Plan A, Plan B, Plan C……how far?
A new methodology for preparing Alternate Plans
Author: Paramita Mukerji
Index
Abstract
Objective
Prologue
Alt-PM (Alternate Planning Methodology)
Prelude
Methodology
Critical factors for success
Benefits
Conclusion
Figures
Fig 1: Basis of Initial Plan
Fig 2: Reasons for change in plan
Fig 3: Root Causes behind change in plans
Fig 4: Project Managers' opinion on preparation of alternate plans
Tables
Table 1: Factors
Table 2: Phases
Table 3: Benchmark Table
Table 4: Calculation of Total Weight
Table 5: Number of Alternate Plans
Abstract
The success of a project is highly dependent on how well the Project Manager is able to steer the project
through various challenges. As a seasoned Project Manager, being proactive, mitigating risks & having
contingency plans in place are some basic things which will help him sail through difficult situations. An
experienced Project Manager should have Plan B ready if Plan A fails or show signs of failure. Going by
the same logic, Plan B can also fail and thus he should be ready with Plan C, Plan D and so on. But how
far? Theoretically it may be good to be fool proof but practically every plan will have its own reason to fail.
So how many plans should the Project Manager have to mitigate risks, ensure on time delivery, high
CSAT scores etc.
The answer to this question cannot be mathematically calculated. A veteran Project Manager may have
an intuitive answer. But that is not a reasonable and sustainable expectation from every Project Manager.
We try to find a model, which provides a framework to allow easy decision making during planning. This
should allow every Project Manager with a model driven second opinion to base his fallback plans. With
inputs received from brainstorming, Q&As, surveys and discussions with project team members, we
develop this model.
This model uses generic factors applicable across all types of IT projects. It will help the Project Manager
arrive at an optimal number of alternative plans to have. This will enable success by design and not by
chance!
Keywords: IT Project types, Project Plans, Fall back Plans, Project Constraints, Project Variables,
Project Resources
Objective
Why have Alternate Plans?
Planning is something which we require to do in every aspect of our lives. A kid is told to make a plan on
how he will utilize his time in preparing for exams. A teenager is expected to make a plan towards
building a good career for himself. If we decide to go on a vacation, we need to plan on how we will make
full use of the time available for sightseeing. A project manager prepares a plan for project execution.
Every job requires the worker to prepare a plan before he starts working on it. The kid wants to score
good marks, the teenager wants to be successful in choosing the right career, the traveler wants to visit
all tourist spots and not leave out any place. The Project Manager wants to successfully deliver and
satisfy the customer along with making profits. To summarize everyone wants to be successful. Thus we
spend a good amount of time & efforts in making the plan. We all believe that better the plans are, better
are the chances of success. But how far do we use the initial plans?
Very often we find that we are not able to stick to the plans which we made initially. We are forced to
make changes on the fly. We don’t get enough time to think and we move over to a different plan. This
leads to the vicious cycle of making & changing plans. Experience tells that we always need to make
frequent modifications in our plans and use alternate ones. Would it be useful to have some alternate
plans with us from the beginning? This study is towards finding out whether there is any benefit in having
alternate plans before the previous one fails. What is the optimum number of such alternate plans one
should be ready with?
I have used my experience in managing various IT projects and also gathered information from people
working in various types of IT projects to analyze the situation, infer and come up with suggestions on
preparing alternate plans.
Prologue
Current scenario in IT projects
Inputs were gathered from people working in various types of IT projects like Development Projects,
System Enhancement Projects, Support & Maintenance Projects, Infrastructure Projects, Package
Implementation Projects, System Integration Projects and Validation & Verification Projects. They were
majorly Project Managers and some in various types of other roles like Project Lead, Analyst, Architect,
Tester, Quality Assurance, Developer, vendor side SPOC across organizations. 70% of them were of the
opinion that they always felt that the plan on which they were working could fail any time and 90% of them
did not have any alternate fall back plan ready with them.
Fig 1: Basis of Initial Plan
In majority of projects the plans are prepared by the project managers during the project planning phase.
0.00% 5.00% 10.00% 15.00% 20.00% 25.00% 30.00% 35.00%
Others
Proposal
Contract
Requirements
Resources
Past Experience
On what basis initial plan is prepared?
Figure 1 gives us an overview on the aspects based on which the plan is built. These plans are approved
by senior team members and then by the customer. On an average, in a span of one year the plans get
changed 1-2 times in 55% of the projects, 3-4 times in 35% of the projects and more than 4 times in 10%
projects. The project teams take into consideration all relevant information to prepare the project plans
and get customer approvals, still these plans stand a high chance of failure. Theoretically we may say
that the success of the plan is dependent on the clarity of information available and the experience of the
person making the plan but, it is practically not possible to prepare a fail proof plan at the start of the
project and use it throughout the life of the project.
It is essential for the project teams to be ready with alternate plans which they can immediately start using
once the current plan fails. In majority of projects, the alternate plans are not created in advance. They
are created just after the current plan fails.
Common reasons for failure
Issues like lack of skilled resources, lack of experience, lack of technical competence and processes
which are either not defined or not followed are considered reasons internal to the team. These can be
controlled internally within the organization. It is not surprising if there are changes in the project plans
due to these reasons but there are factors beyond the control of the project teams which are externally
driven, which definitely lead to change in plans.
Fig 2: Reasons for change in plan
Most common external factors which lead to need for alternate plans are:
0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50%
Others
Change in scope
Change in budget
Change in timelines
Change in target quality parameters
What were the reasons which led to the failure
of the plan you were following earlier?
Change in scope
It is the era for dynamism. No project can have fixed scope which was defined in the start of the project
and has remained the same till the end of the project. New ideas, improvements are suggested
frequently. This causes increase or decrease of scope which need to be accommodated in the projects
being executed. Competition or a statutory body may bring in a new twist in the form of a new feature or
policy which impacts the scope of the project. All this forces the project to make changes in plans.
Change in budget
The financial position of the customer may change anytime. This impacts the availability of resources in
the projects. The projects may have to closed before time or may have to be ramped down to
accommodate the budget of the customer. All this forces the project to make changes in plans.
Change in timelines
Company X and Company Y are competitors. Company X wants to launch a product with exclusive
features and capture the market before Company Y launches its product. While Company X is still
developing the product, it is known from reliable sources that Company Y is also close to developing &
launching a similar product. In order to capture the market and get the maximum business benefit,
Company X will push for a launch before the date decided earlier. This is a typical example of how
change in timelines is not deliberate but driven by many factors beyond the control of any project team or
customer himself.
Change in final product quality/specifications
While eliciting requirements if we follow proper techniques and have experience we can be sure on
capturing all the functional requirements (features) but it is not easy to capture all the non functional
(quality related) requirements. In a project where a web form is to be developed, the number of fields,
number of drop downs and number of submit buttons required by the user can be documented from the
beginning. The user expectation on the time it should take to show the acknowledgement screen when
the user clicks the submit button may change once the user starts using the form. Implementing this
change effects everything from design to code. This causes change in plans!
In a project there may not be only one reason for failure of a plan. Many reasons contribute differently
towards the failure and together give rise to the need for changing the course of the project. The root
cause of failure of plans across different types of projects based on inputs from project managers across
projects is listed below. The data below also gives us the % distribution across these causes.
Fig 3: Root Causes behind failure of plans
Timing of alternate planning
Organizations which have well defined quality processes mandate the project teams to practice proactive
project management. The Project Managers to proactively analyze the situations (as listed in Figure 2)
and are ready with the alternate plans. They need to prioritize based on project dynamics and decide on
the plans they need to be ready with. This is taken care under Risk Management. The Project Managers
along with all stakeholders evaluate the project variables, have internal discussions / brainstorming
sessions and prepare a prioritized list of risks. Based on the priority they decide on the mitigation plans.
Some of the mitigation activities do include preparation of alternate project plans to be used in case of
eventuality.
After discussion with many project managers it is found that 60% of the projects did not prepare alternate
plans whereas 40% projects prepared them. In the projects where they used the alternate plans, a good
proportion of the plans were prepared after the current plans failed. Majority of the project managers feel
that it would be better if the alternate plans were prepared beforehand.
9%
11%
43%
4%
4%
22%
7%
What was the root cause of failure?
In capability of the delivery team
Unavailability of resources
Customer driven
Competition driven
Statutory regulations
Technology related
Others
Fig 4: Project Managers' opinion on preparation of alternate plans
Constraints in proactive planning
Maximum numbers of managers want the alternate plans to be prepared in advance but this is hardly
practiced in reality. There are many constraints which the managers faces because of which the alternate
plans are not prepared. Some of the major constraints are:
Inability to look ahead
The Project Manager’s experience should enable him to think ahead of time which will help him preparing
alternate plans. A seasoned project manager along with inputs from his team should be able to
understand the dynamics of the project and the environment and be prepared with alternate plans. The
Project Manager should be well prepared for any eventuality. He should be connected to the business to
foresee disruptions. In the absence of this capability preparing alternate plans proactively is difficult.
Unavailability of time (budget)
When the initial plan is prepared, Project Manager invests good amount to time & effort in preparing it.
Managers don’t put in enough thought and efforts while preparing the alternate plans assuming that they
will not be required to use them. In terms of budget, less than 2% of it is used in preparing alternate
plans. Most times this effort is not billed to customer. Creating alternate plans is considered a trivial
activity and not given its due importance in terms of time & effort.
0% 10% 20% 30% 40% 50% 60% 70% 80%
Can't say
After the earlier plan failed
Before the earlier plan failed
No need to prepare alternate plans
When do you think the alternate plan should be
prepared?
Unavailability of data required to prepare the plan
Due to disconnect between the various teams and also between the vendor & the customer, relevant data
does not reach the Project Manager. The Project Manager is not aware of many contractual agreements
which they come to know later on in the project leading to unplanned changes in the plans.
Not part of process to be followed
Following the defined policy, processes & guidelines ensures that the basic hygiene factors are not
overlooked. Preparing alternate plans should be mandated in the form of strict policy and not left on
choice which is the situation at present.
There is some key information needed by the managers which are helpful in overcoming the above
constraints and prepare the alternate plans. These include clarity on the revised scope, revised budget,
revised timelines and available resources (skill & tenure). This information is easily available once the
changes actually happen in the project. Thus preparing the alternate plans after the change has
happened is comparatively easier than preparing it before hand. We need to equip the project managers
with information which will enable him to think ahead and prepare the alternate plans proactively.
Constraints in implementing plans
In situations where alternate plans are available we find that there is apprehension in the teams towards
shifting to a new plan or unavailability of resources required. The teams tend to have inertia in moving
over to something different. The reasons for such inertia can be classified under the following categories:
Tendency to revert to earlier plan
Unavailability of a detailed revised plan
Unavailability of resources (Human, Hard or Software)
Lack of faith in the revised plan
Frequent changes in the revised plan
Delay in getting Customer Approval
Delay is getting Senior Management Approval
The managers need to overcome the above constraints for success of the project. It is an established fact
that all projects will undergo changes. To take care of the changes, effective alternate plans need to
available and also be followed. Without successful implementation of alternate plans the projects cannot
be successful. The best of plans will not work if not used by the team. We need to equip the project
managers with guidelines on how this can be achieved.
Alt-PM (Alternate Planning Methodology)
This is reference tool to help projects identify the optimum number of alternate plans required
under varying project conditions.
Based on what we have discussed so far in the document above, we can summarize it as:
 Initial Plans are designed to be more robust as teams spend more efforts in building them.
 There is 90% probability that the project will have to change the plan. There are many reasons to
support this cause.
 Even though it is known, rarely the alternative plans are prepared beforehand.
 Majority of the alternate plans are prepared at the spur of the moment when the previous plan
fails. The effort spent in this is much less than what was spent for making the initial plan.
 There is challenge in shifting from one plan to the other.
There is strong need to equip the project managers with a frame work which will help them identify the
need of the alternate plans, overcome the constraints in developing the alternate plans proactively and
also overcome the constraints in implementing these plans. No two projects are same. Each project will
have something unique about it. The challenges faced by one project are different from the ones faced by
the other. Each project has its own set of data with respect to scope, budget, timelines, resources, quality
and the customer. The requirement for alternate plans will also vary accordingly.
Prelude
Alt-PM is a methodology aimed towards helping the managers in identifying the alternate plans they
should prepare at the beginning of each phase proactively based on information available. It also factors
in the challenges with respect to implementation of these plans. This methodology leverages on the
experience of managers and the information available from successfully implemented past projects. It
provides the flexibility to users to define their own project constraints based on their project information. It
captures the experience gained by project managers during execution of previous projects which were of
similar type and had similar constraints. This experience is used in building a guideline. Data from similar
types of past projects is then used in benchmarking the number of alternate plans to be prepared so that
they can be prepared and successfully implemented.
Methodology
Guidelines are prepared by experienced project managers with the inputs from the data from past
projects of similar type. Guidelines once prepared are reusable by projects with similar constraints. These
guidelines can be progressively evolved with usage. The usage of this methodology is a two step
process.
Step 1: Preparation of the Guidelines & Benchmarks
Preparation of the Guidelines
Factors: List the constraints which are generally faced by projects of a particular type. Assign weight to
each of this factor based on how strongly this constraint will affect the project plan. This is done in the
scale of 0-5 where 0 means least effect and 5 means maximum effect. Table 1 below is a sample Factor
Table which is prepared for development projects of similar characteristics.
Phases: List the various phases of the project in a chorological order and assign weight to each phase.
Assign weights based on how any change in this phase will affect the project plan. The weight is higher
for phases where any change during that phase high effect on the plan. Table 2 below is a sample Phase
Table which is prepared for development projects of similar characteristics.
S. No.
Factors due to which changes can happen in any
project
Weights based on impact of
this factor on project plans in
scale of 0-5 (A)
1 Team not experienced in the domain 3
2 Team not experienced in the technology 4
3 Team not skilled for gathering requirements 2
4 Team not clear on the requirements 2
5 Team resists any change 4
6 Team does not follow processes 1
7 Team is not aware of the overall project objective 1
8 Less experienced Project Manager 3
9 Delay in taking decisions by senior management 2
10 Customer not clear on the requirements 4
11 Multiple stakeholders 4
12 Delay in approvals from customer 4
13 Delay in query resolution by customer 3
14 Budget changes due to customer 2
15 Delay due to vendor 3
16 Competitors launching similar product 5
17 Human Resources not available 3
18 Software/Hardware resources not available 2
19 Required tools not available with the team 1
20 Prone to changes through regulatory policies 5
Table 1: Factors
Phases in the project Weight (B)
Initiation 0.25
Table 2: Phases
Defining the Benchmarks (Benchmark Table)
Identify completed projects of similar characteristics. Identify the constraints that were faced by these
projects during the various phases of implementation. For each of the factor, note the corresponding
weights as mentioned in the Factor Table (A). For each of the factor note the phase in which they were
identified and the corresponding weight from Phase Table (B). Take the product of A&B as the final
weight. Since the projects are already completed, the team is able to count the number of alternate plans
which were actually prepared during the execution of these projects. Using this information prepare the
Benchmark Table. More the number of completed projects analyzed better will be the benchmarks.
Consider the average value for the benchmarks as every project may not have prepared the same
number of alternate plans even if the weights were same. Table 3 shows a sample Benchmark Table
which is prepared for development projects of similar characteristics.
Weight
Range
Recommended number of Alternate Plans
Initiation Planning Requirements Design CUT Testing
0-1 0 0 0 0 0 0
2 to10 1 1 2 2 3 3
11 to 20 2 2 3 3 4 4
>20 3 3 4 4 5 5
Table 3: Benchmark Table
Step 2: Calculating the number of Alternate Plans for a new project
When a new project or task is assigned to the team the project manager should follow these steps to
derive the optimum number of alternate plans:
Calculating total weight
List the constraints in the new project. These constraints should be already present in the list of the
factors identified in the Factor Table. Take the corresponding weights from this table (A). For each of the
factor identify the phase of the project when these constraints have maximum probability of identification
and get the corresponding weight using the Phase Table (B). Calculate the final weight as (A*B). Table 4
below gives an example on how the total weight is calculated for a development project.
Planning 0.25
Requirements 1
Design 2
CUT 2
Testing 3
Deriving the number of alternate plans
Calculate the sum of the total weights for each of the phases separately. Look up in the Benchmark Table
and find the number of alternate plans corresponding to the total weight for that phase. Table 5 below
gives an example on how the phase wise optimum number of alternate plans is derived for a
development project.
S. No. Factors effecting the current project
Weight
based on
Table 1 (A)
Phase when
this factor may
be identified
Weight
based on
Table 2
(B)
Total
Weight
(A * B)
1 Team not experienced in the domain 3 Initiation 0.25 0.75
2 Team not clear on the requirements 2 Design 2 4
3 Team does not follow processes 1 Requirements 1 1
4 Multiple stakeholders 4 Planning 0.25 1
5 Delay in query resolution by customer 3 Planning 0.25 0.75
6 Budget changes due to customer 2 Design 2 4
7 Competitors launching similar product 5 Design 2 10
8 Human Resources not available 3 Planning 0.25 0.75
9
Software/Hardware resources not
available
2 Planning 0.25 0.5
10
Required tools not available with the
team
1 CUT 2 2
11
Prone to changes through regulatory
policies
5 Design 2 10
Table 4: Calculation of Total Weight
Phase(s)
Total weight
Calculated
from Table 4
Alternate Plans
to be prepared
Initiation 0.75 0
Planning 3 1
Requirements 1 0
Design 28 4
CUT 2 3
Testing 0 0
Table 5: Number of Alternate Plans
Critical factors for success
The success of this methodology depends on
 Experience of the person/team who is preparing the guidelines & benchmarks.
 Reliability of the data received from past projects.
 Clear understanding of the project constraints by the person/team making the guidelines.
 Updating & improving the guidelines after successful completion of each project in which these
guidelines were used in calculating the number the alternate plans.
 Proper understanding before using the guidelines & the benchmarks.
 Proper use of the guidelines & benchmarks.
 Same set of guidelines and benchmarks cannot be used for all types of projects. Only similar type of
projects can use the same set of guidelines & benchmarks. For other types of projects different set of
guidelines & benchmarks need to be prepared.
Benefits
This methodology is an attempt to help the Project Managers in managing the projects through proactive
planning. The industry is highly dynamic and very uncertain. Through this methodology we are using our
experience & knowledge gained through many years of project execution and trying to bring some
certainty in the area of project planning. The benefits can be measured by way of
 Planning for eventualities in advance and saving project effort & time leading to cost saving.
 Knowledge & experience available with few individuals is documented in the form of guidelines thus
enhancing knowledge sharing and reducing person dependency.
 Achieving higher customer satisfaction scores by showcasing proactive project management.
 Project team is open for changes as they have already planned for such situations. This makes them
very flexible which is a preferred attribute of vendors.
 Keeping the team members motivated as the project manager is able to plan and allocate work in a
more systematic manner even when the project undergoes changes.
Conclusion
The industry today is mature but very dynamic. There is no one way or one golden set of rules which can
resolve the issues. Through this methodology, project managers should be able to face the challenges in
a more structured & organized manner.
About the author
Paramita Mukerji is an IT professional with a proven track record of 13+ years in IT services. She is
currently working as Project Management Consultant with Wipro Technologies, one of the Top-4
companies in IT business in India. She possesses strong leadership capability. Using a system oriented
approach; she has guided many cross functional teams across different business verticals in project
management. She is an Electronics and Telecommunication Engineer by training, with several
professional certifications like PMP, Prince 2 and ITILV3. She specializes in the areas of Software Project
Management and Software Quality Management. She is a certified SEI Audit Team Member and KPMG
Certified Internal Auditor.
For further details please visit: in.linkedin.com/in/paramitamukerji/

Contenu connexe

Tendances

Identifying a project in trouble and re-planning
Identifying a project in trouble and re-planningIdentifying a project in trouble and re-planning
Identifying a project in trouble and re-planningmfarbstein
 
10 tips to rescue a problem project
10 tips to rescue a problem project10 tips to rescue a problem project
10 tips to rescue a problem projectgianarosetti
 
Project Governance Model Powerpoint Presentation Slides
Project Governance Model Powerpoint Presentation SlidesProject Governance Model Powerpoint Presentation Slides
Project Governance Model Powerpoint Presentation SlidesSlideTeam
 
Project Charter Template
Project Charter TemplateProject Charter Template
Project Charter TemplateNaseer Muhammud
 
Project management best practices
Project management best practicesProject management best practices
Project management best practicesJackson Chan
 
A Short Workshop on Project Management
A Short Workshop on Project ManagementA Short Workshop on Project Management
A Short Workshop on Project ManagementNicole Fronda
 
Why do the Projects fail
Why do the Projects failWhy do the Projects fail
Why do the Projects failSwapanK
 
10 tips to avoid a project failure
10 tips to avoid a project failure10 tips to avoid a project failure
10 tips to avoid a project failuregianarosetti
 
Why Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and SolutionsWhy Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and SolutionsMichael Krigsman
 
Presentation by suhail qadir
Presentation by suhail qadirPresentation by suhail qadir
Presentation by suhail qadirPMI_IREP_TP
 
Earning Value from Earned Value
Earning Value from Earned ValueEarning Value from Earned Value
Earning Value from Earned ValueGlen Alleman
 
Project Governance Model PowerPoint Presentation Slides
Project Governance Model PowerPoint Presentation Slides Project Governance Model PowerPoint Presentation Slides
Project Governance Model PowerPoint Presentation Slides SlideTeam
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"David Pedreno
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1Daniel Hucks
 
Project management
Project managementProject management
Project managementsatya pal
 
Project management
Project managementProject management
Project managementAdeel Javaid
 
Product Roadmaps Done Right
Product Roadmaps Done RightProduct Roadmaps Done Right
Product Roadmaps Done RightJohn Carter
 

Tendances (20)

Identifying a project in trouble and re-planning
Identifying a project in trouble and re-planningIdentifying a project in trouble and re-planning
Identifying a project in trouble and re-planning
 
10 tips to rescue a problem project
10 tips to rescue a problem project10 tips to rescue a problem project
10 tips to rescue a problem project
 
Project Governance Model Powerpoint Presentation Slides
Project Governance Model Powerpoint Presentation SlidesProject Governance Model Powerpoint Presentation Slides
Project Governance Model Powerpoint Presentation Slides
 
Project Charter Template
Project Charter TemplateProject Charter Template
Project Charter Template
 
Project management best practices
Project management best practicesProject management best practices
Project management best practices
 
A Short Workshop on Project Management
A Short Workshop on Project ManagementA Short Workshop on Project Management
A Short Workshop on Project Management
 
Why do the Projects fail
Why do the Projects failWhy do the Projects fail
Why do the Projects fail
 
10 tips to avoid a project failure
10 tips to avoid a project failure10 tips to avoid a project failure
10 tips to avoid a project failure
 
Why Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and SolutionsWhy Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and Solutions
 
Presentation by suhail qadir
Presentation by suhail qadirPresentation by suhail qadir
Presentation by suhail qadir
 
Earning Value from Earned Value
Earning Value from Earned ValueEarning Value from Earned Value
Earning Value from Earned Value
 
Project Governance Model PowerPoint Presentation Slides
Project Governance Model PowerPoint Presentation Slides Project Governance Model PowerPoint Presentation Slides
Project Governance Model PowerPoint Presentation Slides
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
 
Is project failure
Is project failureIs project failure
Is project failure
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1
 
Project Plan
Project PlanProject Plan
Project Plan
 
Project management
Project managementProject management
Project management
 
Project management
Project managementProject management
Project management
 
Project charter
Project charterProject charter
Project charter
 
Product Roadmaps Done Right
Product Roadmaps Done RightProduct Roadmaps Done Right
Product Roadmaps Done Right
 

En vedette

Conn's Inc. - Lan Nguyen
Conn's Inc. - Lan NguyenConn's Inc. - Lan Nguyen
Conn's Inc. - Lan NguyenLan Nguyen
 
Day 1 1505 - 1550 - maple - chakradhar purohith
Day 1   1505 - 1550 - maple - chakradhar purohithDay 1   1505 - 1550 - maple - chakradhar purohith
Day 1 1505 - 1550 - maple - chakradhar purohithPMI2011
 
Deep kamalsingh
Deep kamalsinghDeep kamalsingh
Deep kamalsinghPMI2011
 
Influence du secteur touristique dans la region de Marrakech
Influence du secteur touristique dans la region de Marrakech
Influence du secteur touristique dans la region de Marrakech
Influence du secteur touristique dans la region de Marrakech maisonsamarrakech3577
 
Autoprint Machinery Mfg. Pvt. Ltd
Autoprint Machinery Mfg. Pvt. LtdAutoprint Machinery Mfg. Pvt. Ltd
Autoprint Machinery Mfg. Pvt. Ltdengineeringwatch
 
Day 2 1230 - 1315 - pearl 2 - alankar karpe
Day 2   1230 - 1315 - pearl 2 - alankar karpeDay 2   1230 - 1315 - pearl 2 - alankar karpe
Day 2 1230 - 1315 - pearl 2 - alankar karpePMI2011
 
Bhavesh pmi final
Bhavesh  pmi finalBhavesh  pmi final
Bhavesh pmi finalPMI2011
 

En vedette (8)

Trade Cert
Trade CertTrade Cert
Trade Cert
 
Conn's Inc. - Lan Nguyen
Conn's Inc. - Lan NguyenConn's Inc. - Lan Nguyen
Conn's Inc. - Lan Nguyen
 
Day 1 1505 - 1550 - maple - chakradhar purohith
Day 1   1505 - 1550 - maple - chakradhar purohithDay 1   1505 - 1550 - maple - chakradhar purohith
Day 1 1505 - 1550 - maple - chakradhar purohith
 
Deep kamalsingh
Deep kamalsinghDeep kamalsingh
Deep kamalsingh
 
Influence du secteur touristique dans la region de Marrakech
Influence du secteur touristique dans la region de Marrakech
Influence du secteur touristique dans la region de Marrakech
Influence du secteur touristique dans la region de Marrakech
 
Autoprint Machinery Mfg. Pvt. Ltd
Autoprint Machinery Mfg. Pvt. LtdAutoprint Machinery Mfg. Pvt. Ltd
Autoprint Machinery Mfg. Pvt. Ltd
 
Day 2 1230 - 1315 - pearl 2 - alankar karpe
Day 2   1230 - 1315 - pearl 2 - alankar karpeDay 2   1230 - 1315 - pearl 2 - alankar karpe
Day 2 1230 - 1315 - pearl 2 - alankar karpe
 
Bhavesh pmi final
Bhavesh  pmi finalBhavesh  pmi final
Bhavesh pmi final
 

Similaire à Paramita mukerji

Understand the Project Cycle Management & Its Phases Introduction
Understand the Project Cycle Management & Its Phases IntroductionUnderstand the Project Cycle Management & Its Phases Introduction
Understand the Project Cycle Management & Its Phases IntroductionDivya Malik
 
Kinsley FosterJuly 27, 2019PM 430Software .docx
Kinsley FosterJuly 27, 2019PM 430Software .docxKinsley FosterJuly 27, 2019PM 430Software .docx
Kinsley FosterJuly 27, 2019PM 430Software .docxcroysierkathey
 
Project Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training ExampleProject Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training ExampleKate Pynn
 
MGT 3302, Introduction to Project Management 1 Cou.docx
MGT 3302, Introduction to Project Management 1 Cou.docxMGT 3302, Introduction to Project Management 1 Cou.docx
MGT 3302, Introduction to Project Management 1 Cou.docxpoulterbarbara
 
Running Head PROJECT PLAN PART 3PROJECT PLAN PART 35.docx
Running Head PROJECT PLAN PART 3PROJECT PLAN PART 35.docxRunning Head PROJECT PLAN PART 3PROJECT PLAN PART 35.docx
Running Head PROJECT PLAN PART 3PROJECT PLAN PART 35.docxtoltonkendal
 
5 project management project planning
5 project management  project planning5 project management  project planning
5 project management project planningYasirHamour
 
assingnment 56
assingnment 56assingnment 56
assingnment 56Bhas Karan
 
How to Avoid Project Train Wrecks
How to Avoid Project Train WrecksHow to Avoid Project Train Wrecks
How to Avoid Project Train WrecksPete Luan
 
CRG DevCo’s advantages of outsourcing Project Management
CRG DevCo’s advantages of outsourcing Project ManagementCRG DevCo’s advantages of outsourcing Project Management
CRG DevCo’s advantages of outsourcing Project ManagementChris Gorga
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overviewcford1973
 
28.Causes of project failure A Lecture By Mr Allah Dad Khan Visiting Profes...
28.Causes of project failure   A Lecture By Mr Allah Dad Khan Visiting Profes...28.Causes of project failure   A Lecture By Mr Allah Dad Khan Visiting Profes...
28.Causes of project failure A Lecture By Mr Allah Dad Khan Visiting Profes...Mr.Allah Dad Khan
 
Task_TableNameDurationPredecessorsResourcesNotesMobile app plan34 .docx
Task_TableNameDurationPredecessorsResourcesNotesMobile app plan34 .docxTask_TableNameDurationPredecessorsResourcesNotesMobile app plan34 .docx
Task_TableNameDurationPredecessorsResourcesNotesMobile app plan34 .docxerlindaw
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesGlen Alleman
 
WRITTEN INTERVIEW QUESTIONSPhD candidates should provide an aut.docx
WRITTEN INTERVIEW QUESTIONSPhD candidates should provide an aut.docxWRITTEN INTERVIEW QUESTIONSPhD candidates should provide an aut.docx
WRITTEN INTERVIEW QUESTIONSPhD candidates should provide an aut.docxodiliagilby
 
Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptxPranshiGoyal2
 
Project management assignment help
Project management assignment helpProject management assignment help
Project management assignment helpassignmenthelpp
 
Estimate budget and project crashing.pptx
Estimate budget and project crashing.pptxEstimate budget and project crashing.pptx
Estimate budget and project crashing.pptxMIANMNADEEM
 
Why projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfallsWhy projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfallsTa Ngoc
 

Similaire à Paramita mukerji (20)

Understand the Project Cycle Management & Its Phases Introduction
Understand the Project Cycle Management & Its Phases IntroductionUnderstand the Project Cycle Management & Its Phases Introduction
Understand the Project Cycle Management & Its Phases Introduction
 
Kinsley FosterJuly 27, 2019PM 430Software .docx
Kinsley FosterJuly 27, 2019PM 430Software .docxKinsley FosterJuly 27, 2019PM 430Software .docx
Kinsley FosterJuly 27, 2019PM 430Software .docx
 
How to Steer Clear Of Budget Overruns in Software.pdf
How to Steer Clear Of Budget Overruns in Software.pdfHow to Steer Clear Of Budget Overruns in Software.pdf
How to Steer Clear Of Budget Overruns in Software.pdf
 
Project Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training ExampleProject Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training Example
 
MGT 3302, Introduction to Project Management 1 Cou.docx
MGT 3302, Introduction to Project Management 1 Cou.docxMGT 3302, Introduction to Project Management 1 Cou.docx
MGT 3302, Introduction to Project Management 1 Cou.docx
 
Running Head PROJECT PLAN PART 3PROJECT PLAN PART 35.docx
Running Head PROJECT PLAN PART 3PROJECT PLAN PART 35.docxRunning Head PROJECT PLAN PART 3PROJECT PLAN PART 35.docx
Running Head PROJECT PLAN PART 3PROJECT PLAN PART 35.docx
 
5 project management project planning
5 project management  project planning5 project management  project planning
5 project management project planning
 
assingnment 56
assingnment 56assingnment 56
assingnment 56
 
How to Avoid Project Train Wrecks
How to Avoid Project Train WrecksHow to Avoid Project Train Wrecks
How to Avoid Project Train Wrecks
 
CRG DevCo’s advantages of outsourcing Project Management
CRG DevCo’s advantages of outsourcing Project ManagementCRG DevCo’s advantages of outsourcing Project Management
CRG DevCo’s advantages of outsourcing Project Management
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overview
 
28.Causes of project failure A Lecture By Mr Allah Dad Khan Visiting Profes...
28.Causes of project failure   A Lecture By Mr Allah Dad Khan Visiting Profes...28.Causes of project failure   A Lecture By Mr Allah Dad Khan Visiting Profes...
28.Causes of project failure A Lecture By Mr Allah Dad Khan Visiting Profes...
 
Task_TableNameDurationPredecessorsResourcesNotesMobile app plan34 .docx
Task_TableNameDurationPredecessorsResourcesNotesMobile app plan34 .docxTask_TableNameDurationPredecessorsResourcesNotesMobile app plan34 .docx
Task_TableNameDurationPredecessorsResourcesNotesMobile app plan34 .docx
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
WRITTEN INTERVIEW QUESTIONSPhD candidates should provide an aut.docx
WRITTEN INTERVIEW QUESTIONSPhD candidates should provide an aut.docxWRITTEN INTERVIEW QUESTIONSPhD candidates should provide an aut.docx
WRITTEN INTERVIEW QUESTIONSPhD candidates should provide an aut.docx
 
Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptx
 
Project management assignment help
Project management assignment helpProject management assignment help
Project management assignment help
 
JIT Project
JIT ProjectJIT Project
JIT Project
 
Estimate budget and project crashing.pptx
Estimate budget and project crashing.pptxEstimate budget and project crashing.pptx
Estimate budget and project crashing.pptx
 
Why projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfallsWhy projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfalls
 

Plus de PMI2011

Day 1 1410 - 1455 - pearl 2 - vijay sane
Day 1   1410 - 1455 - pearl 2 - vijay saneDay 1   1410 - 1455 - pearl 2 - vijay sane
Day 1 1410 - 1455 - pearl 2 - vijay sanePMI2011
 
Day 1 1620 - 1705 - maple - pranabendu bhattacharyya
Day 1   1620 - 1705 - maple - pranabendu bhattacharyyaDay 1   1620 - 1705 - maple - pranabendu bhattacharyya
Day 1 1620 - 1705 - maple - pranabendu bhattacharyyaPMI2011
 
Final chakradhar purohith proposal milieu analysis (without account data un...
Final chakradhar purohith proposal milieu analysis (without account data   un...Final chakradhar purohith proposal milieu analysis (without account data   un...
Final chakradhar purohith proposal milieu analysis (without account data un...PMI2011
 
Wilso anandaraj balasubramaniankrishnamurthy
Wilso anandaraj balasubramaniankrishnamurthyWilso anandaraj balasubramaniankrishnamurthy
Wilso anandaraj balasubramaniankrishnamurthyPMI2011
 
Vs velan dchakravarty_ppchakraborti
Vs velan dchakravarty_ppchakrabortiVs velan dchakravarty_ppchakraborti
Vs velan dchakravarty_ppchakrabortiPMI2011
 
Vineet jain
Vineet jainVineet jain
Vineet jainPMI2011
 
Yamuna padmanaban
Yamuna padmanabanYamuna padmanaban
Yamuna padmanabanPMI2011
 
Vimal kumarkhanna
Vimal kumarkhannaVimal kumarkhanna
Vimal kumarkhannaPMI2011
 
Venkatraman l
Venkatraman lVenkatraman l
Venkatraman lPMI2011
 
Vardarajan sethuraman
Vardarajan sethuramanVardarajan sethuraman
Vardarajan sethuramanPMI2011
 
Soumen de
Soumen deSoumen de
Soumen dePMI2011
 
Sujit sopan barhate
Sujit sopan barhateSujit sopan barhate
Sujit sopan barhatePMI2011
 
Srinivasa desikanraghavan
Srinivasa desikanraghavanSrinivasa desikanraghavan
Srinivasa desikanraghavanPMI2011
 
Sharad pandey abhisek goswami
Sharad pandey abhisek goswamiSharad pandey abhisek goswami
Sharad pandey abhisek goswamiPMI2011
 
Soma roy sarkar
Soma roy sarkarSoma roy sarkar
Soma roy sarkarPMI2011
 
Shallu soni mymoonshabana_lavanya raghuraman
Shallu soni mymoonshabana_lavanya raghuramanShallu soni mymoonshabana_lavanya raghuraman
Shallu soni mymoonshabana_lavanya raghuramanPMI2011
 
Regeena pererira sujithn_rai_suchitrajoyceb
Regeena pererira sujithn_rai_suchitrajoycebRegeena pererira sujithn_rai_suchitrajoyceb
Regeena pererira sujithn_rai_suchitrajoycebPMI2011
 
Ramesh ganiga
Ramesh ganigaRamesh ganiga
Ramesh ganigaPMI2011
 
Pranabendu
PranabenduPranabendu
PranabenduPMI2011
 
Rt sundari ashutosh_pandey
Rt sundari ashutosh_pandeyRt sundari ashutosh_pandey
Rt sundari ashutosh_pandeyPMI2011
 

Plus de PMI2011 (20)

Day 1 1410 - 1455 - pearl 2 - vijay sane
Day 1   1410 - 1455 - pearl 2 - vijay saneDay 1   1410 - 1455 - pearl 2 - vijay sane
Day 1 1410 - 1455 - pearl 2 - vijay sane
 
Day 1 1620 - 1705 - maple - pranabendu bhattacharyya
Day 1   1620 - 1705 - maple - pranabendu bhattacharyyaDay 1   1620 - 1705 - maple - pranabendu bhattacharyya
Day 1 1620 - 1705 - maple - pranabendu bhattacharyya
 
Final chakradhar purohith proposal milieu analysis (without account data un...
Final chakradhar purohith proposal milieu analysis (without account data   un...Final chakradhar purohith proposal milieu analysis (without account data   un...
Final chakradhar purohith proposal milieu analysis (without account data un...
 
Wilso anandaraj balasubramaniankrishnamurthy
Wilso anandaraj balasubramaniankrishnamurthyWilso anandaraj balasubramaniankrishnamurthy
Wilso anandaraj balasubramaniankrishnamurthy
 
Vs velan dchakravarty_ppchakraborti
Vs velan dchakravarty_ppchakrabortiVs velan dchakravarty_ppchakraborti
Vs velan dchakravarty_ppchakraborti
 
Vineet jain
Vineet jainVineet jain
Vineet jain
 
Yamuna padmanaban
Yamuna padmanabanYamuna padmanaban
Yamuna padmanaban
 
Vimal kumarkhanna
Vimal kumarkhannaVimal kumarkhanna
Vimal kumarkhanna
 
Venkatraman l
Venkatraman lVenkatraman l
Venkatraman l
 
Vardarajan sethuraman
Vardarajan sethuramanVardarajan sethuraman
Vardarajan sethuraman
 
Soumen de
Soumen deSoumen de
Soumen de
 
Sujit sopan barhate
Sujit sopan barhateSujit sopan barhate
Sujit sopan barhate
 
Srinivasa desikanraghavan
Srinivasa desikanraghavanSrinivasa desikanraghavan
Srinivasa desikanraghavan
 
Sharad pandey abhisek goswami
Sharad pandey abhisek goswamiSharad pandey abhisek goswami
Sharad pandey abhisek goswami
 
Soma roy sarkar
Soma roy sarkarSoma roy sarkar
Soma roy sarkar
 
Shallu soni mymoonshabana_lavanya raghuraman
Shallu soni mymoonshabana_lavanya raghuramanShallu soni mymoonshabana_lavanya raghuraman
Shallu soni mymoonshabana_lavanya raghuraman
 
Regeena pererira sujithn_rai_suchitrajoyceb
Regeena pererira sujithn_rai_suchitrajoycebRegeena pererira sujithn_rai_suchitrajoyceb
Regeena pererira sujithn_rai_suchitrajoyceb
 
Ramesh ganiga
Ramesh ganigaRamesh ganiga
Ramesh ganiga
 
Pranabendu
PranabenduPranabendu
Pranabendu
 
Rt sundari ashutosh_pandey
Rt sundari ashutosh_pandeyRt sundari ashutosh_pandey
Rt sundari ashutosh_pandey
 

Dernier

Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 

Dernier (20)

Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 

Paramita mukerji

  • 1. Plan A, Plan B, Plan C……how far? A new methodology for preparing Alternate Plans Author: Paramita Mukerji
  • 2. Index Abstract Objective Prologue Alt-PM (Alternate Planning Methodology) Prelude Methodology Critical factors for success Benefits Conclusion Figures Fig 1: Basis of Initial Plan Fig 2: Reasons for change in plan Fig 3: Root Causes behind change in plans Fig 4: Project Managers' opinion on preparation of alternate plans Tables Table 1: Factors Table 2: Phases Table 3: Benchmark Table Table 4: Calculation of Total Weight Table 5: Number of Alternate Plans
  • 3. Abstract The success of a project is highly dependent on how well the Project Manager is able to steer the project through various challenges. As a seasoned Project Manager, being proactive, mitigating risks & having contingency plans in place are some basic things which will help him sail through difficult situations. An experienced Project Manager should have Plan B ready if Plan A fails or show signs of failure. Going by the same logic, Plan B can also fail and thus he should be ready with Plan C, Plan D and so on. But how far? Theoretically it may be good to be fool proof but practically every plan will have its own reason to fail. So how many plans should the Project Manager have to mitigate risks, ensure on time delivery, high CSAT scores etc. The answer to this question cannot be mathematically calculated. A veteran Project Manager may have an intuitive answer. But that is not a reasonable and sustainable expectation from every Project Manager. We try to find a model, which provides a framework to allow easy decision making during planning. This should allow every Project Manager with a model driven second opinion to base his fallback plans. With inputs received from brainstorming, Q&As, surveys and discussions with project team members, we develop this model. This model uses generic factors applicable across all types of IT projects. It will help the Project Manager arrive at an optimal number of alternative plans to have. This will enable success by design and not by chance! Keywords: IT Project types, Project Plans, Fall back Plans, Project Constraints, Project Variables, Project Resources Objective Why have Alternate Plans? Planning is something which we require to do in every aspect of our lives. A kid is told to make a plan on how he will utilize his time in preparing for exams. A teenager is expected to make a plan towards building a good career for himself. If we decide to go on a vacation, we need to plan on how we will make full use of the time available for sightseeing. A project manager prepares a plan for project execution. Every job requires the worker to prepare a plan before he starts working on it. The kid wants to score good marks, the teenager wants to be successful in choosing the right career, the traveler wants to visit all tourist spots and not leave out any place. The Project Manager wants to successfully deliver and satisfy the customer along with making profits. To summarize everyone wants to be successful. Thus we spend a good amount of time & efforts in making the plan. We all believe that better the plans are, better are the chances of success. But how far do we use the initial plans? Very often we find that we are not able to stick to the plans which we made initially. We are forced to make changes on the fly. We don’t get enough time to think and we move over to a different plan. This leads to the vicious cycle of making & changing plans. Experience tells that we always need to make
  • 4. frequent modifications in our plans and use alternate ones. Would it be useful to have some alternate plans with us from the beginning? This study is towards finding out whether there is any benefit in having alternate plans before the previous one fails. What is the optimum number of such alternate plans one should be ready with? I have used my experience in managing various IT projects and also gathered information from people working in various types of IT projects to analyze the situation, infer and come up with suggestions on preparing alternate plans. Prologue Current scenario in IT projects Inputs were gathered from people working in various types of IT projects like Development Projects, System Enhancement Projects, Support & Maintenance Projects, Infrastructure Projects, Package Implementation Projects, System Integration Projects and Validation & Verification Projects. They were majorly Project Managers and some in various types of other roles like Project Lead, Analyst, Architect, Tester, Quality Assurance, Developer, vendor side SPOC across organizations. 70% of them were of the opinion that they always felt that the plan on which they were working could fail any time and 90% of them did not have any alternate fall back plan ready with them. Fig 1: Basis of Initial Plan In majority of projects the plans are prepared by the project managers during the project planning phase. 0.00% 5.00% 10.00% 15.00% 20.00% 25.00% 30.00% 35.00% Others Proposal Contract Requirements Resources Past Experience On what basis initial plan is prepared?
  • 5. Figure 1 gives us an overview on the aspects based on which the plan is built. These plans are approved by senior team members and then by the customer. On an average, in a span of one year the plans get changed 1-2 times in 55% of the projects, 3-4 times in 35% of the projects and more than 4 times in 10% projects. The project teams take into consideration all relevant information to prepare the project plans and get customer approvals, still these plans stand a high chance of failure. Theoretically we may say that the success of the plan is dependent on the clarity of information available and the experience of the person making the plan but, it is practically not possible to prepare a fail proof plan at the start of the project and use it throughout the life of the project. It is essential for the project teams to be ready with alternate plans which they can immediately start using once the current plan fails. In majority of projects, the alternate plans are not created in advance. They are created just after the current plan fails. Common reasons for failure Issues like lack of skilled resources, lack of experience, lack of technical competence and processes which are either not defined or not followed are considered reasons internal to the team. These can be controlled internally within the organization. It is not surprising if there are changes in the project plans due to these reasons but there are factors beyond the control of the project teams which are externally driven, which definitely lead to change in plans. Fig 2: Reasons for change in plan Most common external factors which lead to need for alternate plans are: 0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50% Others Change in scope Change in budget Change in timelines Change in target quality parameters What were the reasons which led to the failure of the plan you were following earlier?
  • 6. Change in scope It is the era for dynamism. No project can have fixed scope which was defined in the start of the project and has remained the same till the end of the project. New ideas, improvements are suggested frequently. This causes increase or decrease of scope which need to be accommodated in the projects being executed. Competition or a statutory body may bring in a new twist in the form of a new feature or policy which impacts the scope of the project. All this forces the project to make changes in plans. Change in budget The financial position of the customer may change anytime. This impacts the availability of resources in the projects. The projects may have to closed before time or may have to be ramped down to accommodate the budget of the customer. All this forces the project to make changes in plans. Change in timelines Company X and Company Y are competitors. Company X wants to launch a product with exclusive features and capture the market before Company Y launches its product. While Company X is still developing the product, it is known from reliable sources that Company Y is also close to developing & launching a similar product. In order to capture the market and get the maximum business benefit, Company X will push for a launch before the date decided earlier. This is a typical example of how change in timelines is not deliberate but driven by many factors beyond the control of any project team or customer himself. Change in final product quality/specifications While eliciting requirements if we follow proper techniques and have experience we can be sure on capturing all the functional requirements (features) but it is not easy to capture all the non functional (quality related) requirements. In a project where a web form is to be developed, the number of fields, number of drop downs and number of submit buttons required by the user can be documented from the beginning. The user expectation on the time it should take to show the acknowledgement screen when the user clicks the submit button may change once the user starts using the form. Implementing this change effects everything from design to code. This causes change in plans! In a project there may not be only one reason for failure of a plan. Many reasons contribute differently towards the failure and together give rise to the need for changing the course of the project. The root cause of failure of plans across different types of projects based on inputs from project managers across projects is listed below. The data below also gives us the % distribution across these causes.
  • 7. Fig 3: Root Causes behind failure of plans Timing of alternate planning Organizations which have well defined quality processes mandate the project teams to practice proactive project management. The Project Managers to proactively analyze the situations (as listed in Figure 2) and are ready with the alternate plans. They need to prioritize based on project dynamics and decide on the plans they need to be ready with. This is taken care under Risk Management. The Project Managers along with all stakeholders evaluate the project variables, have internal discussions / brainstorming sessions and prepare a prioritized list of risks. Based on the priority they decide on the mitigation plans. Some of the mitigation activities do include preparation of alternate project plans to be used in case of eventuality. After discussion with many project managers it is found that 60% of the projects did not prepare alternate plans whereas 40% projects prepared them. In the projects where they used the alternate plans, a good proportion of the plans were prepared after the current plans failed. Majority of the project managers feel that it would be better if the alternate plans were prepared beforehand. 9% 11% 43% 4% 4% 22% 7% What was the root cause of failure? In capability of the delivery team Unavailability of resources Customer driven Competition driven Statutory regulations Technology related Others
  • 8. Fig 4: Project Managers' opinion on preparation of alternate plans Constraints in proactive planning Maximum numbers of managers want the alternate plans to be prepared in advance but this is hardly practiced in reality. There are many constraints which the managers faces because of which the alternate plans are not prepared. Some of the major constraints are: Inability to look ahead The Project Manager’s experience should enable him to think ahead of time which will help him preparing alternate plans. A seasoned project manager along with inputs from his team should be able to understand the dynamics of the project and the environment and be prepared with alternate plans. The Project Manager should be well prepared for any eventuality. He should be connected to the business to foresee disruptions. In the absence of this capability preparing alternate plans proactively is difficult. Unavailability of time (budget) When the initial plan is prepared, Project Manager invests good amount to time & effort in preparing it. Managers don’t put in enough thought and efforts while preparing the alternate plans assuming that they will not be required to use them. In terms of budget, less than 2% of it is used in preparing alternate plans. Most times this effort is not billed to customer. Creating alternate plans is considered a trivial activity and not given its due importance in terms of time & effort. 0% 10% 20% 30% 40% 50% 60% 70% 80% Can't say After the earlier plan failed Before the earlier plan failed No need to prepare alternate plans When do you think the alternate plan should be prepared?
  • 9. Unavailability of data required to prepare the plan Due to disconnect between the various teams and also between the vendor & the customer, relevant data does not reach the Project Manager. The Project Manager is not aware of many contractual agreements which they come to know later on in the project leading to unplanned changes in the plans. Not part of process to be followed Following the defined policy, processes & guidelines ensures that the basic hygiene factors are not overlooked. Preparing alternate plans should be mandated in the form of strict policy and not left on choice which is the situation at present. There is some key information needed by the managers which are helpful in overcoming the above constraints and prepare the alternate plans. These include clarity on the revised scope, revised budget, revised timelines and available resources (skill & tenure). This information is easily available once the changes actually happen in the project. Thus preparing the alternate plans after the change has happened is comparatively easier than preparing it before hand. We need to equip the project managers with information which will enable him to think ahead and prepare the alternate plans proactively. Constraints in implementing plans In situations where alternate plans are available we find that there is apprehension in the teams towards shifting to a new plan or unavailability of resources required. The teams tend to have inertia in moving over to something different. The reasons for such inertia can be classified under the following categories: Tendency to revert to earlier plan Unavailability of a detailed revised plan Unavailability of resources (Human, Hard or Software) Lack of faith in the revised plan Frequent changes in the revised plan Delay in getting Customer Approval Delay is getting Senior Management Approval The managers need to overcome the above constraints for success of the project. It is an established fact that all projects will undergo changes. To take care of the changes, effective alternate plans need to available and also be followed. Without successful implementation of alternate plans the projects cannot be successful. The best of plans will not work if not used by the team. We need to equip the project managers with guidelines on how this can be achieved. Alt-PM (Alternate Planning Methodology) This is reference tool to help projects identify the optimum number of alternate plans required under varying project conditions. Based on what we have discussed so far in the document above, we can summarize it as:
  • 10.  Initial Plans are designed to be more robust as teams spend more efforts in building them.  There is 90% probability that the project will have to change the plan. There are many reasons to support this cause.  Even though it is known, rarely the alternative plans are prepared beforehand.  Majority of the alternate plans are prepared at the spur of the moment when the previous plan fails. The effort spent in this is much less than what was spent for making the initial plan.  There is challenge in shifting from one plan to the other. There is strong need to equip the project managers with a frame work which will help them identify the need of the alternate plans, overcome the constraints in developing the alternate plans proactively and also overcome the constraints in implementing these plans. No two projects are same. Each project will have something unique about it. The challenges faced by one project are different from the ones faced by the other. Each project has its own set of data with respect to scope, budget, timelines, resources, quality and the customer. The requirement for alternate plans will also vary accordingly. Prelude Alt-PM is a methodology aimed towards helping the managers in identifying the alternate plans they should prepare at the beginning of each phase proactively based on information available. It also factors in the challenges with respect to implementation of these plans. This methodology leverages on the experience of managers and the information available from successfully implemented past projects. It provides the flexibility to users to define their own project constraints based on their project information. It captures the experience gained by project managers during execution of previous projects which were of similar type and had similar constraints. This experience is used in building a guideline. Data from similar types of past projects is then used in benchmarking the number of alternate plans to be prepared so that they can be prepared and successfully implemented. Methodology Guidelines are prepared by experienced project managers with the inputs from the data from past projects of similar type. Guidelines once prepared are reusable by projects with similar constraints. These guidelines can be progressively evolved with usage. The usage of this methodology is a two step process. Step 1: Preparation of the Guidelines & Benchmarks Preparation of the Guidelines Factors: List the constraints which are generally faced by projects of a particular type. Assign weight to each of this factor based on how strongly this constraint will affect the project plan. This is done in the scale of 0-5 where 0 means least effect and 5 means maximum effect. Table 1 below is a sample Factor Table which is prepared for development projects of similar characteristics. Phases: List the various phases of the project in a chorological order and assign weight to each phase. Assign weights based on how any change in this phase will affect the project plan. The weight is higher
  • 11. for phases where any change during that phase high effect on the plan. Table 2 below is a sample Phase Table which is prepared for development projects of similar characteristics. S. No. Factors due to which changes can happen in any project Weights based on impact of this factor on project plans in scale of 0-5 (A) 1 Team not experienced in the domain 3 2 Team not experienced in the technology 4 3 Team not skilled for gathering requirements 2 4 Team not clear on the requirements 2 5 Team resists any change 4 6 Team does not follow processes 1 7 Team is not aware of the overall project objective 1 8 Less experienced Project Manager 3 9 Delay in taking decisions by senior management 2 10 Customer not clear on the requirements 4 11 Multiple stakeholders 4 12 Delay in approvals from customer 4 13 Delay in query resolution by customer 3 14 Budget changes due to customer 2 15 Delay due to vendor 3 16 Competitors launching similar product 5 17 Human Resources not available 3 18 Software/Hardware resources not available 2 19 Required tools not available with the team 1 20 Prone to changes through regulatory policies 5 Table 1: Factors Phases in the project Weight (B) Initiation 0.25
  • 12. Table 2: Phases Defining the Benchmarks (Benchmark Table) Identify completed projects of similar characteristics. Identify the constraints that were faced by these projects during the various phases of implementation. For each of the factor, note the corresponding weights as mentioned in the Factor Table (A). For each of the factor note the phase in which they were identified and the corresponding weight from Phase Table (B). Take the product of A&B as the final weight. Since the projects are already completed, the team is able to count the number of alternate plans which were actually prepared during the execution of these projects. Using this information prepare the Benchmark Table. More the number of completed projects analyzed better will be the benchmarks. Consider the average value for the benchmarks as every project may not have prepared the same number of alternate plans even if the weights were same. Table 3 shows a sample Benchmark Table which is prepared for development projects of similar characteristics. Weight Range Recommended number of Alternate Plans Initiation Planning Requirements Design CUT Testing 0-1 0 0 0 0 0 0 2 to10 1 1 2 2 3 3 11 to 20 2 2 3 3 4 4 >20 3 3 4 4 5 5 Table 3: Benchmark Table Step 2: Calculating the number of Alternate Plans for a new project When a new project or task is assigned to the team the project manager should follow these steps to derive the optimum number of alternate plans: Calculating total weight List the constraints in the new project. These constraints should be already present in the list of the factors identified in the Factor Table. Take the corresponding weights from this table (A). For each of the factor identify the phase of the project when these constraints have maximum probability of identification and get the corresponding weight using the Phase Table (B). Calculate the final weight as (A*B). Table 4 below gives an example on how the total weight is calculated for a development project. Planning 0.25 Requirements 1 Design 2 CUT 2 Testing 3
  • 13. Deriving the number of alternate plans Calculate the sum of the total weights for each of the phases separately. Look up in the Benchmark Table and find the number of alternate plans corresponding to the total weight for that phase. Table 5 below gives an example on how the phase wise optimum number of alternate plans is derived for a development project. S. No. Factors effecting the current project Weight based on Table 1 (A) Phase when this factor may be identified Weight based on Table 2 (B) Total Weight (A * B) 1 Team not experienced in the domain 3 Initiation 0.25 0.75 2 Team not clear on the requirements 2 Design 2 4 3 Team does not follow processes 1 Requirements 1 1 4 Multiple stakeholders 4 Planning 0.25 1 5 Delay in query resolution by customer 3 Planning 0.25 0.75 6 Budget changes due to customer 2 Design 2 4 7 Competitors launching similar product 5 Design 2 10 8 Human Resources not available 3 Planning 0.25 0.75 9 Software/Hardware resources not available 2 Planning 0.25 0.5 10 Required tools not available with the team 1 CUT 2 2 11 Prone to changes through regulatory policies 5 Design 2 10 Table 4: Calculation of Total Weight Phase(s) Total weight Calculated from Table 4 Alternate Plans to be prepared Initiation 0.75 0 Planning 3 1 Requirements 1 0 Design 28 4 CUT 2 3 Testing 0 0 Table 5: Number of Alternate Plans Critical factors for success The success of this methodology depends on
  • 14.  Experience of the person/team who is preparing the guidelines & benchmarks.  Reliability of the data received from past projects.  Clear understanding of the project constraints by the person/team making the guidelines.  Updating & improving the guidelines after successful completion of each project in which these guidelines were used in calculating the number the alternate plans.  Proper understanding before using the guidelines & the benchmarks.  Proper use of the guidelines & benchmarks.  Same set of guidelines and benchmarks cannot be used for all types of projects. Only similar type of projects can use the same set of guidelines & benchmarks. For other types of projects different set of guidelines & benchmarks need to be prepared. Benefits This methodology is an attempt to help the Project Managers in managing the projects through proactive planning. The industry is highly dynamic and very uncertain. Through this methodology we are using our experience & knowledge gained through many years of project execution and trying to bring some certainty in the area of project planning. The benefits can be measured by way of  Planning for eventualities in advance and saving project effort & time leading to cost saving.  Knowledge & experience available with few individuals is documented in the form of guidelines thus enhancing knowledge sharing and reducing person dependency.  Achieving higher customer satisfaction scores by showcasing proactive project management.  Project team is open for changes as they have already planned for such situations. This makes them very flexible which is a preferred attribute of vendors.  Keeping the team members motivated as the project manager is able to plan and allocate work in a more systematic manner even when the project undergoes changes. Conclusion The industry today is mature but very dynamic. There is no one way or one golden set of rules which can resolve the issues. Through this methodology, project managers should be able to face the challenges in a more structured & organized manner.
  • 15. About the author Paramita Mukerji is an IT professional with a proven track record of 13+ years in IT services. She is currently working as Project Management Consultant with Wipro Technologies, one of the Top-4 companies in IT business in India. She possesses strong leadership capability. Using a system oriented approach; she has guided many cross functional teams across different business verticals in project management. She is an Electronics and Telecommunication Engineer by training, with several professional certifications like PMP, Prince 2 and ITILV3. She specializes in the areas of Software Project Management and Software Quality Management. She is a certified SEI Audit Team Member and KPMG Certified Internal Auditor. For further details please visit: in.linkedin.com/in/paramitamukerji/