SlideShare une entreprise Scribd logo
1  sur  4
Télécharger pour lire hors ligne
Identifying the Critical Path

Scenario:

Activity duration estimates for the sidewalk replacement work package have been determined
as shown. You’ve started thinking about when you’ll be able to begin work and what resources
might be available. You examine the company master project schedule and find some openings
where your project might fit in, but you’re unsure if the work that needs to be accomplished can
be performed in the available time slots.




    1. Perform a forward pass to determine the early start (ES) and early finish (EF) for each activity.
       Enter your answers in the appropriate place in the network diagram. What is the ES for activity
       2.3.3.1, Remove Old Sidewalk?

        The ES for the first activity is assumed to be zero.

    2. What is the EF for activity 2.3.3.1?

        EF is 20, the same as the duration.

    3. What are the ES and EF for activity 2.3.3.2, Excavate Lawn?

        EF is 20, the EF for the predecessor activity. EF is 45, its ES + duration.




1                                        Identifying the Critical Path
4. Calculate the ES and EF for the remaining activities. Why is the ES for activity 2.3.3.5 the same as
       the ES for activity 2.3.3.4?

        They both have the same predecessor activity (2.3.3.3).

    5. How do you calculate the ES for the last activity, 2.3.3.7?

        The ES for the last activity is calculated by taking the EF from 2.3.3.4 and adding the 16-hour
        finish-to-start lag for the concrete to cure.

    6. What does your network diagram look like with a forward pass?




    7. Perform a backward pass to determine the late start (LS) and late finish (LF) for each activity.
       Enter your answers in the appropriate place in the network diagram. What is the LF for activity
       2.3.3.7, Remove Forms?

        The LF for the last activity is the same as its EF, which is 81.

    8. Why is the LF for activity 2.2.3.4, Pour Concrete, the same as its EF?

        The activity is on the critical path.

    9. Why is the LF for activity 2.3.3.6, Lay Sod, higher than the LS for activity 2.3.3.4, Pour Concrete?

        There is a 16-hour lag between the finish activity 2.3.3.4, Pour Concrete, and the start of actifity
        2.3.3.7, Remove Forms.


2                                        Identifying the Critical Path
10. What does your completed diagram look like with a backward pass?




    11. Determine the float for this network. Which activities have total float in this network? How
        much float do they have?

        Activities 2.3.3.5 and 2.3.3.6 are the only activities with total float because they are not on the
        critical path. Each has a total float of 10 hours (LF-EF or LS-ES).

    12. Does that mean that those activities can each flex their start or finish time by the total float
        hours?

        No. The 10 hours of total float are shared by the two activities. If activity 2.3.3.5 is delayed for
        eight hours, there will only be two hours of float left for activity 2.3.3.6.

    13. Which activities have free float?

        Only activity 2.3.3.6, Lay Sod, has free float, because it’s the only activity that can safely be
        delayed without delaying the ES of the subsequent activity, which is on the critical path.

    14. How much free float does that activity have?

        Activity 2.3.3.6 has 10 hours of free float, which is the same as its total float. However, activity
        2.3.3.5 does not have free float. The activity shares the 10 hours of total float with activity
        2.3.3.6.

3                                       Identifying the Critical Path
15. What would happen to the free float of that activity if its concurrent activity used up the hours
        of total float?

        It would go to zero, so activity 2.3.3.6 would no longer have any float.

    16. What is the critical path?

        There are two possible paths through the activities. The total duration nodes 2.3.3.1 + 2.3.3.2 +
        2.3.3.3 + 2.3.3.5 + 2.3.3.6 + 2.3.3.7 = 71. The total duration for nodes 2.3.3.1 + 2.3.3.2 + 2.3.3.3 +
        2.3.3.4 + 2.3.3.7 = 81 counting the 16-hour lag for the concrete curing, so that is the critical path.

    17. What will happen to the total time if it takes 12 hours to pour the concrete?

        Activity 2.3.3.4, Pour Concrete, has an estimated duration of eight hours and is on the critical
        path. So if the actual duration of that activity increases by four hours, the total time will also
        increase by four hours.

    18. What will happen to the total time if it takes 10 hours to lay the sod?

        Activity 2.3.3.6, Lay Sod, is not on the critical path. So if the actual duration of that activity
        increases by two hours, the total time will not be affected.

    19. What will happen to the total time if it takes 20 hours to lay the sod?

        The critical path will change, and total time will increase to 83 hours.




4                                        Identifying the Critical Path

Contenu connexe

En vedette

Improving your Project Communications
Improving your Project CommunicationsImproving your Project Communications
Improving your Project CommunicationsArt Gelwicks
 
Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1Amr Miqdadi
 
Path to PMP!
Path to PMP!Path to PMP!
Path to PMP!Edureka!
 
Fast Track Project Management Success w/ Project Online #pmiwdc
Fast Track Project Management Success w/ Project Online #pmiwdcFast Track Project Management Success w/ Project Online #pmiwdc
Fast Track Project Management Success w/ Project Online #pmiwdcDux Raymond Sy
 
Pmbok 5cartulinas
Pmbok 5cartulinasPmbok 5cartulinas
Pmbok 5cartulinasPedro Arcas
 
Final exam review_questions
Final exam review_questionsFinal exam review_questions
Final exam review_questionsCarmenLamdegil
 
Discipline management
Discipline managementDiscipline management
Discipline managementparthproy
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Amr Miqdadi
 
Taking smaller bites with PMP-Bite series - PMP Chapter 1 Part 2 (CONSTRAINTS)
Taking smaller bites with PMP-Bite series - PMP Chapter 1 Part 2 (CONSTRAINTS)Taking smaller bites with PMP-Bite series - PMP Chapter 1 Part 2 (CONSTRAINTS)
Taking smaller bites with PMP-Bite series - PMP Chapter 1 Part 2 (CONSTRAINTS)May Wong, PMP
 
PMP Knowledge Areas Summary
PMP Knowledge Areas SummaryPMP Knowledge Areas Summary
PMP Knowledge Areas SummaryAmr Miqdadi
 

En vedette (16)

Dah time mgmt matching exercise answers
Dah time mgmt matching exercise answersDah time mgmt matching exercise answers
Dah time mgmt matching exercise answers
 
7. project communications management
7. project communications management7. project communications management
7. project communications management
 
Improving your Project Communications
Improving your Project CommunicationsImproving your Project Communications
Improving your Project Communications
 
Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1
 
PMP PMBOK5 Ch4 integration management
PMP PMBOK5 Ch4 integration managementPMP PMBOK5 Ch4 integration management
PMP PMBOK5 Ch4 integration management
 
Path to PMP!
Path to PMP!Path to PMP!
Path to PMP!
 
Fast Track Project Management Success w/ Project Online #pmiwdc
Fast Track Project Management Success w/ Project Online #pmiwdcFast Track Project Management Success w/ Project Online #pmiwdc
Fast Track Project Management Success w/ Project Online #pmiwdc
 
Pmbok 5cartulinas
Pmbok 5cartulinasPmbok 5cartulinas
Pmbok 5cartulinas
 
T344 Web
T344 WebT344 Web
T344 Web
 
Cheatsheet
CheatsheetCheatsheet
Cheatsheet
 
PMP Exam-Prep
PMP Exam-PrepPMP Exam-Prep
PMP Exam-Prep
 
Final exam review_questions
Final exam review_questionsFinal exam review_questions
Final exam review_questions
 
Discipline management
Discipline managementDiscipline management
Discipline management
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3
 
Taking smaller bites with PMP-Bite series - PMP Chapter 1 Part 2 (CONSTRAINTS)
Taking smaller bites with PMP-Bite series - PMP Chapter 1 Part 2 (CONSTRAINTS)Taking smaller bites with PMP-Bite series - PMP Chapter 1 Part 2 (CONSTRAINTS)
Taking smaller bites with PMP-Bite series - PMP Chapter 1 Part 2 (CONSTRAINTS)
 
PMP Knowledge Areas Summary
PMP Knowledge Areas SummaryPMP Knowledge Areas Summary
PMP Knowledge Areas Summary
 

Similaire à Capm scenario identifying the critical path answers

Cm ch4 scheduling
Cm ch4 schedulingCm ch4 scheduling
Cm ch4 schedulingAhmed Gamal
 
Critical path method (CPM).pptx
Critical path method (CPM).pptxCritical path method (CPM).pptx
Critical path method (CPM).pptxHimanshuKaklotar1
 
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.pptNitin137794
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)chandkec
 
12 lecture project scheduling 4
12 lecture project scheduling 412 lecture project scheduling 4
12 lecture project scheduling 4Ahmad Basim Hamza
 
Management science
Management scienceManagement science
Management sciencekamrul islam
 
Session B1 - Planning, Scheduling Monitoring and Control
Session B1 - Planning, Scheduling Monitoring and ControlSession B1 - Planning, Scheduling Monitoring and Control
Session B1 - Planning, Scheduling Monitoring and ControlProject Controls Expo
 
Chapter-2 Solved examples.ppt
Chapter-2 Solved examples.pptChapter-2 Solved examples.ppt
Chapter-2 Solved examples.pptBetshaTizazu2
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptxLJay7
 
Critical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdjCritical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdjlicpn03
 
Complex Project Crashing Algorithm
Complex Project Crashing AlgorithmComplex Project Crashing Algorithm
Complex Project Crashing AlgorithmIOSR Journals
 
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfuPERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfuinfinitepestcontrol
 
Chapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagementChapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagementAKSHAYA0000
 
Pert- program evaluation and review technique
Pert- program evaluation and review techniquePert- program evaluation and review technique
Pert- program evaluation and review techniqueVinci Viveka
 

Similaire à Capm scenario identifying the critical path answers (20)

Cm ch4 scheduling
Cm ch4 schedulingCm ch4 scheduling
Cm ch4 scheduling
 
Critical path method (CPM).pptx
Critical path method (CPM).pptxCritical path method (CPM).pptx
Critical path method (CPM).pptx
 
Cpm pert asgm. prashant
Cpm pert asgm. prashantCpm pert asgm. prashant
Cpm pert asgm. prashant
 
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
12 lecture project scheduling 4
12 lecture project scheduling 412 lecture project scheduling 4
12 lecture project scheduling 4
 
Management science
Management scienceManagement science
Management science
 
Session B1 - Planning, Scheduling Monitoring and Control
Session B1 - Planning, Scheduling Monitoring and ControlSession B1 - Planning, Scheduling Monitoring and Control
Session B1 - Planning, Scheduling Monitoring and Control
 
Project Management Techniques
Project Management TechniquesProject Management Techniques
Project Management Techniques
 
606CPM1.ppt
606CPM1.ppt606CPM1.ppt
606CPM1.ppt
 
Chapter-2 Solved examples.ppt
Chapter-2 Solved examples.pptChapter-2 Solved examples.ppt
Chapter-2 Solved examples.ppt
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptx
 
Pert analysis
Pert analysisPert analysis
Pert analysis
 
Critical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdjCritical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdj
 
Complex Project Crashing Algorithm
Complex Project Crashing AlgorithmComplex Project Crashing Algorithm
Complex Project Crashing Algorithm
 
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfuPERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
 
Chapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagementChapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagement
 
Pert- program evaluation and review technique
Pert- program evaluation and review techniquePert- program evaluation and review technique
Pert- program evaluation and review technique
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 

Plus de University High School - Fresno (13)

Capm time mgmt fas track as
Capm time mgmt fas track asCapm time mgmt fas track as
Capm time mgmt fas track as
 
Capm ccvc capm time 4th edition pmbok review
Capm ccvc capm time   4th edition pmbok reviewCapm ccvc capm time   4th edition pmbok review
Capm ccvc capm time 4th edition pmbok review
 
Capm test taking preparation hints
Capm test taking preparation hintsCapm test taking preparation hints
Capm test taking preparation hints
 
Capm process cheat sheet
Capm process cheat sheetCapm process cheat sheet
Capm process cheat sheet
 
Capm time 150 question final key
Capm time 150 question final keyCapm time 150 question final key
Capm time 150 question final key
 
Capm scenario identifying the critical path answers
Capm scenario identifying the critical path   answersCapm scenario identifying the critical path   answers
Capm scenario identifying the critical path answers
 
Capm time mgmt matching exercise
Capm time mgmt matching exerciseCapm time mgmt matching exercise
Capm time mgmt matching exercise
 
Simple perl scripts
Simple perl scriptsSimple perl scripts
Simple perl scripts
 
Zoskctr hints tips 20090723doc
Zoskctr hints tips 20090723docZoskctr hints tips 20090723doc
Zoskctr hints tips 20090723doc
 
Simple perl scripts
Simple perl scriptsSimple perl scripts
Simple perl scripts
 
Source code examples
Source code examplesSource code examples
Source code examples
 
Business computing survey
Business computing surveyBusiness computing survey
Business computing survey
 
Watson
WatsonWatson
Watson
 

Capm scenario identifying the critical path answers

  • 1. Identifying the Critical Path Scenario: Activity duration estimates for the sidewalk replacement work package have been determined as shown. You’ve started thinking about when you’ll be able to begin work and what resources might be available. You examine the company master project schedule and find some openings where your project might fit in, but you’re unsure if the work that needs to be accomplished can be performed in the available time slots. 1. Perform a forward pass to determine the early start (ES) and early finish (EF) for each activity. Enter your answers in the appropriate place in the network diagram. What is the ES for activity 2.3.3.1, Remove Old Sidewalk? The ES for the first activity is assumed to be zero. 2. What is the EF for activity 2.3.3.1? EF is 20, the same as the duration. 3. What are the ES and EF for activity 2.3.3.2, Excavate Lawn? EF is 20, the EF for the predecessor activity. EF is 45, its ES + duration. 1 Identifying the Critical Path
  • 2. 4. Calculate the ES and EF for the remaining activities. Why is the ES for activity 2.3.3.5 the same as the ES for activity 2.3.3.4? They both have the same predecessor activity (2.3.3.3). 5. How do you calculate the ES for the last activity, 2.3.3.7? The ES for the last activity is calculated by taking the EF from 2.3.3.4 and adding the 16-hour finish-to-start lag for the concrete to cure. 6. What does your network diagram look like with a forward pass? 7. Perform a backward pass to determine the late start (LS) and late finish (LF) for each activity. Enter your answers in the appropriate place in the network diagram. What is the LF for activity 2.3.3.7, Remove Forms? The LF for the last activity is the same as its EF, which is 81. 8. Why is the LF for activity 2.2.3.4, Pour Concrete, the same as its EF? The activity is on the critical path. 9. Why is the LF for activity 2.3.3.6, Lay Sod, higher than the LS for activity 2.3.3.4, Pour Concrete? There is a 16-hour lag between the finish activity 2.3.3.4, Pour Concrete, and the start of actifity 2.3.3.7, Remove Forms. 2 Identifying the Critical Path
  • 3. 10. What does your completed diagram look like with a backward pass? 11. Determine the float for this network. Which activities have total float in this network? How much float do they have? Activities 2.3.3.5 and 2.3.3.6 are the only activities with total float because they are not on the critical path. Each has a total float of 10 hours (LF-EF or LS-ES). 12. Does that mean that those activities can each flex their start or finish time by the total float hours? No. The 10 hours of total float are shared by the two activities. If activity 2.3.3.5 is delayed for eight hours, there will only be two hours of float left for activity 2.3.3.6. 13. Which activities have free float? Only activity 2.3.3.6, Lay Sod, has free float, because it’s the only activity that can safely be delayed without delaying the ES of the subsequent activity, which is on the critical path. 14. How much free float does that activity have? Activity 2.3.3.6 has 10 hours of free float, which is the same as its total float. However, activity 2.3.3.5 does not have free float. The activity shares the 10 hours of total float with activity 2.3.3.6. 3 Identifying the Critical Path
  • 4. 15. What would happen to the free float of that activity if its concurrent activity used up the hours of total float? It would go to zero, so activity 2.3.3.6 would no longer have any float. 16. What is the critical path? There are two possible paths through the activities. The total duration nodes 2.3.3.1 + 2.3.3.2 + 2.3.3.3 + 2.3.3.5 + 2.3.3.6 + 2.3.3.7 = 71. The total duration for nodes 2.3.3.1 + 2.3.3.2 + 2.3.3.3 + 2.3.3.4 + 2.3.3.7 = 81 counting the 16-hour lag for the concrete curing, so that is the critical path. 17. What will happen to the total time if it takes 12 hours to pour the concrete? Activity 2.3.3.4, Pour Concrete, has an estimated duration of eight hours and is on the critical path. So if the actual duration of that activity increases by four hours, the total time will also increase by four hours. 18. What will happen to the total time if it takes 10 hours to lay the sod? Activity 2.3.3.6, Lay Sod, is not on the critical path. So if the actual duration of that activity increases by two hours, the total time will not be affected. 19. What will happen to the total time if it takes 20 hours to lay the sod? The critical path will change, and total time will increase to 83 hours. 4 Identifying the Critical Path