SlideShare une entreprise Scribd logo
1  sur  28
INITIAL ENVIRONMENTAL
EXAMINATION
REPORT
Presented By: Eleasa Jacob & Faryal Saleemi
Project Name:
Power Distribution Enhancement
Project Tranche – 3,
Augmentation of PESCOSubprojects
(Rehman Baba, Swabi, Bannu, D.I.Khan, Kotal Town Kohat, Jalala,
Jehangir and Batal)
Project Coordinator:
PEPCO (Pakistan Electric Power Company)
CONTENTS:
 Introduction
 Description of the Project
 Description of Environmental and Social Conditions
 Assessment of Environmental Impacts and Mitigation
Measures
 Institutional Requirements Environmental Management
Plan
 Public Consultation
 Conclusion
Introduction:
 The Initial Environmental Examination (IEE) for the
Tranche- 3 augmentation of 8 sub-projects proposed by the
Peshawar Electricity Supply Company (PESCO)and have
been submitted by PEPCO.
 The sub project is to be financed under the Asian
Development Bank’s (ADB) Power Distribution and
Enhancement Multi-trance Finance Facility (PDEMFF).
The proposed PDEMF facility has been
designed to address both investments and
institutional aspects in the electrical power
sector.
Surveys took place in July 2012.
The field studies were undertaken by a core
study team with experience of environmental
assessment for power projects in Pakistan.
Description of Project:
Type of Project:
Improvements to the equipment that supports the
power distribution network at eight existing
distribution sub-stations DGS.
Beneficiaries of the project:
People, companies, government and non-
government agencies in Pakistan with improved,
secure faster distribution services.
Need of Project:
The conditions of the power transmission
system in Pakistan are presently inadequate to
meet the rapidly increasing demand for
electrical power. This situation limits national
development and economic growth.
To cope with the constraints, the existing power
transmission infrastructure has to be improved
and upgraded.
 Replacement of an existing transformer in an
existing DGS with a transformer of a higher
capacity (augmentation) because the
transformers are over loaded and needs urgent
up gradation.
 The Project Proponent (PESCO) plans to have
the T3 completed by mid to late 2015.
Sr. No. Name of
Sub Station
Voltage Total
Capacity
Capacity
Added
MVa
Existing
Capacity MVa
1. Rehman
Baba
132/11 1x40 MVA 1x26 3x26
2. Swabi 132/11 1x40 MVA 1x16 3x26
3. Bannu 132/11 2x40 MVA 2x26 3x26
4. DI Khan 132/11 1x40 MVA 1x26 2x26
5. Kotal Town
Kohat
132/11 1x40 MVA 1x26 3x26
6. Jalala 132/11 1x26 MVA 1x13 2x13
7 Jehangira 132/11 1x26 MVA 1x13 1x13+1x26
8. Batal 132/11 1x26 MVA --- 2x26
Rehman Baba
Kohat sub Station – Existing transformers
Kohat sub station
Nowshera City
Jehangira sub station – Space for extension
extension
Jalala- Switch yard
DI Khan- Switchyard
Swabi- Transformer
to be replaced
Description of Environment:
 Project Area:
The augmentation projects will all be within the eight (08) existing DGS
and will not encroach on any land outside the sub-stations.
PHYSICAL RESOURSES:
 Topography, Geography, Geology, and Soils
 Flat with the land sloping gently in a NE-SW direction.
 Some sites like Mansehra, Swat and Dir are in more hilly areas.
 The natural soils within the sub-station boundaries have been covered
with cobblestones, bricks or concrete in various areas.
 Climate:
Little or no variation between the climate of the subproject areas.
 Groundwater and Water Supply:
 In most of the places where PHED supplies water, the water is of very
good quality.
 The local population is generally reliant on supply from tube wells,
occasional open wells and hand pumps.
 There should be no impact on these sources of water by the construction
of the extension and augmentation subprojects.
Surface water:
The Indus River, River Swat, Pingkora River, Kabul River in Peshawar.
 Air Quality:
 Air quality appears fairly good based on observation during
the study period.
 Areas nearer the busy main roads are clearly impacted by
vehicle fumes and dust.
 It is unlikely that large powered mechanical equipment will
be needed for the extension and augmentation projects
other than delivery lorries and lifting cranes.
 CO, SO2 and NO levels were in excess of the acceptable
levels in some areas but the average levels were found below
WHO standards.
ECOLOGICALRESOURCES:
No significant ecological resources, aquatic biological resources in the
urban areas near the sub-projects are found.
ECONOMICDEVELOPMENT:
 Industries, Agriculture and Tourism:
There are thousands of industrial and commercial businesses in the
vicinity of the Tranche 3 augmentation sub-projects reliant on the
efficient distribution of electrical power.
 Transportation:
The support systems for air, rail and road transport are all
reliant to some extent on electrical power and thus the
majority of the local population is reliant on the power
network for transportation.
 Social and Cultural Resources:
 None of augmentation sub-projects will require relocation or
resettlement.
 No cultural and archeological sites are located in the vicinity of
the any of the Tranche 3 augmentation sub-projects.
Screening Potential Environmental Impacts &
Mitigation Measures
 In some cases few sensitive receivers (SR) are within a few meters
of the DGS boundary walls and the SR’s are in the form of
residential buildings, some schools and shops in the
surrounding villages.
 There will be potential impacts in the construction stage from
disturbance and significant noise and dust if any of the
residences and schools are close enough to sub-projects.
 Water is available in the study area although surplus water may
not always be available to suppress dust at many locations in the
dry season.
 Prevention of Ground Contamination:
 Best measures to control oily residues should be included.
 Transformer oil and lubricants may be released in the
operational stage from maintenance.
 Cultural Heritage, Temples, Religious Sites, Social
Infrastructure:
 No temples or religious sites are so close to the subproject
works in the DGS as to expect a nuisance.
 The clinic/hospitals are all well separated from the
boundary walls of the sub-project DGS and there
will be sufficient distance between the works and
the SR.
Cut and Fill and Waste Disposal
 Projects should not require any significant cutting
and filling.
 Trees, Ecology and Protected Areas:
If for some unforeseen reason Reserved Trees or other
trees do need to be removed permission should be
obtained from the forest authority after written
justification.
 Air Pollution from Rock Crushing, Cut, Fill, & Asphalt:
In transmission line construction sand and aggregate
are delivered directly to the tower location from the
quarry / source, there is no intermediate or bulk storage
of these materials.
Noise, Vibration
“Environmental quality standards for noise”
 working hours: 6 .00 am to 10.00 pm
Silence zone: An area comprising not less
than 100 meters around hospitals,
educational institutions and courts.
 Mitigation measures are required to reduce residual impact to
acceptable levels and achieve the expected outcomes of the project.
 The IEE and EPM plan must be reviewed by the project
management and approved by the EPA before any construction
activity is initiated.
 PESCO must prepare the future contractors to co-operate with all
stakeholders in the mitigation of impacts.
 Actions like monitoring and inspection must be taken to address
unexpected impacts or not duly complied measurements.
Institutional Requirements & Environmental
Management Plan
Public Consultation:
 The public consultation (PC) process with various
stakeholders has been approached so as to involve
public and other stakeholders from the initial stages.
 Public consultation has taken place during the
planning and design stage.
 Viewpoints of the stakeholders have been taken into
account and their concerns and suggestions for
possible improvements have been included where
appropriate.
Conclusion:
 For initial environmental study potential
environmental impacts were assessed in a
comprehensive manner.
Project is a feasible and sustainable option from the
engineering, environmental, and socioeconomic points
of view.
Overall, report has provided a picture of all potential
environmental impacts associated with the Project and
recommended suitable mitigation measures.
THANKS FOR
YOUR PATIENCE :)

Contenu connexe

Tendances

Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
Sayyid Ina
 
Road development projects.
Road development projects.Road development projects.
Road development projects.
Abhishek Rajput
 

Tendances (20)

Baseline study for EIA
Baseline study for EIABaseline study for EIA
Baseline study for EIA
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
 
Seminar on Environmental Impact Assessment
Seminar on Environmental Impact AssessmentSeminar on Environmental Impact Assessment
Seminar on Environmental Impact Assessment
 
ENVIRONMENTAL IMPACT ASSESSMENT - EIA
ENVIRONMENTAL IMPACT ASSESSMENT - EIAENVIRONMENTAL IMPACT ASSESSMENT - EIA
ENVIRONMENTAL IMPACT ASSESSMENT - EIA
 
Environmental Planning
Environmental PlanningEnvironmental Planning
Environmental Planning
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
 
Environment impact assessment study
Environment impact assessment studyEnvironment impact assessment study
Environment impact assessment study
 
ENVIRONMENTAL IMPACTS ASSESMENT (EIA)
ENVIRONMENTAL  IMPACTS ASSESMENT (EIA)ENVIRONMENTAL  IMPACTS ASSESMENT (EIA)
ENVIRONMENTAL IMPACTS ASSESMENT (EIA)
 
Environmental Impact Assessment(EIA)
Environmental Impact Assessment(EIA)Environmental Impact Assessment(EIA)
Environmental Impact Assessment(EIA)
 
Eia of township and area development projects
Eia of township and area development projectsEia of township and area development projects
Eia of township and area development projects
 
IEE and screening in EIA
IEE and screening in EIAIEE and screening in EIA
IEE and screening in EIA
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
EIA-process
 EIA-process EIA-process
EIA-process
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
EIA Process
EIA ProcessEIA Process
EIA Process
 
Environmental Impact Assessment (EIA)
Environmental Impact Assessment (EIA)Environmental Impact Assessment (EIA)
Environmental Impact Assessment (EIA)
 
Impact prediction, evaluation and mitigation in eia
Impact prediction, evaluation and mitigation in eiaImpact prediction, evaluation and mitigation in eia
Impact prediction, evaluation and mitigation in eia
 
Road development projects.
Road development projects.Road development projects.
Road development projects.
 
Environmental Impact Assessment, Initial Environmental Examination
Environmental Impact Assessment, Initial Environmental ExaminationEnvironmental Impact Assessment, Initial Environmental Examination
Environmental Impact Assessment, Initial Environmental Examination
 

En vedette

Environmental modeling and environmental impact assessments final
Environmental modeling and environmental impact assessments finalEnvironmental modeling and environmental impact assessments final
Environmental modeling and environmental impact assessments final
Sanjay Singh
 
Unit 1: Principles Of Responsible Tourism
Unit 1: Principles Of Responsible TourismUnit 1: Principles Of Responsible Tourism
Unit 1: Principles Of Responsible Tourism
duanesrt
 
Unit 2: Responsible Tourism Product Development
Unit 2: Responsible Tourism Product DevelopmentUnit 2: Responsible Tourism Product Development
Unit 2: Responsible Tourism Product Development
duanesrt
 

En vedette (9)

Iee
IeeIee
Iee
 
PEISS
PEISSPEISS
PEISS
 
Environmental modeling and environmental impact assessments final
Environmental modeling and environmental impact assessments finalEnvironmental modeling and environmental impact assessments final
Environmental modeling and environmental impact assessments final
 
Unit 1: Principles Of Responsible Tourism
Unit 1: Principles Of Responsible TourismUnit 1: Principles Of Responsible Tourism
Unit 1: Principles Of Responsible Tourism
 
Unit 2: Responsible Tourism Product Development
Unit 2: Responsible Tourism Product DevelopmentUnit 2: Responsible Tourism Product Development
Unit 2: Responsible Tourism Product Development
 
EIA Methods
EIA MethodsEIA Methods
EIA Methods
 
Southeast Asia Technology Investment Landscape
Southeast Asia Technology Investment LandscapeSoutheast Asia Technology Investment Landscape
Southeast Asia Technology Investment Landscape
 
e-conomy SEA by Google and Temasek
e-conomy SEA by Google and Temaseke-conomy SEA by Google and Temasek
e-conomy SEA by Google and Temasek
 
Effluent Treatment Plant Design, Operation And Analysis Of Waste Water
Effluent Treatment Plant Design, Operation And Analysis Of Waste Water Effluent Treatment Plant Design, Operation And Analysis Of Waste Water
Effluent Treatment Plant Design, Operation And Analysis Of Waste Water
 

Similaire à Iee ppt

Similaire à Iee ppt (20)

LESCO- EIA report
LESCO- EIA reportLESCO- EIA report
LESCO- EIA report
 
Final eia of 500 kv t l lakhra pp
Final eia of 500 kv t l lakhra ppFinal eia of 500 kv t l lakhra pp
Final eia of 500 kv t l lakhra pp
 
ESIA 132kV Underground Single Circuit Transmission Line from Creek City Grid ...
ESIA 132kV Underground Single Circuit Transmission Line from Creek City Grid ...ESIA 132kV Underground Single Circuit Transmission Line from Creek City Grid ...
ESIA 132kV Underground Single Circuit Transmission Line from Creek City Grid ...
 
EIA Presentation Group-2 Final.pptx
EIA Presentation Group-2 Final.pptxEIA Presentation Group-2 Final.pptx
EIA Presentation Group-2 Final.pptx
 
Report on practical training NTPC BARH
Report on practical training NTPC BARHReport on practical training NTPC BARH
Report on practical training NTPC BARH
 
EIA Report of Orange Line Train
EIA Report of Orange Line TrainEIA Report of Orange Line Train
EIA Report of Orange Line Train
 
Esia of 132 k v interconnection scheme loop in out from existing boc dhabeji ...
Esia of 132 k v interconnection scheme loop in out from existing boc dhabeji ...Esia of 132 k v interconnection scheme loop in out from existing boc dhabeji ...
Esia of 132 k v interconnection scheme loop in out from existing boc dhabeji ...
 
Vijayakanth CV_ 27 Oct 15
Vijayakanth CV_ 27 Oct 15Vijayakanth CV_ 27 Oct 15
Vijayakanth CV_ 27 Oct 15
 
CV-1
CV-1CV-1
CV-1
 
Presentation project miel_ii
Presentation project miel_iiPresentation project miel_ii
Presentation project miel_ii
 
Critical Study on Kochi Barrage
Critical Study on Kochi BarrageCritical Study on Kochi Barrage
Critical Study on Kochi Barrage
 
-Project professionals: Ready for the future? Climate change, Leigh Woodcock
 -Project professionals: Ready for the future? Climate change, Leigh Woodcock -Project professionals: Ready for the future? Climate change, Leigh Woodcock
-Project professionals: Ready for the future? Climate change, Leigh Woodcock
 
Green infrastructure as a foundation for climate resilience and sustainabilit...
Green infrastructure as a foundation for climate resilience and sustainabilit...Green infrastructure as a foundation for climate resilience and sustainabilit...
Green infrastructure as a foundation for climate resilience and sustainabilit...
 
EIA Presentation.pptx
EIA Presentation.pptxEIA Presentation.pptx
EIA Presentation.pptx
 
kochi Metro
kochi Metrokochi Metro
kochi Metro
 
Curriculum vitae
Curriculum vitaeCurriculum vitae
Curriculum vitae
 
hydro-electric-power-plant-.pptx
hydro-electric-power-plant-.pptxhydro-electric-power-plant-.pptx
hydro-electric-power-plant-.pptx
 
Guest Lecture at University of Mataram (UNRAM).pdf
Guest Lecture at University of Mataram (UNRAM).pdfGuest Lecture at University of Mataram (UNRAM).pdf
Guest Lecture at University of Mataram (UNRAM).pdf
 
CV~PW~02-02-16 Opus
CV~PW~02-02-16 OpusCV~PW~02-02-16 Opus
CV~PW~02-02-16 Opus
 
Lgu services amp
Lgu services ampLgu services amp
Lgu services amp
 

Dernier

Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
KarakKing
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 

Dernier (20)

Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptx
 
Wellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxWellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptx
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 

Iee ppt

  • 2. Project Name: Power Distribution Enhancement Project Tranche – 3, Augmentation of PESCOSubprojects (Rehman Baba, Swabi, Bannu, D.I.Khan, Kotal Town Kohat, Jalala, Jehangir and Batal) Project Coordinator: PEPCO (Pakistan Electric Power Company)
  • 3.
  • 4. CONTENTS:  Introduction  Description of the Project  Description of Environmental and Social Conditions  Assessment of Environmental Impacts and Mitigation Measures  Institutional Requirements Environmental Management Plan  Public Consultation  Conclusion
  • 5. Introduction:  The Initial Environmental Examination (IEE) for the Tranche- 3 augmentation of 8 sub-projects proposed by the Peshawar Electricity Supply Company (PESCO)and have been submitted by PEPCO.  The sub project is to be financed under the Asian Development Bank’s (ADB) Power Distribution and Enhancement Multi-trance Finance Facility (PDEMFF).
  • 6. The proposed PDEMF facility has been designed to address both investments and institutional aspects in the electrical power sector. Surveys took place in July 2012. The field studies were undertaken by a core study team with experience of environmental assessment for power projects in Pakistan.
  • 7. Description of Project: Type of Project: Improvements to the equipment that supports the power distribution network at eight existing distribution sub-stations DGS. Beneficiaries of the project: People, companies, government and non- government agencies in Pakistan with improved, secure faster distribution services.
  • 8. Need of Project: The conditions of the power transmission system in Pakistan are presently inadequate to meet the rapidly increasing demand for electrical power. This situation limits national development and economic growth. To cope with the constraints, the existing power transmission infrastructure has to be improved and upgraded.
  • 9.  Replacement of an existing transformer in an existing DGS with a transformer of a higher capacity (augmentation) because the transformers are over loaded and needs urgent up gradation.  The Project Proponent (PESCO) plans to have the T3 completed by mid to late 2015.
  • 10. Sr. No. Name of Sub Station Voltage Total Capacity Capacity Added MVa Existing Capacity MVa 1. Rehman Baba 132/11 1x40 MVA 1x26 3x26 2. Swabi 132/11 1x40 MVA 1x16 3x26 3. Bannu 132/11 2x40 MVA 2x26 3x26 4. DI Khan 132/11 1x40 MVA 1x26 2x26 5. Kotal Town Kohat 132/11 1x40 MVA 1x26 3x26 6. Jalala 132/11 1x26 MVA 1x13 2x13 7 Jehangira 132/11 1x26 MVA 1x13 1x13+1x26 8. Batal 132/11 1x26 MVA --- 2x26
  • 11. Rehman Baba Kohat sub Station – Existing transformers
  • 13. Jehangira sub station – Space for extension extension Jalala- Switch yard
  • 14. DI Khan- Switchyard Swabi- Transformer to be replaced
  • 15. Description of Environment:  Project Area: The augmentation projects will all be within the eight (08) existing DGS and will not encroach on any land outside the sub-stations. PHYSICAL RESOURSES:  Topography, Geography, Geology, and Soils  Flat with the land sloping gently in a NE-SW direction.  Some sites like Mansehra, Swat and Dir are in more hilly areas.  The natural soils within the sub-station boundaries have been covered with cobblestones, bricks or concrete in various areas.
  • 16.  Climate: Little or no variation between the climate of the subproject areas.  Groundwater and Water Supply:  In most of the places where PHED supplies water, the water is of very good quality.  The local population is generally reliant on supply from tube wells, occasional open wells and hand pumps.  There should be no impact on these sources of water by the construction of the extension and augmentation subprojects. Surface water: The Indus River, River Swat, Pingkora River, Kabul River in Peshawar.
  • 17.  Air Quality:  Air quality appears fairly good based on observation during the study period.  Areas nearer the busy main roads are clearly impacted by vehicle fumes and dust.  It is unlikely that large powered mechanical equipment will be needed for the extension and augmentation projects other than delivery lorries and lifting cranes.  CO, SO2 and NO levels were in excess of the acceptable levels in some areas but the average levels were found below WHO standards.
  • 18. ECOLOGICALRESOURCES: No significant ecological resources, aquatic biological resources in the urban areas near the sub-projects are found. ECONOMICDEVELOPMENT:  Industries, Agriculture and Tourism: There are thousands of industrial and commercial businesses in the vicinity of the Tranche 3 augmentation sub-projects reliant on the efficient distribution of electrical power.
  • 19.  Transportation: The support systems for air, rail and road transport are all reliant to some extent on electrical power and thus the majority of the local population is reliant on the power network for transportation.  Social and Cultural Resources:  None of augmentation sub-projects will require relocation or resettlement.  No cultural and archeological sites are located in the vicinity of the any of the Tranche 3 augmentation sub-projects.
  • 20. Screening Potential Environmental Impacts & Mitigation Measures  In some cases few sensitive receivers (SR) are within a few meters of the DGS boundary walls and the SR’s are in the form of residential buildings, some schools and shops in the surrounding villages.  There will be potential impacts in the construction stage from disturbance and significant noise and dust if any of the residences and schools are close enough to sub-projects.  Water is available in the study area although surplus water may not always be available to suppress dust at many locations in the dry season.
  • 21.  Prevention of Ground Contamination:  Best measures to control oily residues should be included.  Transformer oil and lubricants may be released in the operational stage from maintenance.  Cultural Heritage, Temples, Religious Sites, Social Infrastructure:  No temples or religious sites are so close to the subproject works in the DGS as to expect a nuisance.
  • 22.  The clinic/hospitals are all well separated from the boundary walls of the sub-project DGS and there will be sufficient distance between the works and the SR. Cut and Fill and Waste Disposal  Projects should not require any significant cutting and filling.
  • 23.  Trees, Ecology and Protected Areas: If for some unforeseen reason Reserved Trees or other trees do need to be removed permission should be obtained from the forest authority after written justification.  Air Pollution from Rock Crushing, Cut, Fill, & Asphalt: In transmission line construction sand and aggregate are delivered directly to the tower location from the quarry / source, there is no intermediate or bulk storage of these materials.
  • 24. Noise, Vibration “Environmental quality standards for noise”  working hours: 6 .00 am to 10.00 pm Silence zone: An area comprising not less than 100 meters around hospitals, educational institutions and courts.
  • 25.  Mitigation measures are required to reduce residual impact to acceptable levels and achieve the expected outcomes of the project.  The IEE and EPM plan must be reviewed by the project management and approved by the EPA before any construction activity is initiated.  PESCO must prepare the future contractors to co-operate with all stakeholders in the mitigation of impacts.  Actions like monitoring and inspection must be taken to address unexpected impacts or not duly complied measurements. Institutional Requirements & Environmental Management Plan
  • 26. Public Consultation:  The public consultation (PC) process with various stakeholders has been approached so as to involve public and other stakeholders from the initial stages.  Public consultation has taken place during the planning and design stage.  Viewpoints of the stakeholders have been taken into account and their concerns and suggestions for possible improvements have been included where appropriate.
  • 27. Conclusion:  For initial environmental study potential environmental impacts were assessed in a comprehensive manner. Project is a feasible and sustainable option from the engineering, environmental, and socioeconomic points of view. Overall, report has provided a picture of all potential environmental impacts associated with the Project and recommended suitable mitigation measures.