SlideShare une entreprise Scribd logo
1  sur  51
Télécharger pour lire hors ligne
Application of San Diego Gas & Electric
Company (U902M) for authority to update its gas
and electric revenue requirement and base rates
effective on January 1, 2012.


Application No. 10-12-___
Exhibit No.: (SDG&E-11-CWP)




                        CAPITAL WORKPAPERS TO
                     PREPARED DIRECT TESTIMONY
                    OF THOMAS O. BIALEK, Ph.D., P.E.
      ON BEHALF OF SAN DIEGO GAS & ELECTRIC COMPANY




             BEFORE THE PUBLIC UTILITIES COMMISSION
                  OF THE STATE OF CALIFORNIA



                               DECEMBER 2010




                                    TOB-CWP-1
CAPITAL PROJECT WORKPAPER
                                                                                       Page 2 of 27

PROJECT TITLE                                                                          SBUDGET NO.
Smart Grid Portfolio                                                                      10261
WITNESS                                                                               IN SERVICE DATE
Lee Krevat/Tom Bialek                                                                    various

      PROJECT COST          PRIOR                                                 REMAINING
      ($000 in 2009$)       YEARS       2009       2010       2011      2012        YEARS     TOTAL

DIRECT LABOR                        0          0          0     9696     15093            0        24789

DIRECT NONLABOR                     0          0          0    26872     42176            0        69048

TOTAL DIRECT CAPITAL                0          0          0    36568     57269            0        93837

COLLECTIBLE

NET CAPITAL                         0          0          0    36568     57269            0        93837

FTE                                 0          0          0     129.3     201.2           0        330.5




BUSINESS PURPOSE
This project portfolio incorporates smart grid technologies into the electric system infrastructure
with a goal of maintaining and/or improving system performance and operational flexibility and
reliability. As the penetration levels of renewables and electric vehicles increase relative to the
local load on the system, they are expected to impact system operations and reliability and this
portfolio will provide implementation of effective measures to mitigate these impacts. Relative
to infrastructure expansion, projects that involve building completely new large scale elements of
the distribution network such as new substations and new circuits shall be designed with a
perspective that strives to incorporate smart grid concepts and equipment where applicable.


This project portfolio also integrates with system improvement work being done to reduce the
fire threat in the overhead electric system located in the very high/extreme fire threat zone as this
hardening work provides a unique opportunity to incorporate smart grid elements to achieve the
most overall effective and superior solution. Smart grid and the fire hardening rebuilding
projects are particularly synergistic as the projects can be designed with a goal of providing more
operational flexibility, improved reliability and at the same time reduce fire risk. Smart grid
sensor technology, advanced system monitoring and control features can be integrated into the




                                               TOB-CWP-2
CAPITAL PROJECT WORKPAPER
                                                                                     Page 3 of 27

PROJECT TITLE                                                                        SBUDGET NO.
Smart Grid Portfolio                                                                   10261
WITNESS                                                                            IN SERVICE DATE
Lee Krevat/Tom Bialek                                                                  various


operation of the system which is especially valuable during storms and extreme fire risk weather
events. In addition to maintaining and/or improving reliability, the circuit hardening work with
smart grid technologies should facilitate integration of distributed energy resources such as solar
and wind, as well as energy storage for back up of important community infrastructure such as
cell phone networks, communications devices and small water pumps used to supply drinking
water and fill small storage tanks that otherwise may lose power during extreme conditions. This
project portfolio should provide the ability to incorporate technologies that can keep more
customers and critical infrastructure safely in service during extreme fire risk weather events as
well as during storm periods and times when the electric system is stressed due to high operating
loads or operational emergencies. Specific categories of technologies to be provided by this
project are listed below.


PROJECT DESCRIPTION AND JUSTIFICATION
The description and justification for each of the Smart Grid technologies included in this capital
project are given below:


RENEWABLE GROWTH
ƒEnergy Storage (ES) - A cost forecast is provided for two types of energy storage systems to assist
   in addressing intermittency issues created by the variable output of renewable energy resources.
   One solution will place distributed energy storage systems on circuits with high penetration of
   customer photovoltaic systems. Additionally, energy storage systems will be strategically located
   in substations to mitigate the impact of multiple circuits with PV as the second budget item.
ƒDynamic Line Ratings – A cost forecast is provided for implementation of dynamic ratings for
   distribution circuits. The implementation of dynamic line ratings has the potential for increasing
   circuit capacity and accommodating new renewable generation.
ƒPhasor Measurement Units – A cost forecast is provided for implementation of phasor
   measurement units on the electric distribution system. Installation of phasor measurement units




                                            TOB-CWP-3
CAPITAL PROJECT WORKPAPER
                                                                                      Page 4 of 27

PROJECT TITLE                                                                         SBUDGET NO.
Smart Grid Portfolio                                                                    10261
WITNESS                                                                             IN SERVICE DATE
Lee Krevat/Tom Bialek                                                                   various


   on the electric distribution system are expected improve reliability by employing high speed, time
   synchronized measurement devices. These devices will be utilized in conjunction with energy
   storage devices to create a closed loop control system to mitigate the impact of intermittent
   renewables.
ƒCapacitor SCADA – A cost forecast is provided to implement SCADA control of all capacitors on
   SDG&E’s distribution system and is distinct from the SCADA expansion for switches discussed
   below. Benefits of SCADA for capacitors should include: better voltage and VAr control,
   reduced maintenance, and better system diagnostics. When coupled with energy storage,
   dynamic line ratings and phasor measurements new control schemes can be implemented which
   will mitigate the impact of PV system output fluctuations on system voltage.
ƒSCADA Expansion – A cost forecast is provided for expansion of SCADA to expand remote
   operability and automated operation of distribution SCADA capable switches. This will continue
   SDG&E’s goal of providing faster isolation of faulted electric distribution circuits and branches,
   resulting in faster load restoration and isolation of system disturbances.


ELECTRIC VEHICLE GROWTH
ƒSmart Transformers – A cost forecast is provided for the installation of sensors and technology on
   distribution transformers so that they can monitor and report loading, and the state of the
   transformers. This project has the potential to allow increased transformer capacity utilization
   and accommodate future loads such as electric vehicle charging.
ƒPublic Access Charging Facilities – A cost forecast is provided for the installation of utility owned
   public charging facilities for electric vehicles. SDG&E will install and own the charging facilities
   in under-served areas in order to broaden the coverage of public charging stations within its
   service territory. This project will also help to develop the services offered by 3rd parties to
   support vehicle charging facilities.




                                            TOB-CWP-4
CAPITAL PROJECT WORKPAPER
                                                                                     Page 5 of 27

PROJECT TITLE                                                                         SBUDGET NO.
Smart Grid Portfolio                                                                    10261
WITNESS                                                                             IN SERVICE DATE
Lee Krevat/Tom Bialek                                                                  various


RELIABILITY
ƒWireless Faulted Circuit Indicators - A cost forecast is provided for implementation of wireless
   faulted circuit indicators. This system is expected to provide rapid identification and location of
   faulted distribution circuits resulting in reduced outage and repair times.
ƒPhase Identification – A cost forecast is provided for accurate identification of phasing for
   implementation in the new distribution operating system. This project should enable improved
   worker safety, more accurate fusing, improved system planning, and reduced system losses.
ƒCondition Based Maintenance Expansion – A cost forecast is provided for expansion of CBM to
   include distribution substation transformers at 4 kV substations. This project should reduce the
   risk of catastrophic failures and improve customer satisfaction.


SMART GRID DEVELOPMENT
Integrated Test Facility – A cost forecast is provided to construct facility upgrades and
purchase and install equipment to create an integrated test facility. This will allow testing of the
integration of multiple complex hardware and software systems comprising smart grid
technologies.




                                            TOB-CWP-5
CAPITAL PROJECT WORKPAPER
                                                                                     Page 6 of 27

PROJECT TITLE                                                                        SBUDGET NO.
Smart Grid Portfolio                                                                    10261
WITNESS                                                                             IN SERVICE DATE
Lee Krevat/Tom Bialek                                                                  various


RENEWABLE GROWTH: ENERGY STORAGE

A cost forecast is provided for two types of energy storage systems to assist in addressing
intermittency issues created by the variable output of renewable energy resources. One solution will
place distributed energy storage systems on circuits with high penetration of customer photovoltaic
systems. Additionally, energy storage systems will be strategically located in substations to mitigate
the impact of multiple circuits with PV as the second budget item.


Energy storage systems will be used to demonstrate the ability to enhance the value of energy
from renewable distributed generation in at least two fundamental ways: minimize the
intermittency problem of renewables by installing storage and if appropriate and possible, use
storage so that electric energy generated during times of lowest system need can be “time-
shifted” and used during time of greatest need to the electric system.


As the penetration of distributed energy resources, DER, continues to increase, the need for
distributed storage will also increase in order to mitigate intermittency problems at the local 12
kV feeder level. This project will install energy storage in two forms: 1) distributed storage in
the form of community energy storage, CES, devices in those circuits where the penetration of
distributed PV is 20% or more of the circuit load at times of high photovoltaic system output and
low circuit loads, and 2) substation energy storage of utility scale, size anticipated to be 1 MW or
greater, which will be installed to mitigate the effects of utility scale (up to 2 MW) PV projects
that will be installed in various locations.


Storage devices will be installed at substations with identified large PV additions (Creelman,
Pala, Valley Center, Lilac) and substations with high forecasted PV growth (Border, Kyocera,
Middletown, Poway). Unit-cost estimates for substation Storage are based on price quotation
obtained from Bulk Storage providers in September, 2009.




                                               TOB-CWP-6
CAPITAL PROJECT WORKPAPER
                                                                                      Page 7 of 27

PROJECT TITLE                                                                         SBUDGET NO.
Smart Grid Portfolio                                                                     10261
WITNESS                                                                              IN SERVICE DATE
Lee Krevat/Tom Bialek                                                                   various


Energy Storage, installed in conjunction with the appropriate sensors, control and
communication systems should provide a solution for the mitigation of intermittency via the
management and discharge of stored energy in a controlled and coordinated way.


Based on the historical and forecasted penetration of distributed PV in the SDG&E service
territory, CES devices, which are small, 50kW batteries, will be installed on 11 circuits in 2011,
and on 14 more circuits in 2012. In addition to the CES devices, substation energy storage
amounting to 4 MW will be installed in 2011 and another 4 MW will be installed in 2012.


A prioritized list of circuits that are good candidates for distributed storage, based on PV growth
projections, has been developed. CES unit-cost estimates were obtained from the EPRI Storage
System Cost Workbook, published in March, 2010.

Cash Flow:
($000 in 2009$)
Year:                      2010                2011                 2012                 Total
Direct Labor:               0                 6281                 7427                  13708
Direct Non-labor:            0                18912                22363                 41275
Total Capital:               0                25193                29790                 54983




                                            TOB-CWP-7
CAPITAL PROJECT WORKPAPER
                                                                                    Page 16 of 27

PROJECT TITLE                                                                         SBUDGET NO.
Smart Grid Portfolio                                                                    10261
WITNESS                                                                             IN SERVICE DATE
Lee Krevat/Tom Bialek                                                                  various


ELECTRIC VEHICLE GROWTH: SMART TRANSFORMERS

A cost forecast is provided for the installation of sensors and technology on distribution transformers
so that they can monitor and report loading, and the state of the transformers. This project has the
potential to allow increased transformer capacity utilization and accommodate future loads such as
electric vehicle charging.


Distribution line transformers can be converted into smart devices by installing monitoring
equipment on the secondary bushings. These monitors will provide information to engineers and
operators about the state of the grid including distributed resources and loads at the location of
the transformers. This data will be especially valuable for monitoring the load and condition of
transformers feeding plug-in electric vehicles. It will also provide information about the state
and condition of the transformer. Transformer monitors will facilitate dynamic ratings for the
transformers, the ability to verify energy consumed or generated by new distributed resources or
loads for potential management applications, and the ability to assess detailed transformer
conditions in order to proactively troubleshoot customer or secondary voltage problems.


This project will install transformer monitoring devices on all transformers serving customers
with plug-in electric vehicles. Sensing devices attached to transformers will be used to monitor
real-time loading and establish accurate load profiles. This information will be available to
system operators to alert them to possible overloads, imbalances, voltage excursions or other
operational issues. Additionally, engineers will use this information to revise transformer
loading guidelines which may lead to optimizing the number of customers that may be served
from an individual transformer and reducing transformer loading problems.


One transformer monitoring device will be installed on every distribution transformer that serves
a customer with a PEV and associated charge stations. The number of PEV charge stations is
anticipated to be:



                                           TOB-CWP-16
CAPITAL PROJECT WORKPAPER
                                                                                   Page 17 of 27

PROJECT TITLE                                                                        SBUDGET NO.
Smart Grid Portfolio                                                                     10261
WITNESS                                                                            IN SERVICE DATE
Lee Krevat/Tom Bialek                                                                    various




Year:                             2010             2011              2012                Total
PEV Charge Stations:              600              2150              700                 3450


This estimated number of charge stations is based on the expected sales of battery electric
vehicle and plug-in hybrid electric vehicle sales in the San Diego area. This estimate is based
upon a DOE sponsored program with partnership by ECOtality and Nissan to deploy up to 5,000
electric vehicles and charging infrastructure in San Diego and four other U.S. cities.
This project will begin in 2011, therefore the number of transformer monitors installed in 2011
will match the number of charge stations installed in 2010 and 2011. The cost estimate for this
project is derived from an estimated average cost of $744 per transformer monitor installed on
2750 transformers in 2011 and on 700 transformers in 2012. The average cost estimate per
transformer was based on information provided by a manufacturer of transformer monitoring
equipment that could be used for this project.




Cash Flow:
($000 in 2009$)
Year:                      2010                  2011              2012                   Total
Direct Labor:               0                    680               173                    853
Direct Non-labor:            0                   1367              348                    1715
Total Capital:               0                   2047              521                    2568




                                           TOB-CWP-17
CAPITAL PROJECT WORKPAPER
                                                                                     Page 18 of 27

PROJECT TITLE                                                                          SBUDGET NO.
Smart Grid Portfolio                                                                     10261
WITNESS                                                                              IN SERVICE DATE
Lee Krevat/Tom Bialek                                                                    various


ELECTRIC VEHICLE GROWTH: PUBLIC ACCESS CHARGING FACILITIES

A cost forecast is provided for the installation of utility-owned, public access charging facilities
for electric vehicles. SDG&E will install and own the charging facilities in under-served areas in
order to broaden the coverage of public charging opportunities within its service territory. This
effort will allow SDG&E to continue the momentum of the stakeholder charging facility siting
and installation process established by ECOtality as part of their government funded EV Project
between 2010 and mid-2011. As planned, this project will increase the number of charging
facility services offered by 3rd parties, specifically to provide PEV charging facilities in locations
that are not necessarily commercially or economically desirable, but needed to serve the broader
and growing PEV charging needs of the public.


SDG&E will work with the CPUC to develop broad criteria for evaluating the installation of
“public access charging facilities” with the objective to ensure a network of public charging
facilities is developed in the public interest over time that would provide sufficient support for
the adoption and use of PEVs


The number of 240V Level 2 charges installed will be approximately 1% of the cumulative plug-
in hybrid electric vehicles, PHEVs, anticipated in the 2012 through 2015 period, and the number
of DC Fast Chargers will be approximately 0.1% of the cumulative PHEV’s in the 2012-2015
period (see table below). PEV charging facility users will pay for the use of these charging
facilities through an applicable PEV tariff that will be developed in accordance with policy
established in the CPUC’s Alternative Fueled Vehicle Order Instituting Rulemaking.

Year:                                   2010             2011             2012            Total
240V Level 2 Charge Stations            0                0                129             129
480V DC Fast Charger Stations:          0                0                13              13




                                            TOB-CWP-18
CAPITAL PROJECT WORKPAPER
                                                                                  Page 19 of 27

PROJECT TITLE                                                                       SBUDGET NO.
Smart Grid Portfolio                                                                   10261
WITNESS                                                                            IN SERVICE DATE
Lee Krevat/Tom Bialek                                                                 various


The cash flow below reflects the public access charging facilities funding requirements for the
entire SDG&E system taking place over a four year period (2012-2015) with the work beginning
in 2012. The cash flow below reflects the public access charging facilities funding requirements
taking place over a four year period (2012-2015). This cost estimate is derived from an
estimated average cost of approximately $33,000 per 240V charging facility times 129 such
facilities per year, plus approximately $71,000 per 480V charging facility times 13 such facilities
per year.




Cash Flow:
($000 in 2009$)
Year:                      2010                2011                2012                 Total
Direct Labor:               0                   0                  1503                 1503
Direct Non-labor:            0                  0                  3727                 3727
Total Capital:               0                   0                 5230                 5230




                                           TOB-CWP-19
CAPITAL PROJECT WORKPAPER
                                                                                 Page 27 of 27

PROJECT TITLE                                                                     SBUDGET NO.
Smart Grid Portfolio                                                                 10261
WITNESS                                                                          IN SERVICE DATE
Lee Krevat/Tom Bialek                                                               various


Cash Flow:
($000 in 2009$)
Year:                     2010                2011               2012                 Total
Direct Labor:              0                   45                120                  165
Direct Non-labor:           0                 457                1220                 1677
Total Capital:              0                  502               1340                 1842




SUMMARY CASH FLOW

A summary table of the cash flows for all projects in this workpaper is provided below.




                                          TOB-CWP-27
Application of San Diego Gas & Electric
Company (U902M) for authority to update its gas
and electric revenue requirement and base rates
effective on January 1, 2012.



Application 10-12-____
Exhibit No.: (SDG&E-11)




                        PREPARED DIRECT TESTIMONY OF
                             THOMAS BIALEK, Ph.D., P.E.
          ON BEHALF OF SAN DIEGO GAS & ELECTRIC COMPANY




                     BEFORE THE PUBLIC UTILITIES COMMISSION
                          OF THE STATE OF CALIFORNIA


                                       December 2010




SDGE Doc #249440
TABLE OF CONTENTS

I.          INTRODUCTION...................................................................................................................... 1
       A. Purpose of Testimony ................................................................................................................ 1
       B. Overview of Operations ............................................................................................................. 3
       C. Challenges Facing Operations .................................................................................................. 4
       C. Reliability .................................................................................................................................. 14
       D. Smart Grid Development ........................................................................................................ 15
       E. Summary of Request................................................................................................................ 16
II.         NONSHARED SERVICES ..................................................................................................... 17
       A. Introduction .............................................................................................................................. 17
            1. Smart Grid Team ............................................................................................................... 17
       B. Discussion of O&M Activities ................................................................................................. 17
            1. Smart Grid Team Salaries and Benefits .......................................................................... 17
III.        CAPITAL.................................................................................................................................. 18
       A. Introduction .............................................................................................................................. 18
       B. Capital Request Detail ............................................................................................................. 20
            1. Renewable Growth: Energy Storage (Budget Codes: 10261) ....................................... 20
            2. Renewable Growth: Dynamic Line Ratings (Budget Codes: 10261) ........................... 21
            3. Renewable Growth: Phasor Measurement Units (PMU) - Synchrophasors (Budget
                  Codes: 10261) ..................................................................................................................... 22
            4. Renewable Growth: Capacitor SCADA (Budget Codes: 10261) ................................. 24
            5. Renewable Growth: SCADA Expansion (Budget Codes: 10261) ................................. 25
            6. Electric Vehicle Growth: Plug-In Electric Vehicles ...................................................... 26
            7. Electric Vehicle Growth: Smart Transformers (Budget Codes: 10261) ...................... 27
            8. Electric Vehicle Growth: Public Access Charging Facilities (Budget Codes: 10261) 28
            9. Reliability: Wireless Fault Indicators (FCI) (Budget Codes: 10261) .......................... 31
            10. Reliability: Phase Identification (Budget Codes: 10261) ............................................... 32
            11. Reliability: Condition Based Maintenance (CBM) Expansion
                  (Budget Codes: 10261) ....................................................................................................... 33
            12. Smart Grid Development: Integrated Test Facility (Budget Codes: 10261) ............... 35
IV.         CONCLUSION ........................................................................................................................ 35
V.          WITNESS QUALIFICATIONS ............................................................................................. 37



SDGE Doc #249440                                                         TOB-i
1                                PREPARED DIRECT TESTIMONY OF
 2                                   THOMAS BIALEK, Ph.D., P.E.
 3                     ON BEHALF OF SAN DIEGO GAS & ELECTRIC COMPANY
 4
 5
 6   I.    INTRODUCTION
 7
 8         A.     Purpose of Testimony

 9                1.      New Projects Incremental to Historical Activities
10                        The purpose of this testimony is to sponsor the Smart Grid capital forecasts for
11                San Diego Gas & Electric Company, SDG&E, for the years 2010, 2011 and the test
12                year 2012. The Smart Grid portfolio of projects that are presented in this immediate
13                general rate case, GRC, application also have a life span that extend beyond the test
14                year. Additionally, this GRC funding request is not to be viewed as the entirety of
15                Smart Grid projects that SDG&E may request since other projects may be necessary in
16                the future as requirements change and as new technologies and solutions become
17                available.
18                        As discussed in the Smart Grid policy testimony of Mr. Lee Krevat, Exhibit
19                SDG&E-10, there are many drivers for SDG&E’s Smart Grid activities. Based upon
20                these drivers, SDG&E has developed a limited portfolio of projects with the goal of
21                applying Smart Grid technologies to effectively integrate intermittent renewable
22                generation sources and plug-in electric vehicles, and includes other capabilities
23                designed to maintain and/or improve system reliability. The projects included in this
24                general rate case include only the distribution component of each project. The
25                information technology, IT, capital portions associated with these projects are
26                necessary to provide the communication devices, IT infrastructure and applications
27                required to derive the functionality envisioned with the individual project. The IT
28                components required for the Smart Grid portfolio of projects, while need-justified
29                within the scope of this testimony, are presented in the testimony of Mr. Jeff Nichols,
30                Exhibit SDG&E-18. What might be described today as the conventional or on-going
31                capital and operations and maintenance forecasts are presented in the testimonies of
32                Mr. Alan Marcher, Exhibit SDG&E-06 and Mr. Scott Furgerson, Exhibit SDG&E-05
33                respectively.



     SDGE Doc #249440                              TOB-1
1   A list of the Smart Grid projects by categories and testimony sponsors is shown below:

 2   RENEWABLE GROWTH
 3    Energy Storage (ES)                 Capital       Thomas Bialek, Exhibit SDG&E-11
 4                                        IT            Mr. Jeff Nichols, Exhibit SDG&E-18
 5    Dynamic Line Ratings                Capital       Thomas Bialek, Exhibit SDG&E-11
 6                                        IT            Mr. Jeff Nichols, Exhibit SDG&E-18
 7    Phasor Measurement Units            Capital       Thomas Bialek, Exhibit SDG&E-11
 8                                        IT            Mr. Jeff Nichols, Exhibit SDG&E-18
 9    Capacitor SCADA                     Capital       Thomas Bialek, Exhibit SDG&E-11
10                                        IT            Mr. Jeff Nichols, Exhibit SDG&E-18
11    SCADA expansion                     Capital        Thomas Bialek, Exhibit SDG&E-11
12                                        IT            Mr. Jeff Nichols, Exhibit SDG&E-18
13
14
15   ELECTRIC VEHICLE GROWTH
16    Plug-in Electric Vehicles           Capital       Mr. Alan Marcher, Exhibit SDG&E-06
17                                        IT            Mr. Jeff Nichols, Exhibit SDG&E-18
18    Smart Transformers                  Capital       Thomas Bialek, Exhibit SDG&E-11
19                                        IT            Mr. Jeff Nichols, Exhibit SDG&E-18
20    Public Access Charging Facilities Capital         Thomas Bialek, Exhibit SDG&E-11
21                                        IT            Mr. Jeff Nichols, Exhibit SDG&E-18
22
23   RELIABILITY
24    Wireless Faulted Circuit Indicators Capital       Thomas Bialek, Exhibit SDG&E-11
25                                        IT            Mr. Jeff Nichols, Exhibit SDG&E-18
26    Phase Identification                Capital       Thomas Bialek, Exhibit SDG&E-11
27                                        IT            Mr. Jeff Nichols, Exhibit SDG&E-18
28   Condition Based Maintenance
29    Expansion                           Capital       Thomas Bialek, Exhibit SDG&E-11
30                                        IT            Mr. Jeff Nichols, Exhibit SDG&E-18
31
32




     SDGE Doc #249440                               TOB-2
1   SMART GRID DEVELOPMENT
 2      Integrated Test Facility           Capital         Thomas Bialek, Exhibit SDG&E-11
 3                                         IT              Mr. Jeff Nichols, Exhibit SDG&E-18
 4

 5                   2.     Smart Grid Team
 6                          This testimony also sponsors the ongoing funding of the cost center for the
 7                   Smart Grid Team. This small group of individuals: a Director, Chief Engineer, Lead
 8                   Architect, Policy Manager, Customer Manager and Administrative Associate; are
 9                   responsible for developing SDG&E’s Smart Grid strategy and policy. The organization
10                   is also responsible for aligning the strategy and policy across SDG&E.

11
12                                                 Table TOB -1
13                                        Summary of TY2012 Change
14                                              (Thousands of $2009)
15
     Functional Area: SMART GRID
                 Description                    2009             TY2012            Change          Testimony
                                              Adjusted-         Estimated                          Reference
                                              Recorded
     Total Non-Shared                       330               1,003            673               Section II
     Total Shared Services (Book            0                 0                0
     Expense)
     Total O&M                              330               1,003            673

     Total Capital                          0                 57,269           57,269            Section III
16

17          B.       Overview of Operations

18                   Smart Grid is a new activity. A special cost-center function has been created to deal
19          just with this topic, and that cost center’s role is to provide steering and strategic guidance
20          throughout the organization to coordinate the adoption and implementation of Smart Grid
21          related technologies.
22
23
24




     SDGE Doc #249440                                 TOB-3
1           C.       Challenges Facing Operations

 2                    As described in the testimony of Mr. Lee Krevat, Exhibit SDG&E-10, SDG&E is
 3           committed to meeting California policy goals of promoting increased levels of renewable
 4           energy resources and the deployment of electric vehicles to meet greenhouse gas reduction
 5           targets. However, with advancements in environmentally friendly technologies such as solar
 6           and wind generation, plug-in electric vehicles, and energy storage, as well as the deployment
 7           of new customer empowering Smart Meter technology, the electric system is in the midst of
 8           significant change. SDG&E recognizes the need to leverage equally advancing information
 9           and communication technologies, ICT, to ensure the continued safety, reliability, security, and
10           efficiency of the electric grid as utilization of intermittent energy resources and demand for
11           plug-in electric vehicle, PEV, increases.
12                    In addition to the traditional grid management and customer-facing projects utilities
13           have undertaken in the past, environmental policy and legislation encouraging customer
14           empowerment over energy management is driving the need to accelerate the integration of
15           digital and communications technology with the electric delivery system, creating a smarter
16           grid. The public policy objectives of California and the situation faced in San Diego create a
17           need to move forward with the implementation of advanced technology in order to meet the
18           State’s ambitious energy policy goals.
19                    The seven characteristics or performance features of a Smart Grid as developed by the
20           Department of Energy’s, DOE, Smart Grid Task Force and referenced by the CPUC are1:

21                            •        Anticipating and responding to system disturbances in a
22                                     self-healing manner;
23                            •        Enabling active participation by consumers;
24                            •        Operating resiliently against physical and cyber attack;
25                            •        Accommodating all generation and storage options;
26                            •        Enabling new products, services, and markets;
27                            •        Optimizing asset utilization and operating efficiently; and
28                            •        Providing the power quality for the range of needs in a
29                                     digital economy.
30

     1
      CPUC R.08-12-009, Order Instituting Rulemaking to consider Smart Grid Technologies Pursuant to Federal Legislation
     and on the Commission’s own Motion to Actively Guide Policy in California’s Development of a Smart Grid System, p
     11.



     SDGE Doc #249440                                      TOB-4
1                    SDG&E’s current portfolio of T&D Smart Grid projects focus on four specific areas:
 2           renewable generation growth, electric vehicle growth, reliability and Smart Grid development.
 3           In the first area SDG&E is focused on mitigating the impact of renewable photovoltaic, PV,
 4           distributed generation. For the second area, SDG&E is deploying new Smart Grid
 5           technologies as well as traditional infrastructure to mitigate reliability issues due to customer
 6           adoption of PEVs. The third area focus is to mitigate the reliability impacts of an aging
 7           electric infrastructure by implementing advanced sensors and associated systems. For the last
 8           area, SDG&E is planning to create an integrated test facility to put various emerging
 9           technology solutions together to test for interoperability and provide proof-of-concept
10           demonstrations.

11                    As indicated by Mr. Lee Krevat, Exhibit SDG&E-10, SDG&E needs to mitigate the
12           impacts of renewable generation development that is planned and occurring in the San Diego
13           region to satisfy California’s 33% Renewable Portfolio Standard, RPS. Additionally, San
14           Diegans have installed more total systems and nameplate capacity of distributed photovoltaic
15           generation than consumers in any city in the state based on 2009 data2. The arrival of 1,000
16           Nissan Leaf all-electric vehicles starting in December of 2010 will also increase the immediate
17           need for Smart Grid technologies on the electric grid in San Diego.
18                    Increased situational awareness enabled by sensors, communications, data, analysis and
19           remote control allows the system to be operated with increased reliability and safety. Dynamic
20           measurement of system characteristics and improved distribution management also increases
21           the capabilities and resiliency of energy delivery. However, as a result, the complexity of grid
22           operations is increased significantly.
23
24                    1.      San Diego Drivers
25                            The specific drivers of Smart Grid investments in the San Diego Gas & Electric
26                    service territory are the growth of distributed photovoltaics, PV, the expected growth of
27                    plug-in electric vehicles, PEVs and SDG&E’s aging infrastructure.
28
29


     2
       “California’s Solar Cities: Leading the Way to a Clean Energy Future”; Environment California Research and Policy
     Center, Summer 2009; accessed July 15, 2010 at http://www.environmentcalifornia.org/reports/energy/energy-program-
     reports/californias-solar-cities



     SDGE Doc #249440                                       TOB-5
1                             a.      Distributed Photovoltaic Growth
 2                                     At year end 2009 distributed PV accounted for approximately 65 MWac
 3                             of generating capacity on the SDG&E system. As of the same timeframe,
 4                             SDG&E has ten primary distribution circuits with over 20% of the load served
5                              by PV at times of low circuit loading as shown in Figure TOB-1.3 Figure TOB-
6                              2 illustrates both the actual recorded PV installations and the California Energy
 7                             Commission, CEC, forecast based on past PV growth.4 Applying the CEC
 8                             forecast to existing installations on circuits produces Figure TOB-3 which
 9                             shows the circuits with levels of over 20% PV generation at year end 2020.
10                             This figure shows sixty circuits meet this criteria, which SDG&E believes is an
11                             appropriate threshold to conduct more detailed studies to determine if the circuit
12                             can accommodate these levels of PV without impacting grid voltage operating
13                             limits or creating any operations and maintenance issues.
14
15




     3
       While SDG&E’s Rule 21 places an emphasis on percentage nameplate capacity as a function of peak line section rating,
     for PV systems the maximum output at times of lower system load (no air conditioning) are more critical.
     4
       CEC CALIFORNIA ENERGY DEMAND 2010-2020 December 2009, CEC-200-2009-012-CMF, ADOPTED
     FORECAST , Form 1.4, Page 149.




     SDGE Doc #249440                                       TOB-6
1
2         Figure TOB-1 – PV Penetration YE 2009 as a Percentage of Circuit Load on April 1, 2009, 1
3   pm
4
5
6




    SDGE Doc #249440                            TOB-7
1
2                Figure TOB-2 – Actual Historical PV Installations and CEC PV Forecast




    SDGE Doc #249440                            TOB-8
1
2      Figure TOB-3 – Impact of Increasing PV Penetration versus year with CEC Forecast Installations
3
4           SDG&E has been able to instrument a circuit with a high PV nameplate capacity at a time of
 5   low circuit loading. Figure TOB- 4 shows the impact of a 1 MWac PV system on SDG&E’s primary
 6   voltage for one day recorded with this instrumentation. The upper set of curves shows the impact of
 7   fog burning off on the output of the PV system and the commensurate changes in primary voltage
8    during the day. The lower set of curves is a magnified view, 10 minutes of one particular change in
 9   the PV system output data. Operational issues that are noted from these curves include the following:
10   high primary voltage coincident with PV system output and an approximately 15% swing in primary
11   voltage coincident with PV system output change. These measured and changes in values are outside
12   SDG&E’s design tolerance limits. Therefore, from the data and forecast currently available, SDG&E
13   believes investment in mitigation of intermittent photovoltaic generation is necessary.
14
15




     SDGE Doc #249440                                TOB-9
1
2                 Figure TOB-4 – PV System Output Variability Impact on Primary Voltage
3
4          One component of a solution to this problem is to incorporate energy storage as a grid device.
5   With energy storage, given its cost today, it is necessary to accrue benefits associated with multiple




    SDGE Doc #249440                                TOB-10
1   value streams in order to provide a least-cost solution. The value streams for energy storage are as
 2   follows:
 3               •   Grid operation to islanded system operation
 4                       •   Smoothing electrical transition
 5               •   Power quality
 6               •   Power leveling / regulation on grids with connected variable, renewal energy sources,
 7                   such as Wind, PV, etc.
 8               •   Peak load shifting / shaving
 9                       •   As needed
10                       •   Daily
11               •   Energy storage for off-peak / on-peak energy arbitrage
12               •   Energy regulation / ancillary services related to CAISO operations
13               •   T&D capacity deferral
14
15           SDG&E has utilized a report published by Sandia National Labs as a reference guide for
16   energy storage applications which states5:
17           "The work documented in this report represents another step in the ongoing investigation of
18           innovative and potentially attractive value propositions for electricity storage by the United
19           States Department of Energy (DOE) and Sandia National Laboratories (SNL) Energy Storage
20           Systems (ESS) Program. This study uses updated cost and performance information for
21           modular energy storage (MES) developed for this study to evaluate four prospective value
22           propositions for MES. The four potentially attractive value propositions are defined by a
23           combination of well known benefits that are associated with electricity generation, delivery,
24           and use. The value propositions evaluated are: 1) transportable MES for electric utility
25           transmission and distribution (T&D) equipment upgrade deferral and for improving local
26           power quality, each in alternating years, 2) improving local power quality only, in all years, 3)
27           electric utility T&D deferral in year 1, followed by electricity price arbitrage in following
28           years; plus a generation capacity credit in all years, and 4) electric utility end-user cost
29           management during times when peak and critical peak pricing prevail."

     5
       Sandia National Laboratory, SANDIA REPORT SAND2008-0978, Unlimited Release Printed, February 2008,
     Benefit/Cost Framework for Evaluating Modular Energy Storage, A Study for the DOE Energy Storage Systems Program,
     Susan M. Schoenung and Jim Eyer.
               




     SDGE Doc #249440                                    TOB-11
1
 2           The summary results of the SNL study are shown below.

 3           “Figure 17 shows the present worth of benefits and costs for lead-acid battery storage used for
 4           the four value propositions investigated. Most notably: value proposition 1 (T&D deferral plus
 5           PQ), value proposition 2 (PQ/reliability only) and value proposition 3 (high value T&D
 6           deferral plus arbitrage and generation capacity credit) show promise as they have a benefit/cost
 7           ratio greater than 1.
 8            




 9                                                                                                                     
10
11           Other components of the multi-faceted solution include dynamic line ratings, phasor
12   measurement units and supervisory control and data acquisition, SCADA, expansion to enable remote
13   control of capacitor banks and other switches on the system.
14
15           B.       Plug-In Electric Vehicle (PEV) Growth
16                    As also discussed in the testimony of Mr. Lee Krevat, Exhibit SDG&E-10, the impact
17           of PEVs on SDG&E’s system is expected to be significant. He discussed the US Department
18           of Energy, DOE, and California Energy Commission, CEC, grants awarded to ECOtality6 as


     6
       ECOtality is a San Francisco based company specializing in the development and commercialization of electric
     transportation and storage technologies.



     SDGE Doc #249440                                       TOB-12
1            well as the large loads that these vehicles will impose on the system as a result of the rapid
 2            deployment of PEVs and residential, commercial and public charging facilities in the SDG&E
 3            service territory beginning in 2010. He also mentioned the need to make infrastructure
 4            investments to empower customers and to minimize barriers that would be created without
 5            immediate action taken to ensure the deployment of adequate charging infrastructure. This
 6            position is also supported by the Commission as described in the testimony of Ms. Kathleen
 7            Cordova, Exhibit SDG&E-15 (SDG&E’s Electric Clean Transportation Program). In January
 8            2010, the Commission recognized the importance of early action to support the electric
 9            transportation market in defining the scope for the alternative-fueled vehicles rulemaking and
10            stated that it will follow the directive set forth in Senate Bill 626 to evaluate policies to develop
11            infrastructure sufficient to overcome any barriers to the widespread deployment and use of
12            plug-in hybrid and electric vehicles.7
13                     Figure TOB-5 shows SDG&E’s estimates of PEV sales in its service territory. This
14            estimate of PEV sales was based upon several independent analysts’ forecast of light duty
15            vehicles PEV penetrations adjusted to be applicable to SDG&E’s service territory and related
16            impacts. By 2012 approximately 15,000 PEVs are estimated to be owned by customers in
17            SDG&E’s service territory. With an estimated load of 3 kW per vehicle this equates to 45 MW
18            of new load, that if not managed properly could have a significant impact on the local
19            distribution system and potential generation needs. It should be noted that the Commission
20            approved in June of 2010 the use of three experimental PEV time-of-use rates, each with
21            varying differences between on-peak and off-peak pricing to explore the degree to which rates
22            (and enabling PEV technology) impacts consumer time-of-day charging decisions and
23            behavior.8
24                     One of many challenges associated with PEV growth rates will be with customers who
25            purchase these vehicles and are located in the older coastal areas of SDG&E’s service territory.
26            In most instances these homes are smaller, do not have air conditioning and the number of
27            customers connected per transformer is greater than in the inland valleys. A 3 kW charging

     7
       January 12, 2010 Scoping Memo in R.09-08-009, Commission Rulemaking on alternative-fueled vehicle tariffs,
     infrastructure and policies to support California's greenhouse gas emissions reduction goals.
     8
       http://docs.cpuc.ca.gov/word_pdf/AGENDA_RESOLUTION/119477.pdf Res.E-4334 – The CPUC approved SDG&E’s
     request to establish three new temporary experimental residential rate schedules for plug-in electric vehicle (PEV) charging
     to be used coincident with the EV Project (ECOtality’s deployment of home, commercial and public charging facilities in
     collaboration with Nissan’s deployment of the Leaf PEV in SDG&E’s services territory). This Resolution approves
     implementation of the experimental rate schedules beginning January 1, 2011. The temporary rates will remain in effect
     until November 30, 2012 (or until completion of the related pricing pilot research project.)



     SDGE Doc #249440                                         TOB-13
1              load is comparable to an air conditioner load which now suddenly is placed onto the grid.
 2              SDG&E is currently involved in an Electric Power Research Institute, EPRI, project9 to further
 3              understand the impact of PEVs on the grid. Proactively, SDG&E believes it is imperative to
 4              fund three areas of activities: existing facility upgrades, smart transformers and public charging
 5              infrastructure in order address the coming PEV consumer demand and to reduce potential
 6              market barriers to PEV adoption due to inadequate charging infrastructure.
 7    
         Cumulative and annual PEV sales (2010 to 2020)
 8       BEVs and PHEVs (x 1,000)
 9        300
                             Cumulative B EVs
10
                             Cumulative PHEVs
          250                                                                                                    2 7.5
11                           Annual PEV s ales
                                                                                                                 23 6.6
12
          200                                                                                          2 1.6
13                                                                                                     1 83 .6

14        150                                                                                16 .5
                                                                                             1 40 .1
15                                                                                  12 .01
          100                                                                       10 6.1
16                                                                           8.4
                                                                            7 9.3
17         50
                                                                     5.6
                                                          3 .7      56 .9                                         58.9

18                   0 .2      2.1         2.2     2 .6   38 .6                               38.4
                                                                                                        48.7

                     1 .1      5.2        1 3.1   2 4.1                     25.2
                                                                                     30.5
                                                           15.6
19          0         1.3       6.1        7.9
                                                   11.4              20.2


                  2010        2011      2012      2013    2014      2015    2016    2017     2018      2019      2020
20
21                                        Figure TOB-5 – SDG&E’s Estimate of PEV Sales
22
23              C.          Reliability
24                          As discussed at length in the testimony of Mr. Alan Marcher, Exhibit SDG&E-06,
25              SDG&E has an aging infrastructure and a need to continue to improve its fire preparedness.
26              Seventy-eight percent of SDG&E’s 4 kV substation transformers have been in-service 50 years
27              or more while only thirty seven percent of 12 kV substation transformers have been in-service
28              40 years or more. It is not just transformers but basic equipment such as poles, wire and cable.
29              Putting this in context, these pieces of equipment have to handle not only existing historical
30              loads but now also the intermittent power flows associated with PV systems that have been
31              installed and the PEV loads that are poised to make an appearance at the end of 2010.

     9
         EPRI Project ID No. 065939.



     SDGE Doc #249440                                             TOB-14
1
 2                    As SDG&E works to further reduce the risk of fires and strive to improve its ability to
 3           respond and restore electrical service as quickly as possible, it is leveraging advances in
 4           technology and systems. SDG&E believes that by putting the “smarts” in the grid it should be
 5           possible to maintain and/or improve reliability in the face of these challenges. Therefore,
 6           SDG&E has developed cost forecasts for three Smart Grid projects for incorporation in this
 7           general rate case: wireless faulted circuit indicators, phase identification and an expansion of
 8           condition based maintenance.
 9
10           D.       Smart Grid Development
11                    As the Commission has noted in its recent Smart Grid OIR decision, D.10-06-047,
12           “…that deployment plans should include a discussion of an IOU’s Smart Grid strategy,
13           and that the strategy should offer a sense of direction and guidance, rather than setting rigid
14           requirements. This is clearly a reasonable approach since there are significant uncertainties
15           surrounding future technologies that may be part of a Smart Grid.” 10
16   also
17           “There is a consensus among those parties providing comments that a
18           roadmap can provide useful information concerning technologies and their
19           deployment, even though they will remain subject to change.”11
20
21   and finally
22           “In addition, there is near universal agreement that it is difficult to provide a reliable cost
23           estimate based on future and unknown technologies and infrastructure investments….but the
24           Commission does not find that it would be possible to require detailed, projected cost estimates
25           for technology that is undergoing dramatic changes in costs and technology today, or has yet to
26           be invented.”12
27                    Given that Smart Grid technologies, solutions and standards are rapidly evolving and it
28           is difficult to estimate costs and requirements in the next five years, there is a need, as pointed

     10
         R.08-12-009, Order Instituting Rulemaking to Consider Smart Grid Technologies Pursuant to Federal Legislation and
     on the Commission’s own Motion to Actively Guide Policy in California’s Development of a Smart Grid System, D.10-06-
     047 (Decision Adopting Requirements For Smart Grid Deployment Plans Pursuant To Senate Bill 17 (Padilla), Chapter
     327, Statutes Of 2009)., pg. 47.
     11
        Ibid, pg. 64.
     12
        Ibid, pg. 68.



     SDGE Doc #249440                                     TOB-15
1          out by Mr. Lee Krevat Exhibit SDG&E-10, for SDG&E to test the function of new consumer
 2          focused technologies on the installed smart meters and associated systems to enable two Smart
 3          Grid characteristics. These characteristics are enabling active participation by consumers and
 4          new products, services, and markets. Therefore, SDG&E has developed a cost forecast for an
 5          integrated Smart Grid test facility to address standard, integration and interoperability
 6          challenges for these technologies.
 7

 8          E.     Summary of Request

 9
10                                               Table TOB - 2
11                                         O&M Non-Shared Services
12                                            Testimony Section II
13                                          (Thousands 2009 dollars)
14
     SMART GRID
     Categories of Management                         2009 Adjusted-     TY2012              Change
                                                      Recorded           Estimated
     A. Smart Grid Electric Distribution              330                1,003               673
     Total                                            330                1,003               673
15
16
17
18                                              Table TOB - 3
19                                           Capital Expenditures
20                                          (Thousands 2009 dollars)
21
               SMART GRID
            Category Description              2009          2010           2011      2012
                                            Recorded      Estimated      Estimated Estimated
      1. Smart Grid Portfolio                 $0             $0           $36,568   $57,269
                           Total Capital:        $0            $0         $36,568       $57,269
22
23
24
25
26
27
28



     SDGE Doc #249440                                 TOB-16
1   II.    NONSHARED SERVICES

 2          A.      Introduction

 3                  1.     Smart Grid Team

 4                         This testimony also sponsors the ongoing funding of the cost center for the
 5                  Smart Grid Team. This small group of individuals: a Director, Chief Engineer, Lead
 6                  Architect, Policy Manager, Customer Manager and Administrative Associate; are
 7                  responsible for developing SDG&E’s Smart Grid strategy and policy. The organization
 8                  is responsible for aligning the strategy and policy across SDG&E.

 9
10                                              Table TOB - 4
11                                         O&M Non-Shared Services
12                                         (Thousands of 2009 dollars)
13
     SMART GRID
     A. Smart Grid Electric Distribution             2009 Adjusted-      TY2012             Change
                                                     Recorded            Estimated
     1. Smart Grid Electric Distribution             330                 1,003              673
     Total                                           330                 1,003              673
14
15
16          B.      Discussion of O&M Activities

17                  1.     Smart Grid Team Salaries and Benefits

18                         This funding covers the salaries and incidental O&M expenses of the Smart
19                  Grid Team. This small team was first formed in 2009 as a result of the significant
20                  activities at both the Federal and State level with regards to Smart Grid. It was
21                  recognized that with Federal legislation and the DOE driven activity in this area that a
22                  team was required to specifically focus on this topic; driving SDG&E’s strategy and
23                  vision in this important area. As a consequence, in June 2009, a Director, Chief
24                  Engineer, Lead Architect and an Administrative Associate were brought together to
25                  begin work. In 2010, a Policy Manager and Customer Manager were also brought into
26                  the team completing the staffing goals.
27                         The team spent most of 2009 developing a SDG&E strategy and vision and
28                  subsequently communicating both internally and externally. The Commission’s Smart
29                  Grid Rulemaking was also underway at this time and the team participated in



     SDGE Doc #249440                                TOB-17
1                 workshops and commented on Commission questions. The DOE released its funding
 2                 opportunity notice for Smart Grid and the team spent the summer developing proposal
 3                 for both the investment grant and regional demonstration solicitations.
 4                         In 2010 the work on the Smart Grid OIR continued with a decision being
 5                 released regarding the implementation of SB17. Work has also begun to deliver the
 6                 SDG&E Smart Grid vision and roadmap by the required July 1, 2011 deadline. The
 7                 team directed SDG&E’s effort in the EPRI-led California utilities Smart Grid 2020
 8                 Vision activity in response to the CEC solicitation of the same name. An internal
 9                 stakeholder effort also occurred to align and drive SDG&E’s strategy and policy across
10                 the organization.
11                         Future work activities will include the SB17 mandated yearly updates to
12                 SDG&E’s Smart Grid roadmap, responding to other Commission rulings, other pending
13                 legislation and driving Smart Grid solutions to system problems to name but a few
14                 activities.
15

16   III.   CAPITAL

17          A.     Introduction

18                 This project portfolio incorporates Smart Grid technologies into the electric system
19          infrastructure with a goal of maintaining and/or improving system performance and operational
20          flexibility and reliability. As the penetration levels of renewables and electric vehicles increase
21          relative to the local load on the system, they are expected to impact system operations and
22          reliability and this portfolio will provide implementation of effective measures to mitigate
23          these impacts. Relative to infrastructure expansion, projects that involve building completely
24          new large scale elements of the distribution system such as new substations and new circuits
25          shall be designed with a perspective that strives to incorporate Smart Grid concepts and
26          equipment where applicable.
27                 This project portfolio also integrates with system improvement work being done to
28          further reduce the fire threat in the overhead electric system located in the very high/extreme
29          fire threat zone. As discussed in the testimony of Mr. Alan Marcher, Exhibit SDG&E-06, this
30          system hardening work provides a unique opportunity to incorporate Smart Grid elements to
31          achieve the most overall effective and superior solution. Smart Grid and the fire hardening



     SDGE Doc #249440                                TOB-18
1          projects are particularly synergistic as the projects can be designed with a goal of providing
 2          more operational flexibility, improved reliability and at the same time further reduce fire risk.
3           Smart Grid sensor technology, advanced system monitoring and control features can be
4           integrated into the operation of the system which is especially valuable during storms and
5           extreme fire risk weather events. In addition to maintaining and/or improving reliability, the
 6          circuit hardening work with Smart Grid technologies should facilitate integration of distributed
 7          energy resources such as solar and wind, as well as energy storage for back up of important
 8          community infrastructure such as cell phone networks, communications devices and small
 9          water pumps used to supply drinking water and fill small storage tanks that otherwise may lose
10          power during extreme conditions. This project portfolio should provide the ability to
11          incorporate technologies that can keep more customers and critical infrastructure safely in
12          service during extreme fire risk weather events as well as during storm periods and times when
13          the electric system is stressed due to high operating loads or operational emergencies.
14                 The Smart Grid portfolio is divided into four principal categories. These are Renewable
15          Growth, Electric Vehicle Growth, Reliability and Smart Grid Development. Individual
16          projects comprising the portfolio are grouped into these categories:
17
18   RENEWABLE GROWTH
19    Energy Storage (ES)
20    Dynamic Line Ratings
21    Phasor Measurement Units
22    Capacitor SCADA
23    SCADA Expansion
24   ELECTRIC VEHICLE GROWTH
25    Plug-in Electric Vehicles
26       These costs are incorporated in the testimony of Mr. Alan Marcher, Exhibit SDG&E-06.
27    Smart Transformers
28    Public Access Charging Facilities
29   RELIABILITY
30    Wireless Faulted Circuit Indicators
31    Phase Identification
32      Condition Based Maintenance (CBM) Expansion



     SDGE Doc #249440                                TOB-19
1   SMART GRID DEVELOPMENT
 2      Integrated Test Facility
 3
 4      CAPITAL SUMMARY REQUEST
 5
 6
 7                                              Table TOB - 5
 8                                          Capital Expenditures
 9                                        (Thousands of 2009 dollars)
10
                                             2009          2010           2011      2012
          Category Description             Recorded      Estimated      Estimated Estimated
      1. Smart Grid Portfolio                $0             $0           $36,568   $57,269
                         Total Capital:       $0             $0          $36,568      $57,269
11

12         B.     Capital Request Detail

13                1.     Renewable Growth: Energy Storage (Budget Codes: 10261)

14                       A cost forecast is provided for two types of energy storage systems to assist in
15                addressing intermittency issues created by the variable output of renewable energy
16                resources. One solution will place distributed energy storage systems on circuits with high
17                penetration of customer photovoltaic systems. Additionally, energy storage systems will be
18                strategically located in substations to mitigate the impact of multiple circuits with PV as the
19                second budget item.
20                       Energy storage systems will be used to demonstrate the ability to enhance the value
21                of energy from renewable distributed generation in at least two fundamental ways:
22                minimize the intermittency problem of renewables by installing storage and if appropriate
23                and possible, use storage so that electric energy generated during times of lowest system
24                need can be “time-shifted” and used during time of greatest need to the electric system.
25                       As the penetration of distributed energy resources, DER, continues to increase, the
26                need for distributed storage will also increase in order to mitigate intermittency problems at
27                the local 12 kV feeder level. This project will install energy storage in two forms: 1)
28                distributed storage in the form of community energy storage, CES, devices in those circuits
29                where the penetration of PV is 20% or more of the circuit load at times of high photovoltaic




     SDGE Doc #249440                              TOB-20
1                 system output and low circuit loads and 2) substation energy storage of utility scale, size
 2                 anticipated to be 1 MW or greater, which will be installed to mitigate the effects of utility
 3                 scale (up to 2 MW) PV projects that will be installed in various locations.
 4                        Energy Storage, installed in conjunction with the appropriate sensors, control and
 5                 communication systems should provide a solution for the mitigation of intermittency via the
 6                 management and discharge of stored energy in a controlled and coordinated way.
 7                        Based on the historical and forecasted penetration of distributed PV in the SDG&E
 8                 service territory, CES devices, which are small, 50 kW batteries will be installed on 11
 9                 circuits in 2011, and on 14 more circuits in 2012. In addition to the CES devices, substation
10                 energy storage amounting to 4 MW will be installed in 2011 and another 4 MW will be
11                 installed in 2012.
12

13                                         Table TOB - 6
14                      Renewable Growth, Energy Storage Capital Expenditures
15                                   (Thousands of 2009 dollars)
16
        Description      2009 Adjusted           2010                2011           TY2012
                           Recorded            Estimated          Estimated        Estimated
      Category 1              $0                  $0               $25,193          $29,790
17

18                 2.     Renewable Growth: Dynamic Line Ratings (Budget Codes: 10261)

19                        A cost forecast is provided for implementation of dynamic ratings for distribution
20                 circuits. The implementation of dynamic line ratings has the potential for increasing circuit
21                 capacity and accommodating new renewable generation.
22                        Dynamic ratings of equipment provide an opportunity to optimize capital
23                 investments and operate the grid at higher efficiencies. Dynamic line ratings compare the
24                 weather-adjusted, thermal rating of a conductor against the static design rating. The pre-
25                 calculated static value for the thermal rating of a conductor is developed to protect the
26                 conductor from damage due to annealing and from excessive sag during extreme heat.
27                        This project will install dynamic line rating technologies on ten distribution circuits
28                 per year. Installations will be made on the most critical distribution circuits which include
29                 those circuits with significant renewables penetration and energy storage. Sensors on
30                 overhead distribution lines will be used to monitor the line conductor tension and determine



     SDGE Doc #249440                               TOB-21
1                 ground clearances and weather conditions to calculate the amount of current that can be
 2                 transmitted in real time. This information is then provided to system operators or engineers
 3                 for their use in safe, reliable and economic system operation. By monitoring wind speed,
 4                 conductor tension and solar heating, a real-time line rating that is indicative of current
 5                 conductor capability can be calculated. An advanced human interface will also be
 6                 developed to assist system operators with managing the information.
 7                        SDG&E has 995 distribution circuits, and high loading is anticipated on 1% of
 8                 circuits that will warrant close monitoring and dynamic line rating. Installing dynamic line
 9                 rating technology on 10 distribution circuits per year will result in the following cash flow.
10
11                                          Table TOB - 7
12                    Renewable Growth, Dynamic Line Ratings Capital Expenditures
13                                    (Thousands of 2009 dollars)
14
        Description      2009 Adjusted           2010               2011            TY2012
                           Recorded            Estimated          Estimated        Estimated
      Category 1              $0                  $0               $1,963           $1,963
15

16                        3.      Renewable Growth: Phasor Measurement Units (PMU) -
17                                Synchrophasors (Budget Codes: 10261)

18                        A cost forecast is provided for implementation of phasor measurement units on the
19                 electric distribution system. Installation of phasor measurement units on the electric
20                 distribution system are expected improve reliability by employing high speed, time
21                 synchronized measurement devices. These devices will be utilized in conjunction with
22                 energy storage devices to create a closed loop control system to mitigate the impact of
23                 intermittent renewables. Phasor measurement technologies are a leading example of a new
24                 generation of advanced grid monitoring technologies that rely on high speed, time-
25                 synchronized, digital measurements.
26                        Phasor measurement technologies will help mitigate the intermittency issues
27                 associated with distributed renewables by employing high-speed, time-synchronized
28                 measurement devices installed in substations and at key points on the distribution system.
29                 Using time stamped, digitized waveform measurements, SDG&E can analyze the output of




     SDGE Doc #249440                               TOB-22
1                 PV systems, indentify changes in PV output and enable the dispatch of energy storage
 2                 devices to counteract the effects of the PV output fluctuation.
 3                        Phasor measurement technologies are also needed for understanding potential
 4                 problems with the grid and are therefore a key component of a stable, self-healing grid. As
 5                 the penetration of renewables increases, there will be increased voltage and phase-angle
 6                 fluctuations at various points on the system. PMU data can equip system operators with
 7                 better real-time information about actual operating margins so that they can better
 8                 understand and manage the risk of operating closer to the operating limits. Specifically,
 9                 some of the functionality enabled by PMU technologies include:

10                        •       monitoring and visualization for improved control room operations
11                        •       wide-area control and protection
12                        •       power system restoration
13                        •       time-synchronized, waveform measurements.
14
15                        This project calls for the installation of PMU equipment on 11 distribution circuits
16                 with a high penetration of PV: 4 circuits in 2011 and seven circuits in 2012. The equipment
17                 will be installed at points on the circuit where there is significant aggregation of PV
18                 systems. Additionally, a Phasor Data Collector (PDC) will be installed at each substation.
19                 An assessment tool will be developed to provide the ability to record, archive, analyze and
20                 display phasor data. The interconnection and link of PMUs into a network will bring time-
21                 synchronized data to a central location to create a wide-area view of the grid.
22

23                                         Table TOB - 8
24                 Renewable Growth, Phasor Measurement Units Capital Expenditures
25                                    (Thousands of 2009 dollars)
26
        Description      2009 Adjusted           2010               2011              TY2012
                           Recorded            Estimated          Estimated          Estimated
      Category 1              $0                  $0               $1,475             $2,581
27

28

29




     SDGE Doc #249440                               TOB-23
1                       4.      Renewable Growth: Capacitor SCADA (Budget Codes: 10261)

 2                       A cost forecast is provided to implement SCADA control of all capacitors on
 3                SDG&E’s distribution system and is distinct from the SCADA expansion for switches
 4                discussed below. Benefits of SCADA for capacitors should include: better voltage and VAr
 5                control, reduced maintenance, and better system diagnostics. When coupled with energy
 6                storage, dynamic line ratings and phasor measurements new control schemes can be
 7                implemented which will mitigate the impact of PV system output fluctuations on system
 8                voltage.
 9                       SDG&E has been using SCADA (Supervisory Control and Data Acquisition)
10                controlled devices in various types of equipment for many years. SCADA controlled
11                capacitor banks will provide local and remote control, failure prediction and detection,
12                reduced operating cost, and should enhance distribution system performance through
13                improved voltage and reactive power control. As certain elements of Smart Grid evolve,
14                including less predictable DER, the ability to dynamically adjust reactive power flow will
15                become more critical. Presently, SDG&E discovers capacitor issues during the annual
16                capacitor survey or through customer voltage problems. SCADA controlled capacitors will
17                provide SDG&E the ability to be proactive in capacitor maintenance, instead of reactive.
18                Furthermore, SCADA control will provide a faster and more economical way to update the
19                software and to adjust control settings.
20                       Installing SCADA on capacitor controllers will yield the following capabilities:

21                       SCADA controls offer the ability to over-ride automatic controls of the bank to
22                adjust voltage or reactive support to the distribution system. Reprogramming capability may
23                reduce the need for future field visits by line personnel.

24                       •       SCADA controls can alert utility personnel of capacitor failures and/or
25                               fuse operations. This will increase capacitor bank reliability, minimize
26                               downtime, and expedite repair work.
27                       •       SCADA controls may be used to help facilitate the annual Capacitor
28                               Survey for those sites that are on SCADA.
29                       •       SCADA provides for remote monitoring of the status of the control
30                               devices for the bank.




     SDGE Doc #249440                              TOB-24
1                        •       SCADA controls provide monitoring of all power system parameters
 2                                (i.e. voltage, current, reactive power, real power, power factor, etc…)
 3                                associated with the capacitor bank. This provides a key diagnostic tool
 4                                when power quality concerns arise. This is becoming more critical, as
 5                                the digital economy demands a higher level of power quality.
 6
 7                        •       Improved voltage and reactive power control to mitigate the impact of
 8                                distributed PV.
 9
10                        At this time there are 1,404 capacitors in the SDG&E service territory, 959 are
11                 overhead capacitors and 445 are underground capacitors. The cash flow below reflects
12                 adding SCADA to all these capacitors over a seven year period with the majority of work
13                 taking place over the 2011-2016 period.
14
15                                          Table TOB - 9
16                      Renewable Growth, Capacitor SCADA Capital Expenditures
17                                    (Thousands of 2009 dollars)
18
        Description      2009 Adjusted           2010               2011            TY2012
                           Recorded            Estimated          Estimated        Estimated
      Category 1              $0                  $0               $2,902           $2,902
19

20                        5.      Renewable Growth: SCADA Expansion (Budget Codes: 10261)

21                        A cost forecast is provided for expansion of SCADA to expand remote operability
22                 and automated operation of distribution SCADA capable switches. This will continue
23                 SDG&E’s goal of providing faster isolation of faulted electric distribution circuits and
24                 branches, resulting in faster load restoration and isolation of system disturbances.
25                        This project provides funding for the installation, upgrades, and expansion of the
26                 Supervisory Control and Data Acquisition (SCADA) system at substations and on
27                 distribution circuits through the addition of automated switches. SDG&E’s radial, open-
28                 loop distribution circuit design philosophy incorporates 1.5 SCADA switches per circuit:
29                 one at the midpoint, and one at a strong tie. This design philosophy improves system
30                 reliability while avoiding a full network design.



     SDGE Doc #249440                               TOB-25
1                         As the penetration of distributed renewables increases on the distribution system,
 2                 this SCADA expansion will allow SDG&E to re-configure circuits. By automatically re-
 3                 configuring circuit the amount of PV and load can be balanced to better accommodate areas
 4                 of high PV penetration.
 5                         This will be incremental to work being done on existing budgets. In addition, to
 6                 fully realize the functionality of the line SCADA, the associated feeding substation needs to
 7                 be on SCADA as well. The scope of work required to achieve the capabilities above will
 8                 require installation of SCADA at 13 substations serving 76 circuits, and 281 SCADA
 9                 switches on circuits that lack SCADA line or SCADA tie switches. The cash flow below
10                 reflects this scope of work being implemented over a five year period from 2012-2016.
11                 Expenditures are expected to begin in 2012 as shown below.
12

13                                          Table TOB - 10
14                      Renewable Growth, SCADA Expansion Capital Expenditures
15                                    (Thousands of 2009 dollars)
16
        Description      2009 Adjusted           2010               2011            TY2012
                           Recorded            Estimated          Estimated        Estimated
      Category 1              $0                  $0                  $0            $5,964
17

18                 6.      Electric Vehicle Growth: Plug-In Electric Vehicles

19                         This is project is required to upgrade primary and secondary voltage infrastructure to
20                 accommodate the rollout of electric vehicles in San Diego County in the 2010, 2011 and
21                 2012 timeframe. Transformers, secondary and primary conductors associated with
22                 customers who participate in the Nissan Leaf and Chevrolet Volt rollout will be evaluated
23                 for adequate capacity. If upgrades are required, they will be covered as part of this project.
24                 These costs are incorporated in the testimony of Mr. Alan Marcher, Exhibit SDG&E-06.
25                         Large numbers of PEV’s (both battery electric vehicles and plug-in hybrid electric
26                 vehicles) are estimated to interconnect to the SDG&E grid over the next 10 years, requiring
27                 improvements to the electric distribution system. This may also create opportunities in the
28                 future to use PEVs as distributed energy resources by discharging their batteries into the
29                 grid during times of system resource needs or economic benefit. The upgrade of services
30                 and transformers resulting from residential PEV impacts to the grid occurring over the next



     SDGE Doc #249440                               TOB-26
1                3 years (2010-2012) are included in associated capital projects of Mr. Alan Marcher as
 2                mentioned earlier. Therefore the costs being included on this Smart Grid capital project
 3                associated with impacts due to PEVs, in post test years, will cover distribution feeder
 4                upgrades and infrastructure for larger public charging stations. The cost estimates for this
 5                timeframe are based on a projection of 8300 residential charging stations and 328 public
 6                charging stations
 7

 8                7.     Electric Vehicle Growth: Smart Transformers (Budget Codes: 10261)

 9                       A cost forecast is provided for the installation of sensors and technology on
10                distribution transformers so that they can monitor and report loading, and the state of the
11                transformers. This project has the potential to allow increased transformer capacity
12                utilization and accommodate future loads such as plug-in electric vehicles.
13                       Distribution line transformers can be converted into smart devices by installing
14                monitoring equipment on the secondary bushings. These monitors will provide information
15                to engineers and operators about the state of the grid including distributed resources and
16                loads at the location of the transformers. This data will be especially valuable for
17                monitoring the load and condition of transformers feeding plug-in electric vehicles. It will
18                also provide information about the state and condition of the transformer. Transformer
19                monitors will facilitate dynamic ratings for the transformers, the ability to verify energy
20                consumed or generated by new distributed resources or loads for potential management
21                applications, and the ability to assess detailed transformer conditions in order to proactively
22                troubleshoot customer or secondary voltage problems.
23                       This project will install transformer monitoring devices on all transformers serving
24                customers with plug-in electric vehicles. Sensing devices attached to transformers will be
25                used to monitor real-time loading and establish accurate load profiles. This information will
26                be available to system operators to alert them to possible overloads, imbalances, voltage
27                excursions or other operational issues. Additionally, engineers will use this information to
28                revise transformer loading guidelines which may lead to optimizing the number of
29                customers that may be served from an individual transformer and reducing transformer
30                loading problems.




     SDGE Doc #249440                              TOB-27
1                          One transformer monitoring device will be installed on each distribution transformer
 2                 that serves a customer with a PEV and associated charge stations. The number of PEV
 3                 charge stations is anticipated to be:
 4
 5                                                Table TOB - 11
 6                                             PEV Charging Stations
 7
     Year:                              2010            2011              2012              Total
     PEV Charge Stations:               600             2150              700               3450
 8
 9                          This estimated number of charge stations is based on the expected sales of battery
10                 electric vehicle and plug-in hybrid electric vehicle sales in the San Diego area. This
11                 estimate is based upon a DOE sponsored program with partnership by ECOtality and Nissan
12                 to deploy up to 5,000 electric vehicles and charging infrastructure in San Diego and four
13                 other U.S. cities.
14

15                                           Table TOB - 12
16                 Electric Vehicle Growth, Smart Transformers Capital Expenditures
17                                     (Thousands of 2009 dollars)
18
        Description      2009 Adjusted             2010              2011            TY2012
                           Recorded              Estimated         Estimated        Estimated
      Category 1              $0                    $0              $2,047            $521
19
20                          8.     Electric Vehicle Growth: Public Access Charging Facilities (Budget
21                                 Codes: 10261)

22                          A cost forecast is provided for the installation of utility-owned, public access
23                 charging facilities for electric vehicles. SDG&E will install and own the charging facilities
24                 in under-served areas in order to broaden the coverage of public charging opportunities
25                 within its service territory. This effort will allow SDG&E to continue the momentum of the
26                 stakeholder charging facility siting and installation process established by ECOtality as part
27                 of their government funded EV Project between 2010 and mid-2011. As planned, this
28                 project will increase the number of charging facility services offered by 3rd parties,
29                 specifically to provide PEV charging facilities in locations that are not necessarily



     SDGE Doc #249440                                TOB-28
1                     commercially or economically desirable, but needed to serve the broader and growing PEV
 2                     charging needs of the public.
 3
 4   Charging Facility Site Selection
 5             SDG&E will work with the CPUC to develop broad criteria for evaluating the installation of
 6   “public access charging facilities” with the objective to ensure a network of public charging facilities
 7   is developed in the public interest over time that would provide sufficient support for the adoption and
 8   use of PEVs.
 9             As part of the selection process, SDG&E will use an independent entity to assist in the
10   development of site evaluation criteria to be used in a regional stakeholder charging facility site
11   selection process. The process will be led by an independent coordinating entity, such as the San
12   Diego Association of Governments, SANDAG. SDG&E will adapt the process that has been
13   successfully implemented in the deployment of charging facilities by ECOtality, under an ARRA,
14   DOE grant.13 Once ECOtality completes the charging facility installation portion of their EV Project
15   by mid-2011, SDG&E will continue to play a role in working with stakeholders to help determine the
16   location of the charging facilities that will have the least cost, least impact to the electric distribution
17   system. SDG&E will implement this service as part of a long-term process to extend the deployment
18   of public charging facilities as the growth of PEVs continues.
19             To support the development of electric vehicles and to engender the broad public benefits this
20   yields (lower GHG and other harmful emissions, improve local air quality, less reliance on foreign
21   oil), SDG&E will play an important role during the formative years of market development to ensure
22   that electric charging infrastructure develops which can support the rapid adoption of plug-in electric
23   vehicles. Also, because of their limited range, in order to foster market acceptance of these vehicles, a
24   seamless network of charging facilities will be needed. In order to ensure that this network of
25   charging infrastructure does not have significant voids, SDG&E proposes these "public interest"
26   charging facilities.
27             As a result of the development of a more robust availability of charging facilities, this effort
28   will also help to stimulate market growth for PEV related services and equipment in general, and
29   specifically in under-served areas. Although SDG&E will own these charging facilities, it will also
30   contract with 3rd parties to build, operate and maintain the charging facilities. This approach will help


     13
          http://www.ecotalityna.com/pdf/100109_eTec_DOE_Contract.pdf



     SDGE Doc #249440                                     TOB-29
SDG&E Smart Grid Capital Projects
SDG&E Smart Grid Capital Projects
SDG&E Smart Grid Capital Projects
SDG&E Smart Grid Capital Projects
SDG&E Smart Grid Capital Projects
SDG&E Smart Grid Capital Projects
SDG&E Smart Grid Capital Projects
SDG&E Smart Grid Capital Projects

Contenu connexe

Tendances

Smart grid technologies across the globe
Smart grid technologies across the globeSmart grid technologies across the globe
Smart grid technologies across the globeSchneider Electric
 
[Case study] Dakota Electric Association: Solutions to streamline GIS, design...
[Case study] Dakota Electric Association: Solutions to streamline GIS, design...[Case study] Dakota Electric Association: Solutions to streamline GIS, design...
[Case study] Dakota Electric Association: Solutions to streamline GIS, design...Schneider Electric
 
Schneider Electric Smart Cities
Schneider Electric Smart CitiesSchneider Electric Smart Cities
Schneider Electric Smart CitiesSchneider Electric
 
Can automation manufacturers and system integrators be true partners?
Can automation manufacturers and system integrators be true partners?Can automation manufacturers and system integrators be true partners?
Can automation manufacturers and system integrators be true partners?Schneider Electric
 
Value of Distributed Energy Resources (VDER) Presentation
Value of Distributed Energy Resources (VDER) PresentationValue of Distributed Energy Resources (VDER) Presentation
Value of Distributed Energy Resources (VDER) PresentationDavid Katz
 
Hannover High End Utility Metering
Hannover High End Utility MeteringHannover High End Utility Metering
Hannover High End Utility MeteringSchneider Electric
 
New Approach for Intelligent Motor Control Centers
New Approach for Intelligent Motor Control CentersNew Approach for Intelligent Motor Control Centers
New Approach for Intelligent Motor Control CentersSchneider Electric
 
[Case study] Jacksonville Electric Authority: Implementing a complete enterpr...
[Case study] Jacksonville Electric Authority: Implementing a complete enterpr...[Case study] Jacksonville Electric Authority: Implementing a complete enterpr...
[Case study] Jacksonville Electric Authority: Implementing a complete enterpr...Schneider Electric
 
Implementing energy efficient data centers
Implementing energy efficient  data centersImplementing energy efficient  data centers
Implementing energy efficient data centersSchneider Electric India
 
What is DERMS ? Distributed Energy Resources Management System
What is DERMS ? Distributed  Energy  Resources  Management SystemWhat is DERMS ? Distributed  Energy  Resources  Management System
What is DERMS ? Distributed Energy Resources Management SystemPower System Operation
 
Study of distributed energy resources
Study of distributed energy resourcesStudy of distributed energy resources
Study of distributed energy resourcesvivatechijri
 
The Intelligent and Connected Data Center
The Intelligent and Connected Data CenterThe Intelligent and Connected Data Center
The Intelligent and Connected Data CenterSchneider Electric
 
Underground Self-Healing Solution
Underground Self-Healing Solution Underground Self-Healing Solution
Underground Self-Healing Solution Schneider Electric
 
[Case study] Maine Fiber: Smart Grid solution offers precise GIS capabilities...
[Case study] Maine Fiber: Smart Grid solution offers precise GIS capabilities...[Case study] Maine Fiber: Smart Grid solution offers precise GIS capabilities...
[Case study] Maine Fiber: Smart Grid solution offers precise GIS capabilities...Schneider Electric
 
Power Distribution
Power Distribution Power Distribution
Power Distribution UGL Limited
 
Print statcom operation on wind
Print statcom operation on windPrint statcom operation on wind
Print statcom operation on windOmkar Koduri
 
Eco-mode: Benefits and Risks of Energy-saving Modes of UPS Operation
Eco-mode: Benefits and Risks of Energy-saving Modes of UPS OperationEco-mode: Benefits and Risks of Energy-saving Modes of UPS Operation
Eco-mode: Benefits and Risks of Energy-saving Modes of UPS OperationSchneider Electric India
 
Four practical steps for reducing overall energy costs
Four practical steps for reducing overall energy costsFour practical steps for reducing overall energy costs
Four practical steps for reducing overall energy costsSchneider Electric India
 
Advantages of a modern DCS in coal handling
Advantages of a modern DCS in coal handlingAdvantages of a modern DCS in coal handling
Advantages of a modern DCS in coal handlingSchneider Electric
 
[Case study] Benton Public Utility District: Reducing labor costs while impro...
[Case study] Benton Public Utility District: Reducing labor costs while impro...[Case study] Benton Public Utility District: Reducing labor costs while impro...
[Case study] Benton Public Utility District: Reducing labor costs while impro...Schneider Electric
 

Tendances (20)

Smart grid technologies across the globe
Smart grid technologies across the globeSmart grid technologies across the globe
Smart grid technologies across the globe
 
[Case study] Dakota Electric Association: Solutions to streamline GIS, design...
[Case study] Dakota Electric Association: Solutions to streamline GIS, design...[Case study] Dakota Electric Association: Solutions to streamline GIS, design...
[Case study] Dakota Electric Association: Solutions to streamline GIS, design...
 
Schneider Electric Smart Cities
Schneider Electric Smart CitiesSchneider Electric Smart Cities
Schneider Electric Smart Cities
 
Can automation manufacturers and system integrators be true partners?
Can automation manufacturers and system integrators be true partners?Can automation manufacturers and system integrators be true partners?
Can automation manufacturers and system integrators be true partners?
 
Value of Distributed Energy Resources (VDER) Presentation
Value of Distributed Energy Resources (VDER) PresentationValue of Distributed Energy Resources (VDER) Presentation
Value of Distributed Energy Resources (VDER) Presentation
 
Hannover High End Utility Metering
Hannover High End Utility MeteringHannover High End Utility Metering
Hannover High End Utility Metering
 
New Approach for Intelligent Motor Control Centers
New Approach for Intelligent Motor Control CentersNew Approach for Intelligent Motor Control Centers
New Approach for Intelligent Motor Control Centers
 
[Case study] Jacksonville Electric Authority: Implementing a complete enterpr...
[Case study] Jacksonville Electric Authority: Implementing a complete enterpr...[Case study] Jacksonville Electric Authority: Implementing a complete enterpr...
[Case study] Jacksonville Electric Authority: Implementing a complete enterpr...
 
Implementing energy efficient data centers
Implementing energy efficient  data centersImplementing energy efficient  data centers
Implementing energy efficient data centers
 
What is DERMS ? Distributed Energy Resources Management System
What is DERMS ? Distributed  Energy  Resources  Management SystemWhat is DERMS ? Distributed  Energy  Resources  Management System
What is DERMS ? Distributed Energy Resources Management System
 
Study of distributed energy resources
Study of distributed energy resourcesStudy of distributed energy resources
Study of distributed energy resources
 
The Intelligent and Connected Data Center
The Intelligent and Connected Data CenterThe Intelligent and Connected Data Center
The Intelligent and Connected Data Center
 
Underground Self-Healing Solution
Underground Self-Healing Solution Underground Self-Healing Solution
Underground Self-Healing Solution
 
[Case study] Maine Fiber: Smart Grid solution offers precise GIS capabilities...
[Case study] Maine Fiber: Smart Grid solution offers precise GIS capabilities...[Case study] Maine Fiber: Smart Grid solution offers precise GIS capabilities...
[Case study] Maine Fiber: Smart Grid solution offers precise GIS capabilities...
 
Power Distribution
Power Distribution Power Distribution
Power Distribution
 
Print statcom operation on wind
Print statcom operation on windPrint statcom operation on wind
Print statcom operation on wind
 
Eco-mode: Benefits and Risks of Energy-saving Modes of UPS Operation
Eco-mode: Benefits and Risks of Energy-saving Modes of UPS OperationEco-mode: Benefits and Risks of Energy-saving Modes of UPS Operation
Eco-mode: Benefits and Risks of Energy-saving Modes of UPS Operation
 
Four practical steps for reducing overall energy costs
Four practical steps for reducing overall energy costsFour practical steps for reducing overall energy costs
Four practical steps for reducing overall energy costs
 
Advantages of a modern DCS in coal handling
Advantages of a modern DCS in coal handlingAdvantages of a modern DCS in coal handling
Advantages of a modern DCS in coal handling
 
[Case study] Benton Public Utility District: Reducing labor costs while impro...
[Case study] Benton Public Utility District: Reducing labor costs while impro...[Case study] Benton Public Utility District: Reducing labor costs while impro...
[Case study] Benton Public Utility District: Reducing labor costs while impro...
 

Similaire à SDG&E Smart Grid Capital Projects

Gsm Based Energy Meter Monitoring and Load Control
Gsm Based Energy Meter Monitoring and Load ControlGsm Based Energy Meter Monitoring and Load Control
Gsm Based Energy Meter Monitoring and Load ControlIRJET Journal
 
Demand Side management of smart grid using IoT
Demand Side management of smart grid using IoTDemand Side management of smart grid using IoT
Demand Side management of smart grid using IoTIRJET Journal
 
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...IRJET Journal
 
Case Study - NCC Sportsground 2
Case Study - NCC Sportsground 2Case Study - NCC Sportsground 2
Case Study - NCC Sportsground 2Andrew Mears
 
A Survey on Impact Assessment of D-FACTS Controllers with Electric Vehicles i...
A Survey on Impact Assessment of D-FACTS Controllers with Electric Vehicles i...A Survey on Impact Assessment of D-FACTS Controllers with Electric Vehicles i...
A Survey on Impact Assessment of D-FACTS Controllers with Electric Vehicles i...IRJET Journal
 
Agent based Load Management for Microgrid
Agent based Load Management for MicrogridAgent based Load Management for Microgrid
Agent based Load Management for MicrogridMohamed Abbas
 
IRJET- Optimization of Renewable Energy Sources for DC Microgrid
IRJET-  	  Optimization of Renewable Energy Sources for DC MicrogridIRJET-  	  Optimization of Renewable Energy Sources for DC Microgrid
IRJET- Optimization of Renewable Energy Sources for DC MicrogridIRJET Journal
 
1MWH SOLAR PLANT CONNECTED TO MICROGRID WITH BESS CONTROLLER
1MWH SOLAR PLANT CONNECTED TO MICROGRID WITH BESS CONTROLLER1MWH SOLAR PLANT CONNECTED TO MICROGRID WITH BESS CONTROLLER
1MWH SOLAR PLANT CONNECTED TO MICROGRID WITH BESS CONTROLLERIRJET Journal
 
Renewable Energy Integration in Smart Grids: A Review of Recent Solutions to ...
Renewable Energy Integration in Smart Grids: A Review of Recent Solutions to ...Renewable Energy Integration in Smart Grids: A Review of Recent Solutions to ...
Renewable Energy Integration in Smart Grids: A Review of Recent Solutions to ...IRJET Journal
 
Implementation of modular MPPT algorithm for energy harvesting embedded and I...
Implementation of modular MPPT algorithm for energy harvesting embedded and I...Implementation of modular MPPT algorithm for energy harvesting embedded and I...
Implementation of modular MPPT algorithm for energy harvesting embedded and I...IJECEIAES
 
IRJET- Hybrid Renewable Energy Based Micro Grid
IRJET- Hybrid Renewable Energy Based Micro GridIRJET- Hybrid Renewable Energy Based Micro Grid
IRJET- Hybrid Renewable Energy Based Micro GridIRJET Journal
 
Certsmicrogridwhitepaper
CertsmicrogridwhitepaperCertsmicrogridwhitepaper
CertsmicrogridwhitepaperĐại Lê
 
IRJET- Simulation Analysis of Power Control using Droop Control Method in Ac-...
IRJET- Simulation Analysis of Power Control using Droop Control Method in Ac-...IRJET- Simulation Analysis of Power Control using Droop Control Method in Ac-...
IRJET- Simulation Analysis of Power Control using Droop Control Method in Ac-...IRJET Journal
 
Show and Tell - Renewable Energy integration and Circular Economy.pdf
Show and Tell - Renewable Energy integration and Circular Economy.pdfShow and Tell - Renewable Energy integration and Circular Economy.pdf
Show and Tell - Renewable Energy integration and Circular Economy.pdfSIFOfgem
 
So Cal Edison Smart Grid Strategyand Roadmap
So Cal Edison Smart Grid Strategyand RoadmapSo Cal Edison Smart Grid Strategyand Roadmap
So Cal Edison Smart Grid Strategyand Roadmapbrucetotty
 
Renewable Energy Driven Optimized Microgrid System: A Case Study with Hybrid ...
Renewable Energy Driven Optimized Microgrid System: A Case Study with Hybrid ...Renewable Energy Driven Optimized Microgrid System: A Case Study with Hybrid ...
Renewable Energy Driven Optimized Microgrid System: A Case Study with Hybrid ...IRJET Journal
 

Similaire à SDG&E Smart Grid Capital Projects (20)

Gsm Based Energy Meter Monitoring and Load Control
Gsm Based Energy Meter Monitoring and Load ControlGsm Based Energy Meter Monitoring and Load Control
Gsm Based Energy Meter Monitoring and Load Control
 
project report
project reportproject report
project report
 
Demand Side management of smart grid using IoT
Demand Side management of smart grid using IoTDemand Side management of smart grid using IoT
Demand Side management of smart grid using IoT
 
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
 
Staggering in Power System
Staggering in Power System Staggering in Power System
Staggering in Power System
 
Case Study - NCC Sportsground 2
Case Study - NCC Sportsground 2Case Study - NCC Sportsground 2
Case Study - NCC Sportsground 2
 
A Survey on Impact Assessment of D-FACTS Controllers with Electric Vehicles i...
A Survey on Impact Assessment of D-FACTS Controllers with Electric Vehicles i...A Survey on Impact Assessment of D-FACTS Controllers with Electric Vehicles i...
A Survey on Impact Assessment of D-FACTS Controllers with Electric Vehicles i...
 
Agent based Load Management for Microgrid
Agent based Load Management for MicrogridAgent based Load Management for Microgrid
Agent based Load Management for Microgrid
 
IRJET- Optimization of Renewable Energy Sources for DC Microgrid
IRJET-  	  Optimization of Renewable Energy Sources for DC MicrogridIRJET-  	  Optimization of Renewable Energy Sources for DC Microgrid
IRJET- Optimization of Renewable Energy Sources for DC Microgrid
 
1MWH SOLAR PLANT CONNECTED TO MICROGRID WITH BESS CONTROLLER
1MWH SOLAR PLANT CONNECTED TO MICROGRID WITH BESS CONTROLLER1MWH SOLAR PLANT CONNECTED TO MICROGRID WITH BESS CONTROLLER
1MWH SOLAR PLANT CONNECTED TO MICROGRID WITH BESS CONTROLLER
 
Cired2011 0405 final
Cired2011 0405 finalCired2011 0405 final
Cired2011 0405 final
 
Renewable Energy Integration in Smart Grids: A Review of Recent Solutions to ...
Renewable Energy Integration in Smart Grids: A Review of Recent Solutions to ...Renewable Energy Integration in Smart Grids: A Review of Recent Solutions to ...
Renewable Energy Integration in Smart Grids: A Review of Recent Solutions to ...
 
Implementation of modular MPPT algorithm for energy harvesting embedded and I...
Implementation of modular MPPT algorithm for energy harvesting embedded and I...Implementation of modular MPPT algorithm for energy harvesting embedded and I...
Implementation of modular MPPT algorithm for energy harvesting embedded and I...
 
IRJET- Hybrid Renewable Energy Based Micro Grid
IRJET- Hybrid Renewable Energy Based Micro GridIRJET- Hybrid Renewable Energy Based Micro Grid
IRJET- Hybrid Renewable Energy Based Micro Grid
 
Certsmicrogridwhitepaper
CertsmicrogridwhitepaperCertsmicrogridwhitepaper
Certsmicrogridwhitepaper
 
IRJET- Simulation Analysis of Power Control using Droop Control Method in Ac-...
IRJET- Simulation Analysis of Power Control using Droop Control Method in Ac-...IRJET- Simulation Analysis of Power Control using Droop Control Method in Ac-...
IRJET- Simulation Analysis of Power Control using Droop Control Method in Ac-...
 
Thesis Body
Thesis BodyThesis Body
Thesis Body
 
Show and Tell - Renewable Energy integration and Circular Economy.pdf
Show and Tell - Renewable Energy integration and Circular Economy.pdfShow and Tell - Renewable Energy integration and Circular Economy.pdf
Show and Tell - Renewable Energy integration and Circular Economy.pdf
 
So Cal Edison Smart Grid Strategyand Roadmap
So Cal Edison Smart Grid Strategyand RoadmapSo Cal Edison Smart Grid Strategyand Roadmap
So Cal Edison Smart Grid Strategyand Roadmap
 
Renewable Energy Driven Optimized Microgrid System: A Case Study with Hybrid ...
Renewable Energy Driven Optimized Microgrid System: A Case Study with Hybrid ...Renewable Energy Driven Optimized Microgrid System: A Case Study with Hybrid ...
Renewable Energy Driven Optimized Microgrid System: A Case Study with Hybrid ...
 

Plus de UCSD-Strategic-Energy

Pev consumer behavior study plug in 2012 haddow v3 panel
Pev consumer behavior study plug in 2012 haddow v3 panelPev consumer behavior study plug in 2012 haddow v3 panel
Pev consumer behavior study plug in 2012 haddow v3 panelUCSD-Strategic-Energy
 
CEC pub on calculating additional needs to meet 33% RPS
CEC pub on calculating additional needs to meet 33% RPSCEC pub on calculating additional needs to meet 33% RPS
CEC pub on calculating additional needs to meet 33% RPSUCSD-Strategic-Energy
 
Cpuc changes to adv energy storage incentives sep 2011
Cpuc changes to adv energy storage incentives sep 2011Cpuc changes to adv energy storage incentives sep 2011
Cpuc changes to adv energy storage incentives sep 2011UCSD-Strategic-Energy
 
ORNL econ analysis of repurposed EV batteries for Stationary Applications
ORNL econ analysis of repurposed EV batteries for Stationary ApplicationsORNL econ analysis of repurposed EV batteries for Stationary Applications
ORNL econ analysis of repurposed EV batteries for Stationary ApplicationsUCSD-Strategic-Energy
 
Doe microgrid workshop aug 30 31 2011 presentations
Doe microgrid workshop aug 30 31 2011 presentationsDoe microgrid workshop aug 30 31 2011 presentations
Doe microgrid workshop aug 30 31 2011 presentationsUCSD-Strategic-Energy
 
UH-Maui College Wins DOE Grant for Renewable Energy Charging of Rental Electr...
UH-Maui College Wins DOE Grant for Renewable Energy Charging of Rental Electr...UH-Maui College Wins DOE Grant for Renewable Energy Charging of Rental Electr...
UH-Maui College Wins DOE Grant for Renewable Energy Charging of Rental Electr...UCSD-Strategic-Energy
 
CPUC Ruling on Removing EV Deployment Barriers 139101
CPUC Ruling on Removing EV Deployment Barriers 139101CPUC Ruling on Removing EV Deployment Barriers 139101
CPUC Ruling on Removing EV Deployment Barriers 139101UCSD-Strategic-Energy
 
San Diego Regional Support for Tailpipe Endgame project with AB 118 Investmen...
San Diego Regional Support for Tailpipe Endgame project with AB 118 Investmen...San Diego Regional Support for Tailpipe Endgame project with AB 118 Investmen...
San Diego Regional Support for Tailpipe Endgame project with AB 118 Investmen...UCSD-Strategic-Energy
 
Valuation of Energy Storage White Paper by SCE
Valuation of Energy Storage White Paper by SCEValuation of Energy Storage White Paper by SCE
Valuation of Energy Storage White Paper by SCEUCSD-Strategic-Energy
 
Ricardo low carbon vehicle partnership life cycle co2 measure - final report
Ricardo low carbon vehicle partnership life cycle co2 measure - final reportRicardo low carbon vehicle partnership life cycle co2 measure - final report
Ricardo low carbon vehicle partnership life cycle co2 measure - final reportUCSD-Strategic-Energy
 
White House Smart Grid Strategy for 21st Century
White House Smart Grid Strategy for 21st CenturyWhite House Smart Grid Strategy for 21st Century
White House Smart Grid Strategy for 21st CenturyUCSD-Strategic-Energy
 
UCSD to test 2nd Life EV Batteries for NREL & CCSE
UCSD to test 2nd Life EV Batteries for NREL & CCSEUCSD to test 2nd Life EV Batteries for NREL & CCSE
UCSD to test 2nd Life EV Batteries for NREL & CCSEUCSD-Strategic-Energy
 
Unlocking the microgrid for data centers
Unlocking the microgrid for data centersUnlocking the microgrid for data centers
Unlocking the microgrid for data centersUCSD-Strategic-Energy
 
CA Energy Comm 2011-12 inv plan for plug in electric vehicles
CA Energy Comm 2011-12 inv plan for plug in electric vehiclesCA Energy Comm 2011-12 inv plan for plug in electric vehicles
CA Energy Comm 2011-12 inv plan for plug in electric vehiclesUCSD-Strategic-Energy
 
Micorgrids as an Utility of the Future
Micorgrids as an Utility of the FutureMicorgrids as an Utility of the Future
Micorgrids as an Utility of the FutureUCSD-Strategic-Energy
 
Byron Washom's Microgrid Guest Lecture
Byron Washom's Microgrid Guest LectureByron Washom's Microgrid Guest Lecture
Byron Washom's Microgrid Guest LectureUCSD-Strategic-Energy
 
Smart power generation at ucsd power magazine nov 2010
Smart power generation at ucsd  power magazine nov 2010Smart power generation at ucsd  power magazine nov 2010
Smart power generation at ucsd power magazine nov 2010UCSD-Strategic-Energy
 
Washom tsunami impacts on midway atoll 3 11-11 abbreviated version
Washom tsunami impacts on midway atoll 3 11-11 abbreviated versionWashom tsunami impacts on midway atoll 3 11-11 abbreviated version
Washom tsunami impacts on midway atoll 3 11-11 abbreviated versionUCSD-Strategic-Energy
 

Plus de UCSD-Strategic-Energy (19)

Pev consumer behavior study plug in 2012 haddow v3 panel
Pev consumer behavior study plug in 2012 haddow v3 panelPev consumer behavior study plug in 2012 haddow v3 panel
Pev consumer behavior study plug in 2012 haddow v3 panel
 
CEC pub on calculating additional needs to meet 33% RPS
CEC pub on calculating additional needs to meet 33% RPSCEC pub on calculating additional needs to meet 33% RPS
CEC pub on calculating additional needs to meet 33% RPS
 
Cpuc changes to adv energy storage incentives sep 2011
Cpuc changes to adv energy storage incentives sep 2011Cpuc changes to adv energy storage incentives sep 2011
Cpuc changes to adv energy storage incentives sep 2011
 
ORNL econ analysis of repurposed EV batteries for Stationary Applications
ORNL econ analysis of repurposed EV batteries for Stationary ApplicationsORNL econ analysis of repurposed EV batteries for Stationary Applications
ORNL econ analysis of repurposed EV batteries for Stationary Applications
 
Doe microgrid workshop aug 30 31 2011 presentations
Doe microgrid workshop aug 30 31 2011 presentationsDoe microgrid workshop aug 30 31 2011 presentations
Doe microgrid workshop aug 30 31 2011 presentations
 
UH-Maui College Wins DOE Grant for Renewable Energy Charging of Rental Electr...
UH-Maui College Wins DOE Grant for Renewable Energy Charging of Rental Electr...UH-Maui College Wins DOE Grant for Renewable Energy Charging of Rental Electr...
UH-Maui College Wins DOE Grant for Renewable Energy Charging of Rental Electr...
 
CPUC Ruling on Removing EV Deployment Barriers 139101
CPUC Ruling on Removing EV Deployment Barriers 139101CPUC Ruling on Removing EV Deployment Barriers 139101
CPUC Ruling on Removing EV Deployment Barriers 139101
 
San Diego Regional Support for Tailpipe Endgame project with AB 118 Investmen...
San Diego Regional Support for Tailpipe Endgame project with AB 118 Investmen...San Diego Regional Support for Tailpipe Endgame project with AB 118 Investmen...
San Diego Regional Support for Tailpipe Endgame project with AB 118 Investmen...
 
Valuation of Energy Storage White Paper by SCE
Valuation of Energy Storage White Paper by SCEValuation of Energy Storage White Paper by SCE
Valuation of Energy Storage White Paper by SCE
 
Ricardo low carbon vehicle partnership life cycle co2 measure - final report
Ricardo low carbon vehicle partnership life cycle co2 measure - final reportRicardo low carbon vehicle partnership life cycle co2 measure - final report
Ricardo low carbon vehicle partnership life cycle co2 measure - final report
 
White House Smart Grid Strategy for 21st Century
White House Smart Grid Strategy for 21st CenturyWhite House Smart Grid Strategy for 21st Century
White House Smart Grid Strategy for 21st Century
 
UCSD to test 2nd Life EV Batteries for NREL & CCSE
UCSD to test 2nd Life EV Batteries for NREL & CCSEUCSD to test 2nd Life EV Batteries for NREL & CCSE
UCSD to test 2nd Life EV Batteries for NREL & CCSE
 
New DOE Strategic Plan May 2011
New DOE Strategic Plan May 2011New DOE Strategic Plan May 2011
New DOE Strategic Plan May 2011
 
Unlocking the microgrid for data centers
Unlocking the microgrid for data centersUnlocking the microgrid for data centers
Unlocking the microgrid for data centers
 
CA Energy Comm 2011-12 inv plan for plug in electric vehicles
CA Energy Comm 2011-12 inv plan for plug in electric vehiclesCA Energy Comm 2011-12 inv plan for plug in electric vehicles
CA Energy Comm 2011-12 inv plan for plug in electric vehicles
 
Micorgrids as an Utility of the Future
Micorgrids as an Utility of the FutureMicorgrids as an Utility of the Future
Micorgrids as an Utility of the Future
 
Byron Washom's Microgrid Guest Lecture
Byron Washom's Microgrid Guest LectureByron Washom's Microgrid Guest Lecture
Byron Washom's Microgrid Guest Lecture
 
Smart power generation at ucsd power magazine nov 2010
Smart power generation at ucsd  power magazine nov 2010Smart power generation at ucsd  power magazine nov 2010
Smart power generation at ucsd power magazine nov 2010
 
Washom tsunami impacts on midway atoll 3 11-11 abbreviated version
Washom tsunami impacts on midway atoll 3 11-11 abbreviated versionWashom tsunami impacts on midway atoll 3 11-11 abbreviated version
Washom tsunami impacts on midway atoll 3 11-11 abbreviated version
 

Dernier

TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 
unit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxunit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxBkGupta21
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxLoriGlavin3
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfPrecisely
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyAlfredo García Lavilla
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxLoriGlavin3
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 

Dernier (20)

TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 
unit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxunit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptx
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easy
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptx
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 

SDG&E Smart Grid Capital Projects

  • 1. Application of San Diego Gas & Electric Company (U902M) for authority to update its gas and electric revenue requirement and base rates effective on January 1, 2012. Application No. 10-12-___ Exhibit No.: (SDG&E-11-CWP) CAPITAL WORKPAPERS TO PREPARED DIRECT TESTIMONY OF THOMAS O. BIALEK, Ph.D., P.E. ON BEHALF OF SAN DIEGO GAS & ELECTRIC COMPANY BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA DECEMBER 2010 TOB-CWP-1
  • 2. CAPITAL PROJECT WORKPAPER Page 2 of 27 PROJECT TITLE SBUDGET NO. Smart Grid Portfolio 10261 WITNESS IN SERVICE DATE Lee Krevat/Tom Bialek various PROJECT COST PRIOR REMAINING ($000 in 2009$) YEARS 2009 2010 2011 2012 YEARS TOTAL DIRECT LABOR 0 0 0 9696 15093 0 24789 DIRECT NONLABOR 0 0 0 26872 42176 0 69048 TOTAL DIRECT CAPITAL 0 0 0 36568 57269 0 93837 COLLECTIBLE NET CAPITAL 0 0 0 36568 57269 0 93837 FTE 0 0 0 129.3 201.2 0 330.5 BUSINESS PURPOSE This project portfolio incorporates smart grid technologies into the electric system infrastructure with a goal of maintaining and/or improving system performance and operational flexibility and reliability. As the penetration levels of renewables and electric vehicles increase relative to the local load on the system, they are expected to impact system operations and reliability and this portfolio will provide implementation of effective measures to mitigate these impacts. Relative to infrastructure expansion, projects that involve building completely new large scale elements of the distribution network such as new substations and new circuits shall be designed with a perspective that strives to incorporate smart grid concepts and equipment where applicable. This project portfolio also integrates with system improvement work being done to reduce the fire threat in the overhead electric system located in the very high/extreme fire threat zone as this hardening work provides a unique opportunity to incorporate smart grid elements to achieve the most overall effective and superior solution. Smart grid and the fire hardening rebuilding projects are particularly synergistic as the projects can be designed with a goal of providing more operational flexibility, improved reliability and at the same time reduce fire risk. Smart grid sensor technology, advanced system monitoring and control features can be integrated into the TOB-CWP-2
  • 3. CAPITAL PROJECT WORKPAPER Page 3 of 27 PROJECT TITLE SBUDGET NO. Smart Grid Portfolio 10261 WITNESS IN SERVICE DATE Lee Krevat/Tom Bialek various operation of the system which is especially valuable during storms and extreme fire risk weather events. In addition to maintaining and/or improving reliability, the circuit hardening work with smart grid technologies should facilitate integration of distributed energy resources such as solar and wind, as well as energy storage for back up of important community infrastructure such as cell phone networks, communications devices and small water pumps used to supply drinking water and fill small storage tanks that otherwise may lose power during extreme conditions. This project portfolio should provide the ability to incorporate technologies that can keep more customers and critical infrastructure safely in service during extreme fire risk weather events as well as during storm periods and times when the electric system is stressed due to high operating loads or operational emergencies. Specific categories of technologies to be provided by this project are listed below. PROJECT DESCRIPTION AND JUSTIFICATION The description and justification for each of the Smart Grid technologies included in this capital project are given below: RENEWABLE GROWTH ƒEnergy Storage (ES) - A cost forecast is provided for two types of energy storage systems to assist in addressing intermittency issues created by the variable output of renewable energy resources. One solution will place distributed energy storage systems on circuits with high penetration of customer photovoltaic systems. Additionally, energy storage systems will be strategically located in substations to mitigate the impact of multiple circuits with PV as the second budget item. ƒDynamic Line Ratings – A cost forecast is provided for implementation of dynamic ratings for distribution circuits. The implementation of dynamic line ratings has the potential for increasing circuit capacity and accommodating new renewable generation. ƒPhasor Measurement Units – A cost forecast is provided for implementation of phasor measurement units on the electric distribution system. Installation of phasor measurement units TOB-CWP-3
  • 4. CAPITAL PROJECT WORKPAPER Page 4 of 27 PROJECT TITLE SBUDGET NO. Smart Grid Portfolio 10261 WITNESS IN SERVICE DATE Lee Krevat/Tom Bialek various on the electric distribution system are expected improve reliability by employing high speed, time synchronized measurement devices. These devices will be utilized in conjunction with energy storage devices to create a closed loop control system to mitigate the impact of intermittent renewables. ƒCapacitor SCADA – A cost forecast is provided to implement SCADA control of all capacitors on SDG&E’s distribution system and is distinct from the SCADA expansion for switches discussed below. Benefits of SCADA for capacitors should include: better voltage and VAr control, reduced maintenance, and better system diagnostics. When coupled with energy storage, dynamic line ratings and phasor measurements new control schemes can be implemented which will mitigate the impact of PV system output fluctuations on system voltage. ƒSCADA Expansion – A cost forecast is provided for expansion of SCADA to expand remote operability and automated operation of distribution SCADA capable switches. This will continue SDG&E’s goal of providing faster isolation of faulted electric distribution circuits and branches, resulting in faster load restoration and isolation of system disturbances. ELECTRIC VEHICLE GROWTH ƒSmart Transformers – A cost forecast is provided for the installation of sensors and technology on distribution transformers so that they can monitor and report loading, and the state of the transformers. This project has the potential to allow increased transformer capacity utilization and accommodate future loads such as electric vehicle charging. ƒPublic Access Charging Facilities – A cost forecast is provided for the installation of utility owned public charging facilities for electric vehicles. SDG&E will install and own the charging facilities in under-served areas in order to broaden the coverage of public charging stations within its service territory. This project will also help to develop the services offered by 3rd parties to support vehicle charging facilities. TOB-CWP-4
  • 5. CAPITAL PROJECT WORKPAPER Page 5 of 27 PROJECT TITLE SBUDGET NO. Smart Grid Portfolio 10261 WITNESS IN SERVICE DATE Lee Krevat/Tom Bialek various RELIABILITY ƒWireless Faulted Circuit Indicators - A cost forecast is provided for implementation of wireless faulted circuit indicators. This system is expected to provide rapid identification and location of faulted distribution circuits resulting in reduced outage and repair times. ƒPhase Identification – A cost forecast is provided for accurate identification of phasing for implementation in the new distribution operating system. This project should enable improved worker safety, more accurate fusing, improved system planning, and reduced system losses. ƒCondition Based Maintenance Expansion – A cost forecast is provided for expansion of CBM to include distribution substation transformers at 4 kV substations. This project should reduce the risk of catastrophic failures and improve customer satisfaction. SMART GRID DEVELOPMENT Integrated Test Facility – A cost forecast is provided to construct facility upgrades and purchase and install equipment to create an integrated test facility. This will allow testing of the integration of multiple complex hardware and software systems comprising smart grid technologies. TOB-CWP-5
  • 6. CAPITAL PROJECT WORKPAPER Page 6 of 27 PROJECT TITLE SBUDGET NO. Smart Grid Portfolio 10261 WITNESS IN SERVICE DATE Lee Krevat/Tom Bialek various RENEWABLE GROWTH: ENERGY STORAGE A cost forecast is provided for two types of energy storage systems to assist in addressing intermittency issues created by the variable output of renewable energy resources. One solution will place distributed energy storage systems on circuits with high penetration of customer photovoltaic systems. Additionally, energy storage systems will be strategically located in substations to mitigate the impact of multiple circuits with PV as the second budget item. Energy storage systems will be used to demonstrate the ability to enhance the value of energy from renewable distributed generation in at least two fundamental ways: minimize the intermittency problem of renewables by installing storage and if appropriate and possible, use storage so that electric energy generated during times of lowest system need can be “time- shifted” and used during time of greatest need to the electric system. As the penetration of distributed energy resources, DER, continues to increase, the need for distributed storage will also increase in order to mitigate intermittency problems at the local 12 kV feeder level. This project will install energy storage in two forms: 1) distributed storage in the form of community energy storage, CES, devices in those circuits where the penetration of distributed PV is 20% or more of the circuit load at times of high photovoltaic system output and low circuit loads, and 2) substation energy storage of utility scale, size anticipated to be 1 MW or greater, which will be installed to mitigate the effects of utility scale (up to 2 MW) PV projects that will be installed in various locations. Storage devices will be installed at substations with identified large PV additions (Creelman, Pala, Valley Center, Lilac) and substations with high forecasted PV growth (Border, Kyocera, Middletown, Poway). Unit-cost estimates for substation Storage are based on price quotation obtained from Bulk Storage providers in September, 2009. TOB-CWP-6
  • 7. CAPITAL PROJECT WORKPAPER Page 7 of 27 PROJECT TITLE SBUDGET NO. Smart Grid Portfolio 10261 WITNESS IN SERVICE DATE Lee Krevat/Tom Bialek various Energy Storage, installed in conjunction with the appropriate sensors, control and communication systems should provide a solution for the mitigation of intermittency via the management and discharge of stored energy in a controlled and coordinated way. Based on the historical and forecasted penetration of distributed PV in the SDG&E service territory, CES devices, which are small, 50kW batteries, will be installed on 11 circuits in 2011, and on 14 more circuits in 2012. In addition to the CES devices, substation energy storage amounting to 4 MW will be installed in 2011 and another 4 MW will be installed in 2012. A prioritized list of circuits that are good candidates for distributed storage, based on PV growth projections, has been developed. CES unit-cost estimates were obtained from the EPRI Storage System Cost Workbook, published in March, 2010. Cash Flow: ($000 in 2009$) Year: 2010 2011 2012 Total Direct Labor: 0 6281 7427 13708 Direct Non-labor: 0 18912 22363 41275 Total Capital: 0 25193 29790 54983 TOB-CWP-7
  • 8. CAPITAL PROJECT WORKPAPER Page 16 of 27 PROJECT TITLE SBUDGET NO. Smart Grid Portfolio 10261 WITNESS IN SERVICE DATE Lee Krevat/Tom Bialek various ELECTRIC VEHICLE GROWTH: SMART TRANSFORMERS A cost forecast is provided for the installation of sensors and technology on distribution transformers so that they can monitor and report loading, and the state of the transformers. This project has the potential to allow increased transformer capacity utilization and accommodate future loads such as electric vehicle charging. Distribution line transformers can be converted into smart devices by installing monitoring equipment on the secondary bushings. These monitors will provide information to engineers and operators about the state of the grid including distributed resources and loads at the location of the transformers. This data will be especially valuable for monitoring the load and condition of transformers feeding plug-in electric vehicles. It will also provide information about the state and condition of the transformer. Transformer monitors will facilitate dynamic ratings for the transformers, the ability to verify energy consumed or generated by new distributed resources or loads for potential management applications, and the ability to assess detailed transformer conditions in order to proactively troubleshoot customer or secondary voltage problems. This project will install transformer monitoring devices on all transformers serving customers with plug-in electric vehicles. Sensing devices attached to transformers will be used to monitor real-time loading and establish accurate load profiles. This information will be available to system operators to alert them to possible overloads, imbalances, voltage excursions or other operational issues. Additionally, engineers will use this information to revise transformer loading guidelines which may lead to optimizing the number of customers that may be served from an individual transformer and reducing transformer loading problems. One transformer monitoring device will be installed on every distribution transformer that serves a customer with a PEV and associated charge stations. The number of PEV charge stations is anticipated to be: TOB-CWP-16
  • 9. CAPITAL PROJECT WORKPAPER Page 17 of 27 PROJECT TITLE SBUDGET NO. Smart Grid Portfolio 10261 WITNESS IN SERVICE DATE Lee Krevat/Tom Bialek various Year: 2010 2011 2012 Total PEV Charge Stations: 600 2150 700 3450 This estimated number of charge stations is based on the expected sales of battery electric vehicle and plug-in hybrid electric vehicle sales in the San Diego area. This estimate is based upon a DOE sponsored program with partnership by ECOtality and Nissan to deploy up to 5,000 electric vehicles and charging infrastructure in San Diego and four other U.S. cities. This project will begin in 2011, therefore the number of transformer monitors installed in 2011 will match the number of charge stations installed in 2010 and 2011. The cost estimate for this project is derived from an estimated average cost of $744 per transformer monitor installed on 2750 transformers in 2011 and on 700 transformers in 2012. The average cost estimate per transformer was based on information provided by a manufacturer of transformer monitoring equipment that could be used for this project. Cash Flow: ($000 in 2009$) Year: 2010 2011 2012 Total Direct Labor: 0 680 173 853 Direct Non-labor: 0 1367 348 1715 Total Capital: 0 2047 521 2568 TOB-CWP-17
  • 10. CAPITAL PROJECT WORKPAPER Page 18 of 27 PROJECT TITLE SBUDGET NO. Smart Grid Portfolio 10261 WITNESS IN SERVICE DATE Lee Krevat/Tom Bialek various ELECTRIC VEHICLE GROWTH: PUBLIC ACCESS CHARGING FACILITIES A cost forecast is provided for the installation of utility-owned, public access charging facilities for electric vehicles. SDG&E will install and own the charging facilities in under-served areas in order to broaden the coverage of public charging opportunities within its service territory. This effort will allow SDG&E to continue the momentum of the stakeholder charging facility siting and installation process established by ECOtality as part of their government funded EV Project between 2010 and mid-2011. As planned, this project will increase the number of charging facility services offered by 3rd parties, specifically to provide PEV charging facilities in locations that are not necessarily commercially or economically desirable, but needed to serve the broader and growing PEV charging needs of the public. SDG&E will work with the CPUC to develop broad criteria for evaluating the installation of “public access charging facilities” with the objective to ensure a network of public charging facilities is developed in the public interest over time that would provide sufficient support for the adoption and use of PEVs The number of 240V Level 2 charges installed will be approximately 1% of the cumulative plug- in hybrid electric vehicles, PHEVs, anticipated in the 2012 through 2015 period, and the number of DC Fast Chargers will be approximately 0.1% of the cumulative PHEV’s in the 2012-2015 period (see table below). PEV charging facility users will pay for the use of these charging facilities through an applicable PEV tariff that will be developed in accordance with policy established in the CPUC’s Alternative Fueled Vehicle Order Instituting Rulemaking. Year: 2010 2011 2012 Total 240V Level 2 Charge Stations 0 0 129 129 480V DC Fast Charger Stations: 0 0 13 13 TOB-CWP-18
  • 11. CAPITAL PROJECT WORKPAPER Page 19 of 27 PROJECT TITLE SBUDGET NO. Smart Grid Portfolio 10261 WITNESS IN SERVICE DATE Lee Krevat/Tom Bialek various The cash flow below reflects the public access charging facilities funding requirements for the entire SDG&E system taking place over a four year period (2012-2015) with the work beginning in 2012. The cash flow below reflects the public access charging facilities funding requirements taking place over a four year period (2012-2015). This cost estimate is derived from an estimated average cost of approximately $33,000 per 240V charging facility times 129 such facilities per year, plus approximately $71,000 per 480V charging facility times 13 such facilities per year. Cash Flow: ($000 in 2009$) Year: 2010 2011 2012 Total Direct Labor: 0 0 1503 1503 Direct Non-labor: 0 0 3727 3727 Total Capital: 0 0 5230 5230 TOB-CWP-19
  • 12. CAPITAL PROJECT WORKPAPER Page 27 of 27 PROJECT TITLE SBUDGET NO. Smart Grid Portfolio 10261 WITNESS IN SERVICE DATE Lee Krevat/Tom Bialek various Cash Flow: ($000 in 2009$) Year: 2010 2011 2012 Total Direct Labor: 0 45 120 165 Direct Non-labor: 0 457 1220 1677 Total Capital: 0 502 1340 1842 SUMMARY CASH FLOW A summary table of the cash flows for all projects in this workpaper is provided below. TOB-CWP-27
  • 13. Application of San Diego Gas & Electric Company (U902M) for authority to update its gas and electric revenue requirement and base rates effective on January 1, 2012. Application 10-12-____ Exhibit No.: (SDG&E-11) PREPARED DIRECT TESTIMONY OF THOMAS BIALEK, Ph.D., P.E. ON BEHALF OF SAN DIEGO GAS & ELECTRIC COMPANY BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA December 2010 SDGE Doc #249440
  • 14. TABLE OF CONTENTS I. INTRODUCTION...................................................................................................................... 1 A. Purpose of Testimony ................................................................................................................ 1 B. Overview of Operations ............................................................................................................. 3 C. Challenges Facing Operations .................................................................................................. 4 C. Reliability .................................................................................................................................. 14 D. Smart Grid Development ........................................................................................................ 15 E. Summary of Request................................................................................................................ 16 II. NONSHARED SERVICES ..................................................................................................... 17 A. Introduction .............................................................................................................................. 17 1. Smart Grid Team ............................................................................................................... 17 B. Discussion of O&M Activities ................................................................................................. 17 1. Smart Grid Team Salaries and Benefits .......................................................................... 17 III. CAPITAL.................................................................................................................................. 18 A. Introduction .............................................................................................................................. 18 B. Capital Request Detail ............................................................................................................. 20 1. Renewable Growth: Energy Storage (Budget Codes: 10261) ....................................... 20 2. Renewable Growth: Dynamic Line Ratings (Budget Codes: 10261) ........................... 21 3. Renewable Growth: Phasor Measurement Units (PMU) - Synchrophasors (Budget Codes: 10261) ..................................................................................................................... 22 4. Renewable Growth: Capacitor SCADA (Budget Codes: 10261) ................................. 24 5. Renewable Growth: SCADA Expansion (Budget Codes: 10261) ................................. 25 6. Electric Vehicle Growth: Plug-In Electric Vehicles ...................................................... 26 7. Electric Vehicle Growth: Smart Transformers (Budget Codes: 10261) ...................... 27 8. Electric Vehicle Growth: Public Access Charging Facilities (Budget Codes: 10261) 28 9. Reliability: Wireless Fault Indicators (FCI) (Budget Codes: 10261) .......................... 31 10. Reliability: Phase Identification (Budget Codes: 10261) ............................................... 32 11. Reliability: Condition Based Maintenance (CBM) Expansion (Budget Codes: 10261) ....................................................................................................... 33 12. Smart Grid Development: Integrated Test Facility (Budget Codes: 10261) ............... 35 IV. CONCLUSION ........................................................................................................................ 35 V. WITNESS QUALIFICATIONS ............................................................................................. 37 SDGE Doc #249440 TOB-i
  • 15. 1 PREPARED DIRECT TESTIMONY OF 2 THOMAS BIALEK, Ph.D., P.E. 3 ON BEHALF OF SAN DIEGO GAS & ELECTRIC COMPANY 4 5 6 I. INTRODUCTION 7 8 A. Purpose of Testimony 9 1. New Projects Incremental to Historical Activities 10 The purpose of this testimony is to sponsor the Smart Grid capital forecasts for 11 San Diego Gas & Electric Company, SDG&E, for the years 2010, 2011 and the test 12 year 2012. The Smart Grid portfolio of projects that are presented in this immediate 13 general rate case, GRC, application also have a life span that extend beyond the test 14 year. Additionally, this GRC funding request is not to be viewed as the entirety of 15 Smart Grid projects that SDG&E may request since other projects may be necessary in 16 the future as requirements change and as new technologies and solutions become 17 available. 18 As discussed in the Smart Grid policy testimony of Mr. Lee Krevat, Exhibit 19 SDG&E-10, there are many drivers for SDG&E’s Smart Grid activities. Based upon 20 these drivers, SDG&E has developed a limited portfolio of projects with the goal of 21 applying Smart Grid technologies to effectively integrate intermittent renewable 22 generation sources and plug-in electric vehicles, and includes other capabilities 23 designed to maintain and/or improve system reliability. The projects included in this 24 general rate case include only the distribution component of each project. The 25 information technology, IT, capital portions associated with these projects are 26 necessary to provide the communication devices, IT infrastructure and applications 27 required to derive the functionality envisioned with the individual project. The IT 28 components required for the Smart Grid portfolio of projects, while need-justified 29 within the scope of this testimony, are presented in the testimony of Mr. Jeff Nichols, 30 Exhibit SDG&E-18. What might be described today as the conventional or on-going 31 capital and operations and maintenance forecasts are presented in the testimonies of 32 Mr. Alan Marcher, Exhibit SDG&E-06 and Mr. Scott Furgerson, Exhibit SDG&E-05 33 respectively. SDGE Doc #249440 TOB-1
  • 16. 1 A list of the Smart Grid projects by categories and testimony sponsors is shown below: 2 RENEWABLE GROWTH 3 Energy Storage (ES) Capital Thomas Bialek, Exhibit SDG&E-11 4 IT Mr. Jeff Nichols, Exhibit SDG&E-18 5 Dynamic Line Ratings Capital Thomas Bialek, Exhibit SDG&E-11 6 IT Mr. Jeff Nichols, Exhibit SDG&E-18 7 Phasor Measurement Units Capital Thomas Bialek, Exhibit SDG&E-11 8 IT Mr. Jeff Nichols, Exhibit SDG&E-18 9 Capacitor SCADA Capital Thomas Bialek, Exhibit SDG&E-11 10 IT Mr. Jeff Nichols, Exhibit SDG&E-18 11 SCADA expansion Capital Thomas Bialek, Exhibit SDG&E-11 12 IT Mr. Jeff Nichols, Exhibit SDG&E-18 13 14 15 ELECTRIC VEHICLE GROWTH 16 Plug-in Electric Vehicles Capital Mr. Alan Marcher, Exhibit SDG&E-06 17 IT Mr. Jeff Nichols, Exhibit SDG&E-18 18 Smart Transformers Capital Thomas Bialek, Exhibit SDG&E-11 19 IT Mr. Jeff Nichols, Exhibit SDG&E-18 20 Public Access Charging Facilities Capital Thomas Bialek, Exhibit SDG&E-11 21 IT Mr. Jeff Nichols, Exhibit SDG&E-18 22 23 RELIABILITY 24 Wireless Faulted Circuit Indicators Capital Thomas Bialek, Exhibit SDG&E-11 25 IT Mr. Jeff Nichols, Exhibit SDG&E-18 26 Phase Identification Capital Thomas Bialek, Exhibit SDG&E-11 27 IT Mr. Jeff Nichols, Exhibit SDG&E-18 28 Condition Based Maintenance 29 Expansion Capital Thomas Bialek, Exhibit SDG&E-11 30 IT Mr. Jeff Nichols, Exhibit SDG&E-18 31 32 SDGE Doc #249440 TOB-2
  • 17. 1 SMART GRID DEVELOPMENT 2 Integrated Test Facility Capital Thomas Bialek, Exhibit SDG&E-11 3 IT Mr. Jeff Nichols, Exhibit SDG&E-18 4 5 2. Smart Grid Team 6 This testimony also sponsors the ongoing funding of the cost center for the 7 Smart Grid Team. This small group of individuals: a Director, Chief Engineer, Lead 8 Architect, Policy Manager, Customer Manager and Administrative Associate; are 9 responsible for developing SDG&E’s Smart Grid strategy and policy. The organization 10 is also responsible for aligning the strategy and policy across SDG&E. 11 12 Table TOB -1 13 Summary of TY2012 Change 14 (Thousands of $2009) 15 Functional Area: SMART GRID Description 2009 TY2012 Change Testimony Adjusted- Estimated Reference Recorded Total Non-Shared 330 1,003 673 Section II Total Shared Services (Book 0 0 0 Expense) Total O&M 330 1,003 673 Total Capital 0 57,269 57,269 Section III 16 17 B. Overview of Operations 18 Smart Grid is a new activity. A special cost-center function has been created to deal 19 just with this topic, and that cost center’s role is to provide steering and strategic guidance 20 throughout the organization to coordinate the adoption and implementation of Smart Grid 21 related technologies. 22 23 24 SDGE Doc #249440 TOB-3
  • 18. 1 C. Challenges Facing Operations 2 As described in the testimony of Mr. Lee Krevat, Exhibit SDG&E-10, SDG&E is 3 committed to meeting California policy goals of promoting increased levels of renewable 4 energy resources and the deployment of electric vehicles to meet greenhouse gas reduction 5 targets. However, with advancements in environmentally friendly technologies such as solar 6 and wind generation, plug-in electric vehicles, and energy storage, as well as the deployment 7 of new customer empowering Smart Meter technology, the electric system is in the midst of 8 significant change. SDG&E recognizes the need to leverage equally advancing information 9 and communication technologies, ICT, to ensure the continued safety, reliability, security, and 10 efficiency of the electric grid as utilization of intermittent energy resources and demand for 11 plug-in electric vehicle, PEV, increases. 12 In addition to the traditional grid management and customer-facing projects utilities 13 have undertaken in the past, environmental policy and legislation encouraging customer 14 empowerment over energy management is driving the need to accelerate the integration of 15 digital and communications technology with the electric delivery system, creating a smarter 16 grid. The public policy objectives of California and the situation faced in San Diego create a 17 need to move forward with the implementation of advanced technology in order to meet the 18 State’s ambitious energy policy goals. 19 The seven characteristics or performance features of a Smart Grid as developed by the 20 Department of Energy’s, DOE, Smart Grid Task Force and referenced by the CPUC are1: 21 • Anticipating and responding to system disturbances in a 22 self-healing manner; 23 • Enabling active participation by consumers; 24 • Operating resiliently against physical and cyber attack; 25 • Accommodating all generation and storage options; 26 • Enabling new products, services, and markets; 27 • Optimizing asset utilization and operating efficiently; and 28 • Providing the power quality for the range of needs in a 29 digital economy. 30 1 CPUC R.08-12-009, Order Instituting Rulemaking to consider Smart Grid Technologies Pursuant to Federal Legislation and on the Commission’s own Motion to Actively Guide Policy in California’s Development of a Smart Grid System, p 11. SDGE Doc #249440 TOB-4
  • 19. 1 SDG&E’s current portfolio of T&D Smart Grid projects focus on four specific areas: 2 renewable generation growth, electric vehicle growth, reliability and Smart Grid development. 3 In the first area SDG&E is focused on mitigating the impact of renewable photovoltaic, PV, 4 distributed generation. For the second area, SDG&E is deploying new Smart Grid 5 technologies as well as traditional infrastructure to mitigate reliability issues due to customer 6 adoption of PEVs. The third area focus is to mitigate the reliability impacts of an aging 7 electric infrastructure by implementing advanced sensors and associated systems. For the last 8 area, SDG&E is planning to create an integrated test facility to put various emerging 9 technology solutions together to test for interoperability and provide proof-of-concept 10 demonstrations. 11 As indicated by Mr. Lee Krevat, Exhibit SDG&E-10, SDG&E needs to mitigate the 12 impacts of renewable generation development that is planned and occurring in the San Diego 13 region to satisfy California’s 33% Renewable Portfolio Standard, RPS. Additionally, San 14 Diegans have installed more total systems and nameplate capacity of distributed photovoltaic 15 generation than consumers in any city in the state based on 2009 data2. The arrival of 1,000 16 Nissan Leaf all-electric vehicles starting in December of 2010 will also increase the immediate 17 need for Smart Grid technologies on the electric grid in San Diego. 18 Increased situational awareness enabled by sensors, communications, data, analysis and 19 remote control allows the system to be operated with increased reliability and safety. Dynamic 20 measurement of system characteristics and improved distribution management also increases 21 the capabilities and resiliency of energy delivery. However, as a result, the complexity of grid 22 operations is increased significantly. 23 24 1. San Diego Drivers 25 The specific drivers of Smart Grid investments in the San Diego Gas & Electric 26 service territory are the growth of distributed photovoltaics, PV, the expected growth of 27 plug-in electric vehicles, PEVs and SDG&E’s aging infrastructure. 28 29 2 “California’s Solar Cities: Leading the Way to a Clean Energy Future”; Environment California Research and Policy Center, Summer 2009; accessed July 15, 2010 at http://www.environmentcalifornia.org/reports/energy/energy-program- reports/californias-solar-cities SDGE Doc #249440 TOB-5
  • 20. 1 a. Distributed Photovoltaic Growth 2 At year end 2009 distributed PV accounted for approximately 65 MWac 3 of generating capacity on the SDG&E system. As of the same timeframe, 4 SDG&E has ten primary distribution circuits with over 20% of the load served 5 by PV at times of low circuit loading as shown in Figure TOB-1.3 Figure TOB- 6 2 illustrates both the actual recorded PV installations and the California Energy 7 Commission, CEC, forecast based on past PV growth.4 Applying the CEC 8 forecast to existing installations on circuits produces Figure TOB-3 which 9 shows the circuits with levels of over 20% PV generation at year end 2020. 10 This figure shows sixty circuits meet this criteria, which SDG&E believes is an 11 appropriate threshold to conduct more detailed studies to determine if the circuit 12 can accommodate these levels of PV without impacting grid voltage operating 13 limits or creating any operations and maintenance issues. 14 15 3 While SDG&E’s Rule 21 places an emphasis on percentage nameplate capacity as a function of peak line section rating, for PV systems the maximum output at times of lower system load (no air conditioning) are more critical. 4 CEC CALIFORNIA ENERGY DEMAND 2010-2020 December 2009, CEC-200-2009-012-CMF, ADOPTED FORECAST , Form 1.4, Page 149. SDGE Doc #249440 TOB-6
  • 21. 1 2 Figure TOB-1 – PV Penetration YE 2009 as a Percentage of Circuit Load on April 1, 2009, 1 3 pm 4 5 6 SDGE Doc #249440 TOB-7
  • 22. 1 2 Figure TOB-2 – Actual Historical PV Installations and CEC PV Forecast SDGE Doc #249440 TOB-8
  • 23. 1 2 Figure TOB-3 – Impact of Increasing PV Penetration versus year with CEC Forecast Installations 3 4 SDG&E has been able to instrument a circuit with a high PV nameplate capacity at a time of 5 low circuit loading. Figure TOB- 4 shows the impact of a 1 MWac PV system on SDG&E’s primary 6 voltage for one day recorded with this instrumentation. The upper set of curves shows the impact of 7 fog burning off on the output of the PV system and the commensurate changes in primary voltage 8 during the day. The lower set of curves is a magnified view, 10 minutes of one particular change in 9 the PV system output data. Operational issues that are noted from these curves include the following: 10 high primary voltage coincident with PV system output and an approximately 15% swing in primary 11 voltage coincident with PV system output change. These measured and changes in values are outside 12 SDG&E’s design tolerance limits. Therefore, from the data and forecast currently available, SDG&E 13 believes investment in mitigation of intermittent photovoltaic generation is necessary. 14 15 SDGE Doc #249440 TOB-9
  • 24. 1 2 Figure TOB-4 – PV System Output Variability Impact on Primary Voltage 3 4 One component of a solution to this problem is to incorporate energy storage as a grid device. 5 With energy storage, given its cost today, it is necessary to accrue benefits associated with multiple SDGE Doc #249440 TOB-10
  • 25. 1 value streams in order to provide a least-cost solution. The value streams for energy storage are as 2 follows: 3 • Grid operation to islanded system operation 4 • Smoothing electrical transition 5 • Power quality 6 • Power leveling / regulation on grids with connected variable, renewal energy sources, 7 such as Wind, PV, etc. 8 • Peak load shifting / shaving 9 • As needed 10 • Daily 11 • Energy storage for off-peak / on-peak energy arbitrage 12 • Energy regulation / ancillary services related to CAISO operations 13 • T&D capacity deferral 14 15 SDG&E has utilized a report published by Sandia National Labs as a reference guide for 16 energy storage applications which states5: 17 "The work documented in this report represents another step in the ongoing investigation of 18 innovative and potentially attractive value propositions for electricity storage by the United 19 States Department of Energy (DOE) and Sandia National Laboratories (SNL) Energy Storage 20 Systems (ESS) Program. This study uses updated cost and performance information for 21 modular energy storage (MES) developed for this study to evaluate four prospective value 22 propositions for MES. The four potentially attractive value propositions are defined by a 23 combination of well known benefits that are associated with electricity generation, delivery, 24 and use. The value propositions evaluated are: 1) transportable MES for electric utility 25 transmission and distribution (T&D) equipment upgrade deferral and for improving local 26 power quality, each in alternating years, 2) improving local power quality only, in all years, 3) 27 electric utility T&D deferral in year 1, followed by electricity price arbitrage in following 28 years; plus a generation capacity credit in all years, and 4) electric utility end-user cost 29 management during times when peak and critical peak pricing prevail." 5  Sandia National Laboratory, SANDIA REPORT SAND2008-0978, Unlimited Release Printed, February 2008, Benefit/Cost Framework for Evaluating Modular Energy Storage, A Study for the DOE Energy Storage Systems Program, Susan M. Schoenung and Jim Eyer.   SDGE Doc #249440 TOB-11
  • 26. 1 2 The summary results of the SNL study are shown below. 3 “Figure 17 shows the present worth of benefits and costs for lead-acid battery storage used for 4 the four value propositions investigated. Most notably: value proposition 1 (T&D deferral plus 5 PQ), value proposition 2 (PQ/reliability only) and value proposition 3 (high value T&D 6 deferral plus arbitrage and generation capacity credit) show promise as they have a benefit/cost 7 ratio greater than 1. 8   9   10 11 Other components of the multi-faceted solution include dynamic line ratings, phasor 12 measurement units and supervisory control and data acquisition, SCADA, expansion to enable remote 13 control of capacitor banks and other switches on the system. 14 15 B. Plug-In Electric Vehicle (PEV) Growth 16 As also discussed in the testimony of Mr. Lee Krevat, Exhibit SDG&E-10, the impact 17 of PEVs on SDG&E’s system is expected to be significant. He discussed the US Department 18 of Energy, DOE, and California Energy Commission, CEC, grants awarded to ECOtality6 as 6 ECOtality is a San Francisco based company specializing in the development and commercialization of electric transportation and storage technologies. SDGE Doc #249440 TOB-12
  • 27. 1 well as the large loads that these vehicles will impose on the system as a result of the rapid 2 deployment of PEVs and residential, commercial and public charging facilities in the SDG&E 3 service territory beginning in 2010. He also mentioned the need to make infrastructure 4 investments to empower customers and to minimize barriers that would be created without 5 immediate action taken to ensure the deployment of adequate charging infrastructure. This 6 position is also supported by the Commission as described in the testimony of Ms. Kathleen 7 Cordova, Exhibit SDG&E-15 (SDG&E’s Electric Clean Transportation Program). In January 8 2010, the Commission recognized the importance of early action to support the electric 9 transportation market in defining the scope for the alternative-fueled vehicles rulemaking and 10 stated that it will follow the directive set forth in Senate Bill 626 to evaluate policies to develop 11 infrastructure sufficient to overcome any barriers to the widespread deployment and use of 12 plug-in hybrid and electric vehicles.7 13 Figure TOB-5 shows SDG&E’s estimates of PEV sales in its service territory. This 14 estimate of PEV sales was based upon several independent analysts’ forecast of light duty 15 vehicles PEV penetrations adjusted to be applicable to SDG&E’s service territory and related 16 impacts. By 2012 approximately 15,000 PEVs are estimated to be owned by customers in 17 SDG&E’s service territory. With an estimated load of 3 kW per vehicle this equates to 45 MW 18 of new load, that if not managed properly could have a significant impact on the local 19 distribution system and potential generation needs. It should be noted that the Commission 20 approved in June of 2010 the use of three experimental PEV time-of-use rates, each with 21 varying differences between on-peak and off-peak pricing to explore the degree to which rates 22 (and enabling PEV technology) impacts consumer time-of-day charging decisions and 23 behavior.8 24 One of many challenges associated with PEV growth rates will be with customers who 25 purchase these vehicles and are located in the older coastal areas of SDG&E’s service territory. 26 In most instances these homes are smaller, do not have air conditioning and the number of 27 customers connected per transformer is greater than in the inland valleys. A 3 kW charging 7 January 12, 2010 Scoping Memo in R.09-08-009, Commission Rulemaking on alternative-fueled vehicle tariffs, infrastructure and policies to support California's greenhouse gas emissions reduction goals. 8 http://docs.cpuc.ca.gov/word_pdf/AGENDA_RESOLUTION/119477.pdf Res.E-4334 – The CPUC approved SDG&E’s request to establish three new temporary experimental residential rate schedules for plug-in electric vehicle (PEV) charging to be used coincident with the EV Project (ECOtality’s deployment of home, commercial and public charging facilities in collaboration with Nissan’s deployment of the Leaf PEV in SDG&E’s services territory). This Resolution approves implementation of the experimental rate schedules beginning January 1, 2011. The temporary rates will remain in effect until November 30, 2012 (or until completion of the related pricing pilot research project.) SDGE Doc #249440 TOB-13
  • 28. 1 load is comparable to an air conditioner load which now suddenly is placed onto the grid. 2 SDG&E is currently involved in an Electric Power Research Institute, EPRI, project9 to further 3 understand the impact of PEVs on the grid. Proactively, SDG&E believes it is imperative to 4 fund three areas of activities: existing facility upgrades, smart transformers and public charging 5 infrastructure in order address the coming PEV consumer demand and to reduce potential 6 market barriers to PEV adoption due to inadequate charging infrastructure. 7   Cumulative and annual PEV sales (2010 to 2020) 8 BEVs and PHEVs (x 1,000) 9 300 Cumulative B EVs 10 Cumulative PHEVs 250 2 7.5 11 Annual PEV s ales 23 6.6 12 200 2 1.6 13 1 83 .6 14 150 16 .5 1 40 .1 15 12 .01 100 10 6.1 16 8.4 7 9.3 17 50 5.6 3 .7 56 .9 58.9 18 0 .2 2.1 2.2 2 .6 38 .6 38.4 48.7 1 .1 5.2 1 3.1 2 4.1 25.2 30.5 15.6 19 0 1.3 6.1 7.9 11.4 20.2 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 20 21 Figure TOB-5 – SDG&E’s Estimate of PEV Sales 22 23 C. Reliability 24 As discussed at length in the testimony of Mr. Alan Marcher, Exhibit SDG&E-06, 25 SDG&E has an aging infrastructure and a need to continue to improve its fire preparedness. 26 Seventy-eight percent of SDG&E’s 4 kV substation transformers have been in-service 50 years 27 or more while only thirty seven percent of 12 kV substation transformers have been in-service 28 40 years or more. It is not just transformers but basic equipment such as poles, wire and cable. 29 Putting this in context, these pieces of equipment have to handle not only existing historical 30 loads but now also the intermittent power flows associated with PV systems that have been 31 installed and the PEV loads that are poised to make an appearance at the end of 2010. 9 EPRI Project ID No. 065939. SDGE Doc #249440 TOB-14
  • 29. 1 2 As SDG&E works to further reduce the risk of fires and strive to improve its ability to 3 respond and restore electrical service as quickly as possible, it is leveraging advances in 4 technology and systems. SDG&E believes that by putting the “smarts” in the grid it should be 5 possible to maintain and/or improve reliability in the face of these challenges. Therefore, 6 SDG&E has developed cost forecasts for three Smart Grid projects for incorporation in this 7 general rate case: wireless faulted circuit indicators, phase identification and an expansion of 8 condition based maintenance. 9 10 D. Smart Grid Development 11 As the Commission has noted in its recent Smart Grid OIR decision, D.10-06-047, 12 “…that deployment plans should include a discussion of an IOU’s Smart Grid strategy, 13 and that the strategy should offer a sense of direction and guidance, rather than setting rigid 14 requirements. This is clearly a reasonable approach since there are significant uncertainties 15 surrounding future technologies that may be part of a Smart Grid.” 10 16 also 17 “There is a consensus among those parties providing comments that a 18 roadmap can provide useful information concerning technologies and their 19 deployment, even though they will remain subject to change.”11 20 21 and finally 22 “In addition, there is near universal agreement that it is difficult to provide a reliable cost 23 estimate based on future and unknown technologies and infrastructure investments….but the 24 Commission does not find that it would be possible to require detailed, projected cost estimates 25 for technology that is undergoing dramatic changes in costs and technology today, or has yet to 26 be invented.”12 27 Given that Smart Grid technologies, solutions and standards are rapidly evolving and it 28 is difficult to estimate costs and requirements in the next five years, there is a need, as pointed 10 R.08-12-009, Order Instituting Rulemaking to Consider Smart Grid Technologies Pursuant to Federal Legislation and on the Commission’s own Motion to Actively Guide Policy in California’s Development of a Smart Grid System, D.10-06- 047 (Decision Adopting Requirements For Smart Grid Deployment Plans Pursuant To Senate Bill 17 (Padilla), Chapter 327, Statutes Of 2009)., pg. 47. 11 Ibid, pg. 64. 12 Ibid, pg. 68. SDGE Doc #249440 TOB-15
  • 30. 1 out by Mr. Lee Krevat Exhibit SDG&E-10, for SDG&E to test the function of new consumer 2 focused technologies on the installed smart meters and associated systems to enable two Smart 3 Grid characteristics. These characteristics are enabling active participation by consumers and 4 new products, services, and markets. Therefore, SDG&E has developed a cost forecast for an 5 integrated Smart Grid test facility to address standard, integration and interoperability 6 challenges for these technologies. 7 8 E. Summary of Request 9 10 Table TOB - 2 11 O&M Non-Shared Services 12 Testimony Section II 13 (Thousands 2009 dollars) 14 SMART GRID Categories of Management 2009 Adjusted- TY2012 Change Recorded Estimated A. Smart Grid Electric Distribution 330 1,003 673 Total 330 1,003 673 15 16 17 18 Table TOB - 3 19 Capital Expenditures 20 (Thousands 2009 dollars) 21 SMART GRID Category Description 2009 2010 2011 2012 Recorded Estimated Estimated Estimated 1. Smart Grid Portfolio $0 $0 $36,568 $57,269 Total Capital: $0 $0 $36,568 $57,269 22 23 24 25 26 27 28 SDGE Doc #249440 TOB-16
  • 31. 1 II. NONSHARED SERVICES 2 A. Introduction 3 1. Smart Grid Team 4 This testimony also sponsors the ongoing funding of the cost center for the 5 Smart Grid Team. This small group of individuals: a Director, Chief Engineer, Lead 6 Architect, Policy Manager, Customer Manager and Administrative Associate; are 7 responsible for developing SDG&E’s Smart Grid strategy and policy. The organization 8 is responsible for aligning the strategy and policy across SDG&E. 9 10 Table TOB - 4 11 O&M Non-Shared Services 12 (Thousands of 2009 dollars) 13 SMART GRID A. Smart Grid Electric Distribution 2009 Adjusted- TY2012 Change Recorded Estimated 1. Smart Grid Electric Distribution 330 1,003 673 Total 330 1,003 673 14 15 16 B. Discussion of O&M Activities 17 1. Smart Grid Team Salaries and Benefits 18 This funding covers the salaries and incidental O&M expenses of the Smart 19 Grid Team. This small team was first formed in 2009 as a result of the significant 20 activities at both the Federal and State level with regards to Smart Grid. It was 21 recognized that with Federal legislation and the DOE driven activity in this area that a 22 team was required to specifically focus on this topic; driving SDG&E’s strategy and 23 vision in this important area. As a consequence, in June 2009, a Director, Chief 24 Engineer, Lead Architect and an Administrative Associate were brought together to 25 begin work. In 2010, a Policy Manager and Customer Manager were also brought into 26 the team completing the staffing goals. 27 The team spent most of 2009 developing a SDG&E strategy and vision and 28 subsequently communicating both internally and externally. The Commission’s Smart 29 Grid Rulemaking was also underway at this time and the team participated in SDGE Doc #249440 TOB-17
  • 32. 1 workshops and commented on Commission questions. The DOE released its funding 2 opportunity notice for Smart Grid and the team spent the summer developing proposal 3 for both the investment grant and regional demonstration solicitations. 4 In 2010 the work on the Smart Grid OIR continued with a decision being 5 released regarding the implementation of SB17. Work has also begun to deliver the 6 SDG&E Smart Grid vision and roadmap by the required July 1, 2011 deadline. The 7 team directed SDG&E’s effort in the EPRI-led California utilities Smart Grid 2020 8 Vision activity in response to the CEC solicitation of the same name. An internal 9 stakeholder effort also occurred to align and drive SDG&E’s strategy and policy across 10 the organization. 11 Future work activities will include the SB17 mandated yearly updates to 12 SDG&E’s Smart Grid roadmap, responding to other Commission rulings, other pending 13 legislation and driving Smart Grid solutions to system problems to name but a few 14 activities. 15 16 III. CAPITAL 17 A. Introduction 18 This project portfolio incorporates Smart Grid technologies into the electric system 19 infrastructure with a goal of maintaining and/or improving system performance and operational 20 flexibility and reliability. As the penetration levels of renewables and electric vehicles increase 21 relative to the local load on the system, they are expected to impact system operations and 22 reliability and this portfolio will provide implementation of effective measures to mitigate 23 these impacts. Relative to infrastructure expansion, projects that involve building completely 24 new large scale elements of the distribution system such as new substations and new circuits 25 shall be designed with a perspective that strives to incorporate Smart Grid concepts and 26 equipment where applicable. 27 This project portfolio also integrates with system improvement work being done to 28 further reduce the fire threat in the overhead electric system located in the very high/extreme 29 fire threat zone. As discussed in the testimony of Mr. Alan Marcher, Exhibit SDG&E-06, this 30 system hardening work provides a unique opportunity to incorporate Smart Grid elements to 31 achieve the most overall effective and superior solution. Smart Grid and the fire hardening SDGE Doc #249440 TOB-18
  • 33. 1 projects are particularly synergistic as the projects can be designed with a goal of providing 2 more operational flexibility, improved reliability and at the same time further reduce fire risk. 3 Smart Grid sensor technology, advanced system monitoring and control features can be 4 integrated into the operation of the system which is especially valuable during storms and 5 extreme fire risk weather events. In addition to maintaining and/or improving reliability, the 6 circuit hardening work with Smart Grid technologies should facilitate integration of distributed 7 energy resources such as solar and wind, as well as energy storage for back up of important 8 community infrastructure such as cell phone networks, communications devices and small 9 water pumps used to supply drinking water and fill small storage tanks that otherwise may lose 10 power during extreme conditions. This project portfolio should provide the ability to 11 incorporate technologies that can keep more customers and critical infrastructure safely in 12 service during extreme fire risk weather events as well as during storm periods and times when 13 the electric system is stressed due to high operating loads or operational emergencies. 14 The Smart Grid portfolio is divided into four principal categories. These are Renewable 15 Growth, Electric Vehicle Growth, Reliability and Smart Grid Development. Individual 16 projects comprising the portfolio are grouped into these categories: 17 18 RENEWABLE GROWTH 19 Energy Storage (ES) 20 Dynamic Line Ratings 21 Phasor Measurement Units 22 Capacitor SCADA 23 SCADA Expansion 24 ELECTRIC VEHICLE GROWTH 25 Plug-in Electric Vehicles 26 These costs are incorporated in the testimony of Mr. Alan Marcher, Exhibit SDG&E-06. 27 Smart Transformers 28 Public Access Charging Facilities 29 RELIABILITY 30 Wireless Faulted Circuit Indicators 31 Phase Identification 32 Condition Based Maintenance (CBM) Expansion SDGE Doc #249440 TOB-19
  • 34. 1 SMART GRID DEVELOPMENT 2 Integrated Test Facility 3 4 CAPITAL SUMMARY REQUEST 5 6 7 Table TOB - 5 8 Capital Expenditures 9 (Thousands of 2009 dollars) 10 2009 2010 2011 2012 Category Description Recorded Estimated Estimated Estimated 1. Smart Grid Portfolio $0 $0 $36,568 $57,269 Total Capital: $0 $0 $36,568 $57,269 11 12 B. Capital Request Detail 13 1. Renewable Growth: Energy Storage (Budget Codes: 10261) 14 A cost forecast is provided for two types of energy storage systems to assist in 15 addressing intermittency issues created by the variable output of renewable energy 16 resources. One solution will place distributed energy storage systems on circuits with high 17 penetration of customer photovoltaic systems. Additionally, energy storage systems will be 18 strategically located in substations to mitigate the impact of multiple circuits with PV as the 19 second budget item. 20 Energy storage systems will be used to demonstrate the ability to enhance the value 21 of energy from renewable distributed generation in at least two fundamental ways: 22 minimize the intermittency problem of renewables by installing storage and if appropriate 23 and possible, use storage so that electric energy generated during times of lowest system 24 need can be “time-shifted” and used during time of greatest need to the electric system. 25 As the penetration of distributed energy resources, DER, continues to increase, the 26 need for distributed storage will also increase in order to mitigate intermittency problems at 27 the local 12 kV feeder level. This project will install energy storage in two forms: 1) 28 distributed storage in the form of community energy storage, CES, devices in those circuits 29 where the penetration of PV is 20% or more of the circuit load at times of high photovoltaic SDGE Doc #249440 TOB-20
  • 35. 1 system output and low circuit loads and 2) substation energy storage of utility scale, size 2 anticipated to be 1 MW or greater, which will be installed to mitigate the effects of utility 3 scale (up to 2 MW) PV projects that will be installed in various locations. 4 Energy Storage, installed in conjunction with the appropriate sensors, control and 5 communication systems should provide a solution for the mitigation of intermittency via the 6 management and discharge of stored energy in a controlled and coordinated way. 7 Based on the historical and forecasted penetration of distributed PV in the SDG&E 8 service territory, CES devices, which are small, 50 kW batteries will be installed on 11 9 circuits in 2011, and on 14 more circuits in 2012. In addition to the CES devices, substation 10 energy storage amounting to 4 MW will be installed in 2011 and another 4 MW will be 11 installed in 2012. 12 13 Table TOB - 6 14 Renewable Growth, Energy Storage Capital Expenditures 15 (Thousands of 2009 dollars) 16 Description 2009 Adjusted 2010 2011 TY2012 Recorded Estimated Estimated Estimated Category 1 $0 $0 $25,193 $29,790 17 18 2. Renewable Growth: Dynamic Line Ratings (Budget Codes: 10261) 19 A cost forecast is provided for implementation of dynamic ratings for distribution 20 circuits. The implementation of dynamic line ratings has the potential for increasing circuit 21 capacity and accommodating new renewable generation. 22 Dynamic ratings of equipment provide an opportunity to optimize capital 23 investments and operate the grid at higher efficiencies. Dynamic line ratings compare the 24 weather-adjusted, thermal rating of a conductor against the static design rating. The pre- 25 calculated static value for the thermal rating of a conductor is developed to protect the 26 conductor from damage due to annealing and from excessive sag during extreme heat. 27 This project will install dynamic line rating technologies on ten distribution circuits 28 per year. Installations will be made on the most critical distribution circuits which include 29 those circuits with significant renewables penetration and energy storage. Sensors on 30 overhead distribution lines will be used to monitor the line conductor tension and determine SDGE Doc #249440 TOB-21
  • 36. 1 ground clearances and weather conditions to calculate the amount of current that can be 2 transmitted in real time. This information is then provided to system operators or engineers 3 for their use in safe, reliable and economic system operation. By monitoring wind speed, 4 conductor tension and solar heating, a real-time line rating that is indicative of current 5 conductor capability can be calculated. An advanced human interface will also be 6 developed to assist system operators with managing the information. 7 SDG&E has 995 distribution circuits, and high loading is anticipated on 1% of 8 circuits that will warrant close monitoring and dynamic line rating. Installing dynamic line 9 rating technology on 10 distribution circuits per year will result in the following cash flow. 10 11 Table TOB - 7 12 Renewable Growth, Dynamic Line Ratings Capital Expenditures 13 (Thousands of 2009 dollars) 14 Description 2009 Adjusted 2010 2011 TY2012 Recorded Estimated Estimated Estimated Category 1 $0 $0 $1,963 $1,963 15 16 3. Renewable Growth: Phasor Measurement Units (PMU) - 17 Synchrophasors (Budget Codes: 10261) 18 A cost forecast is provided for implementation of phasor measurement units on the 19 electric distribution system. Installation of phasor measurement units on the electric 20 distribution system are expected improve reliability by employing high speed, time 21 synchronized measurement devices. These devices will be utilized in conjunction with 22 energy storage devices to create a closed loop control system to mitigate the impact of 23 intermittent renewables. Phasor measurement technologies are a leading example of a new 24 generation of advanced grid monitoring technologies that rely on high speed, time- 25 synchronized, digital measurements. 26 Phasor measurement technologies will help mitigate the intermittency issues 27 associated with distributed renewables by employing high-speed, time-synchronized 28 measurement devices installed in substations and at key points on the distribution system. 29 Using time stamped, digitized waveform measurements, SDG&E can analyze the output of SDGE Doc #249440 TOB-22
  • 37. 1 PV systems, indentify changes in PV output and enable the dispatch of energy storage 2 devices to counteract the effects of the PV output fluctuation. 3 Phasor measurement technologies are also needed for understanding potential 4 problems with the grid and are therefore a key component of a stable, self-healing grid. As 5 the penetration of renewables increases, there will be increased voltage and phase-angle 6 fluctuations at various points on the system. PMU data can equip system operators with 7 better real-time information about actual operating margins so that they can better 8 understand and manage the risk of operating closer to the operating limits. Specifically, 9 some of the functionality enabled by PMU technologies include: 10 • monitoring and visualization for improved control room operations 11 • wide-area control and protection 12 • power system restoration 13 • time-synchronized, waveform measurements. 14 15 This project calls for the installation of PMU equipment on 11 distribution circuits 16 with a high penetration of PV: 4 circuits in 2011 and seven circuits in 2012. The equipment 17 will be installed at points on the circuit where there is significant aggregation of PV 18 systems. Additionally, a Phasor Data Collector (PDC) will be installed at each substation. 19 An assessment tool will be developed to provide the ability to record, archive, analyze and 20 display phasor data. The interconnection and link of PMUs into a network will bring time- 21 synchronized data to a central location to create a wide-area view of the grid. 22 23 Table TOB - 8 24 Renewable Growth, Phasor Measurement Units Capital Expenditures 25 (Thousands of 2009 dollars) 26 Description 2009 Adjusted 2010 2011 TY2012 Recorded Estimated Estimated Estimated Category 1 $0 $0 $1,475 $2,581 27 28 29 SDGE Doc #249440 TOB-23
  • 38. 1 4. Renewable Growth: Capacitor SCADA (Budget Codes: 10261) 2 A cost forecast is provided to implement SCADA control of all capacitors on 3 SDG&E’s distribution system and is distinct from the SCADA expansion for switches 4 discussed below. Benefits of SCADA for capacitors should include: better voltage and VAr 5 control, reduced maintenance, and better system diagnostics. When coupled with energy 6 storage, dynamic line ratings and phasor measurements new control schemes can be 7 implemented which will mitigate the impact of PV system output fluctuations on system 8 voltage. 9 SDG&E has been using SCADA (Supervisory Control and Data Acquisition) 10 controlled devices in various types of equipment for many years. SCADA controlled 11 capacitor banks will provide local and remote control, failure prediction and detection, 12 reduced operating cost, and should enhance distribution system performance through 13 improved voltage and reactive power control. As certain elements of Smart Grid evolve, 14 including less predictable DER, the ability to dynamically adjust reactive power flow will 15 become more critical. Presently, SDG&E discovers capacitor issues during the annual 16 capacitor survey or through customer voltage problems. SCADA controlled capacitors will 17 provide SDG&E the ability to be proactive in capacitor maintenance, instead of reactive. 18 Furthermore, SCADA control will provide a faster and more economical way to update the 19 software and to adjust control settings. 20 Installing SCADA on capacitor controllers will yield the following capabilities: 21 SCADA controls offer the ability to over-ride automatic controls of the bank to 22 adjust voltage or reactive support to the distribution system. Reprogramming capability may 23 reduce the need for future field visits by line personnel. 24 • SCADA controls can alert utility personnel of capacitor failures and/or 25 fuse operations. This will increase capacitor bank reliability, minimize 26 downtime, and expedite repair work. 27 • SCADA controls may be used to help facilitate the annual Capacitor 28 Survey for those sites that are on SCADA. 29 • SCADA provides for remote monitoring of the status of the control 30 devices for the bank. SDGE Doc #249440 TOB-24
  • 39. 1 • SCADA controls provide monitoring of all power system parameters 2 (i.e. voltage, current, reactive power, real power, power factor, etc…) 3 associated with the capacitor bank. This provides a key diagnostic tool 4 when power quality concerns arise. This is becoming more critical, as 5 the digital economy demands a higher level of power quality. 6 7 • Improved voltage and reactive power control to mitigate the impact of 8 distributed PV. 9 10 At this time there are 1,404 capacitors in the SDG&E service territory, 959 are 11 overhead capacitors and 445 are underground capacitors. The cash flow below reflects 12 adding SCADA to all these capacitors over a seven year period with the majority of work 13 taking place over the 2011-2016 period. 14 15 Table TOB - 9 16 Renewable Growth, Capacitor SCADA Capital Expenditures 17 (Thousands of 2009 dollars) 18 Description 2009 Adjusted 2010 2011 TY2012 Recorded Estimated Estimated Estimated Category 1 $0 $0 $2,902 $2,902 19 20 5. Renewable Growth: SCADA Expansion (Budget Codes: 10261) 21 A cost forecast is provided for expansion of SCADA to expand remote operability 22 and automated operation of distribution SCADA capable switches. This will continue 23 SDG&E’s goal of providing faster isolation of faulted electric distribution circuits and 24 branches, resulting in faster load restoration and isolation of system disturbances. 25 This project provides funding for the installation, upgrades, and expansion of the 26 Supervisory Control and Data Acquisition (SCADA) system at substations and on 27 distribution circuits through the addition of automated switches. SDG&E’s radial, open- 28 loop distribution circuit design philosophy incorporates 1.5 SCADA switches per circuit: 29 one at the midpoint, and one at a strong tie. This design philosophy improves system 30 reliability while avoiding a full network design. SDGE Doc #249440 TOB-25
  • 40. 1 As the penetration of distributed renewables increases on the distribution system, 2 this SCADA expansion will allow SDG&E to re-configure circuits. By automatically re- 3 configuring circuit the amount of PV and load can be balanced to better accommodate areas 4 of high PV penetration. 5 This will be incremental to work being done on existing budgets. In addition, to 6 fully realize the functionality of the line SCADA, the associated feeding substation needs to 7 be on SCADA as well. The scope of work required to achieve the capabilities above will 8 require installation of SCADA at 13 substations serving 76 circuits, and 281 SCADA 9 switches on circuits that lack SCADA line or SCADA tie switches. The cash flow below 10 reflects this scope of work being implemented over a five year period from 2012-2016. 11 Expenditures are expected to begin in 2012 as shown below. 12 13 Table TOB - 10 14 Renewable Growth, SCADA Expansion Capital Expenditures 15 (Thousands of 2009 dollars) 16 Description 2009 Adjusted 2010 2011 TY2012 Recorded Estimated Estimated Estimated Category 1 $0 $0 $0 $5,964 17 18 6. Electric Vehicle Growth: Plug-In Electric Vehicles 19 This is project is required to upgrade primary and secondary voltage infrastructure to 20 accommodate the rollout of electric vehicles in San Diego County in the 2010, 2011 and 21 2012 timeframe. Transformers, secondary and primary conductors associated with 22 customers who participate in the Nissan Leaf and Chevrolet Volt rollout will be evaluated 23 for adequate capacity. If upgrades are required, they will be covered as part of this project. 24 These costs are incorporated in the testimony of Mr. Alan Marcher, Exhibit SDG&E-06. 25 Large numbers of PEV’s (both battery electric vehicles and plug-in hybrid electric 26 vehicles) are estimated to interconnect to the SDG&E grid over the next 10 years, requiring 27 improvements to the electric distribution system. This may also create opportunities in the 28 future to use PEVs as distributed energy resources by discharging their batteries into the 29 grid during times of system resource needs or economic benefit. The upgrade of services 30 and transformers resulting from residential PEV impacts to the grid occurring over the next SDGE Doc #249440 TOB-26
  • 41. 1 3 years (2010-2012) are included in associated capital projects of Mr. Alan Marcher as 2 mentioned earlier. Therefore the costs being included on this Smart Grid capital project 3 associated with impacts due to PEVs, in post test years, will cover distribution feeder 4 upgrades and infrastructure for larger public charging stations. The cost estimates for this 5 timeframe are based on a projection of 8300 residential charging stations and 328 public 6 charging stations 7 8 7. Electric Vehicle Growth: Smart Transformers (Budget Codes: 10261) 9 A cost forecast is provided for the installation of sensors and technology on 10 distribution transformers so that they can monitor and report loading, and the state of the 11 transformers. This project has the potential to allow increased transformer capacity 12 utilization and accommodate future loads such as plug-in electric vehicles. 13 Distribution line transformers can be converted into smart devices by installing 14 monitoring equipment on the secondary bushings. These monitors will provide information 15 to engineers and operators about the state of the grid including distributed resources and 16 loads at the location of the transformers. This data will be especially valuable for 17 monitoring the load and condition of transformers feeding plug-in electric vehicles. It will 18 also provide information about the state and condition of the transformer. Transformer 19 monitors will facilitate dynamic ratings for the transformers, the ability to verify energy 20 consumed or generated by new distributed resources or loads for potential management 21 applications, and the ability to assess detailed transformer conditions in order to proactively 22 troubleshoot customer or secondary voltage problems. 23 This project will install transformer monitoring devices on all transformers serving 24 customers with plug-in electric vehicles. Sensing devices attached to transformers will be 25 used to monitor real-time loading and establish accurate load profiles. This information will 26 be available to system operators to alert them to possible overloads, imbalances, voltage 27 excursions or other operational issues. Additionally, engineers will use this information to 28 revise transformer loading guidelines which may lead to optimizing the number of 29 customers that may be served from an individual transformer and reducing transformer 30 loading problems. SDGE Doc #249440 TOB-27
  • 42. 1 One transformer monitoring device will be installed on each distribution transformer 2 that serves a customer with a PEV and associated charge stations. The number of PEV 3 charge stations is anticipated to be: 4 5 Table TOB - 11 6 PEV Charging Stations 7 Year: 2010 2011 2012 Total PEV Charge Stations: 600 2150 700 3450 8 9 This estimated number of charge stations is based on the expected sales of battery 10 electric vehicle and plug-in hybrid electric vehicle sales in the San Diego area. This 11 estimate is based upon a DOE sponsored program with partnership by ECOtality and Nissan 12 to deploy up to 5,000 electric vehicles and charging infrastructure in San Diego and four 13 other U.S. cities. 14 15 Table TOB - 12 16 Electric Vehicle Growth, Smart Transformers Capital Expenditures 17 (Thousands of 2009 dollars) 18 Description 2009 Adjusted 2010 2011 TY2012 Recorded Estimated Estimated Estimated Category 1 $0 $0 $2,047 $521 19 20 8. Electric Vehicle Growth: Public Access Charging Facilities (Budget 21 Codes: 10261) 22 A cost forecast is provided for the installation of utility-owned, public access 23 charging facilities for electric vehicles. SDG&E will install and own the charging facilities 24 in under-served areas in order to broaden the coverage of public charging opportunities 25 within its service territory. This effort will allow SDG&E to continue the momentum of the 26 stakeholder charging facility siting and installation process established by ECOtality as part 27 of their government funded EV Project between 2010 and mid-2011. As planned, this 28 project will increase the number of charging facility services offered by 3rd parties, 29 specifically to provide PEV charging facilities in locations that are not necessarily SDGE Doc #249440 TOB-28
  • 43. 1 commercially or economically desirable, but needed to serve the broader and growing PEV 2 charging needs of the public. 3 4 Charging Facility Site Selection 5 SDG&E will work with the CPUC to develop broad criteria for evaluating the installation of 6 “public access charging facilities” with the objective to ensure a network of public charging facilities 7 is developed in the public interest over time that would provide sufficient support for the adoption and 8 use of PEVs. 9 As part of the selection process, SDG&E will use an independent entity to assist in the 10 development of site evaluation criteria to be used in a regional stakeholder charging facility site 11 selection process. The process will be led by an independent coordinating entity, such as the San 12 Diego Association of Governments, SANDAG. SDG&E will adapt the process that has been 13 successfully implemented in the deployment of charging facilities by ECOtality, under an ARRA, 14 DOE grant.13 Once ECOtality completes the charging facility installation portion of their EV Project 15 by mid-2011, SDG&E will continue to play a role in working with stakeholders to help determine the 16 location of the charging facilities that will have the least cost, least impact to the electric distribution 17 system. SDG&E will implement this service as part of a long-term process to extend the deployment 18 of public charging facilities as the growth of PEVs continues. 19 To support the development of electric vehicles and to engender the broad public benefits this 20 yields (lower GHG and other harmful emissions, improve local air quality, less reliance on foreign 21 oil), SDG&E will play an important role during the formative years of market development to ensure 22 that electric charging infrastructure develops which can support the rapid adoption of plug-in electric 23 vehicles. Also, because of their limited range, in order to foster market acceptance of these vehicles, a 24 seamless network of charging facilities will be needed. In order to ensure that this network of 25 charging infrastructure does not have significant voids, SDG&E proposes these "public interest" 26 charging facilities. 27 As a result of the development of a more robust availability of charging facilities, this effort 28 will also help to stimulate market growth for PEV related services and equipment in general, and 29 specifically in under-served areas. Although SDG&E will own these charging facilities, it will also 30 contract with 3rd parties to build, operate and maintain the charging facilities. This approach will help 13 http://www.ecotalityna.com/pdf/100109_eTec_DOE_Contract.pdf SDGE Doc #249440 TOB-29