McKenney’s made significant upgrades to the mechanical systems infrastructure—including chillers, piping and pumps—without interrupting data center operations.
Seamless Data Center Operations - Norcross, Georgia
1.
2. Project Name
Large Data Center
Project Location
Norcross, Georgia
Project Team
Owner: Communications Services Provider
General Contractor: Westin Construction
Engineer: Black & Veatch
Specializations
Plumbing Shop Prefab
Energy Management
Pipe Shop Prefab
Sheet Metal Shop Prefab
Markets
Mission Critical
Central Plants
3. McKenney’s made significant upgrades to the mechanical systems
infrastructure—including chillers, piping and pumps—without
interrupting data center operations.
4. The Challenge
Critical equipment in the facility had to remain active, with optimal
redundancy at all times. The engineer and McKenney’s had to develop a
detailed sequence of construction procedures.
The Solution
McKenney’s built a large steel platform in sections above the existing
chillers. Each chiller was individually lifted to its section on the platform
where it was reconnected quickly using prefabricated piping connections.
Once startup and commissioning was completed on the relocated chiller,
the team began to work on the next chiller.
The content of this document is not intended as an endorsement.
5. The Results
The complicated process was completed without any interruption to data
center operations while adhering to facility security procedures. The
customer expressed satisfaction with the quality and expediency of the
work.
6. Atlanta Office: 1056 Moreland Industrial Boulevard
Atlanta, Georgia 30316
P: 404-622-5000
Charlotte Office: 3601 Performance Road
Charlotte, North Carolina 28214
P: 704-357-1200
sales@mckenneys.com
www.mckenneys.com
7. Atlanta Office: 1056 Moreland Industrial Boulevard
Atlanta, Georgia 30316
P: 404-622-5000
Charlotte Office: 3601 Performance Road
Charlotte, North Carolina 28214
P: 704-357-1200
sales@mckenneys.com
www.mckenneys.com