EPBD legislation in practice:
Challenges regarding compliance
and quality of the works
Peter Wouters
Manager INIVE EEIG – Coordinator QUALICHeCK
IEE/13/610/SIO2.675574 01/03/2014-28/02/2017
Structure of the presentation
About good compliance and good quality of the works
What kind of activities in QUALICHeCK?
Outcomes of QUALICHeCK
Some considerations about future challenges
Conclusions
Structure of the presentation
About good compliance and good quality of the works
What kind of activities in QUALICHeCK?
Outcomes of QUALICHeCK
Some considerations about future challenges
Conclusions
Cost optimal
requirements
NZEB
ZEB?
PEB??
(nearly zero)
(zero)
(positive)
ALL NEW BUILDINGS!!
… and you expect a good quality
You expect a reliable label
… and you expect a good quality
You expect a reliable label
… and you expect a good quality
2 societal expectations…
• There should be (more) attention for compliance
with the EPC for new and renovated buildings
• There should be (more) attention for achieving a
good quality of the works
=?
Physical modelling
OK?
Components/systems as
assumed in calculations?
Real
occupancy
≈
?
Are the works
correctly executed?
EPC
Energy certificates with respect to ventilation …
EPC calculation
• Efficiency of heat exchanger
• Fan characteristics
• Ductwork airtightness
• Demand controlled ventilation
• …
• …
Execution of the works
• Air flow rates
• Acoustics
• …
• …
Observation:
In many countries no or nearly
no control regarding
compliance of EPC
Observation:
In many countries no or nearly
no control regarding
real performances
Poor design and
execution
• Energy performances
critical
• IAQ problematic
• acoustics
• Maintenance
• …
Which problems are often observed?
• Air flow rates ( IAQ)
• Acoustics: from system or from outside
• Draught problems
• Maintenance
• …
• Problems are found for all kind of systems
• Good execution
exists and also not
extremely difficult
2 objectives of QUALICHeCK project
• To set up a series of actions which should result in more attention and
practical initiatives for actual compliance with the claimed energy
performance for new and renovated buildings
i.e. ‘Boundary conditions which force people to do what they declare’;
• To set up a series of actions, which should result in more attention and
practical initiatives for achieving a better quality of the works,
i.e. ‘Boundary conditions which stimulate and allow the building sector to deliver good
quality of the works’.
Create
boundary conditions
for good compliance
Create
boundary conditions
for a correct execution
Structure of the presentation
About good compliance and good quality of the works
What kind of activities in QUALICHeCK?
Outcomes of QUALICHeCK
Some considerations about future challenges
Conclusions
Solutions
Easy access of compliant EPC input data
Towards more quality of the works
QUALICHeCK project (2014-2017)
Status of compliance
and quality on the ground
Towards better compliance and
effective penalties
4 focus areas in QUALICHeCK
Transmission characteristics
Ventilation and airtightness
Sustainable summer comfort techniques
Renewables in multi-energy systems
= National consortium
Structure of the presentation
About good compliance and good quality of the works
What kind of activities in QUALICHeCK?
Outcomes of QUALICHeCK
Some considerations about future challenges
Conclusions
www.qualicheck-platform.eu
Solutions
Easy access of compliant EPC input data
Towards more quality of the works
Status of compliance
and quality on the ground
Towards better compliance and
effective penalties
0
3
6
9
12
15
NUMBEROFPROJECTS
OUTOF15EXAMINED Example from CYPRUS: Deviations between U-values
in EPC and the actual U-values
Example from FRANCE:
Quality of ventilation systems in 1.287 new dwellings
44 % of multi-family dwellings don’t comply
68% of single-family dwellings don’t comply
Example from the Netherlands
November 2014:
“Ventilation Improvement plan has failed”
• This was a statement by Dutch minister
• Context:
• Findings in 2012: 50% of new residential ventilation systems don’t work well
• All stakeholders’ organisations signed in 2012 a declaration that in 2015 all systems should
function correctly
• Reasons for failure:
• … lack of interest by clients
• … economic pressure
0
150
300
450
600
750
900
1050
1200
B20
B18
B2
B22
B7
B17
B19
B8
B1
B16
B24
B23
B6
B25
B3
B10
B5
B4
B21
B15
B14
B9
B11
B12
B13
Degree-hours>27̊C(Kh)
Building
Requirement ≤150 ̊Kh
Example from ESTONIA:
Assessment of overheating
Overall building results:
17 out of 25 (68%) did not comply with the regulation
Example from SWEDEN:
Airtightness of air distribution systems
Solutions
Easy access of compliant EPC input data
Towards more quality of the works
Status of compliance
and quality on the ground
Towards better compliance and
effective penalties
Special issues by QUALICHeCK
for REHVA Journal
3 special issues are planned:
•1st issue August 2015
•2nd issue around June 2016
•3rd issue around February 2017
Procedures to obtain and prove
compliant data
Robust legal procedures in case of
non-compliance
Handling of non-compliance in
practice
There should be clear procedures
what must be done
There should be clear legal procedures how
to decide on non-compliance and related actions
There should be an effective control
and sanctions if non-compliance
Source book “Compliance in relation to EPC”!Societalsupport!
Procedures to obtain and prove
compliant data
Procedures to obtain and prove
compliant data
Robust legal procedures in case of
non-compliance
Handling of non-compliance in
practice
There should be clear procedures
what must be done
There should be clear legal procedures how
to decide on non-compliance and related actions
There should be an effective control
and sanctions if non-compliance
!Societalsupport!
Procedures to obtain and prove
compliant data
STEP 1: Procedures to obtain and prove
compliant data
Procedures to obtain and prove
compliant data
Robust legal procedures in case of
non-compliance
Handling of non-compliance in
practice
There should be clear procedures
what must be done
There should be clear legal procedures how
to decide on non-compliance and related actions
There should be an effective control
and sanctions if non-compliance
!Societalsupport!
Procedures to obtain and prove
compliant data
STEP 2: Robust legal procedures
in case of non-compliance
Procedures to obtain and prove
compliant data
Robust legal procedures in case of
non-compliance
Handling of non-compliance in
practice
There should be clear procedures
what must be done
There should be clear legal procedures how
to decide on non-compliance and related actions
There should be an effective control
and sanctions if non-compliance
!Societalsupport!
Procedures to obtain and prove
compliant data
STEP 3: Handling of non-compliance in
practice
Timeline for both QUALICHeCK sourcebooks…
2nd QUALICHeCK conference Brussels
September 4 2015
Focus on
- “better compliance/quality of the works”
- “ Review of EPBD recast?”

International QUALICHeCK workshops
(Supported by REHVA)
Transmission characteristics
Ventilation and airtightness
Sustainable summer comfort techniques
Renewables in multi-energy systems
LUND - 16-17 March 2015
ATHENS – 9-10 March 2016
TALLINN – October 2016
LYON – ~January 2017
2nd QUALICHeCK workshop ‘Sustainable summer comfort’
March 9-10 2016 Athens (Greece)
2-days workshop
Technologies to be covered:
• Solar control
• Thermal mass
• Ventilative cooling
• Cool roofs
• Daylighting
Structure of the presentation
About good compliance and good quality of the works
What kind of activities in QUALICHeCK?
Outcomes of QUALICHeCK
Some considerations about future challenges
Conclusions
Some considerations about future challenges
•Should there be more attention by the Member
States for compliance and quality of the works?
•Should these issues receive attention in the
framework of a review of the EPBD?
Structure of the presentation
About good compliance and good quality of the works
What kind of activities in QUALICHeCK?
Outcomes of QUALICHeCK
Some considerations about future challenges
Conclusions
Conclusions
• We have to be ambitious in terms of the requirements imposed
for the energy performances of new and renovated buildings
• But it is also very important to create boundary conditions that:
• Result in good compliance (a ‘reliable’ EPC)
• Result in good quality of the works
The sole responsibility for the content of this presentation lies with the authors. It does not necessarily reflect the opinion of the European Union.
Neither the EASME nor the European Commission are responsible for any use that may be made of the information contained therein.

Contenu connexe

En vedette

SharePoint Usability and Accesibility Best Practices Including 508 Compliance...
SharePoint Usability and Accesibility Best Practices Including 508 Compliance...SharePoint Usability and Accesibility Best Practices Including 508 Compliance...
SharePoint Usability and Accesibility Best Practices Including 508 Compliance...EPC Group
 
EPC Group SharePoint ROI Business Value Case Study - SharePoint Consulting
EPC Group SharePoint ROI Business Value Case Study - SharePoint ConsultingEPC Group SharePoint ROI Business Value Case Study - SharePoint Consulting
EPC Group SharePoint ROI Business Value Case Study - SharePoint ConsultingEPC Group
 
Epc industry in india report by jasubhai media & kpmg
Epc industry in india  report by jasubhai media & kpmgEpc industry in india  report by jasubhai media & kpmg
Epc industry in india report by jasubhai media & kpmgraghunathan janarthanan
 
Law - Rights of an unpaid seller
Law - Rights of an unpaid sellerLaw - Rights of an unpaid seller
Law - Rights of an unpaid sellerMekayeel Hasan
 
Rights of an unpaid seller
Rights of an unpaid sellerRights of an unpaid seller
Rights of an unpaid sellerSweetp999
 
Compliance under labour laws in india
Compliance under labour laws in indiaCompliance under labour laws in india
Compliance under labour laws in indiaAmrik Singh
 

En vedette (6)

SharePoint Usability and Accesibility Best Practices Including 508 Compliance...
SharePoint Usability and Accesibility Best Practices Including 508 Compliance...SharePoint Usability and Accesibility Best Practices Including 508 Compliance...
SharePoint Usability and Accesibility Best Practices Including 508 Compliance...
 
EPC Group SharePoint ROI Business Value Case Study - SharePoint Consulting
EPC Group SharePoint ROI Business Value Case Study - SharePoint ConsultingEPC Group SharePoint ROI Business Value Case Study - SharePoint Consulting
EPC Group SharePoint ROI Business Value Case Study - SharePoint Consulting
 
Epc industry in india report by jasubhai media & kpmg
Epc industry in india  report by jasubhai media & kpmgEpc industry in india  report by jasubhai media & kpmg
Epc industry in india report by jasubhai media & kpmg
 
Law - Rights of an unpaid seller
Law - Rights of an unpaid sellerLaw - Rights of an unpaid seller
Law - Rights of an unpaid seller
 
Rights of an unpaid seller
Rights of an unpaid sellerRights of an unpaid seller
Rights of an unpaid seller
 
Compliance under labour laws in india
Compliance under labour laws in indiaCompliance under labour laws in india
Compliance under labour laws in india
 

Similaire à EPBD legislation in practice - challenges regarding compliance and quality of the works

BUS Methodology presentation from 21st November 2013
BUS Methodology presentation from 21st November 2013BUS Methodology presentation from 21st November 2013
BUS Methodology presentation from 21st November 2013CIBSE_Yorkshire
 
An introduction to EECO2-Energy Efficiency Consultancy Limited
An introduction to EECO2-Energy Efficiency Consultancy LimitedAn introduction to EECO2-Energy Efficiency Consultancy Limited
An introduction to EECO2-Energy Efficiency Consultancy LimitedEECO2
 
EECO2 GMP critical HVAC energy cost reduction
EECO2 GMP critical HVAC energy cost reductionEECO2 GMP critical HVAC energy cost reduction
EECO2 GMP critical HVAC energy cost reductionKeith Beattie
 
Ventilation and building airtightness: Inspection schemes in belgium
Ventilation and building airtightness: Inspection schemes in belgiumVentilation and building airtightness: Inspection schemes in belgium
Ventilation and building airtightness: Inspection schemes in belgiumSustainableEnergyAut
 
Towards a systems approach in Ecodesign and Energy Labelling: How to make the...
Towards a systems approach in Ecodesign and Energy Labelling: How to make the...Towards a systems approach in Ecodesign and Energy Labelling: How to make the...
Towards a systems approach in Ecodesign and Energy Labelling: How to make the...Leonardo ENERGY
 
GENERATION Project; Alan Kiff, Ark Specialist Services Limited
GENERATION Project; Alan Kiff, Ark Specialist Services LimitedGENERATION Project; Alan Kiff, Ark Specialist Services Limited
GENERATION Project; Alan Kiff, Ark Specialist Services LimitedSustainable Business Partnership
 
TAS-S Seminar “From Continuous Monitoring to Continuous Cloud Cybersecurity C...
TAS-S Seminar “From Continuous Monitoring to Continuous Cloud Cybersecurity C...TAS-S Seminar “From Continuous Monitoring to Continuous Cloud Cybersecurity C...
TAS-S Seminar “From Continuous Monitoring to Continuous Cloud Cybersecurity C...MEDINA
 
CRISP project: overview of findings and lessons learned.
CRISP project: overview of findings and lessons learned.CRISP project: overview of findings and lessons learned.
CRISP project: overview of findings and lessons learned.Trilateral Research
 
Bde sc3 2nd_workshop_2016_10_04_p07_laustsen_jens
Bde sc3 2nd_workshop_2016_10_04_p07_laustsen_jensBde sc3 2nd_workshop_2016_10_04_p07_laustsen_jens
Bde sc3 2nd_workshop_2016_10_04_p07_laustsen_jensBigData_Europe
 
Plaquette rescoll etv en
Plaquette rescoll etv enPlaquette rescoll etv en
Plaquette rescoll etv enJosé ALCORTA
 
Regulating for quality in assessment
Regulating for quality in assessmentRegulating for quality in assessment
Regulating for quality in assessmentOfqual Slideshare
 
US Department of Energy's Uniform Methods Project
US Department of Energy's Uniform Methods ProjectUS Department of Energy's Uniform Methods Project
US Department of Energy's Uniform Methods ProjectLeonardo ENERGY
 
Enforcement Reforms at ANEEL: The implementation of OECD’s Best Practice Prin...
Enforcement Reforms at ANEEL: The implementation of OECD’s Best Practice Prin...Enforcement Reforms at ANEEL: The implementation of OECD’s Best Practice Prin...
Enforcement Reforms at ANEEL: The implementation of OECD’s Best Practice Prin...OECD Governance
 
How to deliver improved building performance and productivity
How to deliver improved building performance and productivityHow to deliver improved building performance and productivity
How to deliver improved building performance and productivityGlobal Business Intelligence
 

Similaire à EPBD legislation in practice - challenges regarding compliance and quality of the works (20)

BUS Methodology presentation from 21st November 2013
BUS Methodology presentation from 21st November 2013BUS Methodology presentation from 21st November 2013
BUS Methodology presentation from 21st November 2013
 
An introduction to EECO2-Energy Efficiency Consultancy Limited
An introduction to EECO2-Energy Efficiency Consultancy LimitedAn introduction to EECO2-Energy Efficiency Consultancy Limited
An introduction to EECO2-Energy Efficiency Consultancy Limited
 
EECO2 GMP critical HVAC energy cost reduction
EECO2 GMP critical HVAC energy cost reductionEECO2 GMP critical HVAC energy cost reduction
EECO2 GMP critical HVAC energy cost reduction
 
Ventilation and building airtightness: Inspection schemes in belgium
Ventilation and building airtightness: Inspection schemes in belgiumVentilation and building airtightness: Inspection schemes in belgium
Ventilation and building airtightness: Inspection schemes in belgium
 
Towards a systems approach in Ecodesign and Energy Labelling: How to make the...
Towards a systems approach in Ecodesign and Energy Labelling: How to make the...Towards a systems approach in Ecodesign and Energy Labelling: How to make the...
Towards a systems approach in Ecodesign and Energy Labelling: How to make the...
 
Maintaining Standards
Maintaining StandardsMaintaining Standards
Maintaining Standards
 
P.Maurer_CENCENELEC.pdf
P.Maurer_CENCENELEC.pdfP.Maurer_CENCENELEC.pdf
P.Maurer_CENCENELEC.pdf
 
GENERATION Project; Alan Kiff, Ark Specialist Services Limited
GENERATION Project; Alan Kiff, Ark Specialist Services LimitedGENERATION Project; Alan Kiff, Ark Specialist Services Limited
GENERATION Project; Alan Kiff, Ark Specialist Services Limited
 
TAS-S Seminar “From Continuous Monitoring to Continuous Cloud Cybersecurity C...
TAS-S Seminar “From Continuous Monitoring to Continuous Cloud Cybersecurity C...TAS-S Seminar “From Continuous Monitoring to Continuous Cloud Cybersecurity C...
TAS-S Seminar “From Continuous Monitoring to Continuous Cloud Cybersecurity C...
 
CRISP project: overview of findings and lessons learned.
CRISP project: overview of findings and lessons learned.CRISP project: overview of findings and lessons learned.
CRISP project: overview of findings and lessons learned.
 
Bde sc3 2nd_workshop_2016_10_04_p07_laustsen_jens
Bde sc3 2nd_workshop_2016_10_04_p07_laustsen_jensBde sc3 2nd_workshop_2016_10_04_p07_laustsen_jens
Bde sc3 2nd_workshop_2016_10_04_p07_laustsen_jens
 
Plaquette rescoll etv en
Plaquette rescoll etv enPlaquette rescoll etv en
Plaquette rescoll etv en
 
Quality oepm junio2011
Quality  oepm junio2011Quality  oepm junio2011
Quality oepm junio2011
 
Up to the Measure
Up to the MeasureUp to the Measure
Up to the Measure
 
GHG Programs in the Compliance and Voluntary Markets
GHG Programs in the Compliance and Voluntary MarketsGHG Programs in the Compliance and Voluntary Markets
GHG Programs in the Compliance and Voluntary Markets
 
Manuel Villa _Energy Transition and Energy Regulatory Sandboxes_Funseam Semin...
Manuel Villa _Energy Transition and Energy Regulatory Sandboxes_Funseam Semin...Manuel Villa _Energy Transition and Energy Regulatory Sandboxes_Funseam Semin...
Manuel Villa _Energy Transition and Energy Regulatory Sandboxes_Funseam Semin...
 
Regulating for quality in assessment
Regulating for quality in assessmentRegulating for quality in assessment
Regulating for quality in assessment
 
US Department of Energy's Uniform Methods Project
US Department of Energy's Uniform Methods ProjectUS Department of Energy's Uniform Methods Project
US Department of Energy's Uniform Methods Project
 
Enforcement Reforms at ANEEL: The implementation of OECD’s Best Practice Prin...
Enforcement Reforms at ANEEL: The implementation of OECD’s Best Practice Prin...Enforcement Reforms at ANEEL: The implementation of OECD’s Best Practice Prin...
Enforcement Reforms at ANEEL: The implementation of OECD’s Best Practice Prin...
 
How to deliver improved building performance and productivity
How to deliver improved building performance and productivityHow to deliver improved building performance and productivity
How to deliver improved building performance and productivity
 

Dernier

WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.Christina Parmionova
 
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdfMonastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdfCharlynTorres1
 
High-Level Thematic Event on Tourism - SUSTAINABILITY WEEK 2024- United Natio...
High-Level Thematic Event on Tourism - SUSTAINABILITY WEEK 2024- United Natio...High-Level Thematic Event on Tourism - SUSTAINABILITY WEEK 2024- United Natio...
High-Level Thematic Event on Tourism - SUSTAINABILITY WEEK 2024- United Natio...Christina Parmionova
 
call girls in Kirti Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Kirti Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Kirti Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Kirti Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
Canadian Immigration Tracker - Key Slides - February 2024.pdf
Canadian Immigration Tracker - Key Slides - February 2024.pdfCanadian Immigration Tracker - Key Slides - February 2024.pdf
Canadian Immigration Tracker - Key Slides - February 2024.pdfAndrew Griffith
 
call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...saminamagar
 
If there is a Hell on Earth, it is the Lives of Children in Gaza.pdf
If there is a Hell on Earth, it is the Lives of Children in Gaza.pdfIf there is a Hell on Earth, it is the Lives of Children in Gaza.pdf
If there is a Hell on Earth, it is the Lives of Children in Gaza.pdfKatrina Sriranpong
 
办理约克大学毕业证成绩单|购买加拿大文凭证书
办理约克大学毕业证成绩单|购买加拿大文凭证书办理约克大学毕业证成绩单|购买加拿大文凭证书
办理约克大学毕业证成绩单|购买加拿大文凭证书zdzoqco
 
In credit? Assessing where Universal Credit’s long rollout has left the benef...
In credit? Assessing where Universal Credit’s long rollout has left the benef...In credit? Assessing where Universal Credit’s long rollout has left the benef...
In credit? Assessing where Universal Credit’s long rollout has left the benef...ResolutionFoundation
 
Make Charity for Poor Students to Strong Kurnool
Make Charity for Poor Students to Strong KurnoolMake Charity for Poor Students to Strong Kurnool
Make Charity for Poor Students to Strong KurnoolSERUDS INDIA
 
call girls in DLF Phase 1 gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in DLF Phase 1  gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝...call girls in DLF Phase 1  gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in DLF Phase 1 gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...saminamagar
 
call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
Yellow is My Favorite Color By Annabelle.pdf
Yellow is My Favorite Color By Annabelle.pdfYellow is My Favorite Color By Annabelle.pdf
Yellow is My Favorite Color By Annabelle.pdfAmir Saranga
 
2023 Ecological Profile of Ilocos Norte.pdf
2023 Ecological Profile of Ilocos Norte.pdf2023 Ecological Profile of Ilocos Norte.pdf
2023 Ecological Profile of Ilocos Norte.pdfilocosnortegovph
 
call girls in sector 24 Gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in sector 24 Gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in sector 24 Gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in sector 24 Gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
(格鲁斯特大学毕业证学位证成绩单-烫金工艺)
(格鲁斯特大学毕业证学位证成绩单-烫金工艺)(格鲁斯特大学毕业证学位证成绩单-烫金工艺)
(格鲁斯特大学毕业证学位证成绩单-烫金工艺)twfkn8xj
 
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
Call Girls In Pullman Hotel New Delhi Aerocity 9873777170
Call Girls In Pullman Hotel New Delhi Aerocity 9873777170Call Girls In Pullman Hotel New Delhi Aerocity 9873777170
Call Girls In Pullman Hotel New Delhi Aerocity 9873777170Sonam Pathan
 
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 

Dernier (20)

WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.
 
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdfMonastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
 
High-Level Thematic Event on Tourism - SUSTAINABILITY WEEK 2024- United Natio...
High-Level Thematic Event on Tourism - SUSTAINABILITY WEEK 2024- United Natio...High-Level Thematic Event on Tourism - SUSTAINABILITY WEEK 2024- United Natio...
High-Level Thematic Event on Tourism - SUSTAINABILITY WEEK 2024- United Natio...
 
call girls in Kirti Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Kirti Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Kirti Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Kirti Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
Canadian Immigration Tracker - Key Slides - February 2024.pdf
Canadian Immigration Tracker - Key Slides - February 2024.pdfCanadian Immigration Tracker - Key Slides - February 2024.pdf
Canadian Immigration Tracker - Key Slides - February 2024.pdf
 
call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in Mukherjee Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
 
If there is a Hell on Earth, it is the Lives of Children in Gaza.pdf
If there is a Hell on Earth, it is the Lives of Children in Gaza.pdfIf there is a Hell on Earth, it is the Lives of Children in Gaza.pdf
If there is a Hell on Earth, it is the Lives of Children in Gaza.pdf
 
办理约克大学毕业证成绩单|购买加拿大文凭证书
办理约克大学毕业证成绩单|购买加拿大文凭证书办理约克大学毕业证成绩单|购买加拿大文凭证书
办理约克大学毕业证成绩单|购买加拿大文凭证书
 
In credit? Assessing where Universal Credit’s long rollout has left the benef...
In credit? Assessing where Universal Credit’s long rollout has left the benef...In credit? Assessing where Universal Credit’s long rollout has left the benef...
In credit? Assessing where Universal Credit’s long rollout has left the benef...
 
Make Charity for Poor Students to Strong Kurnool
Make Charity for Poor Students to Strong KurnoolMake Charity for Poor Students to Strong Kurnool
Make Charity for Poor Students to Strong Kurnool
 
call girls in DLF Phase 1 gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in DLF Phase 1  gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝...call girls in DLF Phase 1  gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in DLF Phase 1 gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
 
call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
Yellow is My Favorite Color By Annabelle.pdf
Yellow is My Favorite Color By Annabelle.pdfYellow is My Favorite Color By Annabelle.pdf
Yellow is My Favorite Color By Annabelle.pdf
 
2023 Ecological Profile of Ilocos Norte.pdf
2023 Ecological Profile of Ilocos Norte.pdf2023 Ecological Profile of Ilocos Norte.pdf
2023 Ecological Profile of Ilocos Norte.pdf
 
call girls in sector 24 Gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in sector 24 Gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in sector 24 Gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in sector 24 Gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
(格鲁斯特大学毕业证学位证成绩单-烫金工艺)
(格鲁斯特大学毕业证学位证成绩单-烫金工艺)(格鲁斯特大学毕业证学位证成绩单-烫金工艺)
(格鲁斯特大学毕业证学位证成绩单-烫金工艺)
 
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
Call Girls In Pullman Hotel New Delhi Aerocity 9873777170
Call Girls In Pullman Hotel New Delhi Aerocity 9873777170Call Girls In Pullman Hotel New Delhi Aerocity 9873777170
Call Girls In Pullman Hotel New Delhi Aerocity 9873777170
 
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
Hot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort ServiceHot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort Service
 

EPBD legislation in practice - challenges regarding compliance and quality of the works

  • 1. EPBD legislation in practice: Challenges regarding compliance and quality of the works Peter Wouters Manager INIVE EEIG – Coordinator QUALICHeCK IEE/13/610/SIO2.675574 01/03/2014-28/02/2017
  • 2. Structure of the presentation About good compliance and good quality of the works What kind of activities in QUALICHeCK? Outcomes of QUALICHeCK Some considerations about future challenges Conclusions
  • 3. Structure of the presentation About good compliance and good quality of the works What kind of activities in QUALICHeCK? Outcomes of QUALICHeCK Some considerations about future challenges Conclusions
  • 5. … and you expect a good quality You expect a reliable label
  • 6. … and you expect a good quality You expect a reliable label
  • 7. … and you expect a good quality
  • 8. 2 societal expectations… • There should be (more) attention for compliance with the EPC for new and renovated buildings • There should be (more) attention for achieving a good quality of the works
  • 9. =? Physical modelling OK? Components/systems as assumed in calculations? Real occupancy ≈ ? Are the works correctly executed? EPC
  • 10. Energy certificates with respect to ventilation … EPC calculation • Efficiency of heat exchanger • Fan characteristics • Ductwork airtightness • Demand controlled ventilation • … • … Execution of the works • Air flow rates • Acoustics • … • … Observation: In many countries no or nearly no control regarding compliance of EPC Observation: In many countries no or nearly no control regarding real performances
  • 11. Poor design and execution • Energy performances critical • IAQ problematic • acoustics • Maintenance • …
  • 12.
  • 13. Which problems are often observed? • Air flow rates ( IAQ) • Acoustics: from system or from outside • Draught problems • Maintenance • … • Problems are found for all kind of systems • Good execution exists and also not extremely difficult
  • 14.
  • 15. 2 objectives of QUALICHeCK project • To set up a series of actions which should result in more attention and practical initiatives for actual compliance with the claimed energy performance for new and renovated buildings i.e. ‘Boundary conditions which force people to do what they declare’; • To set up a series of actions, which should result in more attention and practical initiatives for achieving a better quality of the works, i.e. ‘Boundary conditions which stimulate and allow the building sector to deliver good quality of the works’.
  • 16. Create boundary conditions for good compliance Create boundary conditions for a correct execution
  • 17. Structure of the presentation About good compliance and good quality of the works What kind of activities in QUALICHeCK? Outcomes of QUALICHeCK Some considerations about future challenges Conclusions
  • 18. Solutions Easy access of compliant EPC input data Towards more quality of the works QUALICHeCK project (2014-2017) Status of compliance and quality on the ground Towards better compliance and effective penalties
  • 19. 4 focus areas in QUALICHeCK Transmission characteristics Ventilation and airtightness Sustainable summer comfort techniques Renewables in multi-energy systems
  • 21. Structure of the presentation About good compliance and good quality of the works What kind of activities in QUALICHeCK? Outcomes of QUALICHeCK Some considerations about future challenges Conclusions
  • 23.
  • 24. Solutions Easy access of compliant EPC input data Towards more quality of the works Status of compliance and quality on the ground Towards better compliance and effective penalties
  • 25. 0 3 6 9 12 15 NUMBEROFPROJECTS OUTOF15EXAMINED Example from CYPRUS: Deviations between U-values in EPC and the actual U-values
  • 26. Example from FRANCE: Quality of ventilation systems in 1.287 new dwellings 44 % of multi-family dwellings don’t comply 68% of single-family dwellings don’t comply
  • 27. Example from the Netherlands November 2014: “Ventilation Improvement plan has failed” • This was a statement by Dutch minister • Context: • Findings in 2012: 50% of new residential ventilation systems don’t work well • All stakeholders’ organisations signed in 2012 a declaration that in 2015 all systems should function correctly • Reasons for failure: • … lack of interest by clients • … economic pressure
  • 29. Example from SWEDEN: Airtightness of air distribution systems
  • 30. Solutions Easy access of compliant EPC input data Towards more quality of the works Status of compliance and quality on the ground Towards better compliance and effective penalties
  • 31.
  • 32.
  • 33. Special issues by QUALICHeCK for REHVA Journal 3 special issues are planned: •1st issue August 2015 •2nd issue around June 2016 •3rd issue around February 2017
  • 34. Procedures to obtain and prove compliant data Robust legal procedures in case of non-compliance Handling of non-compliance in practice There should be clear procedures what must be done There should be clear legal procedures how to decide on non-compliance and related actions There should be an effective control and sanctions if non-compliance Source book “Compliance in relation to EPC”!Societalsupport! Procedures to obtain and prove compliant data
  • 35. Procedures to obtain and prove compliant data Robust legal procedures in case of non-compliance Handling of non-compliance in practice There should be clear procedures what must be done There should be clear legal procedures how to decide on non-compliance and related actions There should be an effective control and sanctions if non-compliance !Societalsupport! Procedures to obtain and prove compliant data STEP 1: Procedures to obtain and prove compliant data
  • 36. Procedures to obtain and prove compliant data Robust legal procedures in case of non-compliance Handling of non-compliance in practice There should be clear procedures what must be done There should be clear legal procedures how to decide on non-compliance and related actions There should be an effective control and sanctions if non-compliance !Societalsupport! Procedures to obtain and prove compliant data STEP 2: Robust legal procedures in case of non-compliance
  • 37. Procedures to obtain and prove compliant data Robust legal procedures in case of non-compliance Handling of non-compliance in practice There should be clear procedures what must be done There should be clear legal procedures how to decide on non-compliance and related actions There should be an effective control and sanctions if non-compliance !Societalsupport! Procedures to obtain and prove compliant data STEP 3: Handling of non-compliance in practice
  • 38. Timeline for both QUALICHeCK sourcebooks…
  • 39. 2nd QUALICHeCK conference Brussels September 4 2015 Focus on - “better compliance/quality of the works” - “ Review of EPBD recast?” 
  • 40. International QUALICHeCK workshops (Supported by REHVA) Transmission characteristics Ventilation and airtightness Sustainable summer comfort techniques Renewables in multi-energy systems LUND - 16-17 March 2015 ATHENS – 9-10 March 2016 TALLINN – October 2016 LYON – ~January 2017
  • 41. 2nd QUALICHeCK workshop ‘Sustainable summer comfort’ March 9-10 2016 Athens (Greece) 2-days workshop Technologies to be covered: • Solar control • Thermal mass • Ventilative cooling • Cool roofs • Daylighting
  • 42. Structure of the presentation About good compliance and good quality of the works What kind of activities in QUALICHeCK? Outcomes of QUALICHeCK Some considerations about future challenges Conclusions
  • 43. Some considerations about future challenges •Should there be more attention by the Member States for compliance and quality of the works? •Should these issues receive attention in the framework of a review of the EPBD?
  • 44. Structure of the presentation About good compliance and good quality of the works What kind of activities in QUALICHeCK? Outcomes of QUALICHeCK Some considerations about future challenges Conclusions
  • 45. Conclusions • We have to be ambitious in terms of the requirements imposed for the energy performances of new and renovated buildings • But it is also very important to create boundary conditions that: • Result in good compliance (a ‘reliable’ EPC) • Result in good quality of the works The sole responsibility for the content of this presentation lies with the authors. It does not necessarily reflect the opinion of the European Union. Neither the EASME nor the European Commission are responsible for any use that may be made of the information contained therein.