SlideShare a Scribd company logo
1 of 29
Download to read offline
Tathagat Varma


Tathagat Varma
 Session 2/12: 21-May-2010
    Add more people?
    Buy more time?
    Offshore?
    Do Agile?
    Buy the latest and greatest tool?
    New ‘silver bullet’?
    Project Management has some answers
    However, no moneyback guarantees



                            2            4/17/11
    A Project is a temporary endeavor
     undertaken to create a unique product,
     service or result
       Temporary    doesn’t mean short duration
       Temporary doesn’t apply to product, service or
        result created by a project
    Every project creates a unique product,
     service or result, though repetitive elements
     may be present in some project deliverables
    A project can involve single person, an
     organizational unit, or multiple such units

                                3           4/17/11
    Developing a new product or service
    Effecting a change in the structure,
     staffing, or style of an organization
    Developing or acquiring a new or
     modified information system
    Constructing a building or
     infrastructure
    Implement a new business procedure
    Etc.
    An ongoing work effort is generally a
     repetitive process because it follows an
     organization’s existing procedures.
       In contrast, because of the unique nature of projects,
        there may be uncertainties about the products,
        services, or results that the project creates.
       Project tasks can be new to a project team, which
        necessitates more dedicated planning than other
        routine work.
       In addition, projects are undertaken at all
        organizational levels. A project can involve a single
        person, a single organizational unit, or multiple
        organizational units.
Project                          Operations
Definition    Projects typically create   Perform the ongoing execution of
              new product, service or     activities that produce the same
              result for an               product or provide the repetitive
              organization                service
Tenure        Temporary / one-time        Permanent / ongoing

Result /      Unique                      Repetitive
output
Nature of     Typically involve           Basically the same set of tasks
tasks         creating a new result       according to standards
              and could entail            institutionalized in a project lifecycle
              uncertainties
Management    Project Management          Business Process Management or
                                          Operations Management
Termination   Terminates when             Does not terminate when its current
              project’s objectives are    objectives are met but instead follow
              met                         new directions to support the
                                          organization’s strategic plans
                                            6                 4/17/11
    Loksabha Elections 2009
    Bata wants to enter new market for Rs. 5,000+ shoes
    Times of India for 21-May-2010
    Organizing IPL3
    Prepare and declare Infosys quarterly results
    Planning family weekend outing
    Running an Air Traffic Control (ATC) tower
    Catching Veerapan task force
    Bangalore Metro
    Submit a monthly finance report
    Production of Maruthi 800 cars
    Hiring for next project
    Tata Nano
    Tonight’s home dinner
    File your annual taxes
    Project Management is the application of
     knowledge, skills, tools, and techniques to project
     activities to meet project requirements.
    Managing a project typically includes
       Identifying requirements
       Addressing various needs, concerns and expectation of
        stakeholders
       Balancing the competing project constraints like
          o  Scope,
          o  Quality,
          o  Schedule,
          o  Budget,
          o  Resources and
          o  Risk


                                    8              4/17/11
    A Program is defined as a group of
     projects related through the common
     outcome or collective capability. If the
     relationship between projects is only
     that of a shared client, seller,
     technology or resource, the effort
     should be managed as a portfolio of
     projects rather than a program
       Programsmay include elements of related work
      outside the scope of the discrete projects in the
      program
                               9            4/17/11
    Program Management is centralized coordinated
     management of a program to achieve program’s
     strategic objectives and benefits that are not available
     from managing the sub-projects individually
    Program Management focuses on the project
     interdependencies and helps to determine the
     optimal approach for managing them. Action related
     to these interdependencies may include:
       Resolve resource constraints and/or conflicts that affect
        multiple projects within the system
       Align organizational/strategic direction that affects project and
        program goals and objectives
       Resolve issues and change management within a shared
        governance structure
    A Portfolio refers to a collection of
     projects and programs and other work
     that are grouped together to facilitate
     effective management of that work to
     meet strategic business objectives.
       The
          projects and programs of the portfolio
      may not necessarily be interdependent or
      directly related.




                          11         4/17/11
    Portfolio Management refers to the
     centralized management of one or more
     portfolios, which includes identifying,
     prioritizing, authorizing, managing, and
     controlling projects, programs, and other
     related work, to achieve specific strategic
     business objectives. It focuses on ensuring
     that projects and programs are reviewed to
     prioritize resource allocation, and that the
     management of the portfolio is consistent
     with and aligned to organizational strategies.
13   4/17/11
Projects                              Programs                              Portfolios
Scope        Projects have defined objectives.   Programs have a larger scope and        Portfolios have a business scope
             Scope is progressively              provide more significant benefits       that changes with strategic
             elaborated throughout the                                                   goals of the organization
             project lifecycle

Change       Project managers expect change      Program manager must expect             Portfolio managers continually
             and implement processes to          change from both inside and outside     monitor changes in the broad
             keep change managed and             the program and be prepared to          environment
             controlled                          manage it
Planning     Project managers progressively      Program managers develop overall        Portfolio managers create and
             elaborate high-level information    program plan and create high-level      maintain necessary processes
             into detailed plans throughout      plans to guide detailed planning at     and communication relative to
             the project life cycle              the component level                     the aggregate portfolio

Management   Project managers manage the         Program managers manage the             Portfolio managers may
             project team to meet the project    program staff and the project           manage or coordinate portfolio
             objectives                          managers; they provide vision and       management staff
                                                 overall leadership
Success      Success is measured by product      Success is measured by the degree to    Success is measured in terms of
             and project quality, timeliness,    which the program satisfies the needs   aggregate performance of
             budget compliance, and degree       and benefits for which it was           portfolio components
             of customer satisfaction            undertaken

Monitoring   Project managers monitor and        Program managers monitor the            Portfolio managers monitor
             control the work of producing       progress of program components to       aggregate performance and
             the products, services or results   ensure the overall goals, schedules,    value indicators
             that the project was undertaken     budget, and benefits of the program
             to product                          will be met     14                        4/17/11
    A PMO is an organizational body assigned
     various responsibilities related to the
     centralized and coordinated management of
     those projects under its domain
    Responsibilities can range from providing
     project management support to actually
     being responsible for the direct management
     of project
    Project supported or administered by PMO
     may not be related, other than being
     managed together

                          15         4/17/11
    Primary functions:
       Managing    shared resources across all projects
        administered by PMO
       Identify and develop PM methodology, best
        practices and standards
       Coaching, mentoring, training and oversight
       Monitor compliance with PM standard
        policies, etc.
       Develop and manage project policies, etc.
       Coordinate communication across projects
    PMs and PMOs pursue different objectives and, as
     such, are driven by different requirements. All of
     these efforts, however, are aligned with the strategic
     needs of the organization. Differences:
       PM focuses on the specified project objectives, while the PMO
        manages major program scope changes which may be seen as
        potential opportunities to better achieve business objectives
       PM controls the assigned project resources to best meet project
        objectives while the PMO optimizes the use of shared
        organizational resources across all projects
       PM manages the constraints (scope, schedule, cost, and
        quality, etc.) of the individual projects while the PMO
        manages the methodologies, standards, overall risk/
        productivity, and independencies among projects at the
        enterprise level

                                     17              4/17/11
    As a discipline, Project Management developed
     from several fields of application including
     construction, engineering, and defense activity.[8]
    Two forefathers of project management are
     Henry Gantt, called the father of planning and
     control techniques[9], who is famous for his use of
     the Gantt chart as a project management tool; and
     Henri Fayol for his creation of the 5 management
     functions which form the foundation of the body of
     knowledge associated with project and program
     management.[10] Both Gantt and Fayol were students
     of Frederick Winslow Taylor's theories of
     scientific management. His work is the forerunner to
     modern project management tools including
     work breakdown structure (WBS) and 4/17/11
                                18
     resource allocation.
    The 1950s marked the beginning of the modern Project
     Management era. Project management became recognized
     as a distinct discipline arising from the management
     discipline.[11] In the United States, prior to the 1950s,
     projects were managed on an ad hoc basis using mostly
     Gantt Charts, and informal techniques and tools. At that
     time, two mathematical project-scheduling models were
     developed. The "Critical Path Method" (CPM) was
     developed as a joint venture between DuPont Corporation
     and Remington Rand Corporation for managing plant
     maintenance projects. And the "
     Program Evaluation and Review Technique" or PERT, was
     developed by Booz-Allen & Hamilton as part of the
     United States Navy's (in conjunction with the
     Lockheed Corporation) Polaris missile submarine
     program;[12] These mathematical techniques quickly
     spread into many private enterprises.
    At the same time, as project-scheduling models were
     being developed, technology for project cost
     estimating, cost management, and engineering
     economics was evolving, with pioneering work by
     Hans Lang and others. In 1956, the American
     Association of Cost Engineers (now
     AACE International; the Association for the
     Advancement of Cost Engineering) was formed by
     early practitioners of project management and the
     associated specialties of planning and scheduling,
     cost estimating, and cost/schedule control (project
     control). AACE continued its pioneering work and
     in 2006 released the first integrated process for
     portfolio, program and project management (
     Total Cost Management Framework).
                              20          4/17/11
    The International Project Management Association
     (IPMA) was founded in Europe in 1967,[13] as a
     federation of several national project management
     associations. IPMA maintains its federal structure
     today and now includes member associations on
     every continent except Antarctica. IPMA offers a Four
     Level Certification program based on the IPMA
     Competence Baseline (ICB).[14] The ICB covers
     technical competences, contextual competences, and
     behavioral competences.
    In 1969, the Project Management Institute (PMI) was
     formed in the USA.[15] PMI publishes
     A Guide to the Project Management Body of
     Knowledge (PMBOK Guide), which describes project
     management practices that are common to "most
     projects, most of the time."
Framework / approach

Lifecycle

Organization Structure

Leadership Styles

Team formation

Planning

Scheduling

Execution

Monitoring & Control

Closure
    PMI / PMBoK
    PRINCE2
    CMMI
    Critical Chain Project Management




                       23       4/17/11
24   4/17/11
    PRINCE2 is a structured method for effective
     project management. It is a "de facto" standard
     used extensively within UK government and
     within both UK and international industry. It is a
     public domain method offering best practice
     guidance on project management.
    PRINCE2 adopts three principles of good project
     management
       A project is a finite process, with a start date and an end
        date
       Projects must be controlled to be successful
       All parties must be clear about
          o  Why the project is needed
          o  What is to be achieved
          o  How the outcome will be achieved
          o  What their responsibilities are
26   4/17/11
    “A management environment that is created for the
     purpose of delivering one or more business products
     according to a specified Business Case”
    “A temporary organisation that is needed to produce a
     unique and pre-determined outcome or result at a pre-
     specified time using predetermined resources”
    A project has a number of characteristics:
         Finite and defined lifespan - the project is covered by a plan
          showing the date when it is expected to start and the date when it
          is expected to finish;
         Defined and measurable business products - a set of pre-defined
          products which must be delivered to the Customer;
         Corresponding set of activities - A set of planned activities which
          will deliver the products, including management and technical
          activities;
         Defined amount of resources - an agreed amount of resource
          which can be used to develop the products;
         Organization structure - a defined hierarchy and reporting
          structure set up specifically for the project.
28   4/17/11
Yahoo! Presentation, Confidential   29   4/17/11

More Related Content

What's hot

Livre blanc la vente indirecte c'est quoi
Livre blanc   la vente indirecte c'est quoiLivre blanc   la vente indirecte c'est quoi
Livre blanc la vente indirecte c'est quoiPatrick Bouillaud
 
BA225 Week six chapter 10 ppt
BA225 Week six   chapter 10 pptBA225 Week six   chapter 10 ppt
BA225 Week six chapter 10 pptBealCollegeOnline
 
Negotiation Skills Updated
Negotiation Skills UpdatedNegotiation Skills Updated
Negotiation Skills UpdatedMahmoud
 
Negotiation skills PPT along with Slideshow audio description note.
Negotiation skills PPT along with Slideshow audio description note.Negotiation skills PPT along with Slideshow audio description note.
Negotiation skills PPT along with Slideshow audio description note.Sachin PM
 
Negotiation Skills: Principles Practice and Process
Negotiation Skills: Principles Practice and ProcessNegotiation Skills: Principles Practice and Process
Negotiation Skills: Principles Practice and ProcessCharles Cotter, PhD
 
Blue ocean workbook takeaway ver 2.0
Blue ocean workbook takeaway ver 2.0Blue ocean workbook takeaway ver 2.0
Blue ocean workbook takeaway ver 2.0Theorem Solutions
 
Honda International Case Study
Honda International Case StudyHonda International Case Study
Honda International Case StudyJacob Hostetler
 
Strategic Relationships
Strategic RelationshipsStrategic Relationships
Strategic RelationshipsEyya Ahmed
 
DECISION MAKING AND TECHNIQUES OF DECISION MAKING
DECISION MAKING AND TECHNIQUES OF DECISION MAKINGDECISION MAKING AND TECHNIQUES OF DECISION MAKING
DECISION MAKING AND TECHNIQUES OF DECISION MAKINGManah Chhabra
 
Negotiation skills assignment
Negotiation skills assignmentNegotiation skills assignment
Negotiation skills assignmentneha singh
 
integrative negotiation
integrative negotiationintegrative negotiation
integrative negotiationdhiraj.gaur
 
HRM Presentation on Audi
HRM Presentation on AudiHRM Presentation on Audi
HRM Presentation on AudiSuvojit Das
 
Integrated Marketing Communication
Integrated Marketing CommunicationIntegrated Marketing Communication
Integrated Marketing Communicationsingh.the.hacker
 
Marketing- Macroenvironment
Marketing- MacroenvironmentMarketing- Macroenvironment
Marketing- MacroenvironmentKabsideous
 

What's hot (20)

Livre blanc la vente indirecte c'est quoi
Livre blanc   la vente indirecte c'est quoiLivre blanc   la vente indirecte c'est quoi
Livre blanc la vente indirecte c'est quoi
 
BA225 Week six chapter 10 ppt
BA225 Week six   chapter 10 pptBA225 Week six   chapter 10 ppt
BA225 Week six chapter 10 ppt
 
Negotiation skills
Negotiation skillsNegotiation skills
Negotiation skills
 
Negotiation Skills Updated
Negotiation Skills UpdatedNegotiation Skills Updated
Negotiation Skills Updated
 
Negotiation skills PPT along with Slideshow audio description note.
Negotiation skills PPT along with Slideshow audio description note.Negotiation skills PPT along with Slideshow audio description note.
Negotiation skills PPT along with Slideshow audio description note.
 
Negotiation Skills: Principles Practice and Process
Negotiation Skills: Principles Practice and ProcessNegotiation Skills: Principles Practice and Process
Negotiation Skills: Principles Practice and Process
 
Blue ocean workbook takeaway ver 2.0
Blue ocean workbook takeaway ver 2.0Blue ocean workbook takeaway ver 2.0
Blue ocean workbook takeaway ver 2.0
 
BATNA presentation.pptx
BATNA presentation.pptxBATNA presentation.pptx
BATNA presentation.pptx
 
Problem Solving
Problem SolvingProblem Solving
Problem Solving
 
Honda International Case Study
Honda International Case StudyHonda International Case Study
Honda International Case Study
 
Strategic Relationships
Strategic RelationshipsStrategic Relationships
Strategic Relationships
 
DECISION MAKING AND TECHNIQUES OF DECISION MAKING
DECISION MAKING AND TECHNIQUES OF DECISION MAKINGDECISION MAKING AND TECHNIQUES OF DECISION MAKING
DECISION MAKING AND TECHNIQUES OF DECISION MAKING
 
Negotiation skills assignment
Negotiation skills assignmentNegotiation skills assignment
Negotiation skills assignment
 
Synergy Powerpoint
Synergy PowerpointSynergy Powerpoint
Synergy Powerpoint
 
The evolution of toyota
The evolution of toyotaThe evolution of toyota
The evolution of toyota
 
Negotiation skills
Negotiation skillsNegotiation skills
Negotiation skills
 
integrative negotiation
integrative negotiationintegrative negotiation
integrative negotiation
 
HRM Presentation on Audi
HRM Presentation on AudiHRM Presentation on Audi
HRM Presentation on Audi
 
Integrated Marketing Communication
Integrated Marketing CommunicationIntegrated Marketing Communication
Integrated Marketing Communication
 
Marketing- Macroenvironment
Marketing- MacroenvironmentMarketing- Macroenvironment
Marketing- Macroenvironment
 

Viewers also liked

Project Management In The Automotive Industry
Project Management In The Automotive IndustryProject Management In The Automotive Industry
Project Management In The Automotive IndustryGestion Projet Auto
 
A project report on tata nano pre launch survey
A project report on  tata nano pre launch surveyA project report on  tata nano pre launch survey
A project report on tata nano pre launch surveyProjects Kart
 
Case study on TATO NANO-VATION
Case study on TATO NANO-VATIONCase study on TATO NANO-VATION
Case study on TATO NANO-VATIONNarasimha c
 
Marketing research project on tata nano
Marketing research project on tata nanoMarketing research project on tata nano
Marketing research project on tata nanoProjects Kart
 
Tata motors tata nano ppt
Tata motors   tata nano pptTata motors   tata nano ppt
Tata motors tata nano pptDharmik
 
TATA NANO - Brief History and Case Study Analysis
TATA NANO - Brief History and Case Study AnalysisTATA NANO - Brief History and Case Study Analysis
TATA NANO - Brief History and Case Study AnalysisSadat Faruque
 

Viewers also liked (8)

Project Management In The Automotive Industry
Project Management In The Automotive IndustryProject Management In The Automotive Industry
Project Management In The Automotive Industry
 
A project report on tata nano pre launch survey
A project report on  tata nano pre launch surveyA project report on  tata nano pre launch survey
A project report on tata nano pre launch survey
 
Case study on TATO NANO-VATION
Case study on TATO NANO-VATIONCase study on TATO NANO-VATION
Case study on TATO NANO-VATION
 
Positioning of TATA Nano
Positioning of TATA NanoPositioning of TATA Nano
Positioning of TATA Nano
 
Marketing research project on tata nano
Marketing research project on tata nanoMarketing research project on tata nano
Marketing research project on tata nano
 
Tata motors tata nano ppt
Tata motors   tata nano pptTata motors   tata nano ppt
Tata motors tata nano ppt
 
TATA NANO - Brief History and Case Study Analysis
TATA NANO - Brief History and Case Study AnalysisTATA NANO - Brief History and Case Study Analysis
TATA NANO - Brief History and Case Study Analysis
 
tata motors
tata motorstata motors
tata motors
 

Similar to Project Management 02

Project Management Office (Anna Maria Felici)
Project Management Office (Anna Maria Felici)Project Management Office (Anna Maria Felici)
Project Management Office (Anna Maria Felici)GPMS
 
Strategic Management of Multiple Projects (aka Project Whispering)
Strategic Management of Multiple Projects (aka Project Whispering)Strategic Management of Multiple Projects (aka Project Whispering)
Strategic Management of Multiple Projects (aka Project Whispering)Phase2
 
Strategic Management of Multiple Projects (aka Project Whispering)
Strategic Management of Multiple Projects (aka Project Whispering)Strategic Management of Multiple Projects (aka Project Whispering)
Strategic Management of Multiple Projects (aka Project Whispering)Treehouse Agency
 
PMP - Session 01 Updated.pptx
PMP - Session 01 Updated.pptxPMP - Session 01 Updated.pptx
PMP - Session 01 Updated.pptxKareemBullard1
 
PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxSabrinaScott22
 
PMP preparation course
PMP preparation coursePMP preparation course
PMP preparation coursemohamed fawzy
 
Prestiva PMP process approach
Prestiva PMP process approachPrestiva PMP process approach
Prestiva PMP process approachMurali Venkatesh
 
Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2Amr Miqdadi
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management FundamentalsNishant Munjal
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkejlp12
 
Introduction to pmp
Introduction to pmpIntroduction to pmp
Introduction to pmpshkadry
 
Project management 1
Project management 1Project management 1
Project management 1bnettel
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]OyetadeTobi
 
L2-INTRODUCTION TO PROJECT MANAGEMENT.pptx
L2-INTRODUCTION TO PROJECT MANAGEMENT.pptxL2-INTRODUCTION TO PROJECT MANAGEMENT.pptx
L2-INTRODUCTION TO PROJECT MANAGEMENT.pptxARLIEFRESNIDO2
 

Similar to Project Management 02 (20)

Project Management Office (Anna Maria Felici)
Project Management Office (Anna Maria Felici)Project Management Office (Anna Maria Felici)
Project Management Office (Anna Maria Felici)
 
Strategic Management of Multiple Projects (aka Project Whispering)
Strategic Management of Multiple Projects (aka Project Whispering)Strategic Management of Multiple Projects (aka Project Whispering)
Strategic Management of Multiple Projects (aka Project Whispering)
 
Strategic Management of Multiple Projects (aka Project Whispering)
Strategic Management of Multiple Projects (aka Project Whispering)Strategic Management of Multiple Projects (aka Project Whispering)
Strategic Management of Multiple Projects (aka Project Whispering)
 
PMP - Session 01 Updated.pptx
PMP - Session 01 Updated.pptxPMP - Session 01 Updated.pptx
PMP - Session 01 Updated.pptx
 
Pmp Complete Notes
Pmp Complete NotesPmp Complete Notes
Pmp Complete Notes
 
PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptx
 
PMP preparation course
PMP preparation coursePMP preparation course
PMP preparation course
 
Prestiva PMP process approach
Prestiva PMP process approachPrestiva PMP process approach
Prestiva PMP process approach
 
Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
Pmp Complete Notes
Pmp Complete NotesPmp Complete Notes
Pmp Complete Notes
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
 
Project Management V1
Project Management V1Project Management V1
Project Management V1
 
UNIT-1.pptx
UNIT-1.pptxUNIT-1.pptx
UNIT-1.pptx
 
Introduction to pmp
Introduction to pmpIntroduction to pmp
Introduction to pmp
 
Day 1 framework
Day 1 frameworkDay 1 framework
Day 1 framework
 
Project management 1
Project management 1Project management 1
Project management 1
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]
 
L2-INTRODUCTION TO PROJECT MANAGEMENT.pptx
L2-INTRODUCTION TO PROJECT MANAGEMENT.pptxL2-INTRODUCTION TO PROJECT MANAGEMENT.pptx
L2-INTRODUCTION TO PROJECT MANAGEMENT.pptx
 
PMP.pdf
PMP.pdfPMP.pdf
PMP.pdf
 

More from Tathagat Varma

Can AI finally "cure" the Marketing Myopia?
Can AI finally "cure" the Marketing Myopia?Can AI finally "cure" the Marketing Myopia?
Can AI finally "cure" the Marketing Myopia?Tathagat Varma
 
AI in Manufacturing: Opportunities & Challenges
AI in Manufacturing: Opportunities & ChallengesAI in Manufacturing: Opportunities & Challenges
AI in Manufacturing: Opportunities & ChallengesTathagat Varma
 
Preparing for the next ________?
Preparing for the next ________?Preparing for the next ________?
Preparing for the next ________?Tathagat Varma
 
AI in Business: Opportunities & Challenges
AI in Business: Opportunities & ChallengesAI in Business: Opportunities & Challenges
AI in Business: Opportunities & ChallengesTathagat Varma
 
Leadership Agility Mindsets
Leadership Agility MindsetsLeadership Agility Mindsets
Leadership Agility MindsetsTathagat Varma
 
Building an AI Startup
Building an AI StartupBuilding an AI Startup
Building an AI StartupTathagat Varma
 
Agility in an AI / DS / ML Project
Agility in an AI / DS / ML ProjectAgility in an AI / DS / ML Project
Agility in an AI / DS / ML ProjectTathagat Varma
 
AI Technology Delivering Business Value
AI Technology Delivering Business Value AI Technology Delivering Business Value
AI Technology Delivering Business Value Tathagat Varma
 
Nurturing Innovation Mindset
Nurturing Innovation MindsetNurturing Innovation Mindset
Nurturing Innovation MindsetTathagat Varma
 
PMOs and Complexity Management
PMOs and Complexity ManagementPMOs and Complexity Management
PMOs and Complexity ManagementTathagat Varma
 
An Introduction to the Systematic Inventive Thinking (SIT) Method
An Introduction to the Systematic Inventive Thinking (SIT) MethodAn Introduction to the Systematic Inventive Thinking (SIT) Method
An Introduction to the Systematic Inventive Thinking (SIT) MethodTathagat Varma
 
I blog...therefore I am!
I blog...therefore I am!I blog...therefore I am!
I blog...therefore I am!Tathagat Varma
 
Bridging the gap between Education and Learning
Bridging the gap between Education and LearningBridging the gap between Education and Learning
Bridging the gap between Education and LearningTathagat Varma
 
Is my iceberg melting?
Is my iceberg melting?Is my iceberg melting?
Is my iceberg melting?Tathagat Varma
 
Digital Business Model Innovation
Digital Business Model InnovationDigital Business Model Innovation
Digital Business Model InnovationTathagat Varma
 
25 Years of Evolution of Software Product Management: A practitioner's perspe...
25 Years of Evolution of Software Product Management: A practitioner's perspe...25 Years of Evolution of Software Product Management: A practitioner's perspe...
25 Years of Evolution of Software Product Management: A practitioner's perspe...Tathagat Varma
 
Agility from First Principles
Agility from First PrinciplesAgility from First Principles
Agility from First PrinciplesTathagat Varma
 

More from Tathagat Varma (20)

Can AI finally "cure" the Marketing Myopia?
Can AI finally "cure" the Marketing Myopia?Can AI finally "cure" the Marketing Myopia?
Can AI finally "cure" the Marketing Myopia?
 
AI in Manufacturing: Opportunities & Challenges
AI in Manufacturing: Opportunities & ChallengesAI in Manufacturing: Opportunities & Challenges
AI in Manufacturing: Opportunities & Challenges
 
Preparing for the next ________?
Preparing for the next ________?Preparing for the next ________?
Preparing for the next ________?
 
AI in Business: Opportunities & Challenges
AI in Business: Opportunities & ChallengesAI in Business: Opportunities & Challenges
AI in Business: Opportunities & Challenges
 
Leadership Agility Mindsets
Leadership Agility MindsetsLeadership Agility Mindsets
Leadership Agility Mindsets
 
Building an AI Startup
Building an AI StartupBuilding an AI Startup
Building an AI Startup
 
Agility in an AI / DS / ML Project
Agility in an AI / DS / ML ProjectAgility in an AI / DS / ML Project
Agility in an AI / DS / ML Project
 
Cognitive Chasms
Cognitive ChasmsCognitive Chasms
Cognitive Chasms
 
AI Technology Delivering Business Value
AI Technology Delivering Business Value AI Technology Delivering Business Value
AI Technology Delivering Business Value
 
Nurturing Innovation Mindset
Nurturing Innovation MindsetNurturing Innovation Mindset
Nurturing Innovation Mindset
 
Thought Leadership
Thought LeadershipThought Leadership
Thought Leadership
 
PMOs and Complexity Management
PMOs and Complexity ManagementPMOs and Complexity Management
PMOs and Complexity Management
 
An Introduction to the Systematic Inventive Thinking (SIT) Method
An Introduction to the Systematic Inventive Thinking (SIT) MethodAn Introduction to the Systematic Inventive Thinking (SIT) Method
An Introduction to the Systematic Inventive Thinking (SIT) Method
 
Agile at Scale
Agile at ScaleAgile at Scale
Agile at Scale
 
I blog...therefore I am!
I blog...therefore I am!I blog...therefore I am!
I blog...therefore I am!
 
Bridging the gap between Education and Learning
Bridging the gap between Education and LearningBridging the gap between Education and Learning
Bridging the gap between Education and Learning
 
Is my iceberg melting?
Is my iceberg melting?Is my iceberg melting?
Is my iceberg melting?
 
Digital Business Model Innovation
Digital Business Model InnovationDigital Business Model Innovation
Digital Business Model Innovation
 
25 Years of Evolution of Software Product Management: A practitioner's perspe...
25 Years of Evolution of Software Product Management: A practitioner's perspe...25 Years of Evolution of Software Product Management: A practitioner's perspe...
25 Years of Evolution of Software Product Management: A practitioner's perspe...
 
Agility from First Principles
Agility from First PrinciplesAgility from First Principles
Agility from First Principles
 

Project Management 02

  • 1. Tathagat Varma Tathagat Varma Session 2/12: 21-May-2010
  • 2.   Add more people?   Buy more time?   Offshore?   Do Agile?   Buy the latest and greatest tool?   New ‘silver bullet’?   Project Management has some answers   However, no moneyback guarantees 2 4/17/11
  • 3.   A Project is a temporary endeavor undertaken to create a unique product, service or result   Temporary doesn’t mean short duration   Temporary doesn’t apply to product, service or result created by a project   Every project creates a unique product, service or result, though repetitive elements may be present in some project deliverables   A project can involve single person, an organizational unit, or multiple such units 3 4/17/11
  • 4.   Developing a new product or service   Effecting a change in the structure, staffing, or style of an organization   Developing or acquiring a new or modified information system   Constructing a building or infrastructure   Implement a new business procedure   Etc.
  • 5.   An ongoing work effort is generally a repetitive process because it follows an organization’s existing procedures.   In contrast, because of the unique nature of projects, there may be uncertainties about the products, services, or results that the project creates.   Project tasks can be new to a project team, which necessitates more dedicated planning than other routine work.   In addition, projects are undertaken at all organizational levels. A project can involve a single person, a single organizational unit, or multiple organizational units.
  • 6. Project Operations Definition Projects typically create Perform the ongoing execution of new product, service or activities that produce the same result for an product or provide the repetitive organization service Tenure Temporary / one-time Permanent / ongoing Result / Unique Repetitive output Nature of Typically involve Basically the same set of tasks tasks creating a new result according to standards and could entail institutionalized in a project lifecycle uncertainties Management Project Management Business Process Management or Operations Management Termination Terminates when Does not terminate when its current project’s objectives are objectives are met but instead follow met new directions to support the organization’s strategic plans 6 4/17/11
  • 7.   Loksabha Elections 2009   Bata wants to enter new market for Rs. 5,000+ shoes   Times of India for 21-May-2010   Organizing IPL3   Prepare and declare Infosys quarterly results   Planning family weekend outing   Running an Air Traffic Control (ATC) tower   Catching Veerapan task force   Bangalore Metro   Submit a monthly finance report   Production of Maruthi 800 cars   Hiring for next project   Tata Nano   Tonight’s home dinner   File your annual taxes
  • 8.   Project Management is the application of knowledge, skills, tools, and techniques to project activities to meet project requirements.   Managing a project typically includes   Identifying requirements   Addressing various needs, concerns and expectation of stakeholders   Balancing the competing project constraints like o  Scope, o  Quality, o  Schedule, o  Budget, o  Resources and o  Risk 8 4/17/11
  • 9.   A Program is defined as a group of projects related through the common outcome or collective capability. If the relationship between projects is only that of a shared client, seller, technology or resource, the effort should be managed as a portfolio of projects rather than a program   Programsmay include elements of related work outside the scope of the discrete projects in the program 9 4/17/11
  • 10.   Program Management is centralized coordinated management of a program to achieve program’s strategic objectives and benefits that are not available from managing the sub-projects individually   Program Management focuses on the project interdependencies and helps to determine the optimal approach for managing them. Action related to these interdependencies may include:   Resolve resource constraints and/or conflicts that affect multiple projects within the system   Align organizational/strategic direction that affects project and program goals and objectives   Resolve issues and change management within a shared governance structure
  • 11.   A Portfolio refers to a collection of projects and programs and other work that are grouped together to facilitate effective management of that work to meet strategic business objectives.   The projects and programs of the portfolio may not necessarily be interdependent or directly related. 11 4/17/11
  • 12.   Portfolio Management refers to the centralized management of one or more portfolios, which includes identifying, prioritizing, authorizing, managing, and controlling projects, programs, and other related work, to achieve specific strategic business objectives. It focuses on ensuring that projects and programs are reviewed to prioritize resource allocation, and that the management of the portfolio is consistent with and aligned to organizational strategies.
  • 13. 13 4/17/11
  • 14. Projects Programs Portfolios Scope Projects have defined objectives. Programs have a larger scope and Portfolios have a business scope Scope is progressively provide more significant benefits that changes with strategic elaborated throughout the goals of the organization project lifecycle Change Project managers expect change Program manager must expect Portfolio managers continually and implement processes to change from both inside and outside monitor changes in the broad keep change managed and the program and be prepared to environment controlled manage it Planning Project managers progressively Program managers develop overall Portfolio managers create and elaborate high-level information program plan and create high-level maintain necessary processes into detailed plans throughout plans to guide detailed planning at and communication relative to the project life cycle the component level the aggregate portfolio Management Project managers manage the Program managers manage the Portfolio managers may project team to meet the project program staff and the project manage or coordinate portfolio objectives managers; they provide vision and management staff overall leadership Success Success is measured by product Success is measured by the degree to Success is measured in terms of and project quality, timeliness, which the program satisfies the needs aggregate performance of budget compliance, and degree and benefits for which it was portfolio components of customer satisfaction undertaken Monitoring Project managers monitor and Program managers monitor the Portfolio managers monitor control the work of producing progress of program components to aggregate performance and the products, services or results ensure the overall goals, schedules, value indicators that the project was undertaken budget, and benefits of the program to product will be met 14 4/17/11
  • 15.   A PMO is an organizational body assigned various responsibilities related to the centralized and coordinated management of those projects under its domain   Responsibilities can range from providing project management support to actually being responsible for the direct management of project   Project supported or administered by PMO may not be related, other than being managed together 15 4/17/11
  • 16.   Primary functions:   Managing shared resources across all projects administered by PMO   Identify and develop PM methodology, best practices and standards   Coaching, mentoring, training and oversight   Monitor compliance with PM standard policies, etc.   Develop and manage project policies, etc.   Coordinate communication across projects
  • 17.   PMs and PMOs pursue different objectives and, as such, are driven by different requirements. All of these efforts, however, are aligned with the strategic needs of the organization. Differences:   PM focuses on the specified project objectives, while the PMO manages major program scope changes which may be seen as potential opportunities to better achieve business objectives   PM controls the assigned project resources to best meet project objectives while the PMO optimizes the use of shared organizational resources across all projects   PM manages the constraints (scope, schedule, cost, and quality, etc.) of the individual projects while the PMO manages the methodologies, standards, overall risk/ productivity, and independencies among projects at the enterprise level 17 4/17/11
  • 18.   As a discipline, Project Management developed from several fields of application including construction, engineering, and defense activity.[8]   Two forefathers of project management are Henry Gantt, called the father of planning and control techniques[9], who is famous for his use of the Gantt chart as a project management tool; and Henri Fayol for his creation of the 5 management functions which form the foundation of the body of knowledge associated with project and program management.[10] Both Gantt and Fayol were students of Frederick Winslow Taylor's theories of scientific management. His work is the forerunner to modern project management tools including work breakdown structure (WBS) and 4/17/11 18 resource allocation.
  • 19.   The 1950s marked the beginning of the modern Project Management era. Project management became recognized as a distinct discipline arising from the management discipline.[11] In the United States, prior to the 1950s, projects were managed on an ad hoc basis using mostly Gantt Charts, and informal techniques and tools. At that time, two mathematical project-scheduling models were developed. The "Critical Path Method" (CPM) was developed as a joint venture between DuPont Corporation and Remington Rand Corporation for managing plant maintenance projects. And the " Program Evaluation and Review Technique" or PERT, was developed by Booz-Allen & Hamilton as part of the United States Navy's (in conjunction with the Lockheed Corporation) Polaris missile submarine program;[12] These mathematical techniques quickly spread into many private enterprises.
  • 20.   At the same time, as project-scheduling models were being developed, technology for project cost estimating, cost management, and engineering economics was evolving, with pioneering work by Hans Lang and others. In 1956, the American Association of Cost Engineers (now AACE International; the Association for the Advancement of Cost Engineering) was formed by early practitioners of project management and the associated specialties of planning and scheduling, cost estimating, and cost/schedule control (project control). AACE continued its pioneering work and in 2006 released the first integrated process for portfolio, program and project management ( Total Cost Management Framework). 20 4/17/11
  • 21.   The International Project Management Association (IPMA) was founded in Europe in 1967,[13] as a federation of several national project management associations. IPMA maintains its federal structure today and now includes member associations on every continent except Antarctica. IPMA offers a Four Level Certification program based on the IPMA Competence Baseline (ICB).[14] The ICB covers technical competences, contextual competences, and behavioral competences.   In 1969, the Project Management Institute (PMI) was formed in the USA.[15] PMI publishes A Guide to the Project Management Body of Knowledge (PMBOK Guide), which describes project management practices that are common to "most projects, most of the time."
  • 22. Framework / approach Lifecycle Organization Structure Leadership Styles Team formation Planning Scheduling Execution Monitoring & Control Closure
  • 23.   PMI / PMBoK   PRINCE2   CMMI   Critical Chain Project Management 23 4/17/11
  • 24. 24 4/17/11
  • 25.   PRINCE2 is a structured method for effective project management. It is a "de facto" standard used extensively within UK government and within both UK and international industry. It is a public domain method offering best practice guidance on project management.   PRINCE2 adopts three principles of good project management   A project is a finite process, with a start date and an end date   Projects must be controlled to be successful   All parties must be clear about o  Why the project is needed o  What is to be achieved o  How the outcome will be achieved o  What their responsibilities are
  • 26. 26 4/17/11
  • 27.   “A management environment that is created for the purpose of delivering one or more business products according to a specified Business Case”   “A temporary organisation that is needed to produce a unique and pre-determined outcome or result at a pre- specified time using predetermined resources”   A project has a number of characteristics:   Finite and defined lifespan - the project is covered by a plan showing the date when it is expected to start and the date when it is expected to finish;   Defined and measurable business products - a set of pre-defined products which must be delivered to the Customer;   Corresponding set of activities - A set of planned activities which will deliver the products, including management and technical activities;   Defined amount of resources - an agreed amount of resource which can be used to develop the products;   Organization structure - a defined hierarchy and reporting structure set up specifically for the project.
  • 28. 28 4/17/11