EVMS
The Principles, Best Practices and Benefits


           Gary C. Humphreys
        Humphreys & Associates, Inc.


           NASA PM Challenge 2010

                                        Used with Permission
PART 1




Overview, Earned Value Management




            NASA PM Challenge 2010   1
What is EVM?

• Earned Value Management (EVM) is an integrated project
  management process for assessing, understanding and quantifying
  what a contractor or in-house project is achieving with
  program/project dollars
   –   Integrates technical, cost, and schedule with risk management
   –   Allows objective assessment and quantification of current project
       performance
   –   Helps predict future performance based on trends

                                                        “Management 101”       “EVM 101”

                                                              Plan              Organize

                                                            Organize          Plan & Budget
                 EVM is simply good project
                       management!                            Staff         Account for Costs

                                                             Direct             Analyze

                                                             Control       Incorporate Changes



                               NASA PM Challenge 2010                                            2
So why use EVM?



EVM enhances the chances of program/project success

   •   To Succeed, you must Manage
   •   To Manage, you must Measure
   •   To Measure, you must Define
   •   To Define, you must Understand




                          NASA PM Challenge 2010      3
NASA EVM Policy & Requirements

•   NASA EVM requirements are found in NPR 7120.5, NASA Program and Project
    Management Processes and Requirements and NPR 7120.7, NASA Information
    Technology and Institutional Infrastructure Program and Project Management
    Requirements. Policy is contained in NASA FAR Supplement (NFS) 1834.201.
    NASA EVM requirements are predicated on the principles and guidelines in
    ANSI/EIA-748, Industry Guidelines for Earned Value Management Systems.


•   NPR 7120.5 requires the project EVM approach to be in place by Key Decision Point
    (KDP) C (the conclusion of Preliminary Design Review (PDR)) and implemented in
    Phase C (Final Design and Fabrication) through KDP E [Flight Readiness Review
    (FRR) or Launch Readiness Review (LRR)].


•   Additionally, project performance reporting must begin within 60 days after the start
    of Phase C. To meet this timeline, it is highly recommended that projects begin
    implementation planning during Phase B (Preliminary Design and Technology
    Completion).




                                    NASA PM Challenge 2010                                  4
NPR 7120.5 Guidance

•   NPR 7120.5 also requires that NASA programs and projects use EVM on projects
    and contracts that meet the following criteria:
    1. For projects with a total anticipated final value of $20 million or more, EVM principles should
       be applied, as defined by ANSI/EIA-748, Earned Value Management Systems.

      a. If the project's primary NASA Center has a validated EVMS, the project uses that system rather than
         the EVM principles application approach.

    2. For development contracts and subcontracts valued at or between $20M and $50M, the
       contractor is expected to have an EVMS that complies with the 32 guidelines in the
       ANSI/EIA-748 Standard.

    3. For development contracts and subcontracts valued at $50M or more, the contractor is
       required to have an EVMS that has been formally validated by the Government.

    4. EVM is not required on contracts for non-developmental engineering support services,
       steady state operations, basic and applied research, and routine services such as janitorial
       services or grounds maintenance services. In these cases, application of EVM is at the
       discretion of the Program/Project Manager (PM).

•   NASA projects that do not have a validated EVMS will use the seven management
    principles that are contained in ANSI/EIA-748 standard.


                                          NASA PM Challenge 2010                                               5
Seven EVM Principles (ANSI/EIA-748-B-2007)

1. Plan all work scope for the project to completion.

2. Break down the project work scope into finite pieces that can be assigned to a
   responsible person or organization for control of technical schedule and cost
   objectives.

3. Integrate project work scope, schedule, and cost objectives into a performance
   measurement baseline plan against which accomplishments may be measured.
   Control changes to the baseline.

4. Use actual costs incurred and recorded in accomplishing the work performed.

5. Objectively assess accomplishments at the work performance level.

6. Analyze significant variances from the plan, forecast impacts, and prepare an
   estimate at completion based on performance to date and all remaining work that
   must be performed.

7. Incorporate Earned Value Management in the project decision-making and review
   processes.


                                 NASA PM Challenge 2010                              6
32 EVM Guidelines (ANSI/EIA-748-B-2007)
Guideline Categories
•   Organization (5 guidelines)
     –   Define contractual effort and assign responsibilities for the work. Integrate planning,
         scheduling, work authorization, and accounting systems.

•   Planning, Scheduling and Budgeting (10 guidelines)
     –   Plan, schedule, budget and authorize the work. Establish and maintain a time-phased
         budget baseline.

•   Accounting Considerations (6 guidelines)
     –   Accumulate costs of work and material.
     –   Report on progress/accomplishments to date.

•   Analysis & Management Reports (6 guidelines)
     –   Compare planned, earned and actual costs, analyze variances. Develop revised
         estimates at complete. Identify managerial actions.

•   Revisions and Data Maintenance (5 guidelines)
     –   Execute timely incorporation of contractual changes. Maintain traceability from original
         budgets.



                                      NASA PM Challenge 2010                                        7
Earned Value Management Process




                             Risk Monitoring         Informed Management
                                                           Decisions
Scheduling & Resource
  Allocation Systems



                                 Progress
                        Earned Value Mgmt System
                                (Progress)



    Accounting
     System


                          Technical Performance
                              Measurement
                            NASA PM Challenge 2010                         8
Features of a “Good” EVM system

•   Thorough up-front planning based on a detailed product-oriented Work
    Breakdown Structure (WBS), incorporating Risk Management
    –   Timely Performance Measurement Baseline (PMB) establishment and control

    –   Information broken down by product, as well as by organization or function

•   Objective measurement of technical accomplishment against the plan at
    levels where the work is being performed
•   Reporting consistency and discipline – a structured process and
    methodology
    −   Summarized data reporting to higher management (performance metrics) for use
        in effective decision making
    −   Provides for analysis of significant variances and their impact on the project
    −   Facilitates proper management actions to mitigate risk and manage technical,
        cost and schedule performance



                                     NASA PM Challenge 2010                              9
PART 2




       EVMS Terms and the
Performance Measurement Baseline




            NASA PM Challenge 2010
                                     10
Basic EVM Terms

• Budgeted Cost for Work Scheduled (BCWS)
   –   The sum of the time-phased budgets established for all effort (including in-
       process work) scheduled to be accomplished within a given time period

• Budgeted Cost for Work Performed (BCWP)
   –   The sum of the time-phased budgets for work actually completed during a
       specified time period
   –   BCWP is the budgeted value for the work actually accomplished
   –   Earned value can only be determined after the performance (or scheduled
       performance) of work

• Actual Cost of Work Performed (ACWP)
   –   The costs (taken from the Accounting System) actually incurred (or in some
       cases estimated) and recorded, in accomplishing the work performed within a
       given time period




                                  NASA PM Challenge 2010
                                                                                      11
Basic EVM Terms (continued)



• Budget At Completion (BAC)
   –   The budgetary goal (excluding MR) for accomplishment of all authorized work

• Estimate At Completion (EAC)
   –   Actual direct and indirect costs allocable to the contract, plus the estimate of all
       costs for authorized work remaining
   –   Estimated cost to complete the entire project scope of work
   –   Supported with a rationale
   –   Best case, worst case, most likely




                                    NASA PM Challenge 2010                                    12
Basic EVM Terms (continued)


• Total Allocated Budget (TAB)
   –   Total Allocated Budget is the sum of all budgets allocated by the contractor
       against which contract performance is to be measured and reported

• Contract Budget Base (CBB)
   –   Contract Budget Base is the negotiated contract cost plus the estimated cost of
       authorized unpriced work

• Authorized Unpriced Work (AUW)
   –   Contract work authorized by the contracting officer, not yet negotiated, aka not
       yet definitized work




                                  NASA PM Challenge 2010                                  13
Contract/In-house Project –
                                         PMB Relationship

                                                             Contract Price (Project Price)



Total of all authorized
work, both negotiated                     Total Allocated Budget (TAB)                          Contract Fee/Profit
and un-negotiated
                                                Contract Budget Base
                          Authorized Unpriced                              Over Target
                                                  (CBB) or Project
                             Work (AUW)                                   Baseline (OTB)
                                                 Budget Base (PBB)



                                                                                                               MR – Held for known
   The total is also
                           Performance Measurement                                                             unknowns but in-scope
   called Budget at                                                             Management Reserve (MR)        future effort. Not used to
   Completion (BAC)             Baseline (PMB)
                                                                                                               cover cost overruns.


                                                                                                UB – Temporary holding place for
                                                                                                allocation to control accounts not to
                                Distributed Budget                 Undistributed Budget (UB)    exceed two accounting periods
                                                                                                following negotiations.



                                                                   Summary Level Planning
                              Control Account (CA)
                                                                      Package (SLPP)



                               Work Package (WP)                       Planning Package (PP)




                                                       NASA PM Challenge 2010                                                               14
The Performance Measurement Baseline (PMB) –
               Is all the work planned?



What is the PMB?

• A time-phased budget plan against which contract performance is
    measured
•   Developed by the contractor and jointly reviewed with the
    customer within six months of contract award
•   Based on the anticipated flow of work and outcomes
•   Incorporates dynamic, authorized project changes




                            NASA PM Challenge 2010                  15
PMB Development
Establishing the PMB is a 3-step process:
1. DEFINE THE WORK
                          • Statement of Work (SOW)
                                                                       CONTRACT BUDGET BASE
                          • Work Breakdown Structure (WBS)
                          • Organizational Breakdown
                            Structure (OBS)                                                   MR
                          • Responsibility Assignment Matrix
                            (RAM)
2. SCHEDULE THE WORK



                          Integrated Master Schedule (IMS)
                          • Master Schedule
                          • Intermediate Schedule
                          • Detailed Schedules                 $

3. ALLOCATE BUDGETS
          100
     40
               60         • Work Authorization System
                          • Control Account Plan (CAP)
    15                    • Work Packages (WP) &
          25                Planning Packages (PP)
                30
                     30                                                       TIME
          PMB – Time-phased, budgeted plan where contract performance can be measured.

                                              NASA PM Challenge 2010                               16
Work Breakdown Structure (WBS)

•   A product-oriented hierarchical division of the hardware, software,
    services, and data required to produce the project’s end product(s)
•   Should not be functional or organizational oriented
•   Should reflect the total project scope of work
•   Structured according to the way the work will be performed
•   Reflects the way in which project costs, schedule, technical and risk data
    are to be accumulated, summarized, and reported
•   WBS is the most important data item in defining and controlling the
    contracted technical scope
•   Summary level WBS must be the sum of all lower level WBS hierarchical
    in nature
•   Supports historical cost collection necessary for future costing activities of
    similar scoped products



                        “It’s the WHAT that is Going to
                                   Be Done”

                                NASA PM Challenge 2010                               17
Properly Structured WBS
                                                      Standard
                                      Product
                                                      Level 2’s
                                      Oriented




                                                 Clear
                                                 WBS
                                                 Titles




Center Breakout
at Appropriate
Level

                  NASA PM Challenge 2010                          18
Responsibility Assignment Matrix (RAM)
The Responsibility Assignment Matrix (RAM) Integrates WBS with OBS. The
intersecting points are the Control Accounts.
                                                                            Contract Work Breakdown Structure (WBS)

                                                                                                        1.0



                                                                                       1.1              1.2              1.3                        WBS Reporting Level
                                                                                                                                                    CWBS Extension
  Organization Breakdown Structure (OBS)




                                                 Functional Org




                                                                            1.1.1             1.1.2             1.1.3             1.1.4


                                                                                                                                                            Control Account
                                                                  1.1.2.1           1.1.2.2           1.1.2.3           1.1.2.4           1.1.2.5           • Task Description
                                                                                                                                                            • Perform. Measure
                                                                                                                                                            • Work Authorization
                                                                                                                                                            • Cost Accumulation
                                                      SW




                                                                                                                                                            • Work Package, Schedules,
                                                                                                                                                              & Budget
                                                                                              RAM
                                                        Mech
                                           ENG




                                                                                                                                                          CA
                                                       Elec




                                                                                                                                                       Work
                                                                                                                                                     Packages



                                                                                                      NASA PM Challenge 2010                                                             19
Control Account (CA)

•   The CA forms the hub of the technical, cost and, schedule management
    focus
•   Virtually all elements of planning and control come together at the CA
    level including work authorization, schedules, budgets, earned value, cost
    collection (actuals), problem identification/variance analysis and estimate
    to complete
•   Consists of:
     –   Work Packages (WPs) – near term work that is well defined.
     –   Planning Packages (PPs) - more far term effort used for budgeting and
         scheduling purposes. A vehicle for planning at a higher level when details may
         not yet be well defined. Planning packages must also reflect horizontal
         integration with assignment of predecessors and successors.
                                                                       Control Account
                                                                        BUDGET – 150
                                                              10
                                   •   SCOPE                    10
                                   •   SCHEDULE                15                PLANNING
                                                                  20             PACKAGES
                                   •   BUDGET
                                                                            20
                                                                                      45
                                                              WORK
                                                            PACKAGES                       30


                                   NASA PM Challenge 2010                                       20
Schedule Development

• Using the WBS:
   –   Develop a logic network schedule for all contractual activities, including
       technical performance parameters/outcomes

   –   Scheduling is a process of changing work scope into defined tasks:
        •   WBS oriented
        •   Defined time duration (phased over the total life of the program)
        •   Logically connected to all other related tasks

   –   Determine resources required to complete scheduled activities
        •   Labor
              – Direct Labor
              – Civil Service Labor (when applicable)
              – Support Contractors
        •   Material
        •   Contracts/Subcontracts
        •   Other Direct Costs
        •   Indirect Costs




                                    NASA PM Challenge 2010                          21
Horizontal & Vertical Schedule Integration (VSI)

The Scheduling System: Consists of an integrated, multi-tiered hierarchy of
schedule levels. With a complete Logic Network Schedule, the time-phased
PMB will be accurate, allowing for the identification of the true critical path(s).

                                              INTEGRATED MASTER SCHEDULE (IMS)


             Master Schedule
           (Contract Summary)


                                 INTEGRATIO
                                  VERTICAL




        Intermediate Schedule
                                      N



            (Logic Network
              Schedule)                                                    HORIZONTA
                                                                                L
                                                                           INTEGRATIO
                                                                                N



            Detailed Schedules
            (Control Accounts)




                                          NASA PM Challenge 2010                        22
Schedule Considerations

•   Is the schedule logic (activity sequence) established and valid?
•   Are the schedule milestones compatible with the schedule logic?
•   Is the critical path analysis valid?
•   Are durations reasonable compared with other project’s history?
•   Are resources used to their maximum?
•   Are parallel activities reasonable or risky, i.e., flight hardware being
    built before qualification is complete?




                               NASA PM Challenge 2010                          23
Understanding the Baseline

• Is the plan fully defined?
• Is the plan realistic?
• What are the risky areas of the plan?




      How can we understand and assess inherent risk in the plan?

                               NASA PM Challenge 2010               24
Determining Earned Value


• How is Earned Value determined?

   –   When planning work three basic classifications are used:
        •   Discrete Work – Definable end product
        •   Level of Effort (LOE) – End product not defined
        •   Apportioned Effort – Budgeted based on a percentage of another (base)
            related task (e.g., Quality Assurance)


   –   Earned Value must be taken in the same manner in which the work
       was planned




                                  NASA PM Challenge 2010                            25
Discrete Earned Value Techniques
0/100 Method                                       Milestone
• 1 accounting period                              • Identifiable milestone
• No EV at start                                   • Milestone weighting should correlate to the
                                                     resources required to accomplish the task –
• 100% EV at completion
                                                     1 milestone per month
                                                   • 3 or more accounting periods




50/50 Method                                      Percent Complete
• No more than 2 accounting periods               • Least desirable
• 50% EV at start                                 • Somewhat subjective

• 50% EV at complete                              • If used, apply quantitative back-up data




                                      NASA PM Challenge 2010                                       26
Earned Value Techniques
Apportioned Effort (AE)
  •   Work that is dependent on or related to the performance of other discrete
      effort in direct proportion (i.e., Quality Control effort in production)
  •   Percentage and base task must be identified
  •   Take the percentage of the AE for the base task, and that is what is earned




             Production Effort




                  Inspection Effort




                                      NASA PM Challenge 2010                        27
Earned Value Techniques


Level of Effort (LOE)

•   Contract effort that does not produce any definable end product(s)
     –   General or supportive activities; i.e., management, administrative, etc.
•   Used when no other EV method is applicable
•   Over-use will distort project performance measurement
•   Budget is spread over the scheduled period of performance
•   Value of work is earned based on passage of time
•   Planned Work Budget (BCWS) = Earned Value (BCWP)
     –   Never a Schedule Variance




                                     NASA PM Challenge 2010                         28
Characteristics of a “Good” Milestone
•   Tied to a specific product or event
•   Within the authority of the person who will perform the work
•   Clear, objective criteria for measuring accomplishment
•   Directly related to the control account statement of work
•   Weighted in relationship to the time-phased budget
•   Expressed in calendar dates and identified to control account and
    summary schedules




                                NASA PM Challenge 2010                  29
What are some potential causes of
             deviations from a Project Plan?



•   Poor beginning estimates
•   Poor understanding of requirements
•   Lack of risk assessment/planning
•   Requirements creep
•   Poor management
•   Unforeseen technology difficulties
•   Jumping to conclusions about causes




                             NASA PM Challenge 2010   30
Future Performance Predictors

•   Estimate At Completion (EAC)
     –    Actual direct and indirect costs allocable to the contract + the estimate of all
          costs for authorized work remaining, or Estimate to Complete (ETC).

     –    Estimated cost to complete the entire scope of work

     –    Supported with a rationale

     –    EAC trends usually do not reverse

     –    Best case, worst case, most likely required in the CPR

•    Comprehensive Estimate at Completion

     –   Bottoms-up estimate reviewing all remaining work and a thorough estimate of
         that work


     –   Required annually

                                     NASA PM Challenge 2010                                  31
EVM - Key Data Elements
                                                                           Estimate At Completion (EAC)



                                                                        Budget at
                  Contract or Project Budget Base                    Completion (BAC)               Over
                                                                                                   Budget       Variance at
                                                                                                                Completion

            Management Reserve (MR)

                             Estimate to Complete (ETC)


                         Actual Cost
           Actual Cost of Work Performed (ACWP)


                                                                Cost
                                                                Variance

           Planned Value
$       Budgeted Cost for Work
                                                  Schedule
                                                  Variance             Performance Measurement
          Scheduled (BCWS)
                                                                             Baseline (PMB)




                                              Earned Value (Accomplished)
                                              Budgeted Cost for Work Performed                               For Projected
                                                         (BCWP)                                             Slippage (check
                                                                                                                schedule)



Start
                                                       Time Now                             Completion
Date
                                                                                              Date


                                           NASA PM Challenge 2010                                                             32
PART 3




Performance Reporting, Variance
    Analysis and Data Usage




           NASA PM Challenge 2010
                                    33
Where are we headed?

•   First we need to analyze current trends (current performance indicators)
     –   What are our problem areas?
     –   What are the causes of our problems?
•   Forecast the future based on performance to date
     –   How can we stay on plan?
     –   What are the impacts to the project?
     –   Any technical, cost, or schedule surprises?
     –   When will we finish all the work?
     –   What is the estimated cost at completion?
     –   Is it achievable?
•   Indicate areas for management action
     –   What should we do now to mitigate problems?




                                   NASA PM Challenge 2010
                                                                               34
Project Data Trace (Storyboard)
Contractor Example                                                                                                            Time / Accounting              EVM
                                                                                                                              System                         System

                                                                                                                                                  Actuals
                                                                                                                                                  (ACWP)


                     WBS
                     Dictionary                                                                                                                                                   CPR

                                                                                                                                  IMS
                                                                                                                                  (Resource Loaded)
                                                                                                                                                             Planned
                                                                                                                                                           (BCWS) &
                                                                                                                                                       Accomplished
                                                                    WAD                                                                                      (BCWP)



           WBS
                                                                                                                                                                        XML



SOW                                                                                                                                    CAPs


                                  RAM
                                  Page 2                                Organizational Owner
                                                     Requirements




                                                                                 Development




                                                                                                      Packaging



                                                                                                                  Technical
                                           Manager




                                                                                                                   Support
                                           Project




                                                                    Design




                                                                                               Test




                                  WBS #

                                  1.2.7
                                  1.2.8
                                                     x
                                                     x                                                                                                                 wInsight
           OBS
                                  1.2.9              x
                                  1.3.1                             x
                                  1.3.2                             x
                                  1.3.3                                          x
                                  1.3.4                                          x
                                  1.3.5                                          x
                                  1.4.1                                          x
                                  1.4.2                                          x
                                  1.4.3                                          x
                                  1.4.4                                          x




                                                                                                                                   Mgmt Reporting &
                                                                                                                                      Data Analysis



                                                                             NASA PM Challenge 2010                                                                                     35
Variance Calculations
•   Cost Variance (CV): The difference between BCWP and ACWP
     –   CV = (BCWP - ACWP)
     –   Favorable is positive (Cost underrun)
     –   Unfavorable is negative (Cost overrun)
•   Cost Variance Percent (%): The CV divided by the Earned Value times 100
     CV% = (BCWP - ACWP) X 100
               BCWP

•   Schedule Variance (SV): The difference between BCWP and BCWS
     –   SV=BCWP-BCWS
     –   Favorable is positive (Ahead of schedule)
     –   Unfavorable is negative (Behind schedule)
•   Schedule Variance Percent (%): The SV divided by the BCWS times 100
     SV% = (BCWP - BCWS)
                               X 100
                  BCWS

                                   NASA PM Challenge 2010                     36
Variance Calculations (conclusions)


•   Variance at Completion (VAC): The difference between BAC and EAC
     –   VAC = BAC - EAC

     –   Compares what the work was budgeted (BAC) to what it is currently estimated
         to cost (EAC)

     –   Favorable is positive (Forecasted under run)

     –   Unfavorable is negative (Forecasted over run)

•   Variance at Completion Percent (%): The VAC divided by the BAC times 100
         VAC % = VAC
                  BAC X 100




                                   NASA PM Challenge 2010                              37
Variance Analysis Objectives



─   A clear explanation of the cause
─   A comprehensive impact assessment
─   A corrective action plan
─   A revised Estimate at Completion (EAC)
    • Cost
    • Schedule




                          NASA PM Challenge 2010   38
“Root Causes” of Cost Variances

                                                             Rate Variance
                                                (Earned Value-Actual Rate) x Actual Hours
                 Labor
                                                      Usage (Efficiency) Variance
                                              (Earned Hours – Actual Hours) x Earned Rate




                                                              Price Variance
                Material                      (Earned Price – Actual Price) x Actual Quantity
  Cost
                   &
Variance                                                     Usage Variance
               Equipment
                                            (Earned Quantity – Actual Quantity) x Earned Price




                                                              Price Variance
                  Other                       (Earned Price – Actual Price) x Actual Quantity
               Direct Cost
                 (ODC)                                       Usage Variance
                                            (Earned Quantity – Actual Quantity) x Earned Price




                             NASA PM Challenge 2010                                              39
Analysis Considerations

Favorable and unfavorable variances should be carefully evaluated. The project analyst
should examine and understand the reasons for underruns, as well as overruns because
they could be masking a serious problem.
•   Establishing Thresholds for Reporting and Analysis
     – Establish threshold reporting based on risk and tailored to WBS by specific dollar amount and/or variance
         percentage
     –   Identification of threshold reporting should also consider program phase, risk and WBS criticality
•   Good Variance Analysis Identifies
     –   The Problem
     –   Cause of the Problem
     –   Impact to the Program (Cost, Schedule and Technical)
     –   Corrective Action
     –   Get well date
•   Areas to Address
     –   Poor initial planning or estimating
     –   Technical breakthroughs or problems
     –   Cost (or usage) of labor, material, or Other Direct Costs higher or lower than planned
     –   Inflation and new labor contracts
     –   Front-end loading
•   Reconciliation Analysis
     – Other budget/funding documentation
     – Labor resource planning documentation
     – Schedules
                                              NASA PM Challenge 2010                                               40
EVM Reporting

Contract Performance Report (CPR) - Required EVM data report on contracts
where full EVMS compliance is required

    Contains Five Reporting Formats:
    •   Format 1 – Work Breakdown Structure
    •   Format 2 – Organizational Categories
    •   Format 3 -- Baseline
    •   Format 4 – Staffing
    •   Format 5 – Explanations and Problem Analysis
                   – Total contract
                   – Cost & schedule variance analysis
                   – Other analyses (6 topics)
                   – OTB & OTS (as applicable)




                                      NASA PM Challenge 2010                41
Performance Indicators

•   Cost Performance Index (CPI): The average cost efficiency with which work has
    been performed to date

      –   Formula: CPI = BCWP / ACWP

      –   If CPI > 1.0, Effort is under-running budget

      –   If CPI < 1.0, Effort is over-running budget
•   Schedule Performance Index (SPI): The ratio of the budgeted value of work
    performed to the budgeted value of work scheduled
      –   Formula: SPI = BCWP / BCWS
      –   If SPI > 1.0, Effort is ahead of schedule
      –   If SPI < 1.0, Effort is behind schedule
      –   Is only an indicator
      –   More important early in the project




                                      NASA PM Challenge 2010                        42
Current Status Indicators


•   How much of the program SHOULD have been accomplished at this
    point?
     –   Percent Scheduled = (BCWS / BAC) X 100
•   How many of the forecasted funds have been SPENT at this point?
     –   Percent Spent = (ACWP / BAC) X 100
•   How much of the program has been ACCOMPLISHED to this point?
     –   Percent Complete = (BCWP / BAC) X 100
•   What is the budgeted value of the work remaining?
     –   Work Remaining = BAC - BCWP cum




                                NASA PM Challenge 2010                43
Performance Forecasting

• To-Complete Performance Index (TCPI):
       – Cost (CPI) efficiency required to complete the remaining work
       – TCPIEAC= (BAC-BCWP) / (EAC-ACWP)
• Performance Indicator Comparison
       – CPI versus TCPI
       – Cost efficiency to date compared to cost efficiency to complete the
         work remaining
       – Note spread point when more than 20% complete
       – Thoroughly evaluate all point degradations, e.g. 1.42 versus .67
       – Very helpful in reviewing EAC rationales



                              NASA PM Challenge 2010                           44
Future Performance Predicators


                        Independent Estimate At Completion (IEAC)
•   There are many ways to calculate an IEAC
•   An example: Independent Estimate At Completion (IEAC)
     –   IEAC = Actuals + (Work Remaining/Performance Factor)
          •   EAC = ACWP + [(BAC-BCWP)/Performance Factor]
     –   SPI as an indicator of EAC is better in first 50% (early stages) of a project
     –   There is no substitute for GOOD program information
•   Common Performance Factors
     –   Cost Performance Index (CPI)
     –   Schedule Performance Index (SPI)
     –   WEIGHTED (80/20 or some other ratio)



                                      NASA PM Challenge 2010                             45
Using EVM Data as a Predictor *


•   When a contract is more than 15% complete & more than 10% over-run:
     –   The over-run at completion will be more than the over-run incurred to date



•   The final cost variance (in dollars or as a percentage) will be worse than
    the cost variance at the 20% completion point.


* Based on OSD database of more than 500 major DOD contracts since 1977




                                    NASA PM Challenge 2010

                                                                                      46
PART 4



Summary




NASA PM Challenge 2010
                         47
EVM Process Overview

Define the Work        Plan the Work            Work the Plan        Collect Results


                                 PMB
                                                          Risk?
                      (Schedule/Budget)
                                                                     Measure Work
                                                                      in Process

                      Change Control
                                                                      (Earned Value)

                       Changes


                                                                    Analyze Variances

   External Changes                       Internal Changes



                                                                  Implement Corrective
                                                                        Actions
      An iterative process used
   throughout the life of a contract.

                                 NASA PM Challenge 2010                                  48
Benefits of using EVM


•   Provides Project Management with objective, accurate and timely data for
    effective decision making (much more than plan versus actuals)
•   Early warning of issues
•   Allows more efficient use of management resources, by identifying and
    focusing on problem areas
     –   Detail planning at levels where work is performed allows management attention
         to be directed to areas where significant problems are indicated

•   Provides better capability to trace problems to their source
•   Provides better historical performance data
•   EVM is an “Industry Best Practice” for project management (ANSI/EIA-748
    – Earned Value Management Systems)



                                    NASA PM Challenge 2010                               49
Conclusions about EVM


•   An integrated management process for gaining valuable insight into project
    performance.
•   Only management process that effectively integrates technical, cost,
    schedule and risk.
•   Provides valuable quantifiable performance metrics for forecasting at-
    completion cost and schedule.
•   Promotes early visibility to cost and schedule variance sooner than any
    other practice---reduces the ‘shock syndrome’
•   Focuses on significant technical, cost and schedule problems---avoids
    swatting mosquitoes while the elephants charge on by
•   Establishes funding authority’s confidence in program management



                                NASA PM Challenge 2010                           50
Questions?




 NASA PM Challenge 2010   51

Contenu connexe

Tendances

Gary.humphreys
Gary.humphreysGary.humphreys
Gary.humphreysNASAPMC
 
Mahmood porter
Mahmood porterMahmood porter
Mahmood porterNASAPMC
 
Zimmerman barbier
Zimmerman barbierZimmerman barbier
Zimmerman barbierNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
Backup darren elliott
Backup darren elliottBackup darren elliott
Backup darren elliottNASAPMC
 
Matt.gonzales
Matt.gonzalesMatt.gonzales
Matt.gonzalesNASAPMC
 
Blythe.mike
Blythe.mikeBlythe.mike
Blythe.mikeNASAPMC
 
Glenn.counts
Glenn.countsGlenn.counts
Glenn.countsNASAPMC
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthewNASAPMC
 
Borchardt.heidemarie
Borchardt.heidemarieBorchardt.heidemarie
Borchardt.heidemarieNASAPMC
 
Amer.tahani
Amer.tahaniAmer.tahani
Amer.tahaniNASAPMC
 
Law.richard
Law.richardLaw.richard
Law.richardNASAPMC
 
Rhodes.donna
Rhodes.donnaRhodes.donna
Rhodes.donnaNASAPMC
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingChris Carson
 
Project Management Professional (PMP) / 42 Processes
Project Management Professional (PMP) / 42 ProcessesProject Management Professional (PMP) / 42 Processes
Project Management Professional (PMP) / 42 Processesedtichy
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMIChris Carson
 

Tendances (20)

Gary.humphreys
Gary.humphreysGary.humphreys
Gary.humphreys
 
Mahmood porter
Mahmood porterMahmood porter
Mahmood porter
 
Zimmerman barbier
Zimmerman barbierZimmerman barbier
Zimmerman barbier
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
Backup darren elliott
Backup darren elliottBackup darren elliott
Backup darren elliott
 
Matt.gonzales
Matt.gonzalesMatt.gonzales
Matt.gonzales
 
Blythe.mike
Blythe.mikeBlythe.mike
Blythe.mike
 
Glenn.counts
Glenn.countsGlenn.counts
Glenn.counts
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthew
 
Borchardt.heidemarie
Borchardt.heidemarieBorchardt.heidemarie
Borchardt.heidemarie
 
Amer.tahani
Amer.tahaniAmer.tahani
Amer.tahani
 
Law.richard
Law.richardLaw.richard
Law.richard
 
Rhodes.donna
Rhodes.donnaRhodes.donna
Rhodes.donna
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
 
Project Management Professional (PMP) / 42 Processes
Project Management Professional (PMP) / 42 ProcessesProject Management Professional (PMP) / 42 Processes
Project Management Professional (PMP) / 42 Processes
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
PMP Map Color Coded
PMP Map Color CodedPMP Map Color Coded
PMP Map Color Coded
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMI
 
Symons
SymonsSymons
Symons
 

En vedette

Kerby.jerald
Kerby.jeraldKerby.jerald
Kerby.jeraldNASAPMC
 
Terry.cooke davies
Terry.cooke daviesTerry.cooke davies
Terry.cooke daviesNASAPMC
 
Backup ronniegoodinchampionsinventors
Backup ronniegoodinchampionsinventorsBackup ronniegoodinchampionsinventors
Backup ronniegoodinchampionsinventorsNASAPMC
 
Taylor.ron
Taylor.ronTaylor.ron
Taylor.ronNASAPMC
 
Ronnie goodin.ronnie contracts
Ronnie goodin.ronnie contractsRonnie goodin.ronnie contracts
Ronnie goodin.ronnie contractsNASAPMC
 
Canga.m.wood.j
Canga.m.wood.jCanga.m.wood.j
Canga.m.wood.jNASAPMC
 
Ann over
Ann overAnn over
Ann overNASAPMC
 
Dezfuli youngblood
Dezfuli youngbloodDezfuli youngblood
Dezfuli youngbloodNASAPMC
 
Gill.paul
Gill.paulGill.paul
Gill.paulNASAPMC
 
Krasa.lee
Krasa.leeKrasa.lee
Krasa.leeNASAPMC
 
Bilardo2 15-2012
Bilardo2 15-2012Bilardo2 15-2012
Bilardo2 15-2012NASAPMC
 
Augustin.debbie
Augustin.debbieAugustin.debbie
Augustin.debbieNASAPMC
 
Derleth.james
Derleth.jamesDerleth.james
Derleth.jamesNASAPMC
 
Juli.thomas
Juli.thomasJuli.thomas
Juli.thomasNASAPMC
 
Ray hines stegeman
Ray hines stegemanRay hines stegeman
Ray hines stegemanNASAPMC
 
Kelly.michael
Kelly.michaelKelly.michael
Kelly.michaelNASAPMC
 
Kelso.robert
Kelso.robertKelso.robert
Kelso.robertNASAPMC
 
Carol scottcowartmcphillipspm challengefinal
Carol scottcowartmcphillipspm challengefinalCarol scottcowartmcphillipspm challengefinal
Carol scottcowartmcphillipspm challengefinalNASAPMC
 
Garrett.skrobot
Garrett.skrobotGarrett.skrobot
Garrett.skrobotNASAPMC
 

En vedette (20)

Kerby.jerald
Kerby.jeraldKerby.jerald
Kerby.jerald
 
Terry.cooke davies
Terry.cooke daviesTerry.cooke davies
Terry.cooke davies
 
Backup ronniegoodinchampionsinventors
Backup ronniegoodinchampionsinventorsBackup ronniegoodinchampionsinventors
Backup ronniegoodinchampionsinventors
 
Taylor.ron
Taylor.ronTaylor.ron
Taylor.ron
 
Ronnie goodin.ronnie contracts
Ronnie goodin.ronnie contractsRonnie goodin.ronnie contracts
Ronnie goodin.ronnie contracts
 
Canga.m.wood.j
Canga.m.wood.jCanga.m.wood.j
Canga.m.wood.j
 
Ann over
Ann overAnn over
Ann over
 
Dezfuli youngblood
Dezfuli youngbloodDezfuli youngblood
Dezfuli youngblood
 
Gill.paul
Gill.paulGill.paul
Gill.paul
 
Krasa.lee
Krasa.leeKrasa.lee
Krasa.lee
 
Bilardo2 15-2012
Bilardo2 15-2012Bilardo2 15-2012
Bilardo2 15-2012
 
Augustin.debbie
Augustin.debbieAugustin.debbie
Augustin.debbie
 
Derleth.james
Derleth.jamesDerleth.james
Derleth.james
 
Juli.thomas
Juli.thomasJuli.thomas
Juli.thomas
 
Grieman
GriemanGrieman
Grieman
 
Ray hines stegeman
Ray hines stegemanRay hines stegeman
Ray hines stegeman
 
Kelly.michael
Kelly.michaelKelly.michael
Kelly.michael
 
Kelso.robert
Kelso.robertKelso.robert
Kelso.robert
 
Carol scottcowartmcphillipspm challengefinal
Carol scottcowartmcphillipspm challengefinalCarol scottcowartmcphillipspm challengefinal
Carol scottcowartmcphillipspm challengefinal
 
Garrett.skrobot
Garrett.skrobotGarrett.skrobot
Garrett.skrobot
 

Similaire à Humphreys.gary

Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeffNASAPMC
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
2011 pmo symposium Bridging the Agile-to-PMO Communication Gap
2011 pmo symposium Bridging the Agile-to-PMO Communication Gap2011 pmo symposium Bridging the Agile-to-PMO Communication Gap
2011 pmo symposium Bridging the Agile-to-PMO Communication GapBrent Barton
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned ValueGlen Alleman
 
Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysGlen Alleman
 
Introduction to Earned Value Management
Introduction to Earned Value ManagementIntroduction to Earned Value Management
Introduction to Earned Value ManagementUnanet
 
R simpson elee
R simpson eleeR simpson elee
R simpson eleeNASAPMC
 
Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018Roger H. Mandel
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part twoHossam Maghrabi
 
Resume_McColgin_Quentin_Master_Scheduling
Resume_McColgin_Quentin_Master_SchedulingResume_McColgin_Quentin_Master_Scheduling
Resume_McColgin_Quentin_Master_SchedulingQuentin McColgin
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimationssuser9d62d6
 
Sameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle itSameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle itSameer Mitter
 
Defining The Project
Defining The ProjectDefining The Project
Defining The ProjectEarl Tongol
 
Ipao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis llIpao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis llNASAPMC
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxssusercf695b
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 

Similaire à Humphreys.gary (20)

Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeff
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
2011 pmo symposium Bridging the Agile-to-PMO Communication Gap
2011 pmo symposium Bridging the Agile-to-PMO Communication Gap2011 pmo symposium Bridging the Agile-to-PMO Communication Gap
2011 pmo symposium Bridging the Agile-to-PMO Communication Gap
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned Value
 
Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two Days
 
Introduction to Earned Value Management
Introduction to Earned Value ManagementIntroduction to Earned Value Management
Introduction to Earned Value Management
 
R simpson elee
R simpson eleeR simpson elee
R simpson elee
 
Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018
 
Intergrated baseline reviews as a tool in assurance
Intergrated baseline reviews as a tool in assurance Intergrated baseline reviews as a tool in assurance
Intergrated baseline reviews as a tool in assurance
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part two
 
Resume_McColgin_Quentin_Master_Scheduling
Resume_McColgin_Quentin_Master_SchedulingResume_McColgin_Quentin_Master_Scheduling
Resume_McColgin_Quentin_Master_Scheduling
 
DPPM1
DPPM1DPPM1
DPPM1
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
Sameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle itSameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle it
 
Defining The Project
Defining The ProjectDefining The Project
Defining The Project
 
Ipao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis llIpao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis ll
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 

Plus de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerryNASAPMC
 

Plus de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
 

Dernier

Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Farhan Tariq
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxLoriGlavin3
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
Scale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterScale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterMydbops
 
Generative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfGenerative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfIngrid Airi González
 
UiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPathCommunity
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfMounikaPolabathina
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Strongerpanagenda
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rick Flair
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...Wes McKinney
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersNicole Novielli
 
2024 April Patch Tuesday
2024 April Patch Tuesday2024 April Patch Tuesday
2024 April Patch TuesdayIvanti
 
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentEmixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentPim van der Noll
 
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesHow to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesThousandEyes
 
Manual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance AuditManual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance AuditSkynet Technologies
 
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality AssuranceInflectra
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxLoriGlavin3
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
Enhancing User Experience - Exploring the Latest Features of Tallyman Axis Lo...
Enhancing User Experience - Exploring the Latest Features of Tallyman Axis Lo...Enhancing User Experience - Exploring the Latest Features of Tallyman Axis Lo...
Enhancing User Experience - Exploring the Latest Features of Tallyman Axis Lo...Scott Andery
 

Dernier (20)

Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
Scale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterScale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL Router
 
Generative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfGenerative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdf
 
UiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to Hero
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdf
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software Developers
 
2024 April Patch Tuesday
2024 April Patch Tuesday2024 April Patch Tuesday
2024 April Patch Tuesday
 
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentEmixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
 
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesHow to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
 
Manual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance AuditManual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance Audit
 
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
Enhancing User Experience - Exploring the Latest Features of Tallyman Axis Lo...
Enhancing User Experience - Exploring the Latest Features of Tallyman Axis Lo...Enhancing User Experience - Exploring the Latest Features of Tallyman Axis Lo...
Enhancing User Experience - Exploring the Latest Features of Tallyman Axis Lo...
 

Humphreys.gary

  • 1. EVMS The Principles, Best Practices and Benefits Gary C. Humphreys Humphreys & Associates, Inc. NASA PM Challenge 2010 Used with Permission
  • 2. PART 1 Overview, Earned Value Management NASA PM Challenge 2010 1
  • 3. What is EVM? • Earned Value Management (EVM) is an integrated project management process for assessing, understanding and quantifying what a contractor or in-house project is achieving with program/project dollars – Integrates technical, cost, and schedule with risk management – Allows objective assessment and quantification of current project performance – Helps predict future performance based on trends “Management 101” “EVM 101” Plan Organize Organize Plan & Budget EVM is simply good project management! Staff Account for Costs Direct Analyze Control Incorporate Changes NASA PM Challenge 2010 2
  • 4. So why use EVM? EVM enhances the chances of program/project success • To Succeed, you must Manage • To Manage, you must Measure • To Measure, you must Define • To Define, you must Understand NASA PM Challenge 2010 3
  • 5. NASA EVM Policy & Requirements • NASA EVM requirements are found in NPR 7120.5, NASA Program and Project Management Processes and Requirements and NPR 7120.7, NASA Information Technology and Institutional Infrastructure Program and Project Management Requirements. Policy is contained in NASA FAR Supplement (NFS) 1834.201. NASA EVM requirements are predicated on the principles and guidelines in ANSI/EIA-748, Industry Guidelines for Earned Value Management Systems. • NPR 7120.5 requires the project EVM approach to be in place by Key Decision Point (KDP) C (the conclusion of Preliminary Design Review (PDR)) and implemented in Phase C (Final Design and Fabrication) through KDP E [Flight Readiness Review (FRR) or Launch Readiness Review (LRR)]. • Additionally, project performance reporting must begin within 60 days after the start of Phase C. To meet this timeline, it is highly recommended that projects begin implementation planning during Phase B (Preliminary Design and Technology Completion). NASA PM Challenge 2010 4
  • 6. NPR 7120.5 Guidance • NPR 7120.5 also requires that NASA programs and projects use EVM on projects and contracts that meet the following criteria: 1. For projects with a total anticipated final value of $20 million or more, EVM principles should be applied, as defined by ANSI/EIA-748, Earned Value Management Systems. a. If the project's primary NASA Center has a validated EVMS, the project uses that system rather than the EVM principles application approach. 2. For development contracts and subcontracts valued at or between $20M and $50M, the contractor is expected to have an EVMS that complies with the 32 guidelines in the ANSI/EIA-748 Standard. 3. For development contracts and subcontracts valued at $50M or more, the contractor is required to have an EVMS that has been formally validated by the Government. 4. EVM is not required on contracts for non-developmental engineering support services, steady state operations, basic and applied research, and routine services such as janitorial services or grounds maintenance services. In these cases, application of EVM is at the discretion of the Program/Project Manager (PM). • NASA projects that do not have a validated EVMS will use the seven management principles that are contained in ANSI/EIA-748 standard. NASA PM Challenge 2010 5
  • 7. Seven EVM Principles (ANSI/EIA-748-B-2007) 1. Plan all work scope for the project to completion. 2. Break down the project work scope into finite pieces that can be assigned to a responsible person or organization for control of technical schedule and cost objectives. 3. Integrate project work scope, schedule, and cost objectives into a performance measurement baseline plan against which accomplishments may be measured. Control changes to the baseline. 4. Use actual costs incurred and recorded in accomplishing the work performed. 5. Objectively assess accomplishments at the work performance level. 6. Analyze significant variances from the plan, forecast impacts, and prepare an estimate at completion based on performance to date and all remaining work that must be performed. 7. Incorporate Earned Value Management in the project decision-making and review processes. NASA PM Challenge 2010 6
  • 8. 32 EVM Guidelines (ANSI/EIA-748-B-2007) Guideline Categories • Organization (5 guidelines) – Define contractual effort and assign responsibilities for the work. Integrate planning, scheduling, work authorization, and accounting systems. • Planning, Scheduling and Budgeting (10 guidelines) – Plan, schedule, budget and authorize the work. Establish and maintain a time-phased budget baseline. • Accounting Considerations (6 guidelines) – Accumulate costs of work and material. – Report on progress/accomplishments to date. • Analysis & Management Reports (6 guidelines) – Compare planned, earned and actual costs, analyze variances. Develop revised estimates at complete. Identify managerial actions. • Revisions and Data Maintenance (5 guidelines) – Execute timely incorporation of contractual changes. Maintain traceability from original budgets. NASA PM Challenge 2010 7
  • 9. Earned Value Management Process Risk Monitoring Informed Management Decisions Scheduling & Resource Allocation Systems Progress Earned Value Mgmt System (Progress) Accounting System Technical Performance Measurement NASA PM Challenge 2010 8
  • 10. Features of a “Good” EVM system • Thorough up-front planning based on a detailed product-oriented Work Breakdown Structure (WBS), incorporating Risk Management – Timely Performance Measurement Baseline (PMB) establishment and control – Information broken down by product, as well as by organization or function • Objective measurement of technical accomplishment against the plan at levels where the work is being performed • Reporting consistency and discipline – a structured process and methodology − Summarized data reporting to higher management (performance metrics) for use in effective decision making − Provides for analysis of significant variances and their impact on the project − Facilitates proper management actions to mitigate risk and manage technical, cost and schedule performance NASA PM Challenge 2010 9
  • 11. PART 2 EVMS Terms and the Performance Measurement Baseline NASA PM Challenge 2010 10
  • 12. Basic EVM Terms • Budgeted Cost for Work Scheduled (BCWS) – The sum of the time-phased budgets established for all effort (including in- process work) scheduled to be accomplished within a given time period • Budgeted Cost for Work Performed (BCWP) – The sum of the time-phased budgets for work actually completed during a specified time period – BCWP is the budgeted value for the work actually accomplished – Earned value can only be determined after the performance (or scheduled performance) of work • Actual Cost of Work Performed (ACWP) – The costs (taken from the Accounting System) actually incurred (or in some cases estimated) and recorded, in accomplishing the work performed within a given time period NASA PM Challenge 2010 11
  • 13. Basic EVM Terms (continued) • Budget At Completion (BAC) – The budgetary goal (excluding MR) for accomplishment of all authorized work • Estimate At Completion (EAC) – Actual direct and indirect costs allocable to the contract, plus the estimate of all costs for authorized work remaining – Estimated cost to complete the entire project scope of work – Supported with a rationale – Best case, worst case, most likely NASA PM Challenge 2010 12
  • 14. Basic EVM Terms (continued) • Total Allocated Budget (TAB) – Total Allocated Budget is the sum of all budgets allocated by the contractor against which contract performance is to be measured and reported • Contract Budget Base (CBB) – Contract Budget Base is the negotiated contract cost plus the estimated cost of authorized unpriced work • Authorized Unpriced Work (AUW) – Contract work authorized by the contracting officer, not yet negotiated, aka not yet definitized work NASA PM Challenge 2010 13
  • 15. Contract/In-house Project – PMB Relationship Contract Price (Project Price) Total of all authorized work, both negotiated Total Allocated Budget (TAB) Contract Fee/Profit and un-negotiated Contract Budget Base Authorized Unpriced Over Target (CBB) or Project Work (AUW) Baseline (OTB) Budget Base (PBB) MR – Held for known The total is also Performance Measurement unknowns but in-scope called Budget at Management Reserve (MR) future effort. Not used to Completion (BAC) Baseline (PMB) cover cost overruns. UB – Temporary holding place for allocation to control accounts not to Distributed Budget Undistributed Budget (UB) exceed two accounting periods following negotiations. Summary Level Planning Control Account (CA) Package (SLPP) Work Package (WP) Planning Package (PP) NASA PM Challenge 2010 14
  • 16. The Performance Measurement Baseline (PMB) – Is all the work planned? What is the PMB? • A time-phased budget plan against which contract performance is measured • Developed by the contractor and jointly reviewed with the customer within six months of contract award • Based on the anticipated flow of work and outcomes • Incorporates dynamic, authorized project changes NASA PM Challenge 2010 15
  • 17. PMB Development Establishing the PMB is a 3-step process: 1. DEFINE THE WORK • Statement of Work (SOW) CONTRACT BUDGET BASE • Work Breakdown Structure (WBS) • Organizational Breakdown Structure (OBS) MR • Responsibility Assignment Matrix (RAM) 2. SCHEDULE THE WORK Integrated Master Schedule (IMS) • Master Schedule • Intermediate Schedule • Detailed Schedules $ 3. ALLOCATE BUDGETS 100 40 60 • Work Authorization System • Control Account Plan (CAP) 15 • Work Packages (WP) & 25 Planning Packages (PP) 30 30 TIME PMB – Time-phased, budgeted plan where contract performance can be measured. NASA PM Challenge 2010 16
  • 18. Work Breakdown Structure (WBS) • A product-oriented hierarchical division of the hardware, software, services, and data required to produce the project’s end product(s) • Should not be functional or organizational oriented • Should reflect the total project scope of work • Structured according to the way the work will be performed • Reflects the way in which project costs, schedule, technical and risk data are to be accumulated, summarized, and reported • WBS is the most important data item in defining and controlling the contracted technical scope • Summary level WBS must be the sum of all lower level WBS hierarchical in nature • Supports historical cost collection necessary for future costing activities of similar scoped products “It’s the WHAT that is Going to Be Done” NASA PM Challenge 2010 17
  • 19. Properly Structured WBS Standard Product Level 2’s Oriented Clear WBS Titles Center Breakout at Appropriate Level NASA PM Challenge 2010 18
  • 20. Responsibility Assignment Matrix (RAM) The Responsibility Assignment Matrix (RAM) Integrates WBS with OBS. The intersecting points are the Control Accounts. Contract Work Breakdown Structure (WBS) 1.0 1.1 1.2 1.3 WBS Reporting Level CWBS Extension Organization Breakdown Structure (OBS) Functional Org 1.1.1 1.1.2 1.1.3 1.1.4 Control Account 1.1.2.1 1.1.2.2 1.1.2.3 1.1.2.4 1.1.2.5 • Task Description • Perform. Measure • Work Authorization • Cost Accumulation SW • Work Package, Schedules, & Budget RAM Mech ENG CA Elec Work Packages NASA PM Challenge 2010 19
  • 21. Control Account (CA) • The CA forms the hub of the technical, cost and, schedule management focus • Virtually all elements of planning and control come together at the CA level including work authorization, schedules, budgets, earned value, cost collection (actuals), problem identification/variance analysis and estimate to complete • Consists of: – Work Packages (WPs) – near term work that is well defined. – Planning Packages (PPs) - more far term effort used for budgeting and scheduling purposes. A vehicle for planning at a higher level when details may not yet be well defined. Planning packages must also reflect horizontal integration with assignment of predecessors and successors. Control Account BUDGET – 150 10 • SCOPE 10 • SCHEDULE 15 PLANNING 20 PACKAGES • BUDGET 20 45 WORK PACKAGES 30 NASA PM Challenge 2010 20
  • 22. Schedule Development • Using the WBS: – Develop a logic network schedule for all contractual activities, including technical performance parameters/outcomes – Scheduling is a process of changing work scope into defined tasks: • WBS oriented • Defined time duration (phased over the total life of the program) • Logically connected to all other related tasks – Determine resources required to complete scheduled activities • Labor – Direct Labor – Civil Service Labor (when applicable) – Support Contractors • Material • Contracts/Subcontracts • Other Direct Costs • Indirect Costs NASA PM Challenge 2010 21
  • 23. Horizontal & Vertical Schedule Integration (VSI) The Scheduling System: Consists of an integrated, multi-tiered hierarchy of schedule levels. With a complete Logic Network Schedule, the time-phased PMB will be accurate, allowing for the identification of the true critical path(s). INTEGRATED MASTER SCHEDULE (IMS) Master Schedule (Contract Summary) INTEGRATIO VERTICAL Intermediate Schedule N (Logic Network Schedule) HORIZONTA L INTEGRATIO N Detailed Schedules (Control Accounts) NASA PM Challenge 2010 22
  • 24. Schedule Considerations • Is the schedule logic (activity sequence) established and valid? • Are the schedule milestones compatible with the schedule logic? • Is the critical path analysis valid? • Are durations reasonable compared with other project’s history? • Are resources used to their maximum? • Are parallel activities reasonable or risky, i.e., flight hardware being built before qualification is complete? NASA PM Challenge 2010 23
  • 25. Understanding the Baseline • Is the plan fully defined? • Is the plan realistic? • What are the risky areas of the plan? How can we understand and assess inherent risk in the plan? NASA PM Challenge 2010 24
  • 26. Determining Earned Value • How is Earned Value determined? – When planning work three basic classifications are used: • Discrete Work – Definable end product • Level of Effort (LOE) – End product not defined • Apportioned Effort – Budgeted based on a percentage of another (base) related task (e.g., Quality Assurance) – Earned Value must be taken in the same manner in which the work was planned NASA PM Challenge 2010 25
  • 27. Discrete Earned Value Techniques 0/100 Method Milestone • 1 accounting period • Identifiable milestone • No EV at start • Milestone weighting should correlate to the resources required to accomplish the task – • 100% EV at completion 1 milestone per month • 3 or more accounting periods 50/50 Method Percent Complete • No more than 2 accounting periods • Least desirable • 50% EV at start • Somewhat subjective • 50% EV at complete • If used, apply quantitative back-up data NASA PM Challenge 2010 26
  • 28. Earned Value Techniques Apportioned Effort (AE) • Work that is dependent on or related to the performance of other discrete effort in direct proportion (i.e., Quality Control effort in production) • Percentage and base task must be identified • Take the percentage of the AE for the base task, and that is what is earned Production Effort Inspection Effort NASA PM Challenge 2010 27
  • 29. Earned Value Techniques Level of Effort (LOE) • Contract effort that does not produce any definable end product(s) – General or supportive activities; i.e., management, administrative, etc. • Used when no other EV method is applicable • Over-use will distort project performance measurement • Budget is spread over the scheduled period of performance • Value of work is earned based on passage of time • Planned Work Budget (BCWS) = Earned Value (BCWP) – Never a Schedule Variance NASA PM Challenge 2010 28
  • 30. Characteristics of a “Good” Milestone • Tied to a specific product or event • Within the authority of the person who will perform the work • Clear, objective criteria for measuring accomplishment • Directly related to the control account statement of work • Weighted in relationship to the time-phased budget • Expressed in calendar dates and identified to control account and summary schedules NASA PM Challenge 2010 29
  • 31. What are some potential causes of deviations from a Project Plan? • Poor beginning estimates • Poor understanding of requirements • Lack of risk assessment/planning • Requirements creep • Poor management • Unforeseen technology difficulties • Jumping to conclusions about causes NASA PM Challenge 2010 30
  • 32. Future Performance Predictors • Estimate At Completion (EAC) – Actual direct and indirect costs allocable to the contract + the estimate of all costs for authorized work remaining, or Estimate to Complete (ETC). – Estimated cost to complete the entire scope of work – Supported with a rationale – EAC trends usually do not reverse – Best case, worst case, most likely required in the CPR • Comprehensive Estimate at Completion – Bottoms-up estimate reviewing all remaining work and a thorough estimate of that work – Required annually NASA PM Challenge 2010 31
  • 33. EVM - Key Data Elements Estimate At Completion (EAC) Budget at Contract or Project Budget Base Completion (BAC) Over Budget Variance at Completion Management Reserve (MR) Estimate to Complete (ETC) Actual Cost Actual Cost of Work Performed (ACWP) Cost Variance Planned Value $ Budgeted Cost for Work Schedule Variance Performance Measurement Scheduled (BCWS) Baseline (PMB) Earned Value (Accomplished) Budgeted Cost for Work Performed For Projected (BCWP) Slippage (check schedule) Start Time Now Completion Date Date NASA PM Challenge 2010 32
  • 34. PART 3 Performance Reporting, Variance Analysis and Data Usage NASA PM Challenge 2010 33
  • 35. Where are we headed? • First we need to analyze current trends (current performance indicators) – What are our problem areas? – What are the causes of our problems? • Forecast the future based on performance to date – How can we stay on plan? – What are the impacts to the project? – Any technical, cost, or schedule surprises? – When will we finish all the work? – What is the estimated cost at completion? – Is it achievable? • Indicate areas for management action – What should we do now to mitigate problems? NASA PM Challenge 2010 34
  • 36. Project Data Trace (Storyboard) Contractor Example Time / Accounting EVM System System Actuals (ACWP) WBS Dictionary CPR IMS (Resource Loaded) Planned (BCWS) & Accomplished WAD (BCWP) WBS XML SOW CAPs RAM Page 2 Organizational Owner Requirements Development Packaging Technical Manager Support Project Design Test WBS # 1.2.7 1.2.8 x x wInsight OBS 1.2.9 x 1.3.1 x 1.3.2 x 1.3.3 x 1.3.4 x 1.3.5 x 1.4.1 x 1.4.2 x 1.4.3 x 1.4.4 x Mgmt Reporting & Data Analysis NASA PM Challenge 2010 35
  • 37. Variance Calculations • Cost Variance (CV): The difference between BCWP and ACWP – CV = (BCWP - ACWP) – Favorable is positive (Cost underrun) – Unfavorable is negative (Cost overrun) • Cost Variance Percent (%): The CV divided by the Earned Value times 100 CV% = (BCWP - ACWP) X 100 BCWP • Schedule Variance (SV): The difference between BCWP and BCWS – SV=BCWP-BCWS – Favorable is positive (Ahead of schedule) – Unfavorable is negative (Behind schedule) • Schedule Variance Percent (%): The SV divided by the BCWS times 100 SV% = (BCWP - BCWS) X 100 BCWS NASA PM Challenge 2010 36
  • 38. Variance Calculations (conclusions) • Variance at Completion (VAC): The difference between BAC and EAC – VAC = BAC - EAC – Compares what the work was budgeted (BAC) to what it is currently estimated to cost (EAC) – Favorable is positive (Forecasted under run) – Unfavorable is negative (Forecasted over run) • Variance at Completion Percent (%): The VAC divided by the BAC times 100 VAC % = VAC BAC X 100 NASA PM Challenge 2010 37
  • 39. Variance Analysis Objectives ─ A clear explanation of the cause ─ A comprehensive impact assessment ─ A corrective action plan ─ A revised Estimate at Completion (EAC) • Cost • Schedule NASA PM Challenge 2010 38
  • 40. “Root Causes” of Cost Variances Rate Variance (Earned Value-Actual Rate) x Actual Hours Labor Usage (Efficiency) Variance (Earned Hours – Actual Hours) x Earned Rate Price Variance Material (Earned Price – Actual Price) x Actual Quantity Cost & Variance Usage Variance Equipment (Earned Quantity – Actual Quantity) x Earned Price Price Variance Other (Earned Price – Actual Price) x Actual Quantity Direct Cost (ODC) Usage Variance (Earned Quantity – Actual Quantity) x Earned Price NASA PM Challenge 2010 39
  • 41. Analysis Considerations Favorable and unfavorable variances should be carefully evaluated. The project analyst should examine and understand the reasons for underruns, as well as overruns because they could be masking a serious problem. • Establishing Thresholds for Reporting and Analysis – Establish threshold reporting based on risk and tailored to WBS by specific dollar amount and/or variance percentage – Identification of threshold reporting should also consider program phase, risk and WBS criticality • Good Variance Analysis Identifies – The Problem – Cause of the Problem – Impact to the Program (Cost, Schedule and Technical) – Corrective Action – Get well date • Areas to Address – Poor initial planning or estimating – Technical breakthroughs or problems – Cost (or usage) of labor, material, or Other Direct Costs higher or lower than planned – Inflation and new labor contracts – Front-end loading • Reconciliation Analysis – Other budget/funding documentation – Labor resource planning documentation – Schedules NASA PM Challenge 2010 40
  • 42. EVM Reporting Contract Performance Report (CPR) - Required EVM data report on contracts where full EVMS compliance is required Contains Five Reporting Formats: • Format 1 – Work Breakdown Structure • Format 2 – Organizational Categories • Format 3 -- Baseline • Format 4 – Staffing • Format 5 – Explanations and Problem Analysis – Total contract – Cost & schedule variance analysis – Other analyses (6 topics) – OTB & OTS (as applicable) NASA PM Challenge 2010 41
  • 43. Performance Indicators • Cost Performance Index (CPI): The average cost efficiency with which work has been performed to date – Formula: CPI = BCWP / ACWP – If CPI > 1.0, Effort is under-running budget – If CPI < 1.0, Effort is over-running budget • Schedule Performance Index (SPI): The ratio of the budgeted value of work performed to the budgeted value of work scheduled – Formula: SPI = BCWP / BCWS – If SPI > 1.0, Effort is ahead of schedule – If SPI < 1.0, Effort is behind schedule – Is only an indicator – More important early in the project NASA PM Challenge 2010 42
  • 44. Current Status Indicators • How much of the program SHOULD have been accomplished at this point? – Percent Scheduled = (BCWS / BAC) X 100 • How many of the forecasted funds have been SPENT at this point? – Percent Spent = (ACWP / BAC) X 100 • How much of the program has been ACCOMPLISHED to this point? – Percent Complete = (BCWP / BAC) X 100 • What is the budgeted value of the work remaining? – Work Remaining = BAC - BCWP cum NASA PM Challenge 2010 43
  • 45. Performance Forecasting • To-Complete Performance Index (TCPI): – Cost (CPI) efficiency required to complete the remaining work – TCPIEAC= (BAC-BCWP) / (EAC-ACWP) • Performance Indicator Comparison – CPI versus TCPI – Cost efficiency to date compared to cost efficiency to complete the work remaining – Note spread point when more than 20% complete – Thoroughly evaluate all point degradations, e.g. 1.42 versus .67 – Very helpful in reviewing EAC rationales NASA PM Challenge 2010 44
  • 46. Future Performance Predicators Independent Estimate At Completion (IEAC) • There are many ways to calculate an IEAC • An example: Independent Estimate At Completion (IEAC) – IEAC = Actuals + (Work Remaining/Performance Factor) • EAC = ACWP + [(BAC-BCWP)/Performance Factor] – SPI as an indicator of EAC is better in first 50% (early stages) of a project – There is no substitute for GOOD program information • Common Performance Factors – Cost Performance Index (CPI) – Schedule Performance Index (SPI) – WEIGHTED (80/20 or some other ratio) NASA PM Challenge 2010 45
  • 47. Using EVM Data as a Predictor * • When a contract is more than 15% complete & more than 10% over-run: – The over-run at completion will be more than the over-run incurred to date • The final cost variance (in dollars or as a percentage) will be worse than the cost variance at the 20% completion point. * Based on OSD database of more than 500 major DOD contracts since 1977 NASA PM Challenge 2010 46
  • 48. PART 4 Summary NASA PM Challenge 2010 47
  • 49. EVM Process Overview Define the Work Plan the Work Work the Plan Collect Results PMB Risk? (Schedule/Budget) Measure Work in Process Change Control (Earned Value) Changes Analyze Variances External Changes Internal Changes Implement Corrective Actions An iterative process used throughout the life of a contract. NASA PM Challenge 2010 48
  • 50. Benefits of using EVM • Provides Project Management with objective, accurate and timely data for effective decision making (much more than plan versus actuals) • Early warning of issues • Allows more efficient use of management resources, by identifying and focusing on problem areas – Detail planning at levels where work is performed allows management attention to be directed to areas where significant problems are indicated • Provides better capability to trace problems to their source • Provides better historical performance data • EVM is an “Industry Best Practice” for project management (ANSI/EIA-748 – Earned Value Management Systems) NASA PM Challenge 2010 49
  • 51. Conclusions about EVM • An integrated management process for gaining valuable insight into project performance. • Only management process that effectively integrates technical, cost, schedule and risk. • Provides valuable quantifiable performance metrics for forecasting at- completion cost and schedule. • Promotes early visibility to cost and schedule variance sooner than any other practice---reduces the ‘shock syndrome’ • Focuses on significant technical, cost and schedule problems---avoids swatting mosquitoes while the elephants charge on by • Establishes funding authority’s confidence in program management NASA PM Challenge 2010 50
  • 52. Questions? NASA PM Challenge 2010 51