SlideShare une entreprise Scribd logo
1  sur  35
Télécharger pour lire hors ligne
Integrated Cost-Schedule Risk
  Analysis using Risk Drivers
     and Prioritizing Risks
           Presented at
       NASA PM Challenge
       February 9-10, 2010
    Moody Gardens, Galveston TX
              David T. Hulett, Ph.D.
               Hulett & Associates, LLC
                Los Angeles, CA USA
www.projectrisk.com / info@projectrisk.com / +1 (310) 476-7699

                    © 2009 Hulett & Associates, LLC              1
                        Used with permission
Agenda
• Integrating cost and schedule risk analysis
• The Risk Driver method
• The schedule for an offshore gas production
  platform project
• Risk Register risks and their parameters
• Schedule Risk analysis results and priority risks
• Cost Risk analysis results and priority risks
• Risk Mitigation scenarios

                    © 2009 Hulett & Associates, LLC   2
Why Integrate
  Cost and Schedule Risk Analysis? (1)
• Many cost risk analyses assume that the schedule
  is fixed at the baseline and do not account for the
  impact of schedule risk
• Other cost risk analyses take ad hoc account of
  schedule risk but not through the schedule itself
  or from a schedule risk analysis result
• This analysis shows that project cost and time are
  related and that we can model that relationship
  directly
                    © 2009 Hulett & Associates, LLC   3
Why Integrate
  Cost and Schedule Risk Analysis? (2)
• Driving cost risk by schedule risk where
  appropriate:
   – Results in a better estimate of cost risk
   – Helps to understand where the risk comes from
   – Points to mitigation of risks that can affect both
     cost and schedule
   – Is based in the project schedule so we can see the
     time-profile of cash flow, risk adjusted


                    © 2009 Hulett & Associates, LLC       4
Results from Integrated
        Cost and Schedule Risk Analysis
•   The likelihood of schedule and cost success
•   The schedule and cost contingency reserve
    needed for desired level of certainty
•   The list of risks to schedule and to cost in ranked
    order of priority
    – Assists risk mitigation
•   Probabilistic cash flow


                      © 2009 Hulett & Associates, LLC   5
Integrating
       Cost and Schedule Risk Analysis
• Some costs (labor, rigs, barges) are determined
  by changes in duration
  – Cost risk is driven by schedule risk since these
    resources cost more if they work longer
  – Cost risk may also be affected by uncertain burn
    rate/day
• Other costs (equipment, material) are uncertain,
  but not because of activity duration


                   © 2009 Hulett & Associates, LLC     6
Traditional 3-point Estimates of Duration

• Traditional schedule risk analysis starts with the
  activity that is impacted by risks
   – Estimates the 3-points for optimistic, most likely and
     pessimistic duration
   – Creates a probability distribution for activity duration
   – Performs Monte Carlo simulation
• Can we tell the high priority risks? This question is
  typically answered by:
   – Sensitivity – activities that are correlated with total time
     risk
   – Criticality – activities that are most likely on the critical
     path
                         © 2009 Hulett & Associates, LLC             7
Some Problems with Traditional Approach

• Makes poor use of the Risk Register that is usually
  available
• Can tell which activities or schedule paths are
  crucial, but not which risks are driving
   – Traditional approaches cannot prioritize risks, only
     activities or paths




                     © 2009 Hulett & Associates, LLC    8
We Propose the Risk Driver Approach:
           Start with the Risks Themselves
• Drive the schedule risk directly by the risks already
  analyzed in the Risk Register
• For each risk, specify:
   – Probability it will occur – proportion of iterations it affects
     activity durations
   – Impact on time if it does – in terms of multiplicative factors
   – Activities it will affect
• This approach focuses on the risks, not on the risks’ impact on
  activities



                           © 2009 Hulett & Associates, LLC             9
Flow Chart of Risk Management
  using the Risk Driver Approach
Risk Identification – list of potential
        risks to the project

      Qualitative Risk Analysis – prioritized list of
                 risks to time and cost

                        Quantitative Risk Analysis
                          Risk Driver Approach

                                  Mitigating schedule and cost risks

                                             Monitoring and controlling risk


                           © 2009 Hulett & Associates, LLC                     10
Three Types of Risk
• Uncertainties, such as the level of labor
  productivity.
• Ambiguities, such as the accuracy of cost
  estimates and schedules
  – These always occur but may have a range of
    impacts
• Risk events that may or may not occur
  – These have both probability of occurring and
    impact ranges
                   © 2009 Hulett & Associates, LLC   11
Examples of Three Risk Types


• Schedule immaturity is an ambiguity. It has 100%
  probability of occurring and its impact range is both good
  and bad
• Construction labor productivity is an uncertainty that,
  compared to the assumption, could be lower or higher
• The possibility of quality, key personnel unavailability is a
  risk event. It may or may not occur, and in this case its
  impact is never to the good

                       © 2009 Hulett & Associates, LLC        12
Uncertainty and Ambiguity Risks
                Occur 100% of the time
                        0010 - Construction : Duration
                                                                                100% 120


                                                                                95% 116
                                                                                                                  Schedule inaccuracy
       240

                                                                                90% 114                           operates in 100% of the time
       220                                                                      85% 113


                                                                                80% 111
                                                                                                                  (all iterations). On a
       200
                                                                                75% 110                           construction activity of 100
       180                                                                      70% 109
                                                                                                                  days duration the results are
                                                                                65% 109
       160
                                                                                60% 108
                                                                                                                  triangular




                                                                                           Cumulative Frequency
       140                                                                      55% 107
                                                                                                                  The construction labor
Hits




                                                                                                                  productivity risk would look
                                                                                50% 106

       120
                                                                                45% 106



       100
                                                                                40% 105                           similar to this figure
                                                                                35% 104

       80
                                                                                30% 104


                                                                                25% 103
       60

                                                                                20% 102

       40                                                                       15% 101


                                                                                10% 100
       20
                                                                                5% 99


        0                                                                       0% 95
             95   100      105                     110         115        120
                           Distribution (start of interval)


                                                              © 2009 Hulett & Associates, LLC                                                13
Risk Events are Described by their
         Probability and Impact
• If probability is < 100%, the risk will occur in that
  percentage of iterations, chosen at random
• On an iteration if the risk occurs, a factor chosen
  at random from its impact range (following a
  triangular distribution) will multiply the duration
  of the activities to which it is assigned
• If the risk does not occur the multiplicative factor
  is 100% with no effect on duration


                    © 2009 Hulett & Associates, LLC   14
Risk Events occur with a
                            Probability < 100%
                         0010 - Construction : Duration
                                                                                  100% 110


                                                                                  95% 108                           Here a risk event, the possible
       900
                                                                                  90% 107
                                                                                                                    unavailability of quality key
                                                                                  85% 107

       800
                                                                                  80% 106
                                                                                                                    staff, occurs 70% of the time.
                                                                                  75% 106                           Hence, in 30% (900) of the
       700
                                                                                  70% 105


                                                                                  65% 105
                                                                                                                    3,000 iterations the original
       600
                                                                                  60% 105                           duration of construction, 100




                                                                                             Cumulative Frequency
                                                                                  55% 104
                                                                                                                    days, is correct. In 70%
Hits




       500                                                                        50% 104


                                                                                  45% 103
                                                                                                                    (2,100) of the iterations, the
       400                                                                        40% 103                           duration is longer than 100
       300
                                                                                  35% 102


                                                                                  30% 101
                                                                                                                    days as a triangle
                                                                                  25% 100


       200                                                                        20% 100


                                                                                  15% 100


       100                                                                        10% 100


                                                                                  5% 100


        0                                                                         0% 100
             100   102     104                   106            108        110
                             Distribution (start of interval)




                                                                 © 2009 Hulett & Associates, LLC                                                15
Risk Driver Strategy
• Risks are usually higher-level strategic risks rather
  than tactical or technical risks
• Data about risks is derived from in-depth
  interviews
• A risk is usually assigned to several activities
• An activity may have several risks assigned




                    © 2009 Hulett & Associates, LLC   16
A Construction Activity with
                     Three Risks Assigned
                        0010 - Construction : Duration

       160
                                                                                 100% 143


                                                                                 95% 127
                                                                                                                   The interaction of the three
       150
                                                                                 90% 124
                                                                                                                   risks produces the expected
       140                                                                       85% 122                           histogram.
       130
                                                                                 80% 120


                                                                                 75% 118
                                                                                                                   In traditional 3-point risk
       120
                                                                                 70% 117
                                                                                                                   estimating, the analyst and
       110
                                                                                 65% 115                           interviewees must
       100                                                                       60% 114
                                                                                                                   approximate the result of




                                                                                            Cumulative Frequency
       90                                                                        55% 113

                                                                                                                   three risks on duration. The
Hits




                                                                                 50% 112
       80



       70
                                                                                 45% 111                           Risk Driver analysis computes
       60
                                                                                 40% 110


                                                                                 35% 109
                                                                                                                   the distribution.
       50                                                                        30% 108


                                                                                 25% 106
       40

                                                                                 20% 105
       30

                                                                                 15% 103
       20
                                                                                 10% 101

       10
                                                                                 5% 99


        0                                                                        0% 90
             90   100     110                   120            130        140
                           Distribution (start of interval)




                                                              © 2009 Hulett & Associates, LLC                                              17
Risk Drivers Avoid the Need to Estimate the
              Correlation Coefficient
Activities A and B
Correlation is
                                           Risk #1
Calculated to be 100%                P = 50%, Factors
                                      .95, 1.05, 1.15




                  Activity A                                    Activity B


In the traditional approach to risk analysis, the correlation coefficient has to
                                 be estimated.
 Risk Drivers model how correlation occurs and the coefficient is a natural
                              result of the model

                              © 2009 Hulett & Associates, LLC                18
Risk Factors Model How
                     Correlation Occurs (2)
         Risk #2                       Risk #1                         Risk #3
     P = 25%, Factors             P = 50%, Factors                  P = 45%, Factors
       .8, .95, 1.05               .95, 1.05, 1.15                    1.0, 1.1, 1.2

Activities A
and B
Correlation
is Calculated      Activity A                                  Activity B
to be 48%


         Risk Drivers model correlation as it is caused in the project
   based on the common (Risk # 1) and confounding (Risks # 2 and #3) risks
                        affecting pairs of activities
       The correlation coefficient is the result, not the assumption
                             © 2009 Hulett & Associates, LLC                      19
Case Study: Hypothetical Voyage to Europa to
     Probe for Evidence of Microbial Life
Risk Analysis on Space Vehicle Project
                   Risk Factors are from Risk Register
                                                            Schedule Impact Factors    Cost Impact Factors

                                                                    Most                      Most
Risk #   Risk                                     Probability Min            Max      Min              Max
                                                                    Likely                    Likely
   1     Requirements have not been decided          80%     95%    110%     120%     95%     105%     110%
   2     Several alternative designs considered     100%     80%    110%     130%     100%    110%     120%
   3     New instruments not yet proven              60%     95%    110%     120%     95%     100%     110%
   4     Fabricaton requires new materials           50%    100%    105%     115%
         Lost know-how since last new-concept
   5                                                 50%     95%    105%     120%     100%    110%     120%
         probe
   6     Funding from Congress is problematic        70%     90%    105%     115%
   7     Schedule may be aggressive                 100%     95%    110%     120%
         Cost estimate is based on immature
   8                                                100%                              100%    110%     120%
         data
Mapping Risks to Activities

                                                                   Assignment of Risks to Activities
                                                                           Integrate     Launch Integrate
Risk # Risk                                      Decision Probe Sciences                                         PMT
                                                                           Probe/Science Vehicle Vehicle/Payload
  1    Requirements have not been decided           X

  2    Several alternative designs considered       X

  3    New instruments not yet proven                              X             X

  4    Fabricaton requires new materials                    X                    X
       Lost know-how since last new-concept
  5                                                         X      X             X
       probe
  6    Funding from Congress is problematic                 X      X             X                     X

  7    Schedule may be aggressive                           X      X             X          X          X

  8    Cost estimate is based on immature data      X       X      X             X          X          X          X
Schedule and Cost Targets are
                            Unlikely to be Met
                                        Summary Risk Results

                                                  Prob
                                      Base                     P-10       P 50         P-80          P-90
                                                  Base

Schedule Date                        8-Sep-22        < 1% 14-Jul-23      27-Aug-24     30-Jul-25    13-Jan-26
   Overrun of Schedule days                                        309           719      1,056        1,223
   Overrun of Schedule %                                            7%           16%       23%             26%
Cost                                    1,941        < 1%        2,280       2,577        2,841        2,992
   Overrun of Cost $                                               339           636          900      1,051
   Overrun of Cost %                                               17%           33%       46%             54%


                           A launch of September 2022 may be in July 2025 without risk
                            mitigation. In light of these results aggressive risk mitigation
                                                     should be done
                                       © 2009 Hulett & Associates, LLC                                23
Examine the Probability of
              Meeting a 2022 Launch Date
                                                  Eurpoa Probe.mpp
                                                    Entire Plan : Finish Date
                                                                                      100% 20OCT28


                                                                                      95% 19JUN26


                                                                                      90% 13JAN26

                             300
                                                                                      85% 14OCT25

Target Launch Date:                                                                   80% 30JUL25

8 SEP 2022                                                                            75% 15MAY25


P-80 30 JUL 2025             250
                                                                                      70% 14MAR25


                                                                                      65% 17JAN25


                                                                                      60% 25NOV24




                                                                                                     Cumulative Frequency
                             200
                                                                                      55% 09OCT24
                      Hits




                                                                                      50% 27AUG24


                                                                                      45% 15JUL24
                             150

                                                                                      40% 24MAY24


                                                                                      35% 12APR24


                                                                                      30% 27FEB24
                             100

                                                                                      25% 10JAN24


                                                                                      20% 22NOV23


                             50                                                       15% 29SEP23


                                                                                      10% 14JUL23


                                                                                      5% 27MAR23


                              0                                                       0% 08SEP21
                                   22OCT23                                  18JUL26
                                             Distribution (start of interval)
Risk Factor Tornado
                                                   from All-In Simulation
                                      Driving Schedule Risk Factors



            3 - New instruments not yet proven



       6 - Funding from Congress is problematic



               7 - Schedule may be aggressive



5 - Lost know-how since last new-concept probe                                         The main RISK,
                                                                                       however, is new
           4 - Fabricaton requires new materials
                                                                                       instruments not yet
       1 - Requirements have not been decided                                          proven, followed by
                                                                                       funding. These are the
      2 - Several alternative designs considered
                                                                                       main risks to mitigate, if
    8 - Cost estimate is based on immature data               This risk is             possible
                                                              exclusively on cost
                                                0.00   0.10   and does not
                                                               0.20    0.30   0.40   0.50
                                                                   Correlation
                                                              impact schedule
Contribution of
          Each Risk to the Time Contingency (1)
               Explain the Contingency to the P-80 with Risks sorted by Priority
                                                       P-80 Date       Contribution of Risk
                                                                                      % of
All Risks In                                           30-Jul-25    Days Saved
                                                                                   Contingency
                              Specific Risks Taken Out in Order
Schedule may be aggressive                            27-Aug-24         337           32%
New instruments not yet proven                         29-Jan-24        211           20%
Funding from Congress is problematic                  15-Sep-23         136           13%
Lost know-how since last new-concept probe             24-Apr-23        144           14%
Fabricaton requires new materials                      19-Jan-23         95            9%
Requirements have not been decided                    23-Nov-22          57            5%
Several alternative designs considered                 8-Sep-22          76            7%
      Total Contingency                                                1,056         100%
Contribution of
     Each Risk to the Time Contingency (2)
                                                                                                                    Distribution Analyzer
Eurpoa Probe.mpp - Entire Plan - Finish Da                             Eurpoa Probe.mpp - Entire Plan - Finish Da                          Eurpoa Probe.mpp - Entire Plan - Finish Da               Eurpoa Probe.mpp - Entire Plan - Finish Da
Eurpoa Probe.mpp - Entire Plan - Finish Da                             Eurpoa Probe.mpp - Entire Plan - Finish Da                          Eurpoa Probe.mpp - Entire Plan - Finish Da               Eurpoa Probe.mpp - Entire Plan - Finish Da
                                                                                                                                                                                                                                                    100%



                                                                                                                                                                                                                                                    90%

                               Variation:67 Variation:95 Variation:144 Variation:136
                                       Variation:65                                      Variation:212               Variation:337
                                                                                                                                                                                                                                                    80%



                                                                                                                                                                                                                                                    70%




                                                                                                                                                                                                                                                           Cumulative Probability
                                                                                                                                                                                                                                                    60%



                                                                                                                                                                                                                                                    50%



                                                                                                                                                                                                                                                    40%



                                                                                                                                                                                                                                                    30%



                                                                                                                                                                                                                                                    20%



                                                                                                                                                                                                                                                    10%



                                                                                                                                                                                                                                                    0%
      08FEB22              27AUG22             15MAR23              01OCT23             18APR24              04NOV24             23MAY25         09DEC25              27JUN26           13JAN27   01AUG27            17FEB28              04SEP28




                                                                                        © 2009 Hulett & Associates, LLC                                                                                                                             27
With this Target Date, the Cost of Resulting
           Overruns Could be Substantial
                                                                        Eurpoa Probe.mpp
                                                                              Entire Plan : Cost
                                                                                                                    100% $3,739,983.72


                                                                                                                    95% $3,114,983.37

                                  450

Base cost = $1.9 billion                                                                                            90% $2,991,768.98


                                                                                                                    85% $2,898,334.50
P-80 cost = $2.8 billion          400
                                                                                                                    80% $2,841,866.21


                                                                                                                    75% $2,776,666.32

                                  350
                                                                                                                    70% $2,728,127.19


                                                                                                                    65% $2,689,446.07

                                  300
                                                                                                                    60% $2,646,803.87




                                                                                                                                         Cumulative Frequency
                                                                                                                    55% $2,611,179.97




                           Hits
                                  250
                                                                                                                    50% $2,577,090.49


                                                                                                                    45% $2,544,706.54

                                  200
                                                                                                                    40% $2,506,499.31


                                                                                                                    35% $2,473,528.88

                                  150                                                                               30% $2,439,553.06


                                                                                                                    25% $2,405,227.50

                                  100                                                                               20% $2,369,904.75


                                                                                                                    15% $2,329,665.92


                                  50                                                                                10% $2,280,465.17


                                                                                                                    5% $2,208,188.73


                                   0                                                                                0% $1,882,995.94
                                        $2,000,000.00   $2,500,000.00               $3,000,000.00   $3,500,000.00
                                                                 Distribution (start of interval)
The Year-to-Year Budget Could be Compromised
                                                                                  Resource Flow for Cost
                                                                                           Filter: Entire Plan

       Mean                                                                               P20                                                                                                   P80




                                                                                                                                                                                                       3,500,000




                                                                                                                                                                                                       3,000,000




                                                                                                                                                                                                       2,500,000




                                                                                                                                                                                                                   Cumulative
                                            Deterministic Cost: $1,940,800.00                                                                                                                          2,000,000




                                                                                                                               Deterministic Finish: 08SEP22
                                                                                                                                                                                                       1,500,000




                                                                                                                                                                                                       1,000,000




                                                                                                                                                                                                       500,000




                                                                                                                                                                                                       0
  12FEB10     27JUN11   08NOV12   23MAR14         05AUG15           17DEC16     01MAY18     13SEP19              25JAN21   09JUN22                             22OCT23   05MAR25   18JUL26   30NOV27
                                                                                          Time




                                    Scatter plot slope indicates that project delays will add
                                                             to cost
Joint Confidence Level 70%
                                                                        Eurpoa Probe.mpp
                                        Deterministic Point                   Inside both limits                   Outside both limits

                                                                                           78%

                                     8%                                                                                              14%

                    $3,600,000.00



                    $3,400,000.00



                    $3,200,000.00



                    $3,000,000.00
Entire Plan: Cost




                    $2,800,000.00                                                                                                          78%
                                    $2,813,335.74



                    $2,600,000.00



                    $2,400,000.00



                    $2,200,000.00



                    $2,000,000.00

                                    70%                                                        25JUN25                               8%

                                               09JUN22        22OCT23            05MAR25                 18JUL26   30NOV27
                                                                            Entire Plan: Finish



                                                                 © 2009 Hulett & Associates, LLC                                                 30
Contribution of
               Each Risk to the Cost Contingency
                     Effect of Risks on Cost Contingency to the P-80
All risks In                                                     2841

                                                           Contribution to    % of
Risks
                                                            contingency    Contingency

Cost estimate is based on immature data                         271           29%
Lost know-how since last new-concept probe                      240           26%
Schedule may be aggressive                                      190           21%
New instruments not yet proven                                   95           10%
Funding from Congress is problematic                            74            8%
Fabricaton requires new materials                               38            4%
Several alternative designs considered                           6            1%
Requirements have not been decided                               5            1%
Analysis of a
                       Risk Mitigation Scenario  Risk Mitigation Scenario
                                                Schedule Risk Factors              Cost Risk Factors
                                                                                                                      Project
                                                        Most                            Most              Launch
                                      %        Min                  Max          Min               Max                Cost ($
                                                        Likely                          Likely             Date
                                                                                                                      million)
Risk to be Mitigated                                                    Before Mitigation

New Instruments Not Yet Proven       60%       95%      110%       120%          95%    100%      110%    30-Jul-25    2,841

Proposed Mitigation: Provide more testing of the instruments before integration at cost of $120 million
                                                                         After Mitigation
May have trouble interfacing
                                     10%       95%      100%       105%          95%    100%      105%    9-Dec-24     2,746
Phases
 Improvement                                                                                                233         95

 Cost of proposed Mitigation                                                                                            120
Net Improvement from
                                                                                                            233         -25
Mitigation

   Spending $120 million for mitigation is assessed to reduce the probability of this risk from 60%
   to 10%. Because the schedule slippage is 233 days less than before, there is $95 million we
   do not need to reserve, paying for most of the $120 million cost of extra testing.
                                               © 2009 Hulett & Associates, LLC                                         32
Summary
   Integrated Cost and Schedule Risk
• Integrating cost and schedule risk analysis provides
   – Better estimates of cost risk than those ignoring schedule
   – Insight into the contribution of schedule risk to cost risk
• Analyzing cost and schedule risk in the same
  simulation fully integrates the two
   – Schedule slips will cause added cost for labor, rented
     barges and drill rigs, hence…
   – Mitigating schedule risk can reduce the need for
     contingency reserve of cost as well as of time


                        © 2009 Hulett & Associates, LLC            33
Summary
              Risk Driver Approach
• Focuses on the actual risks, not the impact of risks on
  activity durations or cost elements
• Allows prioritization of specific risks and hence facilitates
  the focus on risk mitigation
• Enables risk interviews on the Risk Register items that are
  strategic and fundamental. Interviews are shorter and more
  informative than 3-point estimates on activities
• Models correlation naturally as it occurs in projects
• Links qualitative and quantitative risk analysis explicitly
• Models risk mitigation to cost and schedule with impacts
  on each
                       © 2009 Hulett & Associates, LLC       34
Integrated Cost-Schedule Risk
  Analysis using Risk Drivers
     and Prioritizing Risks
           Presented at
       NASA PM Challenge
       February 9-10, 2010
    Moody Gardens, Galveston TX
              David T. Hulett, Ph.D.
               Hulett & Associates, LLC
                Los Angeles, CA USA
www.projectrisk.com / info@projectrisk.com / +1 (310) 476-7699

                    © 2009 Hulett & Associates, LLC              35

Contenu connexe

En vedette

Pmbok 4th edition chapter 11 - Project Risk Management
Pmbok 4th edition   chapter 11 - Project Risk ManagementPmbok 4th edition   chapter 11 - Project Risk Management
Pmbok 4th edition chapter 11 - Project Risk ManagementAhmad Maharma, PMP,RMP
 
Risk-management
 Risk-management Risk-management
Risk-managementUmesh Gupta
 
Information Technology Project Management - part 11
Information Technology Project Management - part 11Information Technology Project Management - part 11
Information Technology Project Management - part 11Rizwan Khurram
 
Risk management in software engineering
Risk management in software engineeringRisk management in software engineering
Risk management in software engineeringdeep sharma
 
RMMM-Risk Management,Mitigation and Monitoring.
RMMM-Risk Management,Mitigation and Monitoring.RMMM-Risk Management,Mitigation and Monitoring.
RMMM-Risk Management,Mitigation and Monitoring.Aparna Nayak
 
Software Risk Management
Software Risk ManagementSoftware Risk Management
Software Risk ManagementGunjan Patel
 

En vedette (6)

Pmbok 4th edition chapter 11 - Project Risk Management
Pmbok 4th edition   chapter 11 - Project Risk ManagementPmbok 4th edition   chapter 11 - Project Risk Management
Pmbok 4th edition chapter 11 - Project Risk Management
 
Risk-management
 Risk-management Risk-management
Risk-management
 
Information Technology Project Management - part 11
Information Technology Project Management - part 11Information Technology Project Management - part 11
Information Technology Project Management - part 11
 
Risk management in software engineering
Risk management in software engineeringRisk management in software engineering
Risk management in software engineering
 
RMMM-Risk Management,Mitigation and Monitoring.
RMMM-Risk Management,Mitigation and Monitoring.RMMM-Risk Management,Mitigation and Monitoring.
RMMM-Risk Management,Mitigation and Monitoring.
 
Software Risk Management
Software Risk ManagementSoftware Risk Management
Software Risk Management
 

Similaire à Integrated Cost-Schedule Risk Analysis using Risk Drivers and Prioritizing Risks

Patterson.dan
Patterson.danPatterson.dan
Patterson.danNASAPMC
 
David.hulett
David.hulettDavid.hulett
David.hulettNASAPMC
 
Results from Optimized Asset Reliability
Results from Optimized Asset ReliabilityResults from Optimized Asset Reliability
Results from Optimized Asset ReliabilityRicky Smith CMRP, CMRT
 
Understanding and Managing Risk in Complex Supply Chain Projects
Understanding and Managing Risk in Complex Supply Chain ProjectsUnderstanding and Managing Risk in Complex Supply Chain Projects
Understanding and Managing Risk in Complex Supply Chain ProjectsDerek Hill
 
Risk based cost estimating for water infrastructure projects
Risk based cost estimating for water infrastructure projectsRisk based cost estimating for water infrastructure projects
Risk based cost estimating for water infrastructure projectsAdvisian
 
Best Practices in Maintenance and Reliability
Best Practices in Maintenance and ReliabilityBest Practices in Maintenance and Reliability
Best Practices in Maintenance and ReliabilityRicky Smith CMRP, CMRT
 
Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...
Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...
Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...Project Controls Expo
 
Modeling, simulation & data mining: Answering Tough Executive Questions (Agil...
Modeling, simulation & data mining: Answering Tough Executive Questions (Agil...Modeling, simulation & data mining: Answering Tough Executive Questions (Agil...
Modeling, simulation & data mining: Answering Tough Executive Questions (Agil...Troy Magennis
 
Agile Metrics - Modeling, Simulation, and Data Mining
Agile Metrics - Modeling, Simulation, and Data MiningAgile Metrics - Modeling, Simulation, and Data Mining
Agile Metrics - Modeling, Simulation, and Data MiningRally Software
 
Modeling, simulation & data mining agile 2012 (magennis & maccherone)
Modeling, simulation & data mining   agile 2012 (magennis & maccherone)Modeling, simulation & data mining   agile 2012 (magennis & maccherone)
Modeling, simulation & data mining agile 2012 (magennis & maccherone)drewz lin
 
Measuring Risk Exposure through Risk Range Certainty
Measuring Risk Exposure through Risk Range CertaintyMeasuring Risk Exposure through Risk Range Certainty
Measuring Risk Exposure through Risk Range CertaintyAcumen
 
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk AnalysisSession B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk AnalysisProject Controls Expo
 

Similaire à Integrated Cost-Schedule Risk Analysis using Risk Drivers and Prioritizing Risks (13)

Patterson.dan
Patterson.danPatterson.dan
Patterson.dan
 
David.hulett
David.hulettDavid.hulett
David.hulett
 
Results from Optimized Asset Reliability
Results from Optimized Asset ReliabilityResults from Optimized Asset Reliability
Results from Optimized Asset Reliability
 
Understanding and Managing Risk in Complex Supply Chain Projects
Understanding and Managing Risk in Complex Supply Chain ProjectsUnderstanding and Managing Risk in Complex Supply Chain Projects
Understanding and Managing Risk in Complex Supply Chain Projects
 
Risk based cost estimating for water infrastructure projects
Risk based cost estimating for water infrastructure projectsRisk based cost estimating for water infrastructure projects
Risk based cost estimating for water infrastructure projects
 
Best Practices in Maintenance and Reliability
Best Practices in Maintenance and ReliabilityBest Practices in Maintenance and Reliability
Best Practices in Maintenance and Reliability
 
Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...
Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...
Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...
 
Modeling, simulation & data mining: Answering Tough Executive Questions (Agil...
Modeling, simulation & data mining: Answering Tough Executive Questions (Agil...Modeling, simulation & data mining: Answering Tough Executive Questions (Agil...
Modeling, simulation & data mining: Answering Tough Executive Questions (Agil...
 
Agile Metrics - Modeling, Simulation, and Data Mining
Agile Metrics - Modeling, Simulation, and Data MiningAgile Metrics - Modeling, Simulation, and Data Mining
Agile Metrics - Modeling, Simulation, and Data Mining
 
Modeling, simulation & data mining agile 2012 (magennis & maccherone)
Modeling, simulation & data mining   agile 2012 (magennis & maccherone)Modeling, simulation & data mining   agile 2012 (magennis & maccherone)
Modeling, simulation & data mining agile 2012 (magennis & maccherone)
 
H1 2009 IFRS results
H1 2009 IFRS resultsH1 2009 IFRS results
H1 2009 IFRS results
 
Measuring Risk Exposure through Risk Range Certainty
Measuring Risk Exposure through Risk Range CertaintyMeasuring Risk Exposure through Risk Range Certainty
Measuring Risk Exposure through Risk Range Certainty
 
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk AnalysisSession B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
 

Plus de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 

Plus de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Dernier

High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsHigh Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Call Girls Service Nagpur Maya Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Maya Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Maya Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Maya Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
20240417-Calibre-April-2024-Investor-Presentation.pdf
20240417-Calibre-April-2024-Investor-Presentation.pdf20240417-Calibre-April-2024-Investor-Presentation.pdf
20240417-Calibre-April-2024-Investor-Presentation.pdfAdnet Communications
 
(TANVI) Call Girls Nanded City ( 7001035870 ) HI-Fi Pune Escorts Service
(TANVI) Call Girls Nanded City ( 7001035870 ) HI-Fi Pune Escorts Service(TANVI) Call Girls Nanded City ( 7001035870 ) HI-Fi Pune Escorts Service
(TANVI) Call Girls Nanded City ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Log your LOA pain with Pension Lab's brilliant campaign
Log your LOA pain with Pension Lab's brilliant campaignLog your LOA pain with Pension Lab's brilliant campaign
Log your LOA pain with Pension Lab's brilliant campaignHenry Tapper
 
Andheri Call Girls In 9825968104 Mumbai Hot Models
Andheri Call Girls In 9825968104 Mumbai Hot ModelsAndheri Call Girls In 9825968104 Mumbai Hot Models
Andheri Call Girls In 9825968104 Mumbai Hot Modelshematsharma006
 
Lundin Gold April 2024 Corporate Presentation v4.pdf
Lundin Gold April 2024 Corporate Presentation v4.pdfLundin Gold April 2024 Corporate Presentation v4.pdf
Lundin Gold April 2024 Corporate Presentation v4.pdfAdnet Communications
 
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...shivangimorya083
 
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130  Available With RoomVIP Kolkata Call Girl Serampore 👉 8250192130  Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Roomdivyansh0kumar0
 
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptxOAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptxhiddenlevers
 
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...Henry Tapper
 
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...makika9823
 
Stock Market Brief Deck for 4/24/24 .pdf
Stock Market Brief Deck for 4/24/24 .pdfStock Market Brief Deck for 4/24/24 .pdf
Stock Market Brief Deck for 4/24/24 .pdfMichael Silva
 
Quarter 4- Module 3 Principles of Marketing
Quarter 4- Module 3 Principles of MarketingQuarter 4- Module 3 Principles of Marketing
Quarter 4- Module 3 Principles of MarketingMaristelaRamos12
 
VIP Kolkata Call Girl Jodhpur Park 👉 8250192130 Available With Room
VIP Kolkata Call Girl Jodhpur Park 👉 8250192130  Available With RoomVIP Kolkata Call Girl Jodhpur Park 👉 8250192130  Available With Room
VIP Kolkata Call Girl Jodhpur Park 👉 8250192130 Available With Roomdivyansh0kumar0
 
Shrambal_Distributors_Newsletter_Apr-2024 (1).pdf
Shrambal_Distributors_Newsletter_Apr-2024 (1).pdfShrambal_Distributors_Newsletter_Apr-2024 (1).pdf
Shrambal_Distributors_Newsletter_Apr-2024 (1).pdfvikashdidwania1
 
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...Suhani Kapoor
 
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service NashikHigh Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Instant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School DesignsInstant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School Designsegoetzinger
 
The Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdfThe Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdfGale Pooley
 

Dernier (20)

High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsHigh Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nagpur Maya Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Maya Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Maya Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Maya Call 7001035870 Meet With Nagpur Escorts
 
20240417-Calibre-April-2024-Investor-Presentation.pdf
20240417-Calibre-April-2024-Investor-Presentation.pdf20240417-Calibre-April-2024-Investor-Presentation.pdf
20240417-Calibre-April-2024-Investor-Presentation.pdf
 
(TANVI) Call Girls Nanded City ( 7001035870 ) HI-Fi Pune Escorts Service
(TANVI) Call Girls Nanded City ( 7001035870 ) HI-Fi Pune Escorts Service(TANVI) Call Girls Nanded City ( 7001035870 ) HI-Fi Pune Escorts Service
(TANVI) Call Girls Nanded City ( 7001035870 ) HI-Fi Pune Escorts Service
 
Log your LOA pain with Pension Lab's brilliant campaign
Log your LOA pain with Pension Lab's brilliant campaignLog your LOA pain with Pension Lab's brilliant campaign
Log your LOA pain with Pension Lab's brilliant campaign
 
Andheri Call Girls In 9825968104 Mumbai Hot Models
Andheri Call Girls In 9825968104 Mumbai Hot ModelsAndheri Call Girls In 9825968104 Mumbai Hot Models
Andheri Call Girls In 9825968104 Mumbai Hot Models
 
Lundin Gold April 2024 Corporate Presentation v4.pdf
Lundin Gold April 2024 Corporate Presentation v4.pdfLundin Gold April 2024 Corporate Presentation v4.pdf
Lundin Gold April 2024 Corporate Presentation v4.pdf
 
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
 
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130  Available With RoomVIP Kolkata Call Girl Serampore 👉 8250192130  Available With Room
VIP Kolkata Call Girl Serampore 👉 8250192130 Available With Room
 
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptxOAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
 
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
 
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
 
Stock Market Brief Deck for 4/24/24 .pdf
Stock Market Brief Deck for 4/24/24 .pdfStock Market Brief Deck for 4/24/24 .pdf
Stock Market Brief Deck for 4/24/24 .pdf
 
Quarter 4- Module 3 Principles of Marketing
Quarter 4- Module 3 Principles of MarketingQuarter 4- Module 3 Principles of Marketing
Quarter 4- Module 3 Principles of Marketing
 
VIP Kolkata Call Girl Jodhpur Park 👉 8250192130 Available With Room
VIP Kolkata Call Girl Jodhpur Park 👉 8250192130  Available With RoomVIP Kolkata Call Girl Jodhpur Park 👉 8250192130  Available With Room
VIP Kolkata Call Girl Jodhpur Park 👉 8250192130 Available With Room
 
Shrambal_Distributors_Newsletter_Apr-2024 (1).pdf
Shrambal_Distributors_Newsletter_Apr-2024 (1).pdfShrambal_Distributors_Newsletter_Apr-2024 (1).pdf
Shrambal_Distributors_Newsletter_Apr-2024 (1).pdf
 
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
 
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service NashikHigh Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
 
Instant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School DesignsInstant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School Designs
 
The Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdfThe Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdf
 

Integrated Cost-Schedule Risk Analysis using Risk Drivers and Prioritizing Risks

  • 1. Integrated Cost-Schedule Risk Analysis using Risk Drivers and Prioritizing Risks Presented at NASA PM Challenge February 9-10, 2010 Moody Gardens, Galveston TX David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles, CA USA www.projectrisk.com / info@projectrisk.com / +1 (310) 476-7699 © 2009 Hulett & Associates, LLC 1 Used with permission
  • 2. Agenda • Integrating cost and schedule risk analysis • The Risk Driver method • The schedule for an offshore gas production platform project • Risk Register risks and their parameters • Schedule Risk analysis results and priority risks • Cost Risk analysis results and priority risks • Risk Mitigation scenarios © 2009 Hulett & Associates, LLC 2
  • 3. Why Integrate Cost and Schedule Risk Analysis? (1) • Many cost risk analyses assume that the schedule is fixed at the baseline and do not account for the impact of schedule risk • Other cost risk analyses take ad hoc account of schedule risk but not through the schedule itself or from a schedule risk analysis result • This analysis shows that project cost and time are related and that we can model that relationship directly © 2009 Hulett & Associates, LLC 3
  • 4. Why Integrate Cost and Schedule Risk Analysis? (2) • Driving cost risk by schedule risk where appropriate: – Results in a better estimate of cost risk – Helps to understand where the risk comes from – Points to mitigation of risks that can affect both cost and schedule – Is based in the project schedule so we can see the time-profile of cash flow, risk adjusted © 2009 Hulett & Associates, LLC 4
  • 5. Results from Integrated Cost and Schedule Risk Analysis • The likelihood of schedule and cost success • The schedule and cost contingency reserve needed for desired level of certainty • The list of risks to schedule and to cost in ranked order of priority – Assists risk mitigation • Probabilistic cash flow © 2009 Hulett & Associates, LLC 5
  • 6. Integrating Cost and Schedule Risk Analysis • Some costs (labor, rigs, barges) are determined by changes in duration – Cost risk is driven by schedule risk since these resources cost more if they work longer – Cost risk may also be affected by uncertain burn rate/day • Other costs (equipment, material) are uncertain, but not because of activity duration © 2009 Hulett & Associates, LLC 6
  • 7. Traditional 3-point Estimates of Duration • Traditional schedule risk analysis starts with the activity that is impacted by risks – Estimates the 3-points for optimistic, most likely and pessimistic duration – Creates a probability distribution for activity duration – Performs Monte Carlo simulation • Can we tell the high priority risks? This question is typically answered by: – Sensitivity – activities that are correlated with total time risk – Criticality – activities that are most likely on the critical path © 2009 Hulett & Associates, LLC 7
  • 8. Some Problems with Traditional Approach • Makes poor use of the Risk Register that is usually available • Can tell which activities or schedule paths are crucial, but not which risks are driving – Traditional approaches cannot prioritize risks, only activities or paths © 2009 Hulett & Associates, LLC 8
  • 9. We Propose the Risk Driver Approach: Start with the Risks Themselves • Drive the schedule risk directly by the risks already analyzed in the Risk Register • For each risk, specify: – Probability it will occur – proportion of iterations it affects activity durations – Impact on time if it does – in terms of multiplicative factors – Activities it will affect • This approach focuses on the risks, not on the risks’ impact on activities © 2009 Hulett & Associates, LLC 9
  • 10. Flow Chart of Risk Management using the Risk Driver Approach Risk Identification – list of potential risks to the project Qualitative Risk Analysis – prioritized list of risks to time and cost Quantitative Risk Analysis Risk Driver Approach Mitigating schedule and cost risks Monitoring and controlling risk © 2009 Hulett & Associates, LLC 10
  • 11. Three Types of Risk • Uncertainties, such as the level of labor productivity. • Ambiguities, such as the accuracy of cost estimates and schedules – These always occur but may have a range of impacts • Risk events that may or may not occur – These have both probability of occurring and impact ranges © 2009 Hulett & Associates, LLC 11
  • 12. Examples of Three Risk Types • Schedule immaturity is an ambiguity. It has 100% probability of occurring and its impact range is both good and bad • Construction labor productivity is an uncertainty that, compared to the assumption, could be lower or higher • The possibility of quality, key personnel unavailability is a risk event. It may or may not occur, and in this case its impact is never to the good © 2009 Hulett & Associates, LLC 12
  • 13. Uncertainty and Ambiguity Risks Occur 100% of the time 0010 - Construction : Duration 100% 120 95% 116 Schedule inaccuracy 240 90% 114 operates in 100% of the time 220 85% 113 80% 111 (all iterations). On a 200 75% 110 construction activity of 100 180 70% 109 days duration the results are 65% 109 160 60% 108 triangular Cumulative Frequency 140 55% 107 The construction labor Hits productivity risk would look 50% 106 120 45% 106 100 40% 105 similar to this figure 35% 104 80 30% 104 25% 103 60 20% 102 40 15% 101 10% 100 20 5% 99 0 0% 95 95 100 105 110 115 120 Distribution (start of interval) © 2009 Hulett & Associates, LLC 13
  • 14. Risk Events are Described by their Probability and Impact • If probability is < 100%, the risk will occur in that percentage of iterations, chosen at random • On an iteration if the risk occurs, a factor chosen at random from its impact range (following a triangular distribution) will multiply the duration of the activities to which it is assigned • If the risk does not occur the multiplicative factor is 100% with no effect on duration © 2009 Hulett & Associates, LLC 14
  • 15. Risk Events occur with a Probability < 100% 0010 - Construction : Duration 100% 110 95% 108 Here a risk event, the possible 900 90% 107 unavailability of quality key 85% 107 800 80% 106 staff, occurs 70% of the time. 75% 106 Hence, in 30% (900) of the 700 70% 105 65% 105 3,000 iterations the original 600 60% 105 duration of construction, 100 Cumulative Frequency 55% 104 days, is correct. In 70% Hits 500 50% 104 45% 103 (2,100) of the iterations, the 400 40% 103 duration is longer than 100 300 35% 102 30% 101 days as a triangle 25% 100 200 20% 100 15% 100 100 10% 100 5% 100 0 0% 100 100 102 104 106 108 110 Distribution (start of interval) © 2009 Hulett & Associates, LLC 15
  • 16. Risk Driver Strategy • Risks are usually higher-level strategic risks rather than tactical or technical risks • Data about risks is derived from in-depth interviews • A risk is usually assigned to several activities • An activity may have several risks assigned © 2009 Hulett & Associates, LLC 16
  • 17. A Construction Activity with Three Risks Assigned 0010 - Construction : Duration 160 100% 143 95% 127 The interaction of the three 150 90% 124 risks produces the expected 140 85% 122 histogram. 130 80% 120 75% 118 In traditional 3-point risk 120 70% 117 estimating, the analyst and 110 65% 115 interviewees must 100 60% 114 approximate the result of Cumulative Frequency 90 55% 113 three risks on duration. The Hits 50% 112 80 70 45% 111 Risk Driver analysis computes 60 40% 110 35% 109 the distribution. 50 30% 108 25% 106 40 20% 105 30 15% 103 20 10% 101 10 5% 99 0 0% 90 90 100 110 120 130 140 Distribution (start of interval) © 2009 Hulett & Associates, LLC 17
  • 18. Risk Drivers Avoid the Need to Estimate the Correlation Coefficient Activities A and B Correlation is Risk #1 Calculated to be 100% P = 50%, Factors .95, 1.05, 1.15 Activity A Activity B In the traditional approach to risk analysis, the correlation coefficient has to be estimated. Risk Drivers model how correlation occurs and the coefficient is a natural result of the model © 2009 Hulett & Associates, LLC 18
  • 19. Risk Factors Model How Correlation Occurs (2) Risk #2 Risk #1 Risk #3 P = 25%, Factors P = 50%, Factors P = 45%, Factors .8, .95, 1.05 .95, 1.05, 1.15 1.0, 1.1, 1.2 Activities A and B Correlation is Calculated Activity A Activity B to be 48% Risk Drivers model correlation as it is caused in the project based on the common (Risk # 1) and confounding (Risks # 2 and #3) risks affecting pairs of activities The correlation coefficient is the result, not the assumption © 2009 Hulett & Associates, LLC 19
  • 20. Case Study: Hypothetical Voyage to Europa to Probe for Evidence of Microbial Life
  • 21. Risk Analysis on Space Vehicle Project Risk Factors are from Risk Register Schedule Impact Factors Cost Impact Factors Most Most Risk # Risk Probability Min Max Min Max Likely Likely 1 Requirements have not been decided 80% 95% 110% 120% 95% 105% 110% 2 Several alternative designs considered 100% 80% 110% 130% 100% 110% 120% 3 New instruments not yet proven 60% 95% 110% 120% 95% 100% 110% 4 Fabricaton requires new materials 50% 100% 105% 115% Lost know-how since last new-concept 5 50% 95% 105% 120% 100% 110% 120% probe 6 Funding from Congress is problematic 70% 90% 105% 115% 7 Schedule may be aggressive 100% 95% 110% 120% Cost estimate is based on immature 8 100% 100% 110% 120% data
  • 22. Mapping Risks to Activities Assignment of Risks to Activities Integrate Launch Integrate Risk # Risk Decision Probe Sciences PMT Probe/Science Vehicle Vehicle/Payload 1 Requirements have not been decided X 2 Several alternative designs considered X 3 New instruments not yet proven X X 4 Fabricaton requires new materials X X Lost know-how since last new-concept 5 X X X probe 6 Funding from Congress is problematic X X X X 7 Schedule may be aggressive X X X X X 8 Cost estimate is based on immature data X X X X X X X
  • 23. Schedule and Cost Targets are Unlikely to be Met Summary Risk Results Prob Base P-10 P 50 P-80 P-90 Base Schedule Date 8-Sep-22 < 1% 14-Jul-23 27-Aug-24 30-Jul-25 13-Jan-26 Overrun of Schedule days 309 719 1,056 1,223 Overrun of Schedule % 7% 16% 23% 26% Cost 1,941 < 1% 2,280 2,577 2,841 2,992 Overrun of Cost $ 339 636 900 1,051 Overrun of Cost % 17% 33% 46% 54% A launch of September 2022 may be in July 2025 without risk mitigation. In light of these results aggressive risk mitigation should be done © 2009 Hulett & Associates, LLC 23
  • 24. Examine the Probability of Meeting a 2022 Launch Date Eurpoa Probe.mpp Entire Plan : Finish Date 100% 20OCT28 95% 19JUN26 90% 13JAN26 300 85% 14OCT25 Target Launch Date: 80% 30JUL25 8 SEP 2022 75% 15MAY25 P-80 30 JUL 2025 250 70% 14MAR25 65% 17JAN25 60% 25NOV24 Cumulative Frequency 200 55% 09OCT24 Hits 50% 27AUG24 45% 15JUL24 150 40% 24MAY24 35% 12APR24 30% 27FEB24 100 25% 10JAN24 20% 22NOV23 50 15% 29SEP23 10% 14JUL23 5% 27MAR23 0 0% 08SEP21 22OCT23 18JUL26 Distribution (start of interval)
  • 25. Risk Factor Tornado from All-In Simulation Driving Schedule Risk Factors 3 - New instruments not yet proven 6 - Funding from Congress is problematic 7 - Schedule may be aggressive 5 - Lost know-how since last new-concept probe The main RISK, however, is new 4 - Fabricaton requires new materials instruments not yet 1 - Requirements have not been decided proven, followed by funding. These are the 2 - Several alternative designs considered main risks to mitigate, if 8 - Cost estimate is based on immature data This risk is possible exclusively on cost 0.00 0.10 and does not 0.20 0.30 0.40 0.50 Correlation impact schedule
  • 26. Contribution of Each Risk to the Time Contingency (1) Explain the Contingency to the P-80 with Risks sorted by Priority P-80 Date Contribution of Risk % of All Risks In 30-Jul-25 Days Saved Contingency Specific Risks Taken Out in Order Schedule may be aggressive 27-Aug-24 337 32% New instruments not yet proven 29-Jan-24 211 20% Funding from Congress is problematic 15-Sep-23 136 13% Lost know-how since last new-concept probe 24-Apr-23 144 14% Fabricaton requires new materials 19-Jan-23 95 9% Requirements have not been decided 23-Nov-22 57 5% Several alternative designs considered 8-Sep-22 76 7% Total Contingency 1,056 100%
  • 27. Contribution of Each Risk to the Time Contingency (2) Distribution Analyzer Eurpoa Probe.mpp - Entire Plan - Finish Da Eurpoa Probe.mpp - Entire Plan - Finish Da Eurpoa Probe.mpp - Entire Plan - Finish Da Eurpoa Probe.mpp - Entire Plan - Finish Da Eurpoa Probe.mpp - Entire Plan - Finish Da Eurpoa Probe.mpp - Entire Plan - Finish Da Eurpoa Probe.mpp - Entire Plan - Finish Da Eurpoa Probe.mpp - Entire Plan - Finish Da 100% 90% Variation:67 Variation:95 Variation:144 Variation:136 Variation:65 Variation:212 Variation:337 80% 70% Cumulative Probability 60% 50% 40% 30% 20% 10% 0% 08FEB22 27AUG22 15MAR23 01OCT23 18APR24 04NOV24 23MAY25 09DEC25 27JUN26 13JAN27 01AUG27 17FEB28 04SEP28 © 2009 Hulett & Associates, LLC 27
  • 28. With this Target Date, the Cost of Resulting Overruns Could be Substantial Eurpoa Probe.mpp Entire Plan : Cost 100% $3,739,983.72 95% $3,114,983.37 450 Base cost = $1.9 billion 90% $2,991,768.98 85% $2,898,334.50 P-80 cost = $2.8 billion 400 80% $2,841,866.21 75% $2,776,666.32 350 70% $2,728,127.19 65% $2,689,446.07 300 60% $2,646,803.87 Cumulative Frequency 55% $2,611,179.97 Hits 250 50% $2,577,090.49 45% $2,544,706.54 200 40% $2,506,499.31 35% $2,473,528.88 150 30% $2,439,553.06 25% $2,405,227.50 100 20% $2,369,904.75 15% $2,329,665.92 50 10% $2,280,465.17 5% $2,208,188.73 0 0% $1,882,995.94 $2,000,000.00 $2,500,000.00 $3,000,000.00 $3,500,000.00 Distribution (start of interval)
  • 29. The Year-to-Year Budget Could be Compromised Resource Flow for Cost Filter: Entire Plan Mean P20 P80 3,500,000 3,000,000 2,500,000 Cumulative Deterministic Cost: $1,940,800.00 2,000,000 Deterministic Finish: 08SEP22 1,500,000 1,000,000 500,000 0 12FEB10 27JUN11 08NOV12 23MAR14 05AUG15 17DEC16 01MAY18 13SEP19 25JAN21 09JUN22 22OCT23 05MAR25 18JUL26 30NOV27 Time Scatter plot slope indicates that project delays will add to cost
  • 30. Joint Confidence Level 70% Eurpoa Probe.mpp Deterministic Point Inside both limits Outside both limits 78% 8% 14% $3,600,000.00 $3,400,000.00 $3,200,000.00 $3,000,000.00 Entire Plan: Cost $2,800,000.00 78% $2,813,335.74 $2,600,000.00 $2,400,000.00 $2,200,000.00 $2,000,000.00 70% 25JUN25 8% 09JUN22 22OCT23 05MAR25 18JUL26 30NOV27 Entire Plan: Finish © 2009 Hulett & Associates, LLC 30
  • 31. Contribution of Each Risk to the Cost Contingency Effect of Risks on Cost Contingency to the P-80 All risks In 2841 Contribution to % of Risks contingency Contingency Cost estimate is based on immature data 271 29% Lost know-how since last new-concept probe 240 26% Schedule may be aggressive 190 21% New instruments not yet proven 95 10% Funding from Congress is problematic 74 8% Fabricaton requires new materials 38 4% Several alternative designs considered 6 1% Requirements have not been decided 5 1%
  • 32. Analysis of a Risk Mitigation Scenario Risk Mitigation Scenario Schedule Risk Factors Cost Risk Factors Project Most Most Launch % Min Max Min Max Cost ($ Likely Likely Date million) Risk to be Mitigated Before Mitigation New Instruments Not Yet Proven 60% 95% 110% 120% 95% 100% 110% 30-Jul-25 2,841 Proposed Mitigation: Provide more testing of the instruments before integration at cost of $120 million After Mitigation May have trouble interfacing 10% 95% 100% 105% 95% 100% 105% 9-Dec-24 2,746 Phases Improvement 233 95 Cost of proposed Mitigation 120 Net Improvement from 233 -25 Mitigation Spending $120 million for mitigation is assessed to reduce the probability of this risk from 60% to 10%. Because the schedule slippage is 233 days less than before, there is $95 million we do not need to reserve, paying for most of the $120 million cost of extra testing. © 2009 Hulett & Associates, LLC 32
  • 33. Summary Integrated Cost and Schedule Risk • Integrating cost and schedule risk analysis provides – Better estimates of cost risk than those ignoring schedule – Insight into the contribution of schedule risk to cost risk • Analyzing cost and schedule risk in the same simulation fully integrates the two – Schedule slips will cause added cost for labor, rented barges and drill rigs, hence… – Mitigating schedule risk can reduce the need for contingency reserve of cost as well as of time © 2009 Hulett & Associates, LLC 33
  • 34. Summary Risk Driver Approach • Focuses on the actual risks, not the impact of risks on activity durations or cost elements • Allows prioritization of specific risks and hence facilitates the focus on risk mitigation • Enables risk interviews on the Risk Register items that are strategic and fundamental. Interviews are shorter and more informative than 3-point estimates on activities • Models correlation naturally as it occurs in projects • Links qualitative and quantitative risk analysis explicitly • Models risk mitigation to cost and schedule with impacts on each © 2009 Hulett & Associates, LLC 34
  • 35. Integrated Cost-Schedule Risk Analysis using Risk Drivers and Prioritizing Risks Presented at NASA PM Challenge February 9-10, 2010 Moody Gardens, Galveston TX David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles, CA USA www.projectrisk.com / info@projectrisk.com / +1 (310) 476-7699 © 2009 Hulett & Associates, LLC 35