Time Management – Sample Cheat Sheet


Time Processes(6): Activity Definition, Activity Sequencing, Activity Resource Estimating, Activity
Duration Estimating, Schedule Development, Schedule Control

Sequence Activities:
      PDM or AON (FS, FF, SS, SF)
      GERT (rarely used)-(loops between activities)
      Dependencies [Mandatory (hard logic), Discretionary (soft logic), External]
      LEADS and LAGS:
               [Leads: starts activity before predecessor is complete] [Shortens the schedule]
               [Lags: Inserted between activities] [Delays activity start]

Activity Resource Estimating: Equipment, materials, and People

Activity Duration Estimating: (PADDDING is BAD)
         One-Point:( one per activity) (expert judgment) (guessing)
         Analogous: (Top Down) (expert judgment and historical information to predict the future)
         Parametric: (heuristics-80/20 rule) (Regression analysis – scatter diagram, Learning curve)
         Three-Point (PERT): EAD=(P+4M+O)/6, SD=P-O/6, Variance=(((p-o)/6))2, Range=EAD+/-SD
         Reserve Analysis: (Risk Contingency – time reserves and management reserves)

Schedule Network:
       Critical Path Method                                         CPM:
       Schedule Compression: (Fast track, Crash)                     Critical Path-(forward/backward pass)
       What-If Analysis: (Monte Carlo)                               Near Critical Path
       Resource Leveling: (schedule slips and cost increases) TF=LF-EF, FF=LS-ES
       Critical Chain Method:                                        FLOAT is SLACK
                -(takes into account, directly, both activity and resource dependencies)
                -(duration buffers built into the chain at critical milestones)

Project Schedule:
        Network Diagram
        Milestone chart: have no duration; good for reporting to management and the customer
        Bar Chart: completed after the WBS and the network diagram for tracking progress

Schedule Baseline:
       (manages the project and the schedule that the team’s performance is measured against)
       (only changed with approved changes)

Control Schedule: (means measure) (measure against the plan)
        Looking for things causing changes and influencing them to change
        Re-Estimating at least ONCE over the life of the project
        Work performance measurements, changes to schedule baseline and any part of the project
Time Management – Sample Cheat Sheet

Contenu connexe

Tendances

Software project management
Software project managementSoftware project management
Software project management
R A Akerkar
 
The project management information system
The project management information systemThe project management information system
The project management information system
Davinder Singh
 
Project Management Process Groups
Project Management Process GroupsProject Management Process Groups
Project Management Process Groups
TechNoleGirl
 
Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11
PMA Consultants
 

Tendances (20)

Software project management
Software project managementSoftware project management
Software project management
 
The project management information system
The project management information systemThe project management information system
The project management information system
 
Project Management Process Groups
Project Management Process GroupsProject Management Process Groups
Project Management Process Groups
 
Spm ap-network model-
Spm ap-network model-Spm ap-network model-
Spm ap-network model-
 
Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11
 
Lecture 1. general introduction to project management
Lecture 1. general introduction to project management Lecture 1. general introduction to project management
Lecture 1. general introduction to project management
 
Software Project Management
Software Project ManagementSoftware Project Management
Software Project Management
 
Lecture5---Gantt Chart
Lecture5---Gantt ChartLecture5---Gantt Chart
Lecture5---Gantt Chart
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
Project Management
Project ManagementProject Management
Project Management
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full course
 
Real example of PMO deployment
Real example of PMO deploymentReal example of PMO deployment
Real example of PMO deployment
 
Pmp communication chapter 10
Pmp communication chapter 10Pmp communication chapter 10
Pmp communication chapter 10
 
Practical Guide to Useful Project Management Plan
Practical Guide to Useful Project Management PlanPractical Guide to Useful Project Management Plan
Practical Guide to Useful Project Management Plan
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management Processes
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project Management
 
Spm unit 4
Spm unit 4Spm unit 4
Spm unit 4
 
Project Management Steps
Project Management StepsProject Management Steps
Project Management Steps
 
Integrated Project Management
Integrated Project ManagementIntegrated Project Management
Integrated Project Management
 

Similaire à Capm process cheat sheet

L05 time management
L05 time managementL05 time management
L05 time management
Asa Chan
 

Similaire à Capm process cheat sheet (20)

6 time PMBOK
6 time PMBOK6 time PMBOK
6 time PMBOK
 
Itt os
Itt osItt os
Itt os
 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.ppt
 
3. project time management
3. project time management3. project time management
3. project time management
 
Scheduling Task-parallel Applications in Dynamically Asymmetric Environments
Scheduling Task-parallel Applications in Dynamically Asymmetric EnvironmentsScheduling Task-parallel Applications in Dynamically Asymmetric Environments
Scheduling Task-parallel Applications in Dynamically Asymmetric Environments
 
Dynamic Scheduling for Shutdowns and Turnarounds
Dynamic Scheduling for Shutdowns and TurnaroundsDynamic Scheduling for Shutdowns and Turnarounds
Dynamic Scheduling for Shutdowns and Turnarounds
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
 
02-Key Definitions .pdf
02-Key Definitions .pdf02-Key Definitions .pdf
02-Key Definitions .pdf
 
PMP Study Notes
PMP Study NotesPMP Study Notes
PMP Study Notes
 
Assignment project scheduling
Assignment project schedulingAssignment project scheduling
Assignment project scheduling
 
C03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdfC03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdf
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
P6 Analytics history hierarchies and maps - Oracle Primavera P6 Collaborate 14
P6 Analytics history hierarchies and maps - Oracle Primavera P6 Collaborate 14P6 Analytics history hierarchies and maps - Oracle Primavera P6 Collaborate 14
P6 Analytics history hierarchies and maps - Oracle Primavera P6 Collaborate 14
 
L05 time management
L05 time managementL05 time management
L05 time management
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
 
Introduction to SLURM
Introduction to SLURMIntroduction to SLURM
Introduction to SLURM
 
Pmp session 3
Pmp session 3Pmp session 3
Pmp session 3
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 

Plus de University High School - Fresno

Plus de University High School - Fresno (14)

Dah time mgmt matching exercise answers
Dah time mgmt matching exercise answersDah time mgmt matching exercise answers
Dah time mgmt matching exercise answers
 
Capm time mgmt fas track as
Capm time mgmt fas track asCapm time mgmt fas track as
Capm time mgmt fas track as
 
Capm ccvc capm time 4th edition pmbok review
Capm ccvc capm time   4th edition pmbok reviewCapm ccvc capm time   4th edition pmbok review
Capm ccvc capm time 4th edition pmbok review
 
Capm test taking preparation hints
Capm test taking preparation hintsCapm test taking preparation hints
Capm test taking preparation hints
 
Capm time 150 question final key
Capm time 150 question final keyCapm time 150 question final key
Capm time 150 question final key
 
Capm scenario identifying the critical path answers
Capm scenario identifying the critical path   answersCapm scenario identifying the critical path   answers
Capm scenario identifying the critical path answers
 
Capm scenario identifying the critical path answers
Capm scenario identifying the critical path   answersCapm scenario identifying the critical path   answers
Capm scenario identifying the critical path answers
 
Capm time mgmt matching exercise
Capm time mgmt matching exerciseCapm time mgmt matching exercise
Capm time mgmt matching exercise
 
Simple perl scripts
Simple perl scriptsSimple perl scripts
Simple perl scripts
 
Zoskctr hints tips 20090723doc
Zoskctr hints tips 20090723docZoskctr hints tips 20090723doc
Zoskctr hints tips 20090723doc
 
Simple perl scripts
Simple perl scriptsSimple perl scripts
Simple perl scripts
 
Source code examples
Source code examplesSource code examples
Source code examples
 
Business computing survey
Business computing surveyBusiness computing survey
Business computing survey
 
Watson
WatsonWatson
Watson
 

Dernier

Dernier (20)

Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Tech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfTech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdf
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 

Capm process cheat sheet

  • 1. Time Management – Sample Cheat Sheet Time Processes(6): Activity Definition, Activity Sequencing, Activity Resource Estimating, Activity Duration Estimating, Schedule Development, Schedule Control Sequence Activities: PDM or AON (FS, FF, SS, SF) GERT (rarely used)-(loops between activities) Dependencies [Mandatory (hard logic), Discretionary (soft logic), External] LEADS and LAGS: [Leads: starts activity before predecessor is complete] [Shortens the schedule] [Lags: Inserted between activities] [Delays activity start] Activity Resource Estimating: Equipment, materials, and People Activity Duration Estimating: (PADDDING is BAD) One-Point:( one per activity) (expert judgment) (guessing) Analogous: (Top Down) (expert judgment and historical information to predict the future) Parametric: (heuristics-80/20 rule) (Regression analysis – scatter diagram, Learning curve) Three-Point (PERT): EAD=(P+4M+O)/6, SD=P-O/6, Variance=(((p-o)/6))2, Range=EAD+/-SD Reserve Analysis: (Risk Contingency – time reserves and management reserves) Schedule Network: Critical Path Method CPM: Schedule Compression: (Fast track, Crash) Critical Path-(forward/backward pass) What-If Analysis: (Monte Carlo) Near Critical Path Resource Leveling: (schedule slips and cost increases) TF=LF-EF, FF=LS-ES Critical Chain Method: FLOAT is SLACK -(takes into account, directly, both activity and resource dependencies) -(duration buffers built into the chain at critical milestones) Project Schedule: Network Diagram Milestone chart: have no duration; good for reporting to management and the customer Bar Chart: completed after the WBS and the network diagram for tracking progress Schedule Baseline: (manages the project and the schedule that the team’s performance is measured against) (only changed with approved changes) Control Schedule: (means measure) (measure against the plan) Looking for things causing changes and influencing them to change Re-Estimating at least ONCE over the life of the project Work performance measurements, changes to schedule baseline and any part of the project
  • 2. Time Management – Sample Cheat Sheet