched up to 20% created for fuel plates back to 20% enriched UF6 gas for use in a breakout
“involves dissolution by nitric acid, followed by purification by solvent extraction. These are standard processes in the nuclear industry and Iran uses them as part of
its uranium ore processing...The time required from the removal of the fresh TRR fuel from safeguards to the time to produce 19.75% enriched uranium hexafluoride
would be only ‘days to weeks.’ [citing Albert Wohlstetter et al, Swords from Plowshares, Chicago University Press, 1979]” The report is available at http://
www.npolicy.org/article_file/Fueling_the_Tehran_Research_Reactor-Technical_Considerations_on_the_Risks_and_Benefits.pdf.

Further on this topic, Henry Sokolski, NPEC, has written that Iran could withdraw 19.75% enriched uranium from fuel plates in the form of UF6 gas in 1-2 weeks. See
http://www.nationalreview.com/corner/188387/fueling-around-iran-and-bomb/henry-sokolski.

Institute for Science and International Security (ISIS) – ISIS has contributed to a technical debate among experts regarding the feasibility of two-step and three-step
batch recycling methods. ISIS analyses are available at http://isis-online.org/.

Alexander Glaser, “Characteristics of the Gas Centrifuge for Uranium Enrichment and Their Relevance for Nuclear Weapon Proliferation,” Science and Global Security
(16:1-25, 2008) – Glaser’s analysis of the P-1 centrifuge—the foundation of Iran’s IR-1 centrifuge program—is the basis for two-step batch recycling projections for
enriching to weapons-grade uranium. A key aspect of Glaser’s analysis in this paper was that 90% HEU can be produced in one step from 19.7% LEU without the
need to reconfigure the arrangement of cascades. In October 2011, according to Gregory Jones, Glaser said he had “been made aware of certain phenomena that
are not taken into account” in his 2008 analysis and that “We now find that the most credible scenarios involve some kind of cascade reconfiguration.” See Greg
Jones, “Earliest Date Possible for Iran’s First Bomb,” Nonproliferation Education Policy Center, December 6, 2011, http://npolicy.org/article.php?aid=1124&rid=4.
For Glaser’s original analysis, see http://www.princeton.edu/sgs/publications/sgs/archive/16-1-Glaser.pdf.

International Commission on Nuclear Non-Proliferation and Disarmament (ICCND) – The ICCND notes that a basic implosion-type nuclear weapon design with an
explosive yield of 15 kilotons would require 15 kg of weapons-grade uranium. We use this figure as the minimum 90% HEU Iran would produce to fuel one bomb.
See http://icnnd.org/Reference/reports/ent/part-ii-4.html.

Thomas B. Cochran and Christopher E. Paine, “The Amount of Plutonium and Highly-Enriched Uranium Needed for Pure Fission Nuclear Weapons,” National
Resources Defense Council, April 13, 1995. – Cochran and Paine assert that the “significant quantity” measurement of 25 kg weapons-grade HEU used by the IAEA
greatly overestimates the amount of fissile material required to fuel a basic implosion-type nuclear explosive device. They estimate that a state with a low technical
capability can produce a bomb with an explosive yield of 20 kilotons with 16 kg weapons-grade HEU. See: http://www.nrdc.org/nuclear/fissionw/
fissionweapons.pdf.                                                                                                                                             Page 23
                                                                Copyright © 2012 by the AEI Critical Threats Project
For more on Iran, visit
 www.irantracker.org

Contenu connexe

Tendances

Non traditional presentation
Non traditional  presentationNon traditional  presentation
Non traditional presentationsohail ahmad
 
Iran Crisis Final
Iran  Crisis  FinalIran  Crisis  Final
Iran Crisis Finaltranceking
 
USA Foreign policy Analysis
USA Foreign policy AnalysisUSA Foreign policy Analysis
USA Foreign policy AnalysisKARAKORAM
 
Pakistan's Nuclear Weapons Program - An overview and critique
Pakistan's Nuclear Weapons Program - An overview and critiquePakistan's Nuclear Weapons Program - An overview and critique
Pakistan's Nuclear Weapons Program - An overview and critiqueVikas Sharma
 
Making of the u.s foreign policy
Making of the u.s foreign policyMaking of the u.s foreign policy
Making of the u.s foreign policySiraj Maryan
 
International Security 3
International Security 3International Security 3
International Security 3alw1125
 
Organization of islamic cooperation (OIC)
Organization of islamic cooperation (OIC)Organization of islamic cooperation (OIC)
Organization of islamic cooperation (OIC)Umer Aziz
 
CSS International Relations Notes
CSS International Relations NotesCSS International Relations Notes
CSS International Relations NotesEntire Education
 
Foreign policy determinants
Foreign policy determinantsForeign policy determinants
Foreign policy determinantsKhan Zeb
 
Nuclear NON-PROLIFERATION TREATY
Nuclear NON-PROLIFERATION TREATYNuclear NON-PROLIFERATION TREATY
Nuclear NON-PROLIFERATION TREATYShaheera Hassan
 
Foreign Policy of Pakistan Part 2
Foreign Policy of Pakistan Part 2Foreign Policy of Pakistan Part 2
Foreign Policy of Pakistan Part 2Shahid Hussain Raja
 
The Iran Nuclear Deal And The Lift Of Restrictions
The Iran Nuclear Deal And The Lift Of RestrictionsThe Iran Nuclear Deal And The Lift Of Restrictions
The Iran Nuclear Deal And The Lift Of RestrictionsInternationalMoneyTransfers
 
Non proliferation treaty-23_47
Non proliferation treaty-23_47Non proliferation treaty-23_47
Non proliferation treaty-23_47domsr
 
Pak-Afghan Relations in post 9-11 era: A case study of Durand line security b...
Pak-Afghan Relations in post 9-11 era: A case study of Durand line security b...Pak-Afghan Relations in post 9-11 era: A case study of Durand line security b...
Pak-Afghan Relations in post 9-11 era: A case study of Durand line security b...Bilal yousaf
 
shanghai cooperation organization
shanghai cooperation organizationshanghai cooperation organization
shanghai cooperation organizationshafu110
 

Tendances (20)

Non traditional presentation
Non traditional  presentationNon traditional  presentation
Non traditional presentation
 
OIC
OICOIC
OIC
 
Iran Crisis Final
Iran  Crisis  FinalIran  Crisis  Final
Iran Crisis Final
 
USA Foreign policy Analysis
USA Foreign policy AnalysisUSA Foreign policy Analysis
USA Foreign policy Analysis
 
Pakistan's Nuclear Weapons Program - An overview and critique
Pakistan's Nuclear Weapons Program - An overview and critiquePakistan's Nuclear Weapons Program - An overview and critique
Pakistan's Nuclear Weapons Program - An overview and critique
 
SCO.pptx
SCO.pptxSCO.pptx
SCO.pptx
 
Making of the u.s foreign policy
Making of the u.s foreign policyMaking of the u.s foreign policy
Making of the u.s foreign policy
 
International Security 3
International Security 3International Security 3
International Security 3
 
Organization of islamic cooperation (OIC)
Organization of islamic cooperation (OIC)Organization of islamic cooperation (OIC)
Organization of islamic cooperation (OIC)
 
Presentation1
Presentation1Presentation1
Presentation1
 
CSS International Relations Notes
CSS International Relations NotesCSS International Relations Notes
CSS International Relations Notes
 
Foreign policy determinants
Foreign policy determinantsForeign policy determinants
Foreign policy determinants
 
Nuclear Proliferation
Nuclear ProliferationNuclear Proliferation
Nuclear Proliferation
 
Nuclear NON-PROLIFERATION TREATY
Nuclear NON-PROLIFERATION TREATYNuclear NON-PROLIFERATION TREATY
Nuclear NON-PROLIFERATION TREATY
 
Foreign Policy of Pakistan Part 2
Foreign Policy of Pakistan Part 2Foreign Policy of Pakistan Part 2
Foreign Policy of Pakistan Part 2
 
The Iran Nuclear Deal And The Lift Of Restrictions
The Iran Nuclear Deal And The Lift Of RestrictionsThe Iran Nuclear Deal And The Lift Of Restrictions
The Iran Nuclear Deal And The Lift Of Restrictions
 
Non proliferation treaty-23_47
Non proliferation treaty-23_47Non proliferation treaty-23_47
Non proliferation treaty-23_47
 
Deterrence .pptx
Deterrence .pptxDeterrence .pptx
Deterrence .pptx
 
Pak-Afghan Relations in post 9-11 era: A case study of Durand line security b...
Pak-Afghan Relations in post 9-11 era: A case study of Durand line security b...Pak-Afghan Relations in post 9-11 era: A case study of Durand line security b...
Pak-Afghan Relations in post 9-11 era: A case study of Durand line security b...
 
shanghai cooperation organization
shanghai cooperation organizationshanghai cooperation organization
shanghai cooperation organization
 

En vedette

The Iranian Nuclear Program: Timelines, Data, and Estimates V6.0
The Iranian Nuclear Program: Timelines, Data, and Estimates V6.0The Iranian Nuclear Program: Timelines, Data, and Estimates V6.0
The Iranian Nuclear Program: Timelines, Data, and Estimates V6.0AEI's Critical Threats Project
 
Eclipse – living in the shadow of china’s economic dominance
Eclipse – living in the shadow of china’s economic dominanceEclipse – living in the shadow of china’s economic dominance
Eclipse – living in the shadow of china’s economic dominanceVaibhav Vyas
 
Iran economic sanctions
Iran economic sanctionsIran economic sanctions
Iran economic sanctionsIrfan iftekhar
 
Islamic Republic of Iran - Opportunities and Financial Crime Risks.
Islamic Republic of Iran - Opportunities and Financial Crime Risks.Islamic Republic of Iran - Opportunities and Financial Crime Risks.
Islamic Republic of Iran - Opportunities and Financial Crime Risks.Aperio Intelligence
 
Us iran conflict in future aspect
Us iran conflict in  future aspectUs iran conflict in  future aspect
Us iran conflict in future aspectFiverr (Fiverr.com)
 
Foreign trade and its importance in the economy of Iran in the international ...
Foreign trade and its importance in the economy of Iran in the international ...Foreign trade and its importance in the economy of Iran in the international ...
Foreign trade and its importance in the economy of Iran in the international ...Private
 

En vedette (7)

The Iranian Nuclear Program: Timelines, Data, and Estimates V6.0
The Iranian Nuclear Program: Timelines, Data, and Estimates V6.0The Iranian Nuclear Program: Timelines, Data, and Estimates V6.0
The Iranian Nuclear Program: Timelines, Data, and Estimates V6.0
 
Eclipse – living in the shadow of china’s economic dominance
Eclipse – living in the shadow of china’s economic dominanceEclipse – living in the shadow of china’s economic dominance
Eclipse – living in the shadow of china’s economic dominance
 
Iran economic sanctions
Iran economic sanctionsIran economic sanctions
Iran economic sanctions
 
Islamic Republic of Iran - Opportunities and Financial Crime Risks.
Islamic Republic of Iran - Opportunities and Financial Crime Risks.Islamic Republic of Iran - Opportunities and Financial Crime Risks.
Islamic Republic of Iran - Opportunities and Financial Crime Risks.
 
Iran
IranIran
Iran
 
Us iran conflict in future aspect
Us iran conflict in  future aspectUs iran conflict in  future aspect
Us iran conflict in future aspect
 
Foreign trade and its importance in the economy of Iran in the international ...
Foreign trade and its importance in the economy of Iran in the international ...Foreign trade and its importance in the economy of Iran in the international ...
Foreign trade and its importance in the economy of Iran in the international ...
 

Plus de AEI's Critical Threats Project

Plus de AEI's Critical Threats Project (20)

2018 08-07 CTP Update and Assessment
2018 08-07 CTP Update and Assessment2018 08-07 CTP Update and Assessment
2018 08-07 CTP Update and Assessment
 
2018 07-31 CTP Update and Assessment
2018 07-31 CTP Update and Assessment2018 07-31 CTP Update and Assessment
2018 07-31 CTP Update and Assessment
 
2018 07-24 CTP Update and Assessment
2018 07-24 CTP Update and Assessment 2018 07-24 CTP Update and Assessment
2018 07-24 CTP Update and Assessment
 
2018 07-17 CTP Update and Assesment
2018 07-17 CTP Update and Assesment2018 07-17 CTP Update and Assesment
2018 07-17 CTP Update and Assesment
 
2018 07-10 CTP Update and Assessment
2018 07-10 CTP Update and Assessment2018 07-10 CTP Update and Assessment
2018 07-10 CTP Update and Assessment
 
2018 06-26 CTP Update and Assessment
2018 06-26 CTP Update and Assessment2018 06-26 CTP Update and Assessment
2018 06-26 CTP Update and Assessment
 
2018 06-19 CTP Update and Assessment
2018 06-19 CTP Update and Assessment2018 06-19 CTP Update and Assessment
2018 06-19 CTP Update and Assessment
 
2018 06-12 CTP Update and Assessment
2018 06-12 CTP Update and Assessment2018 06-12 CTP Update and Assessment
2018 06-12 CTP Update and Assessment
 
2018 06-05 CTP Update and Assessment
2018 06-05 CTP Update and Assessment2018 06-05 CTP Update and Assessment
2018 06-05 CTP Update and Assessment
 
2018 05-29 CTP Update and Assessment
2018 05-29 CTP Update and Assessment2018 05-29 CTP Update and Assessment
2018 05-29 CTP Update and Assessment
 
2018 05-22 CTP Update and Assessment
2018 05-22 CTP Update and Assessment2018 05-22 CTP Update and Assessment
2018 05-22 CTP Update and Assessment
 
2018 05-15 CTP Update and Assessment
2018 05-15 CTP Update and Assessment2018 05-15 CTP Update and Assessment
2018 05-15 CTP Update and Assessment
 
2018 05-01 CTP Update and Assessment
2018 05-01 CTP Update and Assessment2018 05-01 CTP Update and Assessment
2018 05-01 CTP Update and Assessment
 
2018 04-24 CTP Update and Assessment
2018 04-24 CTP Update and Assessment2018 04-24 CTP Update and Assessment
2018 04-24 CTP Update and Assessment
 
2018 04-17 CTP Update and Assessment
2018 04-17 CTP Update and Assessment2018 04-17 CTP Update and Assessment
2018 04-17 CTP Update and Assessment
 
2018 04-10 ctp update and assessment
2018 04-10 ctp update and assessment 2018 04-10 ctp update and assessment
2018 04-10 ctp update and assessment
 
2018 04-03 CTP Update and Assessment
2018 04-03 CTP Update and Assessment2018 04-03 CTP Update and Assessment
2018 04-03 CTP Update and Assessment
 
2018 03-27 CTP Update and Assessment
2018 03-27 CTP Update and Assessment2018 03-27 CTP Update and Assessment
2018 03-27 CTP Update and Assessment
 
2018 03-20 CTP Update and Assessment
2018 03-20 CTP Update and Assessment2018 03-20 CTP Update and Assessment
2018 03-20 CTP Update and Assessment
 
2018 03 13 CTP Update and Assessment
2018 03 13 CTP Update and Assessment2018 03 13 CTP Update and Assessment
2018 03 13 CTP Update and Assessment
 

The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

  • 1. The Iranian Nuclear Program Timelines, Data, and Estimates Maseh Zarif Deputy Director and Iran Team Lead AEI Critical Threats Project Version 5.0 NOVEMBER 2012 Current as of NOV 21 2012 using data from IAEA report dated NOV 16 2012 www.criticalthreats.org Copyright © 2012 by the AEI Critical Threats Project
  • 2. November 2012 International Atomic Energy Agency (IAEA) Findings Additional Centrifuge Installation Iran increased its enrichment capacity by installing additional centrifuges at its declared sites between August and November 2012. The hardened Fordow facility is now at maximum capacity (2,784 centrifuges). Of the 2,784, 696 centrifuges are currently enriching at Fordow and 696 are ready to begin enriching immediately. The IAEA also noted the addition of first-generation and advanced centrifuges, the latter undergoing testing, at the Natanz facility. Increasing Enriched Uranium Stockpiles Iran continues to produce low- (<5%) and medium-enriched (near 20%) uranium at historically high rates. It has now allocated roughly 40% of its medium-enriched uranium for conversion to reactor fuel plates; only a small fraction of the allocated material, however, has been packaged into fuel plates and placed into a reactor core as of August 2012. Parchin Facility Inspection Iran continues to deny the IAEA access to the Parchin facility, where the agency believes Iran conducted experiments related to nuclear weapons development. The IAEA noted that, even if it is given access to the site, its ability to “conduct effective verification will have been seriously undermined” by physical disruption and sanitization undertaken by Iran at the facility in 2012. Weaponization Iran continues to stonewall the IAEA regarding its weaponization activities. The agency reiterated its assessment of Iran’s work on nuclear weapons development: “the information indicates that, prior to the end of 2003 the activities took place under a structured program; that some continued after 2003; and that some may still be ongoing.” Arak Reactor Timeline Iran told the IAEA that it will begin operating the Arak heavy water reactor later than previously planned. The reactor, now scheduled for an early 2014 launch, will provide Iran with a separate pathway to acquiring fissile material for nuclear weapons in the form of weapons-grade plutonium. Page 2
  • 3. Status of Near-20% Enriched Uranium Iran has enough near-20% enriched uranium with which to produce weapons-grade uranium (WGU) for one warhead. Some of this material is currently stored in oxide powder form, which can be converted back into a gas for weapons-grade enrichment. NEAR-20% ENRICHED URANIUM 141 kg needed to produce one warhead’s worth of WGU 156 kg produced as of November 2012 IAEA report (see pie chart for breakdown) 151.5 kg available in gas or oxide powder form (allocated for use in fuel plates for Tehran Research Reactor) 3.4 kg 1.1 kg Converted into U3O8 fuel Enriched down to <4% plates and placed into or irradiated in reactor core (as of August 2012) 52 kg 99.5 kg Fed into process for Stored as enriched conversion to U3O8 uranium gas (available for WGU (available now for WGU production after re- production) conversion to gas form)* Total near-20% enriched uranium produced: 156 kg *Methods for converting near-20% material in U3O8 form back into a gas “are standard processes in the nuclear industry and Iran uses them as part of its uranium ore processing.”1 The conversion can be done using specialized facilities and can be accomplished in “days to weeks.”2 The near-20% LEU can only be classified as unusable in a breakout once the fuel assemblies containing the U3O8 are inserted and irradiated in a reactor core. Only a small fraction of Iran’s near-20% LEU in the form of U3O8 has been manufactured into fuel assemblies and placed into or irradiated in a reactor core (3.4 kg). 1) Gregory Jones, “Fueling the Tehran Research Reactor: Technical Considerations on the Risks and Benefits,” NPEC, October 12, 2009. Page 3 2) Ibid.
  • 4. Key Points IRAN’S ENRICHMENT CAPABILITIES ARE NO LONGER THE PRIMARY BOTTLENECK IN A NUCLEAR BREAKOUT SCENARIO Iran can produce one bomb’s worth of fissile material faster than it likely can deploy a functioning nuclear device. Tracking Iran’s uranium enrichment activities now addresses only Iran’s intentions and the size of its projected arsenal. Obtaining fissile material in the form of weapons-grade uranium or plutonium is the most technically demanding step in acquiring a nuclear weapons capability. Designing an explosive device (consisting of non-nuclear components) and a delivery system for the device are comparatively less technically challenging. Those efforts can also proceed parallel to enrichment. Iran has the infrastructure and material to produce weapons-grade uranium. It has enough enriched uranium to produce fuel for six nuclear weapons after conversion to weapons-grade levels. Its expanding enrichment activities have significantly reduced the time required for it to produce weapons-grade uranium. The key accelerants for this shrinking timeline have been its growing stockpiles of low- and medium-enriched uranium, which is 90% of the way to weapons-grade uranium, and an increasing number of centrifuges enriching. Page 4 Copyright © 2012 by the AEI Critical Threats Project
  • 5. Nuclear Program Expansion Iran will likely have enough near-20% enriched uranium to rapidly produce fissile material for 2 nuclear weapons by late 2013 or early 2014. Iran has installed many more centrifuges at the hardened Fordow facility than are now actually spinning, providing a reserve and/or surge capacity that will be difficult for Israel to destroy. The installation of 2,088 additional centrifuges at Fordow since summer 2012 gives Iran the ability to: produce near-weapons grade uranium (20% enrichment level) in larger quantities faster, providing rapidly-convertible feedstock for a small arsenal of nuclear weapons; convert near-weapons grade uranium into nuclear weapons fuel in a shorter amount of time. Iran’s uranium enrichment is at historically high rates despite increasing sanctions and damage to the Iranian economy. Iran told the International Atomic Energy Agency (IAEA) that it plans to begin operating the Arak heavy water reactor in early 2014 (it had previously planned commencement for mid-to-late 2013). This reactor will be capable of producing two warheads’ worth of weapons-grade plutonium per year once operational. Page 5
  • 6. Breakout Timelines Time needed to produce fuel for 1 nuclear weapon: Iran needs 3.6 months to produce 25 kg of weapons-grade uranium and 1.9 months to produce weapons-grade uranium at the buried Fordow and pilot Natanz enrichment facilities.* It can cut these times significantly using the centrifuges installed but not yet operating at the Fordow facility. Iran needs 4-10.5 weeks to produce 25 kg of weapons-grade uranium and 1.5-5 weeks to produce 15 kg of weapons-grade uranium at the main Natanz enrichment facility.* The higher end of the range accounts for a three-step conversion process. Estimates of the time Iran needs to build a nuclear device to use this fissile material are generally longer than the timelines above. The existence of undeclared (covert) enrichment sites would have a significant impact on breakout estimates. Evidence of significant Iranian enrichment beyond 20% will strongly suggest not only that the decision to weaponize has been made, but also that the Iranians believe they have (or will shortly have) a viable warhead. *All enriched uranium figures are given in terms of solid uranium (where 1 kg uranium hexafluoride is equal to ~0.67 kg elemental uranium). Estimates assume Natanz and Fordow are used with the operational capacity reflected in the November 2012 IAEA report. Iran may need 15-25 kg of weapons-grade uranium for an implosion-type bomb design depending on its level of technical ability (high technical ability would require less material). See pages 18, 19, and 22 for further detail. Page 6
  • 7. Iran has outfitted the hardened Fordow enrichment facility with 2,784 IR-1 centrifuges. This expansion gives Iran the capacity to produce near-20% enriched uranium at a faster rate and the means to convert that stockpile to weapons-grade uranium (WGU) more rapidly in a deeply buried site. Time needed to produce WGU Time needed to produce near- for 1 warhead from near-20% 20% enriched uranium feed enriched uranium at Fordow for WGU for second warhead* Using 696 centrifuges currently enriching 4.7 MONTHS 14 MONTHS Using 1,392 centrifuges currently enriching and under 2.4 MONTHS 8.6 MONTHS vacuum Using all 2,784 centrifuges available 1.2 MONTHS 4.7 MONTHS *Assumes constant production of near-20% enriched uranium at smaller pilot facility at Natanz Page 7
  • 8. Iran’s Declared 3.5% Enriched Uranium Production at Natanz Assessment: Stuxnet derailed the 2009 Iranian effort to expand enrichment capability for roughly one year, but the enrichment expansion effort recovered in mid-2010. Neither direct actions nor sanctions have had a visible effect on the enrichment program. Even the Stuxnet success does not appear to have derailed the steady growth of the enriched uranium stockpile. Iran is running its highest number of centrifuges and production rates since the enrichment program began. It has produced enough enriched uranium since 2009 to fuel a small arsenal of nuclear weapons after conversion to weapons grade. New U.S./ Iranian Centrifuges Centrifuges 3.5% LEU Stuxnet Scientist UN/EU enriching not produced Launched Killed sanctions enriching 10000 6000 9000 5000 8000 7000 4000 6000 Kilograms LEU # centrifuges 5000 3000 4000 2000 3000 2000 1000 1000 0 0 Jan-09 Apr-09 Jul-09 Oct-09 Jan-10 Apr-10 Jul-10 Oct-10 Jan-11 Apr-11 Jul-11 Oct-11 Jan-12 Apr-12 Jul-12 Oct-12 Enrichment data source: IAEA Page 8 Copyright © 2012 by the AEI Critical Threats Project
  • 9. Near-20% Enriched Uranium Production and Projected Growth at Fordow/Natanz Amount needed for: 705 ~20% enriched uranium production enough to produce WGU for three nuclear bombs by 4 564 weapons Iran will have produced 282 kg late 2013/early 2014. Iran would ~20% enriched uranium by late need to begin enriching gradually Kilograms 19.75% LEU 2013/early 2014 under steady-state in installed Fordow cascades to 3 423 conditions--enough to produce meet this threshold. weapons WGU for two nuclear bombs 282 designed with a low level of 2 technical capability. weapons 141 1 weapon 156 kg (as of NOV 2012) 0 May-12 Jul-12 Oct-12 Jan-13 May-13 Jul-13 Oct-13 Jan-14 BLACK: Reported production RED: Steady-state enrichment (a) GREEN: Gradual enrichment expansion in available centrifuges at Fordow (b) PURPLE: Rapid enrichment expansion at Fordow (c) *The two lines for each colored scenario represent a range based on different calculations of demonstrated centrifuge efficiency. (a) 1,024 centrifuges currently enriching (2 cascades with 328 total IR-1 centrifuges at PFEP and 4 cascades with 696 total IR-1 centrifuges at Fordow) (b) Same as (a) but Iran begins turning on 2 additional cascades at Fordow every three months in DEC. (c) Iran begins enriching in the 4 additional cascades under vacuum at Fordow in DEC. It will begin enriching in the 8 remaining cascades in JAN 2013. Page 9 Copyright © 2012 by the AEI Critical Threats Project
  • 10. Key Upcoming Events 12/15/2013 Approx. date by which Iran—at current rates—will produce enough near-20% enriched uranium to convert to WGU for a second warhead 1/22/2013 - 2/12/2013 4/23/2013 - 5/14/2013 7/30/2013 - 8/20/2013 IAEA Inspection Window IAEA Inspection Window IAEA Inspection Window 12/1/2012 1/1/2013 2/1/2013 3/1/2013 4/1/2013 5/1/2013 6/1/2013 7/1/2013 8/1/2013 9/1/2013 10/1/2013 11/1/2013 12/1/2013 1/1/2014 Italicized dates are estimates; bold dates are fixed Listed inspection windows are approximate. The IAEA may be 11/29/2012 3/4/2013 6/3/2013 9/9/2013 conducting inspections outside of these windows. IAEA BOG IAEA BOG IAEA BOG IAEA BOG meets meets meets meets 2/22/2013 5/24/2013 8/30/2013 IAEA Report IAEA Report IAEA Report IAEA BOG = International Atomic Energy Agency Board of Governors Page 10 Copyright © 2012 by the AEI Critical Threats Project
  • 11. Making an Atomic Bomb (Concept) Acquire Weapons-grade Parallel processes Design Parallel processes Acquire delivery Uranium warhead vehicle Centrifuge Acquire weapon cascade design LEU gas Fed back into produces UF6 gas Shahab-3 (3.5% U-235) 19.75% U-235 missile Fed back into produces Develop detonator technology Centrifuge Centrifuge cascade Two-step cascade Test design uranium Fed through produces and engineering enrichment then UF6 gas process UF6 gas 0.7% U-235 90% U-235 Build weapon Converted to Processed into Test weapon Mate warhead with delivery vehicle Natural uranium High-enriched elemental uranium (Process complete) solid metal (90% U-235) Page 11 Copyright © 2012 by the AEI Critical Threats Project
  • 12. Making an Atomic Bomb (Status as of NOV 2012) ay ay w Acquire Weapons-grade Design Acquire delivery w ne Parallel processes Parallel processes r r de warhead vehicle de Uranium Do Un Un Centrifuge Acquire weapon cascade design ay Shahab-3 w ne ne ne LEU gas Fed back into produces UF6 gas r (3.5% U-235) 19.75% U-235 missile Do Do de Do Un Fed back into produces NB: All estimates of Iran’s Develop detonator ay nuclear status and technology w Centrifuge capabilities assume that Centrifuge r there are no clandestine de cascade cascade facilities, and that the Un IAEA has full access to all Test design Fed through produces declared facilities. The and engineering first assumption is impossible to verify. The d then te second assumption is or ne UF6 gas known to be false. UF6 gas ep 0.7% U-235 Do 90% U-235 tr Build weapon d te No or Converted to Processed ep into tr No Mate warhead with g ne Test weapon in g d in Do te delivery vehicle ar or Natural uranium ar ep ep High-enriched (Process complete) ep Pr tr elemental uranium Pr No solid metal (90% U-235) Page 12 Copyright © 2012 by the AEI Critical Threats Project
  • 13. Why Enrichment Accelerates at Higher Concentration of U-235 Centrifuge 1,373 kg cascade 116 kg LEU gas Fed back into produces UF6 gas (3.5% U-235) 19.75% U-235 559 SWU The work and time required to Fed back into 37 days enrich uranium from its natural produces concentration (0.7%) to 3.5% Centrifuge 5,060 SWU 115 SWU Centrifuge LEU is an order of magnitude cascade 331 days 8 days cascade greater than that required to enrich 20% LEU to weapons- Fed through produces grade concentrations (~90% U- 235). 14,187 kg 15 kg That is because centrifuges UF6 gas UF6 gas 0.7% U-235 90% U-235 must spin more than 14,000 kg of uranium ore to produce Processed Converted to 1,373 kg of 3.5% LEU, but only into 116 kg of 20% LEU to produce 15 kg of weapons-grade uranium. Natural uranium High-enriched elemental uranium SWU = Separative work unit, a measure of the amount of effort solid metal (90% U-235) required to process nuclear material. The SWU requirement is used to determine the time needed to enrich uranium with a given number of centrifuges operating at a given efficiency. Page 13 Copyright © 2012 by the AEI Critical Threats Project
  • 14. Iran’s Declared Uranium Enrichment Facilities Fordow Fuel Enrichment Plant (FFEP) As of NOV 10 2012: 696 IR-1 centrifuges producing near- 20% LEU 696 IR-1 centrifuges under vacuum and 1392 IR-1 centrifuges not enriching Facility producing near-20% low- enriched uranium (LEU) 464.3 kg 3.5% LEU converted to 64 kg near-20% LEU 225 kg 3.5% LEU remaining from Natanz stockpile sent here* Notes * Calculated estimated based on 145 amount IAEA reported has been transferred from Natanz to Fordow km Natanz Fuel Enrichment Plant (FEP) As of NOV 2012: 9156 IR-1 centrifuges producing <5% LEU 1258 additional IR-1 centrifuges not enriching Facility producing 3.5% enriched LEU Pilot Fuel Enrichment Plant (PFEP) 4992 kg 3.5% LEU produced here As of NOV 2012: 328 IR-1 centrifuges producing near- 20% LEU 176 IR-2m and 176 IR-4 centrifuges installed and intermittently fed Facility producing near-20% LEU 788.6 kg 3.5% LEU converted to 92 kg ` near-20% LEU Unknown kg 3.5% LEU stored here Page 14 Copyright © 2012 by the AEI Critical Threats Project
  • 15. Natanz Enrichment Facilities Pilot Fuel Enrichment Plant (PFEP) As of NOV 2012: 328 IR-1 centrifuges producing near- 20% LEU Natanz Fuel Enrichment Plant (FEP) 176 IR-2m and 176 IR-4 centrifuges As of NOV 2012: installed and intermittently fed 9156 IR-1 centrifuges producing <5% Facility producing near-20% LEU LEU 788.6 kg 3.5% LEU converted to 92 kg 1258 additional IR-1 centrifuges not near-20% LEU enriching Unknown kg 3.5% LEU stored here Facility producing 3.5% enriched LEU 4992 kg 3.5% LEU produced here Underground halls under construction FEB 2003 Page 15 Copyright © 2012 by the AEI Critical Threats Project
  • 16. Fordow Enrichment Facility: Status and Construction Image taken SEP 14 2012 Image from MAR 24 2005 (Google Earth) Pleiades, Apollo Mapping Areas covered in 2005 appear as entrances to New above- Fordow Fuel Enrichment Plant (FFEP) underground facilities in 2009 ground As of NOV 10 2012: facility 696 IR-1 centrifuges producing near- appears 20% LEU between 696 IR-1 centrifuges under vacuum and 2005 and 1392 IR-1 centrifuges not enriching 2009 Facility producing near-20% low- enriched uranium (LEU) Ridgeline rises 464.3 kg 3.5% LEU converted to 64 kg roughly 200 feet near-20% LEU from entrances 225 kg 3.5% LEU remaining from Natanz stockpile sent here* to peak. Notes * Calculated estimated based on amount IAEA reported has been transferred from Natanz to Fordow Image from NOV 24 2009 (Google Earth) Page 16 Copyright © 2012 by the AEI Critical Threats Project
  • 17. Scope, Assumptions and Technical Points Page 17
  • 18. Scope This product is an exposition of the technical data contained in numerous IAEA reports informed by the discussions of experts in the field of nuclear proliferation. It is a work-in-progress in that it will be revised continuously based on new information from the IAEA and other sources and on feedback from readers. We welcome your informed commentary on the technical considerations presented in this document. Please send your comments, with references to source-data or documentation, to INP@AEI.ORG. This product does NOT contain policy recommendations. It is intended solely to inform the policy community and the American public about the nature and progress of the Iranian nuclear program. This product does NOT assess Iran’s intentions to weaponize or to pursue breakout scenarios. It is focused entirely on technical feasibility. Page 18
  • 19. Breakout Scenarios Worst-case The worst-case scenarios assume that Iran devotes all operational centrifuges at Natanz (as of NOV 2012) to producing first additional 19.75% LEU and then 90% highly-enriched uranium (HEU), ceasing production of 3.5% LEU. Such actions would be visible to inspectors and so would most likely occur between inspections. Iranian nuclear policy and strategy does not appear to be going down this road. The scenarios assume 9,156 centrifuges spinning (the number being fed uranium as of NOV 2012) operating with an efficiency of 0.9 separative work units (SWU)/centrifuge/year (roughly the efficiency they have demonstrated). 15 kg requirement: Iran begins to race to breakout by producing 116 kg total of 19.75% LEU and then enriching that material to 90% HEU. 25 kg requirement: Iran begins to race to breakout by producing 193 kg total of 19.75% LEU and then enriching that material to 90% HEU. If Iran breaks out using a three-step process, it would need to produce 240 kg total of 19.75% LEU in total, then enrich to 60% HEU and then to 90% HEU to yield 15 kg. Assuming Iran needs 25 kg 90% HEU, it would need to produce 399 kg total of 19.75% LEU before it could convert to 60% and then 90%. These calculations assume tails assays of 2.0% and 9.3% for the two steps in the first process and 2.0%, 12.0%, and 41.1% for the three steps in the second process (see page 22). These data are derived from the Natanz facility; the Fordow installations are notably more efficient with lower tails assays. Most Likely The 9,156 centrifuges being fed in the main cascade hall at Natanz continue to produce 3.5% LEU and are not diverted to higher-level enrichment. Iran uses 85 kg 19.75% LEU to produce 15 kg 90% HEU or continues enriching to 19.75% until it has amassed approximately 141 kg 19.75% LEU, which can yield 25 kg 90% HEU. Enrichment to 19.75% occurs in 4 cascades totaling 696 IR-1 centrifuges at Fordow (2 sets of 2 interconnected cascades) and 2 cascades totaling 328 IR-1 centrifuges at the Natanz PFEP (all currently operational). Enrichment from 19.75% to 90% occurs in 6 cascades at Fordow in one step using a tails assay of 4.6%. The difference in the tails between the worst-case and most likely breakout scenarios reflects the fact that the cascades at Fordow, like the ones at Natanz PFEP, are interconnected in pairs. Page 19 Copyright © 2012 by the AEI Critical Threats Project
  • 20. Atomic Weapons Data Small atomic weapons can be built from cores consisting of 10-25 kg of uranium enriched to 90% U- 235 (weapons-grade HEU). We use 15 kg and 25 kg to assess breakout timelines. The explosive yield of a 15 kg core is on the close order of 15 kilotons. Uranium can be enriched to HEU in a two-step or a three-step process. Both processes begin by enriching natural uranium (0.7% U-235) to 3.5% LEU. The two-step process enriches from 3.5% LEU to 19.75% LEU, and then from 19.75% LEU directly to 90% HEU. The three-step process proceeds from 3.5% LEU to 19.75% LEU, from 19.75% LEU to 60% HEU, and then from 60% HEU to 90% HEU. The most important difference between these processes is the amount of LEU required initially—the time required to enrich from 19.75% to 90% is virtually the same for either process. The two-step process for producing 15 kg weapons-grade HEU requires 85 kg of 19.75% LEU using interconnected cascades (such as at Fordow) or 116 kg using non-interconnected cascades (such as those at Natanz). Producing 25 kg weapons-grade HEU in a two-step process requires 141 kg of 19.75% LEU using interconnected cascades or 193 kg using non-interconnected cascades. The three- step process requires significantly more in non-interconnected cascades (such as at Natanz). There is disagreement among experts about Iran’s ability to execute a two-step process with its current technology and cascade configuration. If Iran were forced to use a three-step process, the primary delay would result from the time required to produce the additional 19.75% LEU, a factor that Iran could affect either by bringing more centrifuge cascades online or by beginning to enrich with more efficient centrifuges, some of which are already installed but not yet producing enriched uranium. Page 20 Copyright © 2012 by the AEI Critical Threats Project
  • 21. Comparison of Estimated Breakout Times 1/16/2013 11/30/2012 3/8/2013 12/18/2012 12/25/2012 15 kg 90% HEU 11/20/2012 2-step at Natanz (15 kg) 2/1/2013 25 kg 90% HEU 2-step at Natanz (25 kg) 3-step at Natanz (15 kg) At Fordow Start + pilot Natanz 3-step at Natanz (25 kg) at Fordow +pilot Natanz AEI Critical Threats Project 2/21/2013 RED boxes denote scenarios using all 11/20/2012 1/4/2013 3-step at Natanz FEP, or majority of available cascades Start 2-step at Natanz FEP and Fordow, and PFEP (20 kg) BLUE boxes denote scenarios not clandestine facility (20 kg) using cascades in the main halls at Natanz Nonproliferation Policy Education Center Note that some analyst estimates are 11/20/2012 based on earlier IAEA reports and do Start 12/20/2012 3/5/2013 not take account of the new 2-step at Natanz (20 kg) 3-step at Natanz (20 kg) information. Assumptions, including efficiency rates and fissile material quantities, vary across the estimates. Bipartisan Policy Center 11/20/2012 Start 1/19/2013 3/20/2013 25 kg 90% HEU 25 kg 90% HEU Institute for Science and International Security 11/20/2012 1/7/2013 2/27/2013 Start Natanz 9,156 centrifuges At Fordow with 1392 centrifuges 16 kg 90% HEU 16 kg 90% HEU Wisconsin Project on Nuclear Arms Control Page 21 Copyright © 2012 by the AEI Critical Threats Project
  • 22. Projections for the February 2013 IAEA Report IR-1 centrifuges being fed at Natanz FEP: 9,156 (moderate confidence) Total 3.5% LEU produced at Natanz FEP: 5,567 kg (moderate confidence)* IR-1 centrifuges being fed for 19.75% enrichment at Natanz and Fordow: 1,024 (low confidence) Total 19.75% LEU produced at Natanz PFEP and Fordow FEP: 184.8 kg (moderate confidence)* PREVIOUS PROJECTIONS 3.5% LEU We previously estimated that Iran would produce an additional 498 kg of 3.5% enriched uranium at Natanz during the last reporting period. The IAEA reported that Iran produced about 492 kg 3.5% enriched uranium during the period. 19.75% LEU We previously estimated that Iran would produce an additional 23 kg of 19.75% enriched uranium at Natanz and Fordow during the last reporting period. The IAEA reported that Iran produced about 29 kg 19.75% enriched uranium. The error is attributed to timing (our estimate was based on a November 4 measurement and the actual measurement took place on November 10-11) and increased production rate per centrifuge at Fordow. *Assuming IAEA measurement on 11 FEB 2013 Page 22
  • 23. Sources International Atomic Energy Agency (IAEA) – The IAEA publishes quarterly reports on Iran’s nuclear program and enrichment progress. Enriched uranium stockpile, centrifuge count, potential inspection windows, and other technical data provided by the IAEA are used in our analysis to determine historical rates of production and to serve as a basis for building projections. IAEA reports on Iran are available at http://www.iaea.org/newscenter/focus/iaeairan/iaea_reports.shtml. World Information Service Project on Energy (WISE) – WISE provides a uranium enrichment calculator for calculating the separative work required to achieve specific levels of U-235 concentration. The calculator uses manual inputs of feed, product, and tails figures to calculate separative work units (SWU). The resultant SWU serves as the basis for calculating time requirements. This assessment uses the WISE calculator to determine the SWU required for enriching at various levels. The online calculator is accessible at http://www.wise-uranium.org/nfcue.html. Gregory Jones, Nonproliferation Education Policy Center (NPEC) – Gregory Jones provided the estimated tails percentage figures for enriching to weapons-grade uranium levels for two-step and three-step batch recycling methods (starting with 3.5% LEU) at the Natanz FEP and two-step batch recycling (from 3.5%) at Natanz PFEP/Fordow FEP, where cascades are interconnected. Jones has written that the technical assumption underlying an Iranian attempt to break out using two-step batch recycling without reconfiguration (from 3.5%) may not be feasible. The alternative Iranian breakout approach he suggests, adding an intermediary step between 19.75% and 90% enrichment, is one that we have relied on in our analysis. Jones’s analyses are available at http://www.npolicy.org/. Jones has written that the process for Iran to convert the U3O8 enriched up to 20% created for fuel plates back to 20% enriched UF6 gas for use in a breakout “involves dissolution by nitric acid, followed by purification by solvent extraction. These are standard processes in the nuclear industry and Iran uses them as part of its uranium ore processing...The time required from the removal of the fresh TRR fuel from safeguards to the time to produce 19.75% enriched uranium hexafluoride would be only ‘days to weeks.’ [citing Albert Wohlstetter et al, Swords from Plowshares, Chicago University Press, 1979]” The report is available at http:// www.npolicy.org/article_file/Fueling_the_Tehran_Research_Reactor-Technical_Considerations_on_the_Risks_and_Benefits.pdf. Further on this topic, Henry Sokolski, NPEC, has written that Iran could withdraw 19.75% enriched uranium from fuel plates in the form of UF6 gas in 1-2 weeks. See http://www.nationalreview.com/corner/188387/fueling-around-iran-and-bomb/henry-sokolski. Institute for Science and International Security (ISIS) – ISIS has contributed to a technical debate among experts regarding the feasibility of two-step and three-step batch recycling methods. ISIS analyses are available at http://isis-online.org/. Alexander Glaser, “Characteristics of the Gas Centrifuge for Uranium Enrichment and Their Relevance for Nuclear Weapon Proliferation,” Science and Global Security (16:1-25, 2008) – Glaser’s analysis of the P-1 centrifuge—the foundation of Iran’s IR-1 centrifuge program—is the basis for two-step batch recycling projections for enriching to weapons-grade uranium. A key aspect of Glaser’s analysis in this paper was that 90% HEU can be produced in one step from 19.7% LEU without the need to reconfigure the arrangement of cascades. In October 2011, according to Gregory Jones, Glaser said he had “been made aware of certain phenomena that are not taken into account” in his 2008 analysis and that “We now find that the most credible scenarios involve some kind of cascade reconfiguration.” See Greg Jones, “Earliest Date Possible for Iran’s First Bomb,” Nonproliferation Education Policy Center, December 6, 2011, http://npolicy.org/article.php?aid=1124&rid=4. For Glaser’s original analysis, see http://www.princeton.edu/sgs/publications/sgs/archive/16-1-Glaser.pdf. International Commission on Nuclear Non-Proliferation and Disarmament (ICCND) – The ICCND notes that a basic implosion-type nuclear weapon design with an explosive yield of 15 kilotons would require 15 kg of weapons-grade uranium. We use this figure as the minimum 90% HEU Iran would produce to fuel one bomb. See http://icnnd.org/Reference/reports/ent/part-ii-4.html. Thomas B. Cochran and Christopher E. Paine, “The Amount of Plutonium and Highly-Enriched Uranium Needed for Pure Fission Nuclear Weapons,” National Resources Defense Council, April 13, 1995. – Cochran and Paine assert that the “significant quantity” measurement of 25 kg weapons-grade HEU used by the IAEA greatly overestimates the amount of fissile material required to fuel a basic implosion-type nuclear explosive device. They estimate that a state with a low technical capability can produce a bomb with an explosive yield of 20 kilotons with 16 kg weapons-grade HEU. See: http://www.nrdc.org/nuclear/fissionw/ fissionweapons.pdf. Page 23 Copyright © 2012 by the AEI Critical Threats Project
  • 24. For more on Iran, visit www.irantracker.org