Construction Update 10-6-2010
1. From: Brandon Valdez To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Office: Kansas City Lee Turner – OnGoal
Date: 10.6.2010 Andy Heitmann – Turner
Dave Dudzik - Turner
Re: Wizards Stadium Project
Update – Week of
10.4.2010
Current Activities this Week:
Foundations:
Area 4 Field Level – Foundations for “infill” area
between Column Lines 39-1 are ongoing.
Concrete Flatwork:
Area 3 Field Level – Concrete for slab-on-grade up to
Stair 1 will be placed this week. Field Level Area 3 – Concrete slab-on grade
prep is ongoing to column line 4.
Masonry:
Area 1 – Field level masonry installation is ongoing in
Area H, G, F, E and D. Area 2/3 – Concourse building
masonry installation is ongoing.
Steel Erection:
Area 4 – Steel erection for “infill” area is ongoing
(Sequence 3-3). Truss installation has started.
Area 2 – Steel joist and metal decking installation for
concourse buildings is ongoing. Canopy decking Field Level Area 3 – Masonry in Section D is
installation is ongoing. Canopy gutter enclosure framing ongoing.
installation is ongoing.
Roofing and Sheetmetal:
Area 1 – Permanent roofing installation at West
Building is ongoing. Area 2/3 – Canopy gutter installation
is ongoing.
Area 4 – Trusses 41 and 42 being set and
connected. 1 more truss remains (40 Line).
Building the Future
2. Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels are ongoing. Exterior metal stud framing
and sheathing installation is ongoing at Field, Suite, and
Press Levels.
Glass:
Area 1 - Curtainwall framing and glass installation is
ongoing at West Building on west, south and east
Field Level Area 4 – Structural steel and
elevations. South “wing” framing has started.
foundations are ongoing at Cauldron Club.
MEP Rough-in:
Area 3 – Underground MEP rough-in is ongoing.
West Building - Ductwork installation on
Concourse, Suite and Press Levels are ongoing.
Plumbing rough-in is ongoing on Suite and
Press Levels. Fire Protection rough-in is ongoing on
Concourse, Suite and Press Levels. Electrical rough-in is
ongoing on Concourse, Suite and Press Levels.
Projected Activities occurring next Week: Area 3 – Shot of the Canopy decking
installation that has started on the east side.
Foundations:
Area 3/4 Field Level – Foundations for “infill” area
Between Column Lines 39-1 will be complete.
Concrete Flatwork:
Area 3 Field Level – Concrete placement for Slab-on
Grade from lower dock area to Column Line 1.
Area 3 and 4 Field Level – Installation of on-grade seating
risers and intermediate stairs will continue.
Masonry: Area 1 – Curtainwall “wing” framing at south
Area 1 – Field level masonry installation will continue in end is being constructed.
Area H, G, F, E and D. Area 2/3 – Concourse building
masonry installation will continue.
Building the Future
3. Structural Steel Erection:
Area 4 – Structural steel erection for “infill” area will
be ongoing. Area 2 – Steel joist and metal decking
installation for concourse buildings will continue.
Canopy decking installation will continue. Canopy gutter
enclosure framing installation will continue.
Roofing and Sheetmetal:
Area 1 – Permanent roofing installation at West Field – Installation of the Storm Loop around
Building will continue. Area 3 – Canopy gutter installation playing field has started.
will continue.
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels will continue. Exterior Framing and
sheathing installation will continue.
Glass:
Area 1 – Curtain Framing and Glass installation around West
Building will continue. Curtainwall framing on Suite and
Press Level balconies will continue. Curtainwall framing
at Field Side of Main Concourse will continue.
MEP Rough-in:
Area 1 – Shot of the west building showing
MEP Rough-in at Concourse, Suite and Press Levels will
the progress of the exterior envelope.
continue. Ductwork installation on Concourse, Suite, and
Press Level will continue. Fire Sprinkler installation will
continue on Concourse, Suite and Press Levels.
Building the Future
4. Additional Photos:
Area 3– On-grade seating installation is Area 3 – Burnished CMU wall topped out at
ongoing at north elevation. Stair 1.
Concourse Level Area 3 – Canopy gutter and
Area 1 – Concrete in Stair 9 is placed. gutter enclosure framing is ongoing.
Area 2 – Shot of the Canopy decking and Area 4 – Shot of Column Line 42 truss be
gutter at the SE corner. raised into place.