1. US Army Corps of Engineers
BUILDING STRONG®
U.S. Army Corps of Engineers Norfolk District
Corps Budget Process,
James River, Virginia
Richard Klein, P.E.
Programs and Civil Works Branch July 18, 2014
3. BUILDING STRONG®
HQ Provides Budget Guidance ( Mar )
HQ Review & Approval
( May -Jun )
Budget Presented to Sec. Army (Jul - Aug )
OMB Passback
( Nov )
Budget Submitted to OMB ( Sep )
President’s Budget to Congress ( Feb )
Field Offices Develop
Program Requirements
( Mar - Apr )
Appropriations Bills
( Jul - Sep )
President Signs Approp. Bill
( Sep - Oct )
OMB Provides Budget Guidance ( Jan )
Funding Alloc. To Field Offices ( Oct - Dec )
Budget Resolutions
4. 4 BUILDING STRONG®
Budget Status
•
FY 2014: President’s Budget released April 2013; Continuing Resolutions through 15 January 2014; the FY2014 Omnibus Bill became Public Law No. 113-76 on 17 January 2014. FY14 funding provided via Work Plan.
•
FY 2015: President’s Budget released 4 March 2014. Energy & Water Development Appropriations Bill, 2015 (H.R. 4923) passed the House 253-170 on 10 July 2014.
•
FY 2016: Budget Guidance (EC) issued March 2014; Budget development in progress.
5. 5 BUILDING STRONG®
New for FY 2014
Water Resources Reform and Development Act of 2014, enacted 11 June 2014 as P.L. No. 113-121
- Increases funding from the Harbor Maintenance Trust Fund (Sec. 2101)
- Criteria for use of the funds (Sec. 2102)
- Assessment of Harbors and Inland Harbors (Sec. 2102)
6. BUILDING STRONG®
Budget Prioritization Factors
Operations and Maintenance (O&M)
►Essential O&M Infrastructure
•Lock, dams, bridges
►Risk & Reliability
•Navigation safety
►Commercial waterborne traffic
•Tonnages – James River 5-yr average = 2.9 mil
►Other Considerations: Dam Safety, Public Safety, Critical Harbor of Refuge, Subsistence Harbor, National Security, etc.
7. 7 BUILDING STRONG®
Norfolk District O&M Funding
FY 13 President’s Budget $23.5 M
FY 13 Allocation $21.9M
FY 13 Supplemental Allocation $24.8M
FY 14 President’s Budget $26.6 M
FY 14 Allocation $26.3M
FY 15 President’s Budget $27.8M
FY 15 Final or Work Plan TBD
8. 8 BUILDING STRONG®
Key Takeaways
Action on FY 2015 Budget is with the Congress
Changes coming from the 2014 WRRDA yet to be implemented
Watershed-based Budgeting proposed for FY 2017 implementation
9. BUILDING STRONG®
Questions/Comments?