SlideShare une entreprise Scribd logo
1  sur  37
Information Session
Great Lakes Council
             4 May 2011
              Lew Short
      Group Manager Community
              Resilience
Development Rural Fire ServicePlanning
       NSW Assessment &
Outline
•   Overview
•   Legislation Changes
•   Complying Development
     • Process
     • Development Standards
     • Recognised Consultants
     • Certificates
     • Best Practice Guidelines and Supporting Documents
•   79BA
     • Recognised Consultants
•   Queries
The next steps for local
           government
• What are the specific needs of Council and
  Council staff
• How can the RFS assist?
• Mentoring by RFS
• Site assessment
Specific Issues
•   Inconsistency with the requirements for ember protection between 100B and 79BA assessments. Example is DA-474/2010 for a boundary adjustment.
    Bush Fire Safety Authority issued subject to condition requiring dwelling to be upgraded for ember protection. Dwelling is not located within part of land
    mapped as bush fire prone. Based on slope, distance to vegetation and type of vegetation the dwelling would not require any specific construction
    requirements (BAL 12.5) under AS 3959.
•   2. Ensuring appropriate conditions are applied to Bush Fire Safety Authority. Example is DA-116/2011. A condition was imposed requiring “Public road
    access shall comply with section 4.1.3 (1) of Planning for Bush Fire Protection 2006. Clarification was sought in relation to the required outer radius of a
    cul-de-sac and advice received that 12m required. Plans were clearly non-compliant (8.5m outer radius). Applicant is unable to comply with this condition
    without substantial change to the form of the subdivision, therefore placing this requirement as a condition could invalidate the any consent and should
    have been raised as an issue rather than placed as a condition.
•   3. Requiring APZ’s on newly created lots and associated roadways which are outside the extent of bush fire prone land (i.e. more than 100m to the
    nearest bushfire hazard) to comply with PBP 2006. Only the residue lot contains bush fire prone land. Example is DA-69/2010
•   I refer to DA 260/2010. A rural dwelling beyond the Council maintained section ( a distance of 5.15Klms) of Black Camp Road, Stroud. The maintained
    section of Black Camp Road varies in width between 2.5 and 5m and also consists of a number of old timber bridges and culverts. To access the
    property, a further distance of 500m was required to be travelled over a non maintained section of Black Camp Road also consisting of a poorly
    constructed pipe crossing. The issues were as follows:-
•   RFS required that only the internal access meet the requirements of 4.1.3 (2)
•   The maintained section of Black Camp Road itself clearly did not meet RFS requirements in terms of height clearances, road width and dubious structural
    adequacy of the existing bridges and culverts.
•   The 500m of unmaintained road was in poor condition as was the pipe crossing within this section.
•   In my mind this raises the following questions:
    1. Does Council have any obligation to ensure that its' maintained or unmaintained rural road network complies with basic RFS requirements such as
    width, height and load capacity? If so, given current and projected budget restraints, would achieving compliance with these requirements be unrealistic or
    even unachievable task?
•   2. Why does the RFS condition for compliance with internal access requirements yet overlooks the condition of the public road itself?
•   3. In terms of liability would Council or the RFS be accountable in any way should it be proven that a fatality occurred due to RFS emergency services not
    being able to negate the public road leading into the property?
•   What is the standard of construction required for secondary access roads on rural properties?
•   I am off work on Mon and at a DAP meeting on Tues so really can’t afford to be there on Weds – so sorry. I have a few issues with the RFS system but
    most are to do with the unnecessary need to send DA’s to them with associated costs and time. Example 1 - house just approved for construction, we
    then submit a DA for subn and we are required to supply RFS report and costs covering that same site?????? .
•   Example 2 – subn approved for 3 lots – clients then request the subn be varied to 2 lots (same location for house sites as previously approved 3 months
    prior) we are required to resubmit the DA to RFS???? Why?
•   I have never liked how in the case of a minor boundary adjustment – RFS place conditions on the long standing existing dwellings (covering in openings,
    covering windows, extra water tanks etc). In some cases it has meant the bdy adjustment is no longer viable so does not proceed. So houses remain the
    same and the boundary stays in an inappropriate location. RFS in later years are becoming better on this issue but still room for improvement
•   I can supply DA refs if needed
    The four above are from a surveyor.
    My specific issues relate to road access widths and turning circle requirements.
•   Robyn Shelley
Legislative Changes
•  The Environmental Planning & Assessment Amendment
  Act 2008 (the Amendment Act)
• s79BA EP&A Act 1979

• Codes SEPP 2008
       – Exempt Provisions (unchanged)
       – Complying Provisions
• Amendment to s733 of the Local Government Act 1919
• Protection of life and property is maintained through
  rigorous assessment processes by suitably qualified
  consultant or Council staff
Background - Complying
           Development
• Exempt & Complying Codes SEPP has been in effect from
  2008.
• Bush Fire was a land based exclusion which only allowed
  minor exempt development such as class 10, fences etc
• Long period of negotiation with Dept of Planning and FPAA
• Maintains NSW strong position for new development in
  Bush Fire Prone Areas.
Background - Complying
           Development
• Exempt & Complying Codes SEPP has been in effect from
  2008.
• Bush Fire was a land based exclusion which only allowed
  minor exempt development such as class 10, fences etc
• Long period of negotiation with Dept of Planning and FPAA
• Maintains NSW strong position for new development in
  Bush Fire Prone Areas.
The changes to complying development
• Bush fire prone land is no longer excluded from the Codes
  SEPP
• New assessment process applies to the General Housing
  Code and the Rural Housing Code
• Part 3 of Codes SEPP
   – Development Standards eg. setbacks, building height & bush fire
     prone land standards
• Cannot be carried out on BFP Land for State
  Significant Development, Integrated
  Development or Other development
• Can be applied to infill situations for alterations,
  additions and new houses that meet the code
  criteria (Development Standards)
• Development Standards are based on the
  zoning of the land
   – Rural zonings covered by Rural Housing Code RU1 – RU 6
   – Residential or the General Housing R1 – R5
Part 3 General Housing Code
cl. 3.36B Development standards for bush fire prone land
(1) This clause applies:
    (a) to all development specified for this code that is to be carried out on a lot that is wholly or
           partly bush fire prone land (other than development that is the erection of non-habitable
           ancillary development that is more than 10m from any dwelling house, landscaping, a
           non-combustible fence or a swimming pool), and
    (b) in addition to all other development standards specified for this code.
(2) The development may be carried out on the lot only if:
    (a) the development conforms to the specifications and requirements of the following that are
             relevant to the development:
    (i) Planning for Bush Fire Protection (ISBN 0 9751033 2 6) published by the NSW Rural Fire
             Service in December 2006,
    (ii) Addendum: Appendix 3 (ISBN 0 9751033 2 6, published by NSW Rural Fire Service in 2010)
             to Planning for Bush Fire Protection (ISBN 0 9751033 2 6),
    (iii) if another document is prescribed by the regulations for the purposes of section 79BA of
             the Environmental Planning and Assessment Act 1979—that document, and
Part 3 General Housing Code
cl. 3.36B Development standards for bush fire prone land
(b) the part of the lot on which the development is to be carried out is not in bush fire
        attack level-40 (BAL-40) or the flame zone (BAL-FZ), and
(c) the lot has direct access to a public road or a road vested in or maintained by the
        council, and
(d) a reticulated water supply is connected to the lot, and
(e) a fire hydrant is located less than 60 metres from the location on the lot of the
        proposed development, and
(f) mains electricity is connected to the lot, and
(g) reticulated or bottled gas on the lot is installed and maintained in accordance with
        AS/NZS 1596:2008, The storage and handling of LP Gas and the requirements of
        relevant authorities (metal piping must be used), and
(h) any gas cylinders on the lot that are within 10m of a dwelling house: (i) have the
        release valves directed away from the dwelling house, and (ii) are enclosed on
        the hazard side of the installation, and (iii) have metal connections to and from
        the cylinders, and (i) there are no polymer sheathed flexible gas supply lines to
        gas meters adjacent to the dwelling.
• 3) A standard specified in subclause (2) (b) is satisfied if one of
  the following certifies that the development is not in bush fire
  attack level-40 (BAL-40) or the flame zone (BAL-FZ):
• (a) until 25 February 2012—the NSW Rural Fire Service, or
• (b) a person who is recognised by the NSW Rural Fire Service as
  a suitably qualified consultant in bush fire risk assessment, or
• (c) the council.
Note. More information about the categories of bush fire attack,
  including the flame zone, can be found in Table A3.4.2 of
  Addendum: Appendix 3 (ISBN 0 9751033 2 6 and published by
  NSW Rural Fire Service in 2010) to the publication titled Planning
  for Bush Fire Protection (ISBN 0 9751033 2 6) published by NSW
  Rural Fire Service in 2006.
Bush fire prone land - CDC
 AS3959 (2009)

BAL Level                           Description

BAL LOW                             Insufficient risk                Council
                                                                     assessment or
BAL 12.5                            Ember attack                     BPAD Certification
BAL 19                              Increased ember attack and
                                    debris

BAL 29                              Ember attack and radiant heat


BAL 40                              Radiant heat, embers and flame     DA Required
                                    exposure

BAL FZ                              Direct exposure to flames and fire DA Required
                                    front



            BAL 40 & FZ - The distance from a bush fire at which there is significant

            potential for sustained flame contact to a building.
RFS Submission Requirements
• Kit for applicants to determine their BAL when applying for
  a BAL Risk Assessment Certificate.

      • Identification of lot particulars

      • Statement of proposed development

      • A site plan with (reference number and dated) drawn to scale
        that indicates building footprint

      • BAL Risk Assessment fee (may be applicable).
BAL Risk Certificate < BAL 40
BAL Risk Certificate BAL 40 +
Suitably Qualified Consultants
• It is a requirement that a person who has suitable
  qualifications and experience undertakes the
  assessment. This could be either the local council or a
  person identified as being a ‘suitably qualified
  consultant’.
http://www.rfs.nsw.gov.au/dsp_content.cfm?CAT_ID=904
Suitably Qualified Consultants
Recognised by NSW Rural Fire Service

   – Fire Protection Association Australia
      • BPAD-A and BPAD-D

      • Or other equivalent BPAD qualification/scheme
Certificate particulars
• Duration of Certificate - 12 months
• Must identify BAL level in the certificate – Site assessment is
  critical
• Amendments – There are no provisions to do amendments to
  the certificate.
• Conditioning – Conditioning cannot be applied. The proposal
  meets the DTS or it does not.
• Based on the hazard at the time of inspection
• No approval for vegetation clearing or establishing APZ’s.
• Multiples assessments for certificates can be undertaken.
  However, only a final certificate can be provided with the
  CDC.
Residential
                DEVELOPMENT STANDARDS

          Construction requirements


          Bushfire Attack Level Low-29


          Public road access


          Reticulated water supply


          A fire hydrant less than 60 metres


          Mains electricity


          Reticulated or bottled gas installation


          Gas cylinder location

          Gas supply lines
Best Practice Guidelines
• New works to comply with Development Standards
  ie. AS3959 2009 ‘Construction of Buildings in
  Bushfire Prone Areas’

• Most homes in NSW pre-date bush fire legislation.

• Unable to achieve increased bush fire protection.

• NSW RFS has produced the Best Practice
  Guidelines to assist existing houses to upgrade.
Is Upgrading Mandatory?
• No, however compliance with the Best Practice
  Guide is strongly recommended as a minimum

• In addition to any other bush fire protection
  measures
   –   Site management
   –   Landscaping
   –   Construction standards
   –   Services
Auditing
• Following issue of CDC, required to be forwarded to
  RFS

• The RFS will carry out an auditing process to ensure
  accuracy of BAL Risk Assessment Certificates

• Will also be used by RFS for operational purposes

• Breaches will be forwarded to the accredited body
s.79BA
Hansard

• S79BA originally intended councils undertake the majority
  of bushfire risk assessment

   – “This will be a general referral requirement although
     councils, as consent authorities, should be able to
     determine whether developments meet the guidelines
     specifications” (Parliament Hansard May 2002)
79BA
(1) Development consent cannot be granted for the carrying out of
   development for any purpose (other than a subdivision of land that
   could lawfully be used for residential or rural residential purposes
   or development for a special fire protection purpose) on bush fire
   prone land unless the consent authority:

  (a) is satisfied that the development conforms to the specifications
  and requirements of the document entitled Planning for Bush Fire
  Protection, ISBN 0 9751033 2 6, prepared by the NSW Rural Fire
  Service in co-operation with the Department of Planning (or, if
  another document is prescribed by the regulations for the purposes
  of this paragraph, that document) that are relevant to the
  development (the relevant specifications and requirements), or
79BA
(b) has been provided with a certificate by a person who is
   recognised by the NSW Rural Fire Service as a qualified
   consultant in bush fire risk assessment stating that the
   development conforms to the relevant specifications and
   requirements
• “relevant specifications” DTS provisions of Planning for
   Bush Fire Protection
• “requirements” documentation provided to Council in
   support of the certificate. Documentation includes that
   detailed in Appendix 4 of PBP.
• “Certificate” means to provide documented evidence to
   Council as the consent authority as to your
   recommendations to be incorporated into the conditions of
   consent. This should include the DTS requirements of
   PBP and the appropriate level of construction in
   accordance with AS3959.
79BA
• (1A) If the consent authority is satisfied that
  the development does not conform to the
  relevant specifications and requirements, the
  consent authority may, despite subsection (1),
  grant consent to the carrying out of the
  development but only if it has consulted with
  the Commissioner of the NSW Rural Fire
  Service concerning measures to be taken with
  respect to the development to protect
  persons, property and the environment from
  danger that may arise from a bush fire.
79BA
• is satisfied that the development does not conform =
  demonstration that there is some form of non-compliance.
• DoP and the RFS will be pushing for this to be done and after the 12
  months transition will be working with councils (training/ mentoring) to
  ensure they are comfortable in the assessment of applications.
• It is envisaged that DAs referred to the RFS will not be accepted
  unless they can demonstrate the non-compliance with PBP.
• Assessment sheets/checklists will be developed to assist councils.

• IMPORTANT – The changes are designed to allow the RFS to focus
  resources on higher risk developments.
In Summary
•   Council shall assess compliance with ‘Planning for Bush Fire
    Protection 2006’ (PBP) for all developments under section 79BA

•   Onus on councils to undertake assessments

•   Referral to RFS only where proposal does not comply with PBP

•   Reduce assessment timeframes and allow RFS to focus upon high
    risk developments

•   Enable recognised consultants to certify developments compliance
Further Information
• NSW Department of Planning website
   – Fact Sheet November 2010
   – Fact Sheet 3 – General Housing Code
   – Fact Sheet 10 Complying Development on Bushfire Prone Land


• RFS Website
   – Fast Fact 5/10 Recognised/Qualified Consultants
   – Practice Note 1/10 Requirements for Recognised/Qualified
     Consultants
   – BAL Risk Self Assessment Tool
   – BAL Risk Assessment User Guide
   – BAL Risk Assessment Application Kit
   – Best Practice Guideline
Questions
Lew Short
Group Manager Community Resilience
NSW Rural Fire Service
8741 5454
Lew.short@rfs.nsw.gov.au

Lew Short
lewshort14

Contenu connexe

En vedette

CoreValues-SourGrapes
CoreValues-SourGrapesCoreValues-SourGrapes
CoreValues-SourGrapesLee Primeau
 
Lew Short emergency response & recovery conference
Lew Short emergency response & recovery conferenceLew Short emergency response & recovery conference
Lew Short emergency response & recovery conferenceBlackash Bushfire Consulting
 
Enhancing Community Resilience through Appropriate Planning & Building
Enhancing Community Resilience through Appropriate Planning & BuildingEnhancing Community Resilience through Appropriate Planning & Building
Enhancing Community Resilience through Appropriate Planning & BuildingBlackash Bushfire Consulting
 
Enhancing Community Resilience through Appropriate Planning and Building Mech...
Enhancing Community Resilience through Appropriate Planning and Building Mech...Enhancing Community Resilience through Appropriate Planning and Building Mech...
Enhancing Community Resilience through Appropriate Planning and Building Mech...Blackash Bushfire Consulting
 
How to break free
How to break freeHow to break free
How to break freemumukshutva
 
Community Resilience Framework for Victoria - Stage 1 work
Community Resilience Framework for Victoria - Stage 1 workCommunity Resilience Framework for Victoria - Stage 1 work
Community Resilience Framework for Victoria - Stage 1 workBlackash Bushfire Consulting
 
Infeccion por citomegalovirus en pacientes con transplante renal
Infeccion por citomegalovirus en pacientes con transplante renalInfeccion por citomegalovirus en pacientes con transplante renal
Infeccion por citomegalovirus en pacientes con transplante renalMarcela Catalina Fandiño Vargas
 

En vedette (11)

Emergency Services Strategic Command
Emergency Services Strategic CommandEmergency Services Strategic Command
Emergency Services Strategic Command
 
CoreValues-SourGrapes
CoreValues-SourGrapesCoreValues-SourGrapes
CoreValues-SourGrapes
 
Lew Short emergency response & recovery conference
Lew Short emergency response & recovery conferenceLew Short emergency response & recovery conference
Lew Short emergency response & recovery conference
 
Enhancing Community Resilience through Appropriate Planning & Building
Enhancing Community Resilience through Appropriate Planning & BuildingEnhancing Community Resilience through Appropriate Planning & Building
Enhancing Community Resilience through Appropriate Planning & Building
 
Enhancing Community Resilience through Appropriate Planning and Building Mech...
Enhancing Community Resilience through Appropriate Planning and Building Mech...Enhancing Community Resilience through Appropriate Planning and Building Mech...
Enhancing Community Resilience through Appropriate Planning and Building Mech...
 
Dealing with Growing Number of Extreme Fire Days
Dealing with Growing Number of Extreme Fire DaysDealing with Growing Number of Extreme Fire Days
Dealing with Growing Number of Extreme Fire Days
 
How to break free
How to break freeHow to break free
How to break free
 
Bushfires, Uncertainty & Instability
Bushfires, Uncertainty & InstabilityBushfires, Uncertainty & Instability
Bushfires, Uncertainty & Instability
 
Community Resilience Framework for Victoria - Stage 1 work
Community Resilience Framework for Victoria - Stage 1 workCommunity Resilience Framework for Victoria - Stage 1 work
Community Resilience Framework for Victoria - Stage 1 work
 
Metabolismo del acido folico y la vitamina b12
Metabolismo del acido folico y la vitamina b12Metabolismo del acido folico y la vitamina b12
Metabolismo del acido folico y la vitamina b12
 
Infeccion por citomegalovirus en pacientes con transplante renal
Infeccion por citomegalovirus en pacientes con transplante renalInfeccion por citomegalovirus en pacientes con transplante renal
Infeccion por citomegalovirus en pacientes con transplante renal
 

Similaire à Great lakes info session april 2011

Planning Staff Report Elizabeth Ann Seton 2010 Oct 14
Planning Staff Report Elizabeth Ann Seton 2010 Oct 14Planning Staff Report Elizabeth Ann Seton 2010 Oct 14
Planning Staff Report Elizabeth Ann Seton 2010 Oct 14Adam Cohen
 
Boston Engineering and Design Poster
Boston Engineering and Design PosterBoston Engineering and Design Poster
Boston Engineering and Design PosterThomas Bryce
 
AH Council Meeting 11/9/15 - Item #7 - MF-D Amendments
AH Council Meeting 11/9/15 - Item #7 - MF-D AmendmentsAH Council Meeting 11/9/15 - Item #7 - MF-D Amendments
AH Council Meeting 11/9/15 - Item #7 - MF-D AmendmentsMarian Vargas Mendoza
 
Economic and Socialized Housing BP 220 (02)
Economic and Socialized Housing BP 220 (02)Economic and Socialized Housing BP 220 (02)
Economic and Socialized Housing BP 220 (02)SQSY
 
Manufactured Housing Ordinance
Manufactured Housing OrdinanceManufactured Housing Ordinance
Manufactured Housing Ordinancegscplanning
 
Understanding the Impact of Growth Plan Reforms
Understanding the Impact of Growth Plan ReformsUnderstanding the Impact of Growth Plan Reforms
Understanding the Impact of Growth Plan ReformsAnne Kaufmann
 
Public sector planning club, January 2017
Public sector planning club, January 2017Public sector planning club, January 2017
Public sector planning club, January 2017Browne Jacobson LLP
 
Housing Standards Review: DCLG Presentation
Housing Standards Review: DCLG PresentationHousing Standards Review: DCLG Presentation
Housing Standards Review: DCLG PresentationPAS_Team
 
Planning and Environmental Law Update
Planning and Environmental Law UpdatePlanning and Environmental Law Update
Planning and Environmental Law Update39 Essex Chambers
 
Conflicts and sufficient grounds presentation
Conflicts and sufficient grounds presentationConflicts and sufficient grounds presentation
Conflicts and sufficient grounds presentationMartine Cousins
 
Public sector planning club, October 2016, Nottingham
Public sector planning club, October 2016, NottinghamPublic sector planning club, October 2016, Nottingham
Public sector planning club, October 2016, NottinghamBrowne Jacobson LLP
 
Beyond the Code for Sustainable Homes + Upholding Quality and Sustainability
Beyond the Code for Sustainable Homes + Upholding Quality and SustainabilityBeyond the Code for Sustainable Homes + Upholding Quality and Sustainability
Beyond the Code for Sustainable Homes + Upholding Quality and SustainabilityPRP
 
Helping practitioners understand changes to Exempt and Complying Development
Helping practitioners understand changes to Exempt and Complying DevelopmentHelping practitioners understand changes to Exempt and Complying Development
Helping practitioners understand changes to Exempt and Complying DevelopmentPlanning & Infrastructure
 
2017Method statements and demolition techniques..pdf
2017Method statements and demolition techniques..pdf2017Method statements and demolition techniques..pdf
2017Method statements and demolition techniques..pdfssuserce0bdc
 
Getting to grips with the new technical standards for housing
Getting to grips with the new technical standards for housingGetting to grips with the new technical standards for housing
Getting to grips with the new technical standards for housingPAS_Team
 

Similaire à Great lakes info session april 2011 (20)

Planning Staff Report Elizabeth Ann Seton 2010 Oct 14
Planning Staff Report Elizabeth Ann Seton 2010 Oct 14Planning Staff Report Elizabeth Ann Seton 2010 Oct 14
Planning Staff Report Elizabeth Ann Seton 2010 Oct 14
 
Boston Engineering and Design Poster
Boston Engineering and Design PosterBoston Engineering and Design Poster
Boston Engineering and Design Poster
 
AH Council Meeting 11/9/15 - Item #7 - MF-D Amendments
AH Council Meeting 11/9/15 - Item #7 - MF-D AmendmentsAH Council Meeting 11/9/15 - Item #7 - MF-D Amendments
AH Council Meeting 11/9/15 - Item #7 - MF-D Amendments
 
Economic and Socialized Housing BP 220 (02)
Economic and Socialized Housing BP 220 (02)Economic and Socialized Housing BP 220 (02)
Economic and Socialized Housing BP 220 (02)
 
Manufactured Housing Ordinance
Manufactured Housing OrdinanceManufactured Housing Ordinance
Manufactured Housing Ordinance
 
Understanding the Impact of Growth Plan Reforms
Understanding the Impact of Growth Plan ReformsUnderstanding the Impact of Growth Plan Reforms
Understanding the Impact of Growth Plan Reforms
 
Public sector planning club, January 2017
Public sector planning club, January 2017Public sector planning club, January 2017
Public sector planning club, January 2017
 
City Council March 5, 2013 Planning
City Council March 5, 2013 PlanningCity Council March 5, 2013 Planning
City Council March 5, 2013 Planning
 
Housing Standards Review: DCLG Presentation
Housing Standards Review: DCLG PresentationHousing Standards Review: DCLG Presentation
Housing Standards Review: DCLG Presentation
 
Planning and Environmental Law Update
Planning and Environmental Law UpdatePlanning and Environmental Law Update
Planning and Environmental Law Update
 
Conflicts and sufficient grounds presentation
Conflicts and sufficient grounds presentationConflicts and sufficient grounds presentation
Conflicts and sufficient grounds presentation
 
Public sector planning club, October 2016, Nottingham
Public sector planning club, October 2016, NottinghamPublic sector planning club, October 2016, Nottingham
Public sector planning club, October 2016, Nottingham
 
Winchester final slides
Winchester final slidesWinchester final slides
Winchester final slides
 
Decision Notice
Decision NoticeDecision Notice
Decision Notice
 
Brownfields Remediation
Brownfields RemediationBrownfields Remediation
Brownfields Remediation
 
Beyond the Code for Sustainable Homes + Upholding Quality and Sustainability
Beyond the Code for Sustainable Homes + Upholding Quality and SustainabilityBeyond the Code for Sustainable Homes + Upholding Quality and Sustainability
Beyond the Code for Sustainable Homes + Upholding Quality and Sustainability
 
Helping practitioners understand changes to Exempt and Complying Development
Helping practitioners understand changes to Exempt and Complying DevelopmentHelping practitioners understand changes to Exempt and Complying Development
Helping practitioners understand changes to Exempt and Complying Development
 
2017Method statements and demolition techniques..pdf
2017Method statements and demolition techniques..pdf2017Method statements and demolition techniques..pdf
2017Method statements and demolition techniques..pdf
 
Getting to grips with the new technical standards for housing
Getting to grips with the new technical standards for housingGetting to grips with the new technical standards for housing
Getting to grips with the new technical standards for housing
 
Appendix and Introduction
Appendix and IntroductionAppendix and Introduction
Appendix and Introduction
 

Plus de Blackash Bushfire Consulting

Plus de Blackash Bushfire Consulting (11)

Why are Critical Infrastructure Failures such an Issue?
Why are Critical Infrastructure Failures such an Issue?Why are Critical Infrastructure Failures such an Issue?
Why are Critical Infrastructure Failures such an Issue?
 
As risks unfold in cascading events
As risks unfold in cascading eventsAs risks unfold in cascading events
As risks unfold in cascading events
 
PIA Challenges to melbourns resilience
PIA Challenges to melbourns resiliencePIA Challenges to melbourns resilience
PIA Challenges to melbourns resilience
 
Presentation to CFA & SES Volunteer Forum on the Community Resilience Framewo...
Presentation to CFA & SES Volunteer Forum on the Community Resilience Framewo...Presentation to CFA & SES Volunteer Forum on the Community Resilience Framewo...
Presentation to CFA & SES Volunteer Forum on the Community Resilience Framewo...
 
Bushfire Persistence & Why Resilience Matters
Bushfire Persistence & Why Resilience MattersBushfire Persistence & Why Resilience Matters
Bushfire Persistence & Why Resilience Matters
 
Challenges of Resilience in Emergency Management
Challenges of Resilience in Emergency ManagementChallenges of Resilience in Emergency Management
Challenges of Resilience in Emergency Management
 
Creativity
CreativityCreativity
Creativity
 
Introduction to direction for Resilience
Introduction to direction for ResilienceIntroduction to direction for Resilience
Introduction to direction for Resilience
 
Conference risk frontiers nov 2012 lew short
Conference risk frontiers nov 2012 lew shortConference risk frontiers nov 2012 lew short
Conference risk frontiers nov 2012 lew short
 
Lew Short National Forum On Arson Prevention Futures
Lew Short National Forum On Arson Prevention FuturesLew Short National Forum On Arson Prevention Futures
Lew Short National Forum On Arson Prevention Futures
 
Final Geo Rabble 16th June Mega Fires What Happens
Final Geo Rabble 16th June Mega Fires   What HappensFinal Geo Rabble 16th June Mega Fires   What Happens
Final Geo Rabble 16th June Mega Fires What Happens
 

Great lakes info session april 2011

  • 1. Information Session Great Lakes Council 4 May 2011 Lew Short Group Manager Community Resilience Development Rural Fire ServicePlanning NSW Assessment &
  • 2. Outline • Overview • Legislation Changes • Complying Development • Process • Development Standards • Recognised Consultants • Certificates • Best Practice Guidelines and Supporting Documents • 79BA • Recognised Consultants • Queries
  • 3. The next steps for local government • What are the specific needs of Council and Council staff • How can the RFS assist? • Mentoring by RFS • Site assessment
  • 4. Specific Issues • Inconsistency with the requirements for ember protection between 100B and 79BA assessments. Example is DA-474/2010 for a boundary adjustment. Bush Fire Safety Authority issued subject to condition requiring dwelling to be upgraded for ember protection. Dwelling is not located within part of land mapped as bush fire prone. Based on slope, distance to vegetation and type of vegetation the dwelling would not require any specific construction requirements (BAL 12.5) under AS 3959. • 2. Ensuring appropriate conditions are applied to Bush Fire Safety Authority. Example is DA-116/2011. A condition was imposed requiring “Public road access shall comply with section 4.1.3 (1) of Planning for Bush Fire Protection 2006. Clarification was sought in relation to the required outer radius of a cul-de-sac and advice received that 12m required. Plans were clearly non-compliant (8.5m outer radius). Applicant is unable to comply with this condition without substantial change to the form of the subdivision, therefore placing this requirement as a condition could invalidate the any consent and should have been raised as an issue rather than placed as a condition. • 3. Requiring APZ’s on newly created lots and associated roadways which are outside the extent of bush fire prone land (i.e. more than 100m to the nearest bushfire hazard) to comply with PBP 2006. Only the residue lot contains bush fire prone land. Example is DA-69/2010 • I refer to DA 260/2010. A rural dwelling beyond the Council maintained section ( a distance of 5.15Klms) of Black Camp Road, Stroud. The maintained section of Black Camp Road varies in width between 2.5 and 5m and also consists of a number of old timber bridges and culverts. To access the property, a further distance of 500m was required to be travelled over a non maintained section of Black Camp Road also consisting of a poorly constructed pipe crossing. The issues were as follows:- • RFS required that only the internal access meet the requirements of 4.1.3 (2) • The maintained section of Black Camp Road itself clearly did not meet RFS requirements in terms of height clearances, road width and dubious structural adequacy of the existing bridges and culverts. • The 500m of unmaintained road was in poor condition as was the pipe crossing within this section. • In my mind this raises the following questions: 1. Does Council have any obligation to ensure that its' maintained or unmaintained rural road network complies with basic RFS requirements such as width, height and load capacity? If so, given current and projected budget restraints, would achieving compliance with these requirements be unrealistic or even unachievable task? • 2. Why does the RFS condition for compliance with internal access requirements yet overlooks the condition of the public road itself? • 3. In terms of liability would Council or the RFS be accountable in any way should it be proven that a fatality occurred due to RFS emergency services not being able to negate the public road leading into the property? • What is the standard of construction required for secondary access roads on rural properties? • I am off work on Mon and at a DAP meeting on Tues so really can’t afford to be there on Weds – so sorry. I have a few issues with the RFS system but most are to do with the unnecessary need to send DA’s to them with associated costs and time. Example 1 - house just approved for construction, we then submit a DA for subn and we are required to supply RFS report and costs covering that same site?????? . • Example 2 – subn approved for 3 lots – clients then request the subn be varied to 2 lots (same location for house sites as previously approved 3 months prior) we are required to resubmit the DA to RFS???? Why? • I have never liked how in the case of a minor boundary adjustment – RFS place conditions on the long standing existing dwellings (covering in openings, covering windows, extra water tanks etc). In some cases it has meant the bdy adjustment is no longer viable so does not proceed. So houses remain the same and the boundary stays in an inappropriate location. RFS in later years are becoming better on this issue but still room for improvement • I can supply DA refs if needed The four above are from a surveyor. My specific issues relate to road access widths and turning circle requirements. • Robyn Shelley
  • 5. Legislative Changes • The Environmental Planning & Assessment Amendment Act 2008 (the Amendment Act) • s79BA EP&A Act 1979 • Codes SEPP 2008 – Exempt Provisions (unchanged) – Complying Provisions • Amendment to s733 of the Local Government Act 1919 • Protection of life and property is maintained through rigorous assessment processes by suitably qualified consultant or Council staff
  • 6. Background - Complying Development • Exempt & Complying Codes SEPP has been in effect from 2008. • Bush Fire was a land based exclusion which only allowed minor exempt development such as class 10, fences etc • Long period of negotiation with Dept of Planning and FPAA • Maintains NSW strong position for new development in Bush Fire Prone Areas.
  • 7. Background - Complying Development • Exempt & Complying Codes SEPP has been in effect from 2008. • Bush Fire was a land based exclusion which only allowed minor exempt development such as class 10, fences etc • Long period of negotiation with Dept of Planning and FPAA • Maintains NSW strong position for new development in Bush Fire Prone Areas.
  • 8. The changes to complying development • Bush fire prone land is no longer excluded from the Codes SEPP • New assessment process applies to the General Housing Code and the Rural Housing Code • Part 3 of Codes SEPP – Development Standards eg. setbacks, building height & bush fire prone land standards
  • 9.
  • 10.
  • 11. • Cannot be carried out on BFP Land for State Significant Development, Integrated Development or Other development • Can be applied to infill situations for alterations, additions and new houses that meet the code criteria (Development Standards) • Development Standards are based on the zoning of the land – Rural zonings covered by Rural Housing Code RU1 – RU 6 – Residential or the General Housing R1 – R5
  • 12. Part 3 General Housing Code cl. 3.36B Development standards for bush fire prone land (1) This clause applies: (a) to all development specified for this code that is to be carried out on a lot that is wholly or partly bush fire prone land (other than development that is the erection of non-habitable ancillary development that is more than 10m from any dwelling house, landscaping, a non-combustible fence or a swimming pool), and (b) in addition to all other development standards specified for this code. (2) The development may be carried out on the lot only if: (a) the development conforms to the specifications and requirements of the following that are relevant to the development: (i) Planning for Bush Fire Protection (ISBN 0 9751033 2 6) published by the NSW Rural Fire Service in December 2006, (ii) Addendum: Appendix 3 (ISBN 0 9751033 2 6, published by NSW Rural Fire Service in 2010) to Planning for Bush Fire Protection (ISBN 0 9751033 2 6), (iii) if another document is prescribed by the regulations for the purposes of section 79BA of the Environmental Planning and Assessment Act 1979—that document, and
  • 13. Part 3 General Housing Code cl. 3.36B Development standards for bush fire prone land (b) the part of the lot on which the development is to be carried out is not in bush fire attack level-40 (BAL-40) or the flame zone (BAL-FZ), and (c) the lot has direct access to a public road or a road vested in or maintained by the council, and (d) a reticulated water supply is connected to the lot, and (e) a fire hydrant is located less than 60 metres from the location on the lot of the proposed development, and (f) mains electricity is connected to the lot, and (g) reticulated or bottled gas on the lot is installed and maintained in accordance with AS/NZS 1596:2008, The storage and handling of LP Gas and the requirements of relevant authorities (metal piping must be used), and (h) any gas cylinders on the lot that are within 10m of a dwelling house: (i) have the release valves directed away from the dwelling house, and (ii) are enclosed on the hazard side of the installation, and (iii) have metal connections to and from the cylinders, and (i) there are no polymer sheathed flexible gas supply lines to gas meters adjacent to the dwelling.
  • 14. • 3) A standard specified in subclause (2) (b) is satisfied if one of the following certifies that the development is not in bush fire attack level-40 (BAL-40) or the flame zone (BAL-FZ): • (a) until 25 February 2012—the NSW Rural Fire Service, or • (b) a person who is recognised by the NSW Rural Fire Service as a suitably qualified consultant in bush fire risk assessment, or • (c) the council. Note. More information about the categories of bush fire attack, including the flame zone, can be found in Table A3.4.2 of Addendum: Appendix 3 (ISBN 0 9751033 2 6 and published by NSW Rural Fire Service in 2010) to the publication titled Planning for Bush Fire Protection (ISBN 0 9751033 2 6) published by NSW Rural Fire Service in 2006.
  • 15. Bush fire prone land - CDC AS3959 (2009) BAL Level Description BAL LOW Insufficient risk Council assessment or BAL 12.5 Ember attack BPAD Certification BAL 19 Increased ember attack and debris BAL 29 Ember attack and radiant heat BAL 40 Radiant heat, embers and flame DA Required exposure BAL FZ Direct exposure to flames and fire DA Required front BAL 40 & FZ - The distance from a bush fire at which there is significant potential for sustained flame contact to a building.
  • 16. RFS Submission Requirements • Kit for applicants to determine their BAL when applying for a BAL Risk Assessment Certificate. • Identification of lot particulars • Statement of proposed development • A site plan with (reference number and dated) drawn to scale that indicates building footprint • BAL Risk Assessment fee (may be applicable).
  • 19. Suitably Qualified Consultants • It is a requirement that a person who has suitable qualifications and experience undertakes the assessment. This could be either the local council or a person identified as being a ‘suitably qualified consultant’.
  • 20.
  • 22. Suitably Qualified Consultants Recognised by NSW Rural Fire Service – Fire Protection Association Australia • BPAD-A and BPAD-D • Or other equivalent BPAD qualification/scheme
  • 23.
  • 24. Certificate particulars • Duration of Certificate - 12 months • Must identify BAL level in the certificate – Site assessment is critical • Amendments – There are no provisions to do amendments to the certificate. • Conditioning – Conditioning cannot be applied. The proposal meets the DTS or it does not. • Based on the hazard at the time of inspection • No approval for vegetation clearing or establishing APZ’s. • Multiples assessments for certificates can be undertaken. However, only a final certificate can be provided with the CDC.
  • 25. Residential DEVELOPMENT STANDARDS Construction requirements Bushfire Attack Level Low-29 Public road access Reticulated water supply A fire hydrant less than 60 metres Mains electricity Reticulated or bottled gas installation Gas cylinder location Gas supply lines
  • 26. Best Practice Guidelines • New works to comply with Development Standards ie. AS3959 2009 ‘Construction of Buildings in Bushfire Prone Areas’ • Most homes in NSW pre-date bush fire legislation. • Unable to achieve increased bush fire protection. • NSW RFS has produced the Best Practice Guidelines to assist existing houses to upgrade.
  • 27. Is Upgrading Mandatory? • No, however compliance with the Best Practice Guide is strongly recommended as a minimum • In addition to any other bush fire protection measures – Site management – Landscaping – Construction standards – Services
  • 28. Auditing • Following issue of CDC, required to be forwarded to RFS • The RFS will carry out an auditing process to ensure accuracy of BAL Risk Assessment Certificates • Will also be used by RFS for operational purposes • Breaches will be forwarded to the accredited body
  • 30. Hansard • S79BA originally intended councils undertake the majority of bushfire risk assessment – “This will be a general referral requirement although councils, as consent authorities, should be able to determine whether developments meet the guidelines specifications” (Parliament Hansard May 2002)
  • 31. 79BA (1) Development consent cannot be granted for the carrying out of development for any purpose (other than a subdivision of land that could lawfully be used for residential or rural residential purposes or development for a special fire protection purpose) on bush fire prone land unless the consent authority: (a) is satisfied that the development conforms to the specifications and requirements of the document entitled Planning for Bush Fire Protection, ISBN 0 9751033 2 6, prepared by the NSW Rural Fire Service in co-operation with the Department of Planning (or, if another document is prescribed by the regulations for the purposes of this paragraph, that document) that are relevant to the development (the relevant specifications and requirements), or
  • 32. 79BA (b) has been provided with a certificate by a person who is recognised by the NSW Rural Fire Service as a qualified consultant in bush fire risk assessment stating that the development conforms to the relevant specifications and requirements • “relevant specifications” DTS provisions of Planning for Bush Fire Protection • “requirements” documentation provided to Council in support of the certificate. Documentation includes that detailed in Appendix 4 of PBP. • “Certificate” means to provide documented evidence to Council as the consent authority as to your recommendations to be incorporated into the conditions of consent. This should include the DTS requirements of PBP and the appropriate level of construction in accordance with AS3959.
  • 33. 79BA • (1A) If the consent authority is satisfied that the development does not conform to the relevant specifications and requirements, the consent authority may, despite subsection (1), grant consent to the carrying out of the development but only if it has consulted with the Commissioner of the NSW Rural Fire Service concerning measures to be taken with respect to the development to protect persons, property and the environment from danger that may arise from a bush fire.
  • 34. 79BA • is satisfied that the development does not conform = demonstration that there is some form of non-compliance. • DoP and the RFS will be pushing for this to be done and after the 12 months transition will be working with councils (training/ mentoring) to ensure they are comfortable in the assessment of applications. • It is envisaged that DAs referred to the RFS will not be accepted unless they can demonstrate the non-compliance with PBP. • Assessment sheets/checklists will be developed to assist councils. • IMPORTANT – The changes are designed to allow the RFS to focus resources on higher risk developments.
  • 35. In Summary • Council shall assess compliance with ‘Planning for Bush Fire Protection 2006’ (PBP) for all developments under section 79BA • Onus on councils to undertake assessments • Referral to RFS only where proposal does not comply with PBP • Reduce assessment timeframes and allow RFS to focus upon high risk developments • Enable recognised consultants to certify developments compliance
  • 36. Further Information • NSW Department of Planning website – Fact Sheet November 2010 – Fact Sheet 3 – General Housing Code – Fact Sheet 10 Complying Development on Bushfire Prone Land • RFS Website – Fast Fact 5/10 Recognised/Qualified Consultants – Practice Note 1/10 Requirements for Recognised/Qualified Consultants – BAL Risk Self Assessment Tool – BAL Risk Assessment User Guide – BAL Risk Assessment Application Kit – Best Practice Guideline
  • 37. Questions Lew Short Group Manager Community Resilience NSW Rural Fire Service 8741 5454 Lew.short@rfs.nsw.gov.au Lew Short lewshort14

Notes de l'éditeur

  1. The RFS has worked with the Department of Planning to remove the land based restriction for complying development on bush fire prone land which is zoned residential or rural residential. Development Standards have also been introduced for development on bush fire prone land in addition to those standards which are already in place for complying development.
  2. The RFS has worked with the Department of Planning to remove the land based restriction for complying development on bush fire prone land which is zoned residential or rural residential. Development Standards have also been introduced for development on bush fire prone land in addition to those standards which are already in place for complying development.
  3. The RFS has worked with the Department of Planning to remove the land based restriction for complying development on bush fire prone land which is zoned residential or rural residential. Development Standards have also been introduced for development on bush fire prone land in addition to those standards which are already in place for complying development.
  4. The RFS has a document called the BAL Risk Assessment Application Kit. This is what the RFS requires applicants to submit as their application for a BAL Risk Assessment Certificate. The BAL RAAK includes the necessary application form. Councils may also like applicants to submit this information. The Application kit includes the minimum information required to carry out an assessment. The first section of the kit includes information on how to do a self assessment of BAL Risk. The second part of the document has the application form and submission requirements including identification of lot particulars, statement of the proposed development, a site plan, photographs of the property and vegetation identified as being the bush fire hazard and the application fee. RFS will not be providing hard copies of the kits, only provided as a downloaded document.
  5. This is a sample of the RFS BAL Risk Certificate for proposals which fall at or below BAL-29. (Run through the paragraphs)
  6. This is a sample of the RFS BAL Risk Certificate for proposals which are determined as being BAL-40 or BAL-FZ. (Run through the paragraphs)
  7. Council is recognised as an assessing authority to determine BAL and compliance with PBP – Council can rely on in-house expertise or seek external advice. External advice can be gained from a suitably qualified consultant. Currently the RFS recognises those people/businesses who are members of the Fire Protection Association of Australia (FPAA) who have obtained the BPAD-A or BPAD-D qualification. BPAD-D consultants are only accredited to carry out Deemed to Satisfy Assessments, BPAD-A consultants can undertake an Alternate Solutions assessment. Eg. Council checking environmental assessment without Environmental degree.
  8. This is a residential site which has been identified as being at or below BAL-29. The development standards that need to be considered for this site include: The development conforms to the specifications and requirements of the following that are relevant to the development: Planning for Bush Fire Protection (ISBN 0 9751033 2 6) published by the NSW Rural Fire Service in December 2006; Addendum: Appendix 3 (ISBN 0 9751033 2 6, published by NSW Rural Fire Service in 2010) to Planning for Bush Fire Protection (ISBN 0 9751033 2 6), If another document is prescribed by the regulations for the purposes of section 79BA of the Environmental Planning and Assessment Act 1979. The part of the lot on which the development is to be carried out is not in bush fire attack level-40 (BAL 40) or the flame zone (BAL-FZ), and The lot has direct access to a public road or a road vested in or maintained by the Council; A reticulated water supply is connected to the lot; A fire hydrant is located less than 60 metres from the location of the lot of the proposed development – focus on this as it could knock out a lot of development being considered under the Codes SEPP. Mains electricity is connected to the lot; Reticulated or bottled gas on the lot is installed and maintained in accordance with AS/NZS 1596:2008, The storage and handling of LP Gas and the requirements of relevant authorities (metal piping must be used), and Any gas cylinders on the lot that are within 10m of a dwelling house: have the release valves directed away from the dwelling house, and are enclosed on the hazard side of the installation, and have metal connections to and from the cylinders, and There are no polymer sheathed flexible gas supply lines to gas meters adjacent to the dwelling;
  9. BAL Risk Assessment only relates to the proposed development. Following the Victorian bush fires of February 2009 Australia introduced national building regulations that require consideration of bush fire protection for residents who are building or renovating their homes. However the majority of residences pre-date this legislation meaning existing houses are unable to achieve the increased level of bush fire protection via AS3959-2009. Consequently, the RFS has developed the Best Practice Guidelines which provides practical recommendations to those who live in bush fire prone areas. These recommendations involve the upgrade of existing homes to be better protected from bush fires.
  10. Upgrading is not mandatory, however compliance with this document is recommended where new works are being undertaken and an existing dwelling exists. In this regard, for all Development Applications, complying developments, etc, the requirements of this document should be applied as a minimum standard to the existing dwelling, in addition to any other bush fire protection measures that may be required. These retrofitting measures assist in making your home safer against the impact of embers and radiant heat in the event of a bush fire, however, they form only part of the solution. Undertaking routine property maintenance and preparing a bush fire survival plan are other important parts to your bush fire protection and survival.
  11. Quality assurance. To ensure accuracy and that there is no dilution with planning and building controls in respect to PBP. With the intention being to maintain protection of life and property. If asked – this is in DoP Fact Sheet 10.
  12. (1)  Development consent cannot be granted for the carrying out of development for any purpose (other than a subdivision of land that could lawfully be used for residential or rural residential purposes or development for a special fire protection purpose) on bush fire prone land unless the consent authority: (a)  is satisfied that the development conforms to the specifications and requirements of the document entitled Planning for Bush Fire Protection, ISBN 0 9751033 2 6, prepared by the NSW Rural Fire Service in co-operation with the Department of Planning (or, if another document is prescribed by the regulations for the purposes of this paragraph, that document) that are relevant to the development (the relevant specifications and requirements), or (b)  has been provided with a certificate by a person who is recognised by the NSW Rural Fire Service as a qualified consultant in bush fire risk assessment stating that the development conforms to the relevant specifications and requirements. (1A)  If the consent authority is satisfied that the development does not conform to the relevant specifications and requirements, the consent authority may, despite subsection (1), grant consent to the carrying out of the development but only if it has consulted with the Commissioner of the NSW Rural Fire Service concerning measures to be taken with respect to the development to protect persons, property and the environment from danger that may arise from a bush fire. is satisfied that the development does not conform = demonstration that there is some form of non-compliance. DoP and the RFS will be pushing for this to be done and after the 12 months transition will be working with councils to ensure they are comfortable in the assessment of applications. It is envisaged that DAs referred to the RFS will not be accepted unless they can demonstrate the non-compliance with PBP. Assessment sheets/checklists will be developed to assist councils. IMPORTANT – The changes are designed to allow the RFS to focus resources on higher risk developments.
  13. (1)  Development consent cannot be granted for the carrying out of development for any purpose (other than a subdivision of land that could lawfully be used for residential or rural residential purposes or development for a special fire protection purpose) on bush fire prone land unless the consent authority: (a)  is satisfied that the development conforms to the specifications and requirements of the document entitled Planning for Bush Fire Protection, ISBN 0 9751033 2 6, prepared by the NSW Rural Fire Service in co-operation with the Department of Planning (or, if another document is prescribed by the regulations for the purposes of this paragraph, that document) that are relevant to the development (the relevant specifications and requirements), or (b)  has been provided with a certificate by a person who is recognised by the NSW Rural Fire Service as a qualified consultant in bush fire risk assessment stating that the development conforms to the relevant specifications and requirements. (1A)  If the consent authority is satisfied that the development does not conform to the relevant specifications and requirements, the consent authority may, despite subsection (1), grant consent to the carrying out of the development but only if it has consulted with the Commissioner of the NSW Rural Fire Service concerning measures to be taken with respect to the development to protect persons, property and the environment from danger that may arise from a bush fire. is satisfied that the development does not conform = demonstration that there is some form of non-compliance. DoP and the RFS will be pushing for this to be done and after the 12 months transition will be working with councils to ensure they are comfortable in the assessment of applications. It is envisaged that DAs referred to the RFS will not be accepted unless they can demonstrate the non-compliance with PBP. Assessment sheets/checklists will be developed to assist councils. IMPORTANT – The changes are designed to allow the RFS to focus resources on higher risk developments.
  14. (1)  Development consent cannot be granted for the carrying out of development for any purpose (other than a subdivision of land that could lawfully be used for residential or rural residential purposes or development for a special fire protection purpose) on bush fire prone land unless the consent authority: (a)  is satisfied that the development conforms to the specifications and requirements of the document entitled Planning for Bush Fire Protection, ISBN 0 9751033 2 6, prepared by the NSW Rural Fire Service in co-operation with the Department of Planning (or, if another document is prescribed by the regulations for the purposes of this paragraph, that document) that are relevant to the development (the relevant specifications and requirements), or (b)  has been provided with a certificate by a person who is recognised by the NSW Rural Fire Service as a qualified consultant in bush fire risk assessment stating that the development conforms to the relevant specifications and requirements. (1A)  If the consent authority is satisfied that the development does not conform to the relevant specifications and requirements, the consent authority may, despite subsection (1), grant consent to the carrying out of the development but only if it has consulted with the Commissioner of the NSW Rural Fire Service concerning measures to be taken with respect to the development to protect persons, property and the environment from danger that may arise from a bush fire. is satisfied that the development does not conform = demonstration that there is some form of non-compliance. DoP and the RFS will be pushing for this to be done and after the 12 months transition will be working with councils to ensure they are comfortable in the assessment of applications. It is envisaged that DAs referred to the RFS will not be accepted unless they can demonstrate the non-compliance with PBP. Assessment sheets/checklists will be developed to assist councils. IMPORTANT – The changes are designed to allow the RFS to focus resources on higher risk developments.
  15. (1)  Development consent cannot be granted for the carrying out of development for any purpose (other than a subdivision of land that could lawfully be used for residential or rural residential purposes or development for a special fire protection purpose) on bush fire prone land unless the consent authority: (a)  is satisfied that the development conforms to the specifications and requirements of the document entitled Planning for Bush Fire Protection, ISBN 0 9751033 2 6, prepared by the NSW Rural Fire Service in co-operation with the Department of Planning (or, if another document is prescribed by the regulations for the purposes of this paragraph, that document) that are relevant to the development (the relevant specifications and requirements), or (b)  has been provided with a certificate by a person who is recognised by the NSW Rural Fire Service as a qualified consultant in bush fire risk assessment stating that the development conforms to the relevant specifications and requirements. (1A)  If the consent authority is satisfied that the development does not conform to the relevant specifications and requirements, the consent authority may, despite subsection (1), grant consent to the carrying out of the development but only if it has consulted with the Commissioner of the NSW Rural Fire Service concerning measures to be taken with respect to the development to protect persons, property and the environment from danger that may arise from a bush fire. is satisfied that the development does not conform = demonstration that there is some form of non-compliance. DoP and the RFS will be pushing for this to be done and after the 12 months transition will be working with councils to ensure they are comfortable in the assessment of applications. It is envisaged that DAs referred to the RFS will not be accepted unless they can demonstrate the non-compliance with PBP. Assessment sheets/checklists will be developed to assist councils. IMPORTANT – The changes are designed to allow the RFS to focus resources on higher risk developments.
  16. The intent of the changes to S79BA is for councils to assess compliance with Planning for Bush fire Protection. Referral of DAs to the RFS should only be when the proposal does not comply with Planning for bush fire protection or if Council feels unable to assess compliance with Planning for bush fire protection. To support Councils in undertaking their own assessments, Section 733 of the Local Government Act, 1993 has been amended to limit councils’ liability when they have undertaken an assessment in good faith. In reducing the number of referrals to the RFS and completing assessments at Council should help reduce assessment timeframes. The changes to S79BA also allow assessment of development to be carried out by a suitably qualified consultant and for the first 12 months, the RFS.
  17. NSW DoP Fact Sheet – Facilitating councils’ assessing low risk and low impact development applications on bush fire prone land – s.79BA of the EP&amp;A Act