In the past decade Brays Bayou has flooded several times due to massive peak flows and urban stormwater runoff. The increase in volume of runoff can be attributed to both increased urbanization and changing weather patterns. However, as flooding issues continue to worsen along the Bayou and are especially dangerous in vulnerable areas such as the Texas Medical Center, this project seeks to redesign the portion of the Bayou between Fannin Street and Main Street in order to mitigate the flood threat. In the early 2000s, the U.S. Army Corps of Engineers (USACE) and the Harris County Flood Control District (HCFCD) launched Project Brays, which outlined specifications for the redevelopment of the entire Bayou. One goal of this project is to design improvements that meet the specifications outlined by USACE and HCFCD. The development of the Bayou will consider increased stormwater flow due to the construction of a new hotel on Main St., and will require close coordination with the developers of the new 7200 Main Street Hotel. The area between the hotel and Bayou will be designed with guest amenities such as trails, terraces, access points, trees, and landscaping. In addition, this project will redesign the Greenbriar Bridge between Braeswood Boulevard and Main Street in order to reduce its backwater effect on the Bayou and ensure that it abides by the elevation specifications mandated by Harris County.
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
Final fall senior design presentation
1. BRAYS BAYOU + BRIDGE
Fall 2015 Concept Presentation
Presented by:
Julianne Crawford, Avi Gori, Kasia Nikiel
2. Project Description + Goals
➔ Design Brays Bayou channel modifications
➔ Reconstruct of Greenbriar Bridge between Braeswood & Main
➔ Consider of additional stormwater flow from 7200 Main
➔ Coordinate with 7200 Main development for other features
➔ Protect Meyerland area from future flooding
6. Project Brays
➔ Funded by US Army Corps and HCFCD
➔ Comprehensive re-design of Brays Bayou
◆ Channel Modifications
◆ Bridge Replacement/Renovation
◆ New Detention Area
➔ Aimed at mitigating riverine flooding throughout Brays Bayou Watershed
➔ Status:
◆ Upper Reach: Completed
◆ Middle Reach: In Progress
◆ Lower Reach: In Progress
➔ Scheduled to be completed in 2021
26. Modified Scenario
➔ Retaining walls and some
widening on both banks
from Main to Greenbriar
➔ Retaining walls and
substantial widening on the
right bank from Greenbriar
to Fannin
33. Impact of Proposed Modifications
➔ Modifications along the Main to Fannin portion of the channel should not have
drastic adverse effects on downstream sections.
➔ According to the 100-year floodplains, both current and post project brays, the
areas downstream of our site already face a much lower inundation hazard
than the middle and upper reaches.
35. Brays Bayou
➔ Finalize channel modifications for Main to Fannin segment
➔ Add additional cross sections to existing HEC-RAS geometry
➔ Perform unsteady state HEC-RAS analysis
➔ Incorporate additional flow from hotel if necessary