CRITICAL CHAIN PROJECT MANAGEMENT – A NEW PROJECT MANAGEMENT
               PHILOSOPHY FOR MULTI PROJECT ENVIRONMENT

                       Jagathipriya, Rajendrasingh.P.Byali, M.V.Kannan
           Projects Division, PPEG, ISRO Satellite Centre, Bangalore-560017, India

                                                   Abstract
Traditional project management has been concentrating mainly on single project optimization based upon task
dependency constraints. The Critical Chain Project management (CCPM) provides a substantial improvement in
   the PM methodology by incorporating resource dependency and buffer management. CCPM improves the
   project scheduling by protecting it from common cause variation (uncertainty, multi-tasking). For a multi-
      project environment CCPM is best suitable since critical chain is calculated based upon both resource
 dependencies and task dependencies and the constraint of multi-tasking is also delt with. Buffer management
  enhances measurement and decision making for project control. This paper provides an insight to the CCPM
         concept with a practical example of scheduling multiple satellite projects using this technique.



    Keywords: Critical Chain, Project Management, Resource Constraint, Multi-tasking, Buffer Management

TRADITIONAL PROJECT MANAGEMENT:                                The task commences after half the allotted time is
         Traditional Project Management concepts               over and once the task commences, if a problem is
have been in use since 1950’s. The development of              encountered the buffer allotted becomes useless
PERT/CPM provided the initial breakthrough in                  and the estimate will certainly overrun.
Project planning/scheduling. But over a period of
time certain limitations in this methodology has               Task Estimation in PERT/CPM
necessitated to relook at the philosophy behind PM                       In traditional PM techniques the safety /
techniques.                                                    buffer is included in each and every task to take
                                                               care of delays/uncertainties in completion of work.
Limitations of PERT/CPM                                        The contributing factors for this are: non-
• Applicable only for Single Project scheduling.               availability of resources in time, to overcome
• Buffer built into each individual activity is overkill       technological problems encountered, to incorporate
  and inefficient.                                             last minute changes in design/configuration etc.
• Strict adherence to task start date and end date             For example - When a task estimate is made
  will lead to work expanding to fill the time                 considering the quantum of work it may require 5
  available.                                                   days. But safety is added to incorporate unplanned
• In a multi project environment collective load on            work interruptions, uncertainty etc and the total
  each project resource is not assessed, as each               task duration becomes 10 days. This estimate is in
  project is scheduled individually which ultimately           turn used to calculate the Critical Path of the
  leads to multitasking.                                       project.
                                                                         Most of the organizations work in a multi-
Laws of Project Management:                                    project environment. As in our case Project
         Generally the following two laws of                   Directors are responsible for successful completion
project management influence the task duration                 of the project. Project Directors have a tendency to
estimation and its completion.                                 be demanding. They think that their project is of
                                                               highest priority and they want to see frequent
1. Parkinson’s Law:                                            progress in their project. This focus on showing
          Work expands to fit the allotted time. If a          progress on as many active projects as possible is
task is estimated to take 10 days, it usually                  the major cause for multi-tasking.
doesn’t take less. This adjustment of effort to fill
the allotted time can come in number of ways.                  CRITICAL CHAIN:
Most of the time there is little or no reward for                       Introduced in 1997, by Eliyahu.M.Goldartt
completing individual activities early. If individuals         this methodology is based upon insight into human
complete the activities early, they get to do more             nature and what happens when a project
work. Most of the people have a tendency to do                 management discipline is applied to people. [4]
the work when the activity completion becomes                           Critical Chain is defined as the longest
critical. This leads to underutilization of the                chain    of   tasks   that  consider   both     task
contingency time resulting in completion of most of            dependencies and resource dependencies. This is
the work in the later portion of the scheduled                 different from the definition of the Critical path,
activity time.                                                 which is defined as the longest chain of tasks
                                                               based upon task dependencies. Critical Chain
2. Student’s Syndrome:                                         recognizes that a delay in resource availability can
        Given a project that is composed of tasks              delay a schedule just as a delay in dependant
with time buffer, it leads to Students Syndrome.               tasks.




                                                           1
Critical Chain Project Management derives
from applying the Theory of Constraints (TOC) to           1. Task Estimation in CCPM
Project Management. TOC says, “Any system must                       Critical Chain task estimating requires a
have a constraint. Otherwise, its output would             change in individual and organizational behavior to
increase without bound, or go to zero.” TOC                be effective. The removal of hidden safety in task
identifies the constraint of a project as Critical         durations      requires    establishment    of    an
Chain or “The sequence of dependent events that            organizational culture that removes fear of
prevents the project from completing in a short            exposing this safety and removing it from task
interval. Resource dependencies determine the              estimates.
critical chain as much as do task dependencies.”[1]                  It is important to note that safety is not
                                                           removed and thrown away. Instead it is pooled as
Relay Race Approach:                                       a project resource as opposed to a hidden task-
          Critical Chain utilizes the relay race           level resource. This can be achieved by estimating
approach to capitalize on the benefit of early             based on following assumptions:
finishes. In the relay race each runner runs his leg       •    When deriving an estimate it should be
as fast as possible and hands on the baton off to               assumed that all material and information
the next runner who is ready to run as soon as the              needed for the task is on hand.
preceding runner is finished. Because the runner           •    It is assumed that uninterrupted focus on the
capitalizes on an early finish of the preceding                 task is given.
runner, a fast leg can offset a slow runner to the         •    It is also assumed that there won’t be any
benefit of the team. Applying this to the critical              surprises that cause additional work.
chain project when one task is getting close to
competition, you must have the next task’s                 2. As Late As Possible Scheduling:
resource on the track and be ready to start as-                      The tasks are scheduled as-late-as-
soon-as-possible     after   the   preceding   task        possible (ALAP) based upon the target end date.
completes.                                                 1. Using production analogy, the Work In
          This relay race approach means that the              Progress (WIP) is minimized and not incurring
team must de-emphasize the task scheduled start                costs earlier than necessary.
and finish dates and instead concentrate on                2. From project executive’s viewpoint, there is
triggering their preparation and start on the                  better focus at the critical start of the project
preceding task’s progress. Importantly, once a                 because there simply aren’t many tasks
task is started, people should work as fast as                 scheduled to start.
possible towards completion without clocking               3. Importantly in complex, knowledge work, your
themselves to the scheduled finish date (As                    knowledge increases the further you go into
against students’ syndrome).                                   the project. By scheduling tasks ALAP, you are
                                                               capitalizing on this increasing knowledge and
The following table gives a general comparison                 will significantly minimize the need for re-
between Critical Path method and Critical Chain                work.
method.                                                    4. If a task is finished earlier than planned, the
Critical Path Method      Critical Chain Method                project executive might be accused of
Focus is on single        Address multi-project                sandbagging the estimates instead of being
project                   scenario as well as                  rewarded for completing ahead of schedule. In
                          single project case                  this environment, the project executive
Focus is directed to      Focus is on both                     worries about the future estimates being cut
manage activities in      resource and activity                based upon history. Hence he always tries to
critical path – the       constraints                          officially finish on schedule. If the task is
longest path in network                                        finished early then the next problem is
The single project        Having a multi project               encountered. The task that is dependent upon
optimization leads to     environment CC helps                 the completed task completion might not be
local, rather than global in achieving global                  able to start early because the required
optimization in multi-    efficiency                           resources are off doing something else.
project situations
Slack      available   in Project buffer is treated        3. Buffer Management:
project is not pooled as project resource and                        The major difference in Critical Chain is
together and is not buffer management is                   the pooling of buffer and recognizing it as a project
managed as a resource     used as a tool for               resource. These buffers automatically contract
                          project evaluation.              when they are pushed by overrunning tasks and
Focus is on individual Project due date is                 absorb the overruns without affecting the target
due dates of each tasks   given importance and is          end date.
                          achieved by monitoring                     Three types of Buffer have been
                          the project buffer               identified.
                                                                     -   Project Buffer
SALIENT FEATURES OF CCPM                                             -   Feeding Buffer
The three salient features of CCPM have been                         -   Capacity Buffer
given below.



                                                       2
3.1 Project Buffer: It protects the target end                 3.3 Capacity Buffer: Capacity buffer comes into
date against overruns in critical chain tasks. It is           picture for multi-project scheduling where the
placed at the end of the project after the last                most critical / overloaded resource (known as
Critical Chain task. In effect, the total safety               Drum Resource) has to be protected / leveled to
hidden in each individual Critical Chain task is               overcome the slippage in schedule due to the non-
reduced and placed in project buffer.                          availability of drum resource. Capacity Buffer will
                                                               be inserted between the last use of the drum
3.2 Feeding Buffer: The Project Buffer protects                resource of one project and the first use of the
critical chain from overruns. However the critical             drum resource in the next project. This acts as a
chain is exposed to overruns from non-critical                 protection for the second project against changes
chain tasks that link to the critical chain. Here the          in first project that delay the availability of drum
Feeding Buffer, placed at the point where the                  resource.
feeding chain (non-critical activities) intersects
with the critical chain, protects the critical chain
from the overruns of the non-critical chain tasks.




Fig1: Activity scheduling as in Critical Path
Method




Fig2: Activity scheduling following Critical
Chain Method

The above 2-activity network diagrams provide a                the most demand or is so limited by capital costs
simple example to understand the difference                    that it is the bottleneck around which schedules
between the CPM & CCPM. The resource for each                  are drawn. There can be more than one drum
activity has been given beside each activity bar               resource.
chart. In CPM the activities in red color indicates
the Critical Path. It can be seen that the project             Case Study: A practical example has been given
takes 65 days to be completed. It can be noted in              below taking into consideration two communication
Fig 2 that each task duration has been reduced by              satellites of I-2K bus, which are similar in
50%. Feeding Buffer has been introduced where                  configuration.
the non-critical chain activities intersect the critical                 A typical communication satellite takes
chain path. Project Buffer, which is 50% of the                18-24     months     for    realization  (from   the
duration of the total Critical Chain activities, has           conceptualization to launch) depending on the
been introduced in the end of the project. It can be           technical complexities involved. The time taken for
observed that the Project duration has come down               integration, from the delivery of structure to AIT
by 10 days (15%).                                              till Shipment of spacecraft for launch is around 11
                                                               to 12 months.
Multi Project Critical Chain:                                            From the past experience it is observed
          The term Drum Resource refers to the                 that when a single project team is given the
key, critical resource around which project will be            responsibility of realization of projects, which are
synchronized. In production system the drum is                 similar in configuration, the work will be taken up
the constraint of the system. This constraint sets             serially. In other words, the activities related to
the pace of the whole production system just as a              one project are completed and then the next
drum is used to set the marching pace of a troop.              project activities are taken up. The time taken for
In the project management area, the drum                       launching the repeat satellite is generally 12 – 14
resource is usually the resource that is always in             months from the date of launch of the first



                                                           3
satellite. Considering this an example of 2               Based on the analysis carried out the following
communication satellites has been taken for               observations are made:
scheduling using the critical chain method.               1. The time taken for realization of the satellite
          In the example considered the activities            in the current scenario is around 327 days
from the delivery of structure to AIT has been                from the date of delivery of the structure.
considered. Only major milestone activities                   Using CCPM the duration for each activity has
concerned with delivery of subsystems to AIT,                 been reduced by 50%. The duration for HILS
integration and testing activities till shipment of           test, Thermovac Test and Assembled mode
the satellite for launch is considered. Fig-3 gives           Integrated Spacecraft tests are not reduced
the activities scheduled in the Critical                      exactly by 50% but only the setup time for the




Fig 3: Project scheduling using conventional                   facility has been reduced. This is because the
method.                                                        test duration for these are fixed which is also
                                                               dependent on the number of test cycles /
Path method. Fig-4 gives the Schedule for two                  cases it has to undergo.
Satellite projects planned based on Critical Chain        2.   The integration activity of the bus system
method.                                                        packages commences as and when the
The following assumptions are made for arriving at             packages are delivered to AIT.
the schedule:                                             3.   Thermovaccum facility can be identified as the
•    Subsystem configuration of both the satellites            Drum resource. This is because being a critical
     considered is assumed to be similar.                      facility it can lead to single point failure if
•    The duration time given in Fig-3 is based on              advanced planning is not done. But since
     previous experience and is being used in the              adequate gap is available in the second
     organization for scheduling all the spacecraft            project for the commencement of the
     project activities.                                       Thermovac test Capacity Buffer has not been
•    The Relay race approach is assumed: i.e the               added.
     necessary resources to commence the activity         4.   It can be observed that the duration for
     as soon as the preceding activity is completed            completion of Satellite-1 has been reduced
     are available.                                            from 327 days to 231 days i.e by 110 days
                                                               (29.35%). Satellite-2 has taken 242 days.
                                                               (26%reduction).




                                                      4
Fig 4: Multiple Satellite Project scheduling                    delay in the completion of the project
using CCPM                                                      activities.
5. The increase of 11 days in Satellite-2                  7.   When      the   subsystem      realization  and
    completion is because RCS integration activity              integration activities for both the project are
    in the Satellite-2 commences only after the                 taken up in parallel it can be observed that
    completion of RCS integration activity of                   both the satellites can be delivered for launch
    Satellite-1. This is assuming that same team is             at a gap of 25 days.
    working on the integration of RCS for both the
    projects.                                              Drawbacks / Limitations of CCPM:
6. The buffer in each activity is made zero and                    There is no clear-cut answer on the ‘best’
    the Project buffer is added at the end for each        way to define the critical chain, and often refer to
    project (75 days – which is 50% of the total           using   the    strategic     considerations    when
    individual activity buffer). The consumption of        determining it. This is similar to the approach
    this buffer gives an indication of the extent of       taken by Goldartt himself in the development of
                                                           the TOC when he declared that a process



                                                       5
bottleneck (or constraint) must be a strategic
decision and not to be based on the accidental              References
situation of a plant at a given time.                       [1] Goldratt Eliyahu.M., “Critical Chain”, North
          The available literature of CCPM does not         River, Great Barrington, MA, 1997.
make a distinction between the technological                [2] Goldratt Eliyahu.M., “The Goal”, North River
uncertainty of an activity and the possible delay           Press, Croton-on Hudson, New York, 1984.
due to unavailability of the required resources at          [3] Goldratt Eliyahu.M.,”Theory of Constraints”,
the time the activity is due to start.                      the North river Press, Great Barrington, 1999.
          The assumption of multi tasking by                [4]    Larry.P.Leach,    “Critical  Chain    Project
resources in CCPM is critical to the roadrunner             Management Improves Project Performance”,
mentality of resources, that is, start an activity as       Advanced Project Institute, 1997.
soon as the predecessor activities are finished.            [5]      Thomas       Lechler,     Boaz      Roven,
However this assumption is generally valid only for         Edward.A.Stohar, “Critical Chain: A New Project
production line concept or for projects that are            Management Paradigm or Old Wine in New Bottle?”
repetitive in nature. Generally in an R & D                 Version6/7/05, CPMR, 2005.
organization multi tasking is quite common and              [6] Jaume Ribera, Marc Sachon, Alex Grasas,
cannot be avoided. This may be due to large                 “Putting the Core Elements of Critical Chain Project
period of idleness that would occur otherwise due           Management       into   perspective:    A   general
to dependency         on external resources for             framework for Buffer Management”, IESE Business
materials/components, technological problems,               School, Spain, 2003.
delay in finalization of configurations due to multi-
disciplinary interactions etc.
          The other critical factor on the roadrunner
mentality is the sharing of information between
activity owners, implemented in CCPM via the
capacity buffers, notifying the delay in availability
of the drum resource fro the next connected
activity. To achieve this, high transparency is
needed on how time is used in the project
organization.
          In spite of the above limitations Critical
Chain method is becoming popular in Aerospace
industries and is already successfully implemented
in the Software industry for execution of projects.

Summary:
This paper gives an overview of the CCPM and the
implementation of this method for execution of
spacecraft projects. Also a case study has been
given where in the methodology of implementation
has been discussed. The essential changes
introduced by CCPM can be summarized as
follows:
     1. Focus on total systems throughput rather
         than individual projects.
     2. Identify /manage constraint resource to
         avoid or solve resource conflicts.
     3. Using buffer management as the primary
         tool for project management and control.
     4. Avoid      multitasking    which leads  to
         prioritizing project activities.

        To exploit the benefits of this method it is
needed to establish a total project environment
that integrates both the human behavioral
elements and methods into an effective operating
unit. The human side requires everyone, from
management to the project team, to understand
and buy-in to the concepts.

Acknowledgements
We acknowledge the valuable suggestions given by
Mr.H. Bhojraj, GD PPEG. We also express our
sincere gratitude to Dr.K.N.Shankara, Director
ISAC for his constant encouragement.



                                                        6

Contenu connexe

Tendances

Terry.conroy
Terry.conroyTerry.conroy
Terry.conroyNASAPMC
 
Agile Project Manager
Agile Project ManagerAgile Project Manager
Agile Project ManagerYogesh Hubli
 
K.pagel.beene
K.pagel.beeneK.pagel.beene
K.pagel.beeneNASAPMC
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidyNASAPMC
 
Richards.robert
Richards.robertRichards.robert
Richards.robertNASAPMC
 
Brian muirhead v1-27-12
Brian muirhead v1-27-12Brian muirhead v1-27-12
Brian muirhead v1-27-12NASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
Lecture6
Lecture6Lecture6
Lecture6soloeng
 
Carmichael.kevin
Carmichael.kevinCarmichael.kevin
Carmichael.kevinNASAPMC
 
Introduction project management
Introduction  project managementIntroduction  project management
Introduction project managementHager Aamer
 
Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6IOSRJMCE
 
Cole ready aim fire impact!- status impact analysis - nasa
Cole   ready aim fire impact!- status impact analysis - nasaCole   ready aim fire impact!- status impact analysis - nasa
Cole ready aim fire impact!- status impact analysis - nasaNASAPMC
 
Murphy.dar jean.jean
Murphy.dar jean.jeanMurphy.dar jean.jean
Murphy.dar jean.jeanNASAPMC
 
Major Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperMajor Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperIan Heptinstall
 
Backup darren elliott
Backup darren elliottBackup darren elliott
Backup darren elliottNASAPMC
 
Noneman.steven
Noneman.stevenNoneman.steven
Noneman.stevenNASAPMC
 

Tendances (20)

Terry.conroy
Terry.conroyTerry.conroy
Terry.conroy
 
Agile Project Manager
Agile Project ManagerAgile Project Manager
Agile Project Manager
 
K.pagel.beene
K.pagel.beeneK.pagel.beene
K.pagel.beene
 
Spm unit 3
Spm unit 3Spm unit 3
Spm unit 3
 
4 Scheduling Monitoring
4 Scheduling Monitoring4 Scheduling Monitoring
4 Scheduling Monitoring
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidy
 
Richards.robert
Richards.robertRichards.robert
Richards.robert
 
Brian muirhead v1-27-12
Brian muirhead v1-27-12Brian muirhead v1-27-12
Brian muirhead v1-27-12
 
Methodoligies
MethodoligiesMethodoligies
Methodoligies
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
Lecture6
Lecture6Lecture6
Lecture6
 
Carmichael.kevin
Carmichael.kevinCarmichael.kevin
Carmichael.kevin
 
Introduction project management
Introduction  project managementIntroduction  project management
Introduction project management
 
An introduction to Critical Chain Project Management (CCPM)
An introduction to Critical Chain Project Management (CCPM)An introduction to Critical Chain Project Management (CCPM)
An introduction to Critical Chain Project Management (CCPM)
 
Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6
 
Cole ready aim fire impact!- status impact analysis - nasa
Cole   ready aim fire impact!- status impact analysis - nasaCole   ready aim fire impact!- status impact analysis - nasa
Cole ready aim fire impact!- status impact analysis - nasa
 
Murphy.dar jean.jean
Murphy.dar jean.jeanMurphy.dar jean.jean
Murphy.dar jean.jean
 
Major Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperMajor Projects - Faster Better Cheaper
Major Projects - Faster Better Cheaper
 
Backup darren elliott
Backup darren elliottBackup darren elliott
Backup darren elliott
 
Noneman.steven
Noneman.stevenNoneman.steven
Noneman.steven
 

En vedette

Getting a charge out of sceience
Getting a charge out of sceienceGetting a charge out of sceience
Getting a charge out of sceienceguest5ac3f31
 
Bideoaetahezkuntza
BideoaetahezkuntzaBideoaetahezkuntza
Bideoaetahezkuntzapatricia
 
Eskolen konparaketa teknologia berrien erabilera
Eskolen konparaketa teknologia berrien erabileraEskolen konparaketa teknologia berrien erabilera
Eskolen konparaketa teknologia berrien erabilerapatricia
 
C re ate-cirma-def-060611
C re ate-cirma-def-060611C re ate-cirma-def-060611
C re ate-cirma-def-060611CSP Scarl
 
Csp@scuola smarttv corso1
Csp@scuola smarttv corso1Csp@scuola smarttv corso1
Csp@scuola smarttv corso1CSP Scarl
 
I4school collaborative 3
I4school collaborative 3I4school collaborative 3
I4school collaborative 3CSP Scarl
 
Lean & Scrum at VietnamWorks
Lean & Scrum at VietnamWorksLean & Scrum at VietnamWorks
Lean & Scrum at VietnamWorksChris Shayan
 
Csp@scuola2011 seminariointro borri
Csp@scuola2011 seminariointro borriCsp@scuola2011 seminariointro borri
Csp@scuola2011 seminariointro borriCSP Scarl
 
Conflicting Interests: World Cup 2010
Conflicting Interests: World Cup 2010Conflicting Interests: World Cup 2010
Conflicting Interests: World Cup 2010Tawanda Kanhema
 
SVEA Presentazione progetto
SVEA Presentazione progettoSVEA Presentazione progetto
SVEA Presentazione progettoCSP Scarl
 
Evidence of implementation
Evidence of implementationEvidence of implementation
Evidence of implementationTess Baguio
 
sistema eragilea
sistema eragileasistema eragilea
sistema eragilealeire
 
Forecast of Duration of Iraq War: Bennett and Stam
Forecast of Duration of Iraq War: Bennett and StamForecast of Duration of Iraq War: Bennett and Stam
Forecast of Duration of Iraq War: Bennett and StamTawanda Kanhema
 

En vedette (20)

Getting a charge out of sceience
Getting a charge out of sceienceGetting a charge out of sceience
Getting a charge out of sceience
 
Bideoaetahezkuntza
BideoaetahezkuntzaBideoaetahezkuntza
Bideoaetahezkuntza
 
Eskolen konparaketa teknologia berrien erabilera
Eskolen konparaketa teknologia berrien erabileraEskolen konparaketa teknologia berrien erabilera
Eskolen konparaketa teknologia berrien erabilera
 
C re ate-cirma-def-060611
C re ate-cirma-def-060611C re ate-cirma-def-060611
C re ate-cirma-def-060611
 
Csp@scuola smarttv corso1
Csp@scuola smarttv corso1Csp@scuola smarttv corso1
Csp@scuola smarttv corso1
 
ubd
ubdubd
ubd
 
I4school collaborative 3
I4school collaborative 3I4school collaborative 3
I4school collaborative 3
 
Hp
HpHp
Hp
 
Lean & Scrum at VietnamWorks
Lean & Scrum at VietnamWorksLean & Scrum at VietnamWorks
Lean & Scrum at VietnamWorks
 
Hippel
HippelHippel
Hippel
 
Multiprojects management
Multiprojects managementMultiprojects management
Multiprojects management
 
Csp@scuola2011 seminariointro borri
Csp@scuola2011 seminariointro borriCsp@scuola2011 seminariointro borri
Csp@scuola2011 seminariointro borri
 
Conflicting Interests: World Cup 2010
Conflicting Interests: World Cup 2010Conflicting Interests: World Cup 2010
Conflicting Interests: World Cup 2010
 
Claude monet
Claude monetClaude monet
Claude monet
 
SVEA Presentazione progetto
SVEA Presentazione progettoSVEA Presentazione progetto
SVEA Presentazione progetto
 
Evidence of implementation
Evidence of implementationEvidence of implementation
Evidence of implementation
 
Travelling
TravellingTravelling
Travelling
 
sistema eragilea
sistema eragileasistema eragilea
sistema eragilea
 
Isha Hussain
Isha HussainIsha Hussain
Isha Hussain
 
Forecast of Duration of Iraq War: Bennett and Stam
Forecast of Duration of Iraq War: Bennett and StamForecast of Duration of Iraq War: Bennett and Stam
Forecast of Duration of Iraq War: Bennett and Stam
 

Similaire à Crtical chain m ethod ver 2

Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project ManagementGreta Blash
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdfSurashmie Kaalmegh
 
Advanced concept of project risk management project report
Advanced concept of project risk management project reportAdvanced concept of project risk management project report
Advanced concept of project risk management project reportramesh roy
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxbriancrawford30935
 
PM Session 6
PM Session 6PM Session 6
PM Session 6dmdk12
 
Critical chain - Eliyahu goldratt
Critical chain - Eliyahu goldrattCritical chain - Eliyahu goldratt
Critical chain - Eliyahu goldrattazadiriz
 
LATEST TOOLS FOR PROJECT PLANNING, MONITORING & IMPLEMENTATION final.pptx
LATEST TOOLS FOR PROJECT PLANNING, MONITORING & IMPLEMENTATION final.pptxLATEST TOOLS FOR PROJECT PLANNING, MONITORING & IMPLEMENTATION final.pptx
LATEST TOOLS FOR PROJECT PLANNING, MONITORING & IMPLEMENTATION final.pptxnovmanahmed
 
IT project management-IT project management-Unit-2.pptx
IT project management-IT project management-Unit-2.pptxIT project management-IT project management-Unit-2.pptx
IT project management-IT project management-Unit-2.pptxMAHASREEM
 
Transition to Critical Chain Multi.pdf
Transition to Critical Chain Multi.pdfTransition to Critical Chain Multi.pdf
Transition to Critical Chain Multi.pdfMuhammad Waqas
 
Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project ManagementMostafa Ewees
 
Project Management Notes 3
Project Management Notes 3Project Management Notes 3
Project Management Notes 3Golam Bitonsir
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project ManagementShyam Kerkar
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects Somashekar S.M
 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4POOJA UDAYAN
 
Project management : Pert and Cpm
Project management : Pert and CpmProject management : Pert and Cpm
Project management : Pert and CpmShashank Kapoor
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSZulfiquer Ahmed Amin
 

Similaire à Crtical chain m ethod ver 2 (20)

Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project Management
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdf
 
Advanced concept of project risk management project report
Advanced concept of project risk management project reportAdvanced concept of project risk management project report
Advanced concept of project risk management project report
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docx
 
PM Session 6
PM Session 6PM Session 6
PM Session 6
 
Critical chain - Eliyahu goldratt
Critical chain - Eliyahu goldrattCritical chain - Eliyahu goldratt
Critical chain - Eliyahu goldratt
 
LATEST TOOLS FOR PROJECT PLANNING, MONITORING & IMPLEMENTATION final.pptx
LATEST TOOLS FOR PROJECT PLANNING, MONITORING & IMPLEMENTATION final.pptxLATEST TOOLS FOR PROJECT PLANNING, MONITORING & IMPLEMENTATION final.pptx
LATEST TOOLS FOR PROJECT PLANNING, MONITORING & IMPLEMENTATION final.pptx
 
IT project management-IT project management-Unit-2.pptx
IT project management-IT project management-Unit-2.pptxIT project management-IT project management-Unit-2.pptx
IT project management-IT project management-Unit-2.pptx
 
Transition to Critical Chain Multi.pdf
Transition to Critical Chain Multi.pdfTransition to Critical Chain Multi.pdf
Transition to Critical Chain Multi.pdf
 
Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project Management
 
Project Management Notes 3
Project Management Notes 3Project Management Notes 3
Project Management Notes 3
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project Management
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects
 
ch09s.ppt
ch09s.pptch09s.ppt
ch09s.ppt
 
topic9.pdf
topic9.pdftopic9.pdf
topic9.pdf
 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4
 
Project management : Pert and Cpm
Project management : Pert and CpmProject management : Pert and Cpm
Project management : Pert and Cpm
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 
Stopping the insanity
Stopping the insanityStopping the insanity
Stopping the insanity
 

Plus de Grintex India Ltd (13)

About planet aerospace
About planet aerospaceAbout planet aerospace
About planet aerospace
 
Project management an overview
Project management an overview Project management an overview
Project management an overview
 
Overview-ISAC
Overview-ISACOverview-ISAC
Overview-ISAC
 
Gtg final
Gtg finalGtg final
Gtg final
 
Gtg final
Gtg finalGtg final
Gtg final
 
Profile in isro 1
Profile in isro 1Profile in isro 1
Profile in isro 1
 
Brain storming-rules
Brain storming-rulesBrain storming-rules
Brain storming-rules
 
Brain storming
Brain stormingBrain storming
Brain storming
 
Mentors
MentorsMentors
Mentors
 
Costing Primer
Costing PrimerCosting Primer
Costing Primer
 
Creativity
CreativityCreativity
Creativity
 
Rajnikanth and management
Rajnikanth and managementRajnikanth and management
Rajnikanth and management
 
My Career profile
My Career profileMy Career profile
My Career profile
 

Dernier

Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfVanessa Camilleri
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
Food processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture honsFood processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture honsManeerUddin
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...Postal Advocate Inc.
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfTechSoup
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Seán Kennedy
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxlancelewisportillo
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptxmary850239
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parentsnavabharathschool99
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYKayeClaireEstoconing
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 

Dernier (20)

Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdf
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
Food processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture honsFood processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture hons
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
 
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptxLEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parents
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 

Crtical chain m ethod ver 2

  • 1. CRITICAL CHAIN PROJECT MANAGEMENT – A NEW PROJECT MANAGEMENT PHILOSOPHY FOR MULTI PROJECT ENVIRONMENT Jagathipriya, Rajendrasingh.P.Byali, M.V.Kannan Projects Division, PPEG, ISRO Satellite Centre, Bangalore-560017, India Abstract Traditional project management has been concentrating mainly on single project optimization based upon task dependency constraints. The Critical Chain Project management (CCPM) provides a substantial improvement in the PM methodology by incorporating resource dependency and buffer management. CCPM improves the project scheduling by protecting it from common cause variation (uncertainty, multi-tasking). For a multi- project environment CCPM is best suitable since critical chain is calculated based upon both resource dependencies and task dependencies and the constraint of multi-tasking is also delt with. Buffer management enhances measurement and decision making for project control. This paper provides an insight to the CCPM concept with a practical example of scheduling multiple satellite projects using this technique. Keywords: Critical Chain, Project Management, Resource Constraint, Multi-tasking, Buffer Management TRADITIONAL PROJECT MANAGEMENT: The task commences after half the allotted time is Traditional Project Management concepts over and once the task commences, if a problem is have been in use since 1950’s. The development of encountered the buffer allotted becomes useless PERT/CPM provided the initial breakthrough in and the estimate will certainly overrun. Project planning/scheduling. But over a period of time certain limitations in this methodology has Task Estimation in PERT/CPM necessitated to relook at the philosophy behind PM In traditional PM techniques the safety / techniques. buffer is included in each and every task to take care of delays/uncertainties in completion of work. Limitations of PERT/CPM The contributing factors for this are: non- • Applicable only for Single Project scheduling. availability of resources in time, to overcome • Buffer built into each individual activity is overkill technological problems encountered, to incorporate and inefficient. last minute changes in design/configuration etc. • Strict adherence to task start date and end date For example - When a task estimate is made will lead to work expanding to fill the time considering the quantum of work it may require 5 available. days. But safety is added to incorporate unplanned • In a multi project environment collective load on work interruptions, uncertainty etc and the total each project resource is not assessed, as each task duration becomes 10 days. This estimate is in project is scheduled individually which ultimately turn used to calculate the Critical Path of the leads to multitasking. project. Most of the organizations work in a multi- Laws of Project Management: project environment. As in our case Project Generally the following two laws of Directors are responsible for successful completion project management influence the task duration of the project. Project Directors have a tendency to estimation and its completion. be demanding. They think that their project is of highest priority and they want to see frequent 1. Parkinson’s Law: progress in their project. This focus on showing Work expands to fit the allotted time. If a progress on as many active projects as possible is task is estimated to take 10 days, it usually the major cause for multi-tasking. doesn’t take less. This adjustment of effort to fill the allotted time can come in number of ways. CRITICAL CHAIN: Most of the time there is little or no reward for Introduced in 1997, by Eliyahu.M.Goldartt completing individual activities early. If individuals this methodology is based upon insight into human complete the activities early, they get to do more nature and what happens when a project work. Most of the people have a tendency to do management discipline is applied to people. [4] the work when the activity completion becomes Critical Chain is defined as the longest critical. This leads to underutilization of the chain of tasks that consider both task contingency time resulting in completion of most of dependencies and resource dependencies. This is the work in the later portion of the scheduled different from the definition of the Critical path, activity time. which is defined as the longest chain of tasks based upon task dependencies. Critical Chain 2. Student’s Syndrome: recognizes that a delay in resource availability can Given a project that is composed of tasks delay a schedule just as a delay in dependant with time buffer, it leads to Students Syndrome. tasks. 1
  • 2. Critical Chain Project Management derives from applying the Theory of Constraints (TOC) to 1. Task Estimation in CCPM Project Management. TOC says, “Any system must Critical Chain task estimating requires a have a constraint. Otherwise, its output would change in individual and organizational behavior to increase without bound, or go to zero.” TOC be effective. The removal of hidden safety in task identifies the constraint of a project as Critical durations requires establishment of an Chain or “The sequence of dependent events that organizational culture that removes fear of prevents the project from completing in a short exposing this safety and removing it from task interval. Resource dependencies determine the estimates. critical chain as much as do task dependencies.”[1] It is important to note that safety is not removed and thrown away. Instead it is pooled as Relay Race Approach: a project resource as opposed to a hidden task- Critical Chain utilizes the relay race level resource. This can be achieved by estimating approach to capitalize on the benefit of early based on following assumptions: finishes. In the relay race each runner runs his leg • When deriving an estimate it should be as fast as possible and hands on the baton off to assumed that all material and information the next runner who is ready to run as soon as the needed for the task is on hand. preceding runner is finished. Because the runner • It is assumed that uninterrupted focus on the capitalizes on an early finish of the preceding task is given. runner, a fast leg can offset a slow runner to the • It is also assumed that there won’t be any benefit of the team. Applying this to the critical surprises that cause additional work. chain project when one task is getting close to competition, you must have the next task’s 2. As Late As Possible Scheduling: resource on the track and be ready to start as- The tasks are scheduled as-late-as- soon-as-possible after the preceding task possible (ALAP) based upon the target end date. completes. 1. Using production analogy, the Work In This relay race approach means that the Progress (WIP) is minimized and not incurring team must de-emphasize the task scheduled start costs earlier than necessary. and finish dates and instead concentrate on 2. From project executive’s viewpoint, there is triggering their preparation and start on the better focus at the critical start of the project preceding task’s progress. Importantly, once a because there simply aren’t many tasks task is started, people should work as fast as scheduled to start. possible towards completion without clocking 3. Importantly in complex, knowledge work, your themselves to the scheduled finish date (As knowledge increases the further you go into against students’ syndrome). the project. By scheduling tasks ALAP, you are capitalizing on this increasing knowledge and The following table gives a general comparison will significantly minimize the need for re- between Critical Path method and Critical Chain work. method. 4. If a task is finished earlier than planned, the Critical Path Method Critical Chain Method project executive might be accused of Focus is on single Address multi-project sandbagging the estimates instead of being project scenario as well as rewarded for completing ahead of schedule. In single project case this environment, the project executive Focus is directed to Focus is on both worries about the future estimates being cut manage activities in resource and activity based upon history. Hence he always tries to critical path – the constraints officially finish on schedule. If the task is longest path in network finished early then the next problem is The single project Having a multi project encountered. The task that is dependent upon optimization leads to environment CC helps the completed task completion might not be local, rather than global in achieving global able to start early because the required optimization in multi- efficiency resources are off doing something else. project situations Slack available in Project buffer is treated 3. Buffer Management: project is not pooled as project resource and The major difference in Critical Chain is together and is not buffer management is the pooling of buffer and recognizing it as a project managed as a resource used as a tool for resource. These buffers automatically contract project evaluation. when they are pushed by overrunning tasks and Focus is on individual Project due date is absorb the overruns without affecting the target due dates of each tasks given importance and is end date. achieved by monitoring Three types of Buffer have been the project buffer identified. - Project Buffer SALIENT FEATURES OF CCPM - Feeding Buffer The three salient features of CCPM have been - Capacity Buffer given below. 2
  • 3. 3.1 Project Buffer: It protects the target end 3.3 Capacity Buffer: Capacity buffer comes into date against overruns in critical chain tasks. It is picture for multi-project scheduling where the placed at the end of the project after the last most critical / overloaded resource (known as Critical Chain task. In effect, the total safety Drum Resource) has to be protected / leveled to hidden in each individual Critical Chain task is overcome the slippage in schedule due to the non- reduced and placed in project buffer. availability of drum resource. Capacity Buffer will be inserted between the last use of the drum 3.2 Feeding Buffer: The Project Buffer protects resource of one project and the first use of the critical chain from overruns. However the critical drum resource in the next project. This acts as a chain is exposed to overruns from non-critical protection for the second project against changes chain tasks that link to the critical chain. Here the in first project that delay the availability of drum Feeding Buffer, placed at the point where the resource. feeding chain (non-critical activities) intersects with the critical chain, protects the critical chain from the overruns of the non-critical chain tasks. Fig1: Activity scheduling as in Critical Path Method Fig2: Activity scheduling following Critical Chain Method The above 2-activity network diagrams provide a the most demand or is so limited by capital costs simple example to understand the difference that it is the bottleneck around which schedules between the CPM & CCPM. The resource for each are drawn. There can be more than one drum activity has been given beside each activity bar resource. chart. In CPM the activities in red color indicates the Critical Path. It can be seen that the project Case Study: A practical example has been given takes 65 days to be completed. It can be noted in below taking into consideration two communication Fig 2 that each task duration has been reduced by satellites of I-2K bus, which are similar in 50%. Feeding Buffer has been introduced where configuration. the non-critical chain activities intersect the critical A typical communication satellite takes chain path. Project Buffer, which is 50% of the 18-24 months for realization (from the duration of the total Critical Chain activities, has conceptualization to launch) depending on the been introduced in the end of the project. It can be technical complexities involved. The time taken for observed that the Project duration has come down integration, from the delivery of structure to AIT by 10 days (15%). till Shipment of spacecraft for launch is around 11 to 12 months. Multi Project Critical Chain: From the past experience it is observed The term Drum Resource refers to the that when a single project team is given the key, critical resource around which project will be responsibility of realization of projects, which are synchronized. In production system the drum is similar in configuration, the work will be taken up the constraint of the system. This constraint sets serially. In other words, the activities related to the pace of the whole production system just as a one project are completed and then the next drum is used to set the marching pace of a troop. project activities are taken up. The time taken for In the project management area, the drum launching the repeat satellite is generally 12 – 14 resource is usually the resource that is always in months from the date of launch of the first 3
  • 4. satellite. Considering this an example of 2 Based on the analysis carried out the following communication satellites has been taken for observations are made: scheduling using the critical chain method. 1. The time taken for realization of the satellite In the example considered the activities in the current scenario is around 327 days from the delivery of structure to AIT has been from the date of delivery of the structure. considered. Only major milestone activities Using CCPM the duration for each activity has concerned with delivery of subsystems to AIT, been reduced by 50%. The duration for HILS integration and testing activities till shipment of test, Thermovac Test and Assembled mode the satellite for launch is considered. Fig-3 gives Integrated Spacecraft tests are not reduced the activities scheduled in the Critical exactly by 50% but only the setup time for the Fig 3: Project scheduling using conventional facility has been reduced. This is because the method. test duration for these are fixed which is also dependent on the number of test cycles / Path method. Fig-4 gives the Schedule for two cases it has to undergo. Satellite projects planned based on Critical Chain 2. The integration activity of the bus system method. packages commences as and when the The following assumptions are made for arriving at packages are delivered to AIT. the schedule: 3. Thermovaccum facility can be identified as the • Subsystem configuration of both the satellites Drum resource. This is because being a critical considered is assumed to be similar. facility it can lead to single point failure if • The duration time given in Fig-3 is based on advanced planning is not done. But since previous experience and is being used in the adequate gap is available in the second organization for scheduling all the spacecraft project for the commencement of the project activities. Thermovac test Capacity Buffer has not been • The Relay race approach is assumed: i.e the added. necessary resources to commence the activity 4. It can be observed that the duration for as soon as the preceding activity is completed completion of Satellite-1 has been reduced are available. from 327 days to 231 days i.e by 110 days (29.35%). Satellite-2 has taken 242 days. (26%reduction). 4
  • 5. Fig 4: Multiple Satellite Project scheduling delay in the completion of the project using CCPM activities. 5. The increase of 11 days in Satellite-2 7. When the subsystem realization and completion is because RCS integration activity integration activities for both the project are in the Satellite-2 commences only after the taken up in parallel it can be observed that completion of RCS integration activity of both the satellites can be delivered for launch Satellite-1. This is assuming that same team is at a gap of 25 days. working on the integration of RCS for both the projects. Drawbacks / Limitations of CCPM: 6. The buffer in each activity is made zero and There is no clear-cut answer on the ‘best’ the Project buffer is added at the end for each way to define the critical chain, and often refer to project (75 days – which is 50% of the total using the strategic considerations when individual activity buffer). The consumption of determining it. This is similar to the approach this buffer gives an indication of the extent of taken by Goldartt himself in the development of the TOC when he declared that a process 5
  • 6. bottleneck (or constraint) must be a strategic decision and not to be based on the accidental References situation of a plant at a given time. [1] Goldratt Eliyahu.M., “Critical Chain”, North The available literature of CCPM does not River, Great Barrington, MA, 1997. make a distinction between the technological [2] Goldratt Eliyahu.M., “The Goal”, North River uncertainty of an activity and the possible delay Press, Croton-on Hudson, New York, 1984. due to unavailability of the required resources at [3] Goldratt Eliyahu.M.,”Theory of Constraints”, the time the activity is due to start. the North river Press, Great Barrington, 1999. The assumption of multi tasking by [4] Larry.P.Leach, “Critical Chain Project resources in CCPM is critical to the roadrunner Management Improves Project Performance”, mentality of resources, that is, start an activity as Advanced Project Institute, 1997. soon as the predecessor activities are finished. [5] Thomas Lechler, Boaz Roven, However this assumption is generally valid only for Edward.A.Stohar, “Critical Chain: A New Project production line concept or for projects that are Management Paradigm or Old Wine in New Bottle?” repetitive in nature. Generally in an R & D Version6/7/05, CPMR, 2005. organization multi tasking is quite common and [6] Jaume Ribera, Marc Sachon, Alex Grasas, cannot be avoided. This may be due to large “Putting the Core Elements of Critical Chain Project period of idleness that would occur otherwise due Management into perspective: A general to dependency on external resources for framework for Buffer Management”, IESE Business materials/components, technological problems, School, Spain, 2003. delay in finalization of configurations due to multi- disciplinary interactions etc. The other critical factor on the roadrunner mentality is the sharing of information between activity owners, implemented in CCPM via the capacity buffers, notifying the delay in availability of the drum resource fro the next connected activity. To achieve this, high transparency is needed on how time is used in the project organization. In spite of the above limitations Critical Chain method is becoming popular in Aerospace industries and is already successfully implemented in the Software industry for execution of projects. Summary: This paper gives an overview of the CCPM and the implementation of this method for execution of spacecraft projects. Also a case study has been given where in the methodology of implementation has been discussed. The essential changes introduced by CCPM can be summarized as follows: 1. Focus on total systems throughput rather than individual projects. 2. Identify /manage constraint resource to avoid or solve resource conflicts. 3. Using buffer management as the primary tool for project management and control. 4. Avoid multitasking which leads to prioritizing project activities. To exploit the benefits of this method it is needed to establish a total project environment that integrates both the human behavioral elements and methods into an effective operating unit. The human side requires everyone, from management to the project team, to understand and buy-in to the concepts. Acknowledgements We acknowledge the valuable suggestions given by Mr.H. Bhojraj, GD PPEG. We also express our sincere gratitude to Dr.K.N.Shankara, Director ISAC for his constant encouragement. 6