Energy and Mineral Resources for People’s Prosperity
MINISTRY OF ENERGY AND MINERAL RESOURCES
DIRECTORATE GENERAL OF NEW, RENEWABLE ENERGY AND ENERGY CONSERVATION
by:
Sjaiful Ruchijat
Directorate of Geothermal
APERC Annual Conference 2014
Tokyo, March 27, 2014
Energy and Mineral Resources for People’s Prosperity
I. BACKGROUND
II. GEOTHERMAL POTENTIAL AND DEVELOPMENT
IN INDONESIA
III. GEOTHERMAL POLICIES
IV. BARRIERS AND SOLUTIONS IN GEOTHERMAL
DEVELOPMENT
V. INVESTMENT OPPORTUNITIES
Energy and Mineral Resources for People’s Prosperity
I. BACKGROUND
Energy and Mineral Resources for People’s Prosperity
 Indonesia’s geothermal potential is approximately 28.6 GW which distributed in 299
locations along the country, yet its utilization has only reached 1,3 GW or equal as
4,5%;
 National Energy Policy encourage development of renewable energy by 23 % in year
2025. Geothermal is expected to contribute 7,12% or equal to 7,210 MW as mentioned
in the national electricity system;
 To support utilization of geothermal energy, the Government of Indonesia (GoI) has
issued Crash Program Phase II to accelerate 10.000 MW electricity development that
derived from geothermal power plant (4,965 MW) as mandated in the Ministry of
Energy and Mineral Resources Regulation No. 21/2013;
 Achieving the proposed 4,965 MW new geothermal capacity would automatically lead
Indonesia to the single largest CO2 mitigation program in the world. The proposed
program will reduce in the period of 2010 – 2025 over 400 million tCO2.
BACKGROUND
Energy and Mineral Resources for People’s Prosperity
II. GEOTHERMAL POTENTIAL AND
DEVELOPMENT IN INDONESIA
Energy and Mineral Resources for People’s Prosperity
GEOTHERMAL POTENTIAL MAP
Note:
Installed
Ready to be developed
Detail Survey
Preliminary Survey
No Island
Number of
Location
Total Installed
1 Sumatera 90 12.760 122
2 Java 71 9.717 1.134
3 Bali-Nusa Tenggara 28 1.805 5
4 Kalimantan 12 145
5 Sulawesi 65 3.044 80
6 Maluku 30 1.071
7 Papua 3 75
Total 299 28.617 1.341
Source: Geological Agency,
MEMR (2011)
Energy and Mineral Resources for People’s Prosperity
No Island
Number of
Location
Potential Energy (Mwe)
Total InstalledResources Reserve
Speculative Hypothetical Possible Probable Proven
1 Sumatera 90 3089 2427 6849 15 380 12760 122
2 Java 71 1710 1826 3708 658 1815 9717 1134
3 Bali-Nusa Tenggara 28 360 417 1013 0 15 1805 5
4 Kalimantan 12 145 0 0 0 0 145
5 Sulawesi 65 1323 119 1374 150 78 3044 80
6 Maluku 30 545 97 429 0 0 1071
7 Papua 3 75 0 0 0 0 75
Total 299 7247 4886 13373 823 2288 28617 1.341
12.133 16.484
28.617
DISTRIBUTION OF GEOTHERMAL POTENTIAL
Source : Geological Agency, MEMR
Status : December 2012
Energy and Mineral Resources for People’s Prosperity
ACEH 2 WKP
 Jaboi: 70 MW
 Seulawah Agam: 130 MW
NORTH SUMATERA 5 WKP
 Sibayak – Sinabung: 130 MW
 Sibual – Buali: 750 MW
 Sipaholon Ria-ria: 75 MW
 Sorik Marapi: 200 MW
 Simbolon Samosir : 155 MW
JAMBI 1 WKP
 Sungai Penuh: 70 MW
SOUTH SUMATERA 2 WKP
 Lumut Balai: 250 MW
 Rantau Dedap: 106 MW
BANTEN 2 WKP
 Kaldera Danau Banten: 115 MW
 G. Endut: 80 MW
WEST SUMATERA 4 WKP
 Bukit Kili: 83 MW
 Gn Talang: 35 MW
 Liki Pinangawan: 400 MW
 Bonjol: 200 MW
LAMPUNG 4 WKP
 Gn.Rajabasa: 91 MW
 Suoh Sekincau: 230 MW
 Waypanas – Ulubelu: 556 MW
 Way Ratai :105 MW
CENTRAL JAVA 5 WKP
 Baturaden: 175 MW
 Dataran Tinggi Dieng: 780 MW
 Guci: 79 MW
 Gn. Ungaran: 100 MW
 Umbul Telomoyo : 72 MW EAST JAVA 3 WKP
 Blawan – Ijen: 270 MW
 Gn. Iyang Argopuro: 295 MW
 Telaga Ngebel: 120 MW
BALI 1 WKP
 Tabanan: 276 MW
WEST NUSA
TENGGARA 2 WKP
 Hu'u Daha: 65 MW
 Sembalun : 100 MW
EAST NUSA TENGGARA 5 WKP
 Atadei: 40 MW
 Sokoria: 30 MW
 Ulumbu: 199 MW
 Mataloko: 63 MW
 Oka Ile Ange : 40 MW
MALUKU 1 WKP
 Tulehu: 100 MW
NORTH MALUKU 2 WKP
 Jailolo: 75 MW
 Songa Wayaua: 140 MW
NORTH SULAWESI 2 WKP
 Kotamobagu: 410 MW
 Lahendong-Tompaso: 358 MW
GORONTALO 1 WKP
 Suwawa: 110 MW
CENTRAL SULAWESI 2 WKP
 Marana: 35 MW
 Bora Pulu : 152 MW
Total : 58 GWAs
BENGKULU 2 WKP
 Tmbg Sawah-Hululais: 873 MW
 Kepahiyang : 180 MW
SOUTH SUMATERA & LAMPUNG 1 WKP
 Danau Ranau: 210 MW
Lisence – Issued : 39 GWAs
Tender on Progress : 2 GWAs
Tender Preparation : 13 GWAs
Tender – Failed : 5 GWAs
Distribution of Geothermal Working Area (GWA)
CENTRAL JAVA & EAST JAVA 1 WKP
 Gunung Lawu : 195 MW
WEST JAVA 10 WKP
Ciater - Tgkban Perahu: 60 MW
Cibeureum–Parabakti: 485 MW
Cibuni: 140 MW
Cisolok Cisukarame: 45 MW
Gn. Tampomas: 50 MW
Gn. Tgkuban Perahu: 100 MW
Kamojang-Darajat: 1465 MW
Karaha Cakrabuana: 725 MW
Pangalengan: 1106 MW
G. Ciremai: 150 MW
Energy and Mineral Resources for People’s Prosperity
INSTALLED GEOTHERMAL POWER PLANT CAPACITY BY JANUARY 2014
Kamojang: 200 MW
Salak: 377 MWDarajat: 270 MW Wayang Windu: 227 MW
Lahendong: 80 MW Sibayak: 12 MW Ulubelu: 110 MW
Dieng: 60 MW Ulumbu: 5 MW
TOTAL
1.341 MW
Energy and Mineral Resources for People’s Prosperity
III. GEOTHERMAL POLICIES
Energy and Mineral Resources for People’s Prosperity
 Relating to geothermal utilization, there are three cores of regulation:
1) Law 27 Year 2003 on Geothermal: The Law is the basic guidance for geothermal development in Indonesia
2) Government Regulation No. 59/2007 on Geothermal Business Activity: This regulation
consists of particular provisions in the area of geothermal business activity
3) Ministerial Regulation No. 11/2009 on Guidance for the Implementation of Geothermal Business Activity:
Regulates the geothermal tender and supervision, as well as stages in geothermal business activity
 According to the Law 27 Year 2003 on Geothermal, there are 5 (five) stages in utilizing geothermal energy:
Preliminary Survey → Exploration → Feasibility Study → Exploitation → Utilization
GEOTHERMAL BUSINESS STAGES
Energy and Mineral Resources for People’s Prosperity
The tender winner could initiate geothermal activities after obtaining
Geothermal Businness Permit (IUP). The authority issuing the Permit
depends on the location where the GWA is located.
Geothermal Working Area
(GWA)
Determined by
the Minister of Energy and Mineral
Resources
Offered by the government or local governments within their
authority through the tender mechanism
Energy and Mineral Resources for People’s Prosperity
 Fiscal Incentives policies:
1) Income Tax Article 21
2) Taxes and duties on imported goods
- Duty exemption (for exploration and exploitation activities)
- Free of Value Added Tax (VAT), Luxury Goods Sales Tax (LGST) and Income Tax – based on
Minister of Finance Regulations No. 27/2012 and No. 70/2013
 Other policies including: accelerating the tender process of new GWAs, building the "public
awareness" on the utilization of geothermal as green and environmentally friendly energy
Tax Holiday Tax Allowance
1. An exemption from corporate income tax for 5 to
10 years
2. A two-year, 50% reduction in corporate income
tax
1. Reducing net taxable income to 30% of the
total investment value, carried over six
years
2. Accelerated depreciation and amortization
3. Impose income tax of 10% for dividends
4. Loss carry forward of at least 5 years and
up to 10 years
Energy and Mineral Resources for People’s Prosperity
 Pricing policies previously set by the government does not provide a significant impact on geothermal
development. It is considered that they are not taking into account some crucial aspects such as location,
generation capacity, transmission, escalation, assignment mechanisms and reservoir quality .
 Therefore, the government is currently developing a comprehensive pricing structure which includes
upstream and downstream sides.
No. Generation Capacity
Ceiling Price for Geothermal Power
(cent US$/kWh)
1. > 55 MW 10,5
2. > 20 MW - 55 MW 12,5
3. > 10 MW - 20 MW 15,5
4. ≤ 10 MW 19,0
PROPOSED CEILING PRICES FOR GEOTHERMAL POWER
Energy and Mineral Resources for People’s Prosperity
IV. BARRIERS AND SOLUTIONS IN
GEOTHERMAL DEVELOPMENT
Energy and Mineral Resources for People’s Prosperity
1. Overlapping Areas with Forestry: most of geothermal potentials are located within the forestry
area (15% in conservation forest, 18% in protected forest)
Solution: Ministry of Energy and Mineral Resources (MEMR) and Ministry of Forestry (MF) have
signed the MoU No. 7662/05/MEM.S/2011 to accelerate the geothermal utilization permit within
the area of protected, production and conservation forest.
2. Legal Uncertainty: disharmony in geothermal business regulations
Solution: improvement and harmonization of regulations in Geothermal Business are as follows:
 Draft on Geothermal Law is currently being discussed by the Special Committee of the House of
Representatives
 Second amendment of the Government Regulation No. 59/2007 soon will be issued
 Revision of Minister of Energy and Mineral Resources Regulation No. 11/2009 on Guidance for the
Implementation of Geothermal Business Activity
 Improvement of Minister of Energy and Mineral Resources Regulation No. 22/2012 relating to electricity
price from geothermal energy, through the ceiling price mechanism
BARRIERS AND SOLUTIONS IN GEOTHERMAL DEVELOPMENT (1/2)
Energy and Mineral Resources for People’s Prosperity
3. Geothermal Price: competitiveness of geothermal energy price
Solution: develop a new pricing structure that meets economic value
4. Funding: high investment cost and unbankable project
Solution: - Provides financial support and Government guarantee
- Government guarantees on the feasibility of PT. PLN (buyer)
- Provides “Geothermal Fund" for geothermal exploration
5. Bidding Process
Solution: the policies regulate bidding process are being revised in order to make the
tender process simpler, more transparent and bankable
6. Shortage of Competent Human Resources
Solution: create training, short courses and advanced level education in collaboration
with local and international educational institutions
7. Others
• Absence of Technology and Research & Development Supports
• Low Environmental Awareness
• Continuing Subsidy of Fossil Fuel Price
BARRIERS AND SOLUTIONS IN GEOTHERMAL DEVELOPMENT (2/2)
Energy and Mineral Resources for People’s Prosperity
V. INVESTMENT OPPORTUNITIES
Energy and Mineral Resources for People’s Prosperity
1. Development of 4,965 MW electricity from Geothermal in 10,000 MW Crash Program Phase II requires
more than US$ 15 billions for the investment.
2. To achieve the targets, international supports are needed in terms of finance, technology, human
resources and Technical Assistance.
3. Foreign ownership in Geothermal Business is allowed up to 95 %.
4. Access to Potential Geothermal Resources for Investors:
a) Preliminary Survey Assignment
b) Participate in the geothermal business through GWAs tendering mechanis
5. Other business opportunities in geothermal sector:
a) Geothermal direct use
b) Low temperature geothermal potential
c) Small scale power plant
d) Services company to support the core business of geothermal
INVESTMENT OPPORTUNITIES
Energy and Mineral Resources for People’s Prosperity
`
Go Green Indonesia !
Geothermal, Energy Solution for Better Future
www.ebtke.esdm.go.id
www.indogeothermal.or.id
Jalan Pegangsaan Timur No. 1 Menteng - Jakarta 10320
MINISTRY OF ENERGY AND MINERAL RESOURCES
DIRECTORATE GENERAL OF NEW RENEWABLE ENERGY AND ENERGY CONSERVATION
THANK YOU

Contenu connexe

Tendances

Bunaken Island | Nov-15 | Renewable and island energy activities
Bunaken Island | Nov-15 | Renewable and island energy activitiesBunaken Island | Nov-15 | Renewable and island energy activities
Bunaken Island | Nov-15 | Renewable and island energy activitiesSmart Villages
 
Renewable Energies Potential in Jamaica
Renewable Energies Potential in Jamaica  Renewable Energies Potential in Jamaica
Renewable Energies Potential in Jamaica QZ1
 
Renewable Energy Strategies For The Indian Railways
Renewable Energy Strategies For The Indian Railways  Renewable Energy Strategies For The Indian Railways
Renewable Energy Strategies For The Indian Railways QZ1
 
Power generation and energy - Electricity Issues in Indonesia
Power generation and energy - Electricity Issues in IndonesiaPower generation and energy - Electricity Issues in Indonesia
Power generation and energy - Electricity Issues in IndonesiaGalih Honggo Baskoro
 
Iaea energy profile uae 2019
Iaea  energy profile uae 2019Iaea  energy profile uae 2019
Iaea energy profile uae 2019Khaled Al Awadi
 
Haripur npp project
Haripur npp projectHaripur npp project
Haripur npp projectAmit Raj
 
An Update on Fukushima Recovery and Reactor Restarts
An Update on Fukushima Recovery and Reactor RestartsAn Update on Fukushima Recovery and Reactor Restarts
An Update on Fukushima Recovery and Reactor RestartsJoe Bacchus
 
Japan’s current Nuclear Energy Policy
Japan’s current Nuclear Energy PolicyJapan’s current Nuclear Energy Policy
Japan’s current Nuclear Energy PolicyJoe Bacchus
 
Indonesia's coal based power market
Indonesia's coal based power marketIndonesia's coal based power market
Indonesia's coal based power marketSuparn Kuer
 
Rooftop Greenhouse and Bio-Diesel
Rooftop Greenhouse and Bio-Diesel  Rooftop Greenhouse and Bio-Diesel
Rooftop Greenhouse and Bio-Diesel QZ1
 
IEA gas based power india
IEA gas based power indiaIEA gas based power india
IEA gas based power indiaManish1611
 
UK Energy Policy
UK Energy PolicyUK Energy Policy
UK Energy PolicyJuan Moreno
 
Renewable Energies In Practice- Ashton Green And London
Renewable Energies In Practice- Ashton Green And LondonRenewable Energies In Practice- Ashton Green And London
Renewable Energies In Practice- Ashton Green And LondonAlejo Etchart Ortiz
 
Nyngan solar director-general's assessment report.pdf
Nyngan solar   director-general's assessment report.pdfNyngan solar   director-general's assessment report.pdf
Nyngan solar director-general's assessment report.pdfTurlough Guerin GAICD FGIA
 
Recent progress-on-regulatory-framework-to-accelerate-energy-transition-in-in...
Recent progress-on-regulatory-framework-to-accelerate-energy-transition-in-in...Recent progress-on-regulatory-framework-to-accelerate-energy-transition-in-in...
Recent progress-on-regulatory-framework-to-accelerate-energy-transition-in-in...OECD Environment
 
Mep1623 power plant cost 1
Mep1623 power plant cost 1Mep1623 power plant cost 1
Mep1623 power plant cost 1Subzero Bill
 
Session3 RE_ situation_in_egypt
Session3 RE_ situation_in_egyptSession3 RE_ situation_in_egypt
Session3 RE_ situation_in_egyptRCREEE
 
Jurnal Internasional – Dampak Energi Terbarukan Terhadap Ketenagakerjaan di I...
Jurnal Internasional – Dampak Energi Terbarukan Terhadap Ketenagakerjaan di I...Jurnal Internasional – Dampak Energi Terbarukan Terhadap Ketenagakerjaan di I...
Jurnal Internasional – Dampak Energi Terbarukan Terhadap Ketenagakerjaan di I...Dani Gunawan
 

Tendances (20)

Bunaken Island | Nov-15 | Renewable and island energy activities
Bunaken Island | Nov-15 | Renewable and island energy activitiesBunaken Island | Nov-15 | Renewable and island energy activities
Bunaken Island | Nov-15 | Renewable and island energy activities
 
Renewable Energies Potential in Jamaica
Renewable Energies Potential in Jamaica  Renewable Energies Potential in Jamaica
Renewable Energies Potential in Jamaica
 
Renewable Energy Strategies For The Indian Railways
Renewable Energy Strategies For The Indian Railways  Renewable Energy Strategies For The Indian Railways
Renewable Energy Strategies For The Indian Railways
 
Power generation and energy - Electricity Issues in Indonesia
Power generation and energy - Electricity Issues in IndonesiaPower generation and energy - Electricity Issues in Indonesia
Power generation and energy - Electricity Issues in Indonesia
 
Iaea energy profile uae 2019
Iaea  energy profile uae 2019Iaea  energy profile uae 2019
Iaea energy profile uae 2019
 
Haripur npp project
Haripur npp projectHaripur npp project
Haripur npp project
 
An Update on Fukushima Recovery and Reactor Restarts
An Update on Fukushima Recovery and Reactor RestartsAn Update on Fukushima Recovery and Reactor Restarts
An Update on Fukushima Recovery and Reactor Restarts
 
Eia of clp jhajjar
Eia of clp jhajjarEia of clp jhajjar
Eia of clp jhajjar
 
Japan’s current Nuclear Energy Policy
Japan’s current Nuclear Energy PolicyJapan’s current Nuclear Energy Policy
Japan’s current Nuclear Energy Policy
 
Indonesia's coal based power market
Indonesia's coal based power marketIndonesia's coal based power market
Indonesia's coal based power market
 
Rooftop Greenhouse and Bio-Diesel
Rooftop Greenhouse and Bio-Diesel  Rooftop Greenhouse and Bio-Diesel
Rooftop Greenhouse and Bio-Diesel
 
IEA gas based power india
IEA gas based power indiaIEA gas based power india
IEA gas based power india
 
UK Energy Policy
UK Energy PolicyUK Energy Policy
UK Energy Policy
 
Renewable Energies In Practice- Ashton Green And London
Renewable Energies In Practice- Ashton Green And LondonRenewable Energies In Practice- Ashton Green And London
Renewable Energies In Practice- Ashton Green And London
 
Nyngan solar director-general's assessment report.pdf
Nyngan solar   director-general's assessment report.pdfNyngan solar   director-general's assessment report.pdf
Nyngan solar director-general's assessment report.pdf
 
Recent progress-on-regulatory-framework-to-accelerate-energy-transition-in-in...
Recent progress-on-regulatory-framework-to-accelerate-energy-transition-in-in...Recent progress-on-regulatory-framework-to-accelerate-energy-transition-in-in...
Recent progress-on-regulatory-framework-to-accelerate-energy-transition-in-in...
 
Mep1623 power plant cost 1
Mep1623 power plant cost 1Mep1623 power plant cost 1
Mep1623 power plant cost 1
 
Session3 RE_ situation_in_egypt
Session3 RE_ situation_in_egyptSession3 RE_ situation_in_egypt
Session3 RE_ situation_in_egypt
 
Jurnal Internasional – Dampak Energi Terbarukan Terhadap Ketenagakerjaan di I...
Jurnal Internasional – Dampak Energi Terbarukan Terhadap Ketenagakerjaan di I...Jurnal Internasional – Dampak Energi Terbarukan Terhadap Ketenagakerjaan di I...
Jurnal Internasional – Dampak Energi Terbarukan Terhadap Ketenagakerjaan di I...
 
Barrow offshore
Barrow offshoreBarrow offshore
Barrow offshore
 

En vedette

WGES 2011 Geothermal Development in Indonesia 2011 (Arc Media Global)
WGES 2011 Geothermal Development in Indonesia 2011 (Arc Media Global)WGES 2011 Geothermal Development in Indonesia 2011 (Arc Media Global)
WGES 2011 Geothermal Development in Indonesia 2011 (Arc Media Global)Frank Mercado
 
InvestmentOpportunities_RenewableEnergy_Oct2014ed
InvestmentOpportunities_RenewableEnergy_Oct2014edInvestmentOpportunities_RenewableEnergy_Oct2014ed
InvestmentOpportunities_RenewableEnergy_Oct2014edFrank Mercado
 
Jenis - jenis diagram
Jenis - jenis diagramJenis - jenis diagram
Jenis - jenis diagramMella Imelda
 
89176662 04-teknik-pemboran
89176662 04-teknik-pemboran89176662 04-teknik-pemboran
89176662 04-teknik-pemboranrramdan383
 
STATISTIKA DASAR TENTANG MACAM-MACAM DIAGRAM
STATISTIKA DASAR TENTANG MACAM-MACAM DIAGRAMSTATISTIKA DASAR TENTANG MACAM-MACAM DIAGRAM
STATISTIKA DASAR TENTANG MACAM-MACAM DIAGRAMimmochacha
 
Lumpur Pengeboran (Drilling Fluid)
Lumpur Pengeboran (Drilling Fluid)Lumpur Pengeboran (Drilling Fluid)
Lumpur Pengeboran (Drilling Fluid)Rais Gunawan
 
1 hoisting system
1 hoisting system1 hoisting system
1 hoisting systemfianxxx
 
Indonesia Geothermal EOI Presentation
Indonesia Geothermal EOI PresentationIndonesia Geothermal EOI Presentation
Indonesia Geothermal EOI PresentationDinno Kurniawan
 
MEDIA PEMBELAJARAN (DIAGRAM)
MEDIA PEMBELAJARAN (DIAGRAM)MEDIA PEMBELAJARAN (DIAGRAM)
MEDIA PEMBELAJARAN (DIAGRAM)johnbandid
 
Dasar dasar reservoir-engineering
Dasar dasar reservoir-engineeringDasar dasar reservoir-engineering
Dasar dasar reservoir-engineeringRandy MC
 
01. drilling rig sistem tenaga power system ok
01. drilling rig sistem tenaga  power system ok01. drilling rig sistem tenaga  power system ok
01. drilling rig sistem tenaga power system okrusihan
 
Peralatan Produksi Lepas Pantai (Offshore Production Facility)
Peralatan Produksi Lepas Pantai (Offshore Production Facility)Peralatan Produksi Lepas Pantai (Offshore Production Facility)
Peralatan Produksi Lepas Pantai (Offshore Production Facility)Muhammad Febriyan Firdaus
 
Teknik Produksi Migas - Teknik Reservoir dan Cadangan Migas
Teknik Produksi Migas  - Teknik Reservoir dan Cadangan MigasTeknik Produksi Migas  - Teknik Reservoir dan Cadangan Migas
Teknik Produksi Migas - Teknik Reservoir dan Cadangan MigaslombkTBK
 
Buku pintar migas indonesia
Buku pintar migas indonesiaBuku pintar migas indonesia
Buku pintar migas indonesiaAsep Imam
 
Q922+de1+l02 v1
Q922+de1+l02 v1Q922+de1+l02 v1
Q922+de1+l02 v1AFATous
 
Rotary System
Rotary SystemRotary System
Rotary SystemAFATous
 
Dasar Dasar Teknik Pengeboran
Dasar Dasar Teknik PengeboranDasar Dasar Teknik Pengeboran
Dasar Dasar Teknik PengeboranlombkTBK
 
Lumpur dan Hidrolika Lumpur Pengeboran
Lumpur dan Hidrolika Lumpur PengeboranLumpur dan Hidrolika Lumpur Pengeboran
Lumpur dan Hidrolika Lumpur PengeboranlombkTBK
 
Teknik Produksi Migas
Teknik Produksi Migas Teknik Produksi Migas
Teknik Produksi Migas lombkTBK
 

En vedette (20)

WGES 2011 Geothermal Development in Indonesia 2011 (Arc Media Global)
WGES 2011 Geothermal Development in Indonesia 2011 (Arc Media Global)WGES 2011 Geothermal Development in Indonesia 2011 (Arc Media Global)
WGES 2011 Geothermal Development in Indonesia 2011 (Arc Media Global)
 
InvestmentOpportunities_RenewableEnergy_Oct2014ed
InvestmentOpportunities_RenewableEnergy_Oct2014edInvestmentOpportunities_RenewableEnergy_Oct2014ed
InvestmentOpportunities_RenewableEnergy_Oct2014ed
 
Jenis - jenis diagram
Jenis - jenis diagramJenis - jenis diagram
Jenis - jenis diagram
 
89176662 04-teknik-pemboran
89176662 04-teknik-pemboran89176662 04-teknik-pemboran
89176662 04-teknik-pemboran
 
Renewable Energy in Carbon Market
Renewable Energy  in Carbon MarketRenewable Energy  in Carbon Market
Renewable Energy in Carbon Market
 
STATISTIKA DASAR TENTANG MACAM-MACAM DIAGRAM
STATISTIKA DASAR TENTANG MACAM-MACAM DIAGRAMSTATISTIKA DASAR TENTANG MACAM-MACAM DIAGRAM
STATISTIKA DASAR TENTANG MACAM-MACAM DIAGRAM
 
Lumpur Pengeboran (Drilling Fluid)
Lumpur Pengeboran (Drilling Fluid)Lumpur Pengeboran (Drilling Fluid)
Lumpur Pengeboran (Drilling Fluid)
 
1 hoisting system
1 hoisting system1 hoisting system
1 hoisting system
 
Indonesia Geothermal EOI Presentation
Indonesia Geothermal EOI PresentationIndonesia Geothermal EOI Presentation
Indonesia Geothermal EOI Presentation
 
MEDIA PEMBELAJARAN (DIAGRAM)
MEDIA PEMBELAJARAN (DIAGRAM)MEDIA PEMBELAJARAN (DIAGRAM)
MEDIA PEMBELAJARAN (DIAGRAM)
 
Dasar dasar reservoir-engineering
Dasar dasar reservoir-engineeringDasar dasar reservoir-engineering
Dasar dasar reservoir-engineering
 
01. drilling rig sistem tenaga power system ok
01. drilling rig sistem tenaga  power system ok01. drilling rig sistem tenaga  power system ok
01. drilling rig sistem tenaga power system ok
 
Peralatan Produksi Lepas Pantai (Offshore Production Facility)
Peralatan Produksi Lepas Pantai (Offshore Production Facility)Peralatan Produksi Lepas Pantai (Offshore Production Facility)
Peralatan Produksi Lepas Pantai (Offshore Production Facility)
 
Teknik Produksi Migas - Teknik Reservoir dan Cadangan Migas
Teknik Produksi Migas  - Teknik Reservoir dan Cadangan MigasTeknik Produksi Migas  - Teknik Reservoir dan Cadangan Migas
Teknik Produksi Migas - Teknik Reservoir dan Cadangan Migas
 
Buku pintar migas indonesia
Buku pintar migas indonesiaBuku pintar migas indonesia
Buku pintar migas indonesia
 
Q922+de1+l02 v1
Q922+de1+l02 v1Q922+de1+l02 v1
Q922+de1+l02 v1
 
Rotary System
Rotary SystemRotary System
Rotary System
 
Dasar Dasar Teknik Pengeboran
Dasar Dasar Teknik PengeboranDasar Dasar Teknik Pengeboran
Dasar Dasar Teknik Pengeboran
 
Lumpur dan Hidrolika Lumpur Pengeboran
Lumpur dan Hidrolika Lumpur PengeboranLumpur dan Hidrolika Lumpur Pengeboran
Lumpur dan Hidrolika Lumpur Pengeboran
 
Teknik Produksi Migas
Teknik Produksi Migas Teknik Produksi Migas
Teknik Produksi Migas
 

Similaire à GEOTHERMAL INDONESIA 2014

New and renewable energy policy and investment in thailand 05-jun-13
New and renewable energy policy and investment in thailand 05-jun-13New and renewable energy policy and investment in thailand 05-jun-13
New and renewable energy policy and investment in thailand 05-jun-13Peerasak C.
 
Prospect of Developments of the Clean Energy in Indonesia
Prospect of Developments of the Clean Energy in IndonesiaProspect of Developments of the Clean Energy in Indonesia
Prospect of Developments of the Clean Energy in IndonesiaBadariahYosiyana
 
Ace acdis jakarta, 9 july 2012
Ace acdis jakarta, 9 july 2012Ace acdis jakarta, 9 july 2012
Ace acdis jakarta, 9 july 2012benisuryadi
 
1_Geothermal_Development_in_Indonesia (2)
1_Geothermal_Development_in_Indonesia (2)1_Geothermal_Development_in_Indonesia (2)
1_Geothermal_Development_in_Indonesia (2)Frank Mercado
 
Energy generation report. final 10 oct 14pptx...Philippine Energy Plan 2012 -...
Energy generation report. final 10 oct 14pptx...Philippine Energy Plan 2012 -...Energy generation report. final 10 oct 14pptx...Philippine Energy Plan 2012 -...
Energy generation report. final 10 oct 14pptx...Philippine Energy Plan 2012 -...alex regado
 
#MP2013 Presentation of the MInister of Power
#MP2013  Presentation of the MInister of Power#MP2013  Presentation of the MInister of Power
#MP2013 Presentation of the MInister of PowerFMINigeria
 
A Presentaion from the Ministry of Power
A  Presentaion from the Ministry of PowerA  Presentaion from the Ministry of Power
A Presentaion from the Ministry of PowerNigeria Centenary
 
Ministry of Power
Ministry of PowerMinistry of Power
Ministry of PowerTransformNG
 
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEF
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEFRenewable Energy status and road-map of Bangladesh and support of UNDP-GEF
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEFDr. Md. Taibur Rahman
 
Sustainable development model of geothermal energy
Sustainable development model of geothermal energySustainable development model of geothermal energy
Sustainable development model of geothermal energyAlexander Decker
 
CPWF Lao Launch Workshop: Presentation by Ministry of Energy and Mines
CPWF Lao Launch Workshop: Presentation by Ministry of Energy and MinesCPWF Lao Launch Workshop: Presentation by Ministry of Energy and Mines
CPWF Lao Launch Workshop: Presentation by Ministry of Energy and MinesCPWF Mekong
 
At a Glace on Renewable Energy (June 2014)
At a Glace on Renewable Energy (June 2014)At a Glace on Renewable Energy (June 2014)
At a Glace on Renewable Energy (June 2014)DepEd-Bataan
 
Indonesia ina002 1366765311
Indonesia ina002 1366765311Indonesia ina002 1366765311
Indonesia ina002 1366765311Nurul Yakin
 
Present energy situation in Bangladesh
Present energy situation in BangladeshPresent energy situation in Bangladesh
Present energy situation in BangladeshKhairul Bashar
 
05.02.2015, Promoting and Advocating Wind Energy in Mongolia, Mr. Achitsan B.
05.02.2015,  Promoting and Advocating Wind Energy in Mongolia, Mr. Achitsan B.05.02.2015,  Promoting and Advocating Wind Energy in Mongolia, Mr. Achitsan B.
05.02.2015, Promoting and Advocating Wind Energy in Mongolia, Mr. Achitsan B.The Business Council of Mongolia
 
Session 2 Dr Ziad Jibril Sabra, Jordan
Session 2 Dr Ziad Jibril Sabra, JordanSession 2 Dr Ziad Jibril Sabra, Jordan
Session 2 Dr Ziad Jibril Sabra, JordanOECDGlobalRelations
 
Iceland Capstone Project
Iceland Capstone ProjectIceland Capstone Project
Iceland Capstone ProjectDaniel Liu
 
Low carbon technology implementation status on bioenergy in indonesia bioenergy
Low carbon technology implementation status on bioenergy in indonesia bioenergyLow carbon technology implementation status on bioenergy in indonesia bioenergy
Low carbon technology implementation status on bioenergy in indonesia bioenergyDewan Nasional Perubahan Iklim
 

Similaire à GEOTHERMAL INDONESIA 2014 (20)

New and renewable energy policy and investment in thailand 05-jun-13
New and renewable energy policy and investment in thailand 05-jun-13New and renewable energy policy and investment in thailand 05-jun-13
New and renewable energy policy and investment in thailand 05-jun-13
 
Prospect of Developments of the Clean Energy in Indonesia
Prospect of Developments of the Clean Energy in IndonesiaProspect of Developments of the Clean Energy in Indonesia
Prospect of Developments of the Clean Energy in Indonesia
 
Indonesia
IndonesiaIndonesia
Indonesia
 
Ace acdis jakarta, 9 july 2012
Ace acdis jakarta, 9 july 2012Ace acdis jakarta, 9 july 2012
Ace acdis jakarta, 9 july 2012
 
Bhutan Country Presentation at ACEF 2014
Bhutan Country Presentation at ACEF 2014Bhutan Country Presentation at ACEF 2014
Bhutan Country Presentation at ACEF 2014
 
1_Geothermal_Development_in_Indonesia (2)
1_Geothermal_Development_in_Indonesia (2)1_Geothermal_Development_in_Indonesia (2)
1_Geothermal_Development_in_Indonesia (2)
 
Energy generation report. final 10 oct 14pptx...Philippine Energy Plan 2012 -...
Energy generation report. final 10 oct 14pptx...Philippine Energy Plan 2012 -...Energy generation report. final 10 oct 14pptx...Philippine Energy Plan 2012 -...
Energy generation report. final 10 oct 14pptx...Philippine Energy Plan 2012 -...
 
#MP2013 Presentation of the MInister of Power
#MP2013  Presentation of the MInister of Power#MP2013  Presentation of the MInister of Power
#MP2013 Presentation of the MInister of Power
 
A Presentaion from the Ministry of Power
A  Presentaion from the Ministry of PowerA  Presentaion from the Ministry of Power
A Presentaion from the Ministry of Power
 
Ministry of Power
Ministry of PowerMinistry of Power
Ministry of Power
 
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEF
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEFRenewable Energy status and road-map of Bangladesh and support of UNDP-GEF
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEF
 
Sustainable development model of geothermal energy
Sustainable development model of geothermal energySustainable development model of geothermal energy
Sustainable development model of geothermal energy
 
CPWF Lao Launch Workshop: Presentation by Ministry of Energy and Mines
CPWF Lao Launch Workshop: Presentation by Ministry of Energy and MinesCPWF Lao Launch Workshop: Presentation by Ministry of Energy and Mines
CPWF Lao Launch Workshop: Presentation by Ministry of Energy and Mines
 
At a Glace on Renewable Energy (June 2014)
At a Glace on Renewable Energy (June 2014)At a Glace on Renewable Energy (June 2014)
At a Glace on Renewable Energy (June 2014)
 
Indonesia ina002 1366765311
Indonesia ina002 1366765311Indonesia ina002 1366765311
Indonesia ina002 1366765311
 
Present energy situation in Bangladesh
Present energy situation in BangladeshPresent energy situation in Bangladesh
Present energy situation in Bangladesh
 
05.02.2015, Promoting and Advocating Wind Energy in Mongolia, Mr. Achitsan B.
05.02.2015,  Promoting and Advocating Wind Energy in Mongolia, Mr. Achitsan B.05.02.2015,  Promoting and Advocating Wind Energy in Mongolia, Mr. Achitsan B.
05.02.2015, Promoting and Advocating Wind Energy in Mongolia, Mr. Achitsan B.
 
Session 2 Dr Ziad Jibril Sabra, Jordan
Session 2 Dr Ziad Jibril Sabra, JordanSession 2 Dr Ziad Jibril Sabra, Jordan
Session 2 Dr Ziad Jibril Sabra, Jordan
 
Iceland Capstone Project
Iceland Capstone ProjectIceland Capstone Project
Iceland Capstone Project
 
Low carbon technology implementation status on bioenergy in indonesia bioenergy
Low carbon technology implementation status on bioenergy in indonesia bioenergyLow carbon technology implementation status on bioenergy in indonesia bioenergy
Low carbon technology implementation status on bioenergy in indonesia bioenergy
 

GEOTHERMAL INDONESIA 2014

  • 1. Energy and Mineral Resources for People’s Prosperity MINISTRY OF ENERGY AND MINERAL RESOURCES DIRECTORATE GENERAL OF NEW, RENEWABLE ENERGY AND ENERGY CONSERVATION by: Sjaiful Ruchijat Directorate of Geothermal APERC Annual Conference 2014 Tokyo, March 27, 2014
  • 2. Energy and Mineral Resources for People’s Prosperity I. BACKGROUND II. GEOTHERMAL POTENTIAL AND DEVELOPMENT IN INDONESIA III. GEOTHERMAL POLICIES IV. BARRIERS AND SOLUTIONS IN GEOTHERMAL DEVELOPMENT V. INVESTMENT OPPORTUNITIES
  • 3. Energy and Mineral Resources for People’s Prosperity I. BACKGROUND
  • 4. Energy and Mineral Resources for People’s Prosperity  Indonesia’s geothermal potential is approximately 28.6 GW which distributed in 299 locations along the country, yet its utilization has only reached 1,3 GW or equal as 4,5%;  National Energy Policy encourage development of renewable energy by 23 % in year 2025. Geothermal is expected to contribute 7,12% or equal to 7,210 MW as mentioned in the national electricity system;  To support utilization of geothermal energy, the Government of Indonesia (GoI) has issued Crash Program Phase II to accelerate 10.000 MW electricity development that derived from geothermal power plant (4,965 MW) as mandated in the Ministry of Energy and Mineral Resources Regulation No. 21/2013;  Achieving the proposed 4,965 MW new geothermal capacity would automatically lead Indonesia to the single largest CO2 mitigation program in the world. The proposed program will reduce in the period of 2010 – 2025 over 400 million tCO2. BACKGROUND
  • 5. Energy and Mineral Resources for People’s Prosperity II. GEOTHERMAL POTENTIAL AND DEVELOPMENT IN INDONESIA
  • 6. Energy and Mineral Resources for People’s Prosperity GEOTHERMAL POTENTIAL MAP Note: Installed Ready to be developed Detail Survey Preliminary Survey No Island Number of Location Total Installed 1 Sumatera 90 12.760 122 2 Java 71 9.717 1.134 3 Bali-Nusa Tenggara 28 1.805 5 4 Kalimantan 12 145 5 Sulawesi 65 3.044 80 6 Maluku 30 1.071 7 Papua 3 75 Total 299 28.617 1.341 Source: Geological Agency, MEMR (2011)
  • 7. Energy and Mineral Resources for People’s Prosperity No Island Number of Location Potential Energy (Mwe) Total InstalledResources Reserve Speculative Hypothetical Possible Probable Proven 1 Sumatera 90 3089 2427 6849 15 380 12760 122 2 Java 71 1710 1826 3708 658 1815 9717 1134 3 Bali-Nusa Tenggara 28 360 417 1013 0 15 1805 5 4 Kalimantan 12 145 0 0 0 0 145 5 Sulawesi 65 1323 119 1374 150 78 3044 80 6 Maluku 30 545 97 429 0 0 1071 7 Papua 3 75 0 0 0 0 75 Total 299 7247 4886 13373 823 2288 28617 1.341 12.133 16.484 28.617 DISTRIBUTION OF GEOTHERMAL POTENTIAL Source : Geological Agency, MEMR Status : December 2012
  • 8. Energy and Mineral Resources for People’s Prosperity ACEH 2 WKP  Jaboi: 70 MW  Seulawah Agam: 130 MW NORTH SUMATERA 5 WKP  Sibayak – Sinabung: 130 MW  Sibual – Buali: 750 MW  Sipaholon Ria-ria: 75 MW  Sorik Marapi: 200 MW  Simbolon Samosir : 155 MW JAMBI 1 WKP  Sungai Penuh: 70 MW SOUTH SUMATERA 2 WKP  Lumut Balai: 250 MW  Rantau Dedap: 106 MW BANTEN 2 WKP  Kaldera Danau Banten: 115 MW  G. Endut: 80 MW WEST SUMATERA 4 WKP  Bukit Kili: 83 MW  Gn Talang: 35 MW  Liki Pinangawan: 400 MW  Bonjol: 200 MW LAMPUNG 4 WKP  Gn.Rajabasa: 91 MW  Suoh Sekincau: 230 MW  Waypanas – Ulubelu: 556 MW  Way Ratai :105 MW CENTRAL JAVA 5 WKP  Baturaden: 175 MW  Dataran Tinggi Dieng: 780 MW  Guci: 79 MW  Gn. Ungaran: 100 MW  Umbul Telomoyo : 72 MW EAST JAVA 3 WKP  Blawan – Ijen: 270 MW  Gn. Iyang Argopuro: 295 MW  Telaga Ngebel: 120 MW BALI 1 WKP  Tabanan: 276 MW WEST NUSA TENGGARA 2 WKP  Hu'u Daha: 65 MW  Sembalun : 100 MW EAST NUSA TENGGARA 5 WKP  Atadei: 40 MW  Sokoria: 30 MW  Ulumbu: 199 MW  Mataloko: 63 MW  Oka Ile Ange : 40 MW MALUKU 1 WKP  Tulehu: 100 MW NORTH MALUKU 2 WKP  Jailolo: 75 MW  Songa Wayaua: 140 MW NORTH SULAWESI 2 WKP  Kotamobagu: 410 MW  Lahendong-Tompaso: 358 MW GORONTALO 1 WKP  Suwawa: 110 MW CENTRAL SULAWESI 2 WKP  Marana: 35 MW  Bora Pulu : 152 MW Total : 58 GWAs BENGKULU 2 WKP  Tmbg Sawah-Hululais: 873 MW  Kepahiyang : 180 MW SOUTH SUMATERA & LAMPUNG 1 WKP  Danau Ranau: 210 MW Lisence – Issued : 39 GWAs Tender on Progress : 2 GWAs Tender Preparation : 13 GWAs Tender – Failed : 5 GWAs Distribution of Geothermal Working Area (GWA) CENTRAL JAVA & EAST JAVA 1 WKP  Gunung Lawu : 195 MW WEST JAVA 10 WKP Ciater - Tgkban Perahu: 60 MW Cibeureum–Parabakti: 485 MW Cibuni: 140 MW Cisolok Cisukarame: 45 MW Gn. Tampomas: 50 MW Gn. Tgkuban Perahu: 100 MW Kamojang-Darajat: 1465 MW Karaha Cakrabuana: 725 MW Pangalengan: 1106 MW G. Ciremai: 150 MW
  • 9. Energy and Mineral Resources for People’s Prosperity INSTALLED GEOTHERMAL POWER PLANT CAPACITY BY JANUARY 2014 Kamojang: 200 MW Salak: 377 MWDarajat: 270 MW Wayang Windu: 227 MW Lahendong: 80 MW Sibayak: 12 MW Ulubelu: 110 MW Dieng: 60 MW Ulumbu: 5 MW TOTAL 1.341 MW
  • 10. Energy and Mineral Resources for People’s Prosperity III. GEOTHERMAL POLICIES
  • 11. Energy and Mineral Resources for People’s Prosperity  Relating to geothermal utilization, there are three cores of regulation: 1) Law 27 Year 2003 on Geothermal: The Law is the basic guidance for geothermal development in Indonesia 2) Government Regulation No. 59/2007 on Geothermal Business Activity: This regulation consists of particular provisions in the area of geothermal business activity 3) Ministerial Regulation No. 11/2009 on Guidance for the Implementation of Geothermal Business Activity: Regulates the geothermal tender and supervision, as well as stages in geothermal business activity  According to the Law 27 Year 2003 on Geothermal, there are 5 (five) stages in utilizing geothermal energy: Preliminary Survey → Exploration → Feasibility Study → Exploitation → Utilization GEOTHERMAL BUSINESS STAGES
  • 12. Energy and Mineral Resources for People’s Prosperity The tender winner could initiate geothermal activities after obtaining Geothermal Businness Permit (IUP). The authority issuing the Permit depends on the location where the GWA is located. Geothermal Working Area (GWA) Determined by the Minister of Energy and Mineral Resources Offered by the government or local governments within their authority through the tender mechanism
  • 13. Energy and Mineral Resources for People’s Prosperity  Fiscal Incentives policies: 1) Income Tax Article 21 2) Taxes and duties on imported goods - Duty exemption (for exploration and exploitation activities) - Free of Value Added Tax (VAT), Luxury Goods Sales Tax (LGST) and Income Tax – based on Minister of Finance Regulations No. 27/2012 and No. 70/2013  Other policies including: accelerating the tender process of new GWAs, building the "public awareness" on the utilization of geothermal as green and environmentally friendly energy Tax Holiday Tax Allowance 1. An exemption from corporate income tax for 5 to 10 years 2. A two-year, 50% reduction in corporate income tax 1. Reducing net taxable income to 30% of the total investment value, carried over six years 2. Accelerated depreciation and amortization 3. Impose income tax of 10% for dividends 4. Loss carry forward of at least 5 years and up to 10 years
  • 14. Energy and Mineral Resources for People’s Prosperity  Pricing policies previously set by the government does not provide a significant impact on geothermal development. It is considered that they are not taking into account some crucial aspects such as location, generation capacity, transmission, escalation, assignment mechanisms and reservoir quality .  Therefore, the government is currently developing a comprehensive pricing structure which includes upstream and downstream sides. No. Generation Capacity Ceiling Price for Geothermal Power (cent US$/kWh) 1. > 55 MW 10,5 2. > 20 MW - 55 MW 12,5 3. > 10 MW - 20 MW 15,5 4. ≤ 10 MW 19,0 PROPOSED CEILING PRICES FOR GEOTHERMAL POWER
  • 15. Energy and Mineral Resources for People’s Prosperity IV. BARRIERS AND SOLUTIONS IN GEOTHERMAL DEVELOPMENT
  • 16. Energy and Mineral Resources for People’s Prosperity 1. Overlapping Areas with Forestry: most of geothermal potentials are located within the forestry area (15% in conservation forest, 18% in protected forest) Solution: Ministry of Energy and Mineral Resources (MEMR) and Ministry of Forestry (MF) have signed the MoU No. 7662/05/MEM.S/2011 to accelerate the geothermal utilization permit within the area of protected, production and conservation forest. 2. Legal Uncertainty: disharmony in geothermal business regulations Solution: improvement and harmonization of regulations in Geothermal Business are as follows:  Draft on Geothermal Law is currently being discussed by the Special Committee of the House of Representatives  Second amendment of the Government Regulation No. 59/2007 soon will be issued  Revision of Minister of Energy and Mineral Resources Regulation No. 11/2009 on Guidance for the Implementation of Geothermal Business Activity  Improvement of Minister of Energy and Mineral Resources Regulation No. 22/2012 relating to electricity price from geothermal energy, through the ceiling price mechanism BARRIERS AND SOLUTIONS IN GEOTHERMAL DEVELOPMENT (1/2)
  • 17. Energy and Mineral Resources for People’s Prosperity 3. Geothermal Price: competitiveness of geothermal energy price Solution: develop a new pricing structure that meets economic value 4. Funding: high investment cost and unbankable project Solution: - Provides financial support and Government guarantee - Government guarantees on the feasibility of PT. PLN (buyer) - Provides “Geothermal Fund" for geothermal exploration 5. Bidding Process Solution: the policies regulate bidding process are being revised in order to make the tender process simpler, more transparent and bankable 6. Shortage of Competent Human Resources Solution: create training, short courses and advanced level education in collaboration with local and international educational institutions 7. Others • Absence of Technology and Research & Development Supports • Low Environmental Awareness • Continuing Subsidy of Fossil Fuel Price BARRIERS AND SOLUTIONS IN GEOTHERMAL DEVELOPMENT (2/2)
  • 18. Energy and Mineral Resources for People’s Prosperity V. INVESTMENT OPPORTUNITIES
  • 19. Energy and Mineral Resources for People’s Prosperity 1. Development of 4,965 MW electricity from Geothermal in 10,000 MW Crash Program Phase II requires more than US$ 15 billions for the investment. 2. To achieve the targets, international supports are needed in terms of finance, technology, human resources and Technical Assistance. 3. Foreign ownership in Geothermal Business is allowed up to 95 %. 4. Access to Potential Geothermal Resources for Investors: a) Preliminary Survey Assignment b) Participate in the geothermal business through GWAs tendering mechanis 5. Other business opportunities in geothermal sector: a) Geothermal direct use b) Low temperature geothermal potential c) Small scale power plant d) Services company to support the core business of geothermal INVESTMENT OPPORTUNITIES
  • 20. Energy and Mineral Resources for People’s Prosperity ` Go Green Indonesia ! Geothermal, Energy Solution for Better Future www.ebtke.esdm.go.id www.indogeothermal.or.id Jalan Pegangsaan Timur No. 1 Menteng - Jakarta 10320 MINISTRY OF ENERGY AND MINERAL RESOURCES DIRECTORATE GENERAL OF NEW RENEWABLE ENERGY AND ENERGY CONSERVATION THANK YOU