SlideShare une entreprise Scribd logo
1  sur  11
Underground coal mining in India –
                              Technological option and challenges ahead

                                                  MD. Suresh Kumar


Abstract



W          orld coal institute estimates coal is the major contributor for energy generation to the tune of 60% and
           remaining from gas, diesel, nuclear, wind and hydel. In India, 75% coal is consumed by power sectors.
           The demand tends to outstrip domestic supply. The power sectors continue to report generation losses




                                                                            ar
from coal shortages. The pace of power capacity additions has hardly been commensurate with the need. Less
than 30 GW of the planned 40 GW for 2002-07 could have been materialized as reported by The Energy and
Research Institute of India (TERI). The Government’s recent effort to build several 4000 MW power plants under




                                                                um
ultra mega power schemes would require coal blocks with reserves of 600-700MT. The projected coal demand for
the year 2024-25 for power, steel, cement and others nearly 1147 MT which is doubled the existing coal
production. Hence the present 6% growth in coal production would not be sufficient.

                                                              hK
The country has nearly 95 BT proven and 55 BT extractable coal reserves. The coal industry in the country is
governed by CIL 80% with 8 subsidiaries, SCCL 9% and 5% captive mines by others. As per the coal mines
amendment bill, Government of India has identified captive coal blocks and nearly 291 blocks were allotted tor
Private and Public sectors to augment the coal production. But this is only transitory solution for the deficit.
                                                        res
Because, most of the coal production comes from open pit mining and it nearly contributing over 84% of absolute
production in the country. Open pit mining has its own implications due to depth and environment pollution
whereas billion tonnes of coal locked up in underground standing pillars and in thick seams requiring suitable
technology. This not only shows lack of resource management but leaves a great technogical void to compensate
                                                 .Su


opencast coal production with proper exploitation of existing underground resources.

 Bulk production of coal at faster rate from underground, particularly at depth is possible from Long wall which is
proven technology worldwide. Besides, nearly 40% of the proven reserves are in thick seams posing technological
                                         MD




challenge for long time. The conventional underground methods like pillar extraction and          multi stage mining
are only proven technologies so far in the country. The percentage of extraction in these methods is well known to
be less than 40%. The other mining methods like Wide stall, Long wall with increased height of extraction and
Top coal caving are having their own draw backs. The Blasting gallery method of winning thick seams introduced
in SCCL in 1989, witnessed to be great success. On the other hand, the coal pillars statued in underground both in
                                   or:




CIL and SCCL due to various complex mining conditions need to be rightly exploited to the present country’s
coal requirement or otherwise in-justification to the nation’s wealth. CIL has introduced short wall mining, a
variant of Long wall mining to extract underground pillars. SCCL has identified few properties for short wall to
                             th




be introduced in near future. High wall mining is the state of art of mining, gifted to the mining community world
wide to survive the open pit mines suffering from uneconomical stripping ratio. It conglomerates both
                          Au




underground and open pit technologies being practiced in US, Australia etc., In India CIL and SCCL have
identified coal blocks to introduce this method in coming years.

This paper deals with the tale of success and failures of mining methods practiced so far in the country and
explores the possibility of sustainable winning of underground resources with the viable technological option and
the challenges ahead.



         Additional Manager, Underground Mech Cell, SCCL
1. Introduction

In India, the Coal is one of the primary sources of energy, accounting for about 67% of the total energy
consumption in the country. The most of the coal production comes from open pit mines. Open pit mining has its
own implications due to depth and environment pollution. Therefore, a proper underground resource management
needs to be explored and implemented at this juncture to bridge the technological void. Proper planning and
methodological adoption for existing underground resources only would do. The study of history of Long wall
method in the country has not shown attractive results, but introduction of new era Long walls would break the
earlier records. Enormous quantity of coal is locked up in underground standing pillars in the country. Extraction
of these pillars by Short wall method and thick seam mining are the area where the Indian mining community has
to have a focus to liquidate the existing underground standing pillars. Besides, developments in exploration,
detailed geo technical studies, ventilation solutions for deeper mines, hazard mapping and support techniques for




                                                                             ar
complex strata conditions are the pre-requisites for sustainable exploitation of existing coal resources in Indian
mines.




                                                                 um
2. Resources in Indian coal mines

Being a third coal producer in the world, India has an age old history in its coal mining sector. Coal mining in

                                                               hK
India dates back to the 18th century, however the regulatory framework for this industry was conceived in 1923.
In 1972-73, the Indian government nationalised the coal industry, primarily to develop the sector, since it was
considered of strategic importance for rapid industrial development. India has the fourth largest reserves of coal in
the world (approx. 197 billion tonnes.). Coal India Ltd (CIL) was incorporated as a holding company for eight
                                                        res
coal producing subsidiaries and SCCL is another major coal producing company in southern part of the country.
Coal deposits in India occur mostly in thick seams and at shallow depths. Non-coking coal reserves aggregate
172.1 billion tonnes (85 per cent) while coking coal reserves are 29.8 billion. Indian coal has high ash content (15-
45%) and low calorific value. Coal in India occurs in two important types, Gondwana and Tertiary. Gondwana
                                                 .Su


coal field occurs with sedimentary rock of lower Gondwana age which contributes 98% and rest is Tertiary.
Gondwana coal field is distributed in the valleys of Domodar, the Son, the Mahanadi, the Godavari and Wardha
whereas the tertiary coal spreaded in extra peninsular areas. When compared to coal, the lignite reserves are
relatively modest.
                                         MD




3. A look into future

India's coal demand is expected to increase manifold within the next 5 to 10 years due to the completion of on-
going coa;-based power projects, and demand from metallurgical and other industries. Demand for coal has been
                                    or:




rising at an annual rate of 6 per cent since 1992-93 and CIL and its subsidiaries will be unable to meet the
projected demand alone. The investment needed to bridge the gap of 400 million tonnes, between the level of
production in the public sector (290 million tonnes in 1995-96) and the projected demand of 690 million tonnes
                             th




(2009-10) is estimated to be US$ 18 billion. The public sector corporations are expected to increase their
production by about 250 million tonnes by 2009-10, subject to their making an additional investment of US$ 8-
                          Au




10 billion. The balance requirement of 150 million tonnes will have to be met by imports in the short run and by
new investments in the long run. With the advent economic reforms, government relaxed controls on pricing and
distribution and a new coal policy permits private sector participation in commercial coal mining. Government of
India has identified captive coal blocks and nearly 291 blocks were allotted to private and public sectors to
augment the coal production. But this is only transitory solution for the deficit. Hence a real challenge lies on how
the existing and future underground resources are managed to produce bulk coal production.

4. Underground coal mining in India
Underground mining in India mainly, the room-and-pillar method with manual loading, accounts for about 20% of
coal production. This is major limiting factor in 80s. The semi-mechanised methods using SDLs and LHDs have
becoming populous only in the last decade. Longwall retreat with caving introduced three decades ago, has
recorded few success story due to the limitations in the method and its application in Indian conditions.
4.1. Conventional mining
4.1.1. Board and pillar
Board and pillar mining is an age old mining system in the country. The development and liquidation of pillars
were manually done with basket loading onto tubs which was abundantly existing still last decade. Scraper loaders
were introduced in late 1960’s which were mounted on rails and load coal onto tubs. But it had little scope due to
its limitations. Steel bolts such as point anchor bolts and wedge bolts were introduced in place of wooden supports
increased safety and productivity. Belt conveyors replaced series of haulers and hectic tramming circuits in
underground for coal transport in 80’s.
4.1.2. Wide stall method
Under difficult geo mining conditions, where caving is restricted to protect surface features or in such conditions
where the roof rocks difficult to cave in, the normal splitting of pillars leaving wide stook was tried but it helped
few. Formation of stook by optimizing recovery causes reduction of strength of natural support. In such cases, the
percentage of extraction was as low as 30%. An attempt to optimise the extraction in the seams 3m plus by




                                                                              ar
heightening has weakened the pillar strength further. Under these circumstances, the wide stall method has given
better results. Matching of gallery size with the strength of immediate roof and strength improvement of the




                                                                 um
natural support by increasing width/height ratio of pillars are the two basic constituents of this method. The
strength and size of the pillar calculated basing load expected on pillars with factor of safety atleast 2. The
effective bearing capacity of a pillar is comparatively more than a number of stook of the equivalent area. On the
basis of extensive laboratory investigations on diffent simulated models, idea of wide stall mining was conceived

                                                               hK
and for the first time implemented in East Bhuggatdih Colliery of Jharia coal field. Later, SCCL adopted this
method in Gdk-8A incline after a major roof fall accident. However, the percentage of coal recovery falls below
40% and the recovery is further increased in thick seams by taking out floor coal in the mines like Gdk-8A
incline.
                                                         res
4.1.3. Yield pillar
Coal mine bursts and sudden roof collapse are not uncommon events in most Indian underground mines under
stiff roof condition. However when a burst occurs, it almost results in a major hazard. Some times, the strength
                                                 .Su


and geometry of pillar and the rock load don’t match and may result in delayed caving, increased goaf exposure
finally its sudden failure. Besides there are number of other fundamental factors that influence such occurrence.
Excess rock load causes violent failures of ribs, roof or floor. In such condition pillars shall not be further
strengthened to prevent caving or not be too weak to stimulate premature collapse. Over many years of dealing
with this hazard, specialised requirements for layouts and novel extraction sequences have been developed on a
                                          MD




site specific basis to safely mine coal. There have been many engineered prevention controls proposed to mitigate
the devastating effects of these dynamic and violent failures. While none of these considered as “stand alone”
design, the technique of yield of pillar has come in the mind of mining engineers. A yield pillar is a pillar which is
critically-sized to withstand the abutment loads and to yield nonviolently or yield before the roof and floor sustain
                                    or:




permanent damage. In India, sccl has introduced this method in one of its mines VK-7 incline to extract pillars
safely with Joy miner where the sand stone roof is reasonably hard to fall. The distressed ground conditions due to
hectic depillaring done in the seam and Longwall caving in the upper seam combined with strata unconformity in
                             th




the vicinity of faults resulting in sudden collapse of roof incurring huge loss of life and machinery in 2006 where
this method is found more useful. However the percentage of coal recovery is not attractive due to lot of coal is
left inside the goaf in the form of pillars and stooks.
                          Au




4.2. Long wall mining
4.2.1. A brief review of Longwall mining in India
As a global phenomenon, the pace of technological change had been especially rapid in the second half of the last
century, the mechanization of unit operations led to the development of Longwall technology on the concept of
mass production in coal mining industry. It was also aimed at reducing the drudgery, monotony and
dangers of work persons engaged in underground mining operations. The development of mass production
technology including Longwall equipment, continuous miners, ploughs and shearers have been accompanied by a
series of incremental and innovative developments in roof supporting. India also as a general rule followed the
world trend and in 1975. ‘Project Black Diamond’ envisaged introduction of 130 powered supports Longwall
(PSLW) faces by the year 2000. Initially, the first fully mechanized self- advancing PSLW face was introduced in
Moonidih mine in Jharia Coalfield in 1978. Subsequently more mines were planned with PSLW in the eighties,
namely, East Katras ( BCCL), Seetalpur, Dhemo-Main, Jhanjra, Khottadih (all in ECL ),Patharkhera (WCL) and
Churcha (SECL), and first long wall in SCCL introduced at GDK 7 incline in 1983 at also a few other mines in
Company. In the process about 30 PSLW sets had been imported from different sources in different countries like,
UK, Poland, Russia, Germany, France and China. Barring a few exceptions, where the powered support Longwall
faces gained moderate success. Most of the Longwall faces were far from the desired level of production and
productivity on sustainable basis. Further large scale introduction of Longwall technology received severe
setbacks due to its successive failures at Churcha (SECL) and Khottadih (ECL) mines. At present, Longwall
mining accounts for a meager production of about 4% of the total underground production

4.2.2. Factors affecting the Longwall performance in Indian mines
4.2.2.1. No Policy for Introduction of Mass-Production Technology
Even after nationalization, the Govt of India was not firm on policy for mass production technology, like
Longwall and continuous miners. Because of that no private/government company has come forward for
manufacture of underground mining equipments for mass production technology.
4.2.2.2. Standardisatin of Longwall equipment




                                                                          ar
There was no standardization of Longwall equipment in the country. As such, different Longwall equipment
purchased in India are of different specifications. As a result, no indigenous manufacturers were motivated to




                                                               um
manufacture small demand of Longwall spare parts. Delay in procurement of spares affected production from
Longwall panels. As the number of operating faces are less, the suppliers were not able to provide either
manufacturing facilities or spares depot within India.
4.2.2.3. Wrong place of Application

                                                             hK
The study of few cases in the country revealed that the Longwall technology was introduced in extremely critical
conditions such as difficult geo-mining conditions, steep and thin seams, at deeper horizons with very high
ambient temperature, Degree-III gassiness and mine where coal evacuation system was extremely circuitous with
a series of conveyors. These factors proved a serious bottleneck in improving productivity from Longwall faces at
its very budding stage and gave a wrong signal as if the techno-logy is not suitable in Indian mining conditions.
                                                      res
4.2.2.4. Face geometry
Longwall face width was designed from 60m-165m, the length varying between 500m to 1.2Km and operated in
depth 30m to 350m so far. In these conditions, very few mines recorded good results such as VK-7 and Gdk-10A
                                               .Su


mines of SCCL with regard to consistency. Non-availability of longer panels due to geological disturbances, or
due to surface features to be protected and presence of standing pillars in an upper seam yet to be extracted,
resulted in frequent shifting of equipment and increase in non-productive work and time. Whereas the coal seams
extremely favoured Chinese, Australian and US mining industries to have longer and wider panels.
4.2.2.5. Lack of Infrastructure Facility
                                        MD




Introduction of Longwalls in already existing mines which were not having sufficient infrastructure to match the
desired level of production resulting in derating the projects. Provision of matching infrastructure was either
delayed or never came up in most of the cases.
4.2.2.6. Advanced geo-technical studies and R&D facility
                                  or:




In most of the cases, inadequate geological information and geo technical knowledge due weak borehole density
to become major chunk for failure which is often led to wrong planning including those wrong selection of power
roof supports, orientation of panels with respect to horizontal stress direction. Further it led to too many
geological surprises while working the face. The weak geo-informations resulted in wrong projections of faults,
                            th




thinning of seams, intrusions and variation in strength of immediate roof rocks. The poor knowledge of hydro-
geology drawn the faces and continuous water percolation in the strata led to strata control problems in many
                         Au




incidents. The most glaring example in this regard is failure of powered supports at Churcha (SECL) and
Khottadih (ECL). In both the cases the supports collapsed and failed to withstand the load exerted by
superincumbent strata during periodic weighting due to underrated supports. These two incidents gave severe jolt
to the programme of large scale introduction of Longwall technology in other Indian mines.
4.2.2.7. Technical lapses
There used to be some severe technical lapses pertaining to face operations that the development with older
version Road headers like AM-50s and Doscos are not matching with Longwall retreat rate, LW units were
introduced inferior quality top and upper seams which hugely affected economics, Lack of man riding facilities in
underground leads workmen reaching to face getting delayed and interrupted face operation too and the
conventional face transfer system including equipment withdrawal from one face, transporting to another face and
installation in the new face consumed 3 months to 6months.
4.3. Extracting thick seams
4.3.1. Blasting Gallery
The Blasting gallery method of thick seam extraction was introduced in SCCL during 1989 with the technical
collaboration of Carbonages de France (CdF), France. Based on its success, the method was introduced in five
mines of the company in VK-7, 21incline, Gdk 10incline, Gdk 8 incline and Gdk 11A in phases in the last two
decades. Over this period, the Blasting gallery method is established as an economically viable with a source for
bulk production. Evidently, this method is so proved to be safer due to its inherent mechanisation of drilling,
loading, transporting and supporting. The bottom section of virgin coal seam is developed in series of headings at
22-25 interval called ‘Rooms’ and connected 80-120m apart to form sub-panels. Such set of sub-panels ranging
from 4 -7 formed a Blasting Gallery panel. A first roof blast called ‘potato blast’ is done upto to the full seam
height at the in-bye end which creates free face for further blast holes. Thus the rooms are retreated continuing the
blasting upto full seam height following a diagonal line. A mobile electric drill drills shotholes all around the
room, at an angle inclined towards goaf upto full seam height in a ‘Ring pattern’. A ring contains 22-35 holes as




                                                                              ar
per the requirements. The different operations like drilling, blasting, supporting and coal production would go
simultaneously in the different rooms. Therefore an average production of 1000Te could be achieved from a




                                                                 um
panel. Whereas the percentage of coal recovery would be higher than the any other methods exist presently. In the
later stage, it was focused to adopt the same methodology to extract coal from developed bord and pillars. Panels
were formed by constructing isolation stoppings around and the Rooms were formed by splitting the existing
pillars. As the mines having intensive development in standing pillars, this method fed right stuff to the miners
wherever technically applicable.

4.3.2. Multi-stage mining and Stowing
                                                               hK
Before the Blasting gallery was landed in Indian soil, thick seams in the country mostly were developed in two or
three lifts depending upon the seam thickness leaving minimum of 3m parting between the lifts as per the
                                                         res
statutory requirement. Such seams were developed with room and pillars superimposed. Conceptually, this has
given confidence amongst the mining engineers with regard to percentage of recovery of coal seams. Later the
bottom section coal was extracted with stowing then the top section coal was removed with or without leaving
                                                 .Su


partition.

4.4. Introduction of SDLs and LHDs
SDLs and LHDs were introduced only in the last decade in the country. It simply replaced manual loading in the
conventional face. A review of accidents where the face workmen involved has thrown serious thoughts of
                                          MD




mechanisation of manual loading. It was taken almost a decade to eradicate manual loading in phased manner.
Initially Eimmco Elecon SDLs and 811 LHDs were introduced in the mines without much concentration on
application techniques in relation to the mining conditions. Later, on care full studies with field experience correct
application was chosen with respect to seam height, gradient, floor conditions and water percolation. Further
                                    or:




improvement was achieved by introducing Simplex SDLs and higher capacity E-912LHDs in the later part of the
decade. However, the introduction of this intermediate technology not only replaced manual mining but reduced
human drudgery and improved safety & productivity.
                             th




4.5. Continuous miners
As the cost of production and accidents trend are on higher side in mines operated with manual loading led to the
                          Au




thought of introduction of CM technology. The first fully mechanised room and pillar system in India, using
continuous miner technology, started its operations in May 2002 at Chirimiri Anjun Hill Mine, South Eastern
Coalfields Limited (SECL) on risk/gain approach.. The complete system, supplied by Joy Mining Machinery Ltd,
included a 12CM15 continuous miner, two shuttle cars, a feeder breaker, a mobile roof bolting machine and
electrical distribution system. Since start up, the system has averaged over 40,000 tonnes per month on the
development of a five entry room and pillar system and has now achieved over 50,000 tonnes in a month on de-
pillaring. To date the de-pillaring operations have been very successful providing the only approved method of
mechanised de-pillaring in India. In the present technological transformation, with considerable awareness and
training it is possible to produce 4 to 6 LTPA in Indian mining condition. Presently miners belong to JOY and
DBT are working in Anjana Hill Mine, Chirimiri (SECL) commissioned in May 2002, Thandasi Mine (WCL)
commissioned in June 2003, VK No: 7 Incline, Kothagudem (SCCL) commissioned in Aug, 2006. Jhangra
Under ground Mine (ECL) commissioned in June, 2007 and GDK 11A Incline (SCCL) commissioned in Dec,
2008.
4.6. Short wall mining
The shortwall mining technique is similar to longwall mining but with shorter face lengths, ranging between 40
and 90 m, with the aim of controlling the caving nature of the overlying upper strata, the load on support and the
overall operation of the supports at the face. Though the concept of shortwall initially aimed at this, Chinese
mines have introduced this technology to mine out standing pillars. The similar equipment used in Longwall is
utilised here too and open galleries ahead the face are well supported with longer roof bolts and cable bolts.
Additionally, breaker line supports which are of normal power supports set in the open galleries with remote
operation. Self advancing, crawler mounted supports are also used as breaker line supports. As per Indo-Chinese
agreement, the first shortwall was introduced at Balarampur of SECL where three such short panels have been
successfully completed and SCCL too planned to introduce shortwall in one of its mine RK-NT. The success of
this method in this two coal companies may lead the entire mining industry in the country to a newer thinking to
liquidate its vast standing on pillars property.




                                                                            ar
5. Road map to Indian coal mines for sustainable exploitation
5.1. Exploration and detailed geo-technical studies




                                                                um
Recently, SCCL has entered into MoU with CSIRO, Australia for implementation of first ever high capacity
Longwall technology where the detailed studies have been conducted which broadly includes increase in borehole
density to 20 / Sq Km, study of overlying strata behavior upto the height of 100 to 150m over the Longwall
panels. The existing practice of study levels depends on the requirements of the projects. Complete and detailed

                                                              hK
studies of entire block are not done before implementing the new projects like in US and Australian practice.
Besides, in the most of cases the mining projections are made depending on the existing geological data. As far as
practicable, coring needs to be done for each borehole, preserved in core library for analysis and photographed
too. The data from non cored boreholes can be generated with Geo–physical logging (neutron, gamma, resistivity
                                                        res
and density. In-situ stress and permeability measurements must be conducted in the boreholes equally spreaded
over the proposed panels. The permeability tests shall be conducted in different depth horizons to have most
representing result ranging from barren measure rock upto geological domain rocks including inter burden. Apart
from the above, PMP tests, Caving index, In-situ strength of coal, Piezometric studies core profiler and micro
                                                 .Su


logging shall be done to formulate most realistic mine panning. Minex modeling is the one software launched in
India and found its success to delineate the coal/ore structure.

5.2. Making Longwall Technology successful
                                         MD




5.2.1. Things to be learned from China
China introduced Longwall mining in the late seventies and early eighties as in India, but within 20 years it has
not only emerged as the world leader in coal production, but has established itself as the largest user of Longwall
technology in underground mines and has created for itself an international market for export of the technology,
expertise and equipment. From the very beginning, it adopted wholesome approach for large scale Longwall
                                   or:




mechanisation in their UG mines. Their approach was very methodical and it took into account their own social
and economical conditions. Instead of instantaneously jumping into hi-tech mechanisation only in some isolated
mines, they introduced the technology stage by stage with incremental development. China has developed tailor
                             th




made equipments suitable to their conditions. For this they have first generated skilled workforce of Engineers,
operators, designers, research institute personnel and manufactures. They gave greater emphasis on applied R & D
for product design and quality development. China has developed huge infrastructure at unit levels as well as
                          Au




central levels. It has constructed a number of new highly productive and efficient mines with different capacities
based on seam/geological conditions by identifying suitable coal blocks in advance. It has improved its
metallurgy for indigenous manufacture of powered supports with higher support resistance, more powerful
shearer, AFC and belt conveyor and started achieving 6-10mt coal from a Longwall face per annum.

5.2.2. Suitable blocks for wide and Lengthy Longwall faces
It is extremely important to choose the proper place of application of this mechanized Longwall technology,
which is capital intensive and involves a lot of time and manpower in installation, salvaging and shifting of
equipment. As the existing underground mines in CIL and SCCL have got limited scope for this technology as for
as the infrastructure is concerned. Hence, suitable virgin blocks can be sought for. As far as practicable, no other
technology shall be combined with Longwall. The expansion of existing mines is possible but only beyond 300m
depth where it is required to explore success of Longwall face at deeper horizons. The existing facilities like man
riding, ventilation and coal conveyance can be utilised during development till permanent set is made. The
minimum proved resources should be 100Mte so that the projects can be sustained for 25-30 years with one
particular set up or infrastructure. Today the world trend is to provide longer and wider panels to minimize the
number of shifting.

5.2.3. Proper equipment for specific geo-mining conditions
It is required to do advanced studies, numerical modeling and preparation of adequate of data related to the
specific geo-mining conditions of the mine, to make Longwall equipment tailor made to the site specific geo-
mining conditions. More over, one set of equipment can be used with only minimum modifications. More
particularly, the power supports which are available in varieties in the market shall be carefully selected with
respect to their load resistance, load expected from overlying strata and seam gradient.

5.2.4. Indigenous capacity of equipment manufacturing at Low cost
The private parties entering into Longwall equipment manufacturing and its spares is mearly nightmare except




                                                                            ar
finger count. But it may take another 10 years to develop the vendors to get technical expertise. With the mixed
result of Longwalls in the last 30 years, the Economy of the projects did not bring any fruitful results mainly due




                                                                um
to the landing cost of the equipment. Two important reasons can be attributed that the number of operating faces
and equipment cost. Developing country like India was not in a position to bare any economic fall outs due to
faces failed to produce to its rated capacity. Success not to come easily on its way, but out of sustained and hard
effort. Sufficient effort was put all these days and Longwalls in the country have produced a huge number of

                                                              hK
experienced mining engineers and experts. But the ultimate requirement is, to reduce equipment cost and
operating cost with self manufactured indigenous technology.

5.2.5. Both CIL and SCCL have to launch LW technology
The indigenous technological expertise comes only if much more Longwalls, atleast 30-50nos with range of face
                                                       res
lengths are both in SCCL and CIL having at least 25 years of project life. The most of the coal seams in the
northern part of the country occurred at lower depth with stripping ratio as low as 0.5 which neither posed any
coal scarcity nor warranted underground large scale mechanisation in the last 30 years. But the situation is
                                                .Su


upturned now and it is bound to makeup the coal demand from underground mines. The Central Government and
its planning commission assessed the ground situation and taken proactive decision to decentralise the mining by
opened up nearly 300 blocks given to private parties for capital coal utilisation. Experts anticipate only mixed
results out of this. A real improvement and next generation mining can be achieved only if CIL which is a larger
mining operator in the country comes forward to do Longwalls for mass underground production.
                                         MD




5.2.6. Introduction of High capacity Longwall for the first time in the country-sccl
Having understood the need of sustained underground mining, The SCCL has timely planned to introduce a latest
version Longwall face on par with USA, Australia and Chinese mines. Around $160 million worth first ever high
                                   or:




capacity Longwall Project of which the equipment is supplied by BUCYRUS. The production capacity would be
3Mtpa with panels ranging from 1500 to 2500 m length, 250m wide faces, Depth of working upto 600 m, Seam
inclination 1 in 5 and height of extraction is 3m. The supports are 1152 Te 2 legged DTDA shields with 120/104
tpsm support density, the shearer type-EL3000 with all electrical motors includes 2x860kw cutting motors,
                            th




3000tph cutting speed and 0.85m web, 3x855kw twin inboard AFC, 400kw BSL, 1600mm 3200tph gate belt with
other high capacity back up arrangements. For the first time in coal mines in the country a deep shaft 468m is
                         Au




being sunk for ventilation. More advanced from conventional like shifting of power packs and electricals with
monorail system and FSVs for transport of supports, men and materials. The entire country is looking forward to
see its implementation and success of this project which may give solution for implementation several high
capacity Longwalls in future.

5.2.7. Bolter miners for Roadway development
The one of the reasons that the Longwalls in the country is barking down is the panel’s development rates. The
low capacity Alpine miners and Doscos are used for panel development whereas machines were modified to their
needs in US, Australia and in China. High powered cutter motors, robust cutter head and traction system in latest
version machines improves machine stability, ability to work in seam gradients upto 10-150 and faster drivage.
The on-board bolting facility further improves machine utility hours and proved the development rate 400-500 per
month. However, Continuous miners had been dominant in development with twin gate roadways two decades
ago. Miners with on-board bolting facility and Bolter miners have further boosted the rate of drivages to cop-up
much sophisticated 6-10 Mte producing Longwall faces. Thus bulk output from Longwall face can not be
achieved without bolting facilitated miners or Bolter miners. There are verities of machines available in the
market to choose the best fit to seam and mining conditions and economy.

5.3. Liquidation of existing standing pillars
5.3.1. More short walls in future
Reintroduction of Long walls is emerging with new strength and high expectations both in CIL and SCCL. Hence,
introduction of more shortwalls may be delayed as it needs combination of older equipment and few new
additions. As such, shortwall sets, if purchased, may not justify economics with low range of production. During
first phase of its introduction, it is possible to put them in existing or older Longwall facilitated mines having
enough infrastructures. More new faces with infrastructure is possible in future with indigenous equipment.
5.3.2. Continuous miners




                                                                              ar
Liquidation of standing pillars with intermediate technologies like SDLs and LHDs with caving or stowing have
got its limitations due to scarcity of timber and sand near the mining areas. Face drilling for blasting and bolting is
a big concern as done mostly manually, consumes lot of time and reduces machine utilization. Mechanised drill




                                                                  um
machines like pneumatic drills, hydraulic drills and UDMs were introduced but did not prove as triumphant
matching machine. This is the reason, they produce just above the break even production and in many mines they
produce less than that. Venturing for bulk production is unattainable with these machines even with more
numbers. The only solution left with is miners. The present miners in India, except Chirimiri and Tansi, reported
                                                                hK
average performance. More experience, expertise and planning would make turn around. There is range of product
available in the market to suit to the mining conditions. But the concern is landing cost of equipment imported.
However it is not far from the reach that indigenous miners at low price may be dominate the market in the
coming years.
                                                         res

5.4. High wall mining for deep seated OC property
Highwall mining is extracting coal from the face in a seam exposed in the final bench of opencast mine, after
reaching to its economical stripping ratio. The extent of an opencast mining is limited by the financial viability,
                                                  .Su


though coal seam continues to exist beyond the quarriable limits. Irrecoverable coal is lost forever within the
highwall. Thus, highwall mining is a valued technology which can revolutionise maximization of extractable
reserves. This technology is being practiced in USA, Australia, and Indonesia and is likely to be introduced in
India in Eastern Coalfields Limited and Tata Steel – West Bokaro in coming years. CIL has identified 17 mines
                                          MD




suitable for highwall mining and SCCL 6 blocks. Coal is extracted with miner or borer and coal is transported
with belt or piped conveyor without artificial roof support and ventilation. The cars are added one by one behind
the miner as it cuts in the seam, in a manner which does not interrupt the flow of coal. The launch vehicle is a two
deck steel structure which sits on the floor of the pit at the base of the highwall. It serves as a work platform,
propulsion unit and utilities supply center. It remains stationary during the mining process, providing a stable
                                    or:




anchor point for the equipment at the highwall. It contains an electric power distribution center, a control cabin
from where the operator operates the entire system by remote control, two separate hydraulic power systems, as
well as cable and hose reels for electric power, coaxial cable and water.
                             th




                             Fig: 1. Typical components of a Highwall Mining Equipment
                          Au




As this method involves drivage of series of parallel roadways into the highwall along a particular horizon
separated by ribs, the dimensions of the roadway, the thickness of the ribs, the maximum depth to be operated
depends on the geo-technical characteristics of the seams / strata and surface features. Since the Technology is
newer to India, all these parameters should be carefully studied before implementation.

5.5. Ventilation for deeper coal mines and introduction of air cooling system in underground
The first shaft for coal mine, only 27m deep was sunk in the year 1851 at Eagra near Damalia in Raniganj coal
field. Whereas a number of shafts of greater than 1000m depth were sunk in 1890s and 1910s at Champion reef-
gold mine in KGF reached to a depth 3211m which is one of the deepest mine in the world. Whereas, the coal
mining operations have crossed 300m depth and extending beyond 400m in the country and facing complex
climatic conditions with high dry bulb temperatures due to strata temperature, mechanisation and humidity.
Hence, it is a need of hour to formulate efficient ventilation in underground to create comfortable conditions.
Deep shafts are inevitable to bring cool air at the deep most points. Higher capacity fans upto 400m3/min
operating upto 250mm water gauge are to be planned to work mechanised faces in deep seated reserves. Except in
few metalliferrous mines, air cooling/ refrigeration was not practiced in coal mines so far. But the present




                                                                              ar
situation emerges underground cooling system to reduce ambient temperature of intake air. SCCL is installing its
first refrigeration plant in underground 500TR chiller with 45000CMH air handling unit working at 40 mm water




                                                                 um
gauge at Vk-7 Joy miner face and planning to install in two more mines. CIL too planning to introduce AC plants
in underground. The cost of refrigeration per tone of coal against the losses that made out of inefficient ventilation
is highly insignificant.

5.6. Thick seam mining
                                                               hK
A huge amount of coal reserves is being locked up in thick seams in the country. Both CIL and SCCL having
huge amount of reserves of such kind. The conventional underground method of board and pillar development and
depillaring in multistage with or without stowing is only available and proven technology exists all these days.
The percentage of extraction in this method is well known to be less than 40%. The other mining methods like
                                                         res
wide stall, sub levels caving, Longwall with increased height if extraction and Longwall with top coal caving are
having its own drawbacks due to either less percentage of extraction or newer technology which is not yet
practiced in the country. The SCCL itself is having thick seam reserves about 40% out of two thousand million
                                                 .Su


tones of proved coal. Interestingly, Australia too has huge thick seam coal resources. The coal reserves in thick
seams in both countries aggregate to several tens of billion tonnes. The current mining methods and designs for
thick coal seams in underground mines are inefficient and result in huge losses of valuable coal resources in both
countries. A MoU was signed by India (SCCL) and Australia (CSIRO) jointly with the major outcome of
optimising extraction methods and/or designs to substantially improve recovery rates and safety of mining
                                          MD




operations in Indian thick seam environments.

5.6.1. Blasting gallery- a success venture in SCCL
Though this method was seemed to be conceptually easier and operationally dangerous in initial days, the simple
                                    or:




mechanisation and the face operation without much complication are the key factors that made people to be well
conversant to the applicability of the system with respect to their local mining conditions. A hydraulic supports
with canopy specially designed for the purpose of having allowance to LHDs to ply can replace existing manual
                             th




installation of steel bars supported on OC props. Walking breaker line supports in the junctions could reduce
human drudgery and still safer and productive too.
                          Au




5.6.1.1. Strata control problems
The experience in SCCL reveals that caving is not a problem in the coal seams with overlying strata having
compressive strength varying between 100-300 Kg/cm2 and of easy to moderate caving roof. The technique of
induced blasting incorporated in this method had proved to be given better results in bringing down the immediate
roof at desirable interval. The regular falls of immediate 3-5m layers of overlying sand stone strata allows the
upper and massive layers to readily cave in. Every periodic fall and induced fall posed minimum impact on the
gallery supports and roof and sides. While working over the worked out panels of bottom seam and simultaneous
working of lower and upper seam in gdk-8 incline revealed that the insitu stress domine is reasonably damaged to
favour easy caving.

5.6.1.2. Fire control in BGs
Spontaneous heating is one of the major problems being faced here. The occurrences of spontaneous heating in
working panels, not only threat to the general safety, but it forces to close down the panels losing huge quantity of
natural resources. It often ended up in sealing a large section of mine affecting the mine economics adversely.
Therefore the prevention of spontaneous heating in Basting gallery become inevitable for mining engineers
otherwise working of thick seams become questionable. The BG panels are being successfully mined in SCCL
with the following preventive measures:
1. Monitoring in-bye most goaf atmosphere through pipelines, thermal images camera and surface boreholes.
2. Removing floor coal and curtain coal meticulously during extraction and descenstional ventilation system to
   contain the gases inside the goaf and to restrict goaf ventilation.
3. Regular induced blasting at an interval of 5m and up to 9 to 10m height in roof to reduce strata control problem
   as well as fill the goaf regularly avoiding air pockets inside.
4. Proactive inertisation by continuous injection of CO2 and N2 into active goaf. A storage tanker with a capacity
   of 30 metric tones of liquid CO2 ensures its constant availability through pipe lines. Combination CO2 and N2
   creates identical density of goaf gases which advantageous that they can cover up the entire sealed off area in a
   quicker period. CO2 has an added advantage that it reacts endothermally consuming heat of 40.8 kcal/mole of




                                                                             ar
   CO2. CO2 is always better in quick replenishment of air, being heavier than air. Besides N2 creates congenial
   environment particularly when liquid N2 is used.




                                                                 um
5. Inertising the adjacent sealed off panels too.

                     Fig 2: Surface CO2 Storage tank establishment at Gdk 10A mine. SCCL.


                                                               hK
                                                         res
                                                 .Su



5.6.2. Long wall top coal caving-LTCC
                                          MD




The LTCC method is based on the 'Soutirage' Longwall caving method originally developed in the French coal
mining industry. Then Australia and China have started LTCC for thick seam mining. It basically involves an
additional AFC to transport top coal falls behind the Shields. When compared to other thick seam mining
techniques it ensures a high recovery rate and productivity. However, it is reported that 24 % of the coal reserve of
                                    or:




a panel operating by LTCC is left behind the face. But today, with the experience of support operators; the coal
recovery percentage is increasing year by year. As an equipment innovation, the more recent Chinese
developments have relocated the top coal draw points to the rear of the longwall supports, rather than bringing
                             th




coal through the roof canopy of the shield onto a conveyor within the shield structure. The Chinese equipment has
a pivoting supplementary goaf or tail canopy behind the support. With the rear AFC extended and the rear canopy
                          Au




lowered/retracted, caved top coal can be loaded onto the rear AFC. The Chinese industry had reported averages of
15,000 to 20,000 tpd from an LTCC face; up to 75% recovery of plus 8m thick seams using a 3m operating height
longwall and plus 5 MTPA face production. There are now well over 70 LTCC faces in China. A new semi-
automated 300m long LTCC face was installed at the Xinglongzhuang Colliery of the Yankuang Group, in
Shandong Province, in August, 2001, with production capacities of at least 7MTPA. The consistent cavability of
the top coal in an LTCC operation is crucial to its success. If the coal caves, but in too large a pieces it can cause
blockages and handling problems both feeding onto, and traveling along the rear conveyor. Of even greater
problem is if the coal hangs up, even only for a short time, such that it caves but beyond the reach of the rear
AFC. The main geotechnical components affecting coal cavability are uniaxial compressive strength (UCS);
cleat, bedding and other discontinuities; and vertical stress on the coal. Chinese experience is understood to be
that compressive strength ranging from 15 MPa to 25 MPa is well suited to good caving conditions. Horizontal
stress too has lot of influence.
6. Conclusion
India, being a third coal producer in the world and producing nearly 85% of coal from opencast mining presently.
The country has to exercise lot to get bulk output from underground mines. As the opencast mining have its own
implications due to depth and environment pollution, bulk production is possible by opening new coal blocks
suitable for sophisticated mechanisation and managing existing coal resources in underground mines to achieve
sustaining improvements. Country need to focus Longwall mining and ought to revive its earlier policy 1975
‘block diamond’ to introduce power supports Longwall in both CIL and SCCL in feasible blocks having good
quality of coal. If Longwall faces planned abundantly, it creates a base for competition in foreign manufacturers
and develops indigenous market too which would bring down cost of production. Different modules like mine
developer cum operator (MDO), Technology provider cum operator (TPO) and Risk/gain sharing can be worked
out with foreign participants.
Blasting gallery is typical mining method to extract thick seams presently. The method is moderately mechanised,
not much complicated and proved to be safer in operations in the last two decades in SCCL which is to be




                                                                           ar
practised elsewhere in the country with further safety and productivity inputs. The number of CM units, presently
5 in the country should be multifolded to develop and extract 3-4m high seams. Shortwall mining a variant of




                                                                um
Longwall to extract standing pillars presently practised in SECL mines and proposed in SCCL too, must be vastly
implemented to all the feasible mines. Highwall mining is a state art of mining by which the huge quantity of coal
is locked up in highwalls of opencast mines can be successfully mined out.

References/ Literatures
1.
2.
                                                              hK
      US Energy Information Administration – independent statistics and analysis 2009.
      Report on 4th Thermal power India 2010
3.    Report on “competition in India Energy sector” by The Energy and Resources Institute (TERI).
                                                       res
4.    Report on “The Expert committee on road map for coal sectors reforms” by Ministry of Coal. GOI. April
      2007
5.    Report of the working group on Coal & Lignite for formulation of Eleventh Five Year Plan (2007-12) by
      GOI, Ministry of Coal, Nov 2006.
                                                 .Su


6.    A Report on coal industry by “The Director, Coal Controller’s Organisation , Kolkatta.
7.    Application of Nitrogen as preventive and controlling surface fire – Indian context by NK. Mohalik, RVK
      singh, J. Pandey and VK singh. CMRI. 2005
8.    CMRI S&T report, study for early detection of the occurrences of spontaneous heating in the Blasting Gallery
                                         MD




      method and to evaluate suitable measures for prevention and control (CMRI-2002).
9.    Why Longwall in India has not Succeeded as in other Developing Country Like China by Prof A K Ghose,
      Fellow
10.   Why Longwall in India has not Succeeded as in other Developing Country Like China by S R Mehta, Non-
      member S Dasgupta, Non-member
                                    or:




11.   Longwall Mining in India – Experiences and expectations by Sri DLR Prasad (Director PP) and M.S.
      Venkataramaiah (AGM).
12.   Hamilton N, (1999) Single pass thick seam Longwall experience at West Wilsend Colliery, second
                             th




      International Underground coal Conference, UNSW, Sydney, Australia 15-18 June,1999 PP55-61.
13.    Hebblewhite BK &Cai YI(2004) evaluation of the application of the Long wall Top Coal Caving (LTCC)
      method in Australia, UNSW Mining Research Center, School of Mining Engineer, Sydney, Australia.
                          Au




14.   Peng SS. Chiang HS (1984) Longwall Mining, John Wiley & Sons Inc, PP 274-333.
15.   Singh R, & Singh TN(1999) Investigation into the behavior of a support system and Roof strata,
      Geotechnical and Geological Engineering 21-35. Netherlands.
16.   Walkers, Highwall evaluation World Coal Vol. 6 No. 10 Oct. 1997 PP 44-52.
17.   Analysis of Practical Ground Control issues in Highwall Mining by R. Karl Zipf Jr. & Suresh Bhatt. National
      Institute of Occupational Safety and Health Pittsburgh. Pennsylvania. USA.
18.   Superior Highwall Miners. LP. Beckley, West Virginea.        http:www.shm.net.2004
19.   Mining technology Inc, Ashland, Kentucky, http:www.addcarsystem.com. 2004
20.   Duncan-Fama, ME Shen B, Craig MS, Kelly M, Follington IL and Leisemann BE Layout and Design- Case
      study for Highwall Mining of coal. Proceedings International Congress of Rock Mechanics eds. G.Vouille
      and P. Berest 1999 vol 1 pp 265-268.
21.   High wall mining in Australia by left Sartaine. President, Mining Technologies. Inc.
22.   Report on introduction of Shortwall mining in SCCL by CODCO, China, 25 Sep. 2009.

Contenu connexe

Tendances

Underground metal mining methods
Underground metal mining methodsUnderground metal mining methods
Underground metal mining methodsSafdar Ali
 
Longwall Mining
Longwall MiningLongwall Mining
Longwall MiningVR M
 
Study of strata control in an ug coal mine being worked by continuous miner
Study of strata control in an ug coal mine being worked by continuous minerStudy of strata control in an ug coal mine being worked by continuous miner
Study of strata control in an ug coal mine being worked by continuous minerSafdar Ali
 
Computer applications in drilling and blasting
Computer applications in drilling and blastingComputer applications in drilling and blasting
Computer applications in drilling and blastingchemistrya40
 
Underground mining method natural support and caving
Underground mining method natural support and cavingUnderground mining method natural support and caving
Underground mining method natural support and cavingrazaullahwazir
 
HIGH WALL MINING at SCCL - A Case Study
HIGH WALL MINING at SCCL - A Case StudyHIGH WALL MINING at SCCL - A Case Study
HIGH WALL MINING at SCCL - A Case Studyknowledge stuff
 
Digitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine planDigitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine planSafdar Ali
 
Longwall - China & India
Longwall - China & IndiaLongwall - China & India
Longwall - China & IndiaVR M
 
"STAGES IN THE LIFE OF MINE"
"STAGES IN THE LIFE OF MINE""STAGES IN THE LIFE OF MINE"
"STAGES IN THE LIFE OF MINE"Anus KK
 
Longwall technology in india, SCCL
Longwall technology in india, SCCLLongwall technology in india, SCCL
Longwall technology in india, SCCLUlimella Siva Sankar
 

Tendances (20)

Underground metal mining methods
Underground metal mining methodsUnderground metal mining methods
Underground metal mining methods
 
Longwall Mining
Longwall MiningLongwall Mining
Longwall Mining
 
ventilation
ventilation ventilation
ventilation
 
Continuous miner
Continuous minerContinuous miner
Continuous miner
 
Study of strata control in an ug coal mine being worked by continuous miner
Study of strata control in an ug coal mine being worked by continuous minerStudy of strata control in an ug coal mine being worked by continuous miner
Study of strata control in an ug coal mine being worked by continuous miner
 
Roof supports in coal mines
Roof supports in coal minesRoof supports in coal mines
Roof supports in coal mines
 
Board & Pillar
Board & PillarBoard & Pillar
Board & Pillar
 
Highwall mining
Highwall miningHighwall mining
Highwall mining
 
Longwall mining[1]
Longwall mining[1]Longwall mining[1]
Longwall mining[1]
 
Computer applications in drilling and blasting
Computer applications in drilling and blastingComputer applications in drilling and blasting
Computer applications in drilling and blasting
 
Continuous miner
Continuous minerContinuous miner
Continuous miner
 
Underground mining method natural support and caving
Underground mining method natural support and cavingUnderground mining method natural support and caving
Underground mining method natural support and caving
 
Mine closure planning ppt_Atun
Mine closure planning ppt_AtunMine closure planning ppt_Atun
Mine closure planning ppt_Atun
 
Highwall mining
Highwall miningHighwall mining
Highwall mining
 
HIGH WALL MINING at SCCL - A Case Study
HIGH WALL MINING at SCCL - A Case StudyHIGH WALL MINING at SCCL - A Case Study
HIGH WALL MINING at SCCL - A Case Study
 
Digitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine planDigitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine plan
 
Longwall - China & India
Longwall - China & IndiaLongwall - China & India
Longwall - China & India
 
"STAGES IN THE LIFE OF MINE"
"STAGES IN THE LIFE OF MINE""STAGES IN THE LIFE OF MINE"
"STAGES IN THE LIFE OF MINE"
 
Longwall technology in india, SCCL
Longwall technology in india, SCCLLongwall technology in india, SCCL
Longwall technology in india, SCCL
 
Surface miner
Surface minerSurface miner
Surface miner
 

Similaire à Underground coal mining in india

Longwall exp india-expectations
Longwall exp india-expectationsLongwall exp india-expectations
Longwall exp india-expectationsVR M
 
Longwall - The road ahead
Longwall - The road aheadLongwall - The road ahead
Longwall - The road aheadVR M
 
Review of Indian coal sector
Review of Indian coal sectorReview of Indian coal sector
Review of Indian coal sectorManoj Jhawar
 
Coal bed methane with reference to india
Coal bed methane with reference to indiaCoal bed methane with reference to india
Coal bed methane with reference to indiaKiran Padman
 
Longwall technology in india, SCCL
Longwall technology in india, SCCLLongwall technology in india, SCCL
Longwall technology in india, SCCLUlimella Siva Sankar
 
Future Longwalls in India
Future Longwalls in IndiaFuture Longwalls in India
Future Longwalls in IndiaVR M
 
jha_indian_coal-sector aaaaaaaaaaaaaaaaaaaaaaaaaaa
jha_indian_coal-sector aaaaaaaaaaaaaaaaaaaaaaaaaaajha_indian_coal-sector aaaaaaaaaaaaaaaaaaaaaaaaaaa
jha_indian_coal-sector aaaaaaaaaaaaaaaaaaaaaaaaaaasaifuddinkhan34
 
Coal production and washing in india
Coal production and washing in india Coal production and washing in india
Coal production and washing in india INDRANEELA1
 
Impact of Thar Coal on Electricity Generation & Economic Growth of Pakistan
Impact of Thar Coal on Electricity Generation & Economic Growth of PakistanImpact of Thar Coal on Electricity Generation & Economic Growth of Pakistan
Impact of Thar Coal on Electricity Generation & Economic Growth of PakistanSandeep Kumar
 
Coal india limited_-_the_biggest_energy_provider_in_india
Coal india limited_-_the_biggest_energy_provider_in_indiaCoal india limited_-_the_biggest_energy_provider_in_india
Coal india limited_-_the_biggest_energy_provider_in_indiahapina
 
Presentation coal oil and gas scenario in the context of power sector-by-rake...
Presentation coal oil and gas scenario in the context of power sector-by-rake...Presentation coal oil and gas scenario in the context of power sector-by-rake...
Presentation coal oil and gas scenario in the context of power sector-by-rake...Prashantkarhade72
 
Future of the Indian Steel Industry
Future of the Indian Steel IndustryFuture of the Indian Steel Industry
Future of the Indian Steel IndustrySusmita Dasgupta
 
Coal mine Presentation (1).pptx
Coal mine Presentation (1).pptxCoal mine Presentation (1).pptx
Coal mine Presentation (1).pptxsonusingh643922
 
State of art of Mechanisation of Underground mines
State of art of Mechanisation of Underground minesState of art of Mechanisation of Underground mines
State of art of Mechanisation of Underground minesMD.Suresh Kumar
 
Roleoflogisticsandinfrastructureinthedevelopmentofcoalmarketinthecountry coal...
Roleoflogisticsandinfrastructureinthedevelopmentofcoalmarketinthecountry coal...Roleoflogisticsandinfrastructureinthedevelopmentofcoalmarketinthecountry coal...
Roleoflogisticsandinfrastructureinthedevelopmentofcoalmarketinthecountry coal...Bharat Nihalani
 

Similaire à Underground coal mining in india (20)

Longwall exp india-expectations
Longwall exp india-expectationsLongwall exp india-expectations
Longwall exp india-expectations
 
Longwall - The road ahead
Longwall - The road aheadLongwall - The road ahead
Longwall - The road ahead
 
Review of Indian coal sector
Review of Indian coal sectorReview of Indian coal sector
Review of Indian coal sector
 
Coal bed methane with reference to india
Coal bed methane with reference to indiaCoal bed methane with reference to india
Coal bed methane with reference to india
 
Longwall technology in india, SCCL
Longwall technology in india, SCCLLongwall technology in india, SCCL
Longwall technology in india, SCCL
 
Future Longwalls in India
Future Longwalls in IndiaFuture Longwalls in India
Future Longwalls in India
 
jha_indian_coal-sector aaaaaaaaaaaaaaaaaaaaaaaaaaa
jha_indian_coal-sector aaaaaaaaaaaaaaaaaaaaaaaaaaajha_indian_coal-sector aaaaaaaaaaaaaaaaaaaaaaaaaaa
jha_indian_coal-sector aaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Coal production and washing in india
Coal production and washing in india Coal production and washing in india
Coal production and washing in india
 
Coal - Demand & Supply
Coal - Demand & SupplyCoal - Demand & Supply
Coal - Demand & Supply
 
Impact of Thar Coal on Electricity Generation & Economic Growth of Pakistan
Impact of Thar Coal on Electricity Generation & Economic Growth of PakistanImpact of Thar Coal on Electricity Generation & Economic Growth of Pakistan
Impact of Thar Coal on Electricity Generation & Economic Growth of Pakistan
 
Coal india limited_-_the_biggest_energy_provider_in_india
Coal india limited_-_the_biggest_energy_provider_in_indiaCoal india limited_-_the_biggest_energy_provider_in_india
Coal india limited_-_the_biggest_energy_provider_in_india
 
pmicg-jp.pdf
pmicg-jp.pdfpmicg-jp.pdf
pmicg-jp.pdf
 
Presentation coal oil and gas scenario in the context of power sector-by-rake...
Presentation coal oil and gas scenario in the context of power sector-by-rake...Presentation coal oil and gas scenario in the context of power sector-by-rake...
Presentation coal oil and gas scenario in the context of power sector-by-rake...
 
Future of the Indian Steel Industry
Future of the Indian Steel IndustryFuture of the Indian Steel Industry
Future of the Indian Steel Industry
 
Coal mine Presentation (1).pptx
Coal mine Presentation (1).pptxCoal mine Presentation (1).pptx
Coal mine Presentation (1).pptx
 
Thar coal hurdle&solution
Thar coal hurdle&solutionThar coal hurdle&solution
Thar coal hurdle&solution
 
State of art of Mechanisation of Underground mines
State of art of Mechanisation of Underground minesState of art of Mechanisation of Underground mines
State of art of Mechanisation of Underground mines
 
Roleoflogisticsandinfrastructureinthedevelopmentofcoalmarketinthecountry coal...
Roleoflogisticsandinfrastructureinthedevelopmentofcoalmarketinthecountry coal...Roleoflogisticsandinfrastructureinthedevelopmentofcoalmarketinthecountry coal...
Roleoflogisticsandinfrastructureinthedevelopmentofcoalmarketinthecountry coal...
 
Managment ppt
Managment pptManagment ppt
Managment ppt
 
Imperatives For Iron Ore Exports
Imperatives For Iron Ore ExportsImperatives For Iron Ore Exports
Imperatives For Iron Ore Exports
 

Plus de MD.Suresh Kumar

Tech paper guttering-case study
Tech paper guttering-case studyTech paper guttering-case study
Tech paper guttering-case studyMD.Suresh Kumar
 
Experience of working p8
Experience of working p8Experience of working p8
Experience of working p8MD.Suresh Kumar
 
1.5MT Longwall faces in SCCL-Few planning issues
1.5MT Longwall faces in SCCL-Few planning issues1.5MT Longwall faces in SCCL-Few planning issues
1.5MT Longwall faces in SCCL-Few planning issuesMD.Suresh Kumar
 
Ground control continues to be a crucial issue in Indian coal mines ..What we...
Ground control continues to be a crucial issue in Indian coal mines ..What we...Ground control continues to be a crucial issue in Indian coal mines ..What we...
Ground control continues to be a crucial issue in Indian coal mines ..What we...MD.Suresh Kumar
 
Experience of working Longwall at shallow depth-Strats mangement issues by MD...
Experience of working Longwall at shallow depth-Strats mangement issues by MD...Experience of working Longwall at shallow depth-Strats mangement issues by MD...
Experience of working Longwall at shallow depth-Strats mangement issues by MD...MD.Suresh Kumar
 
Managing Existing mineral resources in Indian coal mines-Technological option...
Managing Existing mineral resources in Indian coal mines-Technological option...Managing Existing mineral resources in Indian coal mines-Technological option...
Managing Existing mineral resources in Indian coal mines-Technological option...MD.Suresh Kumar
 
Impact of coal mining on environment and ecology with a special note on Envir...
Impact of coal mining on environment and ecology with a special note on Envir...Impact of coal mining on environment and ecology with a special note on Envir...
Impact of coal mining on environment and ecology with a special note on Envir...MD.Suresh Kumar
 
Effect of Environmental conditions in Production, Productivity, Health and Sa...
Effect of Environmental conditions in Production, Productivity, Health and Sa...Effect of Environmental conditions in Production, Productivity, Health and Sa...
Effect of Environmental conditions in Production, Productivity, Health and Sa...MD.Suresh Kumar
 
Preventing spantaneous combustion in Blasting Gallery panels by MD.SURESH KUMAR
Preventing spantaneous combustion in Blasting Gallery panels by MD.SURESH KUMARPreventing spantaneous combustion in Blasting Gallery panels by MD.SURESH KUMAR
Preventing spantaneous combustion in Blasting Gallery panels by MD.SURESH KUMARMD.Suresh Kumar
 
Opencast Mining below HFL of Godavari river bed-An experience of Medipally OC...
Opencast Mining below HFL of Godavari river bed-An experience of Medipally OC...Opencast Mining below HFL of Godavari river bed-An experience of Medipally OC...
Opencast Mining below HFL of Godavari river bed-An experience of Medipally OC...MD.Suresh Kumar
 
Underground mine Ventilation improvement by re organisation
Underground mine Ventilation improvement by re organisationUnderground mine Ventilation improvement by re organisation
Underground mine Ventilation improvement by re organisationMD.Suresh Kumar
 
An experience of Loading pattern on Power supports with Sand stone roof in SCCL
An experience of Loading pattern on Power supports with Sand stone roof in SCCLAn experience of Loading pattern on Power supports with Sand stone roof in SCCL
An experience of Loading pattern on Power supports with Sand stone roof in SCCLMD.Suresh Kumar
 
Longwall mining at shallow depth
Longwall mining at shallow depthLongwall mining at shallow depth
Longwall mining at shallow depthMD.Suresh Kumar
 
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...MD.Suresh Kumar
 
Dynamic loading in the longwall face
Dynamic loading in the longwall faceDynamic loading in the longwall face
Dynamic loading in the longwall faceMD.Suresh Kumar
 

Plus de MD.Suresh Kumar (15)

Tech paper guttering-case study
Tech paper guttering-case studyTech paper guttering-case study
Tech paper guttering-case study
 
Experience of working p8
Experience of working p8Experience of working p8
Experience of working p8
 
1.5MT Longwall faces in SCCL-Few planning issues
1.5MT Longwall faces in SCCL-Few planning issues1.5MT Longwall faces in SCCL-Few planning issues
1.5MT Longwall faces in SCCL-Few planning issues
 
Ground control continues to be a crucial issue in Indian coal mines ..What we...
Ground control continues to be a crucial issue in Indian coal mines ..What we...Ground control continues to be a crucial issue in Indian coal mines ..What we...
Ground control continues to be a crucial issue in Indian coal mines ..What we...
 
Experience of working Longwall at shallow depth-Strats mangement issues by MD...
Experience of working Longwall at shallow depth-Strats mangement issues by MD...Experience of working Longwall at shallow depth-Strats mangement issues by MD...
Experience of working Longwall at shallow depth-Strats mangement issues by MD...
 
Managing Existing mineral resources in Indian coal mines-Technological option...
Managing Existing mineral resources in Indian coal mines-Technological option...Managing Existing mineral resources in Indian coal mines-Technological option...
Managing Existing mineral resources in Indian coal mines-Technological option...
 
Impact of coal mining on environment and ecology with a special note on Envir...
Impact of coal mining on environment and ecology with a special note on Envir...Impact of coal mining on environment and ecology with a special note on Envir...
Impact of coal mining on environment and ecology with a special note on Envir...
 
Effect of Environmental conditions in Production, Productivity, Health and Sa...
Effect of Environmental conditions in Production, Productivity, Health and Sa...Effect of Environmental conditions in Production, Productivity, Health and Sa...
Effect of Environmental conditions in Production, Productivity, Health and Sa...
 
Preventing spantaneous combustion in Blasting Gallery panels by MD.SURESH KUMAR
Preventing spantaneous combustion in Blasting Gallery panels by MD.SURESH KUMARPreventing spantaneous combustion in Blasting Gallery panels by MD.SURESH KUMAR
Preventing spantaneous combustion in Blasting Gallery panels by MD.SURESH KUMAR
 
Opencast Mining below HFL of Godavari river bed-An experience of Medipally OC...
Opencast Mining below HFL of Godavari river bed-An experience of Medipally OC...Opencast Mining below HFL of Godavari river bed-An experience of Medipally OC...
Opencast Mining below HFL of Godavari river bed-An experience of Medipally OC...
 
Underground mine Ventilation improvement by re organisation
Underground mine Ventilation improvement by re organisationUnderground mine Ventilation improvement by re organisation
Underground mine Ventilation improvement by re organisation
 
An experience of Loading pattern on Power supports with Sand stone roof in SCCL
An experience of Loading pattern on Power supports with Sand stone roof in SCCLAn experience of Loading pattern on Power supports with Sand stone roof in SCCL
An experience of Loading pattern on Power supports with Sand stone roof in SCCL
 
Longwall mining at shallow depth
Longwall mining at shallow depthLongwall mining at shallow depth
Longwall mining at shallow depth
 
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
 
Dynamic loading in the longwall face
Dynamic loading in the longwall faceDynamic loading in the longwall face
Dynamic loading in the longwall face
 

Underground coal mining in india

  • 1. Underground coal mining in India – Technological option and challenges ahead MD. Suresh Kumar Abstract W orld coal institute estimates coal is the major contributor for energy generation to the tune of 60% and remaining from gas, diesel, nuclear, wind and hydel. In India, 75% coal is consumed by power sectors. The demand tends to outstrip domestic supply. The power sectors continue to report generation losses ar from coal shortages. The pace of power capacity additions has hardly been commensurate with the need. Less than 30 GW of the planned 40 GW for 2002-07 could have been materialized as reported by The Energy and Research Institute of India (TERI). The Government’s recent effort to build several 4000 MW power plants under um ultra mega power schemes would require coal blocks with reserves of 600-700MT. The projected coal demand for the year 2024-25 for power, steel, cement and others nearly 1147 MT which is doubled the existing coal production. Hence the present 6% growth in coal production would not be sufficient. hK The country has nearly 95 BT proven and 55 BT extractable coal reserves. The coal industry in the country is governed by CIL 80% with 8 subsidiaries, SCCL 9% and 5% captive mines by others. As per the coal mines amendment bill, Government of India has identified captive coal blocks and nearly 291 blocks were allotted tor Private and Public sectors to augment the coal production. But this is only transitory solution for the deficit. res Because, most of the coal production comes from open pit mining and it nearly contributing over 84% of absolute production in the country. Open pit mining has its own implications due to depth and environment pollution whereas billion tonnes of coal locked up in underground standing pillars and in thick seams requiring suitable technology. This not only shows lack of resource management but leaves a great technogical void to compensate .Su opencast coal production with proper exploitation of existing underground resources. Bulk production of coal at faster rate from underground, particularly at depth is possible from Long wall which is proven technology worldwide. Besides, nearly 40% of the proven reserves are in thick seams posing technological MD challenge for long time. The conventional underground methods like pillar extraction and multi stage mining are only proven technologies so far in the country. The percentage of extraction in these methods is well known to be less than 40%. The other mining methods like Wide stall, Long wall with increased height of extraction and Top coal caving are having their own draw backs. The Blasting gallery method of winning thick seams introduced in SCCL in 1989, witnessed to be great success. On the other hand, the coal pillars statued in underground both in or: CIL and SCCL due to various complex mining conditions need to be rightly exploited to the present country’s coal requirement or otherwise in-justification to the nation’s wealth. CIL has introduced short wall mining, a variant of Long wall mining to extract underground pillars. SCCL has identified few properties for short wall to th be introduced in near future. High wall mining is the state of art of mining, gifted to the mining community world wide to survive the open pit mines suffering from uneconomical stripping ratio. It conglomerates both Au underground and open pit technologies being practiced in US, Australia etc., In India CIL and SCCL have identified coal blocks to introduce this method in coming years. This paper deals with the tale of success and failures of mining methods practiced so far in the country and explores the possibility of sustainable winning of underground resources with the viable technological option and the challenges ahead. Additional Manager, Underground Mech Cell, SCCL
  • 2. 1. Introduction In India, the Coal is one of the primary sources of energy, accounting for about 67% of the total energy consumption in the country. The most of the coal production comes from open pit mines. Open pit mining has its own implications due to depth and environment pollution. Therefore, a proper underground resource management needs to be explored and implemented at this juncture to bridge the technological void. Proper planning and methodological adoption for existing underground resources only would do. The study of history of Long wall method in the country has not shown attractive results, but introduction of new era Long walls would break the earlier records. Enormous quantity of coal is locked up in underground standing pillars in the country. Extraction of these pillars by Short wall method and thick seam mining are the area where the Indian mining community has to have a focus to liquidate the existing underground standing pillars. Besides, developments in exploration, detailed geo technical studies, ventilation solutions for deeper mines, hazard mapping and support techniques for ar complex strata conditions are the pre-requisites for sustainable exploitation of existing coal resources in Indian mines. um 2. Resources in Indian coal mines Being a third coal producer in the world, India has an age old history in its coal mining sector. Coal mining in hK India dates back to the 18th century, however the regulatory framework for this industry was conceived in 1923. In 1972-73, the Indian government nationalised the coal industry, primarily to develop the sector, since it was considered of strategic importance for rapid industrial development. India has the fourth largest reserves of coal in the world (approx. 197 billion tonnes.). Coal India Ltd (CIL) was incorporated as a holding company for eight res coal producing subsidiaries and SCCL is another major coal producing company in southern part of the country. Coal deposits in India occur mostly in thick seams and at shallow depths. Non-coking coal reserves aggregate 172.1 billion tonnes (85 per cent) while coking coal reserves are 29.8 billion. Indian coal has high ash content (15- 45%) and low calorific value. Coal in India occurs in two important types, Gondwana and Tertiary. Gondwana .Su coal field occurs with sedimentary rock of lower Gondwana age which contributes 98% and rest is Tertiary. Gondwana coal field is distributed in the valleys of Domodar, the Son, the Mahanadi, the Godavari and Wardha whereas the tertiary coal spreaded in extra peninsular areas. When compared to coal, the lignite reserves are relatively modest. MD 3. A look into future India's coal demand is expected to increase manifold within the next 5 to 10 years due to the completion of on- going coa;-based power projects, and demand from metallurgical and other industries. Demand for coal has been or: rising at an annual rate of 6 per cent since 1992-93 and CIL and its subsidiaries will be unable to meet the projected demand alone. The investment needed to bridge the gap of 400 million tonnes, between the level of production in the public sector (290 million tonnes in 1995-96) and the projected demand of 690 million tonnes th (2009-10) is estimated to be US$ 18 billion. The public sector corporations are expected to increase their production by about 250 million tonnes by 2009-10, subject to their making an additional investment of US$ 8- Au 10 billion. The balance requirement of 150 million tonnes will have to be met by imports in the short run and by new investments in the long run. With the advent economic reforms, government relaxed controls on pricing and distribution and a new coal policy permits private sector participation in commercial coal mining. Government of India has identified captive coal blocks and nearly 291 blocks were allotted to private and public sectors to augment the coal production. But this is only transitory solution for the deficit. Hence a real challenge lies on how the existing and future underground resources are managed to produce bulk coal production. 4. Underground coal mining in India Underground mining in India mainly, the room-and-pillar method with manual loading, accounts for about 20% of coal production. This is major limiting factor in 80s. The semi-mechanised methods using SDLs and LHDs have becoming populous only in the last decade. Longwall retreat with caving introduced three decades ago, has recorded few success story due to the limitations in the method and its application in Indian conditions.
  • 3. 4.1. Conventional mining 4.1.1. Board and pillar Board and pillar mining is an age old mining system in the country. The development and liquidation of pillars were manually done with basket loading onto tubs which was abundantly existing still last decade. Scraper loaders were introduced in late 1960’s which were mounted on rails and load coal onto tubs. But it had little scope due to its limitations. Steel bolts such as point anchor bolts and wedge bolts were introduced in place of wooden supports increased safety and productivity. Belt conveyors replaced series of haulers and hectic tramming circuits in underground for coal transport in 80’s. 4.1.2. Wide stall method Under difficult geo mining conditions, where caving is restricted to protect surface features or in such conditions where the roof rocks difficult to cave in, the normal splitting of pillars leaving wide stook was tried but it helped few. Formation of stook by optimizing recovery causes reduction of strength of natural support. In such cases, the percentage of extraction was as low as 30%. An attempt to optimise the extraction in the seams 3m plus by ar heightening has weakened the pillar strength further. Under these circumstances, the wide stall method has given better results. Matching of gallery size with the strength of immediate roof and strength improvement of the um natural support by increasing width/height ratio of pillars are the two basic constituents of this method. The strength and size of the pillar calculated basing load expected on pillars with factor of safety atleast 2. The effective bearing capacity of a pillar is comparatively more than a number of stook of the equivalent area. On the basis of extensive laboratory investigations on diffent simulated models, idea of wide stall mining was conceived hK and for the first time implemented in East Bhuggatdih Colliery of Jharia coal field. Later, SCCL adopted this method in Gdk-8A incline after a major roof fall accident. However, the percentage of coal recovery falls below 40% and the recovery is further increased in thick seams by taking out floor coal in the mines like Gdk-8A incline. res 4.1.3. Yield pillar Coal mine bursts and sudden roof collapse are not uncommon events in most Indian underground mines under stiff roof condition. However when a burst occurs, it almost results in a major hazard. Some times, the strength .Su and geometry of pillar and the rock load don’t match and may result in delayed caving, increased goaf exposure finally its sudden failure. Besides there are number of other fundamental factors that influence such occurrence. Excess rock load causes violent failures of ribs, roof or floor. In such condition pillars shall not be further strengthened to prevent caving or not be too weak to stimulate premature collapse. Over many years of dealing with this hazard, specialised requirements for layouts and novel extraction sequences have been developed on a MD site specific basis to safely mine coal. There have been many engineered prevention controls proposed to mitigate the devastating effects of these dynamic and violent failures. While none of these considered as “stand alone” design, the technique of yield of pillar has come in the mind of mining engineers. A yield pillar is a pillar which is critically-sized to withstand the abutment loads and to yield nonviolently or yield before the roof and floor sustain or: permanent damage. In India, sccl has introduced this method in one of its mines VK-7 incline to extract pillars safely with Joy miner where the sand stone roof is reasonably hard to fall. The distressed ground conditions due to hectic depillaring done in the seam and Longwall caving in the upper seam combined with strata unconformity in th the vicinity of faults resulting in sudden collapse of roof incurring huge loss of life and machinery in 2006 where this method is found more useful. However the percentage of coal recovery is not attractive due to lot of coal is left inside the goaf in the form of pillars and stooks. Au 4.2. Long wall mining 4.2.1. A brief review of Longwall mining in India As a global phenomenon, the pace of technological change had been especially rapid in the second half of the last century, the mechanization of unit operations led to the development of Longwall technology on the concept of mass production in coal mining industry. It was also aimed at reducing the drudgery, monotony and dangers of work persons engaged in underground mining operations. The development of mass production technology including Longwall equipment, continuous miners, ploughs and shearers have been accompanied by a series of incremental and innovative developments in roof supporting. India also as a general rule followed the world trend and in 1975. ‘Project Black Diamond’ envisaged introduction of 130 powered supports Longwall (PSLW) faces by the year 2000. Initially, the first fully mechanized self- advancing PSLW face was introduced in Moonidih mine in Jharia Coalfield in 1978. Subsequently more mines were planned with PSLW in the eighties, namely, East Katras ( BCCL), Seetalpur, Dhemo-Main, Jhanjra, Khottadih (all in ECL ),Patharkhera (WCL) and Churcha (SECL), and first long wall in SCCL introduced at GDK 7 incline in 1983 at also a few other mines in
  • 4. Company. In the process about 30 PSLW sets had been imported from different sources in different countries like, UK, Poland, Russia, Germany, France and China. Barring a few exceptions, where the powered support Longwall faces gained moderate success. Most of the Longwall faces were far from the desired level of production and productivity on sustainable basis. Further large scale introduction of Longwall technology received severe setbacks due to its successive failures at Churcha (SECL) and Khottadih (ECL) mines. At present, Longwall mining accounts for a meager production of about 4% of the total underground production 4.2.2. Factors affecting the Longwall performance in Indian mines 4.2.2.1. No Policy for Introduction of Mass-Production Technology Even after nationalization, the Govt of India was not firm on policy for mass production technology, like Longwall and continuous miners. Because of that no private/government company has come forward for manufacture of underground mining equipments for mass production technology. 4.2.2.2. Standardisatin of Longwall equipment ar There was no standardization of Longwall equipment in the country. As such, different Longwall equipment purchased in India are of different specifications. As a result, no indigenous manufacturers were motivated to um manufacture small demand of Longwall spare parts. Delay in procurement of spares affected production from Longwall panels. As the number of operating faces are less, the suppliers were not able to provide either manufacturing facilities or spares depot within India. 4.2.2.3. Wrong place of Application hK The study of few cases in the country revealed that the Longwall technology was introduced in extremely critical conditions such as difficult geo-mining conditions, steep and thin seams, at deeper horizons with very high ambient temperature, Degree-III gassiness and mine where coal evacuation system was extremely circuitous with a series of conveyors. These factors proved a serious bottleneck in improving productivity from Longwall faces at its very budding stage and gave a wrong signal as if the techno-logy is not suitable in Indian mining conditions. res 4.2.2.4. Face geometry Longwall face width was designed from 60m-165m, the length varying between 500m to 1.2Km and operated in depth 30m to 350m so far. In these conditions, very few mines recorded good results such as VK-7 and Gdk-10A .Su mines of SCCL with regard to consistency. Non-availability of longer panels due to geological disturbances, or due to surface features to be protected and presence of standing pillars in an upper seam yet to be extracted, resulted in frequent shifting of equipment and increase in non-productive work and time. Whereas the coal seams extremely favoured Chinese, Australian and US mining industries to have longer and wider panels. 4.2.2.5. Lack of Infrastructure Facility MD Introduction of Longwalls in already existing mines which were not having sufficient infrastructure to match the desired level of production resulting in derating the projects. Provision of matching infrastructure was either delayed or never came up in most of the cases. 4.2.2.6. Advanced geo-technical studies and R&D facility or: In most of the cases, inadequate geological information and geo technical knowledge due weak borehole density to become major chunk for failure which is often led to wrong planning including those wrong selection of power roof supports, orientation of panels with respect to horizontal stress direction. Further it led to too many geological surprises while working the face. The weak geo-informations resulted in wrong projections of faults, th thinning of seams, intrusions and variation in strength of immediate roof rocks. The poor knowledge of hydro- geology drawn the faces and continuous water percolation in the strata led to strata control problems in many Au incidents. The most glaring example in this regard is failure of powered supports at Churcha (SECL) and Khottadih (ECL). In both the cases the supports collapsed and failed to withstand the load exerted by superincumbent strata during periodic weighting due to underrated supports. These two incidents gave severe jolt to the programme of large scale introduction of Longwall technology in other Indian mines. 4.2.2.7. Technical lapses There used to be some severe technical lapses pertaining to face operations that the development with older version Road headers like AM-50s and Doscos are not matching with Longwall retreat rate, LW units were introduced inferior quality top and upper seams which hugely affected economics, Lack of man riding facilities in underground leads workmen reaching to face getting delayed and interrupted face operation too and the conventional face transfer system including equipment withdrawal from one face, transporting to another face and installation in the new face consumed 3 months to 6months.
  • 5. 4.3. Extracting thick seams 4.3.1. Blasting Gallery The Blasting gallery method of thick seam extraction was introduced in SCCL during 1989 with the technical collaboration of Carbonages de France (CdF), France. Based on its success, the method was introduced in five mines of the company in VK-7, 21incline, Gdk 10incline, Gdk 8 incline and Gdk 11A in phases in the last two decades. Over this period, the Blasting gallery method is established as an economically viable with a source for bulk production. Evidently, this method is so proved to be safer due to its inherent mechanisation of drilling, loading, transporting and supporting. The bottom section of virgin coal seam is developed in series of headings at 22-25 interval called ‘Rooms’ and connected 80-120m apart to form sub-panels. Such set of sub-panels ranging from 4 -7 formed a Blasting Gallery panel. A first roof blast called ‘potato blast’ is done upto to the full seam height at the in-bye end which creates free face for further blast holes. Thus the rooms are retreated continuing the blasting upto full seam height following a diagonal line. A mobile electric drill drills shotholes all around the room, at an angle inclined towards goaf upto full seam height in a ‘Ring pattern’. A ring contains 22-35 holes as ar per the requirements. The different operations like drilling, blasting, supporting and coal production would go simultaneously in the different rooms. Therefore an average production of 1000Te could be achieved from a um panel. Whereas the percentage of coal recovery would be higher than the any other methods exist presently. In the later stage, it was focused to adopt the same methodology to extract coal from developed bord and pillars. Panels were formed by constructing isolation stoppings around and the Rooms were formed by splitting the existing pillars. As the mines having intensive development in standing pillars, this method fed right stuff to the miners wherever technically applicable. 4.3.2. Multi-stage mining and Stowing hK Before the Blasting gallery was landed in Indian soil, thick seams in the country mostly were developed in two or three lifts depending upon the seam thickness leaving minimum of 3m parting between the lifts as per the res statutory requirement. Such seams were developed with room and pillars superimposed. Conceptually, this has given confidence amongst the mining engineers with regard to percentage of recovery of coal seams. Later the bottom section coal was extracted with stowing then the top section coal was removed with or without leaving .Su partition. 4.4. Introduction of SDLs and LHDs SDLs and LHDs were introduced only in the last decade in the country. It simply replaced manual loading in the conventional face. A review of accidents where the face workmen involved has thrown serious thoughts of MD mechanisation of manual loading. It was taken almost a decade to eradicate manual loading in phased manner. Initially Eimmco Elecon SDLs and 811 LHDs were introduced in the mines without much concentration on application techniques in relation to the mining conditions. Later, on care full studies with field experience correct application was chosen with respect to seam height, gradient, floor conditions and water percolation. Further or: improvement was achieved by introducing Simplex SDLs and higher capacity E-912LHDs in the later part of the decade. However, the introduction of this intermediate technology not only replaced manual mining but reduced human drudgery and improved safety & productivity. th 4.5. Continuous miners As the cost of production and accidents trend are on higher side in mines operated with manual loading led to the Au thought of introduction of CM technology. The first fully mechanised room and pillar system in India, using continuous miner technology, started its operations in May 2002 at Chirimiri Anjun Hill Mine, South Eastern Coalfields Limited (SECL) on risk/gain approach.. The complete system, supplied by Joy Mining Machinery Ltd, included a 12CM15 continuous miner, two shuttle cars, a feeder breaker, a mobile roof bolting machine and electrical distribution system. Since start up, the system has averaged over 40,000 tonnes per month on the development of a five entry room and pillar system and has now achieved over 50,000 tonnes in a month on de- pillaring. To date the de-pillaring operations have been very successful providing the only approved method of mechanised de-pillaring in India. In the present technological transformation, with considerable awareness and training it is possible to produce 4 to 6 LTPA in Indian mining condition. Presently miners belong to JOY and DBT are working in Anjana Hill Mine, Chirimiri (SECL) commissioned in May 2002, Thandasi Mine (WCL) commissioned in June 2003, VK No: 7 Incline, Kothagudem (SCCL) commissioned in Aug, 2006. Jhangra Under ground Mine (ECL) commissioned in June, 2007 and GDK 11A Incline (SCCL) commissioned in Dec, 2008.
  • 6. 4.6. Short wall mining The shortwall mining technique is similar to longwall mining but with shorter face lengths, ranging between 40 and 90 m, with the aim of controlling the caving nature of the overlying upper strata, the load on support and the overall operation of the supports at the face. Though the concept of shortwall initially aimed at this, Chinese mines have introduced this technology to mine out standing pillars. The similar equipment used in Longwall is utilised here too and open galleries ahead the face are well supported with longer roof bolts and cable bolts. Additionally, breaker line supports which are of normal power supports set in the open galleries with remote operation. Self advancing, crawler mounted supports are also used as breaker line supports. As per Indo-Chinese agreement, the first shortwall was introduced at Balarampur of SECL where three such short panels have been successfully completed and SCCL too planned to introduce shortwall in one of its mine RK-NT. The success of this method in this two coal companies may lead the entire mining industry in the country to a newer thinking to liquidate its vast standing on pillars property. ar 5. Road map to Indian coal mines for sustainable exploitation 5.1. Exploration and detailed geo-technical studies um Recently, SCCL has entered into MoU with CSIRO, Australia for implementation of first ever high capacity Longwall technology where the detailed studies have been conducted which broadly includes increase in borehole density to 20 / Sq Km, study of overlying strata behavior upto the height of 100 to 150m over the Longwall panels. The existing practice of study levels depends on the requirements of the projects. Complete and detailed hK studies of entire block are not done before implementing the new projects like in US and Australian practice. Besides, in the most of cases the mining projections are made depending on the existing geological data. As far as practicable, coring needs to be done for each borehole, preserved in core library for analysis and photographed too. The data from non cored boreholes can be generated with Geo–physical logging (neutron, gamma, resistivity res and density. In-situ stress and permeability measurements must be conducted in the boreholes equally spreaded over the proposed panels. The permeability tests shall be conducted in different depth horizons to have most representing result ranging from barren measure rock upto geological domain rocks including inter burden. Apart from the above, PMP tests, Caving index, In-situ strength of coal, Piezometric studies core profiler and micro .Su logging shall be done to formulate most realistic mine panning. Minex modeling is the one software launched in India and found its success to delineate the coal/ore structure. 5.2. Making Longwall Technology successful MD 5.2.1. Things to be learned from China China introduced Longwall mining in the late seventies and early eighties as in India, but within 20 years it has not only emerged as the world leader in coal production, but has established itself as the largest user of Longwall technology in underground mines and has created for itself an international market for export of the technology, expertise and equipment. From the very beginning, it adopted wholesome approach for large scale Longwall or: mechanisation in their UG mines. Their approach was very methodical and it took into account their own social and economical conditions. Instead of instantaneously jumping into hi-tech mechanisation only in some isolated mines, they introduced the technology stage by stage with incremental development. China has developed tailor th made equipments suitable to their conditions. For this they have first generated skilled workforce of Engineers, operators, designers, research institute personnel and manufactures. They gave greater emphasis on applied R & D for product design and quality development. China has developed huge infrastructure at unit levels as well as Au central levels. It has constructed a number of new highly productive and efficient mines with different capacities based on seam/geological conditions by identifying suitable coal blocks in advance. It has improved its metallurgy for indigenous manufacture of powered supports with higher support resistance, more powerful shearer, AFC and belt conveyor and started achieving 6-10mt coal from a Longwall face per annum. 5.2.2. Suitable blocks for wide and Lengthy Longwall faces It is extremely important to choose the proper place of application of this mechanized Longwall technology, which is capital intensive and involves a lot of time and manpower in installation, salvaging and shifting of equipment. As the existing underground mines in CIL and SCCL have got limited scope for this technology as for as the infrastructure is concerned. Hence, suitable virgin blocks can be sought for. As far as practicable, no other technology shall be combined with Longwall. The expansion of existing mines is possible but only beyond 300m depth where it is required to explore success of Longwall face at deeper horizons. The existing facilities like man riding, ventilation and coal conveyance can be utilised during development till permanent set is made. The
  • 7. minimum proved resources should be 100Mte so that the projects can be sustained for 25-30 years with one particular set up or infrastructure. Today the world trend is to provide longer and wider panels to minimize the number of shifting. 5.2.3. Proper equipment for specific geo-mining conditions It is required to do advanced studies, numerical modeling and preparation of adequate of data related to the specific geo-mining conditions of the mine, to make Longwall equipment tailor made to the site specific geo- mining conditions. More over, one set of equipment can be used with only minimum modifications. More particularly, the power supports which are available in varieties in the market shall be carefully selected with respect to their load resistance, load expected from overlying strata and seam gradient. 5.2.4. Indigenous capacity of equipment manufacturing at Low cost The private parties entering into Longwall equipment manufacturing and its spares is mearly nightmare except ar finger count. But it may take another 10 years to develop the vendors to get technical expertise. With the mixed result of Longwalls in the last 30 years, the Economy of the projects did not bring any fruitful results mainly due um to the landing cost of the equipment. Two important reasons can be attributed that the number of operating faces and equipment cost. Developing country like India was not in a position to bare any economic fall outs due to faces failed to produce to its rated capacity. Success not to come easily on its way, but out of sustained and hard effort. Sufficient effort was put all these days and Longwalls in the country have produced a huge number of hK experienced mining engineers and experts. But the ultimate requirement is, to reduce equipment cost and operating cost with self manufactured indigenous technology. 5.2.5. Both CIL and SCCL have to launch LW technology The indigenous technological expertise comes only if much more Longwalls, atleast 30-50nos with range of face res lengths are both in SCCL and CIL having at least 25 years of project life. The most of the coal seams in the northern part of the country occurred at lower depth with stripping ratio as low as 0.5 which neither posed any coal scarcity nor warranted underground large scale mechanisation in the last 30 years. But the situation is .Su upturned now and it is bound to makeup the coal demand from underground mines. The Central Government and its planning commission assessed the ground situation and taken proactive decision to decentralise the mining by opened up nearly 300 blocks given to private parties for capital coal utilisation. Experts anticipate only mixed results out of this. A real improvement and next generation mining can be achieved only if CIL which is a larger mining operator in the country comes forward to do Longwalls for mass underground production. MD 5.2.6. Introduction of High capacity Longwall for the first time in the country-sccl Having understood the need of sustained underground mining, The SCCL has timely planned to introduce a latest version Longwall face on par with USA, Australia and Chinese mines. Around $160 million worth first ever high or: capacity Longwall Project of which the equipment is supplied by BUCYRUS. The production capacity would be 3Mtpa with panels ranging from 1500 to 2500 m length, 250m wide faces, Depth of working upto 600 m, Seam inclination 1 in 5 and height of extraction is 3m. The supports are 1152 Te 2 legged DTDA shields with 120/104 tpsm support density, the shearer type-EL3000 with all electrical motors includes 2x860kw cutting motors, th 3000tph cutting speed and 0.85m web, 3x855kw twin inboard AFC, 400kw BSL, 1600mm 3200tph gate belt with other high capacity back up arrangements. For the first time in coal mines in the country a deep shaft 468m is Au being sunk for ventilation. More advanced from conventional like shifting of power packs and electricals with monorail system and FSVs for transport of supports, men and materials. The entire country is looking forward to see its implementation and success of this project which may give solution for implementation several high capacity Longwalls in future. 5.2.7. Bolter miners for Roadway development The one of the reasons that the Longwalls in the country is barking down is the panel’s development rates. The low capacity Alpine miners and Doscos are used for panel development whereas machines were modified to their needs in US, Australia and in China. High powered cutter motors, robust cutter head and traction system in latest version machines improves machine stability, ability to work in seam gradients upto 10-150 and faster drivage. The on-board bolting facility further improves machine utility hours and proved the development rate 400-500 per month. However, Continuous miners had been dominant in development with twin gate roadways two decades ago. Miners with on-board bolting facility and Bolter miners have further boosted the rate of drivages to cop-up
  • 8. much sophisticated 6-10 Mte producing Longwall faces. Thus bulk output from Longwall face can not be achieved without bolting facilitated miners or Bolter miners. There are verities of machines available in the market to choose the best fit to seam and mining conditions and economy. 5.3. Liquidation of existing standing pillars 5.3.1. More short walls in future Reintroduction of Long walls is emerging with new strength and high expectations both in CIL and SCCL. Hence, introduction of more shortwalls may be delayed as it needs combination of older equipment and few new additions. As such, shortwall sets, if purchased, may not justify economics with low range of production. During first phase of its introduction, it is possible to put them in existing or older Longwall facilitated mines having enough infrastructures. More new faces with infrastructure is possible in future with indigenous equipment. 5.3.2. Continuous miners ar Liquidation of standing pillars with intermediate technologies like SDLs and LHDs with caving or stowing have got its limitations due to scarcity of timber and sand near the mining areas. Face drilling for blasting and bolting is a big concern as done mostly manually, consumes lot of time and reduces machine utilization. Mechanised drill um machines like pneumatic drills, hydraulic drills and UDMs were introduced but did not prove as triumphant matching machine. This is the reason, they produce just above the break even production and in many mines they produce less than that. Venturing for bulk production is unattainable with these machines even with more numbers. The only solution left with is miners. The present miners in India, except Chirimiri and Tansi, reported hK average performance. More experience, expertise and planning would make turn around. There is range of product available in the market to suit to the mining conditions. But the concern is landing cost of equipment imported. However it is not far from the reach that indigenous miners at low price may be dominate the market in the coming years. res 5.4. High wall mining for deep seated OC property Highwall mining is extracting coal from the face in a seam exposed in the final bench of opencast mine, after reaching to its economical stripping ratio. The extent of an opencast mining is limited by the financial viability, .Su though coal seam continues to exist beyond the quarriable limits. Irrecoverable coal is lost forever within the highwall. Thus, highwall mining is a valued technology which can revolutionise maximization of extractable reserves. This technology is being practiced in USA, Australia, and Indonesia and is likely to be introduced in India in Eastern Coalfields Limited and Tata Steel – West Bokaro in coming years. CIL has identified 17 mines MD suitable for highwall mining and SCCL 6 blocks. Coal is extracted with miner or borer and coal is transported with belt or piped conveyor without artificial roof support and ventilation. The cars are added one by one behind the miner as it cuts in the seam, in a manner which does not interrupt the flow of coal. The launch vehicle is a two deck steel structure which sits on the floor of the pit at the base of the highwall. It serves as a work platform, propulsion unit and utilities supply center. It remains stationary during the mining process, providing a stable or: anchor point for the equipment at the highwall. It contains an electric power distribution center, a control cabin from where the operator operates the entire system by remote control, two separate hydraulic power systems, as well as cable and hose reels for electric power, coaxial cable and water. th Fig: 1. Typical components of a Highwall Mining Equipment Au As this method involves drivage of series of parallel roadways into the highwall along a particular horizon separated by ribs, the dimensions of the roadway, the thickness of the ribs, the maximum depth to be operated
  • 9. depends on the geo-technical characteristics of the seams / strata and surface features. Since the Technology is newer to India, all these parameters should be carefully studied before implementation. 5.5. Ventilation for deeper coal mines and introduction of air cooling system in underground The first shaft for coal mine, only 27m deep was sunk in the year 1851 at Eagra near Damalia in Raniganj coal field. Whereas a number of shafts of greater than 1000m depth were sunk in 1890s and 1910s at Champion reef- gold mine in KGF reached to a depth 3211m which is one of the deepest mine in the world. Whereas, the coal mining operations have crossed 300m depth and extending beyond 400m in the country and facing complex climatic conditions with high dry bulb temperatures due to strata temperature, mechanisation and humidity. Hence, it is a need of hour to formulate efficient ventilation in underground to create comfortable conditions. Deep shafts are inevitable to bring cool air at the deep most points. Higher capacity fans upto 400m3/min operating upto 250mm water gauge are to be planned to work mechanised faces in deep seated reserves. Except in few metalliferrous mines, air cooling/ refrigeration was not practiced in coal mines so far. But the present ar situation emerges underground cooling system to reduce ambient temperature of intake air. SCCL is installing its first refrigeration plant in underground 500TR chiller with 45000CMH air handling unit working at 40 mm water um gauge at Vk-7 Joy miner face and planning to install in two more mines. CIL too planning to introduce AC plants in underground. The cost of refrigeration per tone of coal against the losses that made out of inefficient ventilation is highly insignificant. 5.6. Thick seam mining hK A huge amount of coal reserves is being locked up in thick seams in the country. Both CIL and SCCL having huge amount of reserves of such kind. The conventional underground method of board and pillar development and depillaring in multistage with or without stowing is only available and proven technology exists all these days. The percentage of extraction in this method is well known to be less than 40%. The other mining methods like res wide stall, sub levels caving, Longwall with increased height if extraction and Longwall with top coal caving are having its own drawbacks due to either less percentage of extraction or newer technology which is not yet practiced in the country. The SCCL itself is having thick seam reserves about 40% out of two thousand million .Su tones of proved coal. Interestingly, Australia too has huge thick seam coal resources. The coal reserves in thick seams in both countries aggregate to several tens of billion tonnes. The current mining methods and designs for thick coal seams in underground mines are inefficient and result in huge losses of valuable coal resources in both countries. A MoU was signed by India (SCCL) and Australia (CSIRO) jointly with the major outcome of optimising extraction methods and/or designs to substantially improve recovery rates and safety of mining MD operations in Indian thick seam environments. 5.6.1. Blasting gallery- a success venture in SCCL Though this method was seemed to be conceptually easier and operationally dangerous in initial days, the simple or: mechanisation and the face operation without much complication are the key factors that made people to be well conversant to the applicability of the system with respect to their local mining conditions. A hydraulic supports with canopy specially designed for the purpose of having allowance to LHDs to ply can replace existing manual th installation of steel bars supported on OC props. Walking breaker line supports in the junctions could reduce human drudgery and still safer and productive too. Au 5.6.1.1. Strata control problems The experience in SCCL reveals that caving is not a problem in the coal seams with overlying strata having compressive strength varying between 100-300 Kg/cm2 and of easy to moderate caving roof. The technique of induced blasting incorporated in this method had proved to be given better results in bringing down the immediate roof at desirable interval. The regular falls of immediate 3-5m layers of overlying sand stone strata allows the upper and massive layers to readily cave in. Every periodic fall and induced fall posed minimum impact on the gallery supports and roof and sides. While working over the worked out panels of bottom seam and simultaneous working of lower and upper seam in gdk-8 incline revealed that the insitu stress domine is reasonably damaged to favour easy caving. 5.6.1.2. Fire control in BGs Spontaneous heating is one of the major problems being faced here. The occurrences of spontaneous heating in working panels, not only threat to the general safety, but it forces to close down the panels losing huge quantity of
  • 10. natural resources. It often ended up in sealing a large section of mine affecting the mine economics adversely. Therefore the prevention of spontaneous heating in Basting gallery become inevitable for mining engineers otherwise working of thick seams become questionable. The BG panels are being successfully mined in SCCL with the following preventive measures: 1. Monitoring in-bye most goaf atmosphere through pipelines, thermal images camera and surface boreholes. 2. Removing floor coal and curtain coal meticulously during extraction and descenstional ventilation system to contain the gases inside the goaf and to restrict goaf ventilation. 3. Regular induced blasting at an interval of 5m and up to 9 to 10m height in roof to reduce strata control problem as well as fill the goaf regularly avoiding air pockets inside. 4. Proactive inertisation by continuous injection of CO2 and N2 into active goaf. A storage tanker with a capacity of 30 metric tones of liquid CO2 ensures its constant availability through pipe lines. Combination CO2 and N2 creates identical density of goaf gases which advantageous that they can cover up the entire sealed off area in a quicker period. CO2 has an added advantage that it reacts endothermally consuming heat of 40.8 kcal/mole of ar CO2. CO2 is always better in quick replenishment of air, being heavier than air. Besides N2 creates congenial environment particularly when liquid N2 is used. um 5. Inertising the adjacent sealed off panels too. Fig 2: Surface CO2 Storage tank establishment at Gdk 10A mine. SCCL. hK res .Su 5.6.2. Long wall top coal caving-LTCC MD The LTCC method is based on the 'Soutirage' Longwall caving method originally developed in the French coal mining industry. Then Australia and China have started LTCC for thick seam mining. It basically involves an additional AFC to transport top coal falls behind the Shields. When compared to other thick seam mining techniques it ensures a high recovery rate and productivity. However, it is reported that 24 % of the coal reserve of or: a panel operating by LTCC is left behind the face. But today, with the experience of support operators; the coal recovery percentage is increasing year by year. As an equipment innovation, the more recent Chinese developments have relocated the top coal draw points to the rear of the longwall supports, rather than bringing th coal through the roof canopy of the shield onto a conveyor within the shield structure. The Chinese equipment has a pivoting supplementary goaf or tail canopy behind the support. With the rear AFC extended and the rear canopy Au lowered/retracted, caved top coal can be loaded onto the rear AFC. The Chinese industry had reported averages of 15,000 to 20,000 tpd from an LTCC face; up to 75% recovery of plus 8m thick seams using a 3m operating height longwall and plus 5 MTPA face production. There are now well over 70 LTCC faces in China. A new semi- automated 300m long LTCC face was installed at the Xinglongzhuang Colliery of the Yankuang Group, in Shandong Province, in August, 2001, with production capacities of at least 7MTPA. The consistent cavability of the top coal in an LTCC operation is crucial to its success. If the coal caves, but in too large a pieces it can cause blockages and handling problems both feeding onto, and traveling along the rear conveyor. Of even greater problem is if the coal hangs up, even only for a short time, such that it caves but beyond the reach of the rear AFC. The main geotechnical components affecting coal cavability are uniaxial compressive strength (UCS); cleat, bedding and other discontinuities; and vertical stress on the coal. Chinese experience is understood to be that compressive strength ranging from 15 MPa to 25 MPa is well suited to good caving conditions. Horizontal stress too has lot of influence.
  • 11. 6. Conclusion India, being a third coal producer in the world and producing nearly 85% of coal from opencast mining presently. The country has to exercise lot to get bulk output from underground mines. As the opencast mining have its own implications due to depth and environment pollution, bulk production is possible by opening new coal blocks suitable for sophisticated mechanisation and managing existing coal resources in underground mines to achieve sustaining improvements. Country need to focus Longwall mining and ought to revive its earlier policy 1975 ‘block diamond’ to introduce power supports Longwall in both CIL and SCCL in feasible blocks having good quality of coal. If Longwall faces planned abundantly, it creates a base for competition in foreign manufacturers and develops indigenous market too which would bring down cost of production. Different modules like mine developer cum operator (MDO), Technology provider cum operator (TPO) and Risk/gain sharing can be worked out with foreign participants. Blasting gallery is typical mining method to extract thick seams presently. The method is moderately mechanised, not much complicated and proved to be safer in operations in the last two decades in SCCL which is to be ar practised elsewhere in the country with further safety and productivity inputs. The number of CM units, presently 5 in the country should be multifolded to develop and extract 3-4m high seams. Shortwall mining a variant of um Longwall to extract standing pillars presently practised in SECL mines and proposed in SCCL too, must be vastly implemented to all the feasible mines. Highwall mining is a state art of mining by which the huge quantity of coal is locked up in highwalls of opencast mines can be successfully mined out. References/ Literatures 1. 2. hK US Energy Information Administration – independent statistics and analysis 2009. Report on 4th Thermal power India 2010 3. Report on “competition in India Energy sector” by The Energy and Resources Institute (TERI). res 4. Report on “The Expert committee on road map for coal sectors reforms” by Ministry of Coal. GOI. April 2007 5. Report of the working group on Coal & Lignite for formulation of Eleventh Five Year Plan (2007-12) by GOI, Ministry of Coal, Nov 2006. .Su 6. A Report on coal industry by “The Director, Coal Controller’s Organisation , Kolkatta. 7. Application of Nitrogen as preventive and controlling surface fire – Indian context by NK. Mohalik, RVK singh, J. Pandey and VK singh. CMRI. 2005 8. CMRI S&T report, study for early detection of the occurrences of spontaneous heating in the Blasting Gallery MD method and to evaluate suitable measures for prevention and control (CMRI-2002). 9. Why Longwall in India has not Succeeded as in other Developing Country Like China by Prof A K Ghose, Fellow 10. Why Longwall in India has not Succeeded as in other Developing Country Like China by S R Mehta, Non- member S Dasgupta, Non-member or: 11. Longwall Mining in India – Experiences and expectations by Sri DLR Prasad (Director PP) and M.S. Venkataramaiah (AGM). 12. Hamilton N, (1999) Single pass thick seam Longwall experience at West Wilsend Colliery, second th International Underground coal Conference, UNSW, Sydney, Australia 15-18 June,1999 PP55-61. 13. Hebblewhite BK &Cai YI(2004) evaluation of the application of the Long wall Top Coal Caving (LTCC) method in Australia, UNSW Mining Research Center, School of Mining Engineer, Sydney, Australia. Au 14. Peng SS. Chiang HS (1984) Longwall Mining, John Wiley & Sons Inc, PP 274-333. 15. Singh R, & Singh TN(1999) Investigation into the behavior of a support system and Roof strata, Geotechnical and Geological Engineering 21-35. Netherlands. 16. Walkers, Highwall evaluation World Coal Vol. 6 No. 10 Oct. 1997 PP 44-52. 17. Analysis of Practical Ground Control issues in Highwall Mining by R. Karl Zipf Jr. & Suresh Bhatt. National Institute of Occupational Safety and Health Pittsburgh. Pennsylvania. USA. 18. Superior Highwall Miners. LP. Beckley, West Virginea. http:www.shm.net.2004 19. Mining technology Inc, Ashland, Kentucky, http:www.addcarsystem.com. 2004 20. Duncan-Fama, ME Shen B, Craig MS, Kelly M, Follington IL and Leisemann BE Layout and Design- Case study for Highwall Mining of coal. Proceedings International Congress of Rock Mechanics eds. G.Vouille and P. Berest 1999 vol 1 pp 265-268. 21. High wall mining in Australia by left Sartaine. President, Mining Technologies. Inc. 22. Report on introduction of Shortwall mining in SCCL by CODCO, China, 25 Sep. 2009.