1. Presented to the Ottawa Public Library Board
November 18, 2011
Presented by Denise Vaillancourt
City Librarian and CEO
2. Presentation Agenda
Quick recap of events so far
Site selection update
New Building Project Proposal
Objective
Budget
Scope
Milestones
RFP elements
Closing Remarks
4. The Journey So Far
City of Ottawa’s Long Range Plan in 2006 includes the
new central library as an unfunded project
In 2007 the OPL board approves the New Central
Library Detailed Functional Program
City approves $26M in 2009 for land acquisition for
new library site
In 2010, the city begins to acquire land on selected site
and continues into 2011
5. Site Selection Update
In 2010 the city is able to purchase 2 of the lots
Beginning of 2011 the third lot is purchased
In October of 2011 the fourth and final lot is purchased
Site is secured and final occupancy date for negotiated
purchases is Dec 31 2011
10. Objective of the Project
Build a new City of Ottawa Library that incorporates
the key planning concepts and functional programs
elaborated in the New Central Library Project.
11. New Building Project Proposal
Key planning concepts
Create an Urban Focal Point Include a Community Forum
Development
Create a Destination for
Anticipate a Highly Active Children and one for Teens
Building
Include Unique Interior Spaces
Establish a Major Cultural
Destination Include Sustainable Building
Systems and Operations
User Friendly Services
Build in Flexibility
12. Highlights of Functional Program
Spaces Functions Learning Centres
• Concourse, Meeting • Community Library • Languages and
Rooms, and Ancillary • Technology, Literacy
Services Communications • Business and Careers
• City of Ottawa and Digital Services • Local History and
Heritage Gateway • Administrative Genealogy
• Welcome Centre Services
• Children’s Services • Materials Handling
• Teen Zone and Operations
• Fiction, Newspapers
and Magazines • Leasable Space
13. Detailed Numbers
Building Gross Area: 325,000 square feet
Future Expansion: 22,500 square feet
Number of Levels: one sub-grade, ground floor
and four additional
Parking Area On-Site: 300 underground spaces
Exterior Space Area: 12,500 square feet
extensively developed
14. Project Budget
$27.4M Land Acquisition
$135M New Library Building
Construction Costs
Program Areas
Building Gross up
Building Shell
Allowance for Leeds (silver) (3%)
General Requirements and Profit (10%)
Design and Pricing allowance (10%)
Construction allowance
Ancillaries and Soft Costs (20%)
Art Component (1%)
15. Project Budget (cont.)
Site Development and Site Services
Parking
Hardscape Area with Café/Outdoor patio
Service Area
Softscape
Total Library Building Project Budget:
$180M
16. Cost Breakdown
Description Cost
—
Program Areas $31,880,891
—
Building Gross up $3,566,624
—
Building Shell $46,603,675
—
Allowance for Leeds (silver) (3%) $8,205,118
—
Design and Pricing allowance (10%) $8,205,118
—
Construction allowance $4,102,560
—
Ancillaries and Soft Costs (20%) $16,410,237
— Component (1%)
Art $820,512
—
Parking $14,842,800
—
Hardscape Area with Café/Outdoor patio $306,900
—
Service Area $78,120
—
Softscape $27,900
Total Construction $135,050,456
HST 13% $17,556,559
Land Acquisition $27,392,985
Total Project Cost $180,000,000
17. New City of Ottawa
Central Library Project Timelines
Nov 30, 2011 July 30, 2012
Project May 15, 2012 Spring 2013 Fall 2014
Construction
Approval Design RF S Library Opens
Drawings
Presentation Public Art
Dec Mar Jun Sep Dec Mar Jun Sep Dec Mar Jun Se
p
2012 2013 2014
March, 2012
Architectural Aug 15, 2012 Sept, 2014
Design Services Ground Building
Breaking Completion
May 15, 2012
Design
Presentation