1. CURRICULUM VITAE
NAME : MAMOON JAMIL HAWASH
NATIONALITY : JORDANIAN
DATE OF BIRTH : 07 - 02 - 1966
LANGUAGES : ENGLISH, ARABIC
MARITAL STATUS : MARRIED
EDUCATIONAL : B.Sc. CIVIL ENGINEERING
QUALIFICATION ADAMSON UNIVERSITY, PHILIPPINES.
: Engineers Orientation course for Building Projects
: AutoCAD - Release 12
STAAD III – Release 18
Microsoft Office 97
PROFESSIONAL
EXPERIENCE
Oct. 1997 to present : ACTCO General Contracting Co.
December 2014 to till date
Position : QA/QC Manager
Project Description : Jumeirah Park Villas package (P-7A-226 Villas &
P-7B & C-190 Villas total of 416 Villas 4 Bed room
legacy type) comprises the Execution and completion
of Earth, Architectural, Structural, MEP and Fence
works for variable work progressed Villas.
Roles & Responsibilities :
Implement the QA/QC management system at site.
Coordinate with quality inspections with all the site sub contractors and vendors
Coordinate all non destructive testing on site.
Coordinate with the customer representative on all quality matters.
Coordinate all receipt inspections.
Distribute relevant QA/QC documentation to site subcontractors
2. Verify that the quality related site activities are in accordance with the applicable
codes and standards
Participate in the site internal and external site audits
Coordinate all the quality site inspections through the site QC inspectors
Ensure all quality control documentation is complied and competed for as-built hand
over through the QC turnover engineer
Control all nonconformance reports and undertake remedial action
Compete site quality control instructions and action remedial responses
Review the customers specification and undertake relevant training to the site QC
inspector
Monitor the implementation of the approved site QC Plan
Complete and coordinate the approval of the sites QC technical submittals to the
customer
Coordinate with the site construction manager on all quality issues Coordinate and
share the QA/QC site weekly meetings with the projects subcontractors QC personnel
Elaborating inspection and test programs
Assure all technical documents relative to site quality control are current status
Feb. 2012 to Nov. 2014
Position : QA/QC Manager
Project Description : Inter Refinery Pipe Line (IRP II) Project -Mussafah
Civil and Building Works (Area B1 & B2)
June 2011 to Jan. 2012
Position : QA/QC Manager
Project Description : Ruwais Refinery Expansion Project EPC # 4
Civil works (Area 4-2, 4-3-1, 4-5-2, 4-6)
3. October 2007 to May 2011
Position : QA/QC Manager
Project Description : Jebel Ali Power & Desalination Station ‘M’
Package “P” - Dubai
June. 2006 to Sept.07
Position : QA/QC Engineer
Project Description : Abu Dhabi Steel Pipe Factory at Mussafah ICAD2
Jan. 2005 to May 2006
Position : QA/QC Engineer
Project Description : Tabreed Cooling Plant at Marina Mall.
Dec.2003 to Dec.2004
Position : QA/QC Engineer
Project Description : 132/11 kV Subsation and W16, Abu Dhabi
Consisting of control building, GIS building,
Transformer enclosure, A/C Building, Fire Pump house,
Water tank and external works such as Road, Cable
trenches, Cable duct and Boundary wall.
July 2002 to Oct.2003
4. Position : QA/QC Engineer
Project Description : SVC Plant at Mussafah
Consisting of piling works, transformer bays, SVC
building consisting of central 2 storey control building
area, SVC equipment Halls and Busbar Halls, all
drainage works, all external works including cable
trenches, asphalt roads, kerbs and footpaths etc.
Jan.2001 to June 2002
Position : QA/QC Engineer
Project Description : 400 kV Interconnection Taweelah – Mussafah
Extension of Existing 400 kV Substation at Taweelah,
Consisting of piling works, control building, GIS
building, transformer compounds including steel rails,
steel grating, corner protection etc., fire protection plant
room and tanks, water supply and storage system, all
drainage works and external roads.
Oct. 97 to Dec. 2000
Position : Project Engineer
Project Description : Relocation of Abu Dhabi Aviation Facilities to Abu
Dhabi International Airport, consisting of New
Terminal Building, Modification of existing Terminal
building, Mechanical plant, Fire water tank and Pump
house, Maintenance complex and Aircraft Hangers,
Workshop building and others.
Feb 95 to Sept.97 : Al Rawa contracting Co.- Jordan as a site Engineer.
Aug.92 to Dec.94 : Al Jassi Contracting Est. – Jordan as a site Engineer.
Mar. 91 to May 92 : Serving as a conscript supervision engineer.