SlideShare une entreprise Scribd logo
1  sur  5
Télécharger pour lire hors ligne
The Work Breakdown Structure -
   Lack of a Good One Sets Your
      Project Up For Failure
                                       Ed Kozak


                                              the trained eye, all too often the finished
The Work Breakdown Structure, or              version of a WBS isn’t worth the time,
                                              effort, or cost spent to put it together in
WBS as it’s more commonly referred to,
is one of the most valuable instruments       the first place. Many a project manager
that a project team can have, yet             who has been given a WBS prepared by
paradoxically, it’s often the most            someone else has had no choice but to
overlooked      or     poorly-constructed     draft a new one from the very beginning.
document in a project’s file. The WBS         This very simple rule should be followed
is the backbone of any project. It            when creating a WBS, if you’re going to
contains information from which many          do one (and as a project manager you
important project tools are derived. For      always should be the one drafting it)
example, we derive the network diagram        make sure it’s complete and properly put
from the WBS and that enables us to           together so it doesn’t have to be re-
generate our project schedule. We must        drafted from scratch. The four steps in
rely on the WBS when developing our           this paper along with some rules of
resource loading and constructing our         thumb will help you create the strongest
resource allocation matrix. We use the        backbone for your project possible.
WBS when performing a bottom-up
estimation of the project budget and it’s     Any WBS should be viewed as a
used as an input for our risk                 roadmap, a set of directions that a
management plan. Hence, the omission          reasonably competent person at your
of a task from our WBS—whether from           company could follow to manage the
a complete misstep in identifying a piece     lifecycle of the project from its
of the work to be performed or worse,         initialization to its completion. It should
and unfortunately more common,                be descriptive, not vague; it should list
because one of the authors of the WBS         out the steps down to the smallest level
took some short-cuts—can impact               for another project manager (who may
schedule, cost, resource planning, and        be very competent but not have the same
risk management. Unfortunately, many          technical level of expertise as the
people who create work breakdown              drafter) to follow. If six steps are
schedules, such as department managers,       needed to complete a task then all six
project managers, or the people that they     must be listed and not two or three.
delegate this duty to, do far worse than      Anyone who assumes that “everyone
make simple mistakes of omission. To          knows what steps are required to
complete the task” is setting the task—                 each phase or stage should have a
and the project—up for failure. This is a               deliverable associated with it.
lazy mentality and it will create
problems for you—problems that have a                   Step 2: Select a deliverable. Using the
financial repercussion.                                 deliverable as a heading, name all of the
                                                        tasks required to create the deliverable
                                                        underneath that heading. Good practice
The 4 Basic Steps                                       is to make the heading a complete
                                                        descriptive sentence. So, if a prototype
Whether you’re planning a three-week                    were to be a deliverable on your project
or a three-year project, these four basic               then you certainly don’t want to use the
steps will make the difference between a                heading “Prototype” as the name of the
WBS that will have to be re-drafted (or                 heading. Instead, use something more
the very likely probability that the                    descriptive like “Create Prototype of
project will have some financial                        User Interface For Client Review”. Why
repercussion) and one that’s being                      go through this effort? It is necessary
planned for success.                                    for the simple fact that many project
                                                        managers start projects but don’t see
Step 1: List all major deliverables and                 them through to their end. A project
the     high-level    tasks    specifically             manager might start planning a project
mentioned or gleaned from the scope                     but then something else enters the
description.     On a side note, the                    pipeline that needs his or her expertise
description of the scope should be clear                and so the initial project is handed off to
enough to let everyone know—project                     another project manager to manage.
team, project manager, and client (even                 Thus, the task heading should tell the
if the client happens to be someone from                future reader what exactly the tasks
your own company)—what is to be                         directly underneath it will be used to
accomplished in the project. It should                  accomplish. It terms of the WBS, this
delineate both what is considered to be a               descriptive heading is known as a
part of the project and what is out of                  Summary Task.           As an example,
scope, that is, not considered to be part               consider the development of a user
of the project. It’s important to consider              interface. Some tasks associated with
intermediate deliverables as well as end                creating a user interface might be
deliverables. Intermediate deliverables                 Interviewing the client to determine
usually consist of prototypes, samples,                 what the look and the functionality
and reports but they can be anything                    might be, Creating a pictorial mock-up
specific to your company, your industry,                of the interface in Paint or some other
and/or your client that will allow a                    graphics package for the user to see and
decision to be made or that will                        approve, and Creating a software version
communicate the status of the project.                  of     the    interface     with     limited
The scope statement should also specify                 functionality. The portion of the WBS
whether the project will be performed in                that specifies this might look like:
phases or stages. List those out. This
gives you more information because

3.0 Create Prototype of User Interface For Client Review and Approval
The Work Breakdown Structure And Why It Should Be Mandatory For Any Project                           2
© Successful Projects For Leaders. No portion of this document may be copied or distributed without
the expressed written consent of the author.
3.1 Conduct Client Interviews
  3.2 Create User Interface Requirements Document
  3.3 Secure Client Approval of User Interface Requirements Document
  3.4 Create Rough Graphical Design
  3.5 Secure Client Approval of Rough Design
  3.6 Create Limited Functionality Interface
  3.7 Secure Client Approval of User Interface

On a different note, you might be                       floor, the user would eyeing the color of
wondering why the interface at this point               the car, sitting in the vehicle, checking
has only limited functionality. Whatever                for headroom, looking at the dashboard
software is going to be used, whether it                and console, and checking the legroom
be a commercial package that has been                   but not taking the car for a test drive yet.
bought or something customized and
developed on the project, that software                 Step 3: Break down each task under the
will provide the functionality and it will              Summary Task into the smaller tasks—
take some effort to add or build that                   as many tasks as necessary for another
functionality. At this point in the project             project manager to fully follow the
we’re only concerned with the end-                      process. This not only provides the basis
user’s opinion of the look and feel of the              for budget estimating but also a checklist
interface—are all of the buttons there                  for monitoring and controlling the
that the user needs to click on, do the                 project once it’s been started. Some
drop-down menus list all of the                         items were left out of the WBS above
necessary elements, are all of the                      because I felt their place was at a lower
buttons, photos, and other elements                     level. Let’s look at it again:
positioned as the user envisioned? If the
interface were an auto on a showroom

3.0 Create Prototype of User Interface For Client Review and Approval
 3.1 Conduct Client Interviews
   3.1.1 Determine Client Needs for Data Elements
   3.12 Determine Client Needs for Logos, Compliance, Aesthetics, etc.
 3.2 Create User Interface Requirements Document
 3.3 Secure Client Approval of User Interface Requirements Document
   3.3.1 Review User Interface Requirements Doc With Client
   3.3.2 Make Necessary Revisions Conduct Follow-Up Reviews.
   3.3.3 Provide Client With Screen Shots of User Interface Samples
   3.3.4 Obtain Client Sign-Off On User Interface Requirements Doc.
 3.4 Create Rough Graphical Design
 3.5 Secure Client Approval of Rough Design
 3.6 Create Limited Functionality Interface
 3.7 Secure Client Approval of User Interface

For the sake of brevity of this paper,             Create Limited Functionality Interface,
sub-tasks (otherwise known as work                 but they certainly should be present in
packages) have been left out of Item 3.6,          the WBS. Regarding Items 3.4 and 3.5,
The Work Breakdown Structure And Why It Should Be Mandatory For Any Project              3
© Successful Projects For Leaders. No portion of this document may be copied or distributed without
the expressed written consent of the author.
it would be pointless and a waste of time               project team requires some piece of data
to break then down to finer detail                      from the client is also an interface. So to
because one doesn’t need to instruct (nor               is the point where the team requires
micro-manage) a skilled graphics person                 client or Management approval on some
how to create a rough design in some                    item in order to proceed. This simple
graphics package nor the project                        bookkeeping activity will ensure that
manager how to obtain client approval.                  that task gets transferred to the project
                                                        schedule as a task with a duration and
Step 4: Rearrange the tasks and work                    not as a simple milestone. All too often
packages under each summary task so                     the simplest thing like waiting for
that there is a logical flow in them to                 approval can hold up a project and cause
perform the summary task. Rearrange                     the schedule to slip. Making this a task
the summary tasks so that there is a                    with a duration serves as a reminder to
logical flow in them to perform the                     the project manager to set the
project. Ensure that the task headings                  expectation that if approval isn’t
are meaningful and that there is a                      received by its specified return date then
balance between having enough tasks                     the schedule will (or might, whichever
and work packages to provide enough                     the case) be delayed. Lastly, be sure to
detail without overkill.                                get a WBS from your subcontractors, no
                                                        matter how much they might push back.
                                                        Without one in place the project
Criteria For A Successful WBS                           manager will not be able to completely
                                                        assess the project risk (e.g. is the
Always remember that a WBS must be                      subcontractors’ work well-planned out
broken out from the top down. Work                      or not?) nor properly track the
packages must add up to yield the task                  subcontractor’s progress during the
they’re under; tasks must add up to yield               project.
the summary task they’re under;
summary tasks must add up to yield the
project results. Any activity that will
incur a cost on the project must be listed
                                                        It’s somewhat understandable that a
                                                        WBS might be viewed by some project
in the WBS. This means that Project                     managers as a waste of time or
Management itself and all oversight                     something that’s an administrative
activities must have their place in the                 assistant duty, after all, many project
WBS—oftentimes this is not the case.                    managers are technical and by nature
Since the WBS is used to create the                     might      view      such     duties    as
project schedule remember to always                     “bookkeeping” duties that keep them
include a work package to represent any                 from performing their technical jobs.
interface. An interface is defined as any               This attitude is completely wrong and
activity that results in the flow of                    should never be tolerated at any
information from one set of project                     organization. The WBS truly is the
stakeholders to another.        The point               backbone of any project and the ability
where one task ends and another begins                  of the project to successfully stand on its
is an interface and this is represented by              own depends on how well-crafted WBS
the successive listing of tasks in the                  is. With this single document having
WBS. However, a point where the
The Work Breakdown Structure And Why It Should Be Mandatory For Any Project                           4
© Successful Projects For Leaders. No portion of this document may be copied or distributed without
the expressed written consent of the author.
such an impact on cost, schedule, and                   A third benefit that Successful Projects
risk one can see that a top-down                        For Leaders offers is their availability to
approach stressing the importance of                    be out-sourced by Organizations to serve
having an approved WBS in place prior                   as the Chief Projects Officer. In this
to the onset of any project and the need                role, Successful Projects For Leaders
to follow standardized guidelines to                    only develops standards and practices
construct it must be performed.                         directed at the effective execution of
                                                        projects and the attainment of schedule,
                                                        cost, scope, and quality objectives, but
About the Author                                        also communicates enterprise-level
                                                        objectives to the respective project
Ed Kozak, M.S., M.B.A., PMP is the                      groups in the most-appropriate way for
President and CEO of Successful                         them to follow and communicates
Projects For Leaders, international                     project information to Management.
experts in project management process                   This overcomes the problem common to
improvement. The staff of Successful                    many organizations that no connection
Projects For Leaders work with                          between Operations and project groups
companies along three main points of                    exists and no structured, consistent, and
focus.     First, they help companies                   meaningful flow of information between
improve their profitability by cutting                  these two groups occurs, allowing
wasteful project costs (upwards to 50%                  Management to determine if efforts are
or more) and improve their overall                      efficient and effective, if projects are
management of projects in order to                      still the best ones to support strategic
reduce risk, schedule slippage, and                     objectives,     whether      there      are
unnecessary spending on product                         performance issues associated with
rework. As a result their clients are able              meeting objectives.
to exert more control over their projects;
improve target schedule performance;                    Ed is an accomplished professional with
monitor and control cost performance                    has over twenty-three years experience
better; increase their success at hitting               as a consultant, manager, executive,
budget estimates; improve quality and                   facilitator, and instructor that includes
satisfaction;    and    recognize      the              project/program manager experience in
substantial financial benefits that come                the private and Government sectors
along with that.                                        managing multi-year, multi-million
                                                        dollar programs for his clients in fields
Second, Successful Projects For Leaders                 such as IT, healthcare, research,
is hired as project turnaround experts                  development, and manufacturing. He
and is brought in on critical projects that             brings his expertise to management
are in the midst of schedule, budget,                   teams in strategic planning, process re-
and/or quality issues or projects that are              engineering,     program     management
having continual setbacks. They analyze                 offices, and project management and is a
the problems, set a new budget and                      frequent conference speaker.
schedule, and work with the incumbent
project management team to bring them
to completion.

The Work Breakdown Structure And Why It Should Be Mandatory For Any Project                           5
© Successful Projects For Leaders. No portion of this document may be copied or distributed without
the expressed written consent of the author.

Contenu connexe

Tendances

Wbs, estimation and scheduling
Wbs, estimation and schedulingWbs, estimation and scheduling
Wbs, estimation and schedulingSulman Ahmed
 
WBS presentation
WBS presentationWBS presentation
WBS presentationjpstewar
 
Work Break Down Structure
Work Break Down StructureWork Break Down Structure
Work Break Down StructureSomtel
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Schedulingsslovepk
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?Kenny Hirschmann
 
Using the work breakdown structure to plan a project
Using the work breakdown structure to plan a projectUsing the work breakdown structure to plan a project
Using the work breakdown structure to plan a projectMohieudeen Mohamed
 
project on software industry
project on software industryproject on software industry
project on software industryAamir chouhan
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure pptnazi2020
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structureCOEPD HR
 
Project scheduling and work break down structure(wbs) 12 cs18
Project scheduling and work break down structure(wbs) 12 cs18Project scheduling and work break down structure(wbs) 12 cs18
Project scheduling and work break down structure(wbs) 12 cs18Engr Imran Ashraf
 
Lect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost EstimationLect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost EstimationMubashir Ali
 
How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)Insaf Ali Soomro PMP
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures Ian Cammack
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structureNicola2903
 

Tendances (20)

Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Wbs, estimation and scheduling
Wbs, estimation and schedulingWbs, estimation and scheduling
Wbs, estimation and scheduling
 
WBS presentation
WBS presentationWBS presentation
WBS presentation
 
Work Break Down Structure
Work Break Down StructureWork Break Down Structure
Work Break Down Structure
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
P&msp2010 04 wbs-and-estimation
P&msp2010 04 wbs-and-estimationP&msp2010 04 wbs-and-estimation
P&msp2010 04 wbs-and-estimation
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?
 
Using the work breakdown structure to plan a project
Using the work breakdown structure to plan a projectUsing the work breakdown structure to plan a project
Using the work breakdown structure to plan a project
 
project on software industry
project on software industryproject on software industry
project on software industry
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Wbs
WbsWbs
Wbs
 
Project scheduling and work break down structure(wbs) 12 cs18
Project scheduling and work break down structure(wbs) 12 cs18Project scheduling and work break down structure(wbs) 12 cs18
Project scheduling and work break down structure(wbs) 12 cs18
 
Lect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost EstimationLect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost Estimation
 
How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 

Similaire à The Work Breakdown Structure: Lack Of A Good One Already Sets Your Project Up For Failure

6 Work Breakdown Structure and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docxevonnehoggarth79783
 
CMGT 410 HOMEWORK Education Planning--cmgt410homework.com
CMGT 410 HOMEWORK Education Planning--cmgt410homework.comCMGT 410 HOMEWORK Education Planning--cmgt410homework.com
CMGT 410 HOMEWORK Education Planning--cmgt410homework.comcampfort8
 
CMGT 410 Week 1 Project Plan DraftA project plan is a docume.docx
CMGT 410 Week 1 Project Plan DraftA project plan is a docume.docxCMGT 410 Week 1 Project Plan DraftA project plan is a docume.docx
CMGT 410 Week 1 Project Plan DraftA project plan is a docume.docxmary772
 
Work breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jWork breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jIIT delhi
 
CMGT 410 AID Introduction Education--cmgt410aid.com
CMGT 410 AID Introduction Education--cmgt410aid.comCMGT 410 AID Introduction Education--cmgt410aid.com
CMGT 410 AID Introduction Education--cmgt410aid.comkopiko203
 
CMGT 410 HOMEWORK Your Future Our Mission--cmgt410homework.com
CMGT 410 HOMEWORK Your Future Our Mission--cmgt410homework.comCMGT 410 HOMEWORK Your Future Our Mission--cmgt410homework.com
CMGT 410 HOMEWORK Your Future Our Mission--cmgt410homework.comsrivani507
 
CMGT 410 HOMEWORK Education Counseling--cmgt410homework.com
CMGT 410 HOMEWORK Education Counseling--cmgt410homework.comCMGT 410 HOMEWORK Education Counseling--cmgt410homework.com
CMGT 410 HOMEWORK Education Counseling--cmgt410homework.comKeatonJennings69
 
CMGT 410 HOMEWORK Achievement Education--cmgt410homework.com
CMGT 410 HOMEWORK Achievement Education--cmgt410homework.comCMGT 410 HOMEWORK Achievement Education--cmgt410homework.com
CMGT 410 HOMEWORK Achievement Education--cmgt410homework.comkopiko144
 
CMGT 410 AID Redefined Education--cmgt410aid.com
CMGT 410 AID Redefined Education--cmgt410aid.comCMGT 410 AID Redefined Education--cmgt410aid.com
CMGT 410 AID Redefined Education--cmgt410aid.comkopiko172
 
CMGT 410 AID Become Exceptional--cmgt410aid.com
CMGT 410 AID Become Exceptional--cmgt410aid.comCMGT 410 AID Become Exceptional--cmgt410aid.com
CMGT 410 AID Become Exceptional--cmgt410aid.comkopiko125
 
CMGT 410 AID Education Counseling / cmgt410aid.com
CMGT 410 AID Education Counseling / cmgt410aid.comCMGT 410 AID Education Counseling / cmgt410aid.com
CMGT 410 AID Education Counseling / cmgt410aid.comkopiko73
 
CMGT 410 HOMEWORK Inspiring Innovation--cmgt410homework.com
CMGT 410  HOMEWORK Inspiring Innovation--cmgt410homework.comCMGT 410  HOMEWORK Inspiring Innovation--cmgt410homework.com
CMGT 410 HOMEWORK Inspiring Innovation--cmgt410homework.comsachin10202
 
CMGT 410 HOMEWORK Become Exceptional--cmgt410homework.com
CMGT 410 HOMEWORK Become Exceptional--cmgt410homework.comCMGT 410 HOMEWORK Become Exceptional--cmgt410homework.com
CMGT 410 HOMEWORK Become Exceptional--cmgt410homework.comagathachristie111
 
CMGT 410 HOMEWORK Education Counseling--cmgt410homework.com
CMGT 410 HOMEWORK Education Counseling--cmgt410homework.comCMGT 410 HOMEWORK Education Counseling--cmgt410homework.com
CMGT 410 HOMEWORK Education Counseling--cmgt410homework.comwilliamwordsworth38
 
CMGT 410 HOMEWORK Introduction Education--cmgt410homework.com
CMGT 410 HOMEWORK Introduction Education--cmgt410homework.comCMGT 410 HOMEWORK Introduction Education--cmgt410homework.com
CMGT 410 HOMEWORK Introduction Education--cmgt410homework.comagathachristie264
 
CMGT 410 AID Inspiring Innovation--cmgt410aid.com
CMGT 410 AID Inspiring Innovation--cmgt410aid.comCMGT 410 AID Inspiring Innovation--cmgt410aid.com
CMGT 410 AID Inspiring Innovation--cmgt410aid.comwilliamwordsworth35
 
CMGT 410 AID Achievement Education--cmgt410aid.com
CMGT 410 AID Achievement Education--cmgt410aid.comCMGT 410 AID Achievement Education--cmgt410aid.com
CMGT 410 AID Achievement Education--cmgt410aid.comagathachristie182
 
CMGT 410 Inspiring Innovation -- cmgt410.com
CMGT 410 Inspiring Innovation -- cmgt410.comCMGT 410 Inspiring Innovation -- cmgt410.com
CMGT 410 Inspiring Innovation -- cmgt410.comkopiko105
 
CMGT 410 NEW Imagine Your Future/newtonhelp.com   
CMGT 410 NEW Imagine Your Future/newtonhelp.com   CMGT 410 NEW Imagine Your Future/newtonhelp.com   
CMGT 410 NEW Imagine Your Future/newtonhelp.com   bellflower63
 

Similaire à The Work Breakdown Structure: Lack Of A Good One Already Sets Your Project Up For Failure (20)

6 Work Breakdown Structure and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docx
 
Lab exercise 6
Lab exercise 6Lab exercise 6
Lab exercise 6
 
CMGT 410 HOMEWORK Education Planning--cmgt410homework.com
CMGT 410 HOMEWORK Education Planning--cmgt410homework.comCMGT 410 HOMEWORK Education Planning--cmgt410homework.com
CMGT 410 HOMEWORK Education Planning--cmgt410homework.com
 
CMGT 410 Week 1 Project Plan DraftA project plan is a docume.docx
CMGT 410 Week 1 Project Plan DraftA project plan is a docume.docxCMGT 410 Week 1 Project Plan DraftA project plan is a docume.docx
CMGT 410 Week 1 Project Plan DraftA project plan is a docume.docx
 
Work breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jWork breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran j
 
CMGT 410 AID Introduction Education--cmgt410aid.com
CMGT 410 AID Introduction Education--cmgt410aid.comCMGT 410 AID Introduction Education--cmgt410aid.com
CMGT 410 AID Introduction Education--cmgt410aid.com
 
CMGT 410 HOMEWORK Your Future Our Mission--cmgt410homework.com
CMGT 410 HOMEWORK Your Future Our Mission--cmgt410homework.comCMGT 410 HOMEWORK Your Future Our Mission--cmgt410homework.com
CMGT 410 HOMEWORK Your Future Our Mission--cmgt410homework.com
 
CMGT 410 HOMEWORK Education Counseling--cmgt410homework.com
CMGT 410 HOMEWORK Education Counseling--cmgt410homework.comCMGT 410 HOMEWORK Education Counseling--cmgt410homework.com
CMGT 410 HOMEWORK Education Counseling--cmgt410homework.com
 
CMGT 410 HOMEWORK Achievement Education--cmgt410homework.com
CMGT 410 HOMEWORK Achievement Education--cmgt410homework.comCMGT 410 HOMEWORK Achievement Education--cmgt410homework.com
CMGT 410 HOMEWORK Achievement Education--cmgt410homework.com
 
CMGT 410 AID Redefined Education--cmgt410aid.com
CMGT 410 AID Redefined Education--cmgt410aid.comCMGT 410 AID Redefined Education--cmgt410aid.com
CMGT 410 AID Redefined Education--cmgt410aid.com
 
CMGT 410 AID Become Exceptional--cmgt410aid.com
CMGT 410 AID Become Exceptional--cmgt410aid.comCMGT 410 AID Become Exceptional--cmgt410aid.com
CMGT 410 AID Become Exceptional--cmgt410aid.com
 
CMGT 410 AID Education Counseling / cmgt410aid.com
CMGT 410 AID Education Counseling / cmgt410aid.comCMGT 410 AID Education Counseling / cmgt410aid.com
CMGT 410 AID Education Counseling / cmgt410aid.com
 
CMGT 410 HOMEWORK Inspiring Innovation--cmgt410homework.com
CMGT 410  HOMEWORK Inspiring Innovation--cmgt410homework.comCMGT 410  HOMEWORK Inspiring Innovation--cmgt410homework.com
CMGT 410 HOMEWORK Inspiring Innovation--cmgt410homework.com
 
CMGT 410 HOMEWORK Become Exceptional--cmgt410homework.com
CMGT 410 HOMEWORK Become Exceptional--cmgt410homework.comCMGT 410 HOMEWORK Become Exceptional--cmgt410homework.com
CMGT 410 HOMEWORK Become Exceptional--cmgt410homework.com
 
CMGT 410 HOMEWORK Education Counseling--cmgt410homework.com
CMGT 410 HOMEWORK Education Counseling--cmgt410homework.comCMGT 410 HOMEWORK Education Counseling--cmgt410homework.com
CMGT 410 HOMEWORK Education Counseling--cmgt410homework.com
 
CMGT 410 HOMEWORK Introduction Education--cmgt410homework.com
CMGT 410 HOMEWORK Introduction Education--cmgt410homework.comCMGT 410 HOMEWORK Introduction Education--cmgt410homework.com
CMGT 410 HOMEWORK Introduction Education--cmgt410homework.com
 
CMGT 410 AID Inspiring Innovation--cmgt410aid.com
CMGT 410 AID Inspiring Innovation--cmgt410aid.comCMGT 410 AID Inspiring Innovation--cmgt410aid.com
CMGT 410 AID Inspiring Innovation--cmgt410aid.com
 
CMGT 410 AID Achievement Education--cmgt410aid.com
CMGT 410 AID Achievement Education--cmgt410aid.comCMGT 410 AID Achievement Education--cmgt410aid.com
CMGT 410 AID Achievement Education--cmgt410aid.com
 
CMGT 410 Inspiring Innovation -- cmgt410.com
CMGT 410 Inspiring Innovation -- cmgt410.comCMGT 410 Inspiring Innovation -- cmgt410.com
CMGT 410 Inspiring Innovation -- cmgt410.com
 
CMGT 410 NEW Imagine Your Future/newtonhelp.com   
CMGT 410 NEW Imagine Your Future/newtonhelp.com   CMGT 410 NEW Imagine Your Future/newtonhelp.com   
CMGT 410 NEW Imagine Your Future/newtonhelp.com   
 

Plus de Ed Kozak

Using Project Management to Improve ROI Day 1 Event
Using Project Management to Improve ROI  Day 1 EventUsing Project Management to Improve ROI  Day 1 Event
Using Project Management to Improve ROI Day 1 EventEd Kozak
 
Improvement of Hospital Project Cost and Schedule Mgmt Final Rpt
Improvement of Hospital Project Cost and Schedule Mgmt  Final RptImprovement of Hospital Project Cost and Schedule Mgmt  Final Rpt
Improvement of Hospital Project Cost and Schedule Mgmt Final RptEd Kozak
 
The Chief Project Officer And How One Can Benefit Your Organization
The Chief Project Officer And How One Can Benefit Your OrganizationThe Chief Project Officer And How One Can Benefit Your Organization
The Chief Project Officer And How One Can Benefit Your OrganizationEd Kozak
 
If You Want To Earn More Profits Follow An Established Project Management Met...
If You Want To Earn More Profits Follow An Established Project Management Met...If You Want To Earn More Profits Follow An Established Project Management Met...
If You Want To Earn More Profits Follow An Established Project Management Met...Ed Kozak
 
Your Projects May Be Robbing You Blind
Your Projects May Be Robbing You BlindYour Projects May Be Robbing You Blind
Your Projects May Be Robbing You BlindEd Kozak
 
How Project Management Can Improve Your Profitability
How Project Management Can Improve Your ProfitabilityHow Project Management Can Improve Your Profitability
How Project Management Can Improve Your ProfitabilityEd Kozak
 
Don't Add Risk And Double Investment Requirements By Estimating Project Budge...
Don't Add Risk And Double Investment Requirements By Estimating Project Budge...Don't Add Risk And Double Investment Requirements By Estimating Project Budge...
Don't Add Risk And Double Investment Requirements By Estimating Project Budge...Ed Kozak
 

Plus de Ed Kozak (7)

Using Project Management to Improve ROI Day 1 Event
Using Project Management to Improve ROI  Day 1 EventUsing Project Management to Improve ROI  Day 1 Event
Using Project Management to Improve ROI Day 1 Event
 
Improvement of Hospital Project Cost and Schedule Mgmt Final Rpt
Improvement of Hospital Project Cost and Schedule Mgmt  Final RptImprovement of Hospital Project Cost and Schedule Mgmt  Final Rpt
Improvement of Hospital Project Cost and Schedule Mgmt Final Rpt
 
The Chief Project Officer And How One Can Benefit Your Organization
The Chief Project Officer And How One Can Benefit Your OrganizationThe Chief Project Officer And How One Can Benefit Your Organization
The Chief Project Officer And How One Can Benefit Your Organization
 
If You Want To Earn More Profits Follow An Established Project Management Met...
If You Want To Earn More Profits Follow An Established Project Management Met...If You Want To Earn More Profits Follow An Established Project Management Met...
If You Want To Earn More Profits Follow An Established Project Management Met...
 
Your Projects May Be Robbing You Blind
Your Projects May Be Robbing You BlindYour Projects May Be Robbing You Blind
Your Projects May Be Robbing You Blind
 
How Project Management Can Improve Your Profitability
How Project Management Can Improve Your ProfitabilityHow Project Management Can Improve Your Profitability
How Project Management Can Improve Your Profitability
 
Don't Add Risk And Double Investment Requirements By Estimating Project Budge...
Don't Add Risk And Double Investment Requirements By Estimating Project Budge...Don't Add Risk And Double Investment Requirements By Estimating Project Budge...
Don't Add Risk And Double Investment Requirements By Estimating Project Budge...
 

Dernier

Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfRankYa
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Wonjun Hwang
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsRizwan Syed
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Manik S Magar
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Patryk Bandurski
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsMiki Katsuragi
 
The Future of Software Development - Devin AI Innovative Approach.pdf
The Future of Software Development - Devin AI Innovative Approach.pdfThe Future of Software Development - Devin AI Innovative Approach.pdf
The Future of Software Development - Devin AI Innovative Approach.pdfSeasiaInfotech2
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embeddingZilliz
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyAlfredo García Lavilla
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 

Dernier (20)

Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdf
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL Certs
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering Tips
 
The Future of Software Development - Devin AI Innovative Approach.pdf
The Future of Software Development - Devin AI Innovative Approach.pdfThe Future of Software Development - Devin AI Innovative Approach.pdf
The Future of Software Development - Devin AI Innovative Approach.pdf
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embedding
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easy
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 

The Work Breakdown Structure: Lack Of A Good One Already Sets Your Project Up For Failure

  • 1. The Work Breakdown Structure - Lack of a Good One Sets Your Project Up For Failure Ed Kozak the trained eye, all too often the finished The Work Breakdown Structure, or version of a WBS isn’t worth the time, effort, or cost spent to put it together in WBS as it’s more commonly referred to, is one of the most valuable instruments the first place. Many a project manager that a project team can have, yet who has been given a WBS prepared by paradoxically, it’s often the most someone else has had no choice but to overlooked or poorly-constructed draft a new one from the very beginning. document in a project’s file. The WBS This very simple rule should be followed is the backbone of any project. It when creating a WBS, if you’re going to contains information from which many do one (and as a project manager you important project tools are derived. For always should be the one drafting it) example, we derive the network diagram make sure it’s complete and properly put from the WBS and that enables us to together so it doesn’t have to be re- generate our project schedule. We must drafted from scratch. The four steps in rely on the WBS when developing our this paper along with some rules of resource loading and constructing our thumb will help you create the strongest resource allocation matrix. We use the backbone for your project possible. WBS when performing a bottom-up estimation of the project budget and it’s Any WBS should be viewed as a used as an input for our risk roadmap, a set of directions that a management plan. Hence, the omission reasonably competent person at your of a task from our WBS—whether from company could follow to manage the a complete misstep in identifying a piece lifecycle of the project from its of the work to be performed or worse, initialization to its completion. It should and unfortunately more common, be descriptive, not vague; it should list because one of the authors of the WBS out the steps down to the smallest level took some short-cuts—can impact for another project manager (who may schedule, cost, resource planning, and be very competent but not have the same risk management. Unfortunately, many technical level of expertise as the people who create work breakdown drafter) to follow. If six steps are schedules, such as department managers, needed to complete a task then all six project managers, or the people that they must be listed and not two or three. delegate this duty to, do far worse than Anyone who assumes that “everyone make simple mistakes of omission. To knows what steps are required to
  • 2. complete the task” is setting the task— each phase or stage should have a and the project—up for failure. This is a deliverable associated with it. lazy mentality and it will create problems for you—problems that have a Step 2: Select a deliverable. Using the financial repercussion. deliverable as a heading, name all of the tasks required to create the deliverable underneath that heading. Good practice The 4 Basic Steps is to make the heading a complete descriptive sentence. So, if a prototype Whether you’re planning a three-week were to be a deliverable on your project or a three-year project, these four basic then you certainly don’t want to use the steps will make the difference between a heading “Prototype” as the name of the WBS that will have to be re-drafted (or heading. Instead, use something more the very likely probability that the descriptive like “Create Prototype of project will have some financial User Interface For Client Review”. Why repercussion) and one that’s being go through this effort? It is necessary planned for success. for the simple fact that many project managers start projects but don’t see Step 1: List all major deliverables and them through to their end. A project the high-level tasks specifically manager might start planning a project mentioned or gleaned from the scope but then something else enters the description. On a side note, the pipeline that needs his or her expertise description of the scope should be clear and so the initial project is handed off to enough to let everyone know—project another project manager to manage. team, project manager, and client (even Thus, the task heading should tell the if the client happens to be someone from future reader what exactly the tasks your own company)—what is to be directly underneath it will be used to accomplished in the project. It should accomplish. It terms of the WBS, this delineate both what is considered to be a descriptive heading is known as a part of the project and what is out of Summary Task. As an example, scope, that is, not considered to be part consider the development of a user of the project. It’s important to consider interface. Some tasks associated with intermediate deliverables as well as end creating a user interface might be deliverables. Intermediate deliverables Interviewing the client to determine usually consist of prototypes, samples, what the look and the functionality and reports but they can be anything might be, Creating a pictorial mock-up specific to your company, your industry, of the interface in Paint or some other and/or your client that will allow a graphics package for the user to see and decision to be made or that will approve, and Creating a software version communicate the status of the project. of the interface with limited The scope statement should also specify functionality. The portion of the WBS whether the project will be performed in that specifies this might look like: phases or stages. List those out. This gives you more information because 3.0 Create Prototype of User Interface For Client Review and Approval The Work Breakdown Structure And Why It Should Be Mandatory For Any Project 2 © Successful Projects For Leaders. No portion of this document may be copied or distributed without the expressed written consent of the author.
  • 3. 3.1 Conduct Client Interviews 3.2 Create User Interface Requirements Document 3.3 Secure Client Approval of User Interface Requirements Document 3.4 Create Rough Graphical Design 3.5 Secure Client Approval of Rough Design 3.6 Create Limited Functionality Interface 3.7 Secure Client Approval of User Interface On a different note, you might be floor, the user would eyeing the color of wondering why the interface at this point the car, sitting in the vehicle, checking has only limited functionality. Whatever for headroom, looking at the dashboard software is going to be used, whether it and console, and checking the legroom be a commercial package that has been but not taking the car for a test drive yet. bought or something customized and developed on the project, that software Step 3: Break down each task under the will provide the functionality and it will Summary Task into the smaller tasks— take some effort to add or build that as many tasks as necessary for another functionality. At this point in the project project manager to fully follow the we’re only concerned with the end- process. This not only provides the basis user’s opinion of the look and feel of the for budget estimating but also a checklist interface—are all of the buttons there for monitoring and controlling the that the user needs to click on, do the project once it’s been started. Some drop-down menus list all of the items were left out of the WBS above necessary elements, are all of the because I felt their place was at a lower buttons, photos, and other elements level. Let’s look at it again: positioned as the user envisioned? If the interface were an auto on a showroom 3.0 Create Prototype of User Interface For Client Review and Approval 3.1 Conduct Client Interviews 3.1.1 Determine Client Needs for Data Elements 3.12 Determine Client Needs for Logos, Compliance, Aesthetics, etc. 3.2 Create User Interface Requirements Document 3.3 Secure Client Approval of User Interface Requirements Document 3.3.1 Review User Interface Requirements Doc With Client 3.3.2 Make Necessary Revisions Conduct Follow-Up Reviews. 3.3.3 Provide Client With Screen Shots of User Interface Samples 3.3.4 Obtain Client Sign-Off On User Interface Requirements Doc. 3.4 Create Rough Graphical Design 3.5 Secure Client Approval of Rough Design 3.6 Create Limited Functionality Interface 3.7 Secure Client Approval of User Interface For the sake of brevity of this paper, Create Limited Functionality Interface, sub-tasks (otherwise known as work but they certainly should be present in packages) have been left out of Item 3.6, the WBS. Regarding Items 3.4 and 3.5, The Work Breakdown Structure And Why It Should Be Mandatory For Any Project 3 © Successful Projects For Leaders. No portion of this document may be copied or distributed without the expressed written consent of the author.
  • 4. it would be pointless and a waste of time project team requires some piece of data to break then down to finer detail from the client is also an interface. So to because one doesn’t need to instruct (nor is the point where the team requires micro-manage) a skilled graphics person client or Management approval on some how to create a rough design in some item in order to proceed. This simple graphics package nor the project bookkeeping activity will ensure that manager how to obtain client approval. that task gets transferred to the project schedule as a task with a duration and Step 4: Rearrange the tasks and work not as a simple milestone. All too often packages under each summary task so the simplest thing like waiting for that there is a logical flow in them to approval can hold up a project and cause perform the summary task. Rearrange the schedule to slip. Making this a task the summary tasks so that there is a with a duration serves as a reminder to logical flow in them to perform the the project manager to set the project. Ensure that the task headings expectation that if approval isn’t are meaningful and that there is a received by its specified return date then balance between having enough tasks the schedule will (or might, whichever and work packages to provide enough the case) be delayed. Lastly, be sure to detail without overkill. get a WBS from your subcontractors, no matter how much they might push back. Without one in place the project Criteria For A Successful WBS manager will not be able to completely assess the project risk (e.g. is the Always remember that a WBS must be subcontractors’ work well-planned out broken out from the top down. Work or not?) nor properly track the packages must add up to yield the task subcontractor’s progress during the they’re under; tasks must add up to yield project. the summary task they’re under; summary tasks must add up to yield the project results. Any activity that will incur a cost on the project must be listed It’s somewhat understandable that a WBS might be viewed by some project in the WBS. This means that Project managers as a waste of time or Management itself and all oversight something that’s an administrative activities must have their place in the assistant duty, after all, many project WBS—oftentimes this is not the case. managers are technical and by nature Since the WBS is used to create the might view such duties as project schedule remember to always “bookkeeping” duties that keep them include a work package to represent any from performing their technical jobs. interface. An interface is defined as any This attitude is completely wrong and activity that results in the flow of should never be tolerated at any information from one set of project organization. The WBS truly is the stakeholders to another. The point backbone of any project and the ability where one task ends and another begins of the project to successfully stand on its is an interface and this is represented by own depends on how well-crafted WBS the successive listing of tasks in the is. With this single document having WBS. However, a point where the The Work Breakdown Structure And Why It Should Be Mandatory For Any Project 4 © Successful Projects For Leaders. No portion of this document may be copied or distributed without the expressed written consent of the author.
  • 5. such an impact on cost, schedule, and A third benefit that Successful Projects risk one can see that a top-down For Leaders offers is their availability to approach stressing the importance of be out-sourced by Organizations to serve having an approved WBS in place prior as the Chief Projects Officer. In this to the onset of any project and the need role, Successful Projects For Leaders to follow standardized guidelines to only develops standards and practices construct it must be performed. directed at the effective execution of projects and the attainment of schedule, cost, scope, and quality objectives, but About the Author also communicates enterprise-level objectives to the respective project Ed Kozak, M.S., M.B.A., PMP is the groups in the most-appropriate way for President and CEO of Successful them to follow and communicates Projects For Leaders, international project information to Management. experts in project management process This overcomes the problem common to improvement. The staff of Successful many organizations that no connection Projects For Leaders work with between Operations and project groups companies along three main points of exists and no structured, consistent, and focus. First, they help companies meaningful flow of information between improve their profitability by cutting these two groups occurs, allowing wasteful project costs (upwards to 50% Management to determine if efforts are or more) and improve their overall efficient and effective, if projects are management of projects in order to still the best ones to support strategic reduce risk, schedule slippage, and objectives, whether there are unnecessary spending on product performance issues associated with rework. As a result their clients are able meeting objectives. to exert more control over their projects; improve target schedule performance; Ed is an accomplished professional with monitor and control cost performance has over twenty-three years experience better; increase their success at hitting as a consultant, manager, executive, budget estimates; improve quality and facilitator, and instructor that includes satisfaction; and recognize the project/program manager experience in substantial financial benefits that come the private and Government sectors along with that. managing multi-year, multi-million dollar programs for his clients in fields Second, Successful Projects For Leaders such as IT, healthcare, research, is hired as project turnaround experts development, and manufacturing. He and is brought in on critical projects that brings his expertise to management are in the midst of schedule, budget, teams in strategic planning, process re- and/or quality issues or projects that are engineering, program management having continual setbacks. They analyze offices, and project management and is a the problems, set a new budget and frequent conference speaker. schedule, and work with the incumbent project management team to bring them to completion. The Work Breakdown Structure And Why It Should Be Mandatory For Any Project 5 © Successful Projects For Leaders. No portion of this document may be copied or distributed without the expressed written consent of the author.