Planning for Logistics
John Roberts
Solicitor
Planning Team
Introduction
• Planning system increasingly complex
• Planning permission required for operational on-site
facilities
• Focus
– Overview of the planning system
– Key themes in planning development
– Case studies – demonstrate planning policies in action
Background
• 2 tiers of planning policy for England: national & local
• Previously intermediate third tier – regional
– Regional Spatial Strategies
– Abolished by Coalition Government
• National and local tiers in state of transition
National Planning Policy
• National Planning Policy Framework
– Introduced on 27 March 2012
• Previously:
– PPS’s, PPG’s, Circulars, Letters to Chief Planning Officers
– 44 documents
– Over 1,300 pages
– 2 decades of policy development
• New document:
– Single document
– 59 pages
What does it do?
• Sets out the Government’s planning policies for England
and how these are expected to be applied
• Guidance for local planning authorities
– Drawing up local plans
– Determining planning applications
• Local plans should be consistent with the Framework
Aims
• Decision-making driven down to the local level
– Ties in with localism agenda
• Replaced documents were very detailed and prescriptive
• New approach: just bare bones within national policy
– Local councils to produce their own distinctive plans
Controversy
Opposition
“(The) Slim, 52-page draft National Planning Policy
Framework… more unexploded mines per square inch
than the most liberally strewn battlefield”
Daily Telegraph
“… a public relations exercise which will in effect
encourage privatisation of services, open market sale of
public assets and, through the presumption to develop,
render all communities defenceless in the face of the
greed of developers”
Morning Star
Local Planning Policy
• Where detail is found
• Currently Local Plans or Unitary Development Plans
– Set out policies thematically
• Local policy changing
– Local Development Frameworks
– Local Plans
• Few local authorities completed process in timely manner
– Result is “Saved” policies
• Draft policies can be taken into account
Presumption in favour of sustainable
development
• At the heart of the planning system is a presumption in
favour of sustainable development, which should be seen
as a golden thread running through both plan-making and
decision-taking
• Reference to UN definition of sustainable development
• 3 dimensions: economic, social & environmental
Key Considerations
• Key: frontload preparation work
– Within planning application
– Also at pre-application stage
• Identify requirements and stumbling blocks as early as
possible
– Talk to Planning Officers
– Sound them out on their requirements
– Make application documents detailed
• If anything is missing, somebody will spot it!
– Delays
24/7 Working
Lighting
Refrigeration Units
Environment & Protected Species
Lorries
Drainage & Flooding
Substations
Statutory Agreements
Planning Policy in Action
• 3 case studies:
1. World Logistics Hub, Manchester Airport
2. New Hythe Industrial Estate, Kent
3. Lancashire Business Park, Leyland
Case Study 1 – World Logistics Hub
The Proposal
• Airport related freight logistics hub
• Up to 1.4 million square feet
– Units ranging from 7,500 to 200,000 square feet
• Retail and amenity facilities for future workforce
• Nearly 1,500 car parking spaces
• Site: 51.7 hectares
– Mainly grazing land, surrounded by hedgerows, contains ponds
– Bordered by farmland and woodland: SSSI & SBI
Main Issue – Green Belt Location
• Proposal within draft Manchester Airport Masterplan, 2006
– Identified extensions to Airport’s Operational Area and land to be removed
from the green belt
• Masterplan considered in preparing Core Strategy
– This reviewed the green belt boundary
• Core Strategy considered at Public Inquiry, 2011
– Exceptional circumstances to justify altering green belt boundary
• Council considered principle of logistics hub acceptable
– But … other issues required consideration
Other Issues
• Visual amenity
– Council accepted there would not be an unduly adverse impact
• Residential amenity
– Conditions dealing with dust control and acoustic insulation
• Highway network
– Able to take advantage of highways improvements connected to the
second runway at Manchester Airport
• Nature conservation
– 14.8 hectares proposed as landscape and ecological mitigation area
– Enables compliance with the European Habitats Directive
Case Study 2 – Aylesford, Kent
The Proposal
• 3 warehouse units
– One of just over 9,000 square metres
– One of approximately 6,500 square metres
– One of just under 4,000 square metres
• Full provision for car and lorry parking
• Site has long history of industrial use
– Safeguarded for employment use in Tonbridge and Malling Council’s
Land Allocations Development Plan Document, 2008
• 6.81 hectares & within wider industrial estate
– New housing development to the west
Principle of Development
• Acceptable as site within area allocated for employment
use
• Long previous use of site formed basis of Council’s
assessment of other issues
– Existing buildings remained on site at time application was considered
– Could have been fully reoccupied at any time without further approval
– Application was assessed against this background of historic use of site
• Key: Impact be no worse than and, if possible, less than
the previous unfettered use rights of the site
Other Issues
• Design
– New warehouses cumulatively smaller than existing building
• Lorry routing
– Access only from eastern side (away from housing development to west)
– Buildings on industrial estate act as noise buffer between traffic & houses
• 24 hour operation
– Historically, no controls over hours of use
• Conditions to mitigate impacts of development
– Acoustic barrier to be installed before units can be operational
– Details of external lighting submitted & agreed prior to installation
Case Study 3 – Leyland, Lancashire
The Proposal
• 3 storage and distribution warehouses
• Nearly 400,000 square feet of accommodation
– 2 units of 166,000 square feet each
– 1 unit of 50,000 square feet
• Associated car parking and secure compound areas
• Replace large warehouse destroyed by fire in 2011
• Surrounded on three sides by industrial units & offices
– West Coast Mainline to the east
Principle of Development
• National Planning Policy Framework
– Planning system should support sustainable economic growth
– Encourage, rather than impede, sustainable growth
• Local planning policy – South Ribble Local Plan
– Within main existing employment areas, planning permission should be
granted for expansion/redevelopment of industrial & business purposes
• Scheme in accordance with both national and local policy
– No problem with principle of development
Other Issues
• Design
– Local policy requires well related to neighbouring buildings and the locality
– Modern, standard industrial buildings, finished in metal cladding, proposed
– Existing buildings within Business Park of similar height and materials
• Parking
– Local policy requires adequate level of car parking and servicing
– County Highways objected to initial plans – revised to deal with this
• Landscaping
– Six silver birch trees to be removed to facilitate development
– Replacement planting to compensate
– Conditions for landscaping plan and management regime
Conclusion
• Identify the issues
• Work around them
• Explain how an application complies with planning policy
– National and local
• If compliance is not possible, justify any departure from
policy thoroughly
Logistics 2013: John Roberts

Contenu connexe

Tendances

Overview of LACMTA Green Construction Policy
Overview of LACMTA Green Construction PolicyOverview of LACMTA Green Construction Policy
Overview of LACMTA Green Construction Policycliban
 
GSSD13 Solution Forum 6 (UNECE) - Action plan for Energy- efficient Housing i...
GSSD13 Solution Forum 6 (UNECE) - Action plan for Energy- efficient Housing i...GSSD13 Solution Forum 6 (UNECE) - Action plan for Energy- efficient Housing i...
GSSD13 Solution Forum 6 (UNECE) - Action plan for Energy- efficient Housing i...Global South-South Development Expo
 
Housing Standards Review: DCLG Presentation
Housing Standards Review: DCLG PresentationHousing Standards Review: DCLG Presentation
Housing Standards Review: DCLG PresentationPAS_Team
 
LTCP meeting 11-16-05
LTCP meeting 11-16-05LTCP meeting 11-16-05
LTCP meeting 11-16-05HartTWI
 
Jasper Library Site Recommendations Handouts update 091114
Jasper Library Site Recommendations Handouts update 091114Jasper Library Site Recommendations Handouts update 091114
Jasper Library Site Recommendations Handouts update 091114Matthew Crane
 
Central- West Open House - April 2018
Central- West Open House - April 2018Central- West Open House - April 2018
Central- West Open House - April 2018Crosstown TO
 
EU Circular Economy Programme and the Built Environment #cethinking
EU Circular Economy Programme and the Built Environment #cethinkingEU Circular Economy Programme and the Built Environment #cethinking
EU Circular Economy Programme and the Built Environment #cethinkingCircular Economy Thinking
 
Designing for the Circular Economy – the Gatwick Airport Project #cethinking
Designing for the Circular Economy – the Gatwick Airport Project #cethinkingDesigning for the Circular Economy – the Gatwick Airport Project #cethinking
Designing for the Circular Economy – the Gatwick Airport Project #cethinkingCircular Economy Thinking
 
West district library presentation
West district library presentationWest district library presentation
West district library presentationottawapubliclibrary
 
APNIC 23 - Policy SIG - prop-046: IPv4 Countdown Policy Proposal
APNIC 23 - Policy SIG - prop-046: IPv4 Countdown Policy ProposalAPNIC 23 - Policy SIG - prop-046: IPv4 Countdown Policy Proposal
APNIC 23 - Policy SIG - prop-046: IPv4 Countdown Policy ProposalAPNIC
 
Plaša mēroga PPP EPC pieeja Ļubļanas pilsētas ēku atjaunošanai
Plaša mēroga PPP EPC pieeja Ļubļanas pilsētas ēku atjaunošanaiPlaša mēroga PPP EPC pieeja Ļubļanas pilsētas ēku atjaunošanai
Plaša mēroga PPP EPC pieeja Ļubļanas pilsētas ēku atjaunošanaiEkonomikas ministrija/ Dzīvo siltāk
 
PLS 2018: Interest-free financing for energy efficient Street lighting (Kent ...
PLS 2018: Interest-free financing for energy efficient Street lighting (Kent ...PLS 2018: Interest-free financing for energy efficient Street lighting (Kent ...
PLS 2018: Interest-free financing for energy efficient Street lighting (Kent ...Institution of Lighting Professionals
 
Advancing Sustainability in Discretionary Review 2
Advancing Sustainability in Discretionary Review 2Advancing Sustainability in Discretionary Review 2
Advancing Sustainability in Discretionary Review 2Wallace Roberts & Todd
 
Sasniedzot energoefektivitātes mērķus publiskajā sektorā ar ārpus bilances pr...
Sasniedzot energoefektivitātes mērķus publiskajā sektorā ar ārpus bilances pr...Sasniedzot energoefektivitātes mērķus publiskajā sektorā ar ārpus bilances pr...
Sasniedzot energoefektivitātes mērķus publiskajā sektorā ar ārpus bilances pr...Ekonomikas ministrija/ Dzīvo siltāk
 
Austrijas pieredze ESKO projektu īstenošanā valsts īpašumā esošās ēkās
Austrijas pieredze ESKO projektu īstenošanā valsts īpašumā esošās ēkāsAustrijas pieredze ESKO projektu īstenošanā valsts īpašumā esošās ēkās
Austrijas pieredze ESKO projektu īstenošanā valsts īpašumā esošās ēkāsEkonomikas ministrija/ Dzīvo siltāk
 
K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectascemiami-dade
 

Tendances (20)

Overview of LACMTA Green Construction Policy
Overview of LACMTA Green Construction PolicyOverview of LACMTA Green Construction Policy
Overview of LACMTA Green Construction Policy
 
GSSD13 Solution Forum 6 (UNECE) - Action plan for Energy- efficient Housing i...
GSSD13 Solution Forum 6 (UNECE) - Action plan for Energy- efficient Housing i...GSSD13 Solution Forum 6 (UNECE) - Action plan for Energy- efficient Housing i...
GSSD13 Solution Forum 6 (UNECE) - Action plan for Energy- efficient Housing i...
 
TrIsCo UK Study Tour: Code for Sustainable Homes
TrIsCo UK Study Tour: Code for Sustainable HomesTrIsCo UK Study Tour: Code for Sustainable Homes
TrIsCo UK Study Tour: Code for Sustainable Homes
 
Housing Standards Review: DCLG Presentation
Housing Standards Review: DCLG PresentationHousing Standards Review: DCLG Presentation
Housing Standards Review: DCLG Presentation
 
LTCP meeting 11-16-05
LTCP meeting 11-16-05LTCP meeting 11-16-05
LTCP meeting 11-16-05
 
Jasper Library Site Recommendations Handouts update 091114
Jasper Library Site Recommendations Handouts update 091114Jasper Library Site Recommendations Handouts update 091114
Jasper Library Site Recommendations Handouts update 091114
 
Central- West Open House - April 2018
Central- West Open House - April 2018Central- West Open House - April 2018
Central- West Open House - April 2018
 
2018 SRFB PSAR Project List for
2018 SRFB PSAR Project List for2018 SRFB PSAR Project List for
2018 SRFB PSAR Project List for
 
EU Circular Economy Programme and the Built Environment #cethinking
EU Circular Economy Programme and the Built Environment #cethinkingEU Circular Economy Programme and the Built Environment #cethinking
EU Circular Economy Programme and the Built Environment #cethinking
 
Designing for the Circular Economy – the Gatwick Airport Project #cethinking
Designing for the Circular Economy – the Gatwick Airport Project #cethinkingDesigning for the Circular Economy – the Gatwick Airport Project #cethinking
Designing for the Circular Economy – the Gatwick Airport Project #cethinking
 
West district library presentation
West district library presentationWest district library presentation
West district library presentation
 
APNIC 23 - Policy SIG - prop-046: IPv4 Countdown Policy Proposal
APNIC 23 - Policy SIG - prop-046: IPv4 Countdown Policy ProposalAPNIC 23 - Policy SIG - prop-046: IPv4 Countdown Policy Proposal
APNIC 23 - Policy SIG - prop-046: IPv4 Countdown Policy Proposal
 
PLS 2018: ILP Technical Committee Update
PLS 2018: ILP Technical Committee UpdatePLS 2018: ILP Technical Committee Update
PLS 2018: ILP Technical Committee Update
 
Plaša mēroga PPP EPC pieeja Ļubļanas pilsētas ēku atjaunošanai
Plaša mēroga PPP EPC pieeja Ļubļanas pilsētas ēku atjaunošanaiPlaša mēroga PPP EPC pieeja Ļubļanas pilsētas ēku atjaunošanai
Plaša mēroga PPP EPC pieeja Ļubļanas pilsētas ēku atjaunošanai
 
PLS 2018: Interest-free financing for energy efficient Street lighting (Kent ...
PLS 2018: Interest-free financing for energy efficient Street lighting (Kent ...PLS 2018: Interest-free financing for energy efficient Street lighting (Kent ...
PLS 2018: Interest-free financing for energy efficient Street lighting (Kent ...
 
Advancing Sustainability in Discretionary Review 2
Advancing Sustainability in Discretionary Review 2Advancing Sustainability in Discretionary Review 2
Advancing Sustainability in Discretionary Review 2
 
Sasniedzot energoefektivitātes mērķus publiskajā sektorā ar ārpus bilances pr...
Sasniedzot energoefektivitātes mērķus publiskajā sektorā ar ārpus bilances pr...Sasniedzot energoefektivitātes mērķus publiskajā sektorā ar ārpus bilances pr...
Sasniedzot energoefektivitātes mērķus publiskajā sektorā ar ārpus bilances pr...
 
Austrijas pieredze ESKO projektu īstenošanā valsts īpašumā esošās ēkās
Austrijas pieredze ESKO projektu īstenošanā valsts īpašumā esošās ēkāsAustrijas pieredze ESKO projektu īstenošanā valsts īpašumā esošās ēkās
Austrijas pieredze ESKO projektu īstenošanā valsts īpašumā esošās ēkās
 
Energoefektivitātes pakalpojuma līgumi Slovēnijā
Energoefektivitātes pakalpojuma līgumi SlovēnijāEnergoefektivitātes pakalpojuma līgumi Slovēnijā
Energoefektivitātes pakalpojuma līgumi Slovēnijā
 
K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 project
 

Similaire à Logistics 2013: John Roberts

Stephen Cook - Renewable Energy
Stephen Cook - Renewable EnergyStephen Cook - Renewable Energy
Stephen Cook - Renewable EnergyPAS_Team
 
Principles of Sustainable Urban Design
Principles of Sustainable Urban DesignPrinciples of Sustainable Urban Design
Principles of Sustainable Urban DesignESD UNU-IAS
 
Preston Implementing CIL Jan 2016 – Mike M
Preston Implementing CIL Jan 2016 – Mike MPreston Implementing CIL Jan 2016 – Mike M
Preston Implementing CIL Jan 2016 – Mike MPAS_Team
 
OPDC - Old Oak Neighbourhood Area and Forum OPDC Board Presentation - Septemb...
OPDC - Old Oak Neighbourhood Area and Forum OPDC Board Presentation - Septemb...OPDC - Old Oak Neighbourhood Area and Forum OPDC Board Presentation - Septemb...
OPDC - Old Oak Neighbourhood Area and Forum OPDC Board Presentation - Septemb...Alexandra Dobson
 
OPDC second revised draft Local Plan consultation - Design & Environment
OPDC second revised draft Local Plan consultation - Design & EnvironmentOPDC second revised draft Local Plan consultation - Design & Environment
OPDC second revised draft Local Plan consultation - Design & EnvironmentAlexandra Dobson
 
OPDC second revised draft Local Plan consultation - Transport and Old Oak North
OPDC second revised draft Local Plan consultation - Transport and Old Oak North OPDC second revised draft Local Plan consultation - Transport and Old Oak North
OPDC second revised draft Local Plan consultation - Transport and Old Oak North Alexandra Dobson
 
back 2 business week 2011 - green deal: Phil Thomas on planning
back 2 business week 2011 - green deal: Phil Thomas on planningback 2 business week 2011 - green deal: Phil Thomas on planning
back 2 business week 2011 - green deal: Phil Thomas on planningMonmouthshire County Council
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarAssociation for Project Management
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarAssociation for Project Management
 
Neighbourhood planning and the historic environment- Ian Culley, RTPI CPD
Neighbourhood planning and the historic environment- Ian Culley, RTPI CPDNeighbourhood planning and the historic environment- Ian Culley, RTPI CPD
Neighbourhood planning and the historic environment- Ian Culley, RTPI CPDDesign South East
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCrosstown TO
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Crosstown TO
 
Public sector planning club, June 2018, Nottingham
Public sector planning club, June 2018, NottinghamPublic sector planning club, June 2018, Nottingham
Public sector planning club, June 2018, NottinghamBrowne Jacobson LLP
 
Zoning By-law: City of Ottawa Policy Context
Zoning By-law: City of Ottawa Policy ContextZoning By-law: City of Ottawa Policy Context
Zoning By-law: City of Ottawa Policy ContextCAOttawa
 
RUPH121 Environmental Design-1.pptx
RUPH121 Environmental Design-1.pptxRUPH121 Environmental Design-1.pptx
RUPH121 Environmental Design-1.pptxAbelTomondo
 
Establishing the Programme Delivery Arrangements for a Major Infrastructure P...
Establishing the Programme Delivery Arrangements for a Major Infrastructure P...Establishing the Programme Delivery Arrangements for a Major Infrastructure P...
Establishing the Programme Delivery Arrangements for a Major Infrastructure P...Association for Project Management
 
Planning legestation
Planning legestation Planning legestation
Planning legestation MIRAL SONI
 
Carbon management presentation final
Carbon management presentation finalCarbon management presentation final
Carbon management presentation finalSustainability East
 

Similaire à Logistics 2013: John Roberts (20)

Stephen Cook - Renewable Energy
Stephen Cook - Renewable EnergyStephen Cook - Renewable Energy
Stephen Cook - Renewable Energy
 
Principles of Sustainable Urban Design
Principles of Sustainable Urban DesignPrinciples of Sustainable Urban Design
Principles of Sustainable Urban Design
 
Preston Implementing CIL Jan 2016 – Mike M
Preston Implementing CIL Jan 2016 – Mike MPreston Implementing CIL Jan 2016 – Mike M
Preston Implementing CIL Jan 2016 – Mike M
 
OPDC - Old Oak Neighbourhood Area and Forum OPDC Board Presentation - Septemb...
OPDC - Old Oak Neighbourhood Area and Forum OPDC Board Presentation - Septemb...OPDC - Old Oak Neighbourhood Area and Forum OPDC Board Presentation - Septemb...
OPDC - Old Oak Neighbourhood Area and Forum OPDC Board Presentation - Septemb...
 
OPDC second revised draft Local Plan consultation - Design & Environment
OPDC second revised draft Local Plan consultation - Design & EnvironmentOPDC second revised draft Local Plan consultation - Design & Environment
OPDC second revised draft Local Plan consultation - Design & Environment
 
OPDC second revised draft Local Plan consultation - Transport and Old Oak North
OPDC second revised draft Local Plan consultation - Transport and Old Oak North OPDC second revised draft Local Plan consultation - Transport and Old Oak North
OPDC second revised draft Local Plan consultation - Transport and Old Oak North
 
back 2 business week 2011 - green deal: Phil Thomas on planning
back 2 business week 2011 - green deal: Phil Thomas on planningback 2 business week 2011 - green deal: Phil Thomas on planning
back 2 business week 2011 - green deal: Phil Thomas on planning
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...
An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...
An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...
 
Neighbourhood planning and the historic environment- Ian Culley, RTPI CPD
Neighbourhood planning and the historic environment- Ian Culley, RTPI CPDNeighbourhood planning and the historic environment- Ian Culley, RTPI CPD
Neighbourhood planning and the historic environment- Ian Culley, RTPI CPD
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017
 
Public sector planning club, June 2018, Nottingham
Public sector planning club, June 2018, NottinghamPublic sector planning club, June 2018, Nottingham
Public sector planning club, June 2018, Nottingham
 
Zoning By-law: City of Ottawa Policy Context
Zoning By-law: City of Ottawa Policy ContextZoning By-law: City of Ottawa Policy Context
Zoning By-law: City of Ottawa Policy Context
 
RUPH121 Environmental Design-1.pptx
RUPH121 Environmental Design-1.pptxRUPH121 Environmental Design-1.pptx
RUPH121 Environmental Design-1.pptx
 
Establishing the Programme Delivery Arrangements for a Major Infrastructure P...
Establishing the Programme Delivery Arrangements for a Major Infrastructure P...Establishing the Programme Delivery Arrangements for a Major Infrastructure P...
Establishing the Programme Delivery Arrangements for a Major Infrastructure P...
 
Waste strategy
Waste strategyWaste strategy
Waste strategy
 
Planning legestation
Planning legestation Planning legestation
Planning legestation
 
Carbon management presentation final
Carbon management presentation finalCarbon management presentation final
Carbon management presentation final
 

Plus de Place North West

High Streets Task Force.pptx
High Streets Task Force.pptxHigh Streets Task Force.pptx
High Streets Task Force.pptxPlace North West
 
CityCo & Manchester BID.pptx
CityCo & Manchester BID.pptxCityCo & Manchester BID.pptx
CityCo & Manchester BID.pptxPlace North West
 
Martin Property Group.pptx
Martin Property Group.pptxMartin Property Group.pptx
Martin Property Group.pptxPlace North West
 
North West Build-to-Rent - Chapman Taylor.pptx
North West Build-to-Rent - Chapman Taylor.pptxNorth West Build-to-Rent - Chapman Taylor.pptx
North West Build-to-Rent - Chapman Taylor.pptxPlace North West
 
Future of Retail + Leisure - Aew Architects
Future of Retail + Leisure - Aew ArchitectsFuture of Retail + Leisure - Aew Architects
Future of Retail + Leisure - Aew ArchitectsPlace North West
 
Greater Manchester Development Update - Oldham Council
Greater Manchester Development Update - Oldham CouncilGreater Manchester Development Update - Oldham Council
Greater Manchester Development Update - Oldham CouncilPlace North West
 
Rochdale Development Agency
Rochdale Development AgencyRochdale Development Agency
Rochdale Development AgencyPlace North West
 
Chester Growth Partnership
Chester Growth PartnershipChester Growth Partnership
Chester Growth PartnershipPlace North West
 
BDP Manchester Net Zero Carbon Summit - BDP + Architype
BDP Manchester Net Zero Carbon Summit - BDP + Architype BDP Manchester Net Zero Carbon Summit - BDP + Architype
BDP Manchester Net Zero Carbon Summit - BDP + Architype Place North West
 
BDP Manchester Net Zero Carbon Summit - BDP
BDP Manchester Net Zero Carbon Summit - BDPBDP Manchester Net Zero Carbon Summit - BDP
BDP Manchester Net Zero Carbon Summit - BDPPlace North West
 
Cumbria Development Update - Watch This Space
Cumbria Development Update - Watch This Space Cumbria Development Update - Watch This Space
Cumbria Development Update - Watch This Space Place North West
 
Cumbria Development Update - Outpost
Cumbria Development Update - Outpost Cumbria Development Update - Outpost
Cumbria Development Update - Outpost Place North West
 
Place North West - Lancashire Development Update - Blackpool council
Place North West - Lancashire Development Update - Blackpool councilPlace North West - Lancashire Development Update - Blackpool council
Place North West - Lancashire Development Update - Blackpool councilPlace North West
 
Place North West - Lancashire Development Update - Preston City Council
Place North West - Lancashire Development Update - Preston City Council Place North West - Lancashire Development Update - Preston City Council
Place North West - Lancashire Development Update - Preston City Council Place North West
 
Place North West - Lancashire Development Update - Hive Land & Planning
Place North West - Lancashire Development Update - Hive Land & Planning Place North West - Lancashire Development Update - Hive Land & Planning
Place North West - Lancashire Development Update - Hive Land & Planning Place North West
 
North West PRS - John Badman, director, CallisonRTKL
North West PRS - John Badman, director, CallisonRTKLNorth West PRS - John Badman, director, CallisonRTKL
North West PRS - John Badman, director, CallisonRTKLPlace North West
 
North West PRS - Ian Scott, director, Lambert Smith Hampton
North West PRS - Ian Scott, director, Lambert Smith HamptonNorth West PRS - Ian Scott, director, Lambert Smith Hampton
North West PRS - Ian Scott, director, Lambert Smith HamptonPlace North West
 

Plus de Place North West (20)

Direct Access.pptx
Direct Access.pptxDirect Access.pptx
Direct Access.pptx
 
High Streets Task Force.pptx
High Streets Task Force.pptxHigh Streets Task Force.pptx
High Streets Task Force.pptx
 
CityCo & Manchester BID.pptx
CityCo & Manchester BID.pptxCityCo & Manchester BID.pptx
CityCo & Manchester BID.pptx
 
Martin Property Group.pptx
Martin Property Group.pptxMartin Property Group.pptx
Martin Property Group.pptx
 
North West Build-to-Rent - Chapman Taylor.pptx
North West Build-to-Rent - Chapman Taylor.pptxNorth West Build-to-Rent - Chapman Taylor.pptx
North West Build-to-Rent - Chapman Taylor.pptx
 
Future of Retail + Leisure - Aew Architects
Future of Retail + Leisure - Aew ArchitectsFuture of Retail + Leisure - Aew Architects
Future of Retail + Leisure - Aew Architects
 
Greater Manchester Development Update - Oldham Council
Greater Manchester Development Update - Oldham CouncilGreater Manchester Development Update - Oldham Council
Greater Manchester Development Update - Oldham Council
 
Cityheart
CityheartCityheart
Cityheart
 
Rochdale Development Agency
Rochdale Development AgencyRochdale Development Agency
Rochdale Development Agency
 
Chester Growth Partnership
Chester Growth PartnershipChester Growth Partnership
Chester Growth Partnership
 
Onward Homes
Onward HomesOnward Homes
Onward Homes
 
BDP Manchester Net Zero Carbon Summit - BDP + Architype
BDP Manchester Net Zero Carbon Summit - BDP + Architype BDP Manchester Net Zero Carbon Summit - BDP + Architype
BDP Manchester Net Zero Carbon Summit - BDP + Architype
 
BDP Manchester Net Zero Carbon Summit - BDP
BDP Manchester Net Zero Carbon Summit - BDPBDP Manchester Net Zero Carbon Summit - BDP
BDP Manchester Net Zero Carbon Summit - BDP
 
Cumbria Development Update - Watch This Space
Cumbria Development Update - Watch This Space Cumbria Development Update - Watch This Space
Cumbria Development Update - Watch This Space
 
Cumbria Development Update - Outpost
Cumbria Development Update - Outpost Cumbria Development Update - Outpost
Cumbria Development Update - Outpost
 
Place North West - Lancashire Development Update - Blackpool council
Place North West - Lancashire Development Update - Blackpool councilPlace North West - Lancashire Development Update - Blackpool council
Place North West - Lancashire Development Update - Blackpool council
 
Place North West - Lancashire Development Update - Preston City Council
Place North West - Lancashire Development Update - Preston City Council Place North West - Lancashire Development Update - Preston City Council
Place North West - Lancashire Development Update - Preston City Council
 
Place North West - Lancashire Development Update - Hive Land & Planning
Place North West - Lancashire Development Update - Hive Land & Planning Place North West - Lancashire Development Update - Hive Land & Planning
Place North West - Lancashire Development Update - Hive Land & Planning
 
North West PRS - John Badman, director, CallisonRTKL
North West PRS - John Badman, director, CallisonRTKLNorth West PRS - John Badman, director, CallisonRTKL
North West PRS - John Badman, director, CallisonRTKL
 
North West PRS - Ian Scott, director, Lambert Smith Hampton
North West PRS - Ian Scott, director, Lambert Smith HamptonNorth West PRS - Ian Scott, director, Lambert Smith Hampton
North West PRS - Ian Scott, director, Lambert Smith Hampton
 

Dernier

3D Architectural Rendering Company by Panoram CGI
3D Architectural Rendering Company by Panoram CGI3D Architectural Rendering Company by Panoram CGI
3D Architectural Rendering Company by Panoram CGIPanoram CGI
 
9990771857 Call Girls in Dwarka Sector 2 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 2 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 2 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 2 Delhi (Call Girls) Delhidelhimodel235
 
Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024VickyAulakh1
 
2k Shot Call girls Aiims Delhi 9205541914
2k Shot Call girls Aiims Delhi 92055419142k Shot Call girls Aiims Delhi 9205541914
2k Shot Call girls Aiims Delhi 9205541914Delhi Call girls
 
Magarpatta Nova Elegance Mundhwa Pune E-Brochure.pdf
Magarpatta Nova Elegance Mundhwa Pune  E-Brochure.pdfMagarpatta Nova Elegance Mundhwa Pune  E-Brochure.pdf
Magarpatta Nova Elegance Mundhwa Pune E-Brochure.pdfManishSaxena95
 
M3M The Line Brochure - Premium Investment Opportunity for Commercial Ventures
M3M The Line Brochure - Premium Investment Opportunity for Commercial VenturesM3M The Line Brochure - Premium Investment Opportunity for Commercial Ventures
M3M The Line Brochure - Premium Investment Opportunity for Commercial Venturessheltercareglobal
 
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In DelhiLow Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhiasmaqueen5
 
Premium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road BengaluruPremium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road BengaluruShivaSeo3
 
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|AkshayJoshi575980
 
Majestique Viman Nagar Pune Brochure.pdf
Majestique Viman Nagar Pune Brochure.pdfMajestique Viman Nagar Pune Brochure.pdf
Majestique Viman Nagar Pune Brochure.pdfBabyrudram
 
M3M 129 E Brochure Noida Expressway, Sector 129, Noida
M3M 129 E Brochure Noida Expressway, Sector 129, NoidaM3M 129 E Brochure Noida Expressway, Sector 129, Noida
M3M 129 E Brochure Noida Expressway, Sector 129, Noidasarak0han45400
 
9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhidelhimodel235
 
Kohinoor Hinjewadi Phase 2 Pune E-Brochure.pdf
Kohinoor Hinjewadi Phase 2 Pune  E-Brochure.pdfKohinoor Hinjewadi Phase 2 Pune  E-Brochure.pdf
Kohinoor Hinjewadi Phase 2 Pune E-Brochure.pdfManishSaxena95
 
2k Shot Call girls Karol Bagh Delhi 9205541914
2k Shot Call girls Karol Bagh Delhi 92055419142k Shot Call girls Karol Bagh Delhi 9205541914
2k Shot Call girls Karol Bagh Delhi 9205541914Delhi Call girls
 
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️soniya singh
 
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️soniya singh
 
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...ApartmentWala1
 
Kolte Patil Kharadi Pune E Brochure.pdf
Kolte Patil Kharadi Pune E  Brochure.pdfKolte Patil Kharadi Pune E  Brochure.pdf
Kolte Patil Kharadi Pune E Brochure.pdfabbu831446
 
Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...
Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...
Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...asmaqueen5
 
9990771857 Call Girls in Dwarka Sector 137 Noida (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 137 Noida (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 137 Noida (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 137 Noida (Call Girls) Delhidelhimodel235
 

Dernier (20)

3D Architectural Rendering Company by Panoram CGI
3D Architectural Rendering Company by Panoram CGI3D Architectural Rendering Company by Panoram CGI
3D Architectural Rendering Company by Panoram CGI
 
9990771857 Call Girls in Dwarka Sector 2 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 2 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 2 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 2 Delhi (Call Girls) Delhi
 
Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024
 
2k Shot Call girls Aiims Delhi 9205541914
2k Shot Call girls Aiims Delhi 92055419142k Shot Call girls Aiims Delhi 9205541914
2k Shot Call girls Aiims Delhi 9205541914
 
Magarpatta Nova Elegance Mundhwa Pune E-Brochure.pdf
Magarpatta Nova Elegance Mundhwa Pune  E-Brochure.pdfMagarpatta Nova Elegance Mundhwa Pune  E-Brochure.pdf
Magarpatta Nova Elegance Mundhwa Pune E-Brochure.pdf
 
M3M The Line Brochure - Premium Investment Opportunity for Commercial Ventures
M3M The Line Brochure - Premium Investment Opportunity for Commercial VenturesM3M The Line Brochure - Premium Investment Opportunity for Commercial Ventures
M3M The Line Brochure - Premium Investment Opportunity for Commercial Ventures
 
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In DelhiLow Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
 
Premium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road BengaluruPremium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road Bengaluru
 
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
 
Majestique Viman Nagar Pune Brochure.pdf
Majestique Viman Nagar Pune Brochure.pdfMajestique Viman Nagar Pune Brochure.pdf
Majestique Viman Nagar Pune Brochure.pdf
 
M3M 129 E Brochure Noida Expressway, Sector 129, Noida
M3M 129 E Brochure Noida Expressway, Sector 129, NoidaM3M 129 E Brochure Noida Expressway, Sector 129, Noida
M3M 129 E Brochure Noida Expressway, Sector 129, Noida
 
9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi
 
Kohinoor Hinjewadi Phase 2 Pune E-Brochure.pdf
Kohinoor Hinjewadi Phase 2 Pune  E-Brochure.pdfKohinoor Hinjewadi Phase 2 Pune  E-Brochure.pdf
Kohinoor Hinjewadi Phase 2 Pune E-Brochure.pdf
 
2k Shot Call girls Karol Bagh Delhi 9205541914
2k Shot Call girls Karol Bagh Delhi 92055419142k Shot Call girls Karol Bagh Delhi 9205541914
2k Shot Call girls Karol Bagh Delhi 9205541914
 
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
 
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
 
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
 
Kolte Patil Kharadi Pune E Brochure.pdf
Kolte Patil Kharadi Pune E  Brochure.pdfKolte Patil Kharadi Pune E  Brochure.pdf
Kolte Patil Kharadi Pune E Brochure.pdf
 
Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...
Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...
Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...
 
9990771857 Call Girls in Dwarka Sector 137 Noida (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 137 Noida (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 137 Noida (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 137 Noida (Call Girls) Delhi
 

Logistics 2013: John Roberts

  • 1.
  • 2. Planning for Logistics John Roberts Solicitor Planning Team
  • 3. Introduction • Planning system increasingly complex • Planning permission required for operational on-site facilities • Focus – Overview of the planning system – Key themes in planning development – Case studies – demonstrate planning policies in action
  • 4. Background • 2 tiers of planning policy for England: national & local • Previously intermediate third tier – regional – Regional Spatial Strategies – Abolished by Coalition Government • National and local tiers in state of transition
  • 5. National Planning Policy • National Planning Policy Framework – Introduced on 27 March 2012 • Previously: – PPS’s, PPG’s, Circulars, Letters to Chief Planning Officers – 44 documents – Over 1,300 pages – 2 decades of policy development • New document: – Single document – 59 pages
  • 6. What does it do? • Sets out the Government’s planning policies for England and how these are expected to be applied • Guidance for local planning authorities – Drawing up local plans – Determining planning applications • Local plans should be consistent with the Framework
  • 7. Aims • Decision-making driven down to the local level – Ties in with localism agenda • Replaced documents were very detailed and prescriptive • New approach: just bare bones within national policy – Local councils to produce their own distinctive plans
  • 9. Opposition “(The) Slim, 52-page draft National Planning Policy Framework… more unexploded mines per square inch than the most liberally strewn battlefield” Daily Telegraph “… a public relations exercise which will in effect encourage privatisation of services, open market sale of public assets and, through the presumption to develop, render all communities defenceless in the face of the greed of developers” Morning Star
  • 10. Local Planning Policy • Where detail is found • Currently Local Plans or Unitary Development Plans – Set out policies thematically • Local policy changing – Local Development Frameworks – Local Plans • Few local authorities completed process in timely manner – Result is “Saved” policies • Draft policies can be taken into account
  • 11. Presumption in favour of sustainable development • At the heart of the planning system is a presumption in favour of sustainable development, which should be seen as a golden thread running through both plan-making and decision-taking • Reference to UN definition of sustainable development • 3 dimensions: economic, social & environmental
  • 12. Key Considerations • Key: frontload preparation work – Within planning application – Also at pre-application stage • Identify requirements and stumbling blocks as early as possible – Talk to Planning Officers – Sound them out on their requirements – Make application documents detailed • If anything is missing, somebody will spot it! – Delays
  • 21. Planning Policy in Action • 3 case studies: 1. World Logistics Hub, Manchester Airport 2. New Hythe Industrial Estate, Kent 3. Lancashire Business Park, Leyland
  • 22. Case Study 1 – World Logistics Hub
  • 23. The Proposal • Airport related freight logistics hub • Up to 1.4 million square feet – Units ranging from 7,500 to 200,000 square feet • Retail and amenity facilities for future workforce • Nearly 1,500 car parking spaces • Site: 51.7 hectares – Mainly grazing land, surrounded by hedgerows, contains ponds – Bordered by farmland and woodland: SSSI & SBI
  • 24. Main Issue – Green Belt Location • Proposal within draft Manchester Airport Masterplan, 2006 – Identified extensions to Airport’s Operational Area and land to be removed from the green belt • Masterplan considered in preparing Core Strategy – This reviewed the green belt boundary • Core Strategy considered at Public Inquiry, 2011 – Exceptional circumstances to justify altering green belt boundary • Council considered principle of logistics hub acceptable – But … other issues required consideration
  • 25. Other Issues • Visual amenity – Council accepted there would not be an unduly adverse impact • Residential amenity – Conditions dealing with dust control and acoustic insulation • Highway network – Able to take advantage of highways improvements connected to the second runway at Manchester Airport • Nature conservation – 14.8 hectares proposed as landscape and ecological mitigation area – Enables compliance with the European Habitats Directive
  • 26. Case Study 2 – Aylesford, Kent
  • 27. The Proposal • 3 warehouse units – One of just over 9,000 square metres – One of approximately 6,500 square metres – One of just under 4,000 square metres • Full provision for car and lorry parking • Site has long history of industrial use – Safeguarded for employment use in Tonbridge and Malling Council’s Land Allocations Development Plan Document, 2008 • 6.81 hectares & within wider industrial estate – New housing development to the west
  • 28. Principle of Development • Acceptable as site within area allocated for employment use • Long previous use of site formed basis of Council’s assessment of other issues – Existing buildings remained on site at time application was considered – Could have been fully reoccupied at any time without further approval – Application was assessed against this background of historic use of site • Key: Impact be no worse than and, if possible, less than the previous unfettered use rights of the site
  • 29. Other Issues • Design – New warehouses cumulatively smaller than existing building • Lorry routing – Access only from eastern side (away from housing development to west) – Buildings on industrial estate act as noise buffer between traffic & houses • 24 hour operation – Historically, no controls over hours of use • Conditions to mitigate impacts of development – Acoustic barrier to be installed before units can be operational – Details of external lighting submitted & agreed prior to installation
  • 30. Case Study 3 – Leyland, Lancashire
  • 31. The Proposal • 3 storage and distribution warehouses • Nearly 400,000 square feet of accommodation – 2 units of 166,000 square feet each – 1 unit of 50,000 square feet • Associated car parking and secure compound areas • Replace large warehouse destroyed by fire in 2011 • Surrounded on three sides by industrial units & offices – West Coast Mainline to the east
  • 32. Principle of Development • National Planning Policy Framework – Planning system should support sustainable economic growth – Encourage, rather than impede, sustainable growth • Local planning policy – South Ribble Local Plan – Within main existing employment areas, planning permission should be granted for expansion/redevelopment of industrial & business purposes • Scheme in accordance with both national and local policy – No problem with principle of development
  • 33. Other Issues • Design – Local policy requires well related to neighbouring buildings and the locality – Modern, standard industrial buildings, finished in metal cladding, proposed – Existing buildings within Business Park of similar height and materials • Parking – Local policy requires adequate level of car parking and servicing – County Highways objected to initial plans – revised to deal with this • Landscaping – Six silver birch trees to be removed to facilitate development – Replacement planting to compensate – Conditions for landscaping plan and management regime