1. Salford City College
Eccles Sixth Form Centre
BTec Level 3
Extended Diploma in Creative Media Production
Games Design
Final Major Project
Schedule
Review date: 10.04.13
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
w/b 04.02.13 Task 1 - FMP Launch
Meeting
w/b 11.02.13 Half-Term
w/b 18.02.13 Book meeting slot
with project manager.
Research into cell
animations
Research into popular
kid’s shows
Continue Research Continue Research Finish up all Research
tasks
Review Schedule and
Production Log
w/b 25.02.13 Start Story planning Tweak Story planning Do storyboard Continue Storyboard Continue Storyboard Review Schedule and
Production Log
w/b 04.03.13 Finish Storyboard (Do
Pitch)
Research popular
shows from survey
Continue research
from survey
Continue research
from survey
Review Schedule and
Production Log
w/b 11.03.13 Finish research Do Risk Assessment Do preproduction Prepare for
production
Review Schedule and
Production Log
w/b 18.03.13 Think about what to
use to produce FMP
Finish pre-production Review Schedule and
Production Log
25.03.13 Easter Review Schedule and
Production Log
01.04.13 Easter Do Backgrounds in
Sketchbook
Continue Backgrounds Continue Backgrounds Finish Backgrounds Review Schedule and
Production Log
w/b 08.04.13 Start work on Flash
(Backgrounds)
Continue Work on
Flash
Continue Work on
Flash
Continue Work on
Flash
Review Schedule and
Production Log
w/b 15.04.13 Continue Work on
Flash
Continue Work on
Flash
Continue Work on
Flash
Continue Work on
Flash
Review Schedule and
Production Log
w/b 22.04.13 Continue Work on
Flash
Continue Work on
Flash
Finish Flash, Convert
both movies into one.
Do Evaluation Review Schedule and
Production Log
w/b 29.04.13 Spare Day Spare Day Spare Day Spare Day Review Schedule and
Production Log
w/b 06.05.13 Spare Day Spare Day Spare Day Spare Day Review Schedule and
Production Log
w/b 13.05.13 Spare Day Spare Day Spare Day Spare Day Review Schedule and
Production Log
w/b 20.05.13 Task 8: Evaluation DEADLINE