This document provides an update on construction projects for Georgetown ISD funded by the 2010 bond program. It outlines additions and renovations at East View High School, including new academic, athletic, fine arts, and CTE buildings. It also describes additions and renovations at Georgetown High School, such as a new cafeteria, classroom, and athletics buildings. Completed projects including additions at East View High School, a new warehouse facility, and HVAC/roofing upgrades at Annie Purl Elementary are also summarized.
2. 2010 BOND PROGRAM UPDATE
TABLE OF CONTENTS
East View High School Phase 2 Additions, Package 2 3
Georgetown High School Additions and Renovations 7
Completed Projects 12
Huckabee
Georgetown Independent School District 2
3. 2010 BOND PROGRAM UPDATE General Contractor
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2
Original: $25,574,000
I
CATE Addition – $2,121,338
I
J
Baseball & Softball Turf - $880,000 New Athletic Addition
H
H Total - $28,575,338
F
G J
H
J
First Floor
Bid Package 1
A
B J
Existing East View
J High School B
A. New Athletic Addition
B. New Fine Arts Addition New Fine Arts Addition
D
E C. New Academic Addition
C
D. New CTE Building
New Academic Addition
E. New ROTC Addition (Alt.)
CR
10 F. New Tennis Courts
4
ay
29 G. New Tennis Building
hw
Hig H. New Baseball/Softball Fieldhouse,
Bleachers, Lighting & Pressbox
I. New Practice Fields
J. New Parking (1,070 spaces)
New Academic Addition
CTE Building
Second Floor New CTE/ROTC Addition
Academic Wing Softball Field House Huckabee
Georgetown Independent School District 3
4. 2010 BOND PROGRAM UPDATE
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2
Academic Addition
• Interior partition installation is nearing completion.
• Exterior masonry veneer is currently being installed around the academic wing.
• Roof structure, decking and insulation are in place. Finished metal roof panels will start
being installed next.
Athletic Addition
• Exterior masonry veneer is complete at the locker room addition
• Ceiling installation and wall painting has begun at the locker rooms.
• Exterior masonry veneer is currently being installed around the gym and is nearing
completion. Veneer installation at the gym enrty will begin next.
• Roof installation is complete at the gym roof. Roof installation at the gym entry will begin
next.
• Painting and lighting inside the gym will begin next.
CATE/ROTC
• Steel super-structure is in place for both east and west sides of the CATE.
• Masonry walls at the exterior are being constructed.
• Masonry walls for the storage mezzanine are being constructed. Once these are complete
the slab for the storage mezzanine will be poured.
Academic Corridor
Huckabee
Georgetown Independent School District 4
5. 2010 BOND PROGRAM UPDATE
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2
Academic Wing Gym & Locker Rooms
Huckabee
Georgetown Independent School District 5
6. 2010 BOND PROGRAM UPDATE
Gym Entry CATE
Huckabee
Georgetown Independent School District 6
7. 2010 BOND PROGRAM UPDATE Construction Manager
GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS
BAIRD WILLIAMS
Huckabee CONSTRUCTION
GEORGETOWN HIGH SCHOOL
BAIRD WILLIAMS
CONSTRUCTION
3D Rendering Project Manager
Front Entry
Boards.indd 4 7/26/11 8:55 AM
CTE Wing
Cafeteria
Athletics
Auditorium
Academic Athletics Athletics
Computer
Labs
Science
Labs
Library
Athletics
Special Education Academic
Fine
Arts
Huckabee
Georgetown Independent School District 7
8. 2010 BOND PROGRAM UPDATE
GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS
Phase I
CAFETERIA/CLASSROOM ADDITION
• Steel super-structure is in place. Steel roof decking is being installed.
• Perimeter and interior masonry walls are being constructed.
ATHLETICS ADDITION
• Masonry wall construction has begun.
• The remaining slab for the locker rooms is set to pour next.
KITCHEN RENOVATION
• Utility rough-in at existing slab is complete.
• Utility rough-in for new slab will begin next. Once rough-in is complete, the new kitchen
slab can be poured.
• New steel structure supporting the existing roof is in place.
EXISTING GYM & LOCKER ROOM RENOVATION
• Demolition of existing wood floor at lower gym is complete.
• Demolition of locker rooms at lower gym and upper gym is ongoing. Once demolition in
these areas is complete, utility rough-in for new locker rooms and restrooms can begin.
Cafeteria Interior
Huckabee
Georgetown Independent School District 8
9. 2010 BOND PROGRAM UPDATE
georgetown high school additions and renovations
Cafeteria Exterior Locker Room Addition
Huckabee
Georgetown Independent School District 9
10. 2010 BOND PROGRAM UPDATE
Kitchen Renovation Locker Room Demolition
Huckabee
Georgetown Independent School District 10
11. 2010 BOND PROGRAM UPDATE
GEORGETOWN HIGH SCHOOL AND RENOVATIONS
Athletic
Addition
Kitchen
Expansion
Cafeteria
Expansion
Classroom
Greenhouse Addition
Aerial
Huckabee
Georgetown Independent School District 11
12. 2010 BOND PROGRAM UPDATE
COMPLETED PROJECTS
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, NEW WAREHOUSE FACILITY ANNIE PURL ELEMENTARY SCHOOL
PACKAGE 1 ROOF AND HVAC MODIFICATION
Contract Amount: $5,321,000 Contract Amount: $641,000 Contract Amount: $229,000
Substantial Completion Date: August 19, 2011 Substantial Completion Date: November 9, 2011 Substantial Completion Date: August 12, 2011
General Contractor: Charter Builders General Contractor: CSS, Inc. General Contractor: Saratoga
Field House Locker Room Interior View of Warehouse New HVAC Unit and Roofing
Field House Weight Room Storage Shed New Ceiling and Light Fixtures
Huckabee
Georgetown Independent School District 12