- Inform you about the work that has been completed, is under way and planned between now and October 2016
- Present the proposal retained for the anti-noise walls on the South Shore
- Answer questions, find possible solutions and discuss the issues
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
Good neighbourly relations committee City of Brossard - May 4, 2016
1. Good Neighbourly Relations Committee Meeting
City of Brossard: May 4, 2016
New Champlain Bridge Corridor Project
Centre communautaire Nathalie Croteau
2. New Champlain Bridge Corridor Project 2
Committee Members
Residents
Luis Oscar Corrales
Ginette Dufresne
Marc Gagné
Nabil Halouani
Jacques Picard
Jaime Reis
Marc Turcotte – Representative from a community organization
Éric Jutras – Member of the business community
Partners
Dan Genest – The Signature on the Saint-Laurent team
Benoît Fillion – City of Brossard
Vincent Jarry – Infrastructure Canada
3. New Champlain Bridge Corridor Project
Scope:
• Based on similar initiatives in other large-scale projects, creation of the Good
Neighbourly Relations Committee (hereafter the “Committee”) to favour exchanges
between SSL and residents, merchants and community organizations
• The primary purpose of the Committee is to proactively share all information on:
Work completed, underway and to come
Anticipated impacts
Associated mitigation measures
• The meetings shall serve to:
Answer questions
Find possible solutions for the various issues that are raised
Engage in discussions in an open and transparent manner
3
4. New Champlain Bridge Corridor Project
SSL’s commitment
SSL is committed to:
• Listening to Committee members, answering their questions and
concerns, and providing them with accurate and up-to-date
information throughout the project
• Making the required information available to residents, merchants
and community organizations as well as making such information
easily accessible on various platforms
• Searching for solutions to respond to the concerns raised
by the Committee
4
5. New Champlain Bridge Corridor Project
1. Inform you about the work that has been completed, is
under way and planned between now and October 2016
2. Present the proposal retained for the anti-noise walls on
the South Shore
3. Answer questions, find possible solutions and discuss
the issues
Aim of the meeting
5
6. New Champlain Bridge Corridor Project
Agenda
6
Series Item Duration Time
1. Opening 10 min. 7:00 to 7:10 pm
2.
Work completed, underway and to come
• Eastern approach area
• Hwy-10 area
• Cable-stayed bridge area
30 min. 7:10 to 7:40 pm
3. Committee question period 10 min. 7:40 to 7:50 pm
4. Anti-noise walls 30 min. 7:50 to 8:20 pm
5. Committee question period 10 min. 8:20 to 8:30 pm
6. Varia 10 min. 8:30 to 8:40 pm
7. General public question period 30 min. 8:40 to 9:10 pm
8. Adjournment: next meeting and topic 5 min. 9:10 to 9:15 pm
8. New Champlain Bridge Corridor Project
Overview of completed work
8
• Pile caisson drilling and concreting in
the East Approach: 61 out of 78
(78% complete)
• Start of work on footing forms in the
East Approach
• Abutment started
• Relocation of water main and
other utilities
9. New Champlain Bridge Corridor Project
• Easy winter: solid progress for work in general in the East Approach
• Relocation of water main: excellent cooperation by the City of
Brossard and the City of Longueuil
• Work site facilities basically completed: concerns with respect to
access to the work site and motorist safety
• Very few complaints
Completed work: observations
9
10. New Champlain Bridge Corridor Project
Complaints handling
(early June 2015 to April 29, 2016)
Topic
Sector
Brossard
Closed Open Total
Noise 4 - 4
Air quality 0 - 0
Traffic 1 - 1
Vibrations 1 - 1
Brightness 1 - 1
Other 6 1 7
Total 13 1 14
10
11. New Champlain Bridge Corridor Project
Main priorities for the coming months
South Shore
12. New Champlain Bridge Corridor Project
1 2 3
Location of areas
City of Brossard
Gaétan Laberge and Wellington
12
13. New Champlain Bridge Corridor Project
Highway 10
• Soil management and earthworks
East Approach of the new Champlain Bridge
• Construction of footings and pier bases
• Construction of eastern abutment
• Start of installation of prefabricated segments of piers and pier caps
Cable-stayed bridge
• Construction of main pylon and rear span
South Shore
Priorities: May to October 2016
13
14. New Champlain Bridge Corridor Project
Description of activity
Approximate duration of work
Planned work period
Legend: Work and impacts
• Traffic and public transportation:
• Proximity of residential areas:
• Boating:
• Bike paths:
Minor impact
Medium impact
Major impact
Indication by level colour code
14
15. New Champlain Bridge Corridor Project
Key activities under way and to come
East Approach
Design and planning underway so modifications are possible
16. New Champlain Bridge Corridor Project
Objective: Construction of East Approach of the new Champlain Bridge
Upcoming work:
• Completion of pile caissons
• Forming and concreting of footings and pier bases
• Construction of eastern abutment columns and pier caps
• Placement of prefabricated segments of piers and pier caps
Approach:
• Daytime work, to the extent possible, when the impacts (especially noise
levels) are significant
• Nighttime work, to the extent possible, when the impacts on daytime traffic
are too significant
East Approach area
16
17. New Champlain Bridge Corridor Project
Nov
2015
May
2016
Nov
2016
May
2017
Nov
2017
Nov
2018
May
2018
Construction
of footings
Installation of piers and
pier caps
Assembly of superstructure
and deck
Finishing work
East Approach: Timetable
17
Feb
2016
Aug
2016
Feb
2017
Aug
2017
Feb
2018
Aug
2018
18. New Champlain Bridge Corridor Project
Work and impacts: East Approach
Pile caisson drilling and concreting
and cofferdam placement
Duration: five months
Projected period: January to May 2016
18
40-metre navigational
corridor
19. New Champlain Bridge Corridor Project
Work and impacts: East Approach
Forming and concreting of footings and pier bases
Duration: six months
Projected period: April to September 2016
19
40-metre navigational
corridor
20. New Champlain Bridge Corridor Project
Work and impacts: East Approach
Construction of East Abutment
Duration: seven months
Projected period: January to July 2016
20
21. New Champlain Bridge Corridor Project
Work and impacts: East Approach
Placement of prefabricated segments
of piers and pier caps
Duration: one year
Projected period: August 2016 to August 2017
21
22. New Champlain Bridge Corridor Project
Work and
impacts: La
Riveraine bike
path
22
Detour of La Riveraine
bike path until summer 2019
DETOUR OF
LA RIVERAINE
BIKE PATH
23. New Champlain Bridge Corridor Project
Work and impacts:
East Approach work site exit
23
Worker
parking
Daily flow of traffic
• 20 heavy trucks
•150 light vehicles
24. New Champlain Bridge Corridor Project
Key activities under way and to come
Highway 10
Design and planning under way
so modifications are possible
25. New Champlain Bridge Corridor Project
Highway 10 area
25
Objective: Area reserved for soil management for the work site and preparatory
work for the reconfiguration of highway links
Upcoming work:
• Soil storage and earthworks at the eastern abutment
• Creation of a retaining basin for permanent drainage
• Installation of permanent anti-noise walls
Approach:
• Daytime work, to the extent possible, when the impacts (especially noise
levels) are significant
• Night-time trucking from the West Approach to the East Approach
26. New Champlain Bridge Corridor Project
Work and impacts: Highway 10
Soil management and creation of a retaining basin
Duration: duration of project
Projected period: 2016 to 2019
26
27. New Champlain Bridge Corridor Project
Work and impacts: Highway 10
Earthworks at the eastern abutment
Duration: one year
Projected period: April 2016 to spring 2017
27
28. New Champlain Bridge Corridor Project
Key activities under way and to come
Cable-stayed bridge
Design and planning underway so modifications are possible
29. New Champlain Bridge Corridor Project
Cable-stayed bridge: Timetable
29
2. Pylon foundations
October 2015 to April 20161. Jetty
August to October 2015
6. Main span
March 2017 to June 2018
3. Rear span
November 2015 to March 2017
5. Upper pylon
September 2016 to
June 2017
4. Lower pylon
May to September 2016
31. New Champlain Bridge Corridor Project
Work and impacts:
Seaway dike bike path
31
Occasional closures starting this summer
Final closure: fall 2016 or spring 2017 (TBC) to December 2018
33. New Champlain Bridge Corridor Project
Anticipated impacts
• Road, bicycle and water traffic
• Noise
• Air quality
33
34. New Champlain Bridge Corridor Project
Traffic
• JCCBI blitz from May 6 to 9: complete closure of
northbound Hwy-15 North
• Fall JCCBI blitz: four weekends in September
and October
• Minimal impact over the next six months: shoulder
closure and lane deviation
• Upcoming major disruptions: installation of
superstructure and deck above Highway
132 traffic lanes
34
35. New Champlain Bridge Corridor Project
Bike traffic
35
• Detour of La Riveraine bike path until summer 2019
• Closure of Seaway dike bike path between Champlain
Bridge and the St-Lambert locks starting in all 2016 or
spring 2017 (TBC) until December 2018
36. New Champlain Bridge Corridor Project
Water traffic
36
Background
• Work site in water as well as a transport
corridor for heavy parts between the Port of
Montreal and the cable-stayed bridge area
• Navigational vigilance in the St. Lawrence
and in the Lesser La Prairie Basin
• Four one-day-long closures of the Lesser
La Prairie Basin navigational corridor
Main mitigation measures
• Communication
• Waterway signs and marking
• Patrolling and nautical surveillance
• Equipment lighting
37. New Champlain Bridge Corridor Project 37
B1: Turenne area
B2: Voltaire area
B3: Tisserand area
Noise management
Area
Activity
Period
J/S/N
Exposed
sensitive
area
Ambient
noise
dBA
Criterion
dBA
Estimated
noise dBA
Required
measure
s
Pile caisson drilling and
concreting and cofferdam
placement
J B1 60 75 75 Monitoring
required
Forming and concreting of
footings and pier bases J B1/B2 60/62 75 68/66 Not required
Construction
of eastern abutment
J B1/B2 60/62 75 62/66 Not required
Placement of prefabricated
segments of piers and
pier caps
J B1/B2 60/62 75 61/64 Not required
A10
Earthworks at the Eastern
Abutment
J B2 62 75 73 Monitoring
required
Cable-
stayed
bridge
Miscellaneous work J B1/B2 60/62 75 61/63 Not required
EastApproach
41. New Champlain Bridge Corridor Project
• Good Neighbourly Relations Committee: September 21 or 28 (TBC)
Topic: none projected
• No public information meeting is planned for the time being
Next meetings (for discussion)
41
42. New Champlain Bridge Corridor Project
• Newsletter: sign up online
• Information sheets delivered to residents’ homes, if required, and
notices in local newspapers
• Sign up / contact us:
Website: www.newchamplain.ca
Email: info@sslc.ca
Phone us at: (514) 876-1020
Twitter: @NOUV_CHAMPLAIN
Communication
42