SlideShare une entreprise Scribd logo
1  sur  20
Télécharger pour lire hors ligne
NASA External Cost/Schedule
  Performance Reporting:

Update on How Changes are being
           Folded in

      Mary Beth Zimmerman
       February 24, 2009
What’s New Since the last PM
              Challenge?
•   Two new reports
     – GAO Quick Look semi-annual reviews (Julie Pollitt’s presentation covers
       in detail)
     – ‘High Risk’ Metrics for OMB (Riva Svarcas’ presentation covers in detail)

•   Updated NASA policies and process affecting reporting
     – Distinction between margin held by projects and that held by programs
       or Mission Directorates
     – Review of quarterly reports to OMB by projects and centers
     – Update of quarterly data for operating plan changes

•   Distinguishing between internal and external reasons for reported
    cost and schedule changes.

•   Reporting will continue to evolve as additional details are worked
    with NASA’s stakeholders. Key items being refined:
     – Contract cost growth                  -- Milestone completion dates
     – Changes in content & scope            -- Explanations of change
     – Confidence Levels
Folding Changes into the Process

Report template
+ Data template    Data template                         Report templates
  Reporting         Quarterly          Any                MDs prepare
  baseline          data               thresholds         threshold
  established       updates            breached?          notifications &
                    form MDs                              reports


                                   OMB quarterly
 Data template
                                   MPAR
  Operating Plan
                                   GAO Quick Look (cost & schedule sections)
  data updates
                                   ‘High Risk’ metrics
Coordinated Data Management
•   Integrated quarterly data call to Mission Directorates includes:
     – A common data template and guidance serves as a basis for the cost
       and schedule information required in annual, semi-annual, and quarterly
       external reports.
     – Templates for any required baseline or threshold reports.
     – Guidance for completing each.
     – New policy being worked into quarterly process: projects, centers &
       Mission Directorates will sign off on quarterly reports to OMB.

•   Coordination of quarterly data call with other reporting elements.
     – Q1 report is coordinated with annual reporting (MPAR).
     – A GAO template is used to collect additional information on technology.
     – Lifecycle cost estimate (LCCE) changes reported in Agency Operation
       Plans to Congress will be based on updates to quarterly reports.

•   Coordination with Agency Baseline Program Review (BPI)
     – Distinguishes between cost margin held by the project and held for the
       project by the Program or Mission Directorate.
     – Coordination with cost and schedule data from KDPs.
     – Data call is being transitioned from PA&E to OCE to merge with BPR
       data collection.
Data Requirements
Project Cost                        Contracts
 Phase                                Pending awards
 Year                                 Cost growth
 WBS2                               Explanation of Change
 Budget line                         Changes in content
Project Schedule                      Reasons for change
 Key milestone                      Technical progress
 Interim milestones                   Technical maturity
Project Content                       Design stability
 Scope                              Project Risk
 Parameters                           Confidence level
 Critical technologies                Backup technologies

                  Blue text: New since last PM Challenge
Baseline Reports: No Changes
•   Baseline Reports are prepared for projects subject to MPAR reporting
    to Congress or NSPD-49 reporting to OMB when:
     – A project in formulation awards contract w/ development content =>$50M
       (for OMB only).
     – A project with a lifecycle cost estimate (LCCE) of $250M or more receives
       KDP-C approval to enter Phase C (for OMB & Congress).

•   Baseline Report includes
     – baseline numbers subject to threshold requirements.
          • Projects in development:      • Projects in formulation
            – Lifecycle cost                 – Ave. contract value
            – Development cost
            – Key schedule milestone

     – additional information as required by Congress or OMB.

•   Baseline Reports look similar to the project pages in the Agency’s
    budget.
Data Template
                  Projects in Formulation
                                                                NASA Formulation Cost and Contract Data Template Rev 3
                      Person completing this form:                                              Project Name:
                      Most recent budget/op plan assumed:                                       6-digit project code
                      Date of Estimate:


                      Schedule Assumptions
Expanded                Milestone                                                    Date
                        System Design Review
schedule                Start Phase B
                        NAR/PDR
milestone               Start Phase C
                        Start Phase D
information for         LRD/IOC


GAO Quick                                                                            Current LCC Estimate-At-Completion
                      Additional assumptions required to understand ROM LCC cost estimate:

Look                  Explanation of changes to direct project costs since last update:


                      Explanation of changes to indirect project costs since last update:
                                                                    Prior   FY05       FY06      FY07     FY08    FY09        FY10    FY11    FY12    FY13    FY14    FY15     BTC TOTAL
                      Project LCC by Year                             0.0      0.0        0.0       0.0     0.0        0.0      0.0     0.0     0.0     0.0     0.0     0.0     0.0      0.0
                      To be completed by Mission Directorate:
                      Direct Costs                                    0.0      0.0        0.0       0.0     0.0        0.0      0.0     0.0     0.0     0.0     0.0     0.0     0.0
No WBS                  Pre Formulation *
                        Formulation (A, B)
                                                                                                                                                                                         0.0
                                                                                                                                                                                         0.0

elements at             Development (C, D)
                        Operations Prime (E)
                                                                                                                                                                                         0.0
                                                                                                                                                                                         0.0

this stage              Operations Extended (E')
                        Closeout (F)
                                                                                                                                                                                         0.0
                                                                                                                                                                                         0.0
                      Will be updated by PA&E based on OCFO rates:
                      Indirect costs assigned to project        0.0                       0.0       0.0     0.0        0.0      0.0     0.0     0.0     0.0     0.0     0.0     0.0      0.0
                        Center M&O                                                                                                                                                       0.0
                        Corporate G&A                                                                                                                                                    0.0
                        Other indirect costs                                                                                                                                             0.0

                                 Contract Description:               Provider:       Project Element(s) this Supports           Current     Date of Current   Reason(s) for Change in Value
 Contract                                                                                                                    Contract Value (month/year)
                                                                                                                                 ($M)

 information
Data Template
                    Projects in Development
                                                                                       NASA Development Project Cost & Schedule Data Template (Rev 5)
• Filled out for:     Person completing this form:
                      Budget/Op Plan assumed:
                                                                                                                Project Name:
                                                                                                                Date of Estimate:
                                                                                                                                                                                                   6-digit project code



   – Each baseline                                      Current Estimated Schedule                                                    Directions
                            Milestone          Date         Milestone         Date       Other Milestones         Date
                                                                                                                                      Expanded schedule information
                                                                                                                                           1 Do NOT change any cell location or headings, or overwright formulas

   – Each quarter     Start Phase A                   Start Phase D                                                                        2 Report current best estimate-at-completion, whether or not it exceeds last approved.
                      SRR
                      MDR/SDR (PNAR)
                                                      ORR/FRR
                                                      LRD                                                                             per Quick Look reporting.
                                                                                                                                           3 Report $ in millions to the 1st decimal place; use nominal (real year) $ or note otherwise..
                                                                                                                                           4 When 2 phases occur in one FY, include a comment as to how these were allocated.

   – Each Op Plan     Start Phase B                   Launch/IOC                                                                           5 Fill in future years through FY18 before placing remianing in BTC


     LCC
                      PDR (NAR)
                      Start Phase C
                                                      Start Phase E/FOC
                                                      End Prime Mission                                                               Confidence level information goes
                                                                                                                                           6 Report new obligation authority (NOA) required for each year, not the expected costing.
                                                                                                                                           7 Clearly note any exceptions to NASA's Cost Handbook requirements for this LCC estimate.
                      CDR                             End Ex Mission                                                                       8 List ALL MPAR & APG milestones; do not change any of these milestones.
                      SIR                                                                                                             here                       Completed by project; verified by MD                           Completed by SI-PA&E

• Technical                                                                                                     Current LCC Estimate at Completion

  information is         Estimated confidence level for this LCC:                                                                              Check here if no changes from last quarter:



  provided               Explanation of changes to project scope, schedule, or diret costs since last update:


                                      Explanations of Change goes here
  separately.                                           Prior       FY01      FY02      FY03    FY04    FY05      FY06      FY07      FY08      FY09     FY10     FY11    FY12    FY13    FY14      FY15     FY16    FY17       FY18     BTC TOTAL
                      Full Cost LCC by Year                  0.0        0.0      0.0      0.0     0.0     0.0         0.0       0.0      0.0       0.0     0.0      0.0     0.0     0.0      0.0       0.0     0.0        0.0      0.0    0.0    0.0
   – GAO Quick        To be completed by Mission Directorate:
                      Direct Costs                           0.0        0.0      0.0      0.0     0.0     0.0         0.0       0.0      0.0       0.0     0.0      0.0     0.0     0.0      0.0       0.0     0.0        0.0      0.0    0.0    0.0
     Look Data        Pre Formulation *
                      Formulation (A, B)
                                                                                                                                                                                                                                                 0.0
                                                                                                                                                                                                                                                 0.0
     Collection       Development (C, D)
                         Technology Development
                                                             0.0        0.0      0.0      0.0     0.0     0.0         0.0       0.0      0.0       0.0     0.0      0.0     0.0     0.0      0.0       0.0     0.0        0.0      0.0    0.0    0.0
                                                                                                                                                                                                                                                 0.0

     Instrument          Aircraft/Spacecraft
                         Payload(s)
                                                                                                                                                                                                                                                 0.0
                                                                                                                                                                                                                                                 0.0

     (DCI)               Systems I&T
                         Launch Vehicle/Services
                                                                                                                                                                                                                                                 0.0
                                                                                                                                                                                                                                                 0.0


   – Written
                         Ground Systems                                                                                                                                                                                                          0.0
                         Science/Technology                                                                                                                                                                                                      0.0
                         Other direct project cost                                                                                                                                                                                               0.0
     reports,            Reserves*
                      MO&DA - Prime (E)
                                                                                                                                                                                                                                                 0.0
                                                                                                                                                                                                                                                 0.0

     budget pages     MO&DA - Extended * (E')
                      Closeout (F)
                                                                                                                                                                                                                                                 0.0
                                                                                                                                                                                                                                                 0.0


                      Additional reserves




      New: ‘purple line” provides for reporting of portion of
      cost held for projects by Programs or MDs.
Quarterly Reports to OMB
        Development Projects (no changes)
          External LCC                                 Updated totals by                                                                     % change
               baseline                                quarter                                                                               from baseline
                Project                                                                                                                                                  Q4 FY 2008 Cost and Schedule Update Report to OMB
                Date of Estimate


                Table 1: Summary
                                                                                                          FY08
  Accounting                                                 Base at       Reporting
                                                                                        Q1         Q2            Q3        Q4           Change to


 adjustments    LCC
                                                             KDP-C           Base
                                                                             ($M)       ($M)       ($M)       ($M)
                                                                                                                                     Last Rpt
                                                                                                                                        %
                                                                                                                                                 Base
                                                                                                                                                  %
                                                                                                                                                                                    Reason(s) for change

                Direct                                                          224                                          247                   10%
                Full Cost - Unadjusted                                          266                                          251
                Full Cost - Adjusted to Current Accounting                      228                                          251                   10%

Development     Development Cost                                             ($M)       ($M)       ($M)       ($M)        ($M)          %          %                 Explanation
                Direct                                                          170                                          195                   15%

Cost Baseline   Full Cost - Unadjusted
                Full Cost - Adjusted to Current Accounting
                                                                                204
                                                                                172
                                                                                                                             197
                                                                                                                             197                   15%
                                                                                                                                                                     of changes
                Schedule                                                                                                             months      months
                CDR
    Schedule    Instrument Pre-ship Review
                Launch Readiness Date                                      Dec-2011                                        Jun-12                  6
     Baseline
                                                                                                   Table 2: Estimated Annual Phasing ($M)
                Reporting Baseline (unadjusted      Prior     FY02           FY03       FY04       FY05       FY06        FY07*       FY08       FY09      FY10   FY11    FY12   FY13   FY14   FY15   FY16   FY17   FY18   BTC TOTAL*
                Direct                                               5           10        10           12        30            40          30      25       22     20       5      5      5      5      -      -      -     -   224
Baseline cost      Formulation
                   Development
                                                                     5           10        10
                                                                                                        10
                                                                                                          2
                                                                                                                  30            40          30      25       20     15
                                                                                                                                                                                                                                  27
                                                                                                                                                                                                                                 170
 by phase, &       Op/Disposal
                Indirect                                               -            -          2          2           6          8           6         5
                                                                                                                                                              2
                                                                                                                                                              4
                                                                                                                                                                     5
                                                                                                                                                                     4
                                                                                                                                                                             5
                                                                                                                                                                             1
                                                                                                                                                                                    5
                                                                                                                                                                                    1
                                                                                                                                                                                           5
                                                                                                                                                                                           1
                                                                                                                                                                                                  5
                                                                                                                                                                                                  1
                                                                                                                                                                                                                                 197
                                                                                                                                                                                                                                  42
 accounting.    Full Cost                                            5           10        12           14        36            48          36      30       26     24       6      6      6      6                              266


                Current Quarter                     Prior     FY02           FY03       FY04       FY05       FY06        FY07        FY08       FY09      FY10   FY11    FY12   FY13   FY14   FY15   FY16   FY17   FY18   BTC TOTAL*
                Direct                                               5           10        10           12        30            30          40      30       30     25      10      5      5      5                              247
 Current cost      Formulation
                   Development
                                                                     5           10        10
                                                                                                        10
                                                                                                          2
                                                                                                                  30            30          40      30       30     20       5
                                                                                                                                                                                                                                  27
                                                                                                                                                                                                                                 195
 by phase, &       Op/Disposal
                Indirect                                                                    2            2
                                                                                                                                                                     5       5      5      5      5      5                       222
                                                                                                                                                                                                                                   4
 accounting.    Full Cost                                            5           10        12           14        30            30          40      30       30     25      10      5      5      5      -                       251


                                             Note: Reported information & format developed with OMB.
As Reported to OMB
                         Formulation Projects
                                                                      No project % changes
LCCE &                                                                      reported
schedule    Project                                                                                             Q1 FY 2009 Cost and Schedule Baseline Report to OMB
            Date of Estimate
  only
            Table 1: Preliminary Estimated Lifecycle Cost and Schedule for Project in Formulation*
                                        OMB Base    FY08    FY08      FY08   FY08    FY09
                                         Estimate   Q1       Q2       Q3     Q4       Q1                           Reason(s) for Changes from Last Quarter
            Estimated TDRS LCC             ($M)     ($M)     ($M)     ($M)   ($M)    ($M)
            Direct
            Full Cost - Unadjusted
            Full Cost - Adjusted Base
                                                                                                  Base                           Current
            Estimated Schedule Assumptions
                                                                                                  value                           value
            LRD/IOC/FOC



            Table 2: Contracts with Development Elements
                                                                                                                 Base        Last     Current
                                                                             Project Element(s) this    Base    Contract   Quarter    Contract Reason(s) for Change in Contract
                      Contract Description                 Provider                 Supports           Quarter Value ($M) Value ($M) Value ($M)              Value




                                                                                            Contract totals          $0        $0         $0
                                                                                      % Change from Base            0%
                                                                               % Change from Last Quarter           0%
 Calculation of average change in                                                 Note: Percent changes do not include the addition of new contracts.


 value for those project contracts
 included quarterly reports to OMB
Data ‘rolled up’ for reporting: Roll-in
   of ‘purple line’ only change.
                                                  Prior          FY05          FY06          FY07           FY08         FY09         BTC         TOTAL
             Project Cost Estimate                        0.0           0.0           0.0           0.0            0.0          0.0         0.0       0.0
    Projects in Formulation or Operations need not complete the light blue cells for WBS level 2 cost breakout.
    Direct Costs (by Phase)                               0.0           0.0           0.0           0.0            0.0          0.0         0.0       0.0
    Formulation (A, B)                                    0.0           0.0           0.0           0.0            0.0          0.0         0.0       0.0
                  Pre Formulation *                                                                                                                   0.0
                  Phase A                                                                                                                             0.0
                  Phase B                                                                                                                             0.0
    Development (C, D)                                    0.0           0.0           0.0           0.0            0.0          0.0         0.0       0.0
                  Technology Develop                                                                                                                  0.0
                  Aircraft/Spacecraft                                                                                                                 0.0
                  Payload(s)                                                                                                                          0.0
                  Systems I&T                                                                                                                         0.0
                  Launch Vehicle/Services                                                                                                             0.0
                  Ground Systems                                                                                                                      0.0
                  Science/Technology                                                                                                                  0.0
                  Other direct project cost                                                                                                           0.0

A                 Project-held Dev Reserve
    Operations (E, F)                                     0.0           0.0           0.0           0.0            0.0          0.0         0.0
                                                                                                                                                      0.0
                                                                                                                                                      0.0
                  MO&DA - Prime (E)
                  MO&DA - Extended * (E')                                                                                                             0.0
                  Closeout (F)                                                                                                                        0.0
C   Indirect costs                                        0.0           0.0           0.0           0.0            0.0          0.0         0.0       0.0
    Program held reserves (UFE)
B
         A Project UFE (‘reserves’)
         B Program-held UFE (‘reserves’)                                                     Rolled into reported numbers
                                                                                             on a pro-rated basis.
         C Indirect costs
Funding higher confidence level
                                                                    Section 4 B: Project Cost Estim
• New ‘purple line’ captures                                                                         TOTA

  unallocated future expenses (UFE)           Project baseline           Project Cost Estimate


  which are part of the project baseline                           Direct Costs (by Phase)
                                                                   Formulation (A, B)
  but held by the program or MD.                           =             Pre Formulation *
                                                                         Phase A
• Project is expected to perform to its                                  Phase B

  internal baseline (i.e., with UFE              Managed by        Development (C, D)
                                                                         Technology Develop
  included in its plan, but not additional   project as part of          Aircraft/Spacecraft

  UFE held by program/MD).                        its approved           Payload(s)
                                                                         Systems I&T
                                               plan & internal           Launch Vehicle/Services
• Programs/Mission Directorates can                    baseline          Ground Systems
                                                                         Science/Technology
  allocate UFE to the project if                                         Other direct project cost
  warranted without changing the
  reported baseline.
                                                            +            Project-held Dev UFE
                                                                   Operations (E, F)
                                                                         MO&DA - Prime (E)
                                                Indirect Costs           MO&DA - Extended * (E')
• Helps implement new 1000.5 NPD                                         Closeout (F)

  on Acquisition Policy.                                    +      Indirect costs
                                                                    Program/MD held UFE
    •Project UFE sufficient for 50% CL       UFE held by the
    or as determined by Decision             Program or MD
    Authority.

                            more on UFE & confidence levels, next page
Confidence Levels & UFE
                                                                                Within WBS    UFE (‘reserve’)
• All projects have a                                                           elements      within project’s
  range of cost estimates                                                                     approved plan




                             Probability of completing within cost est.
  with differing levels of




                                                                          90%
  confidence.
• While it’s possible to




                                                                          70%
  assess the additional
  confidence associated


                                                                          50%
  with higher cost                                                                                          UFE (‘reserve’)
  estimates, it’s not                                                                                       within project’s
  possible to know where                                                                                    approved plan
                                                                          30%
  within the project’s
  WBS these costs will
                                                                          10%



  occur.
                                                                                                                  Cost Est. ($)
• Thus, they are
                                                                                       Most Project Agency cost
  unallocated future                                                                   likely plan commitment
  expenses or UFE.
Indirect costs
FY08 PB                             FY04       FY05       FY06       FY07       FY08       Total
                                                                                                    Baseline
Full Cost                            88.7       75.0      132.3      103.5       71.5      471.0
 Direct                              86.4       74.6      119.8       93.3       64.2      438.4
                                                                                                    LCC
 Labor (1000)                         1.0        0.4        1.5        0.9        0.5
 Travel (2100)                        0.0        0.0        0.0        0.0        0.0
 Procurements (3000)                 85.3       74.3      117.5       92.3       63.6
 Service Pool (8020)                       -          -     0.7        0.0             -
 Indirect                             2.3        0.4       12.5       10.2        7.2        32.7
 Corporate G&A (8000)                      -          -     5.6        4.4        3.0
 Prior/PY Center G&A (6551)           0.5        0.4             -          -          -
 Prior/PY Corporate G&A (6552)        1.8             -          -          -          -
 Institutional Investments (8002)          -          -     2.0        2.1        1.4
 Center M&O (8008)                         -          -     4.9        3.7        2.8


 • Indirect costs were included in project budgets starting in
   FY04.
 • FY09 budget removed indirect costs for FY07 and out.*
 • As a result, many projects have ‘legacy’ indirect costs
   still included in the ‘Prior’ years of their NOA runout.
  * Though still part of funds execution through the end of FY08.
Baseline indirect cost adjustments
  Baseline LCC, originally reported
FY08 PB                             FY04       FY05       FY06       FY07       FY08        Total    • Apples-to-apples
Full Cost                             88.7       75.0      132.3      103.5       71.5       471.0
 Direct                               86.4       74.6      119.8       93.3       64.2       438.4
                                                                                                       comparison
                                                                                                       requires adjusting
                                                                                                       the baseline to
Adjusted baseline LCC                                                                                  remove match the
FY08 PB                             FY04       FY05       FY06       FY07       FY08       Total
                                                                                                       changes in indirect
Full Cost                            88.7       75.0      119.8       93.3       64.2      441.1       costs in current
 Direct                              86.4       74.6      119.8       93.3       64.2      438.4       cost estimates.
 Labor (1000)                         1.0        0.4        1.5        0.9        0.5
 Travel (2100)                        0.0        0.0        0.0        0.0        0.0
                                                                                                     • Direct project costs
 Procurements (3000)                 85.3       74.3      117.5       92.3       63.6                  do not change as a
 Service Pool (8020)                       -          -     0.7        0.0             -               result of these
 Indirect                             2.3        0.4             -          -          -      2.7
                                                                                                       adjustments.
 Corporate G&A (8000)                      -          -
 Prior/PY Center G&A (6551)           0.5        0.4
 Prior/PY Corporate G&A (6552)        1.8             -
                                                                 ‘Legacy’ indirect
 Institutional Investments (8002)          -          -          costs in current
 Center M&O (8008)                         -          -          accounting
                                                                 systems
No wonder cost numbers don’t look
            familiar!
Rolled-up elements projects may not see:
• ‘Legacy’ indirect costs (e.g., CM&O) from the full cost
  years (FY04 to FY06) are included in order to be
  consistent with the historical budget amounts.
• Baseline submissions are updated to reflect any
  changes in accounting.
• UFE held for the project is included.
Also note:
• Reporting is broken out annually by the year the New
  Obligation Authority (NOA) is required from Congress,
  not the year the project expects to incur the cost.
• While cost assessments may be done in terms of
  constant dollars (e.g., 2008 $), reported costs include
  expected inflation.
Schedule: 7120.5D milestones
•   Additional milestones
    required for GAO Quick
    Look                                Milestone   Date         Milestone     Date
                                  Start Phase A            Start Phase D
•   We founds that milestone      SRR                      ORR/FRR
    completion was not being      MDR/SDR (PNAR)           LRD
    interpreted the same way      Start Phase B            Launch/IOC
    across the agency, or
    even with in the same         PDR (NAR)                Start Phase E/FOC
    group, resulting in some      Start Phase C            End Prime Mission
    inconsistencies in dates      CDR                      End Ex Mission
    provided.                     SIR


•   As a result, we have
    updated the guidance to
    include definitions for
    completion; as well as
    providing the opportunity
    alternative definitions for
    individual projects.
Explanations of Change
Explanation of changes to project scope, schedule, or diret costs since last update:




  •   Beginning to work with MDs, Centers, and Projects to establish
      greater clarity in reporting. For example:
       – What factors contributed to the changed cost or schedule estimate?
       – Have been any changes to the project’s budget which contributed to
         the change in estimates?
       – Is this a rough first estimate of changes to cost and schedule, or a
         partial estimate, with additional refinement to be reported later?
       – Have there been any changes to the project’s scope or planned
         content?
       – Has any content been moved into or out of the project?

  •   New requirement: Distinguish between internal and external
      factors leading to changes in cost or schedule.
Project contract reporting
Contract Description:   Provider:       Project       Current    Date of   Reason(s) for Change in
                                    Element(s) this   Contract   Current           Value
                                       Supports        Value      (m/y)
Contract 1
Contract 2


  • Each contract with development content is listed
    separately.
  • Contracts are added as they are awarded.
  • Changes in value reported when finalized; estimated
    future changes not included.
  • The average growth in the value of all reported contracts
    for the project provides the basis for estimating contract
    cost growth.
  • Still being worked: Specific guidance on determining
    which contracts require reporting and how to distinguish
    between changes in contract content & cost growth.
Portfolio Cost & Schedule
               Reporting

• PART & PAR metrics reflect the combined
  performance of projects within specified
  themes or divisions.
• ‘High Risk’ Metrics reflect the combined
  performance of projects in development
  entering reporting as of 2008.
• Addressed as a weighted average of the
  performance of individual projects in the
  group.

Contenu connexe

En vedette

Le roy ward
Le roy wardLe roy ward
Le roy wardNASAPMC
 
Dickey.alan
Dickey.alanDickey.alan
Dickey.alanNASAPMC
 
Dumbacher
DumbacherDumbacher
DumbacherNASAPMC
 
Inter fellous freilich
Inter fellous freilichInter fellous freilich
Inter fellous freilichNASAPMC
 
Costello kenneth
Costello kennethCostello kenneth
Costello kennethNASAPMC
 
Crocker.lori
Crocker.loriCrocker.lori
Crocker.loriNASAPMC
 
Newhouse capability modeling v2
Newhouse capability modeling v2Newhouse capability modeling v2
Newhouse capability modeling v2NASAPMC
 
Chris.hardcastle
Chris.hardcastleChris.hardcastle
Chris.hardcastleNASAPMC
 
K gallagher tosborne
K gallagher tosborneK gallagher tosborne
K gallagher tosborneNASAPMC
 
Cathy.carr
Cathy.carrCathy.carr
Cathy.carrNASAPMC
 
Newman.steve
Newman.steveNewman.steve
Newman.steveNASAPMC
 
Elliott.k.liang.a.sauser.b
Elliott.k.liang.a.sauser.bElliott.k.liang.a.sauser.b
Elliott.k.liang.a.sauser.bNASAPMC
 
Glenn.perez
Glenn.perezGlenn.perez
Glenn.perezNASAPMC
 
Patterson.donna
Patterson.donnaPatterson.donna
Patterson.donnaNASAPMC
 
Michael.hazen
Michael.hazenMichael.hazen
Michael.hazenNASAPMC
 
Gwyn.smith
Gwyn.smithGwyn.smith
Gwyn.smithNASAPMC
 
Leon.j.douglas.d
Leon.j.douglas.dLeon.j.douglas.d
Leon.j.douglas.dNASAPMC
 
Gena.henderson
Gena.hendersonGena.henderson
Gena.hendersonNASAPMC
 

En vedette (20)

Le roy ward
Le roy wardLe roy ward
Le roy ward
 
Dickey.alan
Dickey.alanDickey.alan
Dickey.alan
 
Dumbacher
DumbacherDumbacher
Dumbacher
 
Inter fellous freilich
Inter fellous freilichInter fellous freilich
Inter fellous freilich
 
Costello kenneth
Costello kennethCostello kenneth
Costello kenneth
 
Crocker.lori
Crocker.loriCrocker.lori
Crocker.lori
 
Newhouse capability modeling v2
Newhouse capability modeling v2Newhouse capability modeling v2
Newhouse capability modeling v2
 
Chris.hardcastle
Chris.hardcastleChris.hardcastle
Chris.hardcastle
 
K gallagher tosborne
K gallagher tosborneK gallagher tosborne
K gallagher tosborne
 
B leach
B leachB leach
B leach
 
Cathy.carr
Cathy.carrCathy.carr
Cathy.carr
 
Lucht
LuchtLucht
Lucht
 
Newman.steve
Newman.steveNewman.steve
Newman.steve
 
Elliott.k.liang.a.sauser.b
Elliott.k.liang.a.sauser.bElliott.k.liang.a.sauser.b
Elliott.k.liang.a.sauser.b
 
Glenn.perez
Glenn.perezGlenn.perez
Glenn.perez
 
Patterson.donna
Patterson.donnaPatterson.donna
Patterson.donna
 
Michael.hazen
Michael.hazenMichael.hazen
Michael.hazen
 
Gwyn.smith
Gwyn.smithGwyn.smith
Gwyn.smith
 
Leon.j.douglas.d
Leon.j.douglas.dLeon.j.douglas.d
Leon.j.douglas.d
 
Gena.henderson
Gena.hendersonGena.henderson
Gena.henderson
 

Similaire à Zimmerman.mary

Capex opex
Capex opexCapex opex
Capex opexRaju_p1
 
Pollitt.julie
Pollitt.juliePollitt.julie
Pollitt.julieNASAPMC
 
Petze.lara
Petze.laraPetze.lara
Petze.laraNASAPMC
 
Data extraction and retraction in bpc bi
Data extraction and retraction in bpc biData extraction and retraction in bpc bi
Data extraction and retraction in bpc bivikram2355
 
Data extraction and retraction bpc bi
Data extraction and retraction bpc  biData extraction and retraction bpc  bi
Data extraction and retraction bpc bisakthirobotic
 
Zimmerman.marybeth
Zimmerman.marybethZimmerman.marybeth
Zimmerman.marybethNASAPMC
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)Glen Alleman
 
Operational analysis review_jan2010_p2c2
Operational analysis review_jan2010_p2c2Operational analysis review_jan2010_p2c2
Operational analysis review_jan2010_p2c2Jim Kendrick
 
SAP BPC 10.1 training online | SAP BPC Training in Hyderabad
SAP BPC 10.1 training online | SAP BPC Training in HyderabadSAP BPC 10.1 training online | SAP BPC Training in Hyderabad
SAP BPC 10.1 training online | SAP BPC Training in HyderabadN Benchmark IT Solutions
 
SAE2 Application Modernization Process
SAE2 Application Modernization ProcessSAE2 Application Modernization Process
SAE2 Application Modernization ProcessLawrence Wilkes
 
Earned Value + Agile = Success
Earned Value + Agile = SuccessEarned Value + Agile = Success
Earned Value + Agile = SuccessGlen Alleman
 

Similaire à Zimmerman.mary (20)

Capex opex
Capex opexCapex opex
Capex opex
 
D11 Define Review
D11 Define ReviewD11 Define Review
D11 Define Review
 
D11 Define Review
D11 Define ReviewD11 Define Review
D11 Define Review
 
Pollitt.julie
Pollitt.juliePollitt.julie
Pollitt.julie
 
Sambit Resume
Sambit ResumeSambit Resume
Sambit Resume
 
Apd and bpc
Apd and bpcApd and bpc
Apd and bpc
 
ENR467723
ENR467723ENR467723
ENR467723
 
Symons
SymonsSymons
Symons
 
Petze.lara
Petze.laraPetze.lara
Petze.lara
 
Data extraction and retraction in bpc bi
Data extraction and retraction in bpc biData extraction and retraction in bpc bi
Data extraction and retraction in bpc bi
 
Data extraction and retraction bpc bi
Data extraction and retraction bpc  biData extraction and retraction bpc  bi
Data extraction and retraction bpc bi
 
Zimmerman.marybeth
Zimmerman.marybethZimmerman.marybeth
Zimmerman.marybeth
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
 
Operational analysis review_jan2010_p2c2
Operational analysis review_jan2010_p2c2Operational analysis review_jan2010_p2c2
Operational analysis review_jan2010_p2c2
 
Schulte
SchulteSchulte
Schulte
 
SAP BPC 10.1 training online | SAP BPC Training in Hyderabad
SAP BPC 10.1 training online | SAP BPC Training in HyderabadSAP BPC 10.1 training online | SAP BPC Training in Hyderabad
SAP BPC 10.1 training online | SAP BPC Training in Hyderabad
 
Resume
ResumeResume
Resume
 
SAE2 Application Modernization Process
SAE2 Application Modernization ProcessSAE2 Application Modernization Process
SAE2 Application Modernization Process
 
Rexx Shih
Rexx ShihRexx Shih
Rexx Shih
 
Earned Value + Agile = Success
Earned Value + Agile = SuccessEarned Value + Agile = Success
Earned Value + Agile = Success
 

Plus de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 

Plus de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Dernier

Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piececharlottematthew16
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embeddingZilliz
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Manik S Magar
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Wonjun Hwang
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clashcharlottematthew16
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsRizwan Syed
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostLeverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostZilliz
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024Lorenzo Miniero
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxNavinnSomaal
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 

Dernier (20)

Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piece
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embedding
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clash
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL Certs
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostLeverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptx
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 

Zimmerman.mary

  • 1. NASA External Cost/Schedule Performance Reporting: Update on How Changes are being Folded in Mary Beth Zimmerman February 24, 2009
  • 2. What’s New Since the last PM Challenge? • Two new reports – GAO Quick Look semi-annual reviews (Julie Pollitt’s presentation covers in detail) – ‘High Risk’ Metrics for OMB (Riva Svarcas’ presentation covers in detail) • Updated NASA policies and process affecting reporting – Distinction between margin held by projects and that held by programs or Mission Directorates – Review of quarterly reports to OMB by projects and centers – Update of quarterly data for operating plan changes • Distinguishing between internal and external reasons for reported cost and schedule changes. • Reporting will continue to evolve as additional details are worked with NASA’s stakeholders. Key items being refined: – Contract cost growth -- Milestone completion dates – Changes in content & scope -- Explanations of change – Confidence Levels
  • 3. Folding Changes into the Process Report template + Data template Data template Report templates Reporting Quarterly Any MDs prepare baseline data thresholds threshold established updates breached? notifications & form MDs reports OMB quarterly Data template MPAR Operating Plan GAO Quick Look (cost & schedule sections) data updates ‘High Risk’ metrics
  • 4. Coordinated Data Management • Integrated quarterly data call to Mission Directorates includes: – A common data template and guidance serves as a basis for the cost and schedule information required in annual, semi-annual, and quarterly external reports. – Templates for any required baseline or threshold reports. – Guidance for completing each. – New policy being worked into quarterly process: projects, centers & Mission Directorates will sign off on quarterly reports to OMB. • Coordination of quarterly data call with other reporting elements. – Q1 report is coordinated with annual reporting (MPAR). – A GAO template is used to collect additional information on technology. – Lifecycle cost estimate (LCCE) changes reported in Agency Operation Plans to Congress will be based on updates to quarterly reports. • Coordination with Agency Baseline Program Review (BPI) – Distinguishes between cost margin held by the project and held for the project by the Program or Mission Directorate. – Coordination with cost and schedule data from KDPs. – Data call is being transitioned from PA&E to OCE to merge with BPR data collection.
  • 5. Data Requirements Project Cost Contracts Phase Pending awards Year Cost growth WBS2 Explanation of Change Budget line Changes in content Project Schedule Reasons for change Key milestone Technical progress Interim milestones Technical maturity Project Content Design stability Scope Project Risk Parameters Confidence level Critical technologies Backup technologies Blue text: New since last PM Challenge
  • 6. Baseline Reports: No Changes • Baseline Reports are prepared for projects subject to MPAR reporting to Congress or NSPD-49 reporting to OMB when: – A project in formulation awards contract w/ development content =>$50M (for OMB only). – A project with a lifecycle cost estimate (LCCE) of $250M or more receives KDP-C approval to enter Phase C (for OMB & Congress). • Baseline Report includes – baseline numbers subject to threshold requirements. • Projects in development: • Projects in formulation – Lifecycle cost – Ave. contract value – Development cost – Key schedule milestone – additional information as required by Congress or OMB. • Baseline Reports look similar to the project pages in the Agency’s budget.
  • 7. Data Template Projects in Formulation NASA Formulation Cost and Contract Data Template Rev 3 Person completing this form: Project Name: Most recent budget/op plan assumed: 6-digit project code Date of Estimate: Schedule Assumptions Expanded Milestone Date System Design Review schedule Start Phase B NAR/PDR milestone Start Phase C Start Phase D information for LRD/IOC GAO Quick Current LCC Estimate-At-Completion Additional assumptions required to understand ROM LCC cost estimate: Look Explanation of changes to direct project costs since last update: Explanation of changes to indirect project costs since last update: Prior FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15 BTC TOTAL Project LCC by Year 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 To be completed by Mission Directorate: Direct Costs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 No WBS Pre Formulation * Formulation (A, B) 0.0 0.0 elements at Development (C, D) Operations Prime (E) 0.0 0.0 this stage Operations Extended (E') Closeout (F) 0.0 0.0 Will be updated by PA&E based on OCFO rates: Indirect costs assigned to project 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Center M&O 0.0 Corporate G&A 0.0 Other indirect costs 0.0 Contract Description: Provider: Project Element(s) this Supports Current Date of Current Reason(s) for Change in Value Contract Contract Value (month/year) ($M) information
  • 8. Data Template Projects in Development NASA Development Project Cost & Schedule Data Template (Rev 5) • Filled out for: Person completing this form: Budget/Op Plan assumed: Project Name: Date of Estimate: 6-digit project code – Each baseline Current Estimated Schedule Directions Milestone Date Milestone Date Other Milestones Date Expanded schedule information 1 Do NOT change any cell location or headings, or overwright formulas – Each quarter Start Phase A Start Phase D 2 Report current best estimate-at-completion, whether or not it exceeds last approved. SRR MDR/SDR (PNAR) ORR/FRR LRD per Quick Look reporting. 3 Report $ in millions to the 1st decimal place; use nominal (real year) $ or note otherwise.. 4 When 2 phases occur in one FY, include a comment as to how these were allocated. – Each Op Plan Start Phase B Launch/IOC 5 Fill in future years through FY18 before placing remianing in BTC LCC PDR (NAR) Start Phase C Start Phase E/FOC End Prime Mission Confidence level information goes 6 Report new obligation authority (NOA) required for each year, not the expected costing. 7 Clearly note any exceptions to NASA's Cost Handbook requirements for this LCC estimate. CDR End Ex Mission 8 List ALL MPAR & APG milestones; do not change any of these milestones. SIR here Completed by project; verified by MD Completed by SI-PA&E • Technical Current LCC Estimate at Completion information is Estimated confidence level for this LCC: Check here if no changes from last quarter: provided Explanation of changes to project scope, schedule, or diret costs since last update: Explanations of Change goes here separately. Prior FY01 FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18 BTC TOTAL Full Cost LCC by Year 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 – GAO Quick To be completed by Mission Directorate: Direct Costs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Look Data Pre Formulation * Formulation (A, B) 0.0 0.0 Collection Development (C, D) Technology Development 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Instrument Aircraft/Spacecraft Payload(s) 0.0 0.0 (DCI) Systems I&T Launch Vehicle/Services 0.0 0.0 – Written Ground Systems 0.0 Science/Technology 0.0 Other direct project cost 0.0 reports, Reserves* MO&DA - Prime (E) 0.0 0.0 budget pages MO&DA - Extended * (E') Closeout (F) 0.0 0.0 Additional reserves New: ‘purple line” provides for reporting of portion of cost held for projects by Programs or MDs.
  • 9. Quarterly Reports to OMB Development Projects (no changes) External LCC Updated totals by % change baseline quarter from baseline Project Q4 FY 2008 Cost and Schedule Update Report to OMB Date of Estimate Table 1: Summary FY08 Accounting Base at Reporting Q1 Q2 Q3 Q4 Change to adjustments LCC KDP-C Base ($M) ($M) ($M) ($M) Last Rpt % Base % Reason(s) for change Direct 224 247 10% Full Cost - Unadjusted 266 251 Full Cost - Adjusted to Current Accounting 228 251 10% Development Development Cost ($M) ($M) ($M) ($M) ($M) % % Explanation Direct 170 195 15% Cost Baseline Full Cost - Unadjusted Full Cost - Adjusted to Current Accounting 204 172 197 197 15% of changes Schedule months months CDR Schedule Instrument Pre-ship Review Launch Readiness Date Dec-2011 Jun-12 6 Baseline Table 2: Estimated Annual Phasing ($M) Reporting Baseline (unadjusted Prior FY02 FY03 FY04 FY05 FY06 FY07* FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18 BTC TOTAL* Direct 5 10 10 12 30 40 30 25 22 20 5 5 5 5 - - - - 224 Baseline cost Formulation Development 5 10 10 10 2 30 40 30 25 20 15 27 170 by phase, & Op/Disposal Indirect - - 2 2 6 8 6 5 2 4 5 4 5 1 5 1 5 1 5 1 197 42 accounting. Full Cost 5 10 12 14 36 48 36 30 26 24 6 6 6 6 266 Current Quarter Prior FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18 BTC TOTAL* Direct 5 10 10 12 30 30 40 30 30 25 10 5 5 5 247 Current cost Formulation Development 5 10 10 10 2 30 30 40 30 30 20 5 27 195 by phase, & Op/Disposal Indirect 2 2 5 5 5 5 5 5 222 4 accounting. Full Cost 5 10 12 14 30 30 40 30 30 25 10 5 5 5 - 251 Note: Reported information & format developed with OMB.
  • 10. As Reported to OMB Formulation Projects No project % changes LCCE & reported schedule Project Q1 FY 2009 Cost and Schedule Baseline Report to OMB Date of Estimate only Table 1: Preliminary Estimated Lifecycle Cost and Schedule for Project in Formulation* OMB Base FY08 FY08 FY08 FY08 FY09 Estimate Q1 Q2 Q3 Q4 Q1 Reason(s) for Changes from Last Quarter Estimated TDRS LCC ($M) ($M) ($M) ($M) ($M) ($M) Direct Full Cost - Unadjusted Full Cost - Adjusted Base Base Current Estimated Schedule Assumptions value value LRD/IOC/FOC Table 2: Contracts with Development Elements Base Last Current Project Element(s) this Base Contract Quarter Contract Reason(s) for Change in Contract Contract Description Provider Supports Quarter Value ($M) Value ($M) Value ($M) Value Contract totals $0 $0 $0 % Change from Base 0% % Change from Last Quarter 0% Calculation of average change in Note: Percent changes do not include the addition of new contracts. value for those project contracts included quarterly reports to OMB
  • 11. Data ‘rolled up’ for reporting: Roll-in of ‘purple line’ only change. Prior FY05 FY06 FY07 FY08 FY09 BTC TOTAL Project Cost Estimate 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Projects in Formulation or Operations need not complete the light blue cells for WBS level 2 cost breakout. Direct Costs (by Phase) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Formulation (A, B) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Pre Formulation * 0.0 Phase A 0.0 Phase B 0.0 Development (C, D) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Technology Develop 0.0 Aircraft/Spacecraft 0.0 Payload(s) 0.0 Systems I&T 0.0 Launch Vehicle/Services 0.0 Ground Systems 0.0 Science/Technology 0.0 Other direct project cost 0.0 A Project-held Dev Reserve Operations (E, F) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 MO&DA - Prime (E) MO&DA - Extended * (E') 0.0 Closeout (F) 0.0 C Indirect costs 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Program held reserves (UFE) B A Project UFE (‘reserves’) B Program-held UFE (‘reserves’) Rolled into reported numbers on a pro-rated basis. C Indirect costs
  • 12. Funding higher confidence level Section 4 B: Project Cost Estim • New ‘purple line’ captures TOTA unallocated future expenses (UFE) Project baseline Project Cost Estimate which are part of the project baseline Direct Costs (by Phase) Formulation (A, B) but held by the program or MD. = Pre Formulation * Phase A • Project is expected to perform to its Phase B internal baseline (i.e., with UFE Managed by Development (C, D) Technology Develop included in its plan, but not additional project as part of Aircraft/Spacecraft UFE held by program/MD). its approved Payload(s) Systems I&T plan & internal Launch Vehicle/Services • Programs/Mission Directorates can baseline Ground Systems Science/Technology allocate UFE to the project if Other direct project cost warranted without changing the reported baseline. + Project-held Dev UFE Operations (E, F) MO&DA - Prime (E) Indirect Costs MO&DA - Extended * (E') • Helps implement new 1000.5 NPD Closeout (F) on Acquisition Policy. + Indirect costs Program/MD held UFE •Project UFE sufficient for 50% CL UFE held by the or as determined by Decision Program or MD Authority. more on UFE & confidence levels, next page
  • 13. Confidence Levels & UFE Within WBS UFE (‘reserve’) • All projects have a elements within project’s range of cost estimates approved plan Probability of completing within cost est. with differing levels of 90% confidence. • While it’s possible to 70% assess the additional confidence associated 50% with higher cost UFE (‘reserve’) estimates, it’s not within project’s possible to know where approved plan 30% within the project’s WBS these costs will 10% occur. Cost Est. ($) • Thus, they are Most Project Agency cost unallocated future likely plan commitment expenses or UFE.
  • 14. Indirect costs FY08 PB FY04 FY05 FY06 FY07 FY08 Total Baseline Full Cost 88.7 75.0 132.3 103.5 71.5 471.0 Direct 86.4 74.6 119.8 93.3 64.2 438.4 LCC Labor (1000) 1.0 0.4 1.5 0.9 0.5 Travel (2100) 0.0 0.0 0.0 0.0 0.0 Procurements (3000) 85.3 74.3 117.5 92.3 63.6 Service Pool (8020) - - 0.7 0.0 - Indirect 2.3 0.4 12.5 10.2 7.2 32.7 Corporate G&A (8000) - - 5.6 4.4 3.0 Prior/PY Center G&A (6551) 0.5 0.4 - - - Prior/PY Corporate G&A (6552) 1.8 - - - - Institutional Investments (8002) - - 2.0 2.1 1.4 Center M&O (8008) - - 4.9 3.7 2.8 • Indirect costs were included in project budgets starting in FY04. • FY09 budget removed indirect costs for FY07 and out.* • As a result, many projects have ‘legacy’ indirect costs still included in the ‘Prior’ years of their NOA runout. * Though still part of funds execution through the end of FY08.
  • 15. Baseline indirect cost adjustments Baseline LCC, originally reported FY08 PB FY04 FY05 FY06 FY07 FY08 Total • Apples-to-apples Full Cost 88.7 75.0 132.3 103.5 71.5 471.0 Direct 86.4 74.6 119.8 93.3 64.2 438.4 comparison requires adjusting the baseline to Adjusted baseline LCC remove match the FY08 PB FY04 FY05 FY06 FY07 FY08 Total changes in indirect Full Cost 88.7 75.0 119.8 93.3 64.2 441.1 costs in current Direct 86.4 74.6 119.8 93.3 64.2 438.4 cost estimates. Labor (1000) 1.0 0.4 1.5 0.9 0.5 Travel (2100) 0.0 0.0 0.0 0.0 0.0 • Direct project costs Procurements (3000) 85.3 74.3 117.5 92.3 63.6 do not change as a Service Pool (8020) - - 0.7 0.0 - result of these Indirect 2.3 0.4 - - - 2.7 adjustments. Corporate G&A (8000) - - Prior/PY Center G&A (6551) 0.5 0.4 Prior/PY Corporate G&A (6552) 1.8 - ‘Legacy’ indirect Institutional Investments (8002) - - costs in current Center M&O (8008) - - accounting systems
  • 16. No wonder cost numbers don’t look familiar! Rolled-up elements projects may not see: • ‘Legacy’ indirect costs (e.g., CM&O) from the full cost years (FY04 to FY06) are included in order to be consistent with the historical budget amounts. • Baseline submissions are updated to reflect any changes in accounting. • UFE held for the project is included. Also note: • Reporting is broken out annually by the year the New Obligation Authority (NOA) is required from Congress, not the year the project expects to incur the cost. • While cost assessments may be done in terms of constant dollars (e.g., 2008 $), reported costs include expected inflation.
  • 17. Schedule: 7120.5D milestones • Additional milestones required for GAO Quick Look Milestone Date Milestone Date Start Phase A Start Phase D • We founds that milestone SRR ORR/FRR completion was not being MDR/SDR (PNAR) LRD interpreted the same way Start Phase B Launch/IOC across the agency, or even with in the same PDR (NAR) Start Phase E/FOC group, resulting in some Start Phase C End Prime Mission inconsistencies in dates CDR End Ex Mission provided. SIR • As a result, we have updated the guidance to include definitions for completion; as well as providing the opportunity alternative definitions for individual projects.
  • 18. Explanations of Change Explanation of changes to project scope, schedule, or diret costs since last update: • Beginning to work with MDs, Centers, and Projects to establish greater clarity in reporting. For example: – What factors contributed to the changed cost or schedule estimate? – Have been any changes to the project’s budget which contributed to the change in estimates? – Is this a rough first estimate of changes to cost and schedule, or a partial estimate, with additional refinement to be reported later? – Have there been any changes to the project’s scope or planned content? – Has any content been moved into or out of the project? • New requirement: Distinguish between internal and external factors leading to changes in cost or schedule.
  • 19. Project contract reporting Contract Description: Provider: Project Current Date of Reason(s) for Change in Element(s) this Contract Current Value Supports Value (m/y) Contract 1 Contract 2 • Each contract with development content is listed separately. • Contracts are added as they are awarded. • Changes in value reported when finalized; estimated future changes not included. • The average growth in the value of all reported contracts for the project provides the basis for estimating contract cost growth. • Still being worked: Specific guidance on determining which contracts require reporting and how to distinguish between changes in contract content & cost growth.
  • 20. Portfolio Cost & Schedule Reporting • PART & PAR metrics reflect the combined performance of projects within specified themes or divisions. • ‘High Risk’ Metrics reflect the combined performance of projects in development entering reporting as of 2008. • Addressed as a weighted average of the performance of individual projects in the group.