Weekly Construction Update 07-07-2010
1. From: Brandon Valdez To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Office: Kansas City Lee Turner – OnGoal
Date: 7.7.2010 Andy Heitmann – Turner
Dave Dudzik - Turner
Re: Wizards Stadium Project
Update – Week of
7.5.2010
Current Activities this Week:
Mass Excavation:
Backfilling of on-grade seating is ongoing in Area 2
and Area 3.
Site Utilities:
Storm Sewer installation (Line 3000) is ongoing along Concourse Level Area 2 – Underground
Village West Parkway. plumbing and electrical rough-in for the
Concourse Buildings is ongoing.
Storm Line Installation (Line 6000 and Sanitary Sewer
Line E installation is ongoing on east side of France
Family Dive is ongoing.
Foundations:
Area 3 Field Level – Isolated footing installation is
ongoing and is currently to Column Line 3.5.
Concrete Flatwork:
Area 1 – Mezzanine slab-on deck is complete, Main
Concourse structural slab is complete, Suite Level slab Field Level Area 1 – Cast-in-place concrete
on deck is complete, Press Level slab on deck is riser installation has started.
complete. Field Level Area 1 slab-on-grade is complete
from column line 32-29.
Structural Steel Erection:
Area 1 – Detailing and decking in sequence 1-3 is ongoing.
Erection of Steel Sequence 2-1 is ongoing.
Field Level Area 1 – Concrete placement for
slab-on-grade between column lines 32-29.
Building the Future
2. Structural Steel Erection:
Area 1 – Detailing and decking in sequence 1-3 is ongoing.
Erection of Steel Sequence 2-1 is ongoing.
Underground MEP:
Electrical Secondary Distribution is ongoing in Area 3.
MEP Rough-in:
Area 1 – Shallow electrical and plumbing rough-in will Area 2 –Steel erection in Sequence 2-1 is in
continue. full swing.
Metal Stud Framing:
Area 1 Suite Level – Metal stud framing for Suites is
ongoing.
Projected Activities occurring next Week:
Mass Excavation:
Backfilling of on-grade seating areas will continue in Area
3.
Site Utilities: Area 1 – Shot of the West Building from the
Installation of the Storm Line 6000 on the East Side (France south concourse area.
Family Drive) of the site will continue.
Deep Underground MEP:
Deep Sanitary and Electrical Distribution installation
in Area 3 will continue.
Foundations:
Area 3 Field Level – Foundation installation will continue.
Area 4 Mezzanine Level – Foundation Wall installation will
continue.
Suite Level Area 1 – Metal stud framing for
Suites are ongoing.
Building the Future
3. Concrete Flatwork:
Area 1 Field Level – Prep for concrete placement for
slab-on-grade will continue.
Area 1 Field Level – Installation of on-grade seating risers
will continue.
Structural Steel Erection: Area 1 – Shot from Roof Level showing
Erection of Structural Steel in Sequence 2-1 will precast concrete and curvature of steel
continue. Decking and detailing in Sequence 2-1 will begin. structure.
Erection of the Canopy Trusses will begin.
Underground MEP:
Electrical Secondary will continue in Area 3.
MEP Rough-in:
Plumbing and Electrical rough-in for Area 1 Field Level slab
on grade will continue.
Metal Stud Framing:
Area 1 Suite Level – Metal stud framing for Suites will
continue. Field Level Area 3 – Foundation installation
is ongoing.
Area 1 Press Level – Metal stud framing for Suites will
begin.
Building the Future
4. Additional Photos:
Field Level Area 3 – Cauldron Club field wall Area 1 – Shot of the West Building from the
reinforcing in place. northeast.
Suite Level Area 1 – Precast tub being picked
Suite Level Area 1 – Metal Stud Framing
by crane on its way to be installed.
installation is ongoing.
Suite Level Area 1 – Ironworkers setting and Mezzanine Level Area 4 – Shot of north
fastening precast seating tubs. foundation wall installation.
Building the Future