Life Cycle Cost Growth Study
20 Science Mission Directorate (SMD) Missions
                        Presented at the
       2011 NASA Program Management Challenge
            9-10 February 2011, Long Beach, California




Claude Freaner, Science Mission Directorate, NASA HQ

                                  1
Background

  • Previous studies1, 2 have primarily examined Development Cost
    Growth in an attempt to determine when in the development
    lifecycle the growth occurs
  • Growth was studied for 20 SMD Missions launched between 2000
    and 2009.
      – Mass, Power, Cost, and Schedule were examined
  • Launch vehicle and Phase E operations costs (planned versus
    actual) have also grown but the amounts/phasing of this growth
    were not included in the prior studies
      – Current study includes LV and Phase E operations cost


1. “Using Historical NASA Cost and Schedule Growth to Set Future Program and Project Reserve Guidelines”, Bitten R., Emmons D., Freaner C.,
IEEE Aerospace Conference, Big Sky, Montana, March 3-10, 2007
2, “Optimism in Early Conceptual Designs and Its Effect on Cost and Schedule Growth: An Update”, Bitten R., Freaner C., Emmons D., 2010
NASA Program Management Challenge, Galveston, Texas, February 9-10, 2010




                                                                         2
Study Approach
• For a set of 20 missions in the study, the cost data were obtained from
  all of the CADRes for missions at ATP (Phase B start), PDR, CDR, and
  Launch.
• The cost data was “binned” into these Work Breakdown Structure
  (WBS) element categories:
    –    PMSEMA: Project Management, Systems Engineering, Mission Assurance
    –    SCI/EPO: Science, Education, Public Outreach
    –    Payload
    –    Bus/AIT: Spacecraft Bus, System Assembly Integration and Test
    –    GDS/MOS: pre-launch Ground Data System, Mission Operations
    –    L/V: Launch Vehicle
    –    Phase E: Post-Launch Operations and Data Analysis
• Cost data has not been adjusted for “Full Cost” effects
     –     Primarily impacts STEREO, CALIPSO, FERMI
 The majority of these missions were in development prior to the CADRe requirement existing, so separation of the costs
 into the standard WBS Level 2 elements was difficult. Therefore, the elements were combined into the above bins.


                                                             3
Database Description:
       20 Missions Represent a Wide Range of Recent NASA Missions
                                                                                          Key         Launch Acquisition Number of
                                        Planetary?    Program       Science Type        Center(s)      Year     Type     Instruments                  Comments
                                                                                                                                       Advanced land imaging technology
                          EO-1                       NMP         Earth Science            GSFC         2000   Competed       5
                                                                                                                                       demonstrator
                                                                                                                                       Collect samples of solar wind particles at
                          GENESIS           X        Discovery   Planetary Science          JPL        2001   Competed       4
                                                                                                                                       L1 point and return them to Earth
• 5 Directed vs. 15       GRACE                      ESSP        Earth Science              JPL        2002   Competed       6         Earth Gravity Measurement

  Competed missions       Spitzer
                                                     Physics of
                                                     the Cosmos
                                                                Astrophysics                JPL        2003    Directed      4
                                                                                                                                       IR space telescope, the last of the Great
                                                                                                                                       Observatories
                          GALEX                      Explorers   Astrophysics           JPL/CalTech    2003   Competed       1         UV space telescope

                          SWIFT                      Explorers   Astrophysics             GSFC         2004   Competed       4         Gamma Ray burst detector
• 7 Planetary missions    MESSENGER         X        Discovery   Planetary Science         APL         2004   Competed       7         Investigate Mercury
  vs. 13 Earth or near-   MRO               X        MEP         Planetary Science          JPL        2005    Directed      7         Investigate history of water on Mars

  Earth Orbiters          Deep Impact       X        Discovery   Planetary Science          JPL        2005   Competed       3         Comet impactor

                          Cloudsat                   ESSP        Earth Science              JPL        2006   Competed       1         Radar observation of clouds
                                                                                                                                       2 spacecraft looking at solar dynamics -
                          STEREO                     STP         Heliospheric Science   GSFC/APL       2006    Directed      4
• 7 Planetary Science                                                                                                                  Earth leading and trailing orbits
                          CALIPSO                    ESSP        Earth Science             LARC        2006   Competed       3         Aerosols
  vs. 5 Astrophysics      New
                                            X
                                                     New
                                                                 Planetary Science         APL         2006   Competed       7         Investigate Pluto
                          Horizons                   Frontiers
  vs. 5 Earth Science     DAWN              X        Discovery   Planetary Science          JPL        2007   Competed       2         Investigate Ceres and Vesta protoplanets

  vs. 3 Heliophysics      AIM                        Explorers   Heliospheric Science      LASP        2007   Competed       3         Aeronomy of Ice in Mesosphere

  missions                Fermi
                          (GLAST)
                                                     Physics of
                                                     the Cosmos
                                                                Astrophysics              GSFC         2008    Directed      2         Gamma Ray Telescope
                                                                                                                                       Interaction between solar wind and
                          IBEX                       Explorers   Heliospheric Science     GSFC         2008   Competed       2
                                                                                                                                       interstellar medium
                          Kepler                     Discovery   Astrophysics               JPL        2009   Competed       1         Search for Earth-sized exoplanets
                                                     Robotic     ESMD/Planetary
                          LRO               X                                             GSFC         2009    Directed      7         Origin of the Moon
                                                     Lunar       Science
                                                                                                                                       Carbon Dioxide Investigation. Mission
                          OCO                        ESSP        Earth Science              JPL        2009   Competed       1
                                                                                                                                       failed due to launch vehicle failure




                                                                                4
Composition of Average Life Cycle Cost & Cost Growth

   Category as Percent of                Distribution of Growth of LCC
   Average LCC at Launch                      From PDR to Launch
                                                Phase E
                                                  6%
                           SCI/EPO
                             3%                                     SCI/EPO
                   PMSEM                                  PMSE        2%
         Phase E                             L/V
           11%
                      A                                    MA
                     9%                      7%
                                                           12%
   L/V
                                         GDS/
   17%                                   MOS
                           Payload       12%
                            23%

                                                                 Payload
  GDS                                        Bus/AIT              32%
  6%                                          29%
              Bus/AIT
               31%




                                     5
“Portfolio” % Average LCC Cost Growth
                                       Average Cost Growth by Major WBS,
                   200%
                                       Reserves Not Included (20 Missions)
                   180%
                   160%
                   140%
  Percent Growth




                   120%
                   100%
                   80%                                                 ATP to LRD
                   60% 56%                                             PDR to LRD
                         40%
                   40%
                   20%
                    0%




                          Largest Percent Growth for PMSEMA & GDS/OS
Growth = (Total LCC at Launch/Total LCC at KDP) -1
Note: ATP is equivalent to KDP-B
                                                     6
Total Cost Growth ($) by Major WBS Element
                                                           (20 Missions)
                    1,000,000


                     800,000                                                                 Total Growth =
                                                                                                 $2.1B

                     600,000                                                                 Total Growth =
                                                                                                 $1.6B
                     400,000
Cost Growth in $K




                     200,000
                                                                                            ATP to LRD
                                                                                            PDR to LRD
                           -


                    (200,000)


                    (400,000)
                                                                                              Total Cost at
                                                                                             Launch = $7.6B
                    (600,000)
                                          Reserves shown were planned to cover all growth
                    (800,000)

                                Largest Absolute Dollar Growth for Payload & Spacecraft

                                                                    7
PMSEMA Cost Growth from ATP* (Phase B start)
  450%                                                     Mission #1
                                                           Mission #2
  400%                                                     Mission #3
                                                           Mission #4
  350%                                                     Mission #5
                                                           Mission #6
  300%                                                     Mission #7
                                                           Mission #8
  250%                                                     Mission #9
                                                           Mission #10
  200%                                      178%           Mission #11
                                                           Mission #12
  150%                                                     Mission #13
                                                           Mission #14
  100%                                                     Mission #15
                                      61%                  Mission #16
   50%                          38%                        Mission #17
               0%                                          Mission #18
    0%                                                     Mission #19
              ATP               PDR   CDR   Launch         Mission #20
  -50%                                                     Average


 -100%

              Majority of PMSEMA Growth Occurs After CDR
* Note: Reserves not included

                                       8
PMSEMA Cost Growth from PDR*
   400%
                                                        Mission #1
                                                        Mission #2
   350%
                                                        Mission #3
                                                        Mission #4
   300%                                                 Mission #5
                                                        Mission #6
   250%                                                 Mission #7
                                                        Mission #8
   200%                                                 Mission #9
                                                        Mission #10
   150%                                                 Mission #11
                                            114%        Mission #12
   100%                                                 Mission #13
                                                        Mission #14

    50%                                                 Mission #15
                                17%                     Mission #16
                  0%
                                                        Mission #17
     0%
                  PDR           CDR        Launch       Mission #18
                                                        Mission #19
   -50%
                                                        Mission #20
                                                        Average
  -100%


               Majority of PMSEMA Growth Occurs After CDR
* Note: Reserves not included

                                      9
Science/EPO Cost Growth from ATP* (Phase B start)
    500%
                                                              Mission #1
                                                              Mission #2
                                                              Mission #3
    400%                                                      Mission #4
                                                              Mission #5
                                                              Mission #6
    300%                                                      Mission #7
                                                              Mission #8
                                                              Mission #9
    200%                                                      Mission #10
                                                              Mission #11
                                                              Mission #12
    100%                                                      Mission #13
                                                48%           Mission #14
                                 11%   18%                    Mission #15
                 0%
      0%                                                      Mission #16
                 ATP             PDR   CDR     Launch         Mission #17
                                                              Mission #18
   -100%                                                      Mission #19
                                                              Mission #20
                                                              Average

   -200%


            Majority of Science/EPO Growth Occurs After CDR
 * Note: Reserves not included

                                       10
Science/EPO Cost Growth from PDR*
 300%
                                                              Mission #1
                                                              Mission #2
                                                              Mission #3
 250%
                                                              Mission #4
                                                              Mission #5
 200%                                                         Mission #6
                                                              Mission #7
                                                              Mission #8
 150%                                                         Mission #9
                                                              Mission #10
                                                              Mission #11
 100%                                                         Mission #12
                                                              Mission #13
                                                              Mission #14
  50%                                            32%
                                                              Mission #15
                                  18%
                                                              Mission #16
                 0%
   0%                                                         Mission #17
                 PDR              CDR           Launch        Mission #18
                                                              Mission #19
  -50%                                                        Mission #20
                                                              Average

 -100%

                       Science/EPO Grows Steadily After PDR
* Note: Reserves not included

                                         11
Payload Cost Growth from ATP* (Phase B start)
250%
                                                                 Mission #1
                                                                 Mission #2
                                                                 Mission #3
200%
                                                                 Mission #4
                                                                 Mission #5
                                                                 Mission #6
150%
                                                                 Mission #7
                                                                 Mission #8
                                                     103%        Mission #9
100%                                                             Mission #10
                                                                 Mission #11
                                                                 Mission #12
                                                                 Mission #13
50%
                                        34%
                                                                 Mission #14
                                  15%                            Mission #15
              0%                                                 Mission #16
 0%
                                                                 Mission #17
             ATP                  PDR   CDR         Launch
                                                                 Mission #18
                                                                 Mission #19
-50%


                   Majority of Payload Growth Occurs After CDR
  * Note: Reserves not included

                                        12
Payload Cost Growth from PDR*
200%
                                                              Mission #1
                                                              Mission #2
                                                              Mission #3
                                                              Mission #4
150%                                                          Mission #5
                                                              Mission #6
                                                              Mission #7
                                                              Mission #8
                                                              Mission #9
100%
                                                              Mission #10
                                                  77%
                                                              Mission #11
                                                              Mission #12
                                                              Mission #13
 50%                                                          Mission #14
                                                              Mission #15
                                 17%                          Mission #16
                                                              Mission #17
                 0%
                                                              Mission #18
  0%
                 PDR             CDR             Launch       Mission #19
                                                              Mission #20
                                                              Average


-50%            Majority of Payload Growth Occurs After CDR
* Note: Reserves not included

                                       13
Bus/AIT Cost Growth from ATP*
    160%
                                                               Mission #1
                                                               Mission #2
    140%                                                       Mission #3
                                                               Mission #4
    120%                                                       Mission #5
                                                               Mission #6

    100%                                                       Mission #7
                                                               Mission #8
                                                               Mission #9
     80%
                                                               Mission #10
                                                               Mission #11
     60%                                        55%
                                                               Mission #12
                                                               Mission #13
     40%                                                       Mission #14
                                                               Mission #15
                                      18%                      Mission #16
     20%                        11%
                                                               Mission #17
                 0%                                            Mission #18
      0%
                                                               Mission #19
                ATP             PDR   CDR      Launch
                                                               Mission #20
    -20%                                                       Average


    -40%

                 Majority of Bus/AIT Growth Occurs After CDR
* Note: Reserves not included

                                      14
Bus/AIT Cost Growth from PDR*
120%
                                                                Mission #1
                                                                Mission #2
                                                                Mission #3
100%
                                                                Mission #4
                                                                Mission #5
                                                                Mission #6
80%                                                             Mission #7
                                                                Mission #8
                                                                Mission #9
60%                                                             Mission #10
                                                                Mission #11
                                                                Mission #12
                                                 40%
40%                                                             Mission #13
                                                                Mission #14
                                                                Mission #15
                                                                Mission #16
20%
                                                                Mission #17
                                 7%                             Mission #18
                0%                                              Mission #19
 0%
                                                                Mission #20
                PDR              CDR            Launch
                                                                Average

-20%

                  Majority of Bus/AIT Growth Occurs After CDR
 * Note: Reserves not included

                                       15
Pre-Launch GDS/MOS Cost Growth from ATP* (Phase B start)
                                     EO-1 Excluded from Average
        800%                                                          Mission #1
                                                                      Mission #2
        700%                                                          Mission #3
                                                                      Mission #4
                                                                      Mission #5
        600%
                                                                      Mission #6
                                                                      Mission #7
        500%                                                          Mission #8
                                                                      Mission #9

        400%                                                          Mission #10
                                                                      Mission #11
                                                                      Mission #12
        300%
                                                                      Mission #13
                                                                      Mission #14
        200%                                                 165%     Mission #15
                                                                      Mission #16

        100%                                      67%                 Mission #17
                                      54%
                                                                      Mission #18
                     0%                                               Mission #19
          0%
                                                                      Mission #20
                     ATP              PDR         CDR        Launch
                                                                      Average
       -100%

           Majority of Pre-Launch GDS/MOS Growth Occurs After CDR
     * Note: Reserves not included

                                                  16
Pre-Launch GDS/MOS Cost Growth from PDR*
                        EO-1 & CALIPSO Excluded from Average
  900%
                                                               Mission #1
                                                               Mission #2
  800%
                                                               Mission #3

  700%                                                         Mission #4
                                                               Mission #5
  600%                                                         Mission #6
                                                               Mission #7
  500%                                                         Mission #8
                                                               Mission #9
  400%                                                         Mission #10
                                                               Mission #11
  300%                                                         Mission #12
                                                               Mission #13
  200%                                                         Mission #14
                                                               Mission #15
  100%                                               74%
                                                               Mission #16
                   0%               11%                        Mission #17
    0%                                                         Mission #18
                  PDR               CDR             Launch
                                                               Mission #19
  -100%
                                                               Mission #20
                                                               Average
  -200%


      Majority of Pre-Launch GDS/MOS Growth Occurs After CDR
* Note: Reserves not included

                                          17
Launch Vehicle Cost Growth from ATP* (Phase B start)
   100%
                                                                  Mission #1
                                                                  Mission #2
                                                                  Mission #3
    80%
                                                                  Mission #4
                                                                  Mission #5
                                                                  Mission #6
    60%
                                                                  Mission #7
                                                                  Mission #8
                                                                  Mission #9
    40%                                                           Mission #10
                                                                  Mission #11
                                                                  Mission #12
    20%                                                           Mission #13
                                                      10%
                                                                  Mission #14
                  0%                         2%                   Mission #15
                                  -3%                             Mission #16
     0%
                 ATP              PDR        CDR     Launch       Mission #17
                                                                  Mission #18
    -20%                                                          Mission #19
                                                                  Mission #20
                                                                  Average

    -40%


             Majority of Launch Vehicle Growth Occurs After CDR
  * Note: Reserves not included

                                        18
Launch Vehicle Cost Growth from PDR*
 100%
                                                                Mission #1
                                                                Mission #2
                                                                Mission #3
  80%
                                                                Mission #4
                                                                Mission #5
                                                                Mission #6
  60%
                                                                Mission #7
                                                                Mission #8
                                                                Mission #9
  40%                                                           Mission #10
                                                                Mission #11
                                                                Mission #12
  20%                                             14%           Mission #13
                                                                Mission #14
                                 5%                             Mission #15
                   0%
   0%                                                           Mission #16
                  PDR           CDR              Launch         Mission #17
                                                                Mission #18
                                                                Mission #19
 -20%
                                                                Mission #20
                                                                Average

 -40%

           Majority of Launch Vehicle Growth Occurs After CDR
* Note: Reserves not included

                                      19
Planned Phase E Cost Growth from ATP* (Phase B start)
                             CALIPSO Excluded from Average
   400%
                                                                      Mission #1
                                                                      Mission #2
   350%
                                                                      Mission #3
                                                                      Mission #4
   300%
                                                                      Mission #5
                                                                      Mission #6
   250%                                                               Mission #7
                                                                      Mission #8
   200%                                                               Mission #9
                                                                      Mission #10

   150%                                                               Mission #11
                                                                      Mission #12
                                                                      Mission #13
   100%
                                                                      Mission #14
                                                                      Mission #15
   50%                                           27%          34%     Mission #16
                                  11%                                 Mission #17
                0%
    0%                                                                Mission #18
                ATP               PDR            CDR         Launch   Mission #19
   -50%                                                               Mission #20
                                                                      Average

  -100%

                Majority of Phase E Growth Occurs Prior to CDR
  * Note: Reserves not included

                                            20
Planned Phase E Cost Growth from PDR*
                           CALIPSO Excluded from Average
 400%

                                                            Mission #1
 350%                                                       Mission #2
                                                            Mission #3
 300%                                                       Mission #4
                                                            Mission #5
                                                            Mission #6
 250%
                                                            Mission #7
                                                            Mission #8
 200%                                                       Mission #9
                                                            Mission #10
 150%                                                       Mission #11
                                                            Mission #12
                                                            Mission #13
 100%
                                                            Mission #14
                                                            Mission #15
  50%                                                       Mission #16
                                   13%              21%
                                                            Mission #17
                 0%
   0%                                                       Mission #18
                 PDR               CDR             Launch   Mission #19
                                                            Mission #20
 -50%
                                                            Average

-100%


              Majority of Phase E Growth Occurs Prior to CDR
* Note: Reserves not included

                                          21
LCC Growth from ATP* (Phase B start)
                                (Includes Planned Phase E)
  180%
                                                                                  Mission #1
                                                                                  Mission #2
  160%                                                                            Mission #3
                                                                                  Mission #4
  140%                                                                            Mission #5
                                                                                  Mission #6
  120%                                                                            Mission #7
                                                                                  Mission #8
                                                                                  Mission #9
  100%
                                                                                  Mission #10
                                                                                  Mission #11
   80%
                                                                                  Mission #12
                                                                58%               Mission #13
   60%                                                                            Mission #14
                                                                                  Mission #15
   40%                                                                            Mission #16
                                                                                  Mission #17
                                              20%
   20%                                                                            Mission #18
                                 9%                                               Mission #19
                0%                                                                Mission #20
    0%
                                                                                  Average
               ATP               PDR          CDR              Launch
  -20%

                     Majority of LCC Growth Occurs After CDR
* Note: Reserves not included               Growth = Average ((Mission LCC at Launch/Mission LCC at KDP)-1)
                                             22
LCC Growth from PDR*
                                (Includes Planned Phase E)
140%
                                                                              Mission #1
                                                                              Mission #2
120%                                                                          Mission #3
                                                                              Mission #4
                                                                              Mission #5
100%                                                                          Mission #6
                                                                              Mission #7
                                                                              Mission #8
80%
                                                                              Mission #9
                                                                              Mission #10
60%                                                                           Mission #11
                                                                              Mission #12
                                                        45%
                                                                              Mission #13
40%                                                                           Mission #14
                                                                              Mission #15
                                                                              Mission #16
20%                                                                           Mission #17
                                    10%
                                                                              Mission #18
               0%                                                             Mission #19
 0%
                                                                              Mission #20
               PDR                  CDR                 LRD
                                                                              Average

-20%

                     Majority of LCC Growth Occurs After CDR
* Note: Reserves not included               Growth = Average ((Mission LCC at Launch/Mission LCC at KDP)-1)
                                             23
Reserves Standards

• JPL Flight Project Practices, Rev. 7:
   – At PDR, budget reserves must be 25% of cost to go.
   – At CDR, budget reserves must be 20% of cost to go.
   – At start of ATLO, budget reserves must be 20% of cost to go.
• GSFC “Gold Rules”
   – At PDR, budget reserves must be 25% of cost to go.




•LCC growth from PDR to Launch averages 41% of
 Total Cost (reserves excluded), not cost to go
•LCC growth from CDR to Launch averages 32% of
 Total Cost (reserves excluded), not cost to go

                                      24
Probability that 25% Reserves at PDR Are Sufficient
• Growth from PDR to Launch average is 41% (excluding EO-1)
  – Standard Deviation = 21%
  – Probability that a mission with 25% reserves at PDR will stay within
    those reserves by Launch = 22%
  – To achieve 70% CL, reserves of 47% would have been needed


• Growth from PDR to Launch average is 45% (including EO-1)
  – Standard Deviation = 28%
  – Probability that a mission with 25% reserves at PDR will stay within
    those reserves by Launch = 23%
  – To achieve 70% CL, reserves of 52% would have been needed




                                      25
So…Why Do We Have Cost Growth?
• Over-optimism at the start
   – Propensity for proposers to be in marketing mode
   – Initial Mass estimates are low
        • Average Payload Mass Growth PDR-Launch = 77%
   – Initial Schedule estimates are short
   – Cost… Likely bid to the cost cap or available budget, not what it realistically
     takes
• Cost estimators can use wider ranges on parameters for estimating the
  input values used for cost risk analysis
   – Current Cost risk process appears to be underestimating the resource growth
• Schedule slips
   – Average Launch date slip from PDR plan: 13+ Months
   – Average Launch date slip from CDR plan: 10- Months
   – Majority of schedule slips occur during ATLO.
• “Stuff” happens
   –   Harder than we thought
   –   Suppliers have problems
   –   Things break
   –   Congress/OMB/NASA HQ change funding profiles


                                          26
What Can We Do to Decrease Cost Growth?
• Proper scoping of projects early in conceptual design to provide executable
  program plans
• Require better Basis of Estimate
   – Require proposers to show relevant actuals from prior missions at the subsystem
     level
   – “Relevant actuals” means Mass, Power, Cost, Schedule
   – Risk assessment and quantification of risk
• Independent validation of instrument resources, and the resulting spacecraft
  resources needed to meet mission requirements, would allow more accurate
  estimates
• Increase reserves is one possible solution
   – Reduces number of missions per year
   – Costs will likely rise to beyond the new reserves after a short time.
• Incentivize contracts
   – Large rewards to Center/Team for performing to initial budget/schedule
   – Punishment
      • Easy to apply to Corporations: take away fee, cost share any overruns, etc.
      • Difficult to apply to NASA Centers

                                             27
The author wishes to express sincere appreciation to Robert E. Bitten and Debra L.
  Emmons, The Aerospace Corporation, for their help in the preparation of this presentation.



Electronic copies of this and the two previous studies referenced on slide 2 may be obtained
  by sending an email to

                              claude.freaner@nasa.gov




                                            28

Contenu connexe

Tendances

N15. Lucchesi- "fundamental physics with lageos satellites"
N15. Lucchesi- "fundamental physics with lageos satellites"N15. Lucchesi- "fundamental physics with lageos satellites"
N15. Lucchesi- "fundamental physics with lageos satellites"IAPS
 
Hufenback,bernhard isecg ger hufenbach pmc v2
Hufenback,bernhard isecg ger hufenbach pmc v2Hufenback,bernhard isecg ger hufenbach pmc v2
Hufenback,bernhard isecg ger hufenbach pmc v2NASAPMC
 
Jody.singer
Jody.singerJody.singer
Jody.singerNASAPMC
 
The use of geoinformatics in mineral exploration and exploitation
The use of geoinformatics in mineral exploration and exploitationThe use of geoinformatics in mineral exploration and exploitation
The use of geoinformatics in mineral exploration and exploitationMarguerite Walsh
 
Indian Satellite Program(2001-2020)
Indian Satellite Program(2001-2020)Indian Satellite Program(2001-2020)
Indian Satellite Program(2001-2020)Priyanka More
 
Intro to RS and GIS by mndp poonia
Intro to RS and GIS by mndp pooniaIntro to RS and GIS by mndp poonia
Intro to RS and GIS by mndp pooniamndp_slide
 
IRS satallites
IRS satallitesIRS satallites
IRS satallitesBharath YG
 
Galaxy Forum SEA 2016 Malaysia - Hakim Malasan
Galaxy Forum SEA 2016 Malaysia - Hakim MalasanGalaxy Forum SEA 2016 Malaysia - Hakim Malasan
Galaxy Forum SEA 2016 Malaysia - Hakim MalasanILOAHawaii
 
MODIS (Moderate Resolution Imaging Spectrometer)
MODIS (Moderate Resolution Imaging Spectrometer)MODIS (Moderate Resolution Imaging Spectrometer)
MODIS (Moderate Resolution Imaging Spectrometer)Nepal Flying Labs
 
GNSS Satellite System Basics by ASIM khan GNSS-7
GNSS Satellite System Basics  by ASIM khan GNSS-7GNSS Satellite System Basics  by ASIM khan GNSS-7
GNSS Satellite System Basics by ASIM khan GNSS-7AsimKhan367
 
Introduction to Landsat
Introduction to LandsatIntroduction to Landsat
Introduction to LandsatNizam GIS
 
Inter fellous freilich
Inter fellous freilichInter fellous freilich
Inter fellous freilichNASAPMC
 
Apartes de la conferencia de la SJG del 14 y 21 de Enero de 2012: Alternative...
Apartes de la conferencia de la SJG del 14 y 21 de Enero de 2012: Alternative...Apartes de la conferencia de la SJG del 14 y 21 de Enero de 2012: Alternative...
Apartes de la conferencia de la SJG del 14 y 21 de Enero de 2012: Alternative...SOCIEDAD JULIO GARAVITO
 

Tendances (19)

Glavich
GlavichGlavich
Glavich
 
Fundamentals aquatic-web
Fundamentals aquatic-webFundamentals aquatic-web
Fundamentals aquatic-web
 
N15. Lucchesi- "fundamental physics with lageos satellites"
N15. Lucchesi- "fundamental physics with lageos satellites"N15. Lucchesi- "fundamental physics with lageos satellites"
N15. Lucchesi- "fundamental physics with lageos satellites"
 
Hufenback,bernhard isecg ger hufenbach pmc v2
Hufenback,bernhard isecg ger hufenbach pmc v2Hufenback,bernhard isecg ger hufenbach pmc v2
Hufenback,bernhard isecg ger hufenbach pmc v2
 
Jody.singer
Jody.singerJody.singer
Jody.singer
 
The use of geoinformatics in mineral exploration and exploitation
The use of geoinformatics in mineral exploration and exploitationThe use of geoinformatics in mineral exploration and exploitation
The use of geoinformatics in mineral exploration and exploitation
 
Indian Satellite Program(2001-2020)
Indian Satellite Program(2001-2020)Indian Satellite Program(2001-2020)
Indian Satellite Program(2001-2020)
 
Thailand Earth Observation System sattellite
Thailand Earth Observation System sattelliteThailand Earth Observation System sattellite
Thailand Earth Observation System sattellite
 
Intro to RS and GIS by mndp poonia
Intro to RS and GIS by mndp pooniaIntro to RS and GIS by mndp poonia
Intro to RS and GIS by mndp poonia
 
IRS satallites
IRS satallitesIRS satallites
IRS satallites
 
AAS National Conference 2008: Diana Blaney
AAS National Conference 2008: Diana BlaneyAAS National Conference 2008: Diana Blaney
AAS National Conference 2008: Diana Blaney
 
Galaxy Forum SEA 2016 Malaysia - Hakim Malasan
Galaxy Forum SEA 2016 Malaysia - Hakim MalasanGalaxy Forum SEA 2016 Malaysia - Hakim Malasan
Galaxy Forum SEA 2016 Malaysia - Hakim Malasan
 
MODIS (Moderate Resolution Imaging Spectrometer)
MODIS (Moderate Resolution Imaging Spectrometer)MODIS (Moderate Resolution Imaging Spectrometer)
MODIS (Moderate Resolution Imaging Spectrometer)
 
GNSS Satellite System Basics by ASIM khan GNSS-7
GNSS Satellite System Basics  by ASIM khan GNSS-7GNSS Satellite System Basics  by ASIM khan GNSS-7
GNSS Satellite System Basics by ASIM khan GNSS-7
 
Introduction to Landsat
Introduction to LandsatIntroduction to Landsat
Introduction to Landsat
 
Inter fellous freilich
Inter fellous freilichInter fellous freilich
Inter fellous freilich
 
Display case display
Display case displayDisplay case display
Display case display
 
Indian remote sensing
Indian remote sensingIndian remote sensing
Indian remote sensing
 
Apartes de la conferencia de la SJG del 14 y 21 de Enero de 2012: Alternative...
Apartes de la conferencia de la SJG del 14 y 21 de Enero de 2012: Alternative...Apartes de la conferencia de la SJG del 14 y 21 de Enero de 2012: Alternative...
Apartes de la conferencia de la SJG del 14 y 21 de Enero de 2012: Alternative...
 

En vedette

Diaz franklin
Diaz franklinDiaz franklin
Diaz franklinNASAPMC
 
2012 02-22 rittweger orlando ipmc
2012 02-22 rittweger orlando ipmc2012 02-22 rittweger orlando ipmc
2012 02-22 rittweger orlando ipmcNASAPMC
 
Manzer fred
Manzer fredManzer fred
Manzer fredNASAPMC
 
Cameron pm cpresentation ii of 2-15-12
Cameron pm cpresentation ii of 2-15-12Cameron pm cpresentation ii of 2-15-12
Cameron pm cpresentation ii of 2-15-12NASAPMC
 
Pinck.pascal
Pinck.pascalPinck.pascal
Pinck.pascalNASAPMC
 
Jansen.michael
Jansen.michaelJansen.michael
Jansen.michaelNASAPMC
 
Richard.laws
Richard.lawsRichard.laws
Richard.lawsNASAPMC
 
Graybill.michael
Graybill.michaelGraybill.michael
Graybill.michaelNASAPMC
 
Arthur.chmielewski
Arthur.chmielewskiArthur.chmielewski
Arthur.chmielewskiNASAPMC
 
Neil.dennehy
Neil.dennehyNeil.dennehy
Neil.dennehyNASAPMC
 
Frost.jim
Frost.jimFrost.jim
Frost.jimNASAPMC
 
Shinn.s.hunter.h
Shinn.s.hunter.hShinn.s.hunter.h
Shinn.s.hunter.hNASAPMC
 
Carmichael.kevin
Carmichael.kevinCarmichael.kevin
Carmichael.kevinNASAPMC
 
Chen.tim
Chen.timChen.tim
Chen.timNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Ed mangopanelpm challengefinal
Ed mangopanelpm challengefinalEd mangopanelpm challengefinal
Ed mangopanelpm challengefinalNASAPMC
 
Inter mitchell
Inter mitchellInter mitchell
Inter mitchellNASAPMC
 
Claunch.cathy
Claunch.cathyClaunch.cathy
Claunch.cathyNASAPMC
 
Vince.bilardo
Vince.bilardoVince.bilardo
Vince.bilardoNASAPMC
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNASAPMC
 

En vedette (20)

Diaz franklin
Diaz franklinDiaz franklin
Diaz franklin
 
2012 02-22 rittweger orlando ipmc
2012 02-22 rittweger orlando ipmc2012 02-22 rittweger orlando ipmc
2012 02-22 rittweger orlando ipmc
 
Manzer fred
Manzer fredManzer fred
Manzer fred
 
Cameron pm cpresentation ii of 2-15-12
Cameron pm cpresentation ii of 2-15-12Cameron pm cpresentation ii of 2-15-12
Cameron pm cpresentation ii of 2-15-12
 
Pinck.pascal
Pinck.pascalPinck.pascal
Pinck.pascal
 
Jansen.michael
Jansen.michaelJansen.michael
Jansen.michael
 
Richard.laws
Richard.lawsRichard.laws
Richard.laws
 
Graybill.michael
Graybill.michaelGraybill.michael
Graybill.michael
 
Arthur.chmielewski
Arthur.chmielewskiArthur.chmielewski
Arthur.chmielewski
 
Neil.dennehy
Neil.dennehyNeil.dennehy
Neil.dennehy
 
Frost.jim
Frost.jimFrost.jim
Frost.jim
 
Shinn.s.hunter.h
Shinn.s.hunter.hShinn.s.hunter.h
Shinn.s.hunter.h
 
Carmichael.kevin
Carmichael.kevinCarmichael.kevin
Carmichael.kevin
 
Chen.tim
Chen.timChen.tim
Chen.tim
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Ed mangopanelpm challengefinal
Ed mangopanelpm challengefinalEd mangopanelpm challengefinal
Ed mangopanelpm challengefinal
 
Inter mitchell
Inter mitchellInter mitchell
Inter mitchell
 
Claunch.cathy
Claunch.cathyClaunch.cathy
Claunch.cathy
 
Vince.bilardo
Vince.bilardoVince.bilardo
Vince.bilardo
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_case
 

Similaire à Freaner.claude

Science with small telescopes - exoplanets
Science with small telescopes - exoplanetsScience with small telescopes - exoplanets
Science with small telescopes - exoplanetsguest8aa6ebb
 
The messenger mission_to_mercury
The messenger mission_to_mercuryThe messenger mission_to_mercury
The messenger mission_to_mercurySérgio Sacani
 
The extremely high albedo of LTT 9779 b revealed by CHEOPS
The extremely high albedo of LTT 9779 b revealed by CHEOPSThe extremely high albedo of LTT 9779 b revealed by CHEOPS
The extremely high albedo of LTT 9779 b revealed by CHEOPSSérgio Sacani
 
Phd talk.mini
Phd talk.miniPhd talk.mini
Phd talk.minigf25
 
The James Webb Space Telescope
The James Webb Space TelescopeThe James Webb Space Telescope
The James Webb Space TelescopeAlberto Conti
 
Dennon.clardy
Dennon.clardyDennon.clardy
Dennon.clardyNASAPMC
 
Silicon Happy Valley 2016
Silicon Happy Valley 2016Silicon Happy Valley 2016
Silicon Happy Valley 2016Corey Cochrane
 
Curiosity talk summer_interns_jun2013
Curiosity talk summer_interns_jun2013Curiosity talk summer_interns_jun2013
Curiosity talk summer_interns_jun2013Mouna Lyra
 
Data Science Education: Needs & Opportunities in Astronomy
Data Science Education: Needs & Opportunities in AstronomyData Science Education: Needs & Opportunities in Astronomy
Data Science Education: Needs & Opportunities in AstronomyJoshua Bloom
 
The false positive_rate_of_kepler_and_the_occurrence_of_planets
The false positive_rate_of_kepler_and_the_occurrence_of_planetsThe false positive_rate_of_kepler_and_the_occurrence_of_planets
The false positive_rate_of_kepler_and_the_occurrence_of_planetsSérgio Sacani
 
Gl581 Preprint
Gl581 PreprintGl581 Preprint
Gl581 PreprintSlidesluis
 
Patterson.donna
Patterson.donnaPatterson.donna
Patterson.donnaNASAPMC
 
Exoplanet transit spectroscopy_using_wfc3
Exoplanet transit spectroscopy_using_wfc3Exoplanet transit spectroscopy_using_wfc3
Exoplanet transit spectroscopy_using_wfc3Sérgio Sacani
 

Similaire à Freaner.claude (20)

Bitten
BittenBitten
Bitten
 
The Future of Solar System Exploration
The Future of Solar System ExplorationThe Future of Solar System Exploration
The Future of Solar System Exploration
 
AAS National Conference 2008: Jon Morse
AAS National Conference 2008: Jon MorseAAS National Conference 2008: Jon Morse
AAS National Conference 2008: Jon Morse
 
Eso1134b
Eso1134bEso1134b
Eso1134b
 
Science with small telescopes - exoplanets
Science with small telescopes - exoplanetsScience with small telescopes - exoplanets
Science with small telescopes - exoplanets
 
The messenger mission_to_mercury
The messenger mission_to_mercuryThe messenger mission_to_mercury
The messenger mission_to_mercury
 
Goddard 2015: John Mather, NASA
Goddard 2015: John Mather, NASAGoddard 2015: John Mather, NASA
Goddard 2015: John Mather, NASA
 
Fesen - Space Sciences - Spring Review 2012
Fesen - Space Sciences - Spring Review 2012Fesen - Space Sciences - Spring Review 2012
Fesen - Space Sciences - Spring Review 2012
 
The extremely high albedo of LTT 9779 b revealed by CHEOPS
The extremely high albedo of LTT 9779 b revealed by CHEOPSThe extremely high albedo of LTT 9779 b revealed by CHEOPS
The extremely high albedo of LTT 9779 b revealed by CHEOPS
 
Phd talk.mini
Phd talk.miniPhd talk.mini
Phd talk.mini
 
The James Webb Space Telescope
The James Webb Space TelescopeThe James Webb Space Telescope
The James Webb Space Telescope
 
Dennon.clardy
Dennon.clardyDennon.clardy
Dennon.clardy
 
Silicon Happy Valley 2016
Silicon Happy Valley 2016Silicon Happy Valley 2016
Silicon Happy Valley 2016
 
Bicay_Post
Bicay_PostBicay_Post
Bicay_Post
 
Curiosity talk summer_interns_jun2013
Curiosity talk summer_interns_jun2013Curiosity talk summer_interns_jun2013
Curiosity talk summer_interns_jun2013
 
Data Science Education: Needs & Opportunities in Astronomy
Data Science Education: Needs & Opportunities in AstronomyData Science Education: Needs & Opportunities in Astronomy
Data Science Education: Needs & Opportunities in Astronomy
 
The false positive_rate_of_kepler_and_the_occurrence_of_planets
The false positive_rate_of_kepler_and_the_occurrence_of_planetsThe false positive_rate_of_kepler_and_the_occurrence_of_planets
The false positive_rate_of_kepler_and_the_occurrence_of_planets
 
Gl581 Preprint
Gl581 PreprintGl581 Preprint
Gl581 Preprint
 
Patterson.donna
Patterson.donnaPatterson.donna
Patterson.donna
 
Exoplanet transit spectroscopy_using_wfc3
Exoplanet transit spectroscopy_using_wfc3Exoplanet transit spectroscopy_using_wfc3
Exoplanet transit spectroscopy_using_wfc3
 

Plus de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 

Plus de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Dernier

Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...gurkirankumar98700
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 

Dernier (20)

Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 

Freaner.claude

  • 1. Life Cycle Cost Growth Study 20 Science Mission Directorate (SMD) Missions Presented at the 2011 NASA Program Management Challenge 9-10 February 2011, Long Beach, California Claude Freaner, Science Mission Directorate, NASA HQ 1
  • 2. Background • Previous studies1, 2 have primarily examined Development Cost Growth in an attempt to determine when in the development lifecycle the growth occurs • Growth was studied for 20 SMD Missions launched between 2000 and 2009. – Mass, Power, Cost, and Schedule were examined • Launch vehicle and Phase E operations costs (planned versus actual) have also grown but the amounts/phasing of this growth were not included in the prior studies – Current study includes LV and Phase E operations cost 1. “Using Historical NASA Cost and Schedule Growth to Set Future Program and Project Reserve Guidelines”, Bitten R., Emmons D., Freaner C., IEEE Aerospace Conference, Big Sky, Montana, March 3-10, 2007 2, “Optimism in Early Conceptual Designs and Its Effect on Cost and Schedule Growth: An Update”, Bitten R., Freaner C., Emmons D., 2010 NASA Program Management Challenge, Galveston, Texas, February 9-10, 2010 2
  • 3. Study Approach • For a set of 20 missions in the study, the cost data were obtained from all of the CADRes for missions at ATP (Phase B start), PDR, CDR, and Launch. • The cost data was “binned” into these Work Breakdown Structure (WBS) element categories: – PMSEMA: Project Management, Systems Engineering, Mission Assurance – SCI/EPO: Science, Education, Public Outreach – Payload – Bus/AIT: Spacecraft Bus, System Assembly Integration and Test – GDS/MOS: pre-launch Ground Data System, Mission Operations – L/V: Launch Vehicle – Phase E: Post-Launch Operations and Data Analysis • Cost data has not been adjusted for “Full Cost” effects – Primarily impacts STEREO, CALIPSO, FERMI The majority of these missions were in development prior to the CADRe requirement existing, so separation of the costs into the standard WBS Level 2 elements was difficult. Therefore, the elements were combined into the above bins. 3
  • 4. Database Description: 20 Missions Represent a Wide Range of Recent NASA Missions Key Launch Acquisition Number of Planetary? Program Science Type Center(s) Year Type Instruments Comments Advanced land imaging technology EO-1 NMP Earth Science GSFC 2000 Competed 5 demonstrator Collect samples of solar wind particles at GENESIS X Discovery Planetary Science JPL 2001 Competed 4 L1 point and return them to Earth • 5 Directed vs. 15 GRACE ESSP Earth Science JPL 2002 Competed 6 Earth Gravity Measurement Competed missions Spitzer Physics of the Cosmos Astrophysics JPL 2003 Directed 4 IR space telescope, the last of the Great Observatories GALEX Explorers Astrophysics JPL/CalTech 2003 Competed 1 UV space telescope SWIFT Explorers Astrophysics GSFC 2004 Competed 4 Gamma Ray burst detector • 7 Planetary missions MESSENGER X Discovery Planetary Science APL 2004 Competed 7 Investigate Mercury vs. 13 Earth or near- MRO X MEP Planetary Science JPL 2005 Directed 7 Investigate history of water on Mars Earth Orbiters Deep Impact X Discovery Planetary Science JPL 2005 Competed 3 Comet impactor Cloudsat ESSP Earth Science JPL 2006 Competed 1 Radar observation of clouds 2 spacecraft looking at solar dynamics - STEREO STP Heliospheric Science GSFC/APL 2006 Directed 4 • 7 Planetary Science Earth leading and trailing orbits CALIPSO ESSP Earth Science LARC 2006 Competed 3 Aerosols vs. 5 Astrophysics New X New Planetary Science APL 2006 Competed 7 Investigate Pluto Horizons Frontiers vs. 5 Earth Science DAWN X Discovery Planetary Science JPL 2007 Competed 2 Investigate Ceres and Vesta protoplanets vs. 3 Heliophysics AIM Explorers Heliospheric Science LASP 2007 Competed 3 Aeronomy of Ice in Mesosphere missions Fermi (GLAST) Physics of the Cosmos Astrophysics GSFC 2008 Directed 2 Gamma Ray Telescope Interaction between solar wind and IBEX Explorers Heliospheric Science GSFC 2008 Competed 2 interstellar medium Kepler Discovery Astrophysics JPL 2009 Competed 1 Search for Earth-sized exoplanets Robotic ESMD/Planetary LRO X GSFC 2009 Directed 7 Origin of the Moon Lunar Science Carbon Dioxide Investigation. Mission OCO ESSP Earth Science JPL 2009 Competed 1 failed due to launch vehicle failure 4
  • 5. Composition of Average Life Cycle Cost & Cost Growth Category as Percent of Distribution of Growth of LCC Average LCC at Launch From PDR to Launch Phase E 6% SCI/EPO 3% SCI/EPO PMSEM PMSE 2% Phase E L/V 11% A MA 9% 7% 12% L/V GDS/ 17% MOS Payload 12% 23% Payload GDS Bus/AIT 32% 6% 29% Bus/AIT 31% 5
  • 6. “Portfolio” % Average LCC Cost Growth Average Cost Growth by Major WBS, 200% Reserves Not Included (20 Missions) 180% 160% 140% Percent Growth 120% 100% 80% ATP to LRD 60% 56% PDR to LRD 40% 40% 20% 0% Largest Percent Growth for PMSEMA & GDS/OS Growth = (Total LCC at Launch/Total LCC at KDP) -1 Note: ATP is equivalent to KDP-B 6
  • 7. Total Cost Growth ($) by Major WBS Element (20 Missions) 1,000,000 800,000 Total Growth = $2.1B 600,000 Total Growth = $1.6B 400,000 Cost Growth in $K 200,000 ATP to LRD PDR to LRD - (200,000) (400,000) Total Cost at Launch = $7.6B (600,000) Reserves shown were planned to cover all growth (800,000) Largest Absolute Dollar Growth for Payload & Spacecraft 7
  • 8. PMSEMA Cost Growth from ATP* (Phase B start) 450% Mission #1 Mission #2 400% Mission #3 Mission #4 350% Mission #5 Mission #6 300% Mission #7 Mission #8 250% Mission #9 Mission #10 200% 178% Mission #11 Mission #12 150% Mission #13 Mission #14 100% Mission #15 61% Mission #16 50% 38% Mission #17 0% Mission #18 0% Mission #19 ATP PDR CDR Launch Mission #20 -50% Average -100% Majority of PMSEMA Growth Occurs After CDR * Note: Reserves not included 8
  • 9. PMSEMA Cost Growth from PDR* 400% Mission #1 Mission #2 350% Mission #3 Mission #4 300% Mission #5 Mission #6 250% Mission #7 Mission #8 200% Mission #9 Mission #10 150% Mission #11 114% Mission #12 100% Mission #13 Mission #14 50% Mission #15 17% Mission #16 0% Mission #17 0% PDR CDR Launch Mission #18 Mission #19 -50% Mission #20 Average -100% Majority of PMSEMA Growth Occurs After CDR * Note: Reserves not included 9
  • 10. Science/EPO Cost Growth from ATP* (Phase B start) 500% Mission #1 Mission #2 Mission #3 400% Mission #4 Mission #5 Mission #6 300% Mission #7 Mission #8 Mission #9 200% Mission #10 Mission #11 Mission #12 100% Mission #13 48% Mission #14 11% 18% Mission #15 0% 0% Mission #16 ATP PDR CDR Launch Mission #17 Mission #18 -100% Mission #19 Mission #20 Average -200% Majority of Science/EPO Growth Occurs After CDR * Note: Reserves not included 10
  • 11. Science/EPO Cost Growth from PDR* 300% Mission #1 Mission #2 Mission #3 250% Mission #4 Mission #5 200% Mission #6 Mission #7 Mission #8 150% Mission #9 Mission #10 Mission #11 100% Mission #12 Mission #13 Mission #14 50% 32% Mission #15 18% Mission #16 0% 0% Mission #17 PDR CDR Launch Mission #18 Mission #19 -50% Mission #20 Average -100% Science/EPO Grows Steadily After PDR * Note: Reserves not included 11
  • 12. Payload Cost Growth from ATP* (Phase B start) 250% Mission #1 Mission #2 Mission #3 200% Mission #4 Mission #5 Mission #6 150% Mission #7 Mission #8 103% Mission #9 100% Mission #10 Mission #11 Mission #12 Mission #13 50% 34% Mission #14 15% Mission #15 0% Mission #16 0% Mission #17 ATP PDR CDR Launch Mission #18 Mission #19 -50% Majority of Payload Growth Occurs After CDR * Note: Reserves not included 12
  • 13. Payload Cost Growth from PDR* 200% Mission #1 Mission #2 Mission #3 Mission #4 150% Mission #5 Mission #6 Mission #7 Mission #8 Mission #9 100% Mission #10 77% Mission #11 Mission #12 Mission #13 50% Mission #14 Mission #15 17% Mission #16 Mission #17 0% Mission #18 0% PDR CDR Launch Mission #19 Mission #20 Average -50% Majority of Payload Growth Occurs After CDR * Note: Reserves not included 13
  • 14. Bus/AIT Cost Growth from ATP* 160% Mission #1 Mission #2 140% Mission #3 Mission #4 120% Mission #5 Mission #6 100% Mission #7 Mission #8 Mission #9 80% Mission #10 Mission #11 60% 55% Mission #12 Mission #13 40% Mission #14 Mission #15 18% Mission #16 20% 11% Mission #17 0% Mission #18 0% Mission #19 ATP PDR CDR Launch Mission #20 -20% Average -40% Majority of Bus/AIT Growth Occurs After CDR * Note: Reserves not included 14
  • 15. Bus/AIT Cost Growth from PDR* 120% Mission #1 Mission #2 Mission #3 100% Mission #4 Mission #5 Mission #6 80% Mission #7 Mission #8 Mission #9 60% Mission #10 Mission #11 Mission #12 40% 40% Mission #13 Mission #14 Mission #15 Mission #16 20% Mission #17 7% Mission #18 0% Mission #19 0% Mission #20 PDR CDR Launch Average -20% Majority of Bus/AIT Growth Occurs After CDR * Note: Reserves not included 15
  • 16. Pre-Launch GDS/MOS Cost Growth from ATP* (Phase B start) EO-1 Excluded from Average 800% Mission #1 Mission #2 700% Mission #3 Mission #4 Mission #5 600% Mission #6 Mission #7 500% Mission #8 Mission #9 400% Mission #10 Mission #11 Mission #12 300% Mission #13 Mission #14 200% 165% Mission #15 Mission #16 100% 67% Mission #17 54% Mission #18 0% Mission #19 0% Mission #20 ATP PDR CDR Launch Average -100% Majority of Pre-Launch GDS/MOS Growth Occurs After CDR * Note: Reserves not included 16
  • 17. Pre-Launch GDS/MOS Cost Growth from PDR* EO-1 & CALIPSO Excluded from Average 900% Mission #1 Mission #2 800% Mission #3 700% Mission #4 Mission #5 600% Mission #6 Mission #7 500% Mission #8 Mission #9 400% Mission #10 Mission #11 300% Mission #12 Mission #13 200% Mission #14 Mission #15 100% 74% Mission #16 0% 11% Mission #17 0% Mission #18 PDR CDR Launch Mission #19 -100% Mission #20 Average -200% Majority of Pre-Launch GDS/MOS Growth Occurs After CDR * Note: Reserves not included 17
  • 18. Launch Vehicle Cost Growth from ATP* (Phase B start) 100% Mission #1 Mission #2 Mission #3 80% Mission #4 Mission #5 Mission #6 60% Mission #7 Mission #8 Mission #9 40% Mission #10 Mission #11 Mission #12 20% Mission #13 10% Mission #14 0% 2% Mission #15 -3% Mission #16 0% ATP PDR CDR Launch Mission #17 Mission #18 -20% Mission #19 Mission #20 Average -40% Majority of Launch Vehicle Growth Occurs After CDR * Note: Reserves not included 18
  • 19. Launch Vehicle Cost Growth from PDR* 100% Mission #1 Mission #2 Mission #3 80% Mission #4 Mission #5 Mission #6 60% Mission #7 Mission #8 Mission #9 40% Mission #10 Mission #11 Mission #12 20% 14% Mission #13 Mission #14 5% Mission #15 0% 0% Mission #16 PDR CDR Launch Mission #17 Mission #18 Mission #19 -20% Mission #20 Average -40% Majority of Launch Vehicle Growth Occurs After CDR * Note: Reserves not included 19
  • 20. Planned Phase E Cost Growth from ATP* (Phase B start) CALIPSO Excluded from Average 400% Mission #1 Mission #2 350% Mission #3 Mission #4 300% Mission #5 Mission #6 250% Mission #7 Mission #8 200% Mission #9 Mission #10 150% Mission #11 Mission #12 Mission #13 100% Mission #14 Mission #15 50% 27% 34% Mission #16 11% Mission #17 0% 0% Mission #18 ATP PDR CDR Launch Mission #19 -50% Mission #20 Average -100% Majority of Phase E Growth Occurs Prior to CDR * Note: Reserves not included 20
  • 21. Planned Phase E Cost Growth from PDR* CALIPSO Excluded from Average 400% Mission #1 350% Mission #2 Mission #3 300% Mission #4 Mission #5 Mission #6 250% Mission #7 Mission #8 200% Mission #9 Mission #10 150% Mission #11 Mission #12 Mission #13 100% Mission #14 Mission #15 50% Mission #16 13% 21% Mission #17 0% 0% Mission #18 PDR CDR Launch Mission #19 Mission #20 -50% Average -100% Majority of Phase E Growth Occurs Prior to CDR * Note: Reserves not included 21
  • 22. LCC Growth from ATP* (Phase B start) (Includes Planned Phase E) 180% Mission #1 Mission #2 160% Mission #3 Mission #4 140% Mission #5 Mission #6 120% Mission #7 Mission #8 Mission #9 100% Mission #10 Mission #11 80% Mission #12 58% Mission #13 60% Mission #14 Mission #15 40% Mission #16 Mission #17 20% 20% Mission #18 9% Mission #19 0% Mission #20 0% Average ATP PDR CDR Launch -20% Majority of LCC Growth Occurs After CDR * Note: Reserves not included Growth = Average ((Mission LCC at Launch/Mission LCC at KDP)-1) 22
  • 23. LCC Growth from PDR* (Includes Planned Phase E) 140% Mission #1 Mission #2 120% Mission #3 Mission #4 Mission #5 100% Mission #6 Mission #7 Mission #8 80% Mission #9 Mission #10 60% Mission #11 Mission #12 45% Mission #13 40% Mission #14 Mission #15 Mission #16 20% Mission #17 10% Mission #18 0% Mission #19 0% Mission #20 PDR CDR LRD Average -20% Majority of LCC Growth Occurs After CDR * Note: Reserves not included Growth = Average ((Mission LCC at Launch/Mission LCC at KDP)-1) 23
  • 24. Reserves Standards • JPL Flight Project Practices, Rev. 7: – At PDR, budget reserves must be 25% of cost to go. – At CDR, budget reserves must be 20% of cost to go. – At start of ATLO, budget reserves must be 20% of cost to go. • GSFC “Gold Rules” – At PDR, budget reserves must be 25% of cost to go. •LCC growth from PDR to Launch averages 41% of Total Cost (reserves excluded), not cost to go •LCC growth from CDR to Launch averages 32% of Total Cost (reserves excluded), not cost to go 24
  • 25. Probability that 25% Reserves at PDR Are Sufficient • Growth from PDR to Launch average is 41% (excluding EO-1) – Standard Deviation = 21% – Probability that a mission with 25% reserves at PDR will stay within those reserves by Launch = 22% – To achieve 70% CL, reserves of 47% would have been needed • Growth from PDR to Launch average is 45% (including EO-1) – Standard Deviation = 28% – Probability that a mission with 25% reserves at PDR will stay within those reserves by Launch = 23% – To achieve 70% CL, reserves of 52% would have been needed 25
  • 26. So…Why Do We Have Cost Growth? • Over-optimism at the start – Propensity for proposers to be in marketing mode – Initial Mass estimates are low • Average Payload Mass Growth PDR-Launch = 77% – Initial Schedule estimates are short – Cost… Likely bid to the cost cap or available budget, not what it realistically takes • Cost estimators can use wider ranges on parameters for estimating the input values used for cost risk analysis – Current Cost risk process appears to be underestimating the resource growth • Schedule slips – Average Launch date slip from PDR plan: 13+ Months – Average Launch date slip from CDR plan: 10- Months – Majority of schedule slips occur during ATLO. • “Stuff” happens – Harder than we thought – Suppliers have problems – Things break – Congress/OMB/NASA HQ change funding profiles 26
  • 27. What Can We Do to Decrease Cost Growth? • Proper scoping of projects early in conceptual design to provide executable program plans • Require better Basis of Estimate – Require proposers to show relevant actuals from prior missions at the subsystem level – “Relevant actuals” means Mass, Power, Cost, Schedule – Risk assessment and quantification of risk • Independent validation of instrument resources, and the resulting spacecraft resources needed to meet mission requirements, would allow more accurate estimates • Increase reserves is one possible solution – Reduces number of missions per year – Costs will likely rise to beyond the new reserves after a short time. • Incentivize contracts – Large rewards to Center/Team for performing to initial budget/schedule – Punishment • Easy to apply to Corporations: take away fee, cost share any overruns, etc. • Difficult to apply to NASA Centers 27
  • 28. The author wishes to express sincere appreciation to Robert E. Bitten and Debra L. Emmons, The Aerospace Corporation, for their help in the preparation of this presentation. Electronic copies of this and the two previous studies referenced on slide 2 may be obtained by sending an email to claude.freaner@nasa.gov 28

Notes de l'éditeur

  1. The left pie chart says, at launch, on what we spent our money; the right pie chart shows the portion of total growth in cost between PDR and launch, and where the growth occurred.
  2. In the prior studies, Development Cost Growth, excluding L/V and Phase E was 56% from ATP and 37% from PDR.
  3. If MRO is excluded, Average at launch drops to 27%
  4. Excluding EO-1 would lower the average at launch to 6%; EO-1 growth was from $18M to $32MNew Horizons growth was 41%, or growth from $173M to $243M. It should be noted, that at ATP, the expected cost of the L//V was unknown, and the $174M was a placeholder.
  5. Excluding EO-1 reduces average at launch to 11%; excluding New Horizons, lowers it further to 8%
  6. Excluding EO-1 reduces growth from 58% to 53%The point here is that at ATP (KDP-B), reserves of 58% on LCC were needed, not the 25% on development cost only that is the industry standard.
  7. Excluding EO-1 reduces growth at launch from 45% to 41%Only 5 missions out of 20 kept their LCC growth below 25% between PDR and Launch: GRACE (12%), LRO (16%), GENESIS (17%), MRO (23%), NEW HORIZONS (25%)
  8. 41% of total cost means reserves at PDR should be around 41%/.85, or around 48%32% of total cost means reserves at CDR should be around 32%/.6, or around 53%
  9. StDev at PDR = 8.2 monthsStDev at CDR = 6.5 months