SlideShare une entreprise Scribd logo
1  sur  22
HYDROTEST
SDP-1 V.P.SHUKLA
TESTS
• DESTRUCTIVE TESTS
– Tensile, Impact, Bend etc
• NON-DESTRUCTIVE TESTS
– Radiography
– Ultrasonic
– Dye Penetration
– Magnetic Particle
– Leak tests like Air test,Ammonia test etc.
– Hydrostatic test
WHY HYDROSTATIC TEST
• To ensure the integrity of the equipment
• To ensure the strength of the weld joints &
material
• To ensure the strength of the nozzle flange
joints
• To relieve the stresses
• Ensures safe and reliable performance
during the operational life
HYDRO TEST
• Good planning is essential for completion
of hydrotest in minimum possible time
•Gauges, transducer/ recorder , Sq. Bar,
Hose pipes, Pump
•Location, weight distribution, draining
•Saddles, slope, venting
•Water- quantity,quality & temperature
•Torque tightening / tensioning units
•Flanges, bolts / studs
HYDRO TEST
• The hydro test saddles shall be located on
shell in such a way that all circumferential
seams are free from saddle location. Long
seams if any covered by the saddle; the
corresponding location of saddle material
shall be grooved to facilitate the inspection
of weld joint under test
Sketch for Hydro test
Valves
Pressure Gauge
Towards Venting pipe
Arrangement for Outlet Pressure Gauge
Square Bar
Coupling
From Hydrotest
Pump
Towards Drain
Valves
Pressure Gauge
Square Bar
Coupling
Arrangement for Inlet Pressure Gauge
HYDRO TEST
• Carry out tightening of Nozzle / Man
way covers as per the required
torque
• Use proper tightening unit to meet the
requirement of PSI / Torque and follow
the tightening sequence as per
approved procedure for bolts / studs
• Start filling water after confirmation of
all requirements ( like venting, PPM of
water, Clearance of Job for fill up)
1
2
34
5
6 7
8
TIGHTENING SEQUENCE
(with torque tightening unit)
1
1
22
3
3
4
4
5
5
6
6
7
7
8
8
TIGHTENING SEQUENCE
(with tensioning unit)
HYDRO TEST
• Ensure that the nozzles (top) are
open for air removal
• Let the water flow out of the top
nozzles so that the air is removed
• Close the nozzle & allow the water to
flow from top and confirm absence of
air bubbles
AIR LOCK REMOVAL
1 VESSEL IN HORIZONTAL, INCLINED AT 5 DEG.
Packing
AIR LOCK REMOVAL
2 WHEN INTERNALS LIKE TSRs PROVIDED INSIDE THE VESSEL
AIR LOCK REMOVAL
3 NOZZLES ON DISHEND
HYDRO TEST
• Start the pump for pressurizing the
water inside the equipment. (Selection
of pump depends on the pressure and
discharge of water from pump. Set the
output pressure of pump such that it
should not exceed hydro test pressure
for safer operation)
HYDRO TEST
• Ensure that minimum two pressure
gauges are attached
• The pressure gauges shall have an upper
range of 2 times the test pressure but in
no case less than 1.5 times or more than
4 times the test pressure. The transducer
shall have minimum upper range of 1.25
times the test pressure. Only calibrated
pressure gauge and transducer shall be
used. Validity of calibration shall be
verified on the calibration sticker pasted
on the pressure indicators
HYDRO TEST
• Increase the pressure as per the
requirement given in drawing or the
approved procedure
• During pressurizing from design
pressure to test pressure, no one
shall remain on the vessel or very
near to bolted connections on the
vessel
HYDRO TEST
• Hold the test pressure for minimum
30 minutes or as specified by the
drawing / specification. The test
pressure shall not get dropped
during the holding time. The vessel
connections shall not be inspected
closely for any leakage at this stage
HYDRO TEST
• Reduce the pressure to Design
pressure
• Check for any leakage in weld joints
and bolted joints
• If no leakage is observed,
depressurizing can be started
HYDRO TEST
Depressurizing :
• If cycle is specified , follow the same
• If not specified, reduce pressure
slowly by opening the square bars (at
top) such that pressure drops to zero
• Never open bottom noz./ Sq. bar
• While draining the vessel, the top vent
valve shall be kept open before
opening any nozzle at the bottom. This
is for eliminating the possible collapse
of thin shells due to vacuum created
within the test vessel
HYDRO TEST
• Pressure gauges once used for a
pressure test shall be recalibrated. For
this purpose, the pressure gauges
once used shall be crossed on the
calibration sticker and send to QA

Contenu connexe

Tendances

Pressure safety valves
Pressure safety valvesPressure safety valves
Pressure safety valves
Amol Dudhate
 
Piping sample report
Piping sample reportPiping sample report
Piping sample report
ram111eg
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and Commissioning
Wendy Soerachman
 
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Varun Patel
 

Tendances (20)

API 653 TANK INSPECTION.pdf
API 653 TANK INSPECTION.pdfAPI 653 TANK INSPECTION.pdf
API 653 TANK INSPECTION.pdf
 
Safety valves
Safety valvesSafety valves
Safety valves
 
Piping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning ProcedurePiping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning Procedure
 
Pressure testing
Pressure testingPressure testing
Pressure testing
 
Pressure safety valves
Pressure safety valvesPressure safety valves
Pressure safety valves
 
Heat exchanger types and hydro testing
Heat exchanger types and hydro testingHeat exchanger types and hydro testing
Heat exchanger types and hydro testing
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx
 
Presentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxPresentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptx
 
Floating head heat exchanger - Maintainance
Floating head heat exchanger - MaintainanceFloating head heat exchanger - Maintainance
Floating head heat exchanger - Maintainance
 
Piping sample report
Piping sample reportPiping sample report
Piping sample report
 
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure  What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
 
Pre commissioning and Commissioning Safety.pdf
Pre commissioning and Commissioning Safety.pdfPre commissioning and Commissioning Safety.pdf
Pre commissioning and Commissioning Safety.pdf
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and Commissioning
 
Pressure vessel
Pressure vesselPressure vessel
Pressure vessel
 
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
 
Plumbness & Roundness of storage tanks
Plumbness & Roundness of storage tanksPlumbness & Roundness of storage tanks
Plumbness & Roundness of storage tanks
 
Flange management presentation
Flange management presentationFlange management presentation
Flange management presentation
 
Pressure Vessel Safety
Pressure Vessel SafetyPressure Vessel Safety
Pressure Vessel Safety
 
Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
 

En vedette (9)

Ceramic tiles
Ceramic tilesCeramic tiles
Ceramic tiles
 
presentation on mobile cranes
presentation on mobile cranespresentation on mobile cranes
presentation on mobile cranes
 
Kajaria tiles
Kajaria tilesKajaria tiles
Kajaria tiles
 
Tiles presentations
Tiles presentationsTiles presentations
Tiles presentations
 
Pressure Measurements | Comprehensive search
Pressure Measurements | Comprehensive searchPressure Measurements | Comprehensive search
Pressure Measurements | Comprehensive search
 
Pressure Measurement
Pressure MeasurementPressure Measurement
Pressure Measurement
 
Tiles
TilesTiles
Tiles
 
Tiles presentation
Tiles presentationTiles presentation
Tiles presentation
 
Pressure measuring devices
Pressure measuring devicesPressure measuring devices
Pressure measuring devices
 

Similaire à Hydrotest

05 well testing trisakti 25 nov 2007
05 well testing   trisakti 25 nov 200705 well testing   trisakti 25 nov 2007
05 well testing trisakti 25 nov 2007
yudi05
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trial
Nagesh H
 
Commissioning Supervisor New
Commissioning Supervisor NewCommissioning Supervisor New
Commissioning Supervisor New
Joseph Jaiwin Das
 
Internship Report
Internship ReportInternship Report
Internship Report
Malik Ehsan
 

Similaire à Hydrotest (20)

Dst (Drill Stem Test)
Dst (Drill Stem Test)Dst (Drill Stem Test)
Dst (Drill Stem Test)
 
High pressure system- Anaesthesia Machine
High pressure system- Anaesthesia MachineHigh pressure system- Anaesthesia Machine
High pressure system- Anaesthesia Machine
 
05 well testing trisakti 25 nov 2007
05 well testing   trisakti 25 nov 200705 well testing   trisakti 25 nov 2007
05 well testing trisakti 25 nov 2007
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trial
 
Pressure Draw Down Test
Pressure Draw Down TestPressure Draw Down Test
Pressure Draw Down Test
 
Safe Handling of Compressed Gases by UCSD
Safe Handling of Compressed Gases by UCSDSafe Handling of Compressed Gases by UCSD
Safe Handling of Compressed Gases by UCSD
 
The basic anaesthesia machine
The basic anaesthesia machineThe basic anaesthesia machine
The basic anaesthesia machine
 
Boiler Mountings
Boiler MountingsBoiler Mountings
Boiler Mountings
 
compressor Operation pdf.pdf
compressor Operation pdf.pdfcompressor Operation pdf.pdf
compressor Operation pdf.pdf
 
Compressor operation.pdf
Compressor operation.pdfCompressor operation.pdf
Compressor operation.pdf
 
Formation Evaluation project (drill stem test DST)
Formation Evaluation project (drill stem test DST)Formation Evaluation project (drill stem test DST)
Formation Evaluation project (drill stem test DST)
 
PRESSFITTING. Uniones de Cobre prensadas
PRESSFITTING. Uniones de Cobre prensadasPRESSFITTING. Uniones de Cobre prensadas
PRESSFITTING. Uniones de Cobre prensadas
 
Leak Tests.pptx
Leak Tests.pptxLeak Tests.pptx
Leak Tests.pptx
 
Commissioning Supervisor New
Commissioning Supervisor NewCommissioning Supervisor New
Commissioning Supervisor New
 
WSM Yard-High-Pressure Safety-22.12.19
WSM Yard-High-Pressure Safety-22.12.19WSM Yard-High-Pressure Safety-22.12.19
WSM Yard-High-Pressure Safety-22.12.19
 
Medical gas cylinders
Medical gas cylindersMedical gas cylinders
Medical gas cylinders
 
Viscosity of crude/ petroleum products by Say-bolt
Viscosity of crude/ petroleum products by Say-boltViscosity of crude/ petroleum products by Say-bolt
Viscosity of crude/ petroleum products by Say-bolt
 
Internship Report
Internship ReportInternship Report
Internship Report
 
Control valve
Control valveControl valve
Control valve
 
SAFE HANDING OVER OF EQUIPMENTS.pptx
SAFE HANDING OVER OF EQUIPMENTS.pptxSAFE HANDING OVER OF EQUIPMENTS.pptx
SAFE HANDING OVER OF EQUIPMENTS.pptx
 

Plus de Jithu John (17)

Pwht1
Pwht1Pwht1
Pwht1
 
Rolling
RollingRolling
Rolling
 
Saw defects
Saw defectsSaw defects
Saw defects
 
Saw
SawSaw
Saw
 
Ut c
Ut cUt c
Ut c
 
Weld discountinuitie
Weld discountinuitieWeld discountinuitie
Weld discountinuitie
 
Weld ability of the new generation stainless steels
Weld ability of the new generation stainless steelsWeld ability of the new generation stainless steels
Weld ability of the new generation stainless steels
 
Weldability pc
Weldability pcWeldability pc
Weldability pc
 
Weld defects
Weld defectsWeld defects
Weld defects
 
Welding 1
Welding   1Welding   1
Welding 1
 
Welding 2
Welding  2Welding  2
Welding 2
 
Welding 3
Welding  3Welding  3
Welding 3
 
Welding 4
Welding  4Welding  4
Welding 4
 
Welding iv
Welding   ivWelding   iv
Welding iv
 
Welding flaws
Welding flawsWelding flaws
Welding flaws
 
Welding qualification a
Welding qualification aWelding qualification a
Welding qualification a
 
Radiography
RadiographyRadiography
Radiography
 

Dernier

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
Tonystark477637
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 

Dernier (20)

Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 

Hydrotest

  • 2. TESTS • DESTRUCTIVE TESTS – Tensile, Impact, Bend etc • NON-DESTRUCTIVE TESTS – Radiography – Ultrasonic – Dye Penetration – Magnetic Particle – Leak tests like Air test,Ammonia test etc. – Hydrostatic test
  • 3. WHY HYDROSTATIC TEST • To ensure the integrity of the equipment • To ensure the strength of the weld joints & material • To ensure the strength of the nozzle flange joints • To relieve the stresses • Ensures safe and reliable performance during the operational life
  • 4. HYDRO TEST • Good planning is essential for completion of hydrotest in minimum possible time •Gauges, transducer/ recorder , Sq. Bar, Hose pipes, Pump •Location, weight distribution, draining •Saddles, slope, venting •Water- quantity,quality & temperature •Torque tightening / tensioning units •Flanges, bolts / studs
  • 5. HYDRO TEST • The hydro test saddles shall be located on shell in such a way that all circumferential seams are free from saddle location. Long seams if any covered by the saddle; the corresponding location of saddle material shall be grooved to facilitate the inspection of weld joint under test
  • 7. Valves Pressure Gauge Towards Venting pipe Arrangement for Outlet Pressure Gauge Square Bar Coupling
  • 8. From Hydrotest Pump Towards Drain Valves Pressure Gauge Square Bar Coupling Arrangement for Inlet Pressure Gauge
  • 9. HYDRO TEST • Carry out tightening of Nozzle / Man way covers as per the required torque • Use proper tightening unit to meet the requirement of PSI / Torque and follow the tightening sequence as per approved procedure for bolts / studs • Start filling water after confirmation of all requirements ( like venting, PPM of water, Clearance of Job for fill up)
  • 10. 1 2 34 5 6 7 8 TIGHTENING SEQUENCE (with torque tightening unit)
  • 12. HYDRO TEST • Ensure that the nozzles (top) are open for air removal • Let the water flow out of the top nozzles so that the air is removed • Close the nozzle & allow the water to flow from top and confirm absence of air bubbles
  • 13. AIR LOCK REMOVAL 1 VESSEL IN HORIZONTAL, INCLINED AT 5 DEG. Packing
  • 14. AIR LOCK REMOVAL 2 WHEN INTERNALS LIKE TSRs PROVIDED INSIDE THE VESSEL
  • 15. AIR LOCK REMOVAL 3 NOZZLES ON DISHEND
  • 16. HYDRO TEST • Start the pump for pressurizing the water inside the equipment. (Selection of pump depends on the pressure and discharge of water from pump. Set the output pressure of pump such that it should not exceed hydro test pressure for safer operation)
  • 17. HYDRO TEST • Ensure that minimum two pressure gauges are attached • The pressure gauges shall have an upper range of 2 times the test pressure but in no case less than 1.5 times or more than 4 times the test pressure. The transducer shall have minimum upper range of 1.25 times the test pressure. Only calibrated pressure gauge and transducer shall be used. Validity of calibration shall be verified on the calibration sticker pasted on the pressure indicators
  • 18. HYDRO TEST • Increase the pressure as per the requirement given in drawing or the approved procedure • During pressurizing from design pressure to test pressure, no one shall remain on the vessel or very near to bolted connections on the vessel
  • 19. HYDRO TEST • Hold the test pressure for minimum 30 minutes or as specified by the drawing / specification. The test pressure shall not get dropped during the holding time. The vessel connections shall not be inspected closely for any leakage at this stage
  • 20. HYDRO TEST • Reduce the pressure to Design pressure • Check for any leakage in weld joints and bolted joints • If no leakage is observed, depressurizing can be started
  • 21. HYDRO TEST Depressurizing : • If cycle is specified , follow the same • If not specified, reduce pressure slowly by opening the square bars (at top) such that pressure drops to zero • Never open bottom noz./ Sq. bar • While draining the vessel, the top vent valve shall be kept open before opening any nozzle at the bottom. This is for eliminating the possible collapse of thin shells due to vacuum created within the test vessel
  • 22. HYDRO TEST • Pressure gauges once used for a pressure test shall be recalibrated. For this purpose, the pressure gauges once used shall be crossed on the calibration sticker and send to QA