Advances in Subsea and Deepwater Pipeline Pre-commissioning 1
ADVANCES IN SUBSEA &
DEEPWATER PIPELINE PRE-
COMMISSIONING
JOHN GROVER
BJ PROCESS AND PIPELINE SERVICES
Background
The increasing number of subsea and deepwater developments brings new challenges where
there are no surface connections to the pipeline available for pipeline testing and pre-
commissioning.
Once constructed / installed such subsea and deepwater systems still have to undergo certain
pre-commissioning and commissioning operations, from initial flooding, gauging & testing
up to final start up.
Whilst the provision of such services in shallow water and topside-to-topside developments is
routinely achieved, providing the same services at water depths in excess of 1,000m poses
many challenges. In this paper we shall review the unique challenges in providing such
services deepwater, and then review current / planned technologies including:
Flooding and pigging subsea pipelines using a Remote Flooding Module (RFM) – by
using the available hydrostatic head to flood and pig subsea pipelines whilst meeting
the project requirements in terms of pig speed, filtration and chemical treatment.
Use of subsea ROV driven pumping units for completion of flooding and
pressurisation – by using the hydraulic power from a work class ROV to power a
custom built pump skid built connected on to the RFM allowing all pigging and
pipeline testing to be performed subsea
Use of smart gauge tools (SGT) to gauge pipelines without using aluminium gauge
plates – this allows the gauging of lines with reduced bore PLETs at each end. Also
the ability to communicate the result of the gauging run thru-wall without the need to
recover the gauge plate to surface. This allows testing without pig recovery.
Use of subsea data loggers to record pressures and temperatures during subsea testing,
and use of systems to transmit this data to surface real-time during the test period
Advances in Subsea and Deepwater Pipeline Pre-commissioning 2
1.0 Asia Pacific Deepwater Market Overview
Looking at the Asia Pacific Market, the following table shows some of the deepwater projects
currently in progress within the region.
Looking at Australia in more detail we have visibility on the following deepwater prospects:
Operator Field
Year
Discovered Status
WD
(M) Development Type
Chevron Gorgon Central 1983 Firm Plan 250 Subsea Satellite to Onshore Facility
Chevron Gorgon North 1981 Firm Plan 246 Subsea Satellite to Onshore Facility
Chevron Gorgon South 1980 Firm Plan 220 Subsea Satellite to Onshore Facility
Chevron
Jansz SE/Io
South 2000 Firm Plan 1300 Subsea Satellite to Onshore Facility
Chevron Wheatstone 2004 Firm Plan 216 Subsea Satellite to Fixed Production
Exxon Mobil Jansz 2002 Firm Plan 1300 Subsea Satellite to Onshore Facility
Inpex Ichthys 2000 Firm Plan 230 Floating Production
Shell Prelude/Tocatta 2007 Probable 200 Fixed & Floating Production and Subsea
Woodside Brecknock 1979 Possible 300 Floating Production
Woodside Calliance 2000 Possible 420 Subsea Satellite to Floating Production
Woodside Pluto 2005
Under
Development976 Fixed Production Platform and Subsea
Woodside Sunrise 1974 Possible 180 Fixed Production Platform and Subsea
Woodside Torosa 1971 Possible 250 Fixed & Floating Production and Subsea
Woodside Troubador 1974 Possible 160 Subsea Satellite to Fixed Production
Figure 1 – Asia Pacific Deepwater Developments
Figure 2 – Australia Deepwater Developments
Advances in Subsea and Deepwater Pipeline Pre-commissioning 3
The offshore / deepwater pipeline market dynamics are explained further below:
1.1 Market Overview Summary
From the data in section 1 we can draw the following conclusions:
a. That there are a large number of deepwater pipeline projects planned in the Asia
Pacific region between 2008 and 2014
b. There is steep in crease in global deepwater pipeline installation planned in the next
few years, peaking in 2011
c. Services and techniques will be required to assist with the pre-commissioning and
commissioning of such pipeline systems
Figure 3 – Global Offshore Pipe lay Forecast
Figure 4 – Global Pipe lay Forecast by diameter
Advances in Subsea and Deepwater Pipeline Pre-commissioning 4
2.0 Pipeline Pre-commissioning – What Do We Mean?
The following flow chart illustrates the pre-commissioning process as typically applied to oil
pipelines. The process for gas lines is similar but involved additional steps prior to handover
such as removal of hydrotest water (dewatering), drying, MEG swabbing and nitrogen
packing (these are not covered in this paper).
Cleaning & gauging of
pipeline section
Flooding & testing of
pipeline section
Depressurise line and
handover to client filled
with treated water
Displace hydrotest
water with oil
Dewater using
compressed air
BJ Activity
Client
Commission the pipeline
Perform Caliper Survey,
possibly c/w dewatering
Nitrogen purge and pack
the line
Treat the line with batch
of corrosion inhibitor
Optional Services
Figure 5 – on LHS shows a
typical offshore vessel based
spread required to deliver
the above services to a
subsea pipeline.
Advances in Subsea and Deepwater Pipeline Pre-commissioning 5
3.0 The Aims of Subsea Pipeline Flooding
The first subsea pigging units were conceived and developed to overcome the problems
associated with flooding and pigging pipelines in deep water.
The latest subsea flooding device is the BJ RFM (Remote Flooding Module), which
essentially achieves the same objectives using up to date ROV and Subsea technologies.
The RFM is a Subsea flow control and regulation system. Once positioned on the seabed and
connected to the pipeline to be flooded or pigged by HP loading arm, it is “operated” by the
ROV opening the valves to the pipeline.
The hydrostatic head of the sea then enters the pipeline through the RFM because of the
differential pressure between the inside of the pipeline, which is at atmospheric pressure and
the sea.
Seawater enters the RFM via a filter manifold, which is installed at the specified filtration
level, usually between 50 and 200 microns. It passes through a Venturi device, which creates
a small pressure drop in the on board flexible RFM chemical tanks which are connected to
the water flow pipework. This small differential pressure is used to induce anti-corrosion
chemicals into the water flow at the desired rate. This is pre-set prior to deployment and ROV
adjusted Subsea if necessary via control valves.
Figure 6 – Overview of Remote Flooding Module
Advances in Subsea and Deepwater Pipeline Pre-commissioning 6
The chemically treated water flow is controlled to a pre-determined rate via a flow regulation
system. This maintains the water flow at the desired speed to match specified or optimum pig
speed or flooding rates. Again this can be pre-set prior to deployment and because the rate is
controlled at a steady level the chemical inducement is assured throughout the entire
“unassisted” operation. A Boost pump is required to complete final pigging operations due to
pressure equalisation. This pump is ROV driven, usually operated when the ROV returns to
location to disconnect and recover the RFM, and in Deepwater is required only for a very
short time.
The vessel and ROV can leave the unit in isolation on the seabed during the unassisted
operations and carry out other tasks. There is no need for connection to anything other than
the pipeline. On board batteries power data-logging instrumentation which logs flows,
chemical rates etc, and visual readouts allows the ROV to check status before it leaves and
when it returns.
The RFM is positioned on the seabed by ROV and connected to the pipeline to be flooded via
the innovative rigid loading arm pipe system. The ROV then positions itself on the unit’s roof
from where it can view instruments and operate valves to monitor the initial stages of the
operation and adjust if necessary chemical control valves.
Filtration and chemical treatment specifications are fully met by onboard facilities. Chemicals
are stored onboard in flexible tanks and introduced by a Venturi system regulated by
detecting changes in the water flow through the unit and automatically adjusting the chemical
flow accordingly.
To summarise the aims of subsea pipeline flooding:
• Reduce the size of vessel required for pre-commissioning operations
• Negate the need for the vessel to remain on station during the bulk of the operations
• Remove the need for an expensive down-line, which is prone to damage
• Reduce schedule by increasing possible pig speed
• Reduce schedule by use of seabed water removing thermal stabilisation for Hydrotest
• Reduce crew size, equipment spread size, environmental impact by removal of diesel
engines on pumps, improve safety by taking operations off-deck
Advances in Subsea and Deepwater Pipeline Pre-commissioning 7
4.0 Offshore Vessel Requirements – the Cost Driver
Previously in this paper I have described the functionality and development of subsea
flooding and testing, and in the following section we look at the commercial drivers to use
such a system. As an example we take the following pipeline as an example:
Line NPS 16”
Wall Thickness 12.5mm
Line Length 8KM
Water Depth at launcher 1000m
Water Depth at receiver 1000m
Water Temp at surface 28°C
Water Temp at Seabed 4°C
Average Flooding pig velocity required 0.5 m/sec
Flooding Rate Required 3,420 lpm
Table 1 – Pipeline details (illustration)
The important data from the above is that we need to inject 3,420 lpm of filtered, treated sea
water into a pipeline at a water depth of 1000m. There are 2 ways to achieve this:
Use a Vessel Based Spread and Down-line
The vessel based spread must be designed to deliver 3,420 lpm in to the pipeline – hence the
first consideration is the size of the down-line required. Having looked at the various pressure
drops across the down-line, we then need to evaluate the pump power (HHP / BHP) required
to overcome the system pressure losses and deliver the flow to the system.
Down-line
Diameter
Down-line
Length
Pressure Drop
in barg *
HHP required
for 1m/sec
BHP required
for 1m/sec**
2” 1,200m 210 barg 1,600 HHP 2,560 BHP***
3” 1,200m 78 barg 594 HHP 1,014 BHP
4” 1,200m 24 barg 183 HHP 382 BHP****
Table 2 – Pressure drops and HHP calculations vs. down-line diameter
* Using Mears pipe flow calculator
** Based on 65% efficiency (centrifugal pump) plus 100bhp for engine ancillaries
*** Maximum power from portable, marinised diesel engines approx. 1,800 BHP
**** Pump packages rated at 350 to 500 BHP readily available
Advances in Subsea and Deepwater Pipeline Pre-commissioning 8
Thus taking the data in table 2 we can see that to flood this notional 16” pipeline at a depth of
1,000m would require:
• A 4” x 1,200m down-line including reel and installation system
• A 4” hot stab to connect the hose to the subsea launcher
• 2 qty diesel driven 500 bhp centrifugal pumps
• Lift pumps, break tanks, filters, chemical injection units and hoses
To put this into perspective in figure 7 we show the deck space required on a DP vessel for
the above spread (figure 8 illustrates space requirement for similar RFM spread):
Figure 7 – Vessel Space Requirement Figure 8 – Reduced Space Using RFM
The vessel based spread c/w down-line requires a deck space of approx. 290m2
to flood a 16”
pipeline at 0.5m/sec. To perform such an operations the following steps are required:
a. Deploy down-line and stab in to subsea launcher - 12 hours
b. Flood the 8km line at 0.5m/sec - 5 hours
c. Recover down-line to surface - 12 hours
d. Allow fill water temperature to stabilise - 48 hours
e. TOTAL TIME FOR FLOODING - 77 HOURS
Advances in Subsea and Deepwater Pipeline Pre-commissioning 9
Use a Vessel Based RFM to Flood the Line
Figure 7 shows the deck space required for the
RFM – this is approx. 32m2
. The RFM can carry
sufficient chemicals to fill 16” x 8km in a single
deployment. Using the vessel crane the RFM
can be quickly deployed subsea and connected
to the subsea launcher. Thereafter it can perform
the initial flooding of the pipeline at velocities
up to 1m/sec.
16" Pipeline
Predicted End Point of Flooding by RFM:
Data
Starting end depth d1 = 1000 metres.
Finishing end depth d2 = 1000 metres.
Total line length L = 8 kilometres.
Internal diameter of line b = 371.4 millimetres.
Assumed or required pig speed v = 0.5 m/second.
Assumed pig (train) driving pressure 2 bar.
(If unknown, assume 1 bar per pig.)
Slug length trapped air before boost 81 metres.
Proportion of line flooded by unassisted RFM = 99.0 %.
Time taken for filling by RFM at pig speed 0.5m/s is 4.4 hours.
Volume to be boost pumped for completion = 8.8 cubic metres.
RFM
Sta
Pipelin
d d
Wat Ai
En
Figure 10 – RFM calculation for 16” x 8km line.
In figure 8 we can see that the RFM can flood the line within 4.4 hours and that 8.8m3
has to
be pumped by the ROV powered boost pump – please consider the line has been flooded with
water at seabed ambient temperature.
The vessel based RFM spread requires a deck space of approx. 32m2
to flood a 16” pipeline
at 0.5m/sec. To perform such an operations the following steps are required:
a. Deploy down-line and stab in to subsea launcher - 2 hours
b. Flood the 8km line at 0.5m/sec - 5 hours
c. Recover down-line to surface - 2 hours
d. Allow fill water temperature to stabilise - 0 hours
e. TOTAL TIME FOR FLOODING - 9 HOURS
Figure 9 – RFM ready to deploy
Advances in Subsea and Deepwater Pipeline Pre-commissioning 10
4.1 Vessel Cost Summary
Looking at the example of flooding a 16” x 8km line at 1,000m water depth, we can draw the
following conclusions:
1. The down-line option requires almost 10x the deck space of the RFM option – with
the current shortage of DP vessels and with vessel rates of around US$40,000 per
day, this can have a major impact on overall project costs
2. As the RFM floods the line with ambient temperature water there is no stabilisation
period – this could represent a saving of 2 days
3. The deployment and recovery time for the RFM is far quicker than for a 4” down-line
As with all new technologies, there are circumstances where the RFM may not be suited to a
deepwater project. These include:
• Where one or both ends of the line terminates at a platform / FPSO such as when
using SCR’s
• Where a down-line will be deployed for other operations and can conveniently be
used for flooding
• Where a large number of pigs are used
• Where the line has to be flooded with either fresh water or MEG
• Where one on of the line terminates in shallow water.
Advances in Subsea and Deepwater Pipeline Pre-commissioning 11
5.0 Advances Made in Subsea Pigging Equipment
The original Subsea Pigging Unit was designed by pre-commissioning Engineers with little
input from ROV and Subsea specialists, despite efforts to include them.
Whilst the device was successful in achieving its’ pre-commissioning objectives, it wasn’t the
most optimum method of operation for the ROV or deployment Vessel. Unwieldy HP
flexible Jumper hoses, relatively crude instrumentation and brand new ways to use Choke
Assemblies meant there were areas to improve, for example:
.
• The RFM holds more chemical than the original Subsea unit, allowing less recovery
and deployment cycles and use on longer and larger lines
• The RFM uses rigid loading arm technology to reduce Subsea connection times and
reduce the risk of damage to HP flexible jumper hoses
• The RFM is extremely ROV friendly, ROV specialists were involved in design to
ensure minimum ROV interface issues
• An on-board latching mechanism allows very fast ROV connection for boost
pumping
• An on-board emergency release system means no risk of an ROV getting stuck on the
RFM
• Advances in electronics means much more reliable instrumentation
• Deployment times are down to less than one hour in Deepwater
Figure 11 – RFM loading arm stabbed in Figure 12 – ROV operating RFM
Advances in Subsea and Deepwater Pipeline Pre-commissioning 12
6.0 Development of Subsea Hydrotesting Unit
Recent developments in Subsea pumping systems have allowed ROV pump skids to carry out
Subsea hydrotesting and leak testing of pipeline systems, thus allowing additional savings on
Vessel size, cost etc. When used in conjunction with the RFM, significant overall benefits
can be achieved. Naturally, the systems that can be tested are limited by the maximum
performance available from an ROV test pump skid. The BJ SHP can produce over 40 litres
per minute pressurisation rate from typical Project ROV’s.
In section 4 we reviewed a down-line system
required to flood a 16” x 8km line. Deepwater
lines typically require hydrostatic testing at
between 200 barg and 350 barg. A typical 4”
down-line would not be rated for such
pressures (specialised down-lines such as
those produced by Deepflex and Technip can
handle such pressures but are too costly for
such applications). Thus a different down-line
must then be deployed to in order to pressurise
the line. Deployment times for the down-line
will be similar to those of the flooding down-
line.
A the SHP can be deployed with the RFM boost pump and hence there is no delay between
completion of flooding and commencement of pressurisation – it is estimated this saves a
minimum of 24 hours per pipeline.
Pipeline
Nomial
bore
(inches)
Length
(metres)
Vol/bar
(litres)
Bar/min ex SHP
Test Pressure
(bar)
Vol to test
pressure
(litres)
Time to test
pressure
(hours)
TS-WI-FL-01 12 9553 31.83 0.94 431 114523 7.62
TS-P-FL-01 10 9577 21.71 1.38 431 9921 5.20
TS-P-FL-02 10 9248 20.96 1.43 431 9580 5.02
TS-T-FL-01 8 9553 13.57 2.21 431 6210 3.25
TS-GL-FL-01 8 9479 13.47 2.23 431 6162 3.23
Figure 13 – SHP Unit
Table 3 – Example pressurisation times using SHP
Line 1
Line 2
Line 3
Line 4
Line 5
Advances in Subsea and Deepwater Pipeline Pre-commissioning 13
7.0 Smart Gauge Technology
Previous sections of this paper have dealt with the flooding and hydrostatic testing of
deepwater pipelines – in this section we deal with the gauging of the line. All offshore
pipeline pre-commissioning operations include the proving of the internal bore of the line –
this is normally achieved by fitting a segmented aluminium disk (see figure 14) to one of the
filling pigs, the disk having an outside diameter equal to between 95% and 97% of the
minimum pipeline i.d. The principle is that any restriction in the line (buckle, dent etc.)
would cause one of the aluminium “petals” to bend indicating a restriction in the line.
The gauge pig is then run as part of the pipeline filling pig train and most specifications
require that the gauge plate be visually inspected prior to commencement of the hydrotest –
thus ensure there is no mechanical damage with in the line that could be affected by the
hydrostatic test – figure 15 shows a gauge plate received with some damage.
Removing and inspecting the gauge plate is a simple operation onshore, and for pipelines
with above surface terminations, but requires additional work on pipelines terminating subsea
and deepwater. Thus BJ developed the SMARTGAUGE™ to meet the following needs of
deepwater pipelines:
1. Allows lines with restrictions (heavy wall bends, PLET hub restrictions, reduced bore
valves) to be gauged
2. Permits gauging data to be reviewed and analysed assist in pinpointing any
restriction identified – allows valves etc to be discounted
3. Incorporates a system to remotely annunciate the result of the gauging run such the
hydrotest can commence immediately upon completion of flooding without the need to
recover the gauge plate to surface for visual inspection.
Figure 15 –Gauge plate with damageFigure 14 –Gauge pig prior to launch
Advances in Subsea and Deepwater Pipeline Pre-commissioning 14
A standard mechanical gauge plate gives no indication of
where any damage occurred, making identifying location
difficult, time consuming and expensive. Using the multi-
channel BJ SMARTGAUGE™ tool with a segmented
flexible gauge plate both the clock position and the
location of multiple defects can be ascertained, reducing
the time needed to find the problem. In a further
enhancement for deepwater lines a pinger can be fitted to
the tool, such that any damage to the be left in the receiver
if no damage is detected or removed and repairs made
prior to hydrotest in the event that damage has occurred.
Valuable DSV time can be saved in either case.
8.0 Future developments
Improving ROV capabilities and advances in electronics will undoubtedly have positive
benefits to remote flooding and pigging systems. Use of remote data transmission and
signalling will also allow other associated tasks to be reduced in impact and cost or taken
completely off of project critical paths.
All future developments will be driven by the same common objectives:
• Reducing the in-field time required to complete subsea pre-commissioning
services, hence saving on both the vessel costs and hire periods for pre-
commissioning spreads
• Removing or replacing operational processes that have high risk (such as
deployment of large diameter down-lines in deep water)
• Minimising offshore vessel deck space for pre-commissioning equipment,
allowing smaller & cheaper vessels to be used
Figure 16 –BJ SMARTGAUGE™
Advances in Subsea and Deepwater Pipeline Pre-commissioning 15
Sources
Figure 1 Offshore Engineer
Figures 2 and 3 Australian Deepwater Development Market, Infield Ltd, Perth 2008
Figures 11 and 12 Technip UK Ltd
Figure 14 Profile Ltd, UK.
Other figures BJ Services
References
1. Remote Deepwater Developments, Les Graves, World Pipelines, December 2007

Contenu connexe

Tendances

Engineering of Subsea Production Systems
Engineering of Subsea Production SystemsEngineering of Subsea Production Systems
Engineering of Subsea Production SystemspetroEDGE
 
Global Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea TechnologyGlobal Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea TechnologyConference_Presentations
 
Subsea completion and control system
Subsea completion and control systemSubsea completion and control system
Subsea completion and control systemAmit Nitharwal
 
Design and Evaluation of Submersible 11/0.415kV Distribution Substation for F...
Design and Evaluation of Submersible 11/0.415kV Distribution Substation for F...Design and Evaluation of Submersible 11/0.415kV Distribution Substation for F...
Design and Evaluation of Submersible 11/0.415kV Distribution Substation for F...TELKOMNIKA JOURNAL
 
Subsea689_FinalSubmission_Ashwin_Kim_Thomas
Subsea689_FinalSubmission_Ashwin_Kim_ThomasSubsea689_FinalSubmission_Ashwin_Kim_Thomas
Subsea689_FinalSubmission_Ashwin_Kim_ThomasAshwin Gadgil
 
ISOPE-2014-TPC-0405 Recent Trends and Future 14-02-24
ISOPE-2014-TPC-0405 Recent Trends and Future 14-02-24ISOPE-2014-TPC-0405 Recent Trends and Future 14-02-24
ISOPE-2014-TPC-0405 Recent Trends and Future 14-02-24Jean-Francois Saint-Marcoux
 
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser ProjectsISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser ProjectsJean-Francois Saint-Marcoux
 
PPEJ.090.2010 rev2
PPEJ.090.2010 rev2PPEJ.090.2010 rev2
PPEJ.090.2010 rev2Rahmat Riski
 
50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-Commissioning50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-CommissioningJohn Grover
 
performance evaluation of desilting devices
performance evaluation of desilting devicesperformance evaluation of desilting devices
performance evaluation of desilting devicesGurdeep singh Johar
 
Exploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well TechnologyExploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well TechnologyAbhinav Bisht
 
2.2 gl for-hydaulic_design_of_shp_project
2.2 gl for-hydaulic_design_of_shp_project2.2 gl for-hydaulic_design_of_shp_project
2.2 gl for-hydaulic_design_of_shp_projectSaddam Mussie
 
Application of intelligent well completion in optimizing production
Application of intelligent well completion in optimizing productionApplication of intelligent well completion in optimizing production
Application of intelligent well completion in optimizing productionChirag Vanecha
 
modeling and analysis of subsea pipeline by fem
modeling and analysis of subsea pipeline by femmodeling and analysis of subsea pipeline by fem
modeling and analysis of subsea pipeline by fem9845097705
 
Development of Tight Gas Fields
Development of Tight Gas FieldsDevelopment of Tight Gas Fields
Development of Tight Gas FieldsNeil Barnard
 

Tendances (19)

Engineering of Subsea Production Systems
Engineering of Subsea Production SystemsEngineering of Subsea Production Systems
Engineering of Subsea Production Systems
 
Global Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea TechnologyGlobal Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea Technology
 
Subsea completion and control system
Subsea completion and control systemSubsea completion and control system
Subsea completion and control system
 
Design and Evaluation of Submersible 11/0.415kV Distribution Substation for F...
Design and Evaluation of Submersible 11/0.415kV Distribution Substation for F...Design and Evaluation of Submersible 11/0.415kV Distribution Substation for F...
Design and Evaluation of Submersible 11/0.415kV Distribution Substation for F...
 
Subsea689_FinalSubmission_Ashwin_Kim_Thomas
Subsea689_FinalSubmission_Ashwin_Kim_ThomasSubsea689_FinalSubmission_Ashwin_Kim_Thomas
Subsea689_FinalSubmission_Ashwin_Kim_Thomas
 
ISOPE-2014-TPC-0405 Recent Trends and Future 14-02-24
ISOPE-2014-TPC-0405 Recent Trends and Future 14-02-24ISOPE-2014-TPC-0405 Recent Trends and Future 14-02-24
ISOPE-2014-TPC-0405 Recent Trends and Future 14-02-24
 
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser ProjectsISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
 
PPEJ.090.2010 rev2
PPEJ.090.2010 rev2PPEJ.090.2010 rev2
PPEJ.090.2010 rev2
 
OGJ Nordstream
OGJ NordstreamOGJ Nordstream
OGJ Nordstream
 
50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-Commissioning50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-Commissioning
 
performance evaluation of desilting devices
performance evaluation of desilting devicesperformance evaluation of desilting devices
performance evaluation of desilting devices
 
Exploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well TechnologyExploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well Technology
 
2.2 gl for-hydaulic_design_of_shp_project
2.2 gl for-hydaulic_design_of_shp_project2.2 gl for-hydaulic_design_of_shp_project
2.2 gl for-hydaulic_design_of_shp_project
 
Application of intelligent well completion in optimizing production
Application of intelligent well completion in optimizing productionApplication of intelligent well completion in optimizing production
Application of intelligent well completion in optimizing production
 
modeling and analysis of subsea pipeline by fem
modeling and analysis of subsea pipeline by femmodeling and analysis of subsea pipeline by fem
modeling and analysis of subsea pipeline by fem
 
Culvertdesign
CulvertdesignCulvertdesign
Culvertdesign
 
Minor Project Report On Construction of Pipe Culvert
Minor Project Report  On Construction of  Pipe CulvertMinor Project Report  On Construction of  Pipe Culvert
Minor Project Report On Construction of Pipe Culvert
 
Schmidt
SchmidtSchmidt
Schmidt
 
Development of Tight Gas Fields
Development of Tight Gas FieldsDevelopment of Tight Gas Fields
Development of Tight Gas Fields
 

En vedette

Appendix g preferred management approach testing final_dec2010
Appendix g preferred management approach testing final_dec2010Appendix g preferred management approach testing final_dec2010
Appendix g preferred management approach testing final_dec2010Severn Estuary
 
Offshore Ind Gases J Grover 11 Dec 07
Offshore Ind Gases J Grover 11 Dec 07Offshore Ind Gases J Grover 11 Dec 07
Offshore Ind Gases J Grover 11 Dec 07John Grover
 
Smp2 part b policy statements tidenham only_final
Smp2 part b policy statements tidenham only_finalSmp2 part b policy statements tidenham only_final
Smp2 part b policy statements tidenham only_finalSevern Estuary
 
Appendix f policy development and appraisal final_dec2010
Appendix f policy development and appraisal final_dec2010Appendix f policy development and appraisal final_dec2010
Appendix f policy development and appraisal final_dec2010Severn Estuary
 
Appendix b stakeholder engagement and consultation final_dec2010
Appendix b stakeholder engagement and consultation final_dec2010Appendix b stakeholder engagement and consultation final_dec2010
Appendix b stakeholder engagement and consultation final_dec2010Severn Estuary
 
Smp2 part b policy statements kingston seymour only_final
Smp2 part b policy statements kingston seymour only_finalSmp2 part b policy statements kingston seymour only_final
Smp2 part b policy statements kingston seymour only_finalSevern Estuary
 
Appendix a development of the smp2 final_dec2010
Appendix a development of the smp2 final_dec2010Appendix a development of the smp2 final_dec2010
Appendix a development of the smp2 final_dec2010Severn Estuary
 
Appendix k metadata and bibliographic database final_dec2010
Appendix k metadata and bibliographic database final_dec2010Appendix k metadata and bibliographic database final_dec2010
Appendix k metadata and bibliographic database final_dec2010Severn Estuary
 
Appendix c baseline understanding final_dec2010
Appendix c baseline understanding final_dec2010Appendix c baseline understanding final_dec2010
Appendix c baseline understanding final_dec2010Severn Estuary
 
Smp2 part b policy statements bristol only_final
Smp2 part b policy statements bristol only_finalSmp2 part b policy statements bristol only_final
Smp2 part b policy statements bristol only_finalSevern Estuary
 
Appendix d theme review final_dec2010a
Appendix d theme review final_dec2010aAppendix d theme review final_dec2010a
Appendix d theme review final_dec2010aSevern Estuary
 
Smp2 part c action plan final
Smp2 part c action plan finalSmp2 part c action plan final
Smp2 part c action plan finalSevern Estuary
 
OSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact finalOSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact finalJohn Grover
 
Appendix i part a sea_final_dec2010
Appendix i part a sea_final_dec2010Appendix i part a sea_final_dec2010
Appendix i part a sea_final_dec2010Severn Estuary
 
Appendix i part b _hra_final_dec2010
Appendix i part b _hra_final_dec2010Appendix i part b _hra_final_dec2010
Appendix i part b _hra_final_dec2010Severn Estuary
 
PII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline ConferencePII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline ConferenceJohn Grover
 
Smp2 part a main report final
Smp2 part a main report finalSmp2 part a main report final
Smp2 part a main report finalSevern Estuary
 
Appendix j wfd assessment final_dec2010
Appendix j wfd assessment final_dec2010Appendix j wfd assessment final_dec2010
Appendix j wfd assessment final_dec2010Severn Estuary
 

En vedette (20)

Appendix g preferred management approach testing final_dec2010
Appendix g preferred management approach testing final_dec2010Appendix g preferred management approach testing final_dec2010
Appendix g preferred management approach testing final_dec2010
 
Offshore Ind Gases J Grover 11 Dec 07
Offshore Ind Gases J Grover 11 Dec 07Offshore Ind Gases J Grover 11 Dec 07
Offshore Ind Gases J Grover 11 Dec 07
 
Smp2 part b policy statements tidenham only_final
Smp2 part b policy statements tidenham only_finalSmp2 part b policy statements tidenham only_final
Smp2 part b policy statements tidenham only_final
 
Appendix f policy development and appraisal final_dec2010
Appendix f policy development and appraisal final_dec2010Appendix f policy development and appraisal final_dec2010
Appendix f policy development and appraisal final_dec2010
 
Appendix b stakeholder engagement and consultation final_dec2010
Appendix b stakeholder engagement and consultation final_dec2010Appendix b stakeholder engagement and consultation final_dec2010
Appendix b stakeholder engagement and consultation final_dec2010
 
Smp2 part b policy statements kingston seymour only_final
Smp2 part b policy statements kingston seymour only_finalSmp2 part b policy statements kingston seymour only_final
Smp2 part b policy statements kingston seymour only_final
 
Appendix a development of the smp2 final_dec2010
Appendix a development of the smp2 final_dec2010Appendix a development of the smp2 final_dec2010
Appendix a development of the smp2 final_dec2010
 
Tasnia
TasniaTasnia
Tasnia
 
Appendix k metadata and bibliographic database final_dec2010
Appendix k metadata and bibliographic database final_dec2010Appendix k metadata and bibliographic database final_dec2010
Appendix k metadata and bibliographic database final_dec2010
 
Appendix c baseline understanding final_dec2010
Appendix c baseline understanding final_dec2010Appendix c baseline understanding final_dec2010
Appendix c baseline understanding final_dec2010
 
PII_IQPC_May_04
PII_IQPC_May_04PII_IQPC_May_04
PII_IQPC_May_04
 
Smp2 part b policy statements bristol only_final
Smp2 part b policy statements bristol only_finalSmp2 part b policy statements bristol only_final
Smp2 part b policy statements bristol only_final
 
Appendix d theme review final_dec2010a
Appendix d theme review final_dec2010aAppendix d theme review final_dec2010a
Appendix d theme review final_dec2010a
 
Smp2 part c action plan final
Smp2 part c action plan finalSmp2 part c action plan final
Smp2 part c action plan final
 
OSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact finalOSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact final
 
Appendix i part a sea_final_dec2010
Appendix i part a sea_final_dec2010Appendix i part a sea_final_dec2010
Appendix i part a sea_final_dec2010
 
Appendix i part b _hra_final_dec2010
Appendix i part b _hra_final_dec2010Appendix i part b _hra_final_dec2010
Appendix i part b _hra_final_dec2010
 
PII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline ConferencePII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline Conference
 
Smp2 part a main report final
Smp2 part a main report finalSmp2 part a main report final
Smp2 part a main report final
 
Appendix j wfd assessment final_dec2010
Appendix j wfd assessment final_dec2010Appendix j wfd assessment final_dec2010
Appendix j wfd assessment final_dec2010
 

Similaire à 26-grover-john-final

Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...
Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...
Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...Charlie Reith
 
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKSDAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKSIslam Nassef
 
Underbalance drilling equipment
Underbalance  drilling equipmentUnderbalance  drilling equipment
Underbalance drilling equipmentshivan abdalrahman
 
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartiii
 Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartiii Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartiii
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartiiihydrologyproject001
 
Report on Madras Atomic Power Station Emass Coolant Channel Replacement
Report on Madras Atomic Power Station Emass Coolant Channel ReplacementReport on Madras Atomic Power Station Emass Coolant Channel Replacement
Report on Madras Atomic Power Station Emass Coolant Channel ReplacementSujit Tharakan
 
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartviii
 Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartviii Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartviii
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartviiihydrologyproject001
 
Anchois 1- Oil&Gas Field
Anchois 1- Oil&Gas FieldAnchois 1- Oil&Gas Field
Anchois 1- Oil&Gas FieldJose V.Taboada
 
SPE171748 Surface Safety System for ZADCO (4).pdf
SPE171748 Surface Safety System for ZADCO (4).pdfSPE171748 Surface Safety System for ZADCO (4).pdf
SPE171748 Surface Safety System for ZADCO (4).pdfJalal Neshat
 
Hydrometry: Field Manual, Field Application of ADCP Volume-4 Part V 2003
Hydrometry: Field Manual, Field Application of ADCP Volume-4 Part V 2003 Hydrometry: Field Manual, Field Application of ADCP Volume-4 Part V 2003
Hydrometry: Field Manual, Field Application of ADCP Volume-4 Part V 2003 indiawrm
 
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartii
 Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartii Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartii
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartiihydrologyproject001
 
Design and Fabrication of a Low Cost Submersible ROV for Survey of Lakes
Design and Fabrication of a Low Cost Submersible ROV for Survey of LakesDesign and Fabrication of a Low Cost Submersible ROV for Survey of Lakes
Design and Fabrication of a Low Cost Submersible ROV for Survey of LakesIRJET Journal
 
Center for Sustainable Shale Development Comparison to State/Federal Regulations
Center for Sustainable Shale Development Comparison to State/Federal RegulationsCenter for Sustainable Shale Development Comparison to State/Federal Regulations
Center for Sustainable Shale Development Comparison to State/Federal RegulationsMarcellus Drilling News
 
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartvii
 Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartvii Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartvii
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartviihydrologyproject001
 
Remotely Operated Vehicles (ROVs), A Subsea Enabler
Remotely Operated Vehicles (ROVs), A Subsea EnablerRemotely Operated Vehicles (ROVs), A Subsea Enabler
Remotely Operated Vehicles (ROVs), A Subsea EnablerAhmed Abo Bakr
 
Center for Sustainable Shale Development 15 Performance Standards
Center for Sustainable Shale Development 15 Performance StandardsCenter for Sustainable Shale Development 15 Performance Standards
Center for Sustainable Shale Development 15 Performance StandardsMarcellus Drilling News
 
23-2009 Pre-piling for wind farms.pdf
23-2009 Pre-piling for wind farms.pdf23-2009 Pre-piling for wind farms.pdf
23-2009 Pre-piling for wind farms.pdframadhitaerdina1
 

Similaire à 26-grover-john-final (20)

Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...
Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...
Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...
 
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKSDAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
 
Underbalance drilling equipment
Underbalance  drilling equipmentUnderbalance  drilling equipment
Underbalance drilling equipment
 
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartiii
 Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartiii Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartiii
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartiii
 
Report on Madras Atomic Power Station Emass Coolant Channel Replacement
Report on Madras Atomic Power Station Emass Coolant Channel ReplacementReport on Madras Atomic Power Station Emass Coolant Channel Replacement
Report on Madras Atomic Power Station Emass Coolant Channel Replacement
 
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartviii
 Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartviii Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartviii
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartviii
 
Anchois 1- Oil&Gas Field
Anchois 1- Oil&Gas FieldAnchois 1- Oil&Gas Field
Anchois 1- Oil&Gas Field
 
Submarine outfalls & intakes ppt
Submarine outfalls & intakes pptSubmarine outfalls & intakes ppt
Submarine outfalls & intakes ppt
 
SPE171748 Surface Safety System for ZADCO (4).pdf
SPE171748 Surface Safety System for ZADCO (4).pdfSPE171748 Surface Safety System for ZADCO (4).pdf
SPE171748 Surface Safety System for ZADCO (4).pdf
 
Hydrometry: Field Manual, Field Application of ADCP Volume-4 Part V 2003
Hydrometry: Field Manual, Field Application of ADCP Volume-4 Part V 2003 Hydrometry: Field Manual, Field Application of ADCP Volume-4 Part V 2003
Hydrometry: Field Manual, Field Application of ADCP Volume-4 Part V 2003
 
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartii
 Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartii Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartii
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartii
 
Design and Fabrication of a Low Cost Submersible ROV for Survey of Lakes
Design and Fabrication of a Low Cost Submersible ROV for Survey of LakesDesign and Fabrication of a Low Cost Submersible ROV for Survey of Lakes
Design and Fabrication of a Low Cost Submersible ROV for Survey of Lakes
 
Center for Sustainable Shale Development Comparison to State/Federal Regulations
Center for Sustainable Shale Development Comparison to State/Federal RegulationsCenter for Sustainable Shale Development Comparison to State/Federal Regulations
Center for Sustainable Shale Development Comparison to State/Federal Regulations
 
SPE-172315-MS-Turkmenistan
SPE-172315-MS-TurkmenistanSPE-172315-MS-Turkmenistan
SPE-172315-MS-Turkmenistan
 
[IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme
[IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme [IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme
[IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme
 
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartvii
 Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartvii Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartvii
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartvii
 
Report
ReportReport
Report
 
Remotely Operated Vehicles (ROVs), A Subsea Enabler
Remotely Operated Vehicles (ROVs), A Subsea EnablerRemotely Operated Vehicles (ROVs), A Subsea Enabler
Remotely Operated Vehicles (ROVs), A Subsea Enabler
 
Center for Sustainable Shale Development 15 Performance Standards
Center for Sustainable Shale Development 15 Performance StandardsCenter for Sustainable Shale Development 15 Performance Standards
Center for Sustainable Shale Development 15 Performance Standards
 
23-2009 Pre-piling for wind farms.pdf
23-2009 Pre-piling for wind farms.pdf23-2009 Pre-piling for wind farms.pdf
23-2009 Pre-piling for wind farms.pdf
 

26-grover-john-final

  • 1. Advances in Subsea and Deepwater Pipeline Pre-commissioning 1 ADVANCES IN SUBSEA & DEEPWATER PIPELINE PRE- COMMISSIONING JOHN GROVER BJ PROCESS AND PIPELINE SERVICES Background The increasing number of subsea and deepwater developments brings new challenges where there are no surface connections to the pipeline available for pipeline testing and pre- commissioning. Once constructed / installed such subsea and deepwater systems still have to undergo certain pre-commissioning and commissioning operations, from initial flooding, gauging & testing up to final start up. Whilst the provision of such services in shallow water and topside-to-topside developments is routinely achieved, providing the same services at water depths in excess of 1,000m poses many challenges. In this paper we shall review the unique challenges in providing such services deepwater, and then review current / planned technologies including: Flooding and pigging subsea pipelines using a Remote Flooding Module (RFM) – by using the available hydrostatic head to flood and pig subsea pipelines whilst meeting the project requirements in terms of pig speed, filtration and chemical treatment. Use of subsea ROV driven pumping units for completion of flooding and pressurisation – by using the hydraulic power from a work class ROV to power a custom built pump skid built connected on to the RFM allowing all pigging and pipeline testing to be performed subsea Use of smart gauge tools (SGT) to gauge pipelines without using aluminium gauge plates – this allows the gauging of lines with reduced bore PLETs at each end. Also the ability to communicate the result of the gauging run thru-wall without the need to recover the gauge plate to surface. This allows testing without pig recovery. Use of subsea data loggers to record pressures and temperatures during subsea testing, and use of systems to transmit this data to surface real-time during the test period
  • 2. Advances in Subsea and Deepwater Pipeline Pre-commissioning 2 1.0 Asia Pacific Deepwater Market Overview Looking at the Asia Pacific Market, the following table shows some of the deepwater projects currently in progress within the region. Looking at Australia in more detail we have visibility on the following deepwater prospects: Operator Field Year Discovered Status WD (M) Development Type Chevron Gorgon Central 1983 Firm Plan 250 Subsea Satellite to Onshore Facility Chevron Gorgon North 1981 Firm Plan 246 Subsea Satellite to Onshore Facility Chevron Gorgon South 1980 Firm Plan 220 Subsea Satellite to Onshore Facility Chevron Jansz SE/Io South 2000 Firm Plan 1300 Subsea Satellite to Onshore Facility Chevron Wheatstone 2004 Firm Plan 216 Subsea Satellite to Fixed Production Exxon Mobil Jansz 2002 Firm Plan 1300 Subsea Satellite to Onshore Facility Inpex Ichthys 2000 Firm Plan 230 Floating Production Shell Prelude/Tocatta 2007 Probable 200 Fixed & Floating Production and Subsea Woodside Brecknock 1979 Possible 300 Floating Production Woodside Calliance 2000 Possible 420 Subsea Satellite to Floating Production Woodside Pluto 2005 Under Development976 Fixed Production Platform and Subsea Woodside Sunrise 1974 Possible 180 Fixed Production Platform and Subsea Woodside Torosa 1971 Possible 250 Fixed & Floating Production and Subsea Woodside Troubador 1974 Possible 160 Subsea Satellite to Fixed Production Figure 1 – Asia Pacific Deepwater Developments Figure 2 – Australia Deepwater Developments
  • 3. Advances in Subsea and Deepwater Pipeline Pre-commissioning 3 The offshore / deepwater pipeline market dynamics are explained further below: 1.1 Market Overview Summary From the data in section 1 we can draw the following conclusions: a. That there are a large number of deepwater pipeline projects planned in the Asia Pacific region between 2008 and 2014 b. There is steep in crease in global deepwater pipeline installation planned in the next few years, peaking in 2011 c. Services and techniques will be required to assist with the pre-commissioning and commissioning of such pipeline systems Figure 3 – Global Offshore Pipe lay Forecast Figure 4 – Global Pipe lay Forecast by diameter
  • 4. Advances in Subsea and Deepwater Pipeline Pre-commissioning 4 2.0 Pipeline Pre-commissioning – What Do We Mean? The following flow chart illustrates the pre-commissioning process as typically applied to oil pipelines. The process for gas lines is similar but involved additional steps prior to handover such as removal of hydrotest water (dewatering), drying, MEG swabbing and nitrogen packing (these are not covered in this paper). Cleaning & gauging of pipeline section Flooding & testing of pipeline section Depressurise line and handover to client filled with treated water Displace hydrotest water with oil Dewater using compressed air BJ Activity Client Commission the pipeline Perform Caliper Survey, possibly c/w dewatering Nitrogen purge and pack the line Treat the line with batch of corrosion inhibitor Optional Services Figure 5 – on LHS shows a typical offshore vessel based spread required to deliver the above services to a subsea pipeline.
  • 5. Advances in Subsea and Deepwater Pipeline Pre-commissioning 5 3.0 The Aims of Subsea Pipeline Flooding The first subsea pigging units were conceived and developed to overcome the problems associated with flooding and pigging pipelines in deep water. The latest subsea flooding device is the BJ RFM (Remote Flooding Module), which essentially achieves the same objectives using up to date ROV and Subsea technologies. The RFM is a Subsea flow control and regulation system. Once positioned on the seabed and connected to the pipeline to be flooded or pigged by HP loading arm, it is “operated” by the ROV opening the valves to the pipeline. The hydrostatic head of the sea then enters the pipeline through the RFM because of the differential pressure between the inside of the pipeline, which is at atmospheric pressure and the sea. Seawater enters the RFM via a filter manifold, which is installed at the specified filtration level, usually between 50 and 200 microns. It passes through a Venturi device, which creates a small pressure drop in the on board flexible RFM chemical tanks which are connected to the water flow pipework. This small differential pressure is used to induce anti-corrosion chemicals into the water flow at the desired rate. This is pre-set prior to deployment and ROV adjusted Subsea if necessary via control valves. Figure 6 – Overview of Remote Flooding Module
  • 6. Advances in Subsea and Deepwater Pipeline Pre-commissioning 6 The chemically treated water flow is controlled to a pre-determined rate via a flow regulation system. This maintains the water flow at the desired speed to match specified or optimum pig speed or flooding rates. Again this can be pre-set prior to deployment and because the rate is controlled at a steady level the chemical inducement is assured throughout the entire “unassisted” operation. A Boost pump is required to complete final pigging operations due to pressure equalisation. This pump is ROV driven, usually operated when the ROV returns to location to disconnect and recover the RFM, and in Deepwater is required only for a very short time. The vessel and ROV can leave the unit in isolation on the seabed during the unassisted operations and carry out other tasks. There is no need for connection to anything other than the pipeline. On board batteries power data-logging instrumentation which logs flows, chemical rates etc, and visual readouts allows the ROV to check status before it leaves and when it returns. The RFM is positioned on the seabed by ROV and connected to the pipeline to be flooded via the innovative rigid loading arm pipe system. The ROV then positions itself on the unit’s roof from where it can view instruments and operate valves to monitor the initial stages of the operation and adjust if necessary chemical control valves. Filtration and chemical treatment specifications are fully met by onboard facilities. Chemicals are stored onboard in flexible tanks and introduced by a Venturi system regulated by detecting changes in the water flow through the unit and automatically adjusting the chemical flow accordingly. To summarise the aims of subsea pipeline flooding: • Reduce the size of vessel required for pre-commissioning operations • Negate the need for the vessel to remain on station during the bulk of the operations • Remove the need for an expensive down-line, which is prone to damage • Reduce schedule by increasing possible pig speed • Reduce schedule by use of seabed water removing thermal stabilisation for Hydrotest • Reduce crew size, equipment spread size, environmental impact by removal of diesel engines on pumps, improve safety by taking operations off-deck
  • 7. Advances in Subsea and Deepwater Pipeline Pre-commissioning 7 4.0 Offshore Vessel Requirements – the Cost Driver Previously in this paper I have described the functionality and development of subsea flooding and testing, and in the following section we look at the commercial drivers to use such a system. As an example we take the following pipeline as an example: Line NPS 16” Wall Thickness 12.5mm Line Length 8KM Water Depth at launcher 1000m Water Depth at receiver 1000m Water Temp at surface 28°C Water Temp at Seabed 4°C Average Flooding pig velocity required 0.5 m/sec Flooding Rate Required 3,420 lpm Table 1 – Pipeline details (illustration) The important data from the above is that we need to inject 3,420 lpm of filtered, treated sea water into a pipeline at a water depth of 1000m. There are 2 ways to achieve this: Use a Vessel Based Spread and Down-line The vessel based spread must be designed to deliver 3,420 lpm in to the pipeline – hence the first consideration is the size of the down-line required. Having looked at the various pressure drops across the down-line, we then need to evaluate the pump power (HHP / BHP) required to overcome the system pressure losses and deliver the flow to the system. Down-line Diameter Down-line Length Pressure Drop in barg * HHP required for 1m/sec BHP required for 1m/sec** 2” 1,200m 210 barg 1,600 HHP 2,560 BHP*** 3” 1,200m 78 barg 594 HHP 1,014 BHP 4” 1,200m 24 barg 183 HHP 382 BHP**** Table 2 – Pressure drops and HHP calculations vs. down-line diameter * Using Mears pipe flow calculator ** Based on 65% efficiency (centrifugal pump) plus 100bhp for engine ancillaries *** Maximum power from portable, marinised diesel engines approx. 1,800 BHP **** Pump packages rated at 350 to 500 BHP readily available
  • 8. Advances in Subsea and Deepwater Pipeline Pre-commissioning 8 Thus taking the data in table 2 we can see that to flood this notional 16” pipeline at a depth of 1,000m would require: • A 4” x 1,200m down-line including reel and installation system • A 4” hot stab to connect the hose to the subsea launcher • 2 qty diesel driven 500 bhp centrifugal pumps • Lift pumps, break tanks, filters, chemical injection units and hoses To put this into perspective in figure 7 we show the deck space required on a DP vessel for the above spread (figure 8 illustrates space requirement for similar RFM spread): Figure 7 – Vessel Space Requirement Figure 8 – Reduced Space Using RFM The vessel based spread c/w down-line requires a deck space of approx. 290m2 to flood a 16” pipeline at 0.5m/sec. To perform such an operations the following steps are required: a. Deploy down-line and stab in to subsea launcher - 12 hours b. Flood the 8km line at 0.5m/sec - 5 hours c. Recover down-line to surface - 12 hours d. Allow fill water temperature to stabilise - 48 hours e. TOTAL TIME FOR FLOODING - 77 HOURS
  • 9. Advances in Subsea and Deepwater Pipeline Pre-commissioning 9 Use a Vessel Based RFM to Flood the Line Figure 7 shows the deck space required for the RFM – this is approx. 32m2 . The RFM can carry sufficient chemicals to fill 16” x 8km in a single deployment. Using the vessel crane the RFM can be quickly deployed subsea and connected to the subsea launcher. Thereafter it can perform the initial flooding of the pipeline at velocities up to 1m/sec. 16" Pipeline Predicted End Point of Flooding by RFM: Data Starting end depth d1 = 1000 metres. Finishing end depth d2 = 1000 metres. Total line length L = 8 kilometres. Internal diameter of line b = 371.4 millimetres. Assumed or required pig speed v = 0.5 m/second. Assumed pig (train) driving pressure 2 bar. (If unknown, assume 1 bar per pig.) Slug length trapped air before boost 81 metres. Proportion of line flooded by unassisted RFM = 99.0 %. Time taken for filling by RFM at pig speed 0.5m/s is 4.4 hours. Volume to be boost pumped for completion = 8.8 cubic metres. RFM Sta Pipelin d d Wat Ai En Figure 10 – RFM calculation for 16” x 8km line. In figure 8 we can see that the RFM can flood the line within 4.4 hours and that 8.8m3 has to be pumped by the ROV powered boost pump – please consider the line has been flooded with water at seabed ambient temperature. The vessel based RFM spread requires a deck space of approx. 32m2 to flood a 16” pipeline at 0.5m/sec. To perform such an operations the following steps are required: a. Deploy down-line and stab in to subsea launcher - 2 hours b. Flood the 8km line at 0.5m/sec - 5 hours c. Recover down-line to surface - 2 hours d. Allow fill water temperature to stabilise - 0 hours e. TOTAL TIME FOR FLOODING - 9 HOURS Figure 9 – RFM ready to deploy
  • 10. Advances in Subsea and Deepwater Pipeline Pre-commissioning 10 4.1 Vessel Cost Summary Looking at the example of flooding a 16” x 8km line at 1,000m water depth, we can draw the following conclusions: 1. The down-line option requires almost 10x the deck space of the RFM option – with the current shortage of DP vessels and with vessel rates of around US$40,000 per day, this can have a major impact on overall project costs 2. As the RFM floods the line with ambient temperature water there is no stabilisation period – this could represent a saving of 2 days 3. The deployment and recovery time for the RFM is far quicker than for a 4” down-line As with all new technologies, there are circumstances where the RFM may not be suited to a deepwater project. These include: • Where one or both ends of the line terminates at a platform / FPSO such as when using SCR’s • Where a down-line will be deployed for other operations and can conveniently be used for flooding • Where a large number of pigs are used • Where the line has to be flooded with either fresh water or MEG • Where one on of the line terminates in shallow water.
  • 11. Advances in Subsea and Deepwater Pipeline Pre-commissioning 11 5.0 Advances Made in Subsea Pigging Equipment The original Subsea Pigging Unit was designed by pre-commissioning Engineers with little input from ROV and Subsea specialists, despite efforts to include them. Whilst the device was successful in achieving its’ pre-commissioning objectives, it wasn’t the most optimum method of operation for the ROV or deployment Vessel. Unwieldy HP flexible Jumper hoses, relatively crude instrumentation and brand new ways to use Choke Assemblies meant there were areas to improve, for example: . • The RFM holds more chemical than the original Subsea unit, allowing less recovery and deployment cycles and use on longer and larger lines • The RFM uses rigid loading arm technology to reduce Subsea connection times and reduce the risk of damage to HP flexible jumper hoses • The RFM is extremely ROV friendly, ROV specialists were involved in design to ensure minimum ROV interface issues • An on-board latching mechanism allows very fast ROV connection for boost pumping • An on-board emergency release system means no risk of an ROV getting stuck on the RFM • Advances in electronics means much more reliable instrumentation • Deployment times are down to less than one hour in Deepwater Figure 11 – RFM loading arm stabbed in Figure 12 – ROV operating RFM
  • 12. Advances in Subsea and Deepwater Pipeline Pre-commissioning 12 6.0 Development of Subsea Hydrotesting Unit Recent developments in Subsea pumping systems have allowed ROV pump skids to carry out Subsea hydrotesting and leak testing of pipeline systems, thus allowing additional savings on Vessel size, cost etc. When used in conjunction with the RFM, significant overall benefits can be achieved. Naturally, the systems that can be tested are limited by the maximum performance available from an ROV test pump skid. The BJ SHP can produce over 40 litres per minute pressurisation rate from typical Project ROV’s. In section 4 we reviewed a down-line system required to flood a 16” x 8km line. Deepwater lines typically require hydrostatic testing at between 200 barg and 350 barg. A typical 4” down-line would not be rated for such pressures (specialised down-lines such as those produced by Deepflex and Technip can handle such pressures but are too costly for such applications). Thus a different down-line must then be deployed to in order to pressurise the line. Deployment times for the down-line will be similar to those of the flooding down- line. A the SHP can be deployed with the RFM boost pump and hence there is no delay between completion of flooding and commencement of pressurisation – it is estimated this saves a minimum of 24 hours per pipeline. Pipeline Nomial bore (inches) Length (metres) Vol/bar (litres) Bar/min ex SHP Test Pressure (bar) Vol to test pressure (litres) Time to test pressure (hours) TS-WI-FL-01 12 9553 31.83 0.94 431 114523 7.62 TS-P-FL-01 10 9577 21.71 1.38 431 9921 5.20 TS-P-FL-02 10 9248 20.96 1.43 431 9580 5.02 TS-T-FL-01 8 9553 13.57 2.21 431 6210 3.25 TS-GL-FL-01 8 9479 13.47 2.23 431 6162 3.23 Figure 13 – SHP Unit Table 3 – Example pressurisation times using SHP Line 1 Line 2 Line 3 Line 4 Line 5
  • 13. Advances in Subsea and Deepwater Pipeline Pre-commissioning 13 7.0 Smart Gauge Technology Previous sections of this paper have dealt with the flooding and hydrostatic testing of deepwater pipelines – in this section we deal with the gauging of the line. All offshore pipeline pre-commissioning operations include the proving of the internal bore of the line – this is normally achieved by fitting a segmented aluminium disk (see figure 14) to one of the filling pigs, the disk having an outside diameter equal to between 95% and 97% of the minimum pipeline i.d. The principle is that any restriction in the line (buckle, dent etc.) would cause one of the aluminium “petals” to bend indicating a restriction in the line. The gauge pig is then run as part of the pipeline filling pig train and most specifications require that the gauge plate be visually inspected prior to commencement of the hydrotest – thus ensure there is no mechanical damage with in the line that could be affected by the hydrostatic test – figure 15 shows a gauge plate received with some damage. Removing and inspecting the gauge plate is a simple operation onshore, and for pipelines with above surface terminations, but requires additional work on pipelines terminating subsea and deepwater. Thus BJ developed the SMARTGAUGE™ to meet the following needs of deepwater pipelines: 1. Allows lines with restrictions (heavy wall bends, PLET hub restrictions, reduced bore valves) to be gauged 2. Permits gauging data to be reviewed and analysed assist in pinpointing any restriction identified – allows valves etc to be discounted 3. Incorporates a system to remotely annunciate the result of the gauging run such the hydrotest can commence immediately upon completion of flooding without the need to recover the gauge plate to surface for visual inspection. Figure 15 –Gauge plate with damageFigure 14 –Gauge pig prior to launch
  • 14. Advances in Subsea and Deepwater Pipeline Pre-commissioning 14 A standard mechanical gauge plate gives no indication of where any damage occurred, making identifying location difficult, time consuming and expensive. Using the multi- channel BJ SMARTGAUGE™ tool with a segmented flexible gauge plate both the clock position and the location of multiple defects can be ascertained, reducing the time needed to find the problem. In a further enhancement for deepwater lines a pinger can be fitted to the tool, such that any damage to the be left in the receiver if no damage is detected or removed and repairs made prior to hydrotest in the event that damage has occurred. Valuable DSV time can be saved in either case. 8.0 Future developments Improving ROV capabilities and advances in electronics will undoubtedly have positive benefits to remote flooding and pigging systems. Use of remote data transmission and signalling will also allow other associated tasks to be reduced in impact and cost or taken completely off of project critical paths. All future developments will be driven by the same common objectives: • Reducing the in-field time required to complete subsea pre-commissioning services, hence saving on both the vessel costs and hire periods for pre- commissioning spreads • Removing or replacing operational processes that have high risk (such as deployment of large diameter down-lines in deep water) • Minimising offshore vessel deck space for pre-commissioning equipment, allowing smaller & cheaper vessels to be used Figure 16 –BJ SMARTGAUGE™
  • 15. Advances in Subsea and Deepwater Pipeline Pre-commissioning 15 Sources Figure 1 Offshore Engineer Figures 2 and 3 Australian Deepwater Development Market, Infield Ltd, Perth 2008 Figures 11 and 12 Technip UK Ltd Figure 14 Profile Ltd, UK. Other figures BJ Services References 1. Remote Deepwater Developments, Les Graves, World Pipelines, December 2007