SlideShare une entreprise Scribd logo
1  sur  18
Offshore Industry Experience: -
Design, Manufacture & FAT of Specialist Systems: -
           Carousel & Basket Lay Systems
           Subsea Equipment Launch Systems
           HDPE Crossings and J Tubes systems
           J Tube Gravity Base
           Radial Friction Welding
           Sea-fastening Systems
           Vessel Conversion & Construction
           Solution Engineering

Project Disciplines: -
            Wind Farm Installations
            Jacket “Piece Small” Decommissioning
            Flexibles, Umbilical's, Risers, Power Cables & LoFS Installations
            J Tube Installation
            Pipeline Pre Commissioning
            Product Trenching; Jet Trenching, Ploughing, Rock Cutting
            Remote Intervention
            Riser Pull-ins & Shore Landings
            Pipeline Reel Lay
            Spool Piece; Fabrication, Metrology, Installation
            SSIV / Manifold & Over Protection Structure Installation
            Wet Buckle Repair System
February 2011 – October 2012
Saipem UK - Katy Project Engineering
Manager
ConocoPhillips - Katy Field Development,
Southern North Sea: - Reel lay installation
and jet trenching of 14.2km 10”x22.2mm
pipeline c/w 2” Coil tubing piggyback line.
Design, manufacture and installation of 2
off Subsea manifolds & 4 off Tie in spools.
System Pre Commissioning.

•   Management of all project engineering
•   Establishment of project team
•   Overseeing procurement scope of work
    documents for all project supply
    activities including procurement of
    project line pipe, coil tubing, subsea
    valves & structures.
•   Coordination of project analysis
•   Layout of the Hartlepool spool base
•   Design, manufacture and testing of
    Reel lay vessel SWWD / systems.
•   Client interface and engineering
    reporting
•   Offshore Installation and Pre
    Commissioning phases
October 2009 – February 2011
VSMC - Engineering Manager (UK)

•   Set up a new Energy Engineering Department in
    Darlington, UK
•   Implemented all project systems/documentation
    along Oil & Gas lines and standardised
    installation procedures
•   Recruited and managed a dedicated multi-skilled
    project engineering team
•   Undertook outline / detailed planning of
    installation workscope
•   Managed the analysis, design, build & FAT/SIT of
    specialist project equipment on behalf of Statoil
•   Vessel analysis and selection
•   Shore End approach engineering inc. Pull in
    analysis, Landfall Works, Vessel Positioning &
    Float in and lay of product
•   Export Cable Lay & Second End Pull in at
    Substation
•   Inter Array Cable Installation
•   Trenching Analysis & Equipment selection

► Statoil - Sherringham Shoals Windfarm - 88
Turbine & 2 Sub Station installation
► BritNed – British/Dutch interconnector project
March 2009 – August 2009
Saipem UK - Lead Engineer
Frigg 2009 Decommissioning
Removal of the Quarters Platform
(QP) - Pre and post transit survey of
the route into the Aker stored facility.
Dredging of the pile locations,
diamond wire cutting of the piles and
one piece removal of the jacket by
the S7000 .

Removal of the Drilling Platform 1
(DP1)
Use of subsea remote intervention
technology. Pre-dredging at level
one, “piece small” subsea
preparation, dismantling, lifting and
transfer of jacket sections to subsea
storage containers. General seabed
debris removal.
11 weeks offshore operations
April 2008 - May 2008
CTC Marine Projects Limited
Senior Project Manager - BP Shefa II
Project

120km lay & burial of Fibre Optic product
running from the BP Clair Platform
through to the BP Schiehallion FPSO in
the north east Atlantic, approximately
140km NNE of Cape Wrath, west of
Shetland Islands. Workscope included,
Subsea Clamp installation, dynamic riser
pull-in and hang off assembly. Product
tensioning at the Clair Platform. FOTA
deployment at Schiehallion FPSO. Eleven
crossings to bridge. Recovery and
splicing of BU tails at the FT FO cable
intersection. Trenching of the product
utilises the T1 Wheel Cutting Tractor &
ISU 150te Plough. Construction vessel
Maersk Advancer. Project Value
£6.5million.
November 2006 – April 2008
CTC Marine Projects Ltd
Senior Project Manager - Vessel Build. 106m
“OCV Volantis”

Management of specification and build of the
vessel. Designed for Construction / Trenching
roles. Development and implementation of many
innovative systems enabling the vessel to be
configured to meet the various project demands
efficiently. Features included “Plug and play”
system philosophy, modular container garage
and handling system, unique sea-fastening
system and control room.        Specialist team
consisted of eight persons. Reporting to upper
management. Project Value £70m.
November 2006 – April 2008
CTC Marine Projects Ltd
Senior Project Manager -          2000Te
Carousel Lay System

Specification and management of lay
system including 17m Carousel, Fleeting
tower, Accumulator and Tensioner. A
modular designed system capable of
operation on multiple construction
vessels in various configurations.
Included vessel hull analysis, grillage
design, analysis and build. Incorporated a
unique sea fastening system allowing
efficient mob/demob. Lay control
integrated into the vessel DP system.
“Plug and play” philosophy adopted for
the vessel integration.. Project Value
£5m.
November 2006 – April 2008
CTC Marine Projects Ltd
Senior Project Manager/Designer - Seafastening
System

Primarily designed for the integration of a 2500Te
Carousel lay system on to the OCV Volantis, this
unique seafastening system allows for efficient
mob/demob of equipment on to vessels with no
requirement for welding or burning on deck.
Mob/Demob times cut from 4 - 5 days to approx.
6hrs.
January 2006 – September 2006
CTC Marine Projects Limited
Project Manager - BP Clair Platform West
of Shetland

LoFS (Life of Field Seismic) installation
including field layout and installation
planning, route and boulder clearance, J
Tube Gravity Base design/engineering,
Pipeline Bridge installation & system
testing. The LoFS system included some
50km of product simultaneously laid and
trenched in difficult seabed conditions
utilising the CTC T3 wheel cutter
trenching system. Project Value £11.5m.
January 2006 - September 2006
CTC Marine Projects Ltd.
Project Manager - Gravity J Tube
Base

As part of the overall BP Clair LoFS
project, design, manufacture and
installation of a Gravity J Tube Base
for dynamic riser installation. Design
work included: -
   100 year storm loading analysis
   On bottom stability analysis
   Design finite element analysis
   Launch and recovery analysis
In air weight 65Te
November 2003 – June 2004
Saipem - Lead Project Engineer & Assistant
Project Manager.

Statoil - Sleipner Vest Alfa Nord Extension
Project.

Project Pre requisites
Conversion of the Solstad MV Normand
Cutter cable lay vessel into a construction
vessel. Both vessel conversion and project
were completed on time.
This work included: -
• Clearing / cutting of deck and
    associated cable lay equipment
• Fitting of 300Te heave comp crane.
• Under deck strengthening for Carousel
    lay system.
• Fitting of the 25m, 3000Te product lay      Project
    system                                    • Installation of an 18.5km umbilical comprised 75mm x
                                                 5.5mm super duplex core with associated electrical and
• SIT prior to transit to field
                                                 hydraulic lines
                                              • Product loaded out of Kaverner at Moss Norway after
                                                 completing vessel & equipment trials of the Normand
                                                 Cutter
                                              • Managing Project Engineering & Client interface
                                              • Preparation / submission of project documentation
                                              • Offshore installation activities
May 2002 – July 2002
Saipem - Project Engineering
Manager: -

Installation of two “four-slot”
drilling templates inc. protection
structures for Norsk Hydro on the
‘Fram Vest’ Field Development.

Responsibility for:
• Preparation / submission of
   project documentation &
   Engineering
• Project scheduling
• Vessel mobilisation of activities
   at ERS Base, Rotterdam
• Vessel loading Langesund,
   Norway
• Offshore support.
April 2001 - Aug 2001
Saipem - Lead Engineer –
Bluestream ITUR Cable Crossings

Work included Jig design &
manufacture, Crossing
manufacture & in dock testing.
Controlled and reported budgets
/ schedules to upper
management and liaised daily
with Sub-Contractor.

Technical: -
Quantity 2 off
30m in length
Weighing 30Te in air.
On bottom weight 800Kg.
Manufactured from HDPE

“The fabrications were initially six
weeks behind schedule on hand
over. Delivery of the equipment
was made one day ahead of
original target schedule.”
September 2002 - March 2002
Saipem - Lead Engineer: - WBRS

Transferred within the Bluestream
Project to technically assess and
manage the “Wet Buckle Repair
System” (WBRS) redesign
programme.
Initiated redesign of key elements.
Involved in preparation of the
schedule, procurement, logistics and
cost estimates of the work.
Mobilised the build site in Samsun,
Turkey and finalised documentation
to ‘As Built’ status.
Co-ordinated / managed the 8-week
rebuild phase of the equipment and
FAT.

Technical: -
2300m depth rated
ROV intervention system
2000 – 2001
Stolt Offshore Ltd
Project Manager: -
Deep Matis Launch System

Established design / deployment
data / criteria and all commercial
requirements of the system.
Directed the design scope and
controlled / reported budgets and
schedules to upper management.
Commissioned specialist finite
element analysis, feasibility study
and advanced ‘real time’
modelling.
Managed procurement / supply of
materials & services, as well as
manufacture / assembly of
equipment. Executed
commissioning and handover of
project equipment to site in
Norway and ‘closed out’
contracts.

Technical: -
2300m depth rated
Operation West Africa. Designed
to land on 0.4 kpa soils.
ROV intervention system.

Project Value: - £1.25million
1997 – 2000
Stolt Offshore Ltd
Project Manager - Radial Friction
Welding ‘J’ Lay Pipe System

Set up manufacturing site.
Established management systems.
Controlled / reported manufacturing
budgets to senior management.
Directed the conceptual designs,
manufacturing solutions and
procedures. Manufactured and built
key machines
Wrote and Co-ordinated the
assembly plans, devised
commissioning tests/ procedures.
Implemented design / manufacture
of test equipment, reviewed test
data and set remedial actions.
(value £10 million).


Technical: -
2Mw system designed to friction
weld a variety of metals up to 12 ¾”
API pipe.
Trenching Systems                     Vessels
    Beluga                               Bar Protector DSV
    CMR3 Jetting ROV                     Cygnus
    Flexjet                              Edda Freya
    ISU Product Plough                   Far Samson
    T1 & T3 Rock Cutter                  Far Sovereign
    UT1 Jet Trencher                     Helix Express
                                          Maersk Advancer
                                          Maersk Recorder
                                          Maersk Responder
                                          Maxita
                                          Normand Cutter
                                          Ocean Challenger
                                          Polar Prince
                                          Seaway Falcon
                                          Team Oman
Contact details: -
                                          Volantis
richard.turnbull@offshore-energy.co
www.offshore-energy.co

Contenu connexe

Tendances

Russell bruce cv 2016.
Russell bruce cv 2016.Russell bruce cv 2016.
Russell bruce cv 2016.Russell Bruce
 
Resume Thad Gilbert
Resume Thad GilbertResume Thad Gilbert
Resume Thad GilbertThad Gilbert
 
Ron Williams CV Feb 2017
Ron Williams CV Feb 2017Ron Williams CV Feb 2017
Ron Williams CV Feb 2017Ron Williams
 
Vause Wayne - 6829
Vause Wayne - 6829Vause Wayne - 6829
Vause Wayne - 6829wayne vause
 
DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)Mohd Zaini Baharum
 
RV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaRV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaMichaelUberti
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15ADAM DUKE
 
peter.fitzpatrick.cv.2016-2017
peter.fitzpatrick.cv.2016-2017peter.fitzpatrick.cv.2016-2017
peter.fitzpatrick.cv.2016-2017Peter Fitzpatrick
 
OTC Asia 2014 Petronas
OTC Asia 2014 PetronasOTC Asia 2014 Petronas
OTC Asia 2014 PetronasSteven Kennedy
 
4.BLC IPOP -7th August 2014 - Post Session Update -8.8.14
4.BLC IPOP -7th August 2014 - Post Session Update -8.8.144.BLC IPOP -7th August 2014 - Post Session Update -8.8.14
4.BLC IPOP -7th August 2014 - Post Session Update -8.8.14Kristipoom R-khubut
 
Chandler Geoff 2016 cv
Chandler Geoff 2016 cvChandler Geoff 2016 cv
Chandler Geoff 2016 cvGeoff Chandler
 
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKSDAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKSIslam Nassef
 
R mayers_CV 2302
R mayers_CV 2302R mayers_CV 2302
R mayers_CV 2302Rhod Mayers
 

Tendances (20)

Russell bruce cv 2016.
Russell bruce cv 2016.Russell bruce cv 2016.
Russell bruce cv 2016.
 
Resume Thad Gilbert
Resume Thad GilbertResume Thad Gilbert
Resume Thad Gilbert
 
Ron Williams CV Feb 2017
Ron Williams CV Feb 2017Ron Williams CV Feb 2017
Ron Williams CV Feb 2017
 
Vause Wayne - 6829
Vause Wayne - 6829Vause Wayne - 6829
Vause Wayne - 6829
 
MNC-14
MNC-14MNC-14
MNC-14
 
GEC presentation
GEC  presentationGEC  presentation
GEC presentation
 
DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)
 
Lecture44
Lecture44Lecture44
Lecture44
 
KOM 15082014 HUC
KOM 15082014 HUCKOM 15082014 HUC
KOM 15082014 HUC
 
RV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaRV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey Australia
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15
 
Mechanical cv
Mechanical cvMechanical cv
Mechanical cv
 
peter.fitzpatrick.cv.2016-2017
peter.fitzpatrick.cv.2016-2017peter.fitzpatrick.cv.2016-2017
peter.fitzpatrick.cv.2016-2017
 
OTC Asia 2014 Petronas
OTC Asia 2014 PetronasOTC Asia 2014 Petronas
OTC Asia 2014 Petronas
 
4.BLC IPOP -7th August 2014 - Post Session Update -8.8.14
4.BLC IPOP -7th August 2014 - Post Session Update -8.8.144.BLC IPOP -7th August 2014 - Post Session Update -8.8.14
4.BLC IPOP -7th August 2014 - Post Session Update -8.8.14
 
richie CV 2015
richie CV 2015richie CV 2015
richie CV 2015
 
Resume 1
Resume 1 Resume 1
Resume 1
 
Chandler Geoff 2016 cv
Chandler Geoff 2016 cvChandler Geoff 2016 cv
Chandler Geoff 2016 cv
 
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKSDAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
 
R mayers_CV 2302
R mayers_CV 2302R mayers_CV 2302
R mayers_CV 2302
 

Similaire à Richard Turnbull CV Supplement 2012

Connecting offshore platforms to a subsea cable system
Connecting offshore platforms to a subsea cable system Connecting offshore platforms to a subsea cable system
Connecting offshore platforms to a subsea cable system Jerry Brown
 
MARITIME, NAVAL, OFFSHORE & MARINE ENERGY WELDING SPECIALISTS. DEGIMA Naval &...
MARITIME, NAVAL, OFFSHORE & MARINE ENERGY WELDING SPECIALISTS. DEGIMA Naval &...MARITIME, NAVAL, OFFSHORE & MARINE ENERGY WELDING SPECIALISTS. DEGIMA Naval &...
MARITIME, NAVAL, OFFSHORE & MARINE ENERGY WELDING SPECIALISTS. DEGIMA Naval &...DEGIMA SA
 
Check out the latest projects of the Maritime, Naval, Offshore & Marine Energ...
Check out the latest projects of the Maritime, Naval, Offshore & Marine Energ...Check out the latest projects of the Maritime, Naval, Offshore & Marine Energ...
Check out the latest projects of the Maritime, Naval, Offshore & Marine Energ...Javier Cantera
 
Cameron Punton - CV December 2016
Cameron Punton - CV December 2016Cameron Punton - CV December 2016
Cameron Punton - CV December 2016Cameron Punton
 
930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdf930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdfRaviNobleseas
 
CV. Mechincal Engineer
CV. Mechincal EngineerCV. Mechincal Engineer
CV. Mechincal EngineerAhmad Hassan
 
000-GENERAL presentation_rev06
000-GENERAL presentation_rev06000-GENERAL presentation_rev06
000-GENERAL presentation_rev06Stefan Erents
 
J Ray Firsts
J Ray FirstsJ Ray Firsts
J Ray FirstsMyLast1
 
R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R S Rajaram
 
R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R S Rajaram
 
Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...
Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...
Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...Torben Haagh
 
Pic booklet screen view 2
Pic booklet   screen view 2Pic booklet   screen view 2
Pic booklet screen view 2Amin Hadjaran
 
Item no
Item noItem no
Item norehant
 

Similaire à Richard Turnbull CV Supplement 2012 (20)

Connecting offshore platforms to a subsea cable system
Connecting offshore platforms to a subsea cable system Connecting offshore platforms to a subsea cable system
Connecting offshore platforms to a subsea cable system
 
MARITIME, NAVAL, OFFSHORE & MARINE ENERGY WELDING SPECIALISTS. DEGIMA Naval &...
MARITIME, NAVAL, OFFSHORE & MARINE ENERGY WELDING SPECIALISTS. DEGIMA Naval &...MARITIME, NAVAL, OFFSHORE & MARINE ENERGY WELDING SPECIALISTS. DEGIMA Naval &...
MARITIME, NAVAL, OFFSHORE & MARINE ENERGY WELDING SPECIALISTS. DEGIMA Naval &...
 
KCI Company Presenation Oil & Gas
KCI Company Presenation Oil & GasKCI Company Presenation Oil & Gas
KCI Company Presenation Oil & Gas
 
Check out the latest projects of the Maritime, Naval, Offshore & Marine Energ...
Check out the latest projects of the Maritime, Naval, Offshore & Marine Energ...Check out the latest projects of the Maritime, Naval, Offshore & Marine Energ...
Check out the latest projects of the Maritime, Naval, Offshore & Marine Energ...
 
Cameron Punton - CV December 2016
Cameron Punton - CV December 2016Cameron Punton - CV December 2016
Cameron Punton - CV December 2016
 
Ronald-Smith
Ronald-SmithRonald-Smith
Ronald-Smith
 
Linkedin
LinkedinLinkedin
Linkedin
 
CV_mki2015Nov
CV_mki2015NovCV_mki2015Nov
CV_mki2015Nov
 
930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdf930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdf
 
CV. Mechincal Engineer
CV. Mechincal EngineerCV. Mechincal Engineer
CV. Mechincal Engineer
 
CV CBK 2015 N
CV CBK 2015 NCV CBK 2015 N
CV CBK 2015 N
 
YH profile (E)
YH profile (E)YH profile (E)
YH profile (E)
 
000-GENERAL presentation_rev06
000-GENERAL presentation_rev06000-GENERAL presentation_rev06
000-GENERAL presentation_rev06
 
J Ray Firsts
J Ray FirstsJ Ray Firsts
J Ray Firsts
 
R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017
 
R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017
 
Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...
Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...
Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...
 
Pic booklet screen view 2
Pic booklet   screen view 2Pic booklet   screen view 2
Pic booklet screen view 2
 
Tushar resume
Tushar resumeTushar resume
Tushar resume
 
Item no
Item noItem no
Item no
 

Dernier

LinkedIn Strategic Guidelines April 2024
LinkedIn Strategic Guidelines April 2024LinkedIn Strategic Guidelines April 2024
LinkedIn Strategic Guidelines April 2024Bruce Bennett
 
原版定制copy澳洲查尔斯达尔文大学毕业证CDU毕业证成绩单留信学历认证保障质量
原版定制copy澳洲查尔斯达尔文大学毕业证CDU毕业证成绩单留信学历认证保障质量原版定制copy澳洲查尔斯达尔文大学毕业证CDU毕业证成绩单留信学历认证保障质量
原版定制copy澳洲查尔斯达尔文大学毕业证CDU毕业证成绩单留信学历认证保障质量sehgh15heh
 
定制英国克兰菲尔德大学毕业证成绩单原版一比一
定制英国克兰菲尔德大学毕业证成绩单原版一比一定制英国克兰菲尔德大学毕业证成绩单原版一比一
定制英国克兰菲尔德大学毕业证成绩单原版一比一z zzz
 
Digital Marketing Training Institute in Mohali, India
Digital Marketing Training Institute in Mohali, IndiaDigital Marketing Training Institute in Mohali, India
Digital Marketing Training Institute in Mohali, IndiaDigital Discovery Institute
 
办理老道明大学毕业证成绩单|购买美国ODU文凭证书
办理老道明大学毕业证成绩单|购买美国ODU文凭证书办理老道明大学毕业证成绩单|购买美国ODU文凭证书
办理老道明大学毕业证成绩单|购买美国ODU文凭证书saphesg8
 
Ch. 9- __Skin, hair and nail Assessment (1).pdf
Ch. 9- __Skin, hair and nail Assessment (1).pdfCh. 9- __Skin, hair and nail Assessment (1).pdf
Ch. 9- __Skin, hair and nail Assessment (1).pdfJamalYaseenJameelOde
 
Unlock Your Creative Potential: 7 Skills for Content Creator Evolution
Unlock Your Creative Potential: 7 Skills for Content Creator EvolutionUnlock Your Creative Potential: 7 Skills for Content Creator Evolution
Unlock Your Creative Potential: 7 Skills for Content Creator EvolutionRhazes Ghaisan
 
Introduction to phyton , important topic
Introduction to phyton , important topicIntroduction to phyton , important topic
Introduction to phyton , important topicakpgenious67
 
格里菲斯大学毕业证(Griffith毕业证)#文凭成绩单#真实留信学历认证永久存档
格里菲斯大学毕业证(Griffith毕业证)#文凭成绩单#真实留信学历认证永久存档格里菲斯大学毕业证(Griffith毕业证)#文凭成绩单#真实留信学历认证永久存档
格里菲斯大学毕业证(Griffith毕业证)#文凭成绩单#真实留信学历认证永久存档208367051
 
Ioannis Tzachristas Self-Presentation for MBA.pdf
Ioannis Tzachristas Self-Presentation for MBA.pdfIoannis Tzachristas Self-Presentation for MBA.pdf
Ioannis Tzachristas Self-Presentation for MBA.pdfjtzach
 
Gurgaon Call Girls: Free Delivery 24x7 at Your Doorstep G.G.N = 8377087607
Gurgaon Call Girls: Free Delivery 24x7 at Your Doorstep G.G.N = 8377087607Gurgaon Call Girls: Free Delivery 24x7 at Your Doorstep G.G.N = 8377087607
Gurgaon Call Girls: Free Delivery 24x7 at Your Doorstep G.G.N = 8377087607dollysharma2066
 
Storytelling, Ethics and Workflow in Documentary Photography
Storytelling, Ethics and Workflow in Documentary PhotographyStorytelling, Ethics and Workflow in Documentary Photography
Storytelling, Ethics and Workflow in Documentary PhotographyOrtega Alikwe
 
美国SU学位证,雪城大学毕业证书1:1制作
美国SU学位证,雪城大学毕业证书1:1制作美国SU学位证,雪城大学毕业证书1:1制作
美国SU学位证,雪城大学毕业证书1:1制作ss846v0c
 
办理哈珀亚当斯大学学院毕业证书文凭学位证书
办理哈珀亚当斯大学学院毕业证书文凭学位证书办理哈珀亚当斯大学学院毕业证书文凭学位证书
办理哈珀亚当斯大学学院毕业证书文凭学位证书saphesg8
 
ME 205- Chapter 6 - Pure Bending of Beams.pdf
ME 205- Chapter 6 - Pure Bending of Beams.pdfME 205- Chapter 6 - Pure Bending of Beams.pdf
ME 205- Chapter 6 - Pure Bending of Beams.pdfaae4149584
 
8377877756 Full Enjoy @24/7 Call Girls in Pitampura Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Pitampura Delhi NCR8377877756 Full Enjoy @24/7 Call Girls in Pitampura Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Pitampura Delhi NCRdollysharma2066
 
LinkedIn for Your Job Search in April 2024
LinkedIn for Your Job Search in April 2024LinkedIn for Your Job Search in April 2024
LinkedIn for Your Job Search in April 2024Bruce Bennett
 
AI ppt introduction , advandtage pros and cons.pptx
AI ppt introduction , advandtage pros and cons.pptxAI ppt introduction , advandtage pros and cons.pptx
AI ppt introduction , advandtage pros and cons.pptxdeepakkrlkr2002
 

Dernier (20)

LinkedIn Strategic Guidelines April 2024
LinkedIn Strategic Guidelines April 2024LinkedIn Strategic Guidelines April 2024
LinkedIn Strategic Guidelines April 2024
 
原版定制copy澳洲查尔斯达尔文大学毕业证CDU毕业证成绩单留信学历认证保障质量
原版定制copy澳洲查尔斯达尔文大学毕业证CDU毕业证成绩单留信学历认证保障质量原版定制copy澳洲查尔斯达尔文大学毕业证CDU毕业证成绩单留信学历认证保障质量
原版定制copy澳洲查尔斯达尔文大学毕业证CDU毕业证成绩单留信学历认证保障质量
 
定制英国克兰菲尔德大学毕业证成绩单原版一比一
定制英国克兰菲尔德大学毕业证成绩单原版一比一定制英国克兰菲尔德大学毕业证成绩单原版一比一
定制英国克兰菲尔德大学毕业证成绩单原版一比一
 
Digital Marketing Training Institute in Mohali, India
Digital Marketing Training Institute in Mohali, IndiaDigital Marketing Training Institute in Mohali, India
Digital Marketing Training Institute in Mohali, India
 
办理老道明大学毕业证成绩单|购买美国ODU文凭证书
办理老道明大学毕业证成绩单|购买美国ODU文凭证书办理老道明大学毕业证成绩单|购买美国ODU文凭证书
办理老道明大学毕业证成绩单|购买美国ODU文凭证书
 
Ch. 9- __Skin, hair and nail Assessment (1).pdf
Ch. 9- __Skin, hair and nail Assessment (1).pdfCh. 9- __Skin, hair and nail Assessment (1).pdf
Ch. 9- __Skin, hair and nail Assessment (1).pdf
 
Unlock Your Creative Potential: 7 Skills for Content Creator Evolution
Unlock Your Creative Potential: 7 Skills for Content Creator EvolutionUnlock Your Creative Potential: 7 Skills for Content Creator Evolution
Unlock Your Creative Potential: 7 Skills for Content Creator Evolution
 
Introduction to phyton , important topic
Introduction to phyton , important topicIntroduction to phyton , important topic
Introduction to phyton , important topic
 
格里菲斯大学毕业证(Griffith毕业证)#文凭成绩单#真实留信学历认证永久存档
格里菲斯大学毕业证(Griffith毕业证)#文凭成绩单#真实留信学历认证永久存档格里菲斯大学毕业证(Griffith毕业证)#文凭成绩单#真实留信学历认证永久存档
格里菲斯大学毕业证(Griffith毕业证)#文凭成绩单#真实留信学历认证永久存档
 
Young Call~Girl in Pragati Maidan New Delhi 8448380779 Full Enjoy Escort Service
Young Call~Girl in Pragati Maidan New Delhi 8448380779 Full Enjoy Escort ServiceYoung Call~Girl in Pragati Maidan New Delhi 8448380779 Full Enjoy Escort Service
Young Call~Girl in Pragati Maidan New Delhi 8448380779 Full Enjoy Escort Service
 
Ioannis Tzachristas Self-Presentation for MBA.pdf
Ioannis Tzachristas Self-Presentation for MBA.pdfIoannis Tzachristas Self-Presentation for MBA.pdf
Ioannis Tzachristas Self-Presentation for MBA.pdf
 
Gurgaon Call Girls: Free Delivery 24x7 at Your Doorstep G.G.N = 8377087607
Gurgaon Call Girls: Free Delivery 24x7 at Your Doorstep G.G.N = 8377087607Gurgaon Call Girls: Free Delivery 24x7 at Your Doorstep G.G.N = 8377087607
Gurgaon Call Girls: Free Delivery 24x7 at Your Doorstep G.G.N = 8377087607
 
Storytelling, Ethics and Workflow in Documentary Photography
Storytelling, Ethics and Workflow in Documentary PhotographyStorytelling, Ethics and Workflow in Documentary Photography
Storytelling, Ethics and Workflow in Documentary Photography
 
美国SU学位证,雪城大学毕业证书1:1制作
美国SU学位证,雪城大学毕业证书1:1制作美国SU学位证,雪城大学毕业证书1:1制作
美国SU学位证,雪城大学毕业证书1:1制作
 
办理哈珀亚当斯大学学院毕业证书文凭学位证书
办理哈珀亚当斯大学学院毕业证书文凭学位证书办理哈珀亚当斯大学学院毕业证书文凭学位证书
办理哈珀亚当斯大学学院毕业证书文凭学位证书
 
Students with Oppositional Defiant Disorder
Students with Oppositional Defiant DisorderStudents with Oppositional Defiant Disorder
Students with Oppositional Defiant Disorder
 
ME 205- Chapter 6 - Pure Bending of Beams.pdf
ME 205- Chapter 6 - Pure Bending of Beams.pdfME 205- Chapter 6 - Pure Bending of Beams.pdf
ME 205- Chapter 6 - Pure Bending of Beams.pdf
 
8377877756 Full Enjoy @24/7 Call Girls in Pitampura Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Pitampura Delhi NCR8377877756 Full Enjoy @24/7 Call Girls in Pitampura Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Pitampura Delhi NCR
 
LinkedIn for Your Job Search in April 2024
LinkedIn for Your Job Search in April 2024LinkedIn for Your Job Search in April 2024
LinkedIn for Your Job Search in April 2024
 
AI ppt introduction , advandtage pros and cons.pptx
AI ppt introduction , advandtage pros and cons.pptxAI ppt introduction , advandtage pros and cons.pptx
AI ppt introduction , advandtage pros and cons.pptx
 

Richard Turnbull CV Supplement 2012

  • 1.
  • 2. Offshore Industry Experience: - Design, Manufacture & FAT of Specialist Systems: - Carousel & Basket Lay Systems Subsea Equipment Launch Systems HDPE Crossings and J Tubes systems J Tube Gravity Base Radial Friction Welding Sea-fastening Systems Vessel Conversion & Construction Solution Engineering Project Disciplines: - Wind Farm Installations Jacket “Piece Small” Decommissioning Flexibles, Umbilical's, Risers, Power Cables & LoFS Installations J Tube Installation Pipeline Pre Commissioning Product Trenching; Jet Trenching, Ploughing, Rock Cutting Remote Intervention Riser Pull-ins & Shore Landings Pipeline Reel Lay Spool Piece; Fabrication, Metrology, Installation SSIV / Manifold & Over Protection Structure Installation Wet Buckle Repair System
  • 3. February 2011 – October 2012 Saipem UK - Katy Project Engineering Manager ConocoPhillips - Katy Field Development, Southern North Sea: - Reel lay installation and jet trenching of 14.2km 10”x22.2mm pipeline c/w 2” Coil tubing piggyback line. Design, manufacture and installation of 2 off Subsea manifolds & 4 off Tie in spools. System Pre Commissioning. • Management of all project engineering • Establishment of project team • Overseeing procurement scope of work documents for all project supply activities including procurement of project line pipe, coil tubing, subsea valves & structures. • Coordination of project analysis • Layout of the Hartlepool spool base • Design, manufacture and testing of Reel lay vessel SWWD / systems. • Client interface and engineering reporting • Offshore Installation and Pre Commissioning phases
  • 4. October 2009 – February 2011 VSMC - Engineering Manager (UK) • Set up a new Energy Engineering Department in Darlington, UK • Implemented all project systems/documentation along Oil & Gas lines and standardised installation procedures • Recruited and managed a dedicated multi-skilled project engineering team • Undertook outline / detailed planning of installation workscope • Managed the analysis, design, build & FAT/SIT of specialist project equipment on behalf of Statoil • Vessel analysis and selection • Shore End approach engineering inc. Pull in analysis, Landfall Works, Vessel Positioning & Float in and lay of product • Export Cable Lay & Second End Pull in at Substation • Inter Array Cable Installation • Trenching Analysis & Equipment selection ► Statoil - Sherringham Shoals Windfarm - 88 Turbine & 2 Sub Station installation ► BritNed – British/Dutch interconnector project
  • 5. March 2009 – August 2009 Saipem UK - Lead Engineer Frigg 2009 Decommissioning Removal of the Quarters Platform (QP) - Pre and post transit survey of the route into the Aker stored facility. Dredging of the pile locations, diamond wire cutting of the piles and one piece removal of the jacket by the S7000 . Removal of the Drilling Platform 1 (DP1) Use of subsea remote intervention technology. Pre-dredging at level one, “piece small” subsea preparation, dismantling, lifting and transfer of jacket sections to subsea storage containers. General seabed debris removal. 11 weeks offshore operations
  • 6. April 2008 - May 2008 CTC Marine Projects Limited Senior Project Manager - BP Shefa II Project 120km lay & burial of Fibre Optic product running from the BP Clair Platform through to the BP Schiehallion FPSO in the north east Atlantic, approximately 140km NNE of Cape Wrath, west of Shetland Islands. Workscope included, Subsea Clamp installation, dynamic riser pull-in and hang off assembly. Product tensioning at the Clair Platform. FOTA deployment at Schiehallion FPSO. Eleven crossings to bridge. Recovery and splicing of BU tails at the FT FO cable intersection. Trenching of the product utilises the T1 Wheel Cutting Tractor & ISU 150te Plough. Construction vessel Maersk Advancer. Project Value £6.5million.
  • 7. November 2006 – April 2008 CTC Marine Projects Ltd Senior Project Manager - Vessel Build. 106m “OCV Volantis” Management of specification and build of the vessel. Designed for Construction / Trenching roles. Development and implementation of many innovative systems enabling the vessel to be configured to meet the various project demands efficiently. Features included “Plug and play” system philosophy, modular container garage and handling system, unique sea-fastening system and control room. Specialist team consisted of eight persons. Reporting to upper management. Project Value £70m.
  • 8. November 2006 – April 2008 CTC Marine Projects Ltd Senior Project Manager - 2000Te Carousel Lay System Specification and management of lay system including 17m Carousel, Fleeting tower, Accumulator and Tensioner. A modular designed system capable of operation on multiple construction vessels in various configurations. Included vessel hull analysis, grillage design, analysis and build. Incorporated a unique sea fastening system allowing efficient mob/demob. Lay control integrated into the vessel DP system. “Plug and play” philosophy adopted for the vessel integration.. Project Value £5m.
  • 9. November 2006 – April 2008 CTC Marine Projects Ltd Senior Project Manager/Designer - Seafastening System Primarily designed for the integration of a 2500Te Carousel lay system on to the OCV Volantis, this unique seafastening system allows for efficient mob/demob of equipment on to vessels with no requirement for welding or burning on deck. Mob/Demob times cut from 4 - 5 days to approx. 6hrs.
  • 10. January 2006 – September 2006 CTC Marine Projects Limited Project Manager - BP Clair Platform West of Shetland LoFS (Life of Field Seismic) installation including field layout and installation planning, route and boulder clearance, J Tube Gravity Base design/engineering, Pipeline Bridge installation & system testing. The LoFS system included some 50km of product simultaneously laid and trenched in difficult seabed conditions utilising the CTC T3 wheel cutter trenching system. Project Value £11.5m.
  • 11. January 2006 - September 2006 CTC Marine Projects Ltd. Project Manager - Gravity J Tube Base As part of the overall BP Clair LoFS project, design, manufacture and installation of a Gravity J Tube Base for dynamic riser installation. Design work included: - 100 year storm loading analysis On bottom stability analysis Design finite element analysis Launch and recovery analysis In air weight 65Te
  • 12. November 2003 – June 2004 Saipem - Lead Project Engineer & Assistant Project Manager. Statoil - Sleipner Vest Alfa Nord Extension Project. Project Pre requisites Conversion of the Solstad MV Normand Cutter cable lay vessel into a construction vessel. Both vessel conversion and project were completed on time. This work included: - • Clearing / cutting of deck and associated cable lay equipment • Fitting of 300Te heave comp crane. • Under deck strengthening for Carousel lay system. • Fitting of the 25m, 3000Te product lay Project system • Installation of an 18.5km umbilical comprised 75mm x 5.5mm super duplex core with associated electrical and • SIT prior to transit to field hydraulic lines • Product loaded out of Kaverner at Moss Norway after completing vessel & equipment trials of the Normand Cutter • Managing Project Engineering & Client interface • Preparation / submission of project documentation • Offshore installation activities
  • 13. May 2002 – July 2002 Saipem - Project Engineering Manager: - Installation of two “four-slot” drilling templates inc. protection structures for Norsk Hydro on the ‘Fram Vest’ Field Development. Responsibility for: • Preparation / submission of project documentation & Engineering • Project scheduling • Vessel mobilisation of activities at ERS Base, Rotterdam • Vessel loading Langesund, Norway • Offshore support.
  • 14. April 2001 - Aug 2001 Saipem - Lead Engineer – Bluestream ITUR Cable Crossings Work included Jig design & manufacture, Crossing manufacture & in dock testing. Controlled and reported budgets / schedules to upper management and liaised daily with Sub-Contractor. Technical: - Quantity 2 off 30m in length Weighing 30Te in air. On bottom weight 800Kg. Manufactured from HDPE “The fabrications were initially six weeks behind schedule on hand over. Delivery of the equipment was made one day ahead of original target schedule.”
  • 15. September 2002 - March 2002 Saipem - Lead Engineer: - WBRS Transferred within the Bluestream Project to technically assess and manage the “Wet Buckle Repair System” (WBRS) redesign programme. Initiated redesign of key elements. Involved in preparation of the schedule, procurement, logistics and cost estimates of the work. Mobilised the build site in Samsun, Turkey and finalised documentation to ‘As Built’ status. Co-ordinated / managed the 8-week rebuild phase of the equipment and FAT. Technical: - 2300m depth rated ROV intervention system
  • 16. 2000 – 2001 Stolt Offshore Ltd Project Manager: - Deep Matis Launch System Established design / deployment data / criteria and all commercial requirements of the system. Directed the design scope and controlled / reported budgets and schedules to upper management. Commissioned specialist finite element analysis, feasibility study and advanced ‘real time’ modelling. Managed procurement / supply of materials & services, as well as manufacture / assembly of equipment. Executed commissioning and handover of project equipment to site in Norway and ‘closed out’ contracts. Technical: - 2300m depth rated Operation West Africa. Designed to land on 0.4 kpa soils. ROV intervention system. Project Value: - £1.25million
  • 17. 1997 – 2000 Stolt Offshore Ltd Project Manager - Radial Friction Welding ‘J’ Lay Pipe System Set up manufacturing site. Established management systems. Controlled / reported manufacturing budgets to senior management. Directed the conceptual designs, manufacturing solutions and procedures. Manufactured and built key machines Wrote and Co-ordinated the assembly plans, devised commissioning tests/ procedures. Implemented design / manufacture of test equipment, reviewed test data and set remedial actions. (value £10 million). Technical: - 2Mw system designed to friction weld a variety of metals up to 12 ¾” API pipe.
  • 18. Trenching Systems Vessels  Beluga  Bar Protector DSV  CMR3 Jetting ROV  Cygnus  Flexjet  Edda Freya  ISU Product Plough  Far Samson  T1 & T3 Rock Cutter  Far Sovereign  UT1 Jet Trencher  Helix Express  Maersk Advancer  Maersk Recorder  Maersk Responder  Maxita  Normand Cutter  Ocean Challenger  Polar Prince  Seaway Falcon  Team Oman Contact details: -  Volantis richard.turnbull@offshore-energy.co www.offshore-energy.co