SlideShare une entreprise Scribd logo
1  sur  38
Maximizing the Return on
Your Control Investment
       Part 1 of 2
   Meet the Experts Sessions
Presenters


    James Beall



    Terry Blevins
Session Objective

    Provide a roadmap that may be used to maximize the
     return on your control investment
Agenda

    Assessment of control loop utilization and automatic
     control performance,
    Identifying areas where it is possible to justified the
     cost of improving control performance.
    Tools and techniques to achieve best control
     performance. Identifying and correcting field
     problems.
Evaluating Control System Utilization
                           Product quality and
                            manufacturing efficiency
                            may be impacted by
                            variation in key
                            parameters.
                           When production is
                            process limited, then
                            throughput may be
                            increase by reducing
                            process variation and
                            operating closer to the limit.
                           The control must operate
                            as designed to achieve
                            these benefits.
Control Utilization
  Control utilization is an indicator that can be used to
  quickly determine if control and measurement problems
  exist within a control system. Surveys indicate that the
  primary reasons for control not being fully utilized fall
  into two areas:
     Field measurement or control element

     Process or control design
  An immediate improvement in control utilization will be
  achieved by addressing these problems. To achieve full
  utilization, improved communications between
  maintenance and operations is important.
Example – Case Study
At one pulp and paper plant a snapshot of the control utilization was
collected to quantify the state of the process control. This survey showed:

                            Control    Normal
                            Loops      Mode        Utilization
        Bleach Plant         78          60          76%
        Power House         185         130          70%
        Pulp Mill           174         116          66%
        Paper Mill          236         134          56%

 An instrumentation team was formed to investigate loops that were not
running in their normal design mode. This team was responsible for making
sure measurement, control valve, and process problems were addressed in
a timely fashion. The reduction in variability led to significant improvements
in plant throughput and product quality
Example – Another Case Study
At refinery and petrochemical complex a snapshot of the control utilization
was collected to quantify the state of the process control. This survey
showed:

       System                                Loops     Utilization
       PX                                    471       67.3%
       APS&VPS、CLE、Sulfur Recovery           469       59.7%
       Refinery                              478       60.9%
       IGCCAuxiliary Boiler                 946       52.7%
       Ethylene                              1355      77.5%
       FCCU                                  475       48%
       C4                                    164       68.9%
Examining Control Utilization

   Summarizes performance for System
    or by Area, Cell, or Units
   Abnormal Control Conditions
    indicated for Problem Loops:
     – Control Service Status:
        • Not in Normal mode
        • Limited control output
        • Bad/Uncertain input
     – Control Performance Status:
        • Standard Deviation
        • Variability Index
        • Oscillation Index
        • Tuning Index
DeltaV InSight Control Performance Reports
Roadmap to Improved Control
                                         Transmitter Broken/Unreliable   Fix or Replace
                                                                         Transmitter


                              Reason?                                          Tuning
                                        Poor                                   Valve/Actuator Problem
                                                       Investigate
                                        Performance                            Changing Process Gain
                                                                               Process Dynamics
                      No                                                       Loop Interaction

Starting
 Point Control Loop
         in Normal
         Mode?

                        Yes                                                    Use DeltaV Insight
                                                                               to examine loop
                                                                               tuning

  Use DeltaV Insight
  to Determine
  Control Utilization
DeltaV Insight – On-demand Tuning

                               Allows
                                control loop
                                tuning to be
                                quickly
                                established
Examine Tuning Impact
DeltaV InSight - Adaptive Tuning
  Provides Tuning Based on Normal Operator Changes


                                                        InSight automatically
                                                         calculates dynamic
                        Before vs. After
                                                         models from
                                                         operator changes
                                                        Model Quality and
                                                         Learning Status
                                                        Tuning criteria and
                                                         desired speed of
                                                         response
                                                        Tuning
                                                         Recommendation
                                                        No Testing Required
Tips for Using On-Demand Tuning

    Set step size large enough to insure the response to
     the PID output changing is larger that the
     measurement noise and influence of process
     disturbances.
    Select “Integrating” if the process is not self-
     regulating.
    If the process has low or high gain, then selected
     Default Process and set the process type to match
     the expected behavior.
Manual Tuning (Not a DeltaV System)
   When commissioning PID control associated with a self-regulating
    process, this procedure may be quickly applied to both old and new
    control systems to determine the tuning for PI control.
   The size of the step should be just large enough to easily distinguish
    the resulting change in the controlled process output.
Manual Tuning - (Not a DeltaV System)
Alternate
   When commissioning PID control associated with a self-regulating
    process, this procedure may be quickly applied to both old and new
    control systems to determine the tuning for PI control.
   The size of the step should be just large enough to easily distinguish
    the resulting change in the controlled process output.
   Tune as follows:
     – Place the PV and OUT on a trend.
     – Place the controller in Manual and allow the process to reach steady sate.
     – Impose a step change in OUT and observe the response
     – Set the RESET equal to ¼ of the time it takes to “almost” line out (98% of final
       value)
     – Set the GAIN equal to 1/3 of process gain, Kp where
     – Kp = ((Δ%PV) / (Δ%OUT) (Be sure to convert to % of span!)
     – Place the loop in automatic and make small adjustments to the Setpoint and
       observe the response. Adjust ONLY the GAIN to achieve the desired response.
Impact of Sticky Valve
                                                             When a control loop is
                                                              placed in automatic
        Setpoint (SP)
                                                              control, it is easy to
                                                              detect if a valve or
                   Controlled Parameter (PV)
                                                              damper is not
                                                              responding to the
                           Implied Valve Position (OUT)
Value
                                                              control system by
                                                              observing the
                        Stem Position)
                                                              response of the
                                                              controlled parameter
                                                              to control system
                                          Time
                                                              changes in the PID
                                                              output.
                                                             Cycling can not be
                                                              eliminated through
                                                              tuning.
Valve Positioner Recommendation
 The most common problems in commissioning a control system
 can often be traced to the fact that a positioner has not been
 provided with the valve, or the positioner provided with the valve
 has not been properly installed or has malfunctioned.
     – The rule of thumb is that to achieve best control
        performance, all regulating valves should be equipped
        with a positioner.
     – Without a positioner, the control performance that may be
        achieved is very limited when a valve is sticking – which is
        inherent in most valves.
     – The cyclic behavior caused by a sticky valve (with no
        positioner) cannot be eliminated through tuning. Changes in
        tuning will only impact the period of the cycle that develops.
        The only way to eliminate this type of behavior is to install a
        valve positioner.
Installed Characteristics.

                  7000                                               From a control perspective, it is
                                                                      highly desirable that the process
                  6000                                                gain be constant. If the process
                                                                      gain is constant, then the same
                  5000                                                proportional gain may be used
                                                                      over the entire operating range of
Gas Flow (SCFH)




                  4000                                                the control loop.
                                                                     If the valve characteristic was not
                  3000                                                been selected based on the
                                                                      process requirements, then the
                  2000                                                installed characteristic could be
                                                                      non-linear.
                    0
                                                                     As illustrated in this example, the
                         0   20     40            60   80   100
                                  Valve Position (%)
                                                                      process gain varies from 0.5 to 4;
                                                                      that is, the process gain changes
                                                                      by a factor of eight.
Impact of Non-linear Installed Characteristics

   Non-linear Process Example
      Process gain and dynamics may change as a function of
       operating conditions such as valve position or feed rate.
Linearizing Response
                          To compensate for
                           the changes in
                           process gain, a
                           characterizer block
                           may be installed
                           between the PID and
                           Analog Output
                           blocks. Select the
                           option to inverse the
                           calculation done in
                           the forward path for
                           the PID back
                           calculation to allow
                           bumpless transfer.
Characterizer Setup
                                                                                                         The relationship between
                                                                                      Characterizer
                     100                                                               IN    OUT          the primary inputs and the
                                         Linear Relationship                            0      0
                     90
                                         Characterizer In-Out
                                                                                        5      1.5        output of the characterizer
                                                                                       10      3
                     80                                                                15
                                                                                       20
                                                                                               5.5
                                                                                               8,5
                                                                                                          block may be defined by
                     70                                                                25
                                                                                       30
                                                                                              10
                                                                                              11.5
                                                                                                          21 x,y pairs over the final
                     60                                                                35
                                                                                       40
                                                                                              13
                                                                                              17
                                                                                                          control element operating
                     50                                                                45     20
                                                                                                          range.
Process Output (%)




                                                                                       50     22
                     40                                                                55     26

                     30
                                                                                       60
                                                                                       65
                                                                                              31
                                                                                              36
                                                                                                         Input values that fall
                     20
                                                                                       70
                                                                                       75
                                                                                              42
                                                                                              48
                                                                                                          between these points are
                     10
                                                                                       80
                                                                                       85
                                                                                              54
                                                                                              63
                                                                                                          automatically determined
                      0
                                                                                       90
                                                                                       95
                                                                                              74
                                                                                              86          by the characterizer block
                                                                                       100   100
                                                                                                          using linear interpolation.
                                                                                                         The curve defined by the
                                                                                                          characterizer points
                           0   10   20     30   40    50   60    70   80   90   100                       appears as the inverse of
                                                 Valve Position (%)                                       the plot of the final control
                                                                                                          element installed
                                                                                                          characteristic.

                               Figure 12-8
Identifying Model - DeltaV InSight
  Gain Process Insight with Model Analysis


                                                Last 200 Models
                                                 automatically stored
                                                 for each control loop
                                                 in a model database
                                                Various plot options
                                                 to analyze impact of
                                                 operating conditions
                                                 on process models
                                                Average of selected
                                                 models may be
                                                 utilized to establish
                                                 the recommended
                                                 tuning
Non-linear Process Models
DeltaV InSight – Adaptive Control
DeltaV InSight – Adaptive Control




            Adaptive Control Enabled
Split Range Control
   One of the most common
    ways of addressing multiple
    process inputs is known as
    split-range control.
   The splitter block may be
    used to define a fixed
    relationship between the
    controller output and each
    manipulated process input –
    appearing as one valve to the
    PID block
   The setup must account for
    the gain associated with
    each process input to
    achieve consistent control
    behavior.
Example – Steam Header Pressure
   To allow the plant to continue operation if the turbine or generator fails
    and must be shut down, pressure reducing valves (PRVs) between the
    high pressure header and the lower pressure header may be adjusted
    to meet the lower pressure header steam demand and to maintain the
    header pressure constant.
   This may be accomplished by using a splitter block in conjunction with
    a PID block to adjust the pressure reducing valves.
Steam Header – Splitter Characterization
   If the valve sizes or operating conditions for the valves are different, then it is
    necessary to characterize the splitter to compensate for these differences.
   For example, if the flow ratings in thousand of pounds per hour, KPPH, of the
    valves used in split-range control were as shown below:
      – Valve 1 flow rating = 50 KPPH
      – Valve 2 flow rating = 150 KPPH
   Then the controller output range of adjustment associated with Valve 1 would
    be:
Interactive Loops

                                          C1
                                                             The fighting between
                                          M2
                                               C2             interactive loops is most
                                               M2
                                                              often addressed by
                                                              simply detuning one of
                      Flow                                    the control loops by
                    Controller
                                                              reducing the proportional
                                                     C1       gain.
                    Composition
                     Controller                      M1      The valve associated
                          Outlet Flow
                                                              with the detuned loop
   Feed
   Valve(M1)
               Mixing
                          (C1)                                will change very slowly.
                                               C2
Additive
Valve(M2)
               Process
                            Composition                       Thus, the two loops will
                            (C2)                M1
                                                              tend not to interact but at
                                                              the expense of the
                                                              detuned loop having
                                                              slow response.
Roadmap to Improved Control
                                               Transmitter Broken/Unreliable   Fix or Replace
                                                                               Transmitter


                               Reason?                                             Tuning
                                             Poor                                  Valve/Actuator Problem
                                                             Investigate
                                             Performance                           Changing Process Gain
                                                                                   Split range Setup incorrect
                         No                                                        Process Dynamics
                                                                                   Loop Interaction
Starting
 Point
              Normal
              Mode?

           Determine     Yes                    Low/acceptable                 Monitor for
           Control                                                             Change
           Utilization         Variation
                               on Control   High
                                                                                   Changing Process Gain
                                                             Investigate           Process Disturbance
                                            Unacceptable
                                                                                   Process Dynamics
                                                                                   Loop Interaction
                                                                                   Changing Limit Condition
Utilize Process Capacity to Absorb Variability
     Step change in load (inflow)              Outflow = inflow



                  Controller Output
                  changing outflow
                                                  PV Back to SP in
                  smoothly!
                                  PV              6 x Lambda




                    Change in       Setpoint                 LIC
                    PV stopped
        Lambda
                                      Inflow
                                                             Outflow
Utilize Process Capacity to Absorb
Variability

    Choose the arrest time “slow” enough to
     provide a variability sink yet maintain level
     within the allowable variation
    Lambda = __2 * ALV___
                  Kp * MLD
     – ALV = Allowable Level Variation
     – Kp = Integrating process gain
     – MLD = Maximum Load Disturbance (converted
       to % of level controller output scale)
Utilize Process Capacity to Absorb Variability
         Before              After




                Level
                                     Level




        Manipulated
        Variable              Manipulated
                              Variable
Reducing Control Variation

 When tuning is not sufficient to achieved the desired
 level of variation in critical control parameter or to
 maintain it at an operating limit, then multi-loop
 techniques may sometimes be applied to improve
 control. Three common multi-loop techniques are:
    Feedforward Control
    Cascade Control
    Override Control
Summary

    An on-line measurement of control utilization and
     variability is provided by DeltaV Insight.
    Exploring the causes of poor utilization is the first
     step in resolving measurement, actuator or control
     issues.
    When single loop control is not sufficient to achieve
     the desired level of control the multi-loops solutions
     should be explored.
Where To Get More Information

    Many of the ideas discussed in this session are
     addressed “Control Loop Foundation – Batch and
     Continuous Processes”. Information on this book
     may be found at the book’s web site:

     – http://controlloopfoundation.com/

     Also, by going to this web site you can use your web
     browser to perform the 19 workshops that go with
     this book.

Contenu connexe

Tendances

Process Education on Demand
Process Education on Demand Process Education on Demand
Process Education on Demand Emerson Exchange
 
Calibration Excellence: Intelligent Application of Smart Technology is Just t...
Calibration Excellence: Intelligent Application of Smart Technology is Just t...Calibration Excellence: Intelligent Application of Smart Technology is Just t...
Calibration Excellence: Intelligent Application of Smart Technology is Just t...Emerson Exchange
 
Boot camp advanced tools and techniques
Boot camp   advanced tools and techniquesBoot camp   advanced tools and techniques
Boot camp advanced tools and techniquesEmerson Exchange
 
Control using wireless measurements
Control using wireless measurementsControl using wireless measurements
Control using wireless measurementsEmerson Exchange
 
Improving continuous process operation using data analytics delta v applicati...
Improving continuous process operation using data analytics delta v applicati...Improving continuous process operation using data analytics delta v applicati...
Improving continuous process operation using data analytics delta v applicati...Emerson Exchange
 
The semantic web an inside look at the creation of control loop foundation
The semantic web   an inside look at the creation of control loop foundationThe semantic web   an inside look at the creation of control loop foundation
The semantic web an inside look at the creation of control loop foundationEmerson Exchange
 
Application of online data analytics to a continuous process polybutene unit
Application of online data analytics to a continuous process polybutene unitApplication of online data analytics to a continuous process polybutene unit
Application of online data analytics to a continuous process polybutene unitEmerson Exchange
 
Practical Advanced Process Control for Engineers and Technicians
Practical Advanced Process Control for Engineers and TechniciansPractical Advanced Process Control for Engineers and Technicians
Practical Advanced Process Control for Engineers and TechniciansLiving Online
 
Recovery from a process saturation condition benefits of using delta v pid_plus
Recovery from a process saturation condition benefits of using delta v pid_plusRecovery from a process saturation condition benefits of using delta v pid_plus
Recovery from a process saturation condition benefits of using delta v pid_plusEmerson Exchange
 
Advanced Process Control for ARC
Advanced Process Control for ARCAdvanced Process Control for ARC
Advanced Process Control for ARCanilkc12
 
Advanced Process Control
Advanced Process ControlAdvanced Process Control
Advanced Process ControlRatul Das
 
In Apc Training Presentation
In  Apc Training PresentationIn  Apc Training Presentation
In Apc Training Presentationahmad bassiouny
 
Transition to online AMS reduces maintenance costs and improves operations
Transition to online AMS reduces maintenance costs and improves operationsTransition to online AMS reduces maintenance costs and improves operations
Transition to online AMS reduces maintenance costs and improves operationsEmerson Exchange
 
IPC_project final
IPC_project finalIPC_project final
IPC_project finalRatul Das
 
Future Perspectives of PID Control
Future Perspectives of PID ControlFuture Perspectives of PID Control
Future Perspectives of PID ControlEmerson Exchange
 
Reliability Centered Maintenance Made Simple
Reliability Centered Maintenance Made SimpleReliability Centered Maintenance Made Simple
Reliability Centered Maintenance Made SimpleRicky Smith CMRP, CMRT
 
Change your board operator to a process control manager
Change your board operator to a process control managerChange your board operator to a process control manager
Change your board operator to a process control managerMary Claire Simoneaux
 
Modernization Lessons Learned -Part 2
Modernization Lessons Learned -Part 2Modernization Lessons Learned -Part 2
Modernization Lessons Learned -Part 2Emerson Exchange
 
Modernization Lessons Learned - Part 1
Modernization Lessons Learned - Part 1Modernization Lessons Learned - Part 1
Modernization Lessons Learned - Part 1Emerson Exchange
 

Tendances (20)

Process Education on Demand
Process Education on Demand Process Education on Demand
Process Education on Demand
 
Calibration Excellence: Intelligent Application of Smart Technology is Just t...
Calibration Excellence: Intelligent Application of Smart Technology is Just t...Calibration Excellence: Intelligent Application of Smart Technology is Just t...
Calibration Excellence: Intelligent Application of Smart Technology is Just t...
 
Boot camp advanced tools and techniques
Boot camp   advanced tools and techniquesBoot camp   advanced tools and techniques
Boot camp advanced tools and techniques
 
Control using wireless measurements
Control using wireless measurementsControl using wireless measurements
Control using wireless measurements
 
Improving continuous process operation using data analytics delta v applicati...
Improving continuous process operation using data analytics delta v applicati...Improving continuous process operation using data analytics delta v applicati...
Improving continuous process operation using data analytics delta v applicati...
 
The semantic web an inside look at the creation of control loop foundation
The semantic web   an inside look at the creation of control loop foundationThe semantic web   an inside look at the creation of control loop foundation
The semantic web an inside look at the creation of control loop foundation
 
Application of online data analytics to a continuous process polybutene unit
Application of online data analytics to a continuous process polybutene unitApplication of online data analytics to a continuous process polybutene unit
Application of online data analytics to a continuous process polybutene unit
 
Practical Advanced Process Control for Engineers and Technicians
Practical Advanced Process Control for Engineers and TechniciansPractical Advanced Process Control for Engineers and Technicians
Practical Advanced Process Control for Engineers and Technicians
 
Recovery from a process saturation condition benefits of using delta v pid_plus
Recovery from a process saturation condition benefits of using delta v pid_plusRecovery from a process saturation condition benefits of using delta v pid_plus
Recovery from a process saturation condition benefits of using delta v pid_plus
 
Advanced Process Control for ARC
Advanced Process Control for ARCAdvanced Process Control for ARC
Advanced Process Control for ARC
 
Advanced Process Control
Advanced Process ControlAdvanced Process Control
Advanced Process Control
 
In Apc Training Presentation
In  Apc Training PresentationIn  Apc Training Presentation
In Apc Training Presentation
 
Transition to online AMS reduces maintenance costs and improves operations
Transition to online AMS reduces maintenance costs and improves operationsTransition to online AMS reduces maintenance costs and improves operations
Transition to online AMS reduces maintenance costs and improves operations
 
IPC_project final
IPC_project finalIPC_project final
IPC_project final
 
Future Perspectives of PID Control
Future Perspectives of PID ControlFuture Perspectives of PID Control
Future Perspectives of PID Control
 
Reliability Centered Maintenance Made Simple
Reliability Centered Maintenance Made SimpleReliability Centered Maintenance Made Simple
Reliability Centered Maintenance Made Simple
 
Change your board operator to a process control manager
Change your board operator to a process control managerChange your board operator to a process control manager
Change your board operator to a process control manager
 
Modernization Lessons Learned -Part 2
Modernization Lessons Learned -Part 2Modernization Lessons Learned -Part 2
Modernization Lessons Learned -Part 2
 
Modernization Lessons Learned - Part 1
Modernization Lessons Learned - Part 1Modernization Lessons Learned - Part 1
Modernization Lessons Learned - Part 1
 
sairam_CV
sairam_CVsairam_CV
sairam_CV
 

Similaire à Maximizing the return on your control investment meet the experts sessions part 1

Alarm Rationalization Workshop - Tips, Tricks and Traps
Alarm Rationalization Workshop - Tips, Tricks and Traps Alarm Rationalization Workshop - Tips, Tricks and Traps
Alarm Rationalization Workshop - Tips, Tricks and Traps Mary Claire Simoneaux
 
T12 exploitation testing - presentation 1.2
T12   exploitation testing - presentation 1.2T12   exploitation testing - presentation 1.2
T12 exploitation testing - presentation 1.2Edwin Loon, van
 
Tools Processes And Training
Tools Processes And TrainingTools Processes And Training
Tools Processes And Trainingdgholden
 
Process Control in Chemical Engineering by MATLAB
Process Control in Chemical Engineering by MATLABProcess Control in Chemical Engineering by MATLAB
Process Control in Chemical Engineering by MATLABpriyachemical
 
IRJET- Optimum Design of PSO based Tuning using PID Controller for an Automat...
IRJET- Optimum Design of PSO based Tuning using PID Controller for an Automat...IRJET- Optimum Design of PSO based Tuning using PID Controller for an Automat...
IRJET- Optimum Design of PSO based Tuning using PID Controller for an Automat...IRJET Journal
 
Mechatroincs universitty for students .ppt
Mechatroincs universitty for students .pptMechatroincs universitty for students .ppt
Mechatroincs universitty for students .pptmohamed abd elrazek
 
Mechatroincs universitty for students .ppt
Mechatroincs universitty for students .pptMechatroincs universitty for students .ppt
Mechatroincs universitty for students .pptmohamed abd elrazek
 
Basics On Process Control and PID's.pdf
Basics On Process Control and PID's.pdfBasics On Process Control and PID's.pdf
Basics On Process Control and PID's.pdfboyrindrawan1
 
Screenshot 2021-02-23 at 2.46.02 PM.pdf
Screenshot 2021-02-23 at 2.46.02 PM.pdfScreenshot 2021-02-23 at 2.46.02 PM.pdf
Screenshot 2021-02-23 at 2.46.02 PM.pdfmuhammadsubhan626458
 
Paper id 21201482
Paper id 21201482Paper id 21201482
Paper id 21201482IJRAT
 
Auto tuning of cascade control systems
Auto tuning of cascade control systemsAuto tuning of cascade control systems
Auto tuning of cascade control systemsISA Interchange
 
Process control 4 chapter
Process control 4 chapterProcess control 4 chapter
Process control 4 chapterSrinivasa Rao
 
PID Controller and its design
PID Controller and its designPID Controller and its design
PID Controller and its designKonirDom1
 
Delta v advanced control overview_en
Delta v advanced control overview_enDelta v advanced control overview_en
Delta v advanced control overview_enLuis Atencio
 
aa-automation-apc-complex-industrial-processes
aa-automation-apc-complex-industrial-processesaa-automation-apc-complex-industrial-processes
aa-automation-apc-complex-industrial-processesDavid Lyon
 

Similaire à Maximizing the return on your control investment meet the experts sessions part 1 (20)

Alarm Rationalization Workshop - Tips, Tricks and Traps
Alarm Rationalization Workshop - Tips, Tricks and Traps Alarm Rationalization Workshop - Tips, Tricks and Traps
Alarm Rationalization Workshop - Tips, Tricks and Traps
 
Ep 5512 lecture-03
Ep 5512 lecture-03Ep 5512 lecture-03
Ep 5512 lecture-03
 
T12 exploitation testing - presentation 1.2
T12   exploitation testing - presentation 1.2T12   exploitation testing - presentation 1.2
T12 exploitation testing - presentation 1.2
 
Tools Processes And Training
Tools Processes And TrainingTools Processes And Training
Tools Processes And Training
 
Process Control in Chemical Engineering by MATLAB
Process Control in Chemical Engineering by MATLABProcess Control in Chemical Engineering by MATLAB
Process Control in Chemical Engineering by MATLAB
 
pid controller
 pid controller pid controller
pid controller
 
IRJET- Optimum Design of PSO based Tuning using PID Controller for an Automat...
IRJET- Optimum Design of PSO based Tuning using PID Controller for an Automat...IRJET- Optimum Design of PSO based Tuning using PID Controller for an Automat...
IRJET- Optimum Design of PSO based Tuning using PID Controller for an Automat...
 
Mechatroincs universitty for students .ppt
Mechatroincs universitty for students .pptMechatroincs universitty for students .ppt
Mechatroincs universitty for students .ppt
 
Mechatroincs universitty for students .ppt
Mechatroincs universitty for students .pptMechatroincs universitty for students .ppt
Mechatroincs universitty for students .ppt
 
Basics On Process Control and PID's.pdf
Basics On Process Control and PID's.pdfBasics On Process Control and PID's.pdf
Basics On Process Control and PID's.pdf
 
Screenshot 2021-02-23 at 2.46.02 PM.pdf
Screenshot 2021-02-23 at 2.46.02 PM.pdfScreenshot 2021-02-23 at 2.46.02 PM.pdf
Screenshot 2021-02-23 at 2.46.02 PM.pdf
 
Paper id 21201482
Paper id 21201482Paper id 21201482
Paper id 21201482
 
Auto tuning of cascade control systems
Auto tuning of cascade control systemsAuto tuning of cascade control systems
Auto tuning of cascade control systems
 
Process control 4 chapter
Process control 4 chapterProcess control 4 chapter
Process control 4 chapter
 
PID Controller and its design
PID Controller and its designPID Controller and its design
PID Controller and its design
 
Delta v advanced control overview_en
Delta v advanced control overview_enDelta v advanced control overview_en
Delta v advanced control overview_en
 
Control actions
Control actionsControl actions
Control actions
 
aa-automation-apc-complex-industrial-processes
aa-automation-apc-complex-industrial-processesaa-automation-apc-complex-industrial-processes
aa-automation-apc-complex-industrial-processes
 
Pid controller bp ganthia
Pid controller bp ganthiaPid controller bp ganthia
Pid controller bp ganthia
 
PEI 1986 Volume 48
PEI 1986 Volume 48PEI 1986 Volume 48
PEI 1986 Volume 48
 

Plus de Emerson Exchange

Using Wireless Measurements in Control Applications
Using Wireless Measurements in Control ApplicationsUsing Wireless Measurements in Control Applications
Using Wireless Measurements in Control ApplicationsEmerson Exchange
 
Device Revisions Management - Best Practices
Device Revisions Management - Best PracticesDevice Revisions Management - Best Practices
Device Revisions Management - Best PracticesEmerson Exchange
 
Master the Mystery and Marvels of DeltaV MPC
Master the Mystery and Marvels of DeltaV MPCMaster the Mystery and Marvels of DeltaV MPC
Master the Mystery and Marvels of DeltaV MPCEmerson Exchange
 
Intelligent PID Product Design
Intelligent PID Product DesignIntelligent PID Product Design
Intelligent PID Product DesignEmerson Exchange
 
A Quick and Easy Way to Connect to FOUNDATION fieldbus using Emerson’s USB Fi...
A Quick and Easy Way to Connect to FOUNDATION fieldbus using Emerson’s USB Fi...A Quick and Easy Way to Connect to FOUNDATION fieldbus using Emerson’s USB Fi...
A Quick and Easy Way to Connect to FOUNDATION fieldbus using Emerson’s USB Fi...Emerson Exchange
 
When the Heat is On, Control with Wireless
When the Heat is On, Control with WirelessWhen the Heat is On, Control with Wireless
When the Heat is On, Control with WirelessEmerson Exchange
 
DeltaV Security - Don’t Let Your Business Be Caught Without It
DeltaV Security - Don’t Let Your Business Be Caught Without ItDeltaV Security - Don’t Let Your Business Be Caught Without It
DeltaV Security - Don’t Let Your Business Be Caught Without ItEmerson Exchange
 
LNG Dispensing Made Simple Using Micro Motion
LNG Dispensing Made Simple Using Micro MotionLNG Dispensing Made Simple Using Micro Motion
LNG Dispensing Made Simple Using Micro MotionEmerson Exchange
 
Project Management Successes with Global Teams
Project Management Successes with Global TeamsProject Management Successes with Global Teams
Project Management Successes with Global TeamsEmerson Exchange
 
Interfacing delta v to motorized actuators addressing control applications
Interfacing delta v to motorized actuators addressing control applications Interfacing delta v to motorized actuators addressing control applications
Interfacing delta v to motorized actuators addressing control applications Emerson Exchange
 
State-of-the-Art Automation at Asphalt Loading/Blending Terminal
State-of-the-Art Automation at Asphalt Loading/Blending TerminalState-of-the-Art Automation at Asphalt Loading/Blending Terminal
State-of-the-Art Automation at Asphalt Loading/Blending TerminalEmerson Exchange
 

Plus de Emerson Exchange (12)

Using Wireless Measurements in Control Applications
Using Wireless Measurements in Control ApplicationsUsing Wireless Measurements in Control Applications
Using Wireless Measurements in Control Applications
 
Device Revisions Management - Best Practices
Device Revisions Management - Best PracticesDevice Revisions Management - Best Practices
Device Revisions Management - Best Practices
 
Adventures in pH Control
Adventures in pH ControlAdventures in pH Control
Adventures in pH Control
 
Master the Mystery and Marvels of DeltaV MPC
Master the Mystery and Marvels of DeltaV MPCMaster the Mystery and Marvels of DeltaV MPC
Master the Mystery and Marvels of DeltaV MPC
 
Intelligent PID Product Design
Intelligent PID Product DesignIntelligent PID Product Design
Intelligent PID Product Design
 
A Quick and Easy Way to Connect to FOUNDATION fieldbus using Emerson’s USB Fi...
A Quick and Easy Way to Connect to FOUNDATION fieldbus using Emerson’s USB Fi...A Quick and Easy Way to Connect to FOUNDATION fieldbus using Emerson’s USB Fi...
A Quick and Easy Way to Connect to FOUNDATION fieldbus using Emerson’s USB Fi...
 
When the Heat is On, Control with Wireless
When the Heat is On, Control with WirelessWhen the Heat is On, Control with Wireless
When the Heat is On, Control with Wireless
 
DeltaV Security - Don’t Let Your Business Be Caught Without It
DeltaV Security - Don’t Let Your Business Be Caught Without ItDeltaV Security - Don’t Let Your Business Be Caught Without It
DeltaV Security - Don’t Let Your Business Be Caught Without It
 
LNG Dispensing Made Simple Using Micro Motion
LNG Dispensing Made Simple Using Micro MotionLNG Dispensing Made Simple Using Micro Motion
LNG Dispensing Made Simple Using Micro Motion
 
Project Management Successes with Global Teams
Project Management Successes with Global TeamsProject Management Successes with Global Teams
Project Management Successes with Global Teams
 
Interfacing delta v to motorized actuators addressing control applications
Interfacing delta v to motorized actuators addressing control applications Interfacing delta v to motorized actuators addressing control applications
Interfacing delta v to motorized actuators addressing control applications
 
State-of-the-Art Automation at Asphalt Loading/Blending Terminal
State-of-the-Art Automation at Asphalt Loading/Blending TerminalState-of-the-Art Automation at Asphalt Loading/Blending Terminal
State-of-the-Art Automation at Asphalt Loading/Blending Terminal
 

Dernier

Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherRemote DBA Services
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWERMadyBayot
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyKhushali Kathiriya
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businesspanagenda
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024The Digital Insurer
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu SubbuApidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbuapidays
 
Ransomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfRansomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfOverkill Security
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Jeffrey Haguewood
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDropbox
 
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...apidays
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoffsammart93
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...DianaGray10
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...apidays
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAndrey Devyatkin
 

Dernier (20)

Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu SubbuApidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
 
Ransomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfRansomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdf
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 

Maximizing the return on your control investment meet the experts sessions part 1

  • 1. Maximizing the Return on Your Control Investment Part 1 of 2 Meet the Experts Sessions
  • 2. Presenters  James Beall  Terry Blevins
  • 3. Session Objective  Provide a roadmap that may be used to maximize the return on your control investment
  • 4. Agenda  Assessment of control loop utilization and automatic control performance,  Identifying areas where it is possible to justified the cost of improving control performance.  Tools and techniques to achieve best control performance. Identifying and correcting field problems.
  • 5. Evaluating Control System Utilization  Product quality and manufacturing efficiency may be impacted by variation in key parameters.  When production is process limited, then throughput may be increase by reducing process variation and operating closer to the limit.  The control must operate as designed to achieve these benefits.
  • 6. Control Utilization Control utilization is an indicator that can be used to quickly determine if control and measurement problems exist within a control system. Surveys indicate that the primary reasons for control not being fully utilized fall into two areas:  Field measurement or control element  Process or control design An immediate improvement in control utilization will be achieved by addressing these problems. To achieve full utilization, improved communications between maintenance and operations is important.
  • 7. Example – Case Study At one pulp and paper plant a snapshot of the control utilization was collected to quantify the state of the process control. This survey showed: Control Normal Loops Mode Utilization Bleach Plant 78 60 76% Power House 185 130 70% Pulp Mill 174 116 66% Paper Mill 236 134 56% An instrumentation team was formed to investigate loops that were not running in their normal design mode. This team was responsible for making sure measurement, control valve, and process problems were addressed in a timely fashion. The reduction in variability led to significant improvements in plant throughput and product quality
  • 8. Example – Another Case Study At refinery and petrochemical complex a snapshot of the control utilization was collected to quantify the state of the process control. This survey showed: System Loops Utilization PX 471 67.3% APS&VPS、CLE、Sulfur Recovery 469 59.7% Refinery 478 60.9% IGCCAuxiliary Boiler 946 52.7% Ethylene 1355 77.5% FCCU 475 48% C4 164 68.9%
  • 9. Examining Control Utilization  Summarizes performance for System or by Area, Cell, or Units  Abnormal Control Conditions indicated for Problem Loops: – Control Service Status: • Not in Normal mode • Limited control output • Bad/Uncertain input – Control Performance Status: • Standard Deviation • Variability Index • Oscillation Index • Tuning Index
  • 10. DeltaV InSight Control Performance Reports
  • 11. Roadmap to Improved Control Transmitter Broken/Unreliable Fix or Replace Transmitter Reason? Tuning Poor Valve/Actuator Problem Investigate Performance Changing Process Gain Process Dynamics No Loop Interaction Starting Point Control Loop in Normal Mode? Yes Use DeltaV Insight to examine loop tuning Use DeltaV Insight to Determine Control Utilization
  • 12. DeltaV Insight – On-demand Tuning  Allows control loop tuning to be quickly established
  • 14. DeltaV InSight - Adaptive Tuning Provides Tuning Based on Normal Operator Changes  InSight automatically calculates dynamic Before vs. After models from operator changes  Model Quality and Learning Status  Tuning criteria and desired speed of response  Tuning Recommendation  No Testing Required
  • 15. Tips for Using On-Demand Tuning  Set step size large enough to insure the response to the PID output changing is larger that the measurement noise and influence of process disturbances.  Select “Integrating” if the process is not self- regulating.  If the process has low or high gain, then selected Default Process and set the process type to match the expected behavior.
  • 16. Manual Tuning (Not a DeltaV System)  When commissioning PID control associated with a self-regulating process, this procedure may be quickly applied to both old and new control systems to determine the tuning for PI control.  The size of the step should be just large enough to easily distinguish the resulting change in the controlled process output.
  • 17. Manual Tuning - (Not a DeltaV System) Alternate  When commissioning PID control associated with a self-regulating process, this procedure may be quickly applied to both old and new control systems to determine the tuning for PI control.  The size of the step should be just large enough to easily distinguish the resulting change in the controlled process output.  Tune as follows: – Place the PV and OUT on a trend. – Place the controller in Manual and allow the process to reach steady sate. – Impose a step change in OUT and observe the response – Set the RESET equal to ¼ of the time it takes to “almost” line out (98% of final value) – Set the GAIN equal to 1/3 of process gain, Kp where – Kp = ((Δ%PV) / (Δ%OUT) (Be sure to convert to % of span!) – Place the loop in automatic and make small adjustments to the Setpoint and observe the response. Adjust ONLY the GAIN to achieve the desired response.
  • 18. Impact of Sticky Valve  When a control loop is placed in automatic Setpoint (SP) control, it is easy to detect if a valve or Controlled Parameter (PV) damper is not responding to the Implied Valve Position (OUT) Value control system by observing the Stem Position) response of the controlled parameter to control system Time changes in the PID output.  Cycling can not be eliminated through tuning.
  • 19. Valve Positioner Recommendation The most common problems in commissioning a control system can often be traced to the fact that a positioner has not been provided with the valve, or the positioner provided with the valve has not been properly installed or has malfunctioned. – The rule of thumb is that to achieve best control performance, all regulating valves should be equipped with a positioner. – Without a positioner, the control performance that may be achieved is very limited when a valve is sticking – which is inherent in most valves. – The cyclic behavior caused by a sticky valve (with no positioner) cannot be eliminated through tuning. Changes in tuning will only impact the period of the cycle that develops. The only way to eliminate this type of behavior is to install a valve positioner.
  • 20. Installed Characteristics. 7000  From a control perspective, it is highly desirable that the process 6000 gain be constant. If the process gain is constant, then the same 5000 proportional gain may be used over the entire operating range of Gas Flow (SCFH) 4000 the control loop.  If the valve characteristic was not 3000 been selected based on the process requirements, then the 2000 installed characteristic could be non-linear. 0  As illustrated in this example, the 0 20 40 60 80 100 Valve Position (%) process gain varies from 0.5 to 4; that is, the process gain changes by a factor of eight.
  • 21. Impact of Non-linear Installed Characteristics Non-linear Process Example  Process gain and dynamics may change as a function of operating conditions such as valve position or feed rate.
  • 22. Linearizing Response  To compensate for the changes in process gain, a characterizer block may be installed between the PID and Analog Output blocks. Select the option to inverse the calculation done in the forward path for the PID back calculation to allow bumpless transfer.
  • 23. Characterizer Setup  The relationship between Characterizer 100 IN OUT the primary inputs and the Linear Relationship 0 0 90 Characterizer In-Out 5 1.5 output of the characterizer 10 3 80 15 20 5.5 8,5 block may be defined by 70 25 30 10 11.5 21 x,y pairs over the final 60 35 40 13 17 control element operating 50 45 20 range. Process Output (%) 50 22 40 55 26 30 60 65 31 36  Input values that fall 20 70 75 42 48 between these points are 10 80 85 54 63 automatically determined 0 90 95 74 86 by the characterizer block 100 100 using linear interpolation.  The curve defined by the characterizer points 0 10 20 30 40 50 60 70 80 90 100 appears as the inverse of Valve Position (%) the plot of the final control element installed characteristic. Figure 12-8
  • 24. Identifying Model - DeltaV InSight Gain Process Insight with Model Analysis  Last 200 Models automatically stored for each control loop in a model database  Various plot options to analyze impact of operating conditions on process models  Average of selected models may be utilized to establish the recommended tuning
  • 26. DeltaV InSight – Adaptive Control
  • 27. DeltaV InSight – Adaptive Control Adaptive Control Enabled
  • 28. Split Range Control  One of the most common ways of addressing multiple process inputs is known as split-range control.  The splitter block may be used to define a fixed relationship between the controller output and each manipulated process input – appearing as one valve to the PID block  The setup must account for the gain associated with each process input to achieve consistent control behavior.
  • 29. Example – Steam Header Pressure  To allow the plant to continue operation if the turbine or generator fails and must be shut down, pressure reducing valves (PRVs) between the high pressure header and the lower pressure header may be adjusted to meet the lower pressure header steam demand and to maintain the header pressure constant.  This may be accomplished by using a splitter block in conjunction with a PID block to adjust the pressure reducing valves.
  • 30. Steam Header – Splitter Characterization  If the valve sizes or operating conditions for the valves are different, then it is necessary to characterize the splitter to compensate for these differences.  For example, if the flow ratings in thousand of pounds per hour, KPPH, of the valves used in split-range control were as shown below: – Valve 1 flow rating = 50 KPPH – Valve 2 flow rating = 150 KPPH  Then the controller output range of adjustment associated with Valve 1 would be:
  • 31. Interactive Loops C1  The fighting between M2 C2 interactive loops is most M2 often addressed by simply detuning one of Flow the control loops by Controller reducing the proportional C1 gain. Composition Controller M1  The valve associated Outlet Flow with the detuned loop Feed Valve(M1) Mixing (C1) will change very slowly. C2 Additive Valve(M2) Process Composition Thus, the two loops will (C2) M1 tend not to interact but at the expense of the detuned loop having slow response.
  • 32. Roadmap to Improved Control Transmitter Broken/Unreliable Fix or Replace Transmitter Reason? Tuning Poor Valve/Actuator Problem Investigate Performance Changing Process Gain Split range Setup incorrect No Process Dynamics Loop Interaction Starting Point Normal Mode? Determine Yes Low/acceptable Monitor for Control Change Utilization Variation on Control High Changing Process Gain Investigate Process Disturbance Unacceptable Process Dynamics Loop Interaction Changing Limit Condition
  • 33. Utilize Process Capacity to Absorb Variability Step change in load (inflow) Outflow = inflow Controller Output changing outflow PV Back to SP in smoothly! PV 6 x Lambda Change in Setpoint LIC PV stopped Lambda Inflow Outflow
  • 34. Utilize Process Capacity to Absorb Variability  Choose the arrest time “slow” enough to provide a variability sink yet maintain level within the allowable variation  Lambda = __2 * ALV___ Kp * MLD – ALV = Allowable Level Variation – Kp = Integrating process gain – MLD = Maximum Load Disturbance (converted to % of level controller output scale)
  • 35. Utilize Process Capacity to Absorb Variability Before After Level Level Manipulated Variable Manipulated Variable
  • 36. Reducing Control Variation When tuning is not sufficient to achieved the desired level of variation in critical control parameter or to maintain it at an operating limit, then multi-loop techniques may sometimes be applied to improve control. Three common multi-loop techniques are:  Feedforward Control  Cascade Control  Override Control
  • 37. Summary  An on-line measurement of control utilization and variability is provided by DeltaV Insight.  Exploring the causes of poor utilization is the first step in resolving measurement, actuator or control issues.  When single loop control is not sufficient to achieve the desired level of control the multi-loops solutions should be explored.
  • 38. Where To Get More Information  Many of the ideas discussed in this session are addressed “Control Loop Foundation – Batch and Continuous Processes”. Information on this book may be found at the book’s web site: – http://controlloopfoundation.com/ Also, by going to this web site you can use your web browser to perform the 19 workshops that go with this book.