Proposal :
Document Management
System
Jawad Farooq
24.07.2013
Purpose of presentation
• To propose a new Document Management System to DWF and to justify the
decision.
• A high level project management proposal determining criteria to ensure
successful project delivery
Background
• DWF is a business law firm based in Manchester.
• 13 UK offices and 2,500 staff,
• Huge need for all staff throughout to be able to access their documents
anytime, anywhere and with ease.
What is a Document Management System?
• A document management system (DMS) is a computer system used to track and
store electronic documents.
• Document storage formats: PDF, Word, Excel, JPG, emails and more
• Capable of keeping track of any amendments made to the file by version control.
Benefits of a new DMS
• Full management of business documents
• Leads to increased efficiency for all fee-earners & business services to:
– Find documents quickly
– Perform a search accurately
• New system should be easier to use meaning fewer calls to IT Support or
assistance
• Improved compliance in controlling client and other sensitive information
• Reduce risk of losing any documents
Review of potential systems
• M-Files
• SharePoint
• Interwoven Filesite
M-Files
- Creates a drive within my computer to access the
application
M-Files
• Easy to install and manage for the IT Dept
• Easy to drag across an email with attachments into the system
• Full dynamic search, such as by client name or project type etc
• Full access anytime, anywhere inc offline
• Cost?
SharePoint
• Can be
accessed by
Outlook
SharePoint
• Extra benefit if organisation is currently using it for its intranet.
• Full check in/check out functionality
• Customisable views to suit your needs
• Enhanced mobile experience
• Can store all types of files
SharePoint
• Can be costly to customize the site structure
• Search can be limited in certain environments
• Cant be deployed to a small environment with its full capabilities – need a separate
OWA server
Interwoven FileSite
Recommended DMS
• Folder hierarchy for easy organization and sharing
• Quick access lists to last 40 documents, last 10 searches – very useful for busy
fee-earners
• Sophisticated version control to ensure accuracy and currency
• Audit trails to track document histories
Interwoven FileSite
Interwoven FileSite
• Comprehensive ‘profiling capabilities’ to tag and classify each document to aid
search
• Publishing in PDF format automatically linking to original file
• Check out documents remotely
• Powerful security controls access to system functionality
• Integrate with other desktop applications
Interwoven FileSite
Project Lifecycle – PRINCE2
Starting up a Project
Initiating a Project
Directing a Project
Controlling a stage
Managing Product Delivery
Managing a Stage Boundary
Closing a Project
Project Lifecycle - DMS
PROJECT START UP
• Pre-project preparation process
• Includes presentation of outline business case to the newly created Project
Board
• The board will determine whether the new document management system
should be approved
• Should include a feasibility study which showing benefits of implementing
the new document management
• Decision on viability will authorise the project manager to formally
commence the project.
Project Lifecycle - DMS
INITIATE PROJECT / RESEARCH
• After approval ,the project manager will create the Project Initiation Document (PID)
• PID contains information regarding
 The goal of implementing the new DMS
 The scope of delivering the new system
 The project organisation which includes all the people working on the delivery
 The constraints which are enforced to keep the project regimented and
 The business case presented to the board (refined at this stage)
INITIATE PROJECT / RESEARCH
• A Requirements Specification document is created
• Serves as the guideline for building the document management system
• Includes information about :
 who will use this system and how,
 what data will be inputted into the system,
 user requirements etc.
Project Lifecycle - DMS
DESIGN
• System will be designed using the Requirements Specifications document
• This will help determine all hardware and software requirements.
• At this stage, third party suppliers or internal developers will contribute to the
system design
• This ensures that all requirements are possible and can be met.
• It is recommended to involve the Training department in every part of the
project so that they have an excellent understanding of the system.
DEVELOPMENT / IMPLEMENTATION
• The project manager will engage with all stakeholders and assign work packages.
• The project manager will be working with the project team, IT personnel and third
party suppliers to work on the development of the new system.
• The project manager will assign work via work packages,
 monitor progress,
 deal with risks/issues
 be creating/maintaining all project documentation and relevant
communication and report to the board and stakeholders accordingly
Key action : To import all the documents into the new system.
Project Lifecycle - DMS
TESTING
• The system will be continually tested to ensure that its working as it should.
• After full development, testing will be carried out to ensure that the system is
completely functional.
• All documents should be imported/migrated into the new system and testers should
ensure that all documents are fully accessible and not corrupted etc.
• Testing methods include System testing, User Acceptance testing and integration
testing.
• Good opportunity for the Training Dept and IT Support to gain experience with the
system.
• After successful testing and approval, the new system can go live.
Project Lifecycle - DMS
DEPLOYMENT
• The new DMS is fully tested, approved and ready to be launched at DWF.
• The training department will have created all relevant training materials and
training will have been provided to all the users.
• Agreement is needed for parallel working or replacement of the old system with
the new one.
• Immediate replacement of old system will encourage users to adapt to the new
system.
Project Lifecycle - DMS
PROJECT CLOSURE
• After full testing and board approval for official launch, DMS will be in place at
DWF.
• The project manager will create all relevant documentation to formally close
the project including:
 a Closure Report/Post Implementation review
 a Lessons Learned Log
 any manuals
 source code
Project Lifecycle - DMS
MAINTENANCE
• Certain issues may occur occasionally
• Agreed SLA’s with third party suppliers will need to be enforced to rectify
issues.
• Key task: to import any outstanding documents into the new system
Project Lifecycle - DMS
Project Plan
• Defines the approach the project team will use to deliver the new document
management system.
• It must address
 the reasons why the new system is being implemented
 for whom is it being implemented,
 persons responsible for delivering the system
 when the expected delivery date is
• This link will open up an example of a Project Plan
Project Governance
• Ensures that projects are aligned to the organisations objectives, are
delivered efficiently and are sustainable.
• Governance of projects also supports the means by which the project board
and other stakeholders are provided with timely and reliable information.
• For correct governance of the new DMS project the project should follow a
structured methodology, such as Prince2.
5 KEY POINTS SHOULD BE CONSIDERED REGARDING PROJECT GOVERNANCE:
1) Alignment to organisational objectives
Ensure the organisation does the right projects as well as successfully.
If aligned, it will provide the context for the projects purpose
2) Golden threads of delegated authority
Direct chain of accountability from the most senior responsible person to the
individuals responsible for completing tasks stating each persons authority
3) Reporting
Regular report on responsibilities by authority holders
Project Governance
4) Decision gates
Formal points of control at particular points in the project lifecycle. The
project is worked on in small parts.
The next step can be started only after a formal review of the previous stage
and approval granted to move on.
5) Independent assurance
An independent check to review whether objectives will be met.
Creation of a Project Assurance role to provide the assurance of appropriate
conduction of the project
Project Governance
Approval
• At the end of each stage, a meeting will be held with the Project Board
• Agenda:
 Discussion on the development status of the new system
 Progress and cost
 Plan for the next stage
• After board approval, the project manager will be authorised to commence
work on the next stage of the development.
• At the completion of the development of the new system, there will be
confirmation that the project is complete and meets its specified
requirements.
• Occurrence of an issue may require a change to be implemented into the project.
• A change directly linked to the project will be submitted as an Exception Report to
the Board.
• Following their review, the project may either be cancelled or the change may be
authorised. An example of this can be change in project scope.
• A change that’s come about as a result of this project may need to be directed to
the Change Advisory Board via a change request form.
• After review, they will advise on the matter accordingly.
• All changes and requests will be logged in the Change Request Log.
Change
• To avoid wasting time on long due answers or work packages , maybe you need
to escalate this issue before it becomes worse.
But First –
• Have you made a sincere attempt to reach an appropriate resolution but have
found that you are at a dead end?
• Is this an issue that your boss would expect you to handle or to escalate?
• Have you exhausted all other options and any further delay could have a
detrimental effect on the project outcome or deliverables?
• If yes, then escalate to avoid project delay!
Escalation
Project Framework
A Project Management Framework consists of three parts:
• A Project Lifecycle
• A Project Control Cycle
• Tool and Templates Project
Management
Framework
Project
Lifecycle
Tool and
Templates
Project
Control
Cycle
Project Framework
A Project Management Framework supports project implementation because:
 It supports the development and replication of accepted practice.
 Helps communication within the team because of a common language.
 Streamlines the use of tools and techniques for key project management
processes.
 Establishes a consistent approach which aid customers understand the project
management process.
 Ensure that focus is maintained on the early stage of the project lifecycle.
Project Framework
PROJECT LIFECYCLE
Provides guidance on the common stages and steps which apply to all projects
Stage 1 – Business Development
Stage 2 – Tendering
Stage 3 – Contract Negotiation
Stage 4 – Project Mobilisation
Stage 5 – Project Implementation
Stage 6 – Project Close Out
Project Framework
Project Control Cycle
• Describes how each stage in planned and managed.
• Ensures that each stage has the appropriate plan, controls and corrective actions
in place.
The 4 stages are:
Stage 1 – Plan: Establish scope, timelines and budgets
Stage 2 – Do: Initiate work and allocate resources
Stage 3 – Check: Progress against baselines, quality control and costs
Stage 4 – Act: Control changes, review risks and plan corrective actions.
Project Framework
TEMPLATE AND TOOLS
• Simple templates and tools support the implementation of project management.
• Using standardised templates support a common methodology and processes
• Examples of templates include:
 - Project Plan
 - Risk Log
 - Checkpoint Report
Stakeholder Management
IDENTIFY
The implementation of a DMS will involve a large number of stakeholders, including:
• CIO/Head of IT – sign off/make aware of project
• IT Teams – Service Desk to support queries regarding new system; Network Team
to support installation of new system on infrastructure
If the system is to be developed in-house, then internal development team will need
to be involved.
• Test Team – test new application is fully accessible by all users; ensure data
integrity. Ideally include end users.
• Document Specialists – Verify the documents before and after migration to ensure
no corruption
Stakeholder Management
IDENTIFY
• Third party suppliers – ensure they’re fully aware of timeframes and agree SLA’s
• Fee-earners – ensure representatives confirm that they’re generally happy with
the new system
• Marketing/Communications – to launch the firm-wide campaign promoting the new
system
• Training – to create training sessions & materials for all end users and IT Support
staff
• PROJECT TEAM – the project support team assisting the project manager with the
management and coordination of all aspects of the project
Stakeholder Management
PRIORITISE ROLES - High power, high interest: Fully engage these
people and keep satisfied
- High power, low interest : Keep these people
satisfied, but not so much that they become
bored with the message.
- Low power, high interest: Keep these people
adequately informed; talk to them to ensure that
no issues arise. These people can often be very
helpful with the detail of the project.
- Low power, low interest: Monitor these
people, but do not bore them with excessive
communication.
Stakeholder Management
Prioritise roles
• High power, high interest
IT teams, Third party suppliers,
project team
• High power, low interest:
End-users / fee-earners
• Low power, high interest:
Marketing team,
• Low power, low interest
Rest of business that wont use the system
IT
teams, Third
party
suppliers, proj
ect team
End
users/Fee
earners
Marketing
Team
Rest of
Business
Stakeholder Management
Prioritise roles
• Once the roles of each stakeholder has been determined, the appropriate level of
communications between them can be arranged,
• For example: they attend a twice weekly meeting, or they receive an email once a
week providing status update
Communications Approach
Examples of communications approach that the firm can use to promote the new
document management system include:
• Email sent out to all staff advising of new proposed system with expected
timeframes
• Marketing team to send out newsletters highlighting the new system, its benefits
and reasons for the new document management system
• Posters put up in key areas advising users of the new system
• IT Support to advise users of the new system when they call in with a query
• A message to be displayed on the firms intranet.
Risk, Action and Issue Management
• Risks, actions and issues should be identified at the start of the
project, recorded in logs and then monitored throughout the project lifecycle.
• A brainstorming session with the project team and stakeholders will bring out
possible issues and risks and actions to ensure successful delivery.
• Capture this information in Individual or joint logs (RAID log) including
 who raised the point
 a level of priority
 timing when it was identified and
 a target resolution date.
Risk Management
• Risk: something which could threaten the achievement of project objectives.
It is a POTENTIAL issue
• Risk management: Identification, assessment and prioritisation of an event
that can have both a negative and a positive effect.
• The new document management system can yield many risks which must be
logged and workarounds planned in the event that they occur.
Examples of risks can include:
What if the documents don’t migrate across accurately?
• What if we lose some documents?
• Affect of this product on company revenue?
• Will users learnt this new system with ease?
• Costs associated with late delivery?
• Are all the software applications compatible with the new DMS?
• Are staff committed for the entire duration of the project?
All the identified risks should have a contingency plan that should be approved of
and implemented in the event that the risk occurs.
Risk Management
Issue Management
• Issue: is something which has happened and threatens achievement of project’s
objectives.
• An issue resolution process should be in place before the project starts to ensure
the project remains on track.
• Issue management is the process of identifying and resolving issues.
• Examples of issues can include:
 User ‘buy-in’ to the new system
 Problems with staff – relating to resources
 Third party suppliers – such as delays with the delivery of a product
 Technical failures – such as a technological problem in the project
Action Management
• An action plan is used to formally and systematically lay out the steps that need to
be taken for successful implementation.
• All the actions that need to be completed must be logged.
• For each action, there will be an owner assigned to complete the action by a
specified date.
• Examples of actions can be:
 Creation of project documentation
 Engage third party suppliers
 Create training materials
Thank you
Questions?

More Related Content

What's hot

Software Project Management lecture 10
Software Project Management lecture 10Software Project Management lecture 10
Software Project Management lecture 10Syed Muhammad Hammad
 
Configuration Management is Old and Boring
Configuration Management is Old and BoringConfiguration Management is Old and Boring
Configuration Management is Old and BoringMandi Walls
 
CS 414 (IT Project Management)
CS 414 (IT Project Management)CS 414 (IT Project Management)
CS 414 (IT Project Management)raszky
 
Configuration Management
Configuration ManagementConfiguration Management
Configuration ManagementSaqib Raza
 
Other software processes (Software project Management)
Other software processes (Software project Management)Other software processes (Software project Management)
Other software processes (Software project Management)Ankit Gupta
 
Four Essential Steps for Removing Risk and Downtime from POWER9 Migration
Four Essential Steps for Removing Risk and Downtime from POWER9 MigrationFour Essential Steps for Removing Risk and Downtime from POWER9 Migration
Four Essential Steps for Removing Risk and Downtime from POWER9 MigrationPrecisely
 
Risk managementforsponsors barnes
Risk managementforsponsors barnesRisk managementforsponsors barnes
Risk managementforsponsors barnescaptsumit
 
Software Project Management lecture 9
Software Project Management lecture 9Software Project Management lecture 9
Software Project Management lecture 9Syed Muhammad Hammad
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system projectalpha1unity
 
PeopleSoft Upgrades: Best Practices
PeopleSoft Upgrades: Best PracticesPeopleSoft Upgrades: Best Practices
PeopleSoft Upgrades: Best PracticesEmtec Inc.
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)ShudipPal
 
503-Cathy Kirch Releasing Release Management-Final
503-Cathy Kirch Releasing Release Management-Final503-Cathy Kirch Releasing Release Management-Final
503-Cathy Kirch Releasing Release Management-FinalCathy Kirch
 
Are processes masquerading as projects hurting your business
Are processes masquerading as projects hurting your businessAre processes masquerading as projects hurting your business
Are processes masquerading as projects hurting your businessBen Bradley
 
Pc Order To Installation Cycle Time Reduction Display
Pc Order To Installation Cycle Time Reduction DisplayPc Order To Installation Cycle Time Reduction Display
Pc Order To Installation Cycle Time Reduction Displaywhayes2000
 
BP Logix Whitepaper: Adding the Dimension of Time to BPM
BP Logix Whitepaper: Adding the Dimension of Time to BPMBP Logix Whitepaper: Adding the Dimension of Time to BPM
BP Logix Whitepaper: Adding the Dimension of Time to BPMBP Logix
 

What's hot (19)

Software Project Management lecture 10
Software Project Management lecture 10Software Project Management lecture 10
Software Project Management lecture 10
 
Kenneth M. Fischler
Kenneth M. FischlerKenneth M. Fischler
Kenneth M. Fischler
 
Configuration Management is Old and Boring
Configuration Management is Old and BoringConfiguration Management is Old and Boring
Configuration Management is Old and Boring
 
CS 414 (IT Project Management)
CS 414 (IT Project Management)CS 414 (IT Project Management)
CS 414 (IT Project Management)
 
PI Training July 2015
PI Training July 2015PI Training July 2015
PI Training July 2015
 
Configuration Management
Configuration ManagementConfiguration Management
Configuration Management
 
Software that truly supports good decisions
Software that truly supports good decisionsSoftware that truly supports good decisions
Software that truly supports good decisions
 
Other software processes (Software project Management)
Other software processes (Software project Management)Other software processes (Software project Management)
Other software processes (Software project Management)
 
Four Essential Steps for Removing Risk and Downtime from POWER9 Migration
Four Essential Steps for Removing Risk and Downtime from POWER9 MigrationFour Essential Steps for Removing Risk and Downtime from POWER9 Migration
Four Essential Steps for Removing Risk and Downtime from POWER9 Migration
 
Risk managementforsponsors barnes
Risk managementforsponsors barnesRisk managementforsponsors barnes
Risk managementforsponsors barnes
 
Agile pgm
Agile pgmAgile pgm
Agile pgm
 
Software Project Management lecture 9
Software Project Management lecture 9Software Project Management lecture 9
Software Project Management lecture 9
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system project
 
PeopleSoft Upgrades: Best Practices
PeopleSoft Upgrades: Best PracticesPeopleSoft Upgrades: Best Practices
PeopleSoft Upgrades: Best Practices
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 
503-Cathy Kirch Releasing Release Management-Final
503-Cathy Kirch Releasing Release Management-Final503-Cathy Kirch Releasing Release Management-Final
503-Cathy Kirch Releasing Release Management-Final
 
Are processes masquerading as projects hurting your business
Are processes masquerading as projects hurting your businessAre processes masquerading as projects hurting your business
Are processes masquerading as projects hurting your business
 
Pc Order To Installation Cycle Time Reduction Display
Pc Order To Installation Cycle Time Reduction DisplayPc Order To Installation Cycle Time Reduction Display
Pc Order To Installation Cycle Time Reduction Display
 
BP Logix Whitepaper: Adding the Dimension of Time to BPM
BP Logix Whitepaper: Adding the Dimension of Time to BPMBP Logix Whitepaper: Adding the Dimension of Time to BPM
BP Logix Whitepaper: Adding the Dimension of Time to BPM
 

Viewers also liked

Viewers also liked (7)

How Search Marketing Is Morphing Into ZMOT Marketing Thought Paper
How Search Marketing Is Morphing Into ZMOT Marketing Thought PaperHow Search Marketing Is Morphing Into ZMOT Marketing Thought Paper
How Search Marketing Is Morphing Into ZMOT Marketing Thought Paper
 
Why ig
Why igWhy ig
Why ig
 
Wildnet Technologies Reviews - #WildnetTechnologiesReview
Wildnet Technologies Reviews - #WildnetTechnologiesReviewWildnet Technologies Reviews - #WildnetTechnologiesReview
Wildnet Technologies Reviews - #WildnetTechnologiesReview
 
PageTraffic Reviews Metric Driven SEO at TFMA
PageTraffic Reviews Metric Driven SEO at TFMA PageTraffic Reviews Metric Driven SEO at TFMA
PageTraffic Reviews Metric Driven SEO at TFMA
 
Next Generation SEO
Next Generation SEONext Generation SEO
Next Generation SEO
 
Content marketing
Content marketingContent marketing
Content marketing
 
Proposal DMS
Proposal   DMS Proposal   DMS
Proposal DMS
 

Similar to Proposal dms for dwf v2

DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)Logitrain: New Zealand
 
UNIT-III SYSTEM DEVELOPMENT LIFE CYCLE.pptx
UNIT-III SYSTEM DEVELOPMENT LIFE CYCLE.pptxUNIT-III SYSTEM DEVELOPMENT LIFE CYCLE.pptx
UNIT-III SYSTEM DEVELOPMENT LIFE CYCLE.pptxabhiisharma0504
 
ERP / MRP - Selection, Qualifying, Implementation
ERP / MRP - Selection, Qualifying, ImplementationERP / MRP - Selection, Qualifying, Implementation
ERP / MRP - Selection, Qualifying, Implementationwww.SMARTvt.org
 
ISBB_Chapter10.pptx
ISBB_Chapter10.pptxISBB_Chapter10.pptx
ISBB_Chapter10.pptxAronBalais1
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system projecta23ccb
 
INAAU Project Management for Telecommunications Professionals
INAAU Project Management for Telecommunications ProfessionalsINAAU Project Management for Telecommunications Professionals
INAAU Project Management for Telecommunications ProfessionalsRory McKenna
 
UNIT V - 1 SPM.pptx
UNIT V - 1 SPM.pptxUNIT V - 1 SPM.pptx
UNIT V - 1 SPM.pptxDevnath13
 
2 approaches to system development
2 approaches to system development2 approaches to system development
2 approaches to system developmentcymark09
 
A guide for the rolling out of a software delivery project
A guide for the rolling out of a software delivery projectA guide for the rolling out of a software delivery project
A guide for the rolling out of a software delivery projectProject Management Solutions
 
Time management
Time management Time management
Time management Pm Joe
 

Similar to Proposal dms for dwf v2 (20)

Proj Mgmt.ppt
Proj Mgmt.pptProj Mgmt.ppt
Proj Mgmt.ppt
 
SPM_UNIT-1(1).pptx
SPM_UNIT-1(1).pptxSPM_UNIT-1(1).pptx
SPM_UNIT-1(1).pptx
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)
 
UNIT-III SYSTEM DEVELOPMENT LIFE CYCLE.pptx
UNIT-III SYSTEM DEVELOPMENT LIFE CYCLE.pptxUNIT-III SYSTEM DEVELOPMENT LIFE CYCLE.pptx
UNIT-III SYSTEM DEVELOPMENT LIFE CYCLE.pptx
 
Seminar on Project Management by Rj
Seminar on Project Management by RjSeminar on Project Management by Rj
Seminar on Project Management by Rj
 
ERP / MRP - Selection, Qualifying, Implementation
ERP / MRP - Selection, Qualifying, ImplementationERP / MRP - Selection, Qualifying, Implementation
ERP / MRP - Selection, Qualifying, Implementation
 
ISBB_Chapter10.pptx
ISBB_Chapter10.pptxISBB_Chapter10.pptx
ISBB_Chapter10.pptx
 
Lecture 2.pptx
Lecture 2.pptxLecture 2.pptx
Lecture 2.pptx
 
CISA Training - Chapter 3 - 2016
CISA Training - Chapter 3 - 2016CISA Training - Chapter 3 - 2016
CISA Training - Chapter 3 - 2016
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system project
 
INAAU Project Management for Telecommunications Professionals
INAAU Project Management for Telecommunications ProfessionalsINAAU Project Management for Telecommunications Professionals
INAAU Project Management for Telecommunications Professionals
 
UNIT V - 1 SPM.pptx
UNIT V - 1 SPM.pptxUNIT V - 1 SPM.pptx
UNIT V - 1 SPM.pptx
 
ecse ppt.pptx
ecse ppt.pptxecse ppt.pptx
ecse ppt.pptx
 
2 approaches to system development
2 approaches to system development2 approaches to system development
2 approaches to system development
 
A guide for the rolling out of a software delivery project
A guide for the rolling out of a software delivery projectA guide for the rolling out of a software delivery project
A guide for the rolling out of a software delivery project
 
Project scheduler doc
Project scheduler docProject scheduler doc
Project scheduler doc
 
ecse ppt.pptx
ecse ppt.pptxecse ppt.pptx
ecse ppt.pptx
 
Robert Latest cv
Robert Latest cvRobert Latest cv
Robert Latest cv
 
Time management
Time management Time management
Time management
 

More from Media-Mosaic

Top 5 Benefits of SEO
Top 5 Benefits of SEOTop 5 Benefits of SEO
Top 5 Benefits of SEOMedia-Mosaic
 
Travelers Resource for Tripadvisor (Infographic)
Travelers Resource for Tripadvisor (Infographic)Travelers Resource for Tripadvisor (Infographic)
Travelers Resource for Tripadvisor (Infographic)Media-Mosaic
 
How to win the zero moment of truth marketing strategies (Zmot infographic)
How to win the zero moment of truth marketing strategies (Zmot infographic)How to win the zero moment of truth marketing strategies (Zmot infographic)
How to win the zero moment of truth marketing strategies (Zmot infographic)Media-Mosaic
 
Case studies pages4
Case studies pages4Case studies pages4
Case studies pages4Media-Mosaic
 
Search Marketing (case-study)
Search Marketing (case-study)Search Marketing (case-study)
Search Marketing (case-study)Media-Mosaic
 
Power of Content marketing
Power of Content marketingPower of Content marketing
Power of Content marketingMedia-Mosaic
 
Facebook Strategies: Media-Mosaic
Facebook Strategies: Media-Mosaic Facebook Strategies: Media-Mosaic
Facebook Strategies: Media-Mosaic Media-Mosaic
 

More from Media-Mosaic (11)

Top 5 Benefits of SEO
Top 5 Benefits of SEOTop 5 Benefits of SEO
Top 5 Benefits of SEO
 
Travelers Resource for Tripadvisor (Infographic)
Travelers Resource for Tripadvisor (Infographic)Travelers Resource for Tripadvisor (Infographic)
Travelers Resource for Tripadvisor (Infographic)
 
How to win the zero moment of truth marketing strategies (Zmot infographic)
How to win the zero moment of truth marketing strategies (Zmot infographic)How to win the zero moment of truth marketing strategies (Zmot infographic)
How to win the zero moment of truth marketing strategies (Zmot infographic)
 
Seo
SeoSeo
Seo
 
Good to-great
Good to-greatGood to-great
Good to-great
 
Case studies pages4
Case studies pages4Case studies pages4
Case studies pages4
 
Search Marketing (case-study)
Search Marketing (case-study)Search Marketing (case-study)
Search Marketing (case-study)
 
Power of Content marketing
Power of Content marketingPower of Content marketing
Power of Content marketing
 
Facebook Strategies: Media-Mosaic
Facebook Strategies: Media-Mosaic Facebook Strategies: Media-Mosaic
Facebook Strategies: Media-Mosaic
 
Negotiation
NegotiationNegotiation
Negotiation
 
Company profile
Company profileCompany profile
Company profile
 

Recently uploaded

[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsJoaquim Jorge
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?Antenna Manufacturer Coco
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoffsammart93
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024The Digital Insurer
 
Evaluating the top large language models.pdf
Evaluating the top large language models.pdfEvaluating the top large language models.pdf
Evaluating the top large language models.pdfChristopherTHyatt
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdflior mazor
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century educationjfdjdjcjdnsjd
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 

Recently uploaded (20)

[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
Evaluating the top large language models.pdf
Evaluating the top large language models.pdfEvaluating the top large language models.pdf
Evaluating the top large language models.pdf
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 

Proposal dms for dwf v2

  • 2. Purpose of presentation • To propose a new Document Management System to DWF and to justify the decision. • A high level project management proposal determining criteria to ensure successful project delivery
  • 3. Background • DWF is a business law firm based in Manchester. • 13 UK offices and 2,500 staff, • Huge need for all staff throughout to be able to access their documents anytime, anywhere and with ease.
  • 4. What is a Document Management System? • A document management system (DMS) is a computer system used to track and store electronic documents. • Document storage formats: PDF, Word, Excel, JPG, emails and more • Capable of keeping track of any amendments made to the file by version control.
  • 5. Benefits of a new DMS • Full management of business documents • Leads to increased efficiency for all fee-earners & business services to: – Find documents quickly – Perform a search accurately • New system should be easier to use meaning fewer calls to IT Support or assistance • Improved compliance in controlling client and other sensitive information • Reduce risk of losing any documents
  • 6. Review of potential systems • M-Files • SharePoint • Interwoven Filesite
  • 7. M-Files - Creates a drive within my computer to access the application
  • 8. M-Files • Easy to install and manage for the IT Dept • Easy to drag across an email with attachments into the system • Full dynamic search, such as by client name or project type etc • Full access anytime, anywhere inc offline • Cost?
  • 10. SharePoint • Extra benefit if organisation is currently using it for its intranet. • Full check in/check out functionality • Customisable views to suit your needs • Enhanced mobile experience • Can store all types of files
  • 11. SharePoint • Can be costly to customize the site structure • Search can be limited in certain environments • Cant be deployed to a small environment with its full capabilities – need a separate OWA server
  • 12. Interwoven FileSite Recommended DMS • Folder hierarchy for easy organization and sharing • Quick access lists to last 40 documents, last 10 searches – very useful for busy fee-earners • Sophisticated version control to ensure accuracy and currency • Audit trails to track document histories
  • 14. Interwoven FileSite • Comprehensive ‘profiling capabilities’ to tag and classify each document to aid search • Publishing in PDF format automatically linking to original file • Check out documents remotely • Powerful security controls access to system functionality • Integrate with other desktop applications
  • 16. Project Lifecycle – PRINCE2 Starting up a Project Initiating a Project Directing a Project Controlling a stage Managing Product Delivery Managing a Stage Boundary Closing a Project
  • 17. Project Lifecycle - DMS PROJECT START UP • Pre-project preparation process • Includes presentation of outline business case to the newly created Project Board • The board will determine whether the new document management system should be approved • Should include a feasibility study which showing benefits of implementing the new document management • Decision on viability will authorise the project manager to formally commence the project.
  • 18. Project Lifecycle - DMS INITIATE PROJECT / RESEARCH • After approval ,the project manager will create the Project Initiation Document (PID) • PID contains information regarding  The goal of implementing the new DMS  The scope of delivering the new system  The project organisation which includes all the people working on the delivery  The constraints which are enforced to keep the project regimented and  The business case presented to the board (refined at this stage)
  • 19. INITIATE PROJECT / RESEARCH • A Requirements Specification document is created • Serves as the guideline for building the document management system • Includes information about :  who will use this system and how,  what data will be inputted into the system,  user requirements etc.
  • 20. Project Lifecycle - DMS DESIGN • System will be designed using the Requirements Specifications document • This will help determine all hardware and software requirements. • At this stage, third party suppliers or internal developers will contribute to the system design • This ensures that all requirements are possible and can be met. • It is recommended to involve the Training department in every part of the project so that they have an excellent understanding of the system.
  • 21. DEVELOPMENT / IMPLEMENTATION • The project manager will engage with all stakeholders and assign work packages. • The project manager will be working with the project team, IT personnel and third party suppliers to work on the development of the new system. • The project manager will assign work via work packages,  monitor progress,  deal with risks/issues  be creating/maintaining all project documentation and relevant communication and report to the board and stakeholders accordingly Key action : To import all the documents into the new system. Project Lifecycle - DMS
  • 22. TESTING • The system will be continually tested to ensure that its working as it should. • After full development, testing will be carried out to ensure that the system is completely functional. • All documents should be imported/migrated into the new system and testers should ensure that all documents are fully accessible and not corrupted etc. • Testing methods include System testing, User Acceptance testing and integration testing. • Good opportunity for the Training Dept and IT Support to gain experience with the system. • After successful testing and approval, the new system can go live. Project Lifecycle - DMS
  • 23. DEPLOYMENT • The new DMS is fully tested, approved and ready to be launched at DWF. • The training department will have created all relevant training materials and training will have been provided to all the users. • Agreement is needed for parallel working or replacement of the old system with the new one. • Immediate replacement of old system will encourage users to adapt to the new system. Project Lifecycle - DMS
  • 24. PROJECT CLOSURE • After full testing and board approval for official launch, DMS will be in place at DWF. • The project manager will create all relevant documentation to formally close the project including:  a Closure Report/Post Implementation review  a Lessons Learned Log  any manuals  source code Project Lifecycle - DMS
  • 25. MAINTENANCE • Certain issues may occur occasionally • Agreed SLA’s with third party suppliers will need to be enforced to rectify issues. • Key task: to import any outstanding documents into the new system Project Lifecycle - DMS
  • 26. Project Plan • Defines the approach the project team will use to deliver the new document management system. • It must address  the reasons why the new system is being implemented  for whom is it being implemented,  persons responsible for delivering the system  when the expected delivery date is • This link will open up an example of a Project Plan
  • 27. Project Governance • Ensures that projects are aligned to the organisations objectives, are delivered efficiently and are sustainable. • Governance of projects also supports the means by which the project board and other stakeholders are provided with timely and reliable information. • For correct governance of the new DMS project the project should follow a structured methodology, such as Prince2.
  • 28. 5 KEY POINTS SHOULD BE CONSIDERED REGARDING PROJECT GOVERNANCE: 1) Alignment to organisational objectives Ensure the organisation does the right projects as well as successfully. If aligned, it will provide the context for the projects purpose 2) Golden threads of delegated authority Direct chain of accountability from the most senior responsible person to the individuals responsible for completing tasks stating each persons authority 3) Reporting Regular report on responsibilities by authority holders Project Governance
  • 29. 4) Decision gates Formal points of control at particular points in the project lifecycle. The project is worked on in small parts. The next step can be started only after a formal review of the previous stage and approval granted to move on. 5) Independent assurance An independent check to review whether objectives will be met. Creation of a Project Assurance role to provide the assurance of appropriate conduction of the project Project Governance
  • 30. Approval • At the end of each stage, a meeting will be held with the Project Board • Agenda:  Discussion on the development status of the new system  Progress and cost  Plan for the next stage • After board approval, the project manager will be authorised to commence work on the next stage of the development. • At the completion of the development of the new system, there will be confirmation that the project is complete and meets its specified requirements.
  • 31. • Occurrence of an issue may require a change to be implemented into the project. • A change directly linked to the project will be submitted as an Exception Report to the Board. • Following their review, the project may either be cancelled or the change may be authorised. An example of this can be change in project scope. • A change that’s come about as a result of this project may need to be directed to the Change Advisory Board via a change request form. • After review, they will advise on the matter accordingly. • All changes and requests will be logged in the Change Request Log. Change
  • 32. • To avoid wasting time on long due answers or work packages , maybe you need to escalate this issue before it becomes worse. But First – • Have you made a sincere attempt to reach an appropriate resolution but have found that you are at a dead end? • Is this an issue that your boss would expect you to handle or to escalate? • Have you exhausted all other options and any further delay could have a detrimental effect on the project outcome or deliverables? • If yes, then escalate to avoid project delay! Escalation
  • 33. Project Framework A Project Management Framework consists of three parts: • A Project Lifecycle • A Project Control Cycle • Tool and Templates Project Management Framework Project Lifecycle Tool and Templates Project Control Cycle
  • 34. Project Framework A Project Management Framework supports project implementation because:  It supports the development and replication of accepted practice.  Helps communication within the team because of a common language.  Streamlines the use of tools and techniques for key project management processes.  Establishes a consistent approach which aid customers understand the project management process.  Ensure that focus is maintained on the early stage of the project lifecycle.
  • 35. Project Framework PROJECT LIFECYCLE Provides guidance on the common stages and steps which apply to all projects Stage 1 – Business Development Stage 2 – Tendering Stage 3 – Contract Negotiation Stage 4 – Project Mobilisation Stage 5 – Project Implementation Stage 6 – Project Close Out
  • 36. Project Framework Project Control Cycle • Describes how each stage in planned and managed. • Ensures that each stage has the appropriate plan, controls and corrective actions in place. The 4 stages are: Stage 1 – Plan: Establish scope, timelines and budgets Stage 2 – Do: Initiate work and allocate resources Stage 3 – Check: Progress against baselines, quality control and costs Stage 4 – Act: Control changes, review risks and plan corrective actions.
  • 37. Project Framework TEMPLATE AND TOOLS • Simple templates and tools support the implementation of project management. • Using standardised templates support a common methodology and processes • Examples of templates include:  - Project Plan  - Risk Log  - Checkpoint Report
  • 38. Stakeholder Management IDENTIFY The implementation of a DMS will involve a large number of stakeholders, including: • CIO/Head of IT – sign off/make aware of project • IT Teams – Service Desk to support queries regarding new system; Network Team to support installation of new system on infrastructure If the system is to be developed in-house, then internal development team will need to be involved. • Test Team – test new application is fully accessible by all users; ensure data integrity. Ideally include end users. • Document Specialists – Verify the documents before and after migration to ensure no corruption
  • 39. Stakeholder Management IDENTIFY • Third party suppliers – ensure they’re fully aware of timeframes and agree SLA’s • Fee-earners – ensure representatives confirm that they’re generally happy with the new system • Marketing/Communications – to launch the firm-wide campaign promoting the new system • Training – to create training sessions & materials for all end users and IT Support staff • PROJECT TEAM – the project support team assisting the project manager with the management and coordination of all aspects of the project
  • 40. Stakeholder Management PRIORITISE ROLES - High power, high interest: Fully engage these people and keep satisfied - High power, low interest : Keep these people satisfied, but not so much that they become bored with the message. - Low power, high interest: Keep these people adequately informed; talk to them to ensure that no issues arise. These people can often be very helpful with the detail of the project. - Low power, low interest: Monitor these people, but do not bore them with excessive communication.
  • 41. Stakeholder Management Prioritise roles • High power, high interest IT teams, Third party suppliers, project team • High power, low interest: End-users / fee-earners • Low power, high interest: Marketing team, • Low power, low interest Rest of business that wont use the system IT teams, Third party suppliers, proj ect team End users/Fee earners Marketing Team Rest of Business
  • 42. Stakeholder Management Prioritise roles • Once the roles of each stakeholder has been determined, the appropriate level of communications between them can be arranged, • For example: they attend a twice weekly meeting, or they receive an email once a week providing status update
  • 43. Communications Approach Examples of communications approach that the firm can use to promote the new document management system include: • Email sent out to all staff advising of new proposed system with expected timeframes • Marketing team to send out newsletters highlighting the new system, its benefits and reasons for the new document management system • Posters put up in key areas advising users of the new system • IT Support to advise users of the new system when they call in with a query • A message to be displayed on the firms intranet.
  • 44. Risk, Action and Issue Management • Risks, actions and issues should be identified at the start of the project, recorded in logs and then monitored throughout the project lifecycle. • A brainstorming session with the project team and stakeholders will bring out possible issues and risks and actions to ensure successful delivery. • Capture this information in Individual or joint logs (RAID log) including  who raised the point  a level of priority  timing when it was identified and  a target resolution date.
  • 45. Risk Management • Risk: something which could threaten the achievement of project objectives. It is a POTENTIAL issue • Risk management: Identification, assessment and prioritisation of an event that can have both a negative and a positive effect. • The new document management system can yield many risks which must be logged and workarounds planned in the event that they occur.
  • 46. Examples of risks can include: What if the documents don’t migrate across accurately? • What if we lose some documents? • Affect of this product on company revenue? • Will users learnt this new system with ease? • Costs associated with late delivery? • Are all the software applications compatible with the new DMS? • Are staff committed for the entire duration of the project? All the identified risks should have a contingency plan that should be approved of and implemented in the event that the risk occurs. Risk Management
  • 47. Issue Management • Issue: is something which has happened and threatens achievement of project’s objectives. • An issue resolution process should be in place before the project starts to ensure the project remains on track. • Issue management is the process of identifying and resolving issues. • Examples of issues can include:  User ‘buy-in’ to the new system  Problems with staff – relating to resources  Third party suppliers – such as delays with the delivery of a product  Technical failures – such as a technological problem in the project
  • 48. Action Management • An action plan is used to formally and systematically lay out the steps that need to be taken for successful implementation. • All the actions that need to be completed must be logged. • For each action, there will be an owner assigned to complete the action by a specified date. • Examples of actions can be:  Creation of project documentation  Engage third party suppliers  Create training materials