SlideShare une entreprise Scribd logo
1  sur  11
Télécharger pour lire hors ligne
GEORGETOWN ISD
2010 BOND PROGRAM UPDATE




     N O V E MB E R 2 011
                            Huckabee
2010 BOND PROGRAM UPDATE




                                                        TABLE OF CONTENTS

                               East View High School Phase 2 Additions, Package 1         3

                               East View High School Phase 2 Additions, Package 2         4

                               New Warehouse Facility                                     7

                               Annie Purl Elementary School Roof and HVAC Modifications   8

                               Georgetown High School Additions and Renovations           9




                                                                                              Huckabee
Georgetown Independent School District                                                               2
2010 BOND PROGRAM UPDATE                                                     General Contractor




                             EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 1
                                               PROGRESS REPORT

                                                                                             MILESTONE DATES
                                                                 Schematic Design Presentation                        November 11, 2010
                                                                 Architect Signs Documents                            November 24, 2010
                                                                 Pre-Proposal Meeting                                 December 8, 2010
                                                                 Proposal Part A Due                                  December 21, 2010
                                                                 Proposal Part B Due                                  December 22, 2010
                                                                 Proposal Evaluations                                 January 4, 2011
                                                                 General Contractor Recommendation to School Board    January 10, 2011
                                                                 First Owner/CO Meeting                               February 15, 2011
   Field House Locker Room
                                                                 Construction Start Date                              February 18, 2011
                                                                 Building Permit Issued                               March 16, 2011
                                                                 Owner, Architect and Contractor Meeting              June 7, 2011
                                                                 Owner, Architect and Contractor Meeting              June 21, 2011
                                                                 Owner, Architect and Contractor Meeting              July 5, 2011
                                                                 Owner, Architect and Contractor Meeting              July 19, 2011
                                                                 Substantial Completion (Field/Track and Bleachers)   August 1, 2011
                                                                 Owner, Architect and Contractor Meeting              August 2, 2011
                                                                 Owner, Architect and Contractor Meeting              August 16, 2011
                                                                 Substantial Completion (Buildings)                   August 19, 2011

   Field House Weight Room
                                                                                                                      Huckabee
Georgetown Independent School District                                                                                                     3
2010 BOND PROGRAM UPDATE                                                                                                                General Contractor




                                                     EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2
                                                                                                                               Original: $25,574,000
                                         I
                                                                                                                            CATE Addition – $2,121,338
                                I
                                                             J
                                                                                                                         Baseball & Softball Turf - $880,000                                                                                           New Athletic Addition

                                                         H
                                                                     H                                                          Total - $28,575,338
                                                                                           F

                                                                                       G                 J
                                                                 H


                                                                                                                 J
                                                                                                                                                                                  First Floor
                Bid Package 1
                                                                                               A


                                                                                                    B                J
                                                                          Existing East View
                                                 J                           High School                     B
                                                                                                                              A. New Athletic Addition
                                                                                                                              B. New Fine Arts Addition                                                                                                     New Fine Arts Addition
                                                     D
                                                         E                                                                    C. New Academic Addition
                                                                 C
                                                                                                                              D. New CTE Building
                                                                                                                                                                     New Academic Addition
                                                                                                                              E. New ROTC Addition (Alt.)
                                    CR
                                         10                                                                                   F. New Tennis Courts
                                             4
                                                                                                 ay
                                                                                                    29                        G. New Tennis Building
                                                                                               hw
                                                                                        Hig                                   H. New Baseball/Softball Fieldhouse,
                                                                                                                                 Bleachers, Lighting & Pressbox
                                                                                                                              I. New Practice Fields
                                                                                                                              J. New Parking (1,070 spaces)




                                                                                                                                                                                                       New Academic Addition




                                                                         CTE Building


                                                                                                                                                                                             Second Floor                      New CTE/ROTC Addition




Academic Wing                                                            Softball Field House                                                                                                                                                Huckabee
Georgetown Independent School District                                                                                                                                                                                                                                         4
2010 BOND PROGRAM UPDATE                                                                      General Contractor




                                         EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2
                                                                                  PROGRESS REPORT
   ATHLETIC ADDITION                                                                                                              MILESTONE DATES
   •	  Concrete slab and plumbing risers are in place.
   •	  CMU wall along the existing building has been started.                                   Schematic Design Presentation                                       January 1, 2011
   •	  Steel structure installation is scheduled to begin next.                                 Architect Signs Documents                                           March 8, 2011
   ACADEMIC ADDITION
   •	 Concrete slab is complete.
                                                                                                Building Permit Application Submittal                               March 15, 2011
   •	 Steel structure installation has begun.                                                   Site Plan Application Submittal                                     March 17, 2011
   •	 Metal door frames have arrived on site.
   CATE/ROTC
                                                                                                Pre-Proposal Meeting                                                March 22, 2011
   •	  Digging for exterior grade beams has begun.                                              Tour with General Contractors at East View Ninth Grade Center       March 30, 2011
   •	  Underground plumbing and electrical utilities are making progress.
   •	  Concrete slab is scheduled to be in place by the end of November.                        Proposal Part A Due                                                 April 7, 2011
   •	  The steel building frame is scheduled to arrive at the beginning of December.
                                                                                                Proposal Part B Due                                                 April 8, 2011
   FINE ARTS
   Drama                                                                                        Proposal Evaluations                                                April 11, 2011
   •	   Steel structure installation is complete.
                                                                                                Received City Building Dept. Plan Review Comments                   April 14, 2011
   •	   Mezzanine slab is in place.
   •	    Steel roof joists are in place.                                                        General Contractor Recommendation to School Board                   April 18, 2011
   •	   CMU walls have begun.
   Orchestra                                                                                    Received City Planning Dept. Plan Review Comments                   April 25, 2011
   •	    Steel structure installation is complete.
                                                                                                Construction Start Date                                             May 19, 2011
   •	   Steel roof joists are in place, and the roof decking has begun.
   •	   CMU walls have begun.                                                                   First Owner/CO Meeting                                              May 24, 2011
   •	   Interior	electrical	conduits	and	roofing	are	scheduled	to	begin	next.
                                                                                                Building Permit Issued                                              June 1, 2011
   BASEBALL/SOFTBALL COMPLEX
   •	  CMU walls are in place for the dugouts. Steel structure and roof decking have begun.     Owner, Architect and Contractor Meeting                             August 30, 2011
   •	  Foundations for the press boxes are complete. CMU walls have begun.
   •	  CMU	walls	for	field	house	are	making	progress.	Mezzanine	slab	is	in	place.               Owner, Architect and Contractor Meeting                             October 11, 2011
   •	  Roof decking on the tennis building is scheduled to begin next. New courts will be       Owner, Architect and Contractor Meeting                             October 25, 2011
       starting in mid-November.
   •	  Progress is being made on the grading, paving and painting of various parking lots and   Owner, Architect and Contractor Meeting                             November 1, 2011
       drives across the site.
                                                                                                Substantial Completion                                              June 27, 2012

                                                                                                                                                                Huckabee
Georgetown Independent School District                                                                                                                                                 5
2010 BOND PROGRAM UPDATE


                               EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2




         Academic Addition                                       Athletic and Fine Arts Additions




         Interior View of Drama Classroom and Black Box          Baseball Dugout
                                                                                                    Huckabee
Georgetown Independent School District                                                                     6
2010 BOND PROGRAM UPDATE


                                           NEW WAREHOUSE FACILITY
                                               PROGRESS REPORT


                                                                                            MILESTONE DATES
                                                                 Schematic Design Presentation                        January 10, 2011
                                                                 Architect Signs Documents                            January 12, 2011
                                                                 Building Permit Application Submittal                January 25, 2011
                                                                 Proposal Part A Due                                  February 15, 2011
                                                                 Proposal Part B Due                                  February 16, 2011
                                                                 Site Plan Application Submittal                      February 17, 2011
                                                                 Proposal Evaluations                                 February 17, 2011
                                                                 Landscaping Plans Approved                           March 1, 2011
         Interior View of Warehouse
                                                                 General Contractor Recommendation to School Board    March 7, 2011
                                                                 Job Coordination Meeting                             March 25, 2011
                                                                 Grading/Utilities Permit Received                    March 31, 2011
                                                                 First Amended Administrative Exception Submitted     April 18, 2011
                                                                 Second Amended Administrative Exception Submitted    April 20, 2011
                                                                 Final Planning Dept. Comments Received               April 25, 2011
                                                                 Building Permit Issued                               April 28, 2011
                                                                 First Owner/CO Meeting                               May 5, 2011
                                                                 Construction Start Date                              May 9, 2011
                                                                 Substantial Completion                               October 21, 2011


         Storage Shed
                                                                                                                     Huckabee
Georgetown Independent School District                                                                                                    7
2010 BOND PROGRAM UPDATE                                                           General Contractor




                     ANNIE PURL ELEMENTARY SCHOOL ROOF AND HVAC MODIFICATIONS
                                                Contract Amount: $229,000


                                                                                                      MILESTONE DATES
                                                                            Schematic Design Presentation                        January 10, 2011
                                                                            Architect Signs Documents                            February 3, 2011
                                                                            Pre-Proposal Meeting                                 February 9, 2011
                                                                            Proposal Part A Due                                  February 22, 2011
                                                                            Proposal Part B Due                                  February 23, 2011
                                                                            Proposal Evaluations                                 February 24, 2011
                                                                            Building Permit Issued                               March 2, 2011
                                                                            General Contractor Recommended to School Board       March 7, 2011
         New HVAC Unit and Roofing
                                                                            First Owner/CO Meeting                               May 24, 2011
                                                                            Construction Start Date                              June 6, 2011
                                                                            Substantial Completion                               August 12, 2011




         New Ceiling and Light Fixtures
                                                                                                                             Huckabee
Georgetown Independent School District                                                                                                               8
2010 BOND PROGRAM UPDATE                                                                                                   Construction Manager




                          GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS
                                                                                                                                                                                                       BAIRD WILLIAMS
                                                                             Huckabee                                                                                                                  CONSTRUCTION
                                                                                                               GEORGETOWN HIGH SCHOOL
                                                                                   BAIRD WILLIAMS
                                                                                   CONSTRUCTION
                                                                                                               3D Rendering                                                                            Project Manager




                                                                                                                                                 Front Entry
                                                       Boards.indd 4                                                                                       7/26/11 8:55 AM




                              CTE Wing




                                                                       Cafeteria
                                                                                                                                                                                          Athletics
                                                                                                                                                                             Auditorium
                                            Academic                                                                   Athletics     Athletics
                                                                                                    Computer
                                                                                                      Labs
                              Science
                               Labs




                                          Library
                                                                                                                                                                                           Athletics
                      Special Education                                                                                            Academic



                                                                                                                Fine
                                                                                                                Arts

                                                                                                                                                                                                       Huckabee
Georgetown Independent School District                                                                                                                                                                                   9
2010 BOND PROGRAM UPDATE


                                   GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS
                                     MILESTONE DATES                                        MILESTONE DATES
     Design Kick-off Meeting with Librarian, Science Dept.                                               Material selection with GHS staff                        June 30, 2011
                                                                           February 28, 2011
     and Nurse                                                                                           Cost Review with Construction Manager                    July 19, 2011
     Design Kick-off Meeting with Athletics                                March 1, 2011
                                                                                                         Interiors Presentation                                   July 25, 2011
     Initial Construction Phasing with Stakeholders                        March 3, 2011
                                                                                                         Architect Signs Documents for Site Utility Package       July 26, 2011
     Design Kick-off Meeting with Special Education                        March 4, 2011                 CD Coordination Meeting on Site with Architect, Owner
                                                                                                                                                                  July 27, 2011
     Design Kick-off Meeting with Administration                           March 10, 2011                and Construction Manager
     Advertisement for Construction Manager at Risk RFQ                    March 12, 2011                Final Review of FF&E with GHS staff                      July 27, 2011
     Received Construction Manager at Risk Step 1                                                        City Comments Received for Site Utility package          August 8, 2011
                                                                           March 29, 2011
     (Qualifications)                                                                                    100 % CD Review                                          August 15, 2011
     Evaluation Team Grades and Develops Recommended Short List            March 30, 2011
                                                                                                         Site Utility Package Bid                                 August 17, 2011
     Facility Assessment of ADA, Code and Existing Conditions              March 29 - 30, 2011
                                                                                                         Review Comments Due                                      August 22, 2011
     School Board Receives Recommended Short List                          April 4, 2011
                                                                                                         Guaranteed Maximum Price on Site Utility Package         August 29, 2011
     Step 2 of RFQ Submitted to Short Listed Contractors
                                                                           April 5, 2011                 Architect Signs Documents                                September 1, 2011
     (Fees and General Conditions)
                                                                                                         Pre-Bid                                                  September 21, 2011
     Fees and General Conditions due by 3 PM                               April 8, 2011
                                                                                                         Pre-Bid (Technology)                                     September 23, 2011
     Board of Trustees Select Construction Manager at Risk                 April 18, 2011
     First Meeting with District, Architect, Project Manager and                                         Bid                                                      October 4, 2011
                                                                           April 19, 2011
     Construction Manager                                                                                Guaranteed Maximum Price Presented to School Board       October 17, 2011
     Site Logistics Survey with District, Architect, Project Manager and                                 Construction Start Date                                  October 18, 2011
                                                                           April 29, 2011
     Construction Manager
                                                                                                         CO Meeting                                               October 27, 2011
     Schematic Design Presentation                                         June 6, 2011
                                                                                                         Substantial Completion                                   July 2013
     Kitchen Design Review with Staff                                      June 14, 2011
     Site Coordination Meeting with Architect, Owner and
                                                                           June 16, 2011
     Construction Manager                                                                                                                                        Huckabee
Georgetown Independent School District                                                                                                                                                 10
2010 BOND PROGRAM UPDATE


                                GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS

     SITE UTILITy PACkAgE – PHASE I
     •	 Transformer and pad are set and complete.
     •	 Steel canopy at the cafeteria has been torn down.
     •	 Trench is being dug for gas line.
     •	 Dirt work and foundation prep will begin within the next week.
     •	 Utility stubs and grade beams will begin after the dirt work is complete.
     •	 Interior demolition will start during Christmas break.




                                                                                    Site




                                                                                    Canopy Demolition
                                                                                                        Huckabee
Georgetown Independent School District                                                                        11

Contenu connexe

En vedette

Linear structures lightning talk
Linear structures lightning talkLinear structures lightning talk
Linear structures lightning talkJack Fox
 
F# for functional enthusiasts
F# for functional enthusiastsF# for functional enthusiasts
F# for functional enthusiastsJack Fox
 
Functional programming for production quality code
Functional programming for production quality codeFunctional programming for production quality code
Functional programming for production quality codeJack Fox
 
Soft rock in argentina
Soft rock in argentinaSoft rock in argentina
Soft rock in argentinarichio
 
Semantically coherent functional linear data structures
Semantically coherent functional linear data structuresSemantically coherent functional linear data structures
Semantically coherent functional linear data structuresJack Fox
 
Intoduction to Homotopy Type Therory
Intoduction to Homotopy Type TheroryIntoduction to Homotopy Type Therory
Intoduction to Homotopy Type TheroryJack Fox
 
Type Theory and Practical Application
Type Theory and Practical ApplicationType Theory and Practical Application
Type Theory and Practical ApplicationJack Fox
 

En vedette (11)

2011 2012 proposed budget 03-21-11
2011 2012 proposed budget 03-21-112011 2012 proposed budget 03-21-11
2011 2012 proposed budget 03-21-11
 
Linear structures lightning talk
Linear structures lightning talkLinear structures lightning talk
Linear structures lightning talk
 
F# for functional enthusiasts
F# for functional enthusiastsF# for functional enthusiasts
F# for functional enthusiasts
 
Functional programming for production quality code
Functional programming for production quality codeFunctional programming for production quality code
Functional programming for production quality code
 
Soft rock in argentina
Soft rock in argentinaSoft rock in argentina
Soft rock in argentina
 
AEIS 2012 Georgetown ISD Presentation
AEIS 2012 Georgetown ISD PresentationAEIS 2012 Georgetown ISD Presentation
AEIS 2012 Georgetown ISD Presentation
 
Financial Presentation July 2014
Financial Presentation July 2014Financial Presentation July 2014
Financial Presentation July 2014
 
Semantically coherent functional linear data structures
Semantically coherent functional linear data structuresSemantically coherent functional linear data structures
Semantically coherent functional linear data structures
 
Intoduction to Homotopy Type Therory
Intoduction to Homotopy Type TheroryIntoduction to Homotopy Type Therory
Intoduction to Homotopy Type Therory
 
Georgetown ISD Elementary School #11
Georgetown ISD Elementary School #11Georgetown ISD Elementary School #11
Georgetown ISD Elementary School #11
 
Type Theory and Practical Application
Type Theory and Practical ApplicationType Theory and Practical Application
Type Theory and Practical Application
 

Plus de Georgetown Independent School District

Plus de Georgetown Independent School District (20)

Georgetown ISD Financial Presentation June 2014
Georgetown ISD Financial Presentation June 2014Georgetown ISD Financial Presentation June 2014
Georgetown ISD Financial Presentation June 2014
 
2013-2014 Budget Update Presentation
2013-2014 Budget Update Presentation2013-2014 Budget Update Presentation
2013-2014 Budget Update Presentation
 
AYP 2012 Georgetown ISD Presentation
AYP 2012 Georgetown ISD PresentationAYP 2012 Georgetown ISD Presentation
AYP 2012 Georgetown ISD Presentation
 
Huckabee Presentat
Huckabee PresentatHuckabee Presentat
Huckabee Presentat
 
Schools First Financial Reports
Schools First Financial ReportsSchools First Financial Reports
Schools First Financial Reports
 
Tax Ratification Election Presentation
Tax Ratification Election PresentationTax Ratification Election Presentation
Tax Ratification Election Presentation
 
GISD Budget and Finance Overview 2012
GISD Budget and Finance Overview 2012GISD Budget and Finance Overview 2012
GISD Budget and Finance Overview 2012
 
2012-2013 Elementary Scheduling
2012-2013 Elementary Scheduling2012-2013 Elementary Scheduling
2012-2013 Elementary Scheduling
 
SHW Construction Update - April 2012
SHW Construction Update - April 2012SHW Construction Update - April 2012
SHW Construction Update - April 2012
 
03-26-12 McCoy Project Update
03-26-12 McCoy Project Update03-26-12 McCoy Project Update
03-26-12 McCoy Project Update
 
STAAR High School Presentation
STAAR High School PresentationSTAAR High School Presentation
STAAR High School Presentation
 
STAAR Grade 3-8 Presentation
STAAR Grade 3-8 PresentationSTAAR Grade 3-8 Presentation
STAAR Grade 3-8 Presentation
 
AYP 2010-2011 Presentation
AYP 2010-2011 PresentationAYP 2010-2011 Presentation
AYP 2010-2011 Presentation
 
AEIS Report Presentation
AEIS Report PresentationAEIS Report Presentation
AEIS Report Presentation
 
SHW Update 02-06-2012
SHW Update 02-06-2012SHW Update 02-06-2012
SHW Update 02-06-2012
 
Huckabee Update 02-06-2012
Huckabee Update 02-06-2012Huckabee Update 02-06-2012
Huckabee Update 02-06-2012
 
SHW Update 01-10-2012
SHW Update 01-10-2012SHW Update 01-10-2012
SHW Update 01-10-2012
 
Huckabee Update 01-10-2012
Huckabee Update 01-10-2012Huckabee Update 01-10-2012
Huckabee Update 01-10-2012
 
A Report to Citizens
A Report to CitizensA Report to Citizens
A Report to Citizens
 
SHW Project Update 12-05-11
SHW Project Update 12-05-11SHW Project Update 12-05-11
SHW Project Update 12-05-11
 

Dernier

Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxAshokKarra1
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Seán Kennedy
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4MiaBumagat1
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxCarlos105
 
Activity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationActivity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationRosabel UA
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptxiammrhaywood
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfErwinPantujan2
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxlancelewisportillo
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...Postal Advocate Inc.
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfVanessa Camilleri
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4JOYLYNSAMANIEGO
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYKayeClaireEstoconing
 

Dernier (20)

Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptx
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
 
Activity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationActivity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translation
 
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptxYOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdf
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
 

Huckabee Update 11/07/2011

  • 1. GEORGETOWN ISD 2010 BOND PROGRAM UPDATE N O V E MB E R 2 011 Huckabee
  • 2. 2010 BOND PROGRAM UPDATE TABLE OF CONTENTS East View High School Phase 2 Additions, Package 1 3 East View High School Phase 2 Additions, Package 2 4 New Warehouse Facility 7 Annie Purl Elementary School Roof and HVAC Modifications 8 Georgetown High School Additions and Renovations 9 Huckabee Georgetown Independent School District 2
  • 3. 2010 BOND PROGRAM UPDATE General Contractor EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 1 PROGRESS REPORT MILESTONE DATES Schematic Design Presentation November 11, 2010 Architect Signs Documents November 24, 2010 Pre-Proposal Meeting December 8, 2010 Proposal Part A Due December 21, 2010 Proposal Part B Due December 22, 2010 Proposal Evaluations January 4, 2011 General Contractor Recommendation to School Board January 10, 2011 First Owner/CO Meeting February 15, 2011 Field House Locker Room Construction Start Date February 18, 2011 Building Permit Issued March 16, 2011 Owner, Architect and Contractor Meeting June 7, 2011 Owner, Architect and Contractor Meeting June 21, 2011 Owner, Architect and Contractor Meeting July 5, 2011 Owner, Architect and Contractor Meeting July 19, 2011 Substantial Completion (Field/Track and Bleachers) August 1, 2011 Owner, Architect and Contractor Meeting August 2, 2011 Owner, Architect and Contractor Meeting August 16, 2011 Substantial Completion (Buildings) August 19, 2011 Field House Weight Room Huckabee Georgetown Independent School District 3
  • 4. 2010 BOND PROGRAM UPDATE General Contractor EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2 Original: $25,574,000 I CATE Addition – $2,121,338 I J Baseball & Softball Turf - $880,000 New Athletic Addition H H Total - $28,575,338 F G J H J First Floor Bid Package 1 A B J Existing East View J High School B A. New Athletic Addition B. New Fine Arts Addition New Fine Arts Addition D E C. New Academic Addition C D. New CTE Building New Academic Addition E. New ROTC Addition (Alt.) CR 10 F. New Tennis Courts 4 ay 29 G. New Tennis Building hw Hig H. New Baseball/Softball Fieldhouse, Bleachers, Lighting & Pressbox I. New Practice Fields J. New Parking (1,070 spaces) New Academic Addition CTE Building Second Floor New CTE/ROTC Addition Academic Wing Softball Field House Huckabee Georgetown Independent School District 4
  • 5. 2010 BOND PROGRAM UPDATE General Contractor EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2 PROGRESS REPORT ATHLETIC ADDITION MILESTONE DATES • Concrete slab and plumbing risers are in place. • CMU wall along the existing building has been started. Schematic Design Presentation January 1, 2011 • Steel structure installation is scheduled to begin next. Architect Signs Documents March 8, 2011 ACADEMIC ADDITION • Concrete slab is complete. Building Permit Application Submittal March 15, 2011 • Steel structure installation has begun. Site Plan Application Submittal March 17, 2011 • Metal door frames have arrived on site. CATE/ROTC Pre-Proposal Meeting March 22, 2011 • Digging for exterior grade beams has begun. Tour with General Contractors at East View Ninth Grade Center March 30, 2011 • Underground plumbing and electrical utilities are making progress. • Concrete slab is scheduled to be in place by the end of November. Proposal Part A Due April 7, 2011 • The steel building frame is scheduled to arrive at the beginning of December. Proposal Part B Due April 8, 2011 FINE ARTS Drama Proposal Evaluations April 11, 2011 • Steel structure installation is complete. Received City Building Dept. Plan Review Comments April 14, 2011 • Mezzanine slab is in place. • Steel roof joists are in place. General Contractor Recommendation to School Board April 18, 2011 • CMU walls have begun. Orchestra Received City Planning Dept. Plan Review Comments April 25, 2011 • Steel structure installation is complete. Construction Start Date May 19, 2011 • Steel roof joists are in place, and the roof decking has begun. • CMU walls have begun. First Owner/CO Meeting May 24, 2011 • Interior electrical conduits and roofing are scheduled to begin next. Building Permit Issued June 1, 2011 BASEBALL/SOFTBALL COMPLEX • CMU walls are in place for the dugouts. Steel structure and roof decking have begun. Owner, Architect and Contractor Meeting August 30, 2011 • Foundations for the press boxes are complete. CMU walls have begun. • CMU walls for field house are making progress. Mezzanine slab is in place. Owner, Architect and Contractor Meeting October 11, 2011 • Roof decking on the tennis building is scheduled to begin next. New courts will be Owner, Architect and Contractor Meeting October 25, 2011 starting in mid-November. • Progress is being made on the grading, paving and painting of various parking lots and Owner, Architect and Contractor Meeting November 1, 2011 drives across the site. Substantial Completion June 27, 2012 Huckabee Georgetown Independent School District 5
  • 6. 2010 BOND PROGRAM UPDATE EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2 Academic Addition Athletic and Fine Arts Additions Interior View of Drama Classroom and Black Box Baseball Dugout Huckabee Georgetown Independent School District 6
  • 7. 2010 BOND PROGRAM UPDATE NEW WAREHOUSE FACILITY PROGRESS REPORT MILESTONE DATES Schematic Design Presentation January 10, 2011 Architect Signs Documents January 12, 2011 Building Permit Application Submittal January 25, 2011 Proposal Part A Due February 15, 2011 Proposal Part B Due February 16, 2011 Site Plan Application Submittal February 17, 2011 Proposal Evaluations February 17, 2011 Landscaping Plans Approved March 1, 2011 Interior View of Warehouse General Contractor Recommendation to School Board March 7, 2011 Job Coordination Meeting March 25, 2011 Grading/Utilities Permit Received March 31, 2011 First Amended Administrative Exception Submitted April 18, 2011 Second Amended Administrative Exception Submitted April 20, 2011 Final Planning Dept. Comments Received April 25, 2011 Building Permit Issued April 28, 2011 First Owner/CO Meeting May 5, 2011 Construction Start Date May 9, 2011 Substantial Completion October 21, 2011 Storage Shed Huckabee Georgetown Independent School District 7
  • 8. 2010 BOND PROGRAM UPDATE General Contractor ANNIE PURL ELEMENTARY SCHOOL ROOF AND HVAC MODIFICATIONS Contract Amount: $229,000 MILESTONE DATES Schematic Design Presentation January 10, 2011 Architect Signs Documents February 3, 2011 Pre-Proposal Meeting February 9, 2011 Proposal Part A Due February 22, 2011 Proposal Part B Due February 23, 2011 Proposal Evaluations February 24, 2011 Building Permit Issued March 2, 2011 General Contractor Recommended to School Board March 7, 2011 New HVAC Unit and Roofing First Owner/CO Meeting May 24, 2011 Construction Start Date June 6, 2011 Substantial Completion August 12, 2011 New Ceiling and Light Fixtures Huckabee Georgetown Independent School District 8
  • 9. 2010 BOND PROGRAM UPDATE Construction Manager GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS BAIRD WILLIAMS Huckabee CONSTRUCTION GEORGETOWN HIGH SCHOOL BAIRD WILLIAMS CONSTRUCTION 3D Rendering Project Manager Front Entry Boards.indd 4 7/26/11 8:55 AM CTE Wing Cafeteria Athletics Auditorium Academic Athletics Athletics Computer Labs Science Labs Library Athletics Special Education Academic Fine Arts Huckabee Georgetown Independent School District 9
  • 10. 2010 BOND PROGRAM UPDATE GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS MILESTONE DATES MILESTONE DATES Design Kick-off Meeting with Librarian, Science Dept. Material selection with GHS staff June 30, 2011 February 28, 2011 and Nurse Cost Review with Construction Manager July 19, 2011 Design Kick-off Meeting with Athletics March 1, 2011 Interiors Presentation July 25, 2011 Initial Construction Phasing with Stakeholders March 3, 2011 Architect Signs Documents for Site Utility Package July 26, 2011 Design Kick-off Meeting with Special Education March 4, 2011 CD Coordination Meeting on Site with Architect, Owner July 27, 2011 Design Kick-off Meeting with Administration March 10, 2011 and Construction Manager Advertisement for Construction Manager at Risk RFQ March 12, 2011 Final Review of FF&E with GHS staff July 27, 2011 Received Construction Manager at Risk Step 1 City Comments Received for Site Utility package August 8, 2011 March 29, 2011 (Qualifications) 100 % CD Review August 15, 2011 Evaluation Team Grades and Develops Recommended Short List March 30, 2011 Site Utility Package Bid August 17, 2011 Facility Assessment of ADA, Code and Existing Conditions March 29 - 30, 2011 Review Comments Due August 22, 2011 School Board Receives Recommended Short List April 4, 2011 Guaranteed Maximum Price on Site Utility Package August 29, 2011 Step 2 of RFQ Submitted to Short Listed Contractors April 5, 2011 Architect Signs Documents September 1, 2011 (Fees and General Conditions) Pre-Bid September 21, 2011 Fees and General Conditions due by 3 PM April 8, 2011 Pre-Bid (Technology) September 23, 2011 Board of Trustees Select Construction Manager at Risk April 18, 2011 First Meeting with District, Architect, Project Manager and Bid October 4, 2011 April 19, 2011 Construction Manager Guaranteed Maximum Price Presented to School Board October 17, 2011 Site Logistics Survey with District, Architect, Project Manager and Construction Start Date October 18, 2011 April 29, 2011 Construction Manager CO Meeting October 27, 2011 Schematic Design Presentation June 6, 2011 Substantial Completion July 2013 Kitchen Design Review with Staff June 14, 2011 Site Coordination Meeting with Architect, Owner and June 16, 2011 Construction Manager Huckabee Georgetown Independent School District 10
  • 11. 2010 BOND PROGRAM UPDATE GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS SITE UTILITy PACkAgE – PHASE I • Transformer and pad are set and complete. • Steel canopy at the cafeteria has been torn down. • Trench is being dug for gas line. • Dirt work and foundation prep will begin within the next week. • Utility stubs and grade beams will begin after the dirt work is complete. • Interior demolition will start during Christmas break. Site Canopy Demolition Huckabee Georgetown Independent School District 11