2. 2
Objectives
At the end of this session you will be able to
Monitor and Control Changes in your Project
Evaluate the Impact of Proposed Changes
(scope, schedule, and cost)
Control the Flow of Changes in your Project
Stop Worrying and BE IN CONTROL
Earn Your Pay as a Project Manager
8. 8
Initiating
Project Charter
Issued by sponsor
Authorizes existence of a project
Gives project manager the authority to
– Apply organizational resources
– Conduct project activities
Like a contract
9. 9
Planning
Project Management Plan
Defines how a project is:
– Executed
– Monitored and Controlled
May include other plans and documents
– Scope / Requirements
– Schedule Baseline / Milestones
– Budget / Cost Performance Baseline
14. 14
Project Goes As Planned
Plan – Set the Baseline
Do – Execute Project Activities
Check – Compare actual vs. planned project
performance
Act – Take corrective action
15. 15
Project Goes as Planned
Plan – Set the Baseline
Do – Execute Project Activities
16. 16
Project Goes as Planned
Plan
Do
Check – Compare actual vs. planned project
performance
– Tollgate Review
– Earned Value Analysis
19. 19
Project Goes As Planned
Plan
Do
Check
Act – Take corrective action
– Within tolerances, no formal change request
– Outside tolerances, Project Manager enters a
Change Request
20. 20
Project Goes as Planned
Take corrective action
Tolerances
How far off before you fix it
– 3 days late
– 10% over budget
Measure each major deliverable
Or whole project?
21. 21
Project Goes as Planned
Measure each major deliverable
Or whole project?
24. 24
Changes from the Peanut Gallery
Integrated Change Management
Change Request Form
Change Control Board
Manage Baselines
Only Approved Changes are Implemented
25. 25
Changes from the Peanut Gallery
Change Happens in all projects
Change Requests Come from Stakeholders:
– Project Manager
– Sponsor
– Team Members
– Customer
– Regulators
– Peanut Gallery
Only Approved Changes are Implemented
26. 26
Change Control Board
Meets to review change requests
Approves or rejects change requests
Roles are clearly defined and agreed upon
by appropriate stakeholders
All board decisions are documented and
communicated to stakeholders
for information and follow-up actions
Only Approved Changes are Implemented
27. 27
Manage Baselines
Approved changes are documented and
added to the project plan
Manage baselines to include these changes
– Scope baseline
– Schedule baseline
– Cost baseline
28. 28
Changes from the Peanut Gallery
Integrated Change Management
Change Request Form
Change Control Board
Manage Baselines
Only Approved Changes are Implemented
This Protects the Project Manager
30. 30
Risk Happens
Change requests can result from risks
An uncertain event or condition that, if it
occurs, has a positive or negative effect on a
project’s objectives
33. 33
Risk Happens
Risk mitigation may require action
Project Manager submits a change
request
Change Control Board reviews request
Approved or Rejected
Communicate to Stakeholders
Adjust Baselines
34. 34
Risk Happens
Change requests can result from risks
An uncertain event or condition that, if it
occurs, has a positive or negative effect on a
project’s objectives
37. 37
Changes from the Peanut Gallery
Integrated Change Management
Change Request Form
Change Control Board
Manage Baselines
Only Approved Changes are Implemented
This Protects the Project Manager
38. 38
Risk Happens
Change requests can result from risks
An uncertain event or condition that, if it
occurs, has a positive or negative effect on a
project’s objectives
39. 39
Objectives
At the end of this session you will be able to
Monitor and Control Changes in your Project
Evaluate the Impact of Proposed Changes
(scope, schedule, and cost)
Control the Flow of Changes in your Project
Stop Worrying and BE IN CONTROL
Earn Your Pay as a Project Manager