Earned Value Management (EVM)
Measure Project Performance
Earned Value Management (EVM)
Earned Value Management (EVM)
Earned Value Management (EVM) is a project management methodology used to
track project performance as well as forecast future performance. EVM integrates
the scope baseline, schedule baseline and cost to provide performance
measurements. Results can be expressed in dollars and/or percentage.
EVM can be used to report current/past project performance, and predict future
project performance based on current/past performance.
Variance Analysis Forecasting
Current/Past Performance Future Performance
PART 1 - BUILDING BLOCKS
Earned Value Management (EVM)
Earned Value Management (EVM)
Starts with 3 building blocks that will be used in all EVM calculations.
Budgeted amount planned to be spent at a point in
time of the project
Planned Value
(PV)
Earned Value
(EV)
Actual Cost
(AC)
Measurement of completed work according to the
budget at a point in time of the project lifecycle
Cost incurred for the work performed at a point
in time of the project lifecycle
Earned Value Management (EVM)
Earned Value Management (EVM)
Scenario:
You are assigned to manage a 12 month project estimated to cost $36,000 at
the end of the project. Today is the end of month 3 and you are 20%
complete. According to the Finance Department you have spent $7,500 to
date.
Planned Value (PV)
1. Calculate % Planned. 3 months / 12 months = .25
2. Calculate $ Planned. $36,000 * .25 = $9,000
Planned Value
(PV)
Earned Value
(EV)
Actual Cost
(AC)
Earned Value (EV)
1. Determine % Complete = .20
2. Calculate $ Earned = 36,000 * .20 = 7,000
Actual Cost (AC)
1. Actual cost provided = $7,500
Earned Value Management (EVM)
PART 2 - VARIANCE ANALYSIS
Earned Value Management (EVM)
Earned Value Management (EVM)
Variance Analysis can be used to monitor project performance based on
schedule and cost. Each method can be expressed in a dollar value or
percentage.
Schedule Variance
• Schedule Variance (SV)
Project schedule performance expressed in dollars
• Schedule Performance Index (SPI)
Project schedule performance expressed in a percentage
Cost Variance
• Cost Variance (CV)
Project cost performance expressed in dollars
• Cost Performance Index (CPI)
Project cost performance expressed in a percentage
Earned Value Management (EVM)
• Schedule Variance (SV) –Project performance expressed in dollars.
SV = EV – PV
SV = 7,000 – 9,000
SV = (2,000)
• Schedule Performance Index (SPI) – Project performance expressed as
a percent.
SPI = EV / PV
SPI = 7,000 / 9,000
SPI = .78
Earned Value Management (EVM)
Schedule Variance Analysis uses EV and PV to calculate a variance to the
project schedule.
Earned Value Management (EVM)
Earned Value Management
Planned Value PV $9,000
Earned Value EV $7,000
Actual Cost AC $7,500
• Cost Variance (CV) –Project performance expressed in dollars.
CV = EV – AC
CV = 7,000 – 7,500
CV = (500)
• Cost Performance Index (CPI) – Project performance expressed as a
percent.
CPI = EV / AC
CPI = 7,000 / 7,500
CPI = .93
Earned Value Management (EVM)
Cost Variance Analysis uses EV and AC to calculate a variance to the project
budget (cost).
Earned Value Management
Planned Value PV $9,000
Earned Value EV $7,000
Actual Cost AC $7,500
Earned Value Management (EVM)
PART 3 - FORECASTING
Earned Value Management (EVM)
Earned Value Management (EVM)
Earned Value Management (EVM)
We can also use EVM to forecast future project spending. Estimate at
Completion (EAC) can be calculated using the 3 following methods:
Project will continue to perform at the budgeted rate
EAC = AC + (BAC – EV)
Budgeted Rate
Current CPI
Current
CPI & SPI
Project will continue to perform at the current CPI:
EAC = BAC / CPI
Project will continue to perform at the current
CPI & SPI:
EAC = AC + [(BAC – EV) / (CPI * SPI)]
Earned Value Management (EVM)
Estimate at Completion (EAC)
Estimate at Completion (EAC) – Budgeted Rate:
EAC = AC + (BAC – EV)
EAC = 7,500 + (36,000 – 7,000)
EAC = 7,500 + 29,000
EAC = $36,500
Earned Value Management (EVM)
Forecasting using Estimate at Completion (EAC) at the Budgeted rate,
assumes the project will continue to perform at the currently budgeted
rate.
Earned Value Management (EVM)
Estimate at Completion (EAC) – Current CPI
EAC = BAC / CPI
EAC = 36,000 / .78
EAC = $46,153.84
Earned Value Management (EVM)
Forecasting using Estimate at Completion at the current CPI, assumes the
project will continue to perform at the Cost Performance Index (CPI)
Earned Value Management (EVM)
Estimate at Completion (EAC) – Current CPI & SPI
EAC = AC + [(BAC – EV) / (CPI * SPI)]
EAC = 7,500 + [(36,000 – 7,000) / (.78 * .93)]
EAC = 7,500 + [29,000 / .7254]
EAC = 7,500 + 39,977.94
EAC = 47,477.94
Earned Value Management (EVM)
Forecasting using Estimate at Completion at the current CPI & SPI,
assumes the project will continue to perform at the Cost Performance
Index (CPI) and Schedule Performance Index (SPI)
Earned Value Management (EVM)
To Complete Performance Index (TCPI)
Based on Balance at Completion:
TCPI = [(BAC – EV) / (BAC - AC)]
TCPI = [(36,000 – 7,000) / (36,000 – 7,500)]
TCPI = (29,000) / (28,500)
TCPI = 1.01
Earned Value Management (EVM)
Earned Value Management (EVM)
To Complete Performance Index (TCPI) Measure of schedule performance
on a project.
To Complete Performance Index (TCPI)
Based on Estimate to Complete:
TCPI = (BAC - EV) / (EAC – AC)
TCPI = (36,000 – 7000) / (36,500 – 7,500)
TCPI = 29,000 / 29,000
TCPI = 1.0
Earned Value Management (EVM)
Earned Value Management (EVM)
To Complete Performance Index (TCPI) Measure of schedule performance
on a project.
PART 4 - PERFORMANCE REVIEWS
Earned Value Management (EVM)
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
PV 3,000 6,000 9,000 12,000 15,000 18,000 21,000 24,000 27,000 30,000 33,000 36,000
EV 3,240 5,400 7,200 10,000 13,000 15,000
AC 3,500 7,000 10,000 14,000 17,500 21,000
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
Earned Value Management (EVM)
Performance Reviews
Earned Value Management (EVM)
Planned Value
PV
Actual Cost
AC
Earned Value
EV
Time
Cost
BAC
EACForecastingVariance Analysis
Status Date
Variance Analysis: We can graph the project performance to show the project is currently
behind schedule and over budget
Forecast: We can also graph the estimated future performance to show the project will
exceed the budget.
APPENDIX – EVM QUICK REFERENCE
Earned Value Management (EVM)
Earned Value Management (EVM)
Earned Value Management – Quick Reference
Name Description Equation
Planned Value PV Budgeted amount planned to be spent Budgeted Rate * % Planned
Earned Value EV Measurement of completed work according to
the budget
% Complete * BAC
Actual Cost AC Cost incurred for the work performed
Budget at Completion BAC Total Planned Value for the project
Cost Variance CV The difference in budgeted amount and actual
spend at a given time.
CV = EV - PV
Schedule Variance SV The difference in Planned value and earned
value indicating if the project is ahead or
behind schedule
SV = EV - PV
Variance at Completion VAC The difference between the planned budget at
completion and estimate to complete
VAC = BAC - EAC
Cost Performance Index CPI Measurement of Cost efficiency expressed as a
percentage
CPI = EV / PV
Schedule Performance Index SPI Measurement of schedule efficiency expressed
as a percentage
SPI = EV / PV
Estimate at Completion EAC Estimated cost to complete the project
Based on current CPI
Based on budgeted rate
Based on current CPI & SPI
EAC = BAC/CPI
EAC = AC + (BAC – EV)
EAC = AC + [(BAC – EV) / (CPI * SPI)]
Estimate to Complete ETC Expected cost to complete work remaining ETC = EAC - AC
To Complete Performance Index TCPI Measurement of performance required to
meet the project goals. Expressed as a
percentage.
EAC = AC + [(BAC – EV) / (CPI * SPI)]
TCPI = [(BAC – EV) / (BAC - AC)]

Contenu connexe

Tendances

Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMansoor Shoaib
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...Fahad Ali
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy piecesGlen Alleman
 
Earned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsEarned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsIftikhar Anjum
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value AnalysisSaqib Raza
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction projectIAEME Publication
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners Shenin Hassan
 
Project Management Earned Value
Project Management Earned ValueProject Management Earned Value
Project Management Earned Valueconstructioninside
 
Earned value
Earned valueEarned value
Earned valueOliver
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis trainingPaul King
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)Harshit Mahajan
 
Evaluating Earned Value Management
Evaluating Earned Value ManagementEvaluating Earned Value Management
Evaluating Earned Value ManagementKristine Hejna
 
Earned value management (EVM)
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)Joshua Render
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMatt Stehling
 

Tendances (20)

Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy pieces
 
Earned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsEarned Value Management (EVM) Limitations
Earned Value Management (EVM) Limitations
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction project
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners
 
Project Management Earned Value
Project Management Earned ValueProject Management Earned Value
Project Management Earned Value
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned value
Earned valueEarned value
Earned value
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis training
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
Evaluating Earned Value Management
Evaluating Earned Value ManagementEvaluating Earned Value Management
Evaluating Earned Value Management
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned value management (EVM)
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)
 
Project Control Process
Project Control ProcessProject Control Process
Project Control Process
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned value management
Earned value managementEarned value management
Earned value management
 

En vedette

The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance ManagementCraig Brown
 
EVM in MS Project
EVM in MS ProjectEVM in MS Project
EVM in MS Projectorsmoot
 
Project Controls Expo, 13th Nov 2013 - "EVM for the Rest of Us" By Javier Slo...
Project Controls Expo, 13th Nov 2013 - "EVM for the Rest of Us" By Javier Slo...Project Controls Expo, 13th Nov 2013 - "EVM for the Rest of Us" By Javier Slo...
Project Controls Expo, 13th Nov 2013 - "EVM for the Rest of Us" By Javier Slo...Project Controls Expo
 
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPEarned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPJustAcademy
 
Improving Project Success with Engaged Teams
Improving Project Success with Engaged TeamsImproving Project Success with Engaged Teams
Improving Project Success with Engaged TeamsBaroness PM
 
32 Earned Value Management guidelines
32 Earned Value Management guidelines32 Earned Value Management guidelines
32 Earned Value Management guidelinesGlen Alleman
 
Evm power point january 2017
Evm power point  january 2017Evm power point  january 2017
Evm power point january 2017Roger H. Mandel
 
Padgett.sam
Padgett.samPadgett.sam
Padgett.samNASAPMC
 
Project Controls Expo 13th Nov 2013 - "Integrating Risk and Earned Value Mana...
Project Controls Expo 13th Nov 2013 - "Integrating Risk and Earned Value Mana...Project Controls Expo 13th Nov 2013 - "Integrating Risk and Earned Value Mana...
Project Controls Expo 13th Nov 2013 - "Integrating Risk and Earned Value Mana...Project Controls Expo
 
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the NumbersPMI-Montréal
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned ValueGlen Alleman
 

En vedette (16)

Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 
EVM in MS Project
EVM in MS ProjectEVM in MS Project
EVM in MS Project
 
Project Controls Expo, 13th Nov 2013 - "EVM for the Rest of Us" By Javier Slo...
Project Controls Expo, 13th Nov 2013 - "EVM for the Rest of Us" By Javier Slo...Project Controls Expo, 13th Nov 2013 - "EVM for the Rest of Us" By Javier Slo...
Project Controls Expo, 13th Nov 2013 - "EVM for the Rest of Us" By Javier Slo...
 
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPEarned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMP
 
Improving Project Success with Engaged Teams
Improving Project Success with Engaged TeamsImproving Project Success with Engaged Teams
Improving Project Success with Engaged Teams
 
AS08
AS08AS08
AS08
 
32 Earned Value Management guidelines
32 Earned Value Management guidelines32 Earned Value Management guidelines
32 Earned Value Management guidelines
 
Evm power point january 2017
Evm power point  january 2017Evm power point  january 2017
Evm power point january 2017
 
Padgett.sam
Padgett.samPadgett.sam
Padgett.sam
 
Project Controls Expo 13th Nov 2013 - "Integrating Risk and Earned Value Mana...
Project Controls Expo 13th Nov 2013 - "Integrating Risk and Earned Value Mana...Project Controls Expo 13th Nov 2013 - "Integrating Risk and Earned Value Mana...
Project Controls Expo 13th Nov 2013 - "Integrating Risk and Earned Value Mana...
 
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
 
Lukas
LukasLukas
Lukas
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned Value
 
NARA EVM Case Study Presentation For MPA
NARA EVM Case Study Presentation For MPANARA EVM Case Study Presentation For MPA
NARA EVM Case Study Presentation For MPA
 
Project Management Discussion with the BDPA Baltimore Chapter
 Project Management Discussion with the BDPA Baltimore Chapter Project Management Discussion with the BDPA Baltimore Chapter
Project Management Discussion with the BDPA Baltimore Chapter
 

Similaire à Track Project Performance - Earned Value Management

PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfNajm Naqvi
 
Evm Basics
Evm BasicsEvm Basics
Evm Basicsgfbreaux
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfNabeel Ahmad
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Earned value management
Earned value managementEarned value management
Earned value managementGautam Kumar
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)Nita Cristian
 
Project cost & control
Project cost & controlProject cost & control
Project cost & controlAMARAYYA
 
Examine how the PM uses project control charts to show project status.docx
Examine how the PM uses project control charts to show project status.docxExamine how the PM uses project control charts to show project status.docx
Examine how the PM uses project control charts to show project status.docxvtuan3
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxsagarlesley
 
Earned Value Management Project Analysis
Earned Value Management Project Analysis Earned Value Management Project Analysis
Earned Value Management Project Analysis Roger H. Mandel
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasAnand Bobade
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Vivek Prakash
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementProPM Academy
 

Similaire à Track Project Performance - Earned Value Management (20)

PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
Evm Basics
Evm BasicsEvm Basics
Evm Basics
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
Project cost control
Project cost controlProject cost control
Project cost control
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Examine how the PM uses project control charts to show project status.docx
Examine how the PM uses project control charts to show project status.docxExamine how the PM uses project control charts to show project status.docx
Examine how the PM uses project control charts to show project status.docx
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Earned Value Management Project Analysis
Earned Value Management Project Analysis Earned Value Management Project Analysis
Earned Value Management Project Analysis
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 
Delivering nothing efficiently
Delivering nothing efficientlyDelivering nothing efficiently
Delivering nothing efficiently
 

Dernier

Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)
Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)
Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)tazeenaila12
 
Anyhr.io | Presentation HR&Recruiting agency
Anyhr.io | Presentation HR&Recruiting agencyAnyhr.io | Presentation HR&Recruiting agency
Anyhr.io | Presentation HR&Recruiting agencyHanna Klim
 
AMAZON SELLER VIRTUAL ASSISTANT PRODUCT RESEARCH .pdf
AMAZON SELLER VIRTUAL ASSISTANT PRODUCT RESEARCH .pdfAMAZON SELLER VIRTUAL ASSISTANT PRODUCT RESEARCH .pdf
AMAZON SELLER VIRTUAL ASSISTANT PRODUCT RESEARCH .pdfJohnCarloValencia4
 
Introduction to The overview of GAAP LO 1-5.pptx
Introduction to The overview of GAAP LO 1-5.pptxIntroduction to The overview of GAAP LO 1-5.pptx
Introduction to The overview of GAAP LO 1-5.pptxJemalSeid25
 
Personal Brand Exploration Presentation Eric Bonilla
Personal Brand Exploration Presentation Eric BonillaPersonal Brand Exploration Presentation Eric Bonilla
Personal Brand Exploration Presentation Eric BonillaEricBonilla13
 
MoneyBridge Pitch Deck - Investor Presentation
MoneyBridge Pitch Deck - Investor PresentationMoneyBridge Pitch Deck - Investor Presentation
MoneyBridge Pitch Deck - Investor Presentationbaron83
 
PDT 88 - 4 million seed - Seed - Protecto.pdf
PDT 88 - 4 million seed - Seed - Protecto.pdfPDT 88 - 4 million seed - Seed - Protecto.pdf
PDT 88 - 4 million seed - Seed - Protecto.pdfHajeJanKamps
 
Building Your Personal Brand on LinkedIn - Expert Planet- 2024
 Building Your Personal Brand on LinkedIn - Expert Planet-  2024 Building Your Personal Brand on LinkedIn - Expert Planet-  2024
Building Your Personal Brand on LinkedIn - Expert Planet- 2024Stephan Koning
 
UNLEASHING THE POWER OF PROGRAMMATIC ADVERTISING
UNLEASHING THE POWER OF PROGRAMMATIC ADVERTISINGUNLEASHING THE POWER OF PROGRAMMATIC ADVERTISING
UNLEASHING THE POWER OF PROGRAMMATIC ADVERTISINGlokeshwarmaha
 
The Vietnam Believer Newsletter_MARCH 25, 2024_EN_Vol. 003
The Vietnam Believer Newsletter_MARCH 25, 2024_EN_Vol. 003The Vietnam Believer Newsletter_MARCH 25, 2024_EN_Vol. 003
The Vietnam Believer Newsletter_MARCH 25, 2024_EN_Vol. 003believeminhh
 
Developing Coaching Skills: Mine, Yours, Ours
Developing Coaching Skills: Mine, Yours, OursDeveloping Coaching Skills: Mine, Yours, Ours
Developing Coaching Skills: Mine, Yours, OursKaiNexus
 
Ethical stalking by Mark Williams. UpliftLive 2024
Ethical stalking by Mark Williams. UpliftLive 2024Ethical stalking by Mark Williams. UpliftLive 2024
Ethical stalking by Mark Williams. UpliftLive 2024Winbusinessin
 
HELENE HECKROTTE'S PROFESSIONAL PORTFOLIO.pptx
HELENE HECKROTTE'S PROFESSIONAL PORTFOLIO.pptxHELENE HECKROTTE'S PROFESSIONAL PORTFOLIO.pptx
HELENE HECKROTTE'S PROFESSIONAL PORTFOLIO.pptxHelene Heckrotte
 
7movierulz.uk
7movierulz.uk7movierulz.uk
7movierulz.ukaroemirsr
 
NASA CoCEI Scaling Strategy - November 2023
NASA CoCEI Scaling Strategy - November 2023NASA CoCEI Scaling Strategy - November 2023
NASA CoCEI Scaling Strategy - November 2023Steve Rader
 
Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)Lviv Startup Club
 
Entrepreneurship & organisations: influences and organizations
Entrepreneurship & organisations: influences and organizationsEntrepreneurship & organisations: influences and organizations
Entrepreneurship & organisations: influences and organizationsP&CO
 
Team B Mind Map for Organizational Chg..
Team B Mind Map for Organizational Chg..Team B Mind Map for Organizational Chg..
Team B Mind Map for Organizational Chg..dlewis191
 
Data skills for Agile Teams- Killing story points
Data skills for Agile Teams- Killing story pointsData skills for Agile Teams- Killing story points
Data skills for Agile Teams- Killing story pointsyasinnathani
 

Dernier (20)

Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)
Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)
Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)
 
Anyhr.io | Presentation HR&Recruiting agency
Anyhr.io | Presentation HR&Recruiting agencyAnyhr.io | Presentation HR&Recruiting agency
Anyhr.io | Presentation HR&Recruiting agency
 
AMAZON SELLER VIRTUAL ASSISTANT PRODUCT RESEARCH .pdf
AMAZON SELLER VIRTUAL ASSISTANT PRODUCT RESEARCH .pdfAMAZON SELLER VIRTUAL ASSISTANT PRODUCT RESEARCH .pdf
AMAZON SELLER VIRTUAL ASSISTANT PRODUCT RESEARCH .pdf
 
Introduction to The overview of GAAP LO 1-5.pptx
Introduction to The overview of GAAP LO 1-5.pptxIntroduction to The overview of GAAP LO 1-5.pptx
Introduction to The overview of GAAP LO 1-5.pptx
 
Personal Brand Exploration Presentation Eric Bonilla
Personal Brand Exploration Presentation Eric BonillaPersonal Brand Exploration Presentation Eric Bonilla
Personal Brand Exploration Presentation Eric Bonilla
 
MoneyBridge Pitch Deck - Investor Presentation
MoneyBridge Pitch Deck - Investor PresentationMoneyBridge Pitch Deck - Investor Presentation
MoneyBridge Pitch Deck - Investor Presentation
 
PDT 88 - 4 million seed - Seed - Protecto.pdf
PDT 88 - 4 million seed - Seed - Protecto.pdfPDT 88 - 4 million seed - Seed - Protecto.pdf
PDT 88 - 4 million seed - Seed - Protecto.pdf
 
Building Your Personal Brand on LinkedIn - Expert Planet- 2024
 Building Your Personal Brand on LinkedIn - Expert Planet-  2024 Building Your Personal Brand on LinkedIn - Expert Planet-  2024
Building Your Personal Brand on LinkedIn - Expert Planet- 2024
 
UNLEASHING THE POWER OF PROGRAMMATIC ADVERTISING
UNLEASHING THE POWER OF PROGRAMMATIC ADVERTISINGUNLEASHING THE POWER OF PROGRAMMATIC ADVERTISING
UNLEASHING THE POWER OF PROGRAMMATIC ADVERTISING
 
The Vietnam Believer Newsletter_MARCH 25, 2024_EN_Vol. 003
The Vietnam Believer Newsletter_MARCH 25, 2024_EN_Vol. 003The Vietnam Believer Newsletter_MARCH 25, 2024_EN_Vol. 003
The Vietnam Believer Newsletter_MARCH 25, 2024_EN_Vol. 003
 
Developing Coaching Skills: Mine, Yours, Ours
Developing Coaching Skills: Mine, Yours, OursDeveloping Coaching Skills: Mine, Yours, Ours
Developing Coaching Skills: Mine, Yours, Ours
 
Ethical stalking by Mark Williams. UpliftLive 2024
Ethical stalking by Mark Williams. UpliftLive 2024Ethical stalking by Mark Williams. UpliftLive 2024
Ethical stalking by Mark Williams. UpliftLive 2024
 
HELENE HECKROTTE'S PROFESSIONAL PORTFOLIO.pptx
HELENE HECKROTTE'S PROFESSIONAL PORTFOLIO.pptxHELENE HECKROTTE'S PROFESSIONAL PORTFOLIO.pptx
HELENE HECKROTTE'S PROFESSIONAL PORTFOLIO.pptx
 
7movierulz.uk
7movierulz.uk7movierulz.uk
7movierulz.uk
 
NASA CoCEI Scaling Strategy - November 2023
NASA CoCEI Scaling Strategy - November 2023NASA CoCEI Scaling Strategy - November 2023
NASA CoCEI Scaling Strategy - November 2023
 
Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)
 
Entrepreneurship & organisations: influences and organizations
Entrepreneurship & organisations: influences and organizationsEntrepreneurship & organisations: influences and organizations
Entrepreneurship & organisations: influences and organizations
 
Investment Opportunity for Thailand's Automotive & EV Industries
Investment Opportunity for Thailand's Automotive & EV IndustriesInvestment Opportunity for Thailand's Automotive & EV Industries
Investment Opportunity for Thailand's Automotive & EV Industries
 
Team B Mind Map for Organizational Chg..
Team B Mind Map for Organizational Chg..Team B Mind Map for Organizational Chg..
Team B Mind Map for Organizational Chg..
 
Data skills for Agile Teams- Killing story points
Data skills for Agile Teams- Killing story pointsData skills for Agile Teams- Killing story points
Data skills for Agile Teams- Killing story points
 

Track Project Performance - Earned Value Management

  • 1. Earned Value Management (EVM) Measure Project Performance
  • 2. Earned Value Management (EVM) Earned Value Management (EVM) Earned Value Management (EVM) is a project management methodology used to track project performance as well as forecast future performance. EVM integrates the scope baseline, schedule baseline and cost to provide performance measurements. Results can be expressed in dollars and/or percentage. EVM can be used to report current/past project performance, and predict future project performance based on current/past performance. Variance Analysis Forecasting Current/Past Performance Future Performance
  • 3. PART 1 - BUILDING BLOCKS Earned Value Management (EVM)
  • 4. Earned Value Management (EVM) Starts with 3 building blocks that will be used in all EVM calculations. Budgeted amount planned to be spent at a point in time of the project Planned Value (PV) Earned Value (EV) Actual Cost (AC) Measurement of completed work according to the budget at a point in time of the project lifecycle Cost incurred for the work performed at a point in time of the project lifecycle Earned Value Management (EVM)
  • 5. Earned Value Management (EVM) Scenario: You are assigned to manage a 12 month project estimated to cost $36,000 at the end of the project. Today is the end of month 3 and you are 20% complete. According to the Finance Department you have spent $7,500 to date. Planned Value (PV) 1. Calculate % Planned. 3 months / 12 months = .25 2. Calculate $ Planned. $36,000 * .25 = $9,000 Planned Value (PV) Earned Value (EV) Actual Cost (AC) Earned Value (EV) 1. Determine % Complete = .20 2. Calculate $ Earned = 36,000 * .20 = 7,000 Actual Cost (AC) 1. Actual cost provided = $7,500 Earned Value Management (EVM)
  • 6. PART 2 - VARIANCE ANALYSIS Earned Value Management (EVM)
  • 7. Earned Value Management (EVM) Variance Analysis can be used to monitor project performance based on schedule and cost. Each method can be expressed in a dollar value or percentage. Schedule Variance • Schedule Variance (SV) Project schedule performance expressed in dollars • Schedule Performance Index (SPI) Project schedule performance expressed in a percentage Cost Variance • Cost Variance (CV) Project cost performance expressed in dollars • Cost Performance Index (CPI) Project cost performance expressed in a percentage Earned Value Management (EVM)
  • 8. • Schedule Variance (SV) –Project performance expressed in dollars. SV = EV – PV SV = 7,000 – 9,000 SV = (2,000) • Schedule Performance Index (SPI) – Project performance expressed as a percent. SPI = EV / PV SPI = 7,000 / 9,000 SPI = .78 Earned Value Management (EVM) Schedule Variance Analysis uses EV and PV to calculate a variance to the project schedule. Earned Value Management (EVM) Earned Value Management Planned Value PV $9,000 Earned Value EV $7,000 Actual Cost AC $7,500
  • 9. • Cost Variance (CV) –Project performance expressed in dollars. CV = EV – AC CV = 7,000 – 7,500 CV = (500) • Cost Performance Index (CPI) – Project performance expressed as a percent. CPI = EV / AC CPI = 7,000 / 7,500 CPI = .93 Earned Value Management (EVM) Cost Variance Analysis uses EV and AC to calculate a variance to the project budget (cost). Earned Value Management Planned Value PV $9,000 Earned Value EV $7,000 Actual Cost AC $7,500 Earned Value Management (EVM)
  • 10. PART 3 - FORECASTING Earned Value Management (EVM) Earned Value Management (EVM)
  • 11. Earned Value Management (EVM) We can also use EVM to forecast future project spending. Estimate at Completion (EAC) can be calculated using the 3 following methods: Project will continue to perform at the budgeted rate EAC = AC + (BAC – EV) Budgeted Rate Current CPI Current CPI & SPI Project will continue to perform at the current CPI: EAC = BAC / CPI Project will continue to perform at the current CPI & SPI: EAC = AC + [(BAC – EV) / (CPI * SPI)] Earned Value Management (EVM) Estimate at Completion (EAC)
  • 12. Estimate at Completion (EAC) – Budgeted Rate: EAC = AC + (BAC – EV) EAC = 7,500 + (36,000 – 7,000) EAC = 7,500 + 29,000 EAC = $36,500 Earned Value Management (EVM) Forecasting using Estimate at Completion (EAC) at the Budgeted rate, assumes the project will continue to perform at the currently budgeted rate. Earned Value Management (EVM)
  • 13. Estimate at Completion (EAC) – Current CPI EAC = BAC / CPI EAC = 36,000 / .78 EAC = $46,153.84 Earned Value Management (EVM) Forecasting using Estimate at Completion at the current CPI, assumes the project will continue to perform at the Cost Performance Index (CPI) Earned Value Management (EVM)
  • 14. Estimate at Completion (EAC) – Current CPI & SPI EAC = AC + [(BAC – EV) / (CPI * SPI)] EAC = 7,500 + [(36,000 – 7,000) / (.78 * .93)] EAC = 7,500 + [29,000 / .7254] EAC = 7,500 + 39,977.94 EAC = 47,477.94 Earned Value Management (EVM) Forecasting using Estimate at Completion at the current CPI & SPI, assumes the project will continue to perform at the Cost Performance Index (CPI) and Schedule Performance Index (SPI) Earned Value Management (EVM)
  • 15. To Complete Performance Index (TCPI) Based on Balance at Completion: TCPI = [(BAC – EV) / (BAC - AC)] TCPI = [(36,000 – 7,000) / (36,000 – 7,500)] TCPI = (29,000) / (28,500) TCPI = 1.01 Earned Value Management (EVM) Earned Value Management (EVM) To Complete Performance Index (TCPI) Measure of schedule performance on a project.
  • 16. To Complete Performance Index (TCPI) Based on Estimate to Complete: TCPI = (BAC - EV) / (EAC – AC) TCPI = (36,000 – 7000) / (36,500 – 7,500) TCPI = 29,000 / 29,000 TCPI = 1.0 Earned Value Management (EVM) Earned Value Management (EVM) To Complete Performance Index (TCPI) Measure of schedule performance on a project.
  • 17. PART 4 - PERFORMANCE REVIEWS Earned Value Management (EVM)
  • 18. JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC PV 3,000 6,000 9,000 12,000 15,000 18,000 21,000 24,000 27,000 30,000 33,000 36,000 EV 3,240 5,400 7,200 10,000 13,000 15,000 AC 3,500 7,000 10,000 14,000 17,500 21,000 0 5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 Earned Value Management (EVM) Performance Reviews Earned Value Management (EVM) Planned Value PV Actual Cost AC Earned Value EV Time Cost BAC EACForecastingVariance Analysis Status Date Variance Analysis: We can graph the project performance to show the project is currently behind schedule and over budget Forecast: We can also graph the estimated future performance to show the project will exceed the budget.
  • 19. APPENDIX – EVM QUICK REFERENCE Earned Value Management (EVM)
  • 20. Earned Value Management (EVM) Earned Value Management – Quick Reference Name Description Equation Planned Value PV Budgeted amount planned to be spent Budgeted Rate * % Planned Earned Value EV Measurement of completed work according to the budget % Complete * BAC Actual Cost AC Cost incurred for the work performed Budget at Completion BAC Total Planned Value for the project Cost Variance CV The difference in budgeted amount and actual spend at a given time. CV = EV - PV Schedule Variance SV The difference in Planned value and earned value indicating if the project is ahead or behind schedule SV = EV - PV Variance at Completion VAC The difference between the planned budget at completion and estimate to complete VAC = BAC - EAC Cost Performance Index CPI Measurement of Cost efficiency expressed as a percentage CPI = EV / PV Schedule Performance Index SPI Measurement of schedule efficiency expressed as a percentage SPI = EV / PV Estimate at Completion EAC Estimated cost to complete the project Based on current CPI Based on budgeted rate Based on current CPI & SPI EAC = BAC/CPI EAC = AC + (BAC – EV) EAC = AC + [(BAC – EV) / (CPI * SPI)] Estimate to Complete ETC Expected cost to complete work remaining ETC = EAC - AC To Complete Performance Index TCPI Measurement of performance required to meet the project goals. Expressed as a percentage. EAC = AC + [(BAC – EV) / (CPI * SPI)] TCPI = [(BAC – EV) / (BAC - AC)]